How much does it cost to keep the lights on?

Keep the lights on: $.70

Keep the lights on: $.47

Source: IBM Estimates

Basic Data Centers

Strategic Data Centers

Innovation: $.30

Innovation: $.53

2

Data Center capital costs60% costs from mechanical /

electrical systems

Shell 7%

Mechanical20%

Fees24%

Fit-Up Costs

9%

Instrumentation & Controls4%

Power36%

Source: IBM Estimates

Operating costs3 - 5X capital costs

Cum

ulat

ive

Cos

t of O

pera

tions

($M

illion

s)

Year1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Energy CostStaffingBldg. Maint. & Mgmt.R E Tax

$100

$150

$200

$250

$50

0

Cum

ulat

ive

Cos

t of O

pera

tions

($M

illion

s)

Year1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Energy CostStaffingBldg. Maint. & Mgmt.R E Tax

Energy CostStaffingBldg. Maint. & Mgmt.R E Tax

$100

$150

$200

$250

$50

0

Lifecycle costs of a Basic Data Center

3

Advantages of a Strategic Data Center:

Strategic Basic

Source: IBM Estimates

4

Advantages of a Strategic Data Center:

5

Data Center capital costs60% costs from mechanical /

electrical systems

Shell 7%

Mechanical20%

Fees24%

Fit-Up Costs

9%

Instrumentation & Controls4%

Power36%

Source: IBM Estimates

Operating costs3 - 5X capital costs

Strategic Data Centers can defer 40% - 50% of the lifecycle costs

What Challenges Are You Facing?

• Visibility• Capacity planning• Improving sustainability

• Regulatory compliance initiatives

• Reducing the total cost of ownership

6

• Visibility• Capacity planning• Sustainability• Resilience • Compliance with legislation

Business Drivers and Aims

Centralized data collection for optimal management

Reduced dependency on external resource suppliers

Actionable granular information for capacity planning

Reduced OpEx

Low energy/carbon consumption

Efficient capacity utilization

Fully compliant, green operations

7

Data Centers are dynamically growing in scale, density and complexity.

Common Obstacles

Escalating energy costs

Increasing power demands

Tracking assets and networks w/ error-prone spreadsheets

Insufficient power metering due to poor instrumentation

Uninformed deployment choices

Lost assets

Hotspots/cooling problems

Air flow management issues

Lack of accurate, correlated operational information makes it tough to overcome obstacles like these and make the best operational decisions for your facility.

8

Manual Workarounds, Higher OpEx, Missed Goals

The Unfortunate Result

• Fragmentation: As a data center becomes increasingly “fragmented”, power, space, cooling, and connectivity become unbalanced

• Moves, Adds, and Changes made without awareness of the impacts leads to:

• Lost Capacity• Misplaced or loss of assets• Lower Resilience• CapEx Expenditures

• Retrofits• New Builds

• However…this is all avoidable!

9

Power and energy

Cooling and environmental

Connectivity

Assets and space 

10

Intelligent Infrastructure ManagementData Center and Enterprises

Capacity

Efficiency

Uptime

11

• Target right level of automation• Leverage existing systems• Treat a granular, attribute‐rich asset tracking as foundational

• Minimize risk of strategy and implementation with a phased approach

DCIM Best Practices

Address Power, Environmental, Asset, and Connectivity Needs Holistically

1

Zone 1: Building Point‐of‐Entry– Monitors the building utility metering “Point of Entry”, providing power, oil, water, and gas consumption information and CO2 emissions.

2

Zone 2: Switchboard Distribution Board ‐Monitors sub meters at the main distribution board for DC related equipment.

3

Zone 3: Plant Equipment ‐ Distributed monitoring of supporting facility services, including individual chillers, AHU, CRAC, UPS and lighting circuits.

4Zone 4: Branch Circuit Monitoring of Data Hall –Focuses on monitoring of total rack or cabinet IT loads and environmentals.

5Zone 5: Rack & Cabinet Level Monitoring –Intelligent monitoring and control of power, environmentals, and cabinet level security in addition to DCIM level asset tracking and capacity planning for the data center and enterprise.

6

Zone 6: Device Level Monitoring –Automated connectivity patch field management, as well as monitoring and control of per outlet or device power, within a data center or enterprise.

Let’s Break Down the Problem by Zones

12

PANDUIT Confidential Information

Zone Methodology approachTo demonstrate how Panduit resolves power, energy, connectivity concerns in new or existing data centers, the following slides cover:

• 6 Zone Methodology6 Zone is Panduit’s logical step‐by‐step methodology of assessing simplified, dissected views of distinct enterprise, data center, and facility zones to holistically monitor, manage, and optimize power/energy, asset/connectivity, and thermal management within each zone with greater control.

