3
1) Motor starting analysis are generally performed for the largest motor connected to a switchboard. 2) For worst case results, motor starting analysis are generally performed considering the weakest source. 3) Considering the above two facts, any given electrical network, where a starting analysis of a motor is required, can be reduced to a simplified network consisting of a source (generator/s or grid), the starting motor (largest motor), the running motor/s (second largest motor/s or motor of same rating as the largest motor under study) and other loads lumped together. 4) Modeling This spread sheet allows the user to model a given network as follows: a) Generator/s: The details of one generator shall be entered. If there are more than one generator of identical rating, these can be modeled simply by enter the number of generator in parallel. b) Grid: The details of grid shall be entered c) Transformer/s: The details of one transformer shall be entered. If there are more than one transformer of identical rating, these can be modeled simply by enter the number of transformer in parallel. d) The spread sheet considered either the "Generator/s" or the "Grid" supply for the motor starting analysis. The "source for the motor starting analysis" can be selected by the use via the drop down menu. The selection automatically simulates switching "ON" or "OFF" the respective source breaker. e) Starting Motor: The details of the largest motor connected to the switchboard shall be entered. f) Running Motor/s: The details of the second largest running motor/s (or motor of rating same as the starting motor) connected to the switchboard shall be entered. This model can also be utilized by the user to check the voltage drop at the terminals of any remote motor/s. g) Lumped Load: The details of the remaing load on the switchboard can be modeled as a lumped load. The % motor can be defined which shall be modeled as constant power load while remaining % of load shall be modeled as constant impedance load for the calculation. h) Error in data entry of the "voltage" input shall be highlighted, if bus voltages are much different from the generator terminal voltage input of transformer voltage ratio inputs. 5) Calculation: The spread sheet performs a static motor starting analysis using the iterative method. The re-acceleration of motors is not considered. Ensure that the following options are enabled: Tools=>Options=> Calculation=> Automatic=> Iteration=>Max iteration= 100=> Max change = 0.001 Note: Change of any variable in the spread sheet, automatically initiates the iteration and recalculated the results. It may happen that due to incorrect details, the iteration diverges and erroneous results are displayed. In such case, check and correct the input and press "Ctrl+Shift+H" to reset. 6) Results: Two sets are of results are displayed on the spread sheet as follows: Prestart: These voltages and power flows results are for "Pre-start" condition. i.e. before the starting of the "Starting motor" During: These voltages and power flows results are for "Starting" condition. i.e. at the time of starting of the "Starting motor" Sr. No. Notes

Motor Starting Calculation-Rev1

Embed Size (px)

DESCRIPTION

excel sheet

Citation preview

Motor starting analysis

IntroductionSr. No.Notes1)Motor starting analysis are generally performed for the largest motor connected to a switchboard.2)For worst case results, motor starting analysis are generally performed considering the weakest source.3)Considering the above two facts, any given electrical network, where a starting analysis of a motor is required, can be reduced to a simplified network consisting of a source (generator/s or grid), the starting motor (largest motor), the running motor/s (second largest motor/s or motor of same rating as the largest motor under study) and other loads lumped together.4)ModelingThis spread sheet allows the user to model a given network as follows:a)Generator/s: The details of one generator shall be entered. If there are more than one generator of identical rating, these can be modeled simply by enter the number of generator in parallel.b)Grid: The details of grid shall be enteredc)Transformer/s: The details of one transformer shall be entered. If there are more than one transformer of identical rating, these can be modeled simply by enter the number of transformer in parallel.d)The spread sheet considered either the "Generator/s" or the "Grid" supply for the motor starting analysis. The "source for the motor starting analysis" can be selected by the use via the drop down menu. The selection automatically simulates switching "ON" or "OFF" the respective source breaker.e)Starting Motor: The details of the largest motor connected to the switchboard shall be entered.f)Running Motor/s: The details of the second largest running motor/s (or motor of rating same as the starting motor) connected to the switchboard shall be entered. This model can also be utilized by the user to check the voltage drop at the terminals of any remote motor/s.g)Lumped Load: The details of the remaing load on the switchboard can be modeled as a lumped load. The % motor can be defined which shall be modeled as constant power load while remaining % of load shall be modeled as constant impedance load for the calculation.h)Error in data entry of the "voltage" input shall be highlighted, if bus voltages are much different from the generator terminal voltage input of transformer voltage ratio inputs.5)Calculation: The spread sheet performs a static motor starting analysis using the iterative method. The re-acceleration of motors is not considered.Ensure that the following options are enabled:Tools=>Options=> Calculation=> Automatic=> Iteration=>Max iteration= 100=> Max change = 0.001Note: Change of any variable in the spread sheet, automatically initiates the iteration and recalculated the results. It may happen that due to incorrect details, the iteration diverges and erroneous results are displayed. In such case, check and correct the input and press "Ctrl+Shift+H" to reset.6)Results: Two sets are of results are displayed on the spread sheet as follows:Prestart: These voltages and power flows results are for "Pre-start" condition. i.e. before the starting of the "Starting motor"During: These voltages and power flows results are for "Starting" condition. i.e. at the time of starting of the "Starting motor"The voltage variations shall be highlighted if they exceed the permissible limitsAlso power flow over the cable-1 shall be highlighted if it exceeds the generator capacity7)Application: This spread sheet can be useful for following checksa)Accessing normal running and starting voltage dropsb)Deciding the number/rating of the generator for starting a given rating of largest motorc)Checking adequacy of selected cable sizes etc.

