Upload
aaporlando
View
228
Download
0
Embed Size (px)
Citation preview
7/27/2019 Moses Crreek IPP Project
1/50
MOSES CREEK POWER INC.
MOSES CREEK HYDROELECTRIC PROJECT
DEVELOPMENT PLAN
Land File: 4405108
Water File: 4005985
APRIL 2013
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC-
Moses CreekHydro Electric Project Page 87 of 162Page 87 of 162Page 87 of 162Page 87 of 162
7/27/2019 Moses Crreek IPP Project
2/50
Development Plan
For the Moses Creek Hydroelectric Project
Submitted in support of applications filed under
Land Act and Water Act
Applicant: Moses Creek Power Inc.
1870 Glacier Lane
P.O. Box 1919
Revelstoke, BC V0E 2S0
Date: April 2013
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 88 of 162Page 88 of 162Page 88 of 162Page 88 of 162
7/27/2019 Moses Crreek IPP Project
3/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. iii April 2013
TABLE OF CONTENTS
TABLE OF CONTENTS ............................................................................................................. iii
LIST OF DRAWINGS .................................................................................................................. v
LIST OF APPENDICES .............................................................................................................. v
EXECUTIVE SUMMARY ........................................................................................................... 1
1. PROJECT DEFINITION ....................................................................................... 2
1.1 PROPONENT ........................................................................................................... 2
1.2 DECISION REQUESTED ............................................................................................ 2
1.2.1 Water Act Application ............................................................................... 2
1.2.2 Land Act Application ................................................................................. 2
1.3 DESCRIPTION OF LAND REQUIREMENTS .................................................................... 3
1.4 GENERALARRANGEMENT OF WORKS ....................................................................... 4
1.4.1 Moses Creek Weir and Intake .................................................................. 41.4.2 Penstock .................................................................................................. 6
1.4.3 Powerhouse ............................................................................................. 6
1.4.4 Beattie Creek Diversion Weir and Intake ........... ........... ........... ........... ...... 7
1.4.5 Diversion Conduit ..................................................................................... 8
1.4.6 Roadside Drainage Ditch ......................................................................... 9
1.4.7 Power Line ............................................................................................... 9
1.4.8 Access Roads ........... ........... ........... ........... ........... ........... ........... ........... .. 9
1.4.9 Staging and Borrowing Areas ................................................................. 10
1.5 GEOPHYSICAL CONSIDERATIONS ............................................................................ 10
1.6 SEISMIC CONSIDERATIONS..................................................................................... 11
1.7 PARAMETERS FOR OPERATION OF WORKS .............................................................. 111.8 WATERSHED CHARACTERISTICS............................................................................. 12
1.9 WATERAVAILABILITY............................................................................................. 13
1.10 MARKET FOR THE PRODUCT................................................................................... 13
1.11 EFFECTS OF PROJECT ON RIGHTS OF OTHERS ........................................................ 14
1.12 PROJECT DEVELOPMENT SCHEDULE ...................................................................... 14
2. IMPACT ASSESSMENT .................................................................................... 15
2.1 FISH AND FISH HABITAT ......................................................................................... 15
2.1.1 Fish Habitat ............................................................................................ 15
2.1.2 Fish Presence ........................................................................................ 19
2.1.3 Invertebrate Data .................................................................................... 20
2.1.4 Instream Flows ....................................................................................... 21
2.2 WILDLIFE AND HABITAT.......................................................................................... 21
2.2.1 Terrestrial Habitat and Vegetation .......................................................... 22
2.2.2 Wildlife .................................................................................................... 24
2.3 RECREATION ........................................................................................................ 27