• S Zone SolutionsBased upon findings from the 6 Zone methodology, S Zone solutions deliver comprehensive energy and physical infrastructure efficiency in data centers, building facilities, and remote enterprise sites through intelligent products, systems, and services.

13

6 Zone Methodology

14

Zone 1 Zone 2 Zone 3 Zone 4 Zone 5 Zone 6

Software (Control, Manage, and Document)

6 Zone is Panduit’s logical step-by-step methodology of assessing simplified, dissected views of distinct enterprise, data center, and facility zones to holistically monitor, manage, and optimize power/energy, asset/connectivity, and thermal management within each zone with greater control.

Supported by S Zone Solutions

Services (Assess and Evaluate Zones)

6 Zone Methodology

Monitoring Devices (Capture Data)

Gateways (Process Data)

S Zone Solutions

Accurate and Actionable Information to Optimize

Advisory Services(Part of S Zone Solutions)

6 Zone Methodology

15

Zone 3

Water Power In Gas

Main MV / LV Distribution Board (A or B)

Lighting Boilers Fire Security CRACChillers Back up Generator

UPS

Sub PDUSub PDUData Hall Environmental

Data Rack or Free Standing

Equipment

Individual Payloads &

Devices

S one Power Monitoring AppliancesS Zone EnvironmentalMonitoring Appliances

Zone 1

Zone 2

Zone 4

Zone 5

Zone 6

Oil

S Zone Asset & Connectivity Monitoring Appliances

Supported by S Zone Solutions

This approach provides an opportunity for both IT and facility managers to assess, discover and articulate all infrastructure issues in a single pane of glass view., helps in addressing them collaboratively.

Bringing together IT and Facilities

Breaking Down the Silos

16

Which Zones Do Clients Begin with?

• Pinpoint energy savings opportunities through trending reporting• Manage asset lifecycle from dock to rack to end of life• Manage capacity planning information around space, power and evironmentals• Reduce cooling costs through cooling system optimization (CFD thermal analysis)• Automated reports to simplify regulatory reporting

• Audit utility bills• Live alerts to fluctuations in utility usage• Comparison between like facilities to identify inefficiencies• Monitor Energy Reductions– collect data for regulatory compliance

• Dynamic PUE: Benchmark and Monitor Trends• Integration: Centralized data collection and reporting for analysis• Power sub-metering at main distribution boards – granular power consumption of

your supporting facility services

• Capacity Planning: Power, Cooling, Connectivity, Assets• Uptime/Resilience: Alarms and Alerts• Dashboard Reporting: Trending, Identification of Inefficiencies

Optimize Power, Space, and Cooling Capacity, Increase Resiliency, Reduce PUE

Real time Utility/fiscal metering (power, oil, water, gas) at the facility point of entry

IT Capacity and Environmental Management at Room and Rack Level

Facilities Single Pane of Glass

Monitor Zones 4-6Monitor

Zones 4-6

MonitorZone 1MonitorZone 1

Monitor Zone 2-3

Optimize &Manage

Optimize &Manage

(typical progression)

17

S Zone Solutions

18

Optimal Data Center / Enterprise Operations

S Zone solutions deliver comprehensive energy and physical infrastructure efficiency through a range of intelligent instrumentation products, systems, and services, in order to help you reach…

Zone 1

Zone 2

Zone 3

Zone 4

Zone 5

Zone 6

Consolidate Fiscals

Granular Reports

PUE

Asset Monitoring

Optimized Data Center

and Enterprise

Management

Fiscal Meters

Switchboard Dist.

Plant

Branch Circuit

Rack & Cabinet

Device

Drive Down PUE

High-level Benefits

19

Internet Business Challenges

20

• Need the ability to monitor power and environmental factors, such as temperature and humidity.

• Visibility to monitor how much space their customers are using to avoid under/over provisioning.

• Measure and improve PUE to reduce power consumption and costs while reducing carbon emissions to comply with the UK government’s Carbon Reduction Commitment Scheme.

Business ChallengesAs a rapidly growing organization, Customer Internet data center infrastructure and business systems need to be agile and scalable. As the company grew, so did the demand on key business systems and their physical infrastructure. 

Resolution

21

• Improved capacity management for Co‐location customers in terms of over/under provisioning resulted in cost savings and improved energy efficiency

• Increased energy efficiency across Zen’s data centers achieving a PUE rating of 1.6

• Exceeded annual 5% target and achieved an 8% reduction in energy consumption and carbon emissions

Customer required a partner that could provide custom built, robust power control and environmental monitoring solutions.  We also needed the confidence that the partner could suitably scale as we grew our Hosting business. Having such a good close working relationship with Panduit has really helped meet all those requirements, and has provided us with the right tools to expand the range of services we provide to our customers in the future.”

David Horner – Senior Data Center Design Engineer

Next StepsHelp us understand your data center challenges so we can meet your specific needs!

22

Building a smarter, unified business foundation