CalculationNotesGridFault MVAkVX/RGridZ1ohmsGridR1ohmsGridX1ohmsE=100.000%3-ph1)The spread sheet cells highlighted asare for userdata entry.1006120.360000.029900.358762)Following voltage variation is permissible:SOURCE FOR STATIC MOTOR STARTING ANALYSIS =GENERATOR ONLY100.00MinMaxDuring normal operation:95%105%Prestart0.000 MW0.000 MVarApf0.01.000During motor starting condition:80%115%3)The static motor starting analysis allows user to select either the generator/s or grid supply as source. (Weak source should be considered for worst case results).During0.000 MW0.000 MVar0.01.000Set Grid Terminal voltage =100.0%4)The spread sheet allows more than one number of transformer /generator / motor of identical rating to be modeled in parallel. The load flow result indicated on the branch side are for single circuit.Vt-prestart100.00%Bus-3 Voltage =6.000 kVVt-duringstart100.00%5)Voltages and power flows for "pre-start" condition, i.e. before starting of the motor are displayed in "black" font.4.50.36)Voltages and power flows for "during-start" condition, i.e. at the time of starting of the motor are displayed in "blue" font.Transformer/s7.50.5Nos. of Transformers in parallel=1X'merMVAX'merprikVX'merseckVX'merImp - Z1(pu)X'merX/RX'merZ1ohmsX'merR1ohmsX'merX1ohmsNos. of Generator circuits in parallel=12.560.40.06010.670.003840.000360.00382E=116.2%Vt-prestart100.0%0.30.060Generator/sVt-duringstart100.00%0.5R0.0016GMVAkVpf(pu)Xd"(pu)Xd'(pu)Xd"/RXs(pu)QmaxMvarSet Generator Terminal voltage =100.0%Bus-1 Voltage =0.400 kV10.40.80.200.28201.550.8350.80ApfVt-prestart100.00%0.200.04480.248Prestart0.000 MW0.000 MVar0.01.000Vt-duringstart89.43%ApfPrestart0.779 MW0.480 MVarCable-1 : size3C300During0.000 MW0.000 MW0.01.0000.921320.90.851r(ohms/km)x(ohms/km)Nos of runslength(km)1.131828.10.767During0.869 MW0.727 MVar0.12700.078030.1ONOFFMWMvarpfAmpBus-2 Voltage=0.400kVPrestart0.7570.4660.8511320.9Vt-prestart97.16%97.16%98.66%During0.8260.7010.7631828.145272316Vt-duringstart85.54%85.54%97.80%ONONONCable-2 : size3C185Cable-3 : size3C185Cable-4 : size3C185r(ohms/km)x(ohms/km)Nos of runslength(km)r(ohms/km)x(ohms/km)Nos of runslength(km)r(ohms/km)x(ohms/km)Nos of runslength(km)Prestart0.000 MW0.000 MVarPrestart0.690 MW0.425 MVarPrestart0.067 MW0.042 MVar0.12700.078010.10.12800.075010.150.12800.075020.15During0.082 MW0.243 MVarDuring0.677 MW0.416 MVarDuring0.067 MW0.042 MVarVt-prestart97.16%Bus-4 Voltage =0.400 kVVt-prestart85.56%Bus-5 Voltage =0.400 kVVt-prestart96.59%Bus-6 Voltage =0.400 kVVt-duringstart83.41%MWkVpf(pu)eff(pu)LRC(pu)LRC pf(pu)Vt-duringstart72.63%MWkVpf (pu)% MotorVt-duringstart84.90%MWkVpf(pu)eff(pu)REVISION-1MMNos. of Motor circuits=1Prepared By0.0450.40.750.754.50.30.650.40.8575%0.050.40.850.75Starting MotorRunning Motor/sFLC Amp115.47433.41Lumped LoadFLC Amp1203.61340.3FLC [email protected]

HK: Set generator terminal voltage in % of generator rated voltage depending on its AVR regulation (95% to 105%). Minimum generator terminal voltage shall be considered for worst case resultsHK: Enter number of identical generator circuits (i.e. Generator and its associated 'Cable-1') in parallel at 'Bus-2'.HK: Enter number of identical Transformers in parallel at 'Bus-2' and 'Bus-3'.HK: Enter number of identical Motor circuits (i.e. Motor and its associated 'Cable-4'), in parallel at 'Bus-3'.HK: Set grid terminal voltage in % of grid rated voltage depending on min/max bus voltage variation observed (95% to 105%). Minimum grid terminal voltage shall be considered for worst case [email protected]