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 89 of 162Page 89 of 162Page 89 of 162Page 89 of 162
7/27/2019 Moses Crreek IPP Project
4/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. iv April 2013
2.4 FLOOD CONTROL .................................................................................................. 27
2.5 WATER QUALITY ................................................................................................... 28
2.5.1 Physiochemical Parameters ................................................................... 292.5.2 Anions and Nutrients .......... ........... ........... ........... ........... ........... ........... .. 29
2.5.3 Potential Project Effects ......................................................................... 30
2.6 ROADS AND BRIDGES ............................................................................................ 30
2.7 CROWN OWNED RESOURCES................................................................................. 30
2.8 EXISTING RIGHTSWATER AND LAND TENURES ..................................................... 31
2.9 FIRST NATIONS ..................................................................................................... 31
2.9.1 Sexqeltkemc (Lakes Division) of the Secwepemc Nation .......... ........... .. 31
2.9.2 Okanagan Nation Alliance ...................................................................... 32
2.10 ARCHAEOLOGY ..................................................................................................... 32
2.11 AESTHETIC VALUES............................................................................................... 33
2.12 MINERAL CLAIMS................................................................................................... 342.13 NAVIGABLE WATERS PROTECTIONACT................................................................... 34
2.14 HAZARD TO THE PUBLIC......................................................................................... 34
2.15 HAZARD TO THE ENVIRONMENT .............................................................................. 35
2.15.1 Monitoring, Mitigation and Enhancement ............................................ 35
2.15.2 Accidents and Malfunctions .................. ........... ........... ........... ........... .. 35
2.15.3 Climate Change .................................................................................. 36
2.16 COMMUNITY CONSULTATION .................................................................................. 37
2.16.1 Sexqeltkemc (Lakes Division) of the Secwepemc Nation and the
Okanagan Nation Alliance .................................................................................. 37
2.16.2 Revelstoke Snowmobile Club ............................................................. 37
2.16.3 Snowmobile Revelstoke Society ......................................................... 37
2.16.4 Revelstoke Rod and Gun Club ........... ........... ........... ........... ........... ..... 37
2.16.5 Revy Riders Dirt Bike Club ........... ........... ........... ........... ........... ........... 37
2.16.6 City of Revelstoke ............................................................................... 38
2.16.7 Ministry of Tourism, Culture and the Arts ............................................ 38
2.16.8 Transport Canada, Navigable Waters Protection Division ................ .. 38
2.16.9 BC Hydro ............................................................................................ 38
2.17 SOCIO-ECONOMIC BENEFITS.................................................................................. 38
2.17.1 Economic Benefits .............................................................................. 38
2.17.2 Energy Plan Benefits ........................................................................... 39
3. SUMMARY AND CONCLUSION ....................................................................... 40
4. REFERENCES ................................................................................................... 41
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 90 of 162Page 90 of 162Page 90 of 162Page 90 of 162
7/27/2019 Moses Crreek IPP Project
5/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. v April 2013
LIST OF DRAWINGS
Figure 1 Location PlanFigure 2 Drainage Basin BoundariesFigure 3 Project LayoutFigure 4 Moses Creek Power Intake Plan and SectionFigure 5 Penstock Plan and ProfileFigure 6 Penstock Plan and SectionFigure 7 Penstock Pipe Bridge Plan and SectionFigure 8.1 Powerhouse Site PlanFigure 8.2 Powerhouse Site ElevationFigure 9 Beattie Creek Diversion Intake Plan and SectionFigure 10 Diversion Conduit Plan and ProfileFigure 11 Diversion Conduit Plan and SectionFigure 12 Access Road
Figure 13 Transmission LineFigure 14 Crown Land Application Area
LIST OF APPENDICES
Appendix A Construction EnvironmentalManagement Plan
Sigma Engineering Ltd.
Appendix B Hydrology Report Sigma Engineering Ltd.Appendix C Project Schedule Sigma Engineering Ltd.Appendix D Fisheries Impact Assessment Naito EnvironmentalAppendix E Flow Measurement Report Bruce Granstrom
Appendix F Terrestrial Ecology and Wildlife ImpactAssessment Robert G. DEonConsulting Ltd.Appendix G Correspondence with First Nations Bruce GranstromAppendix H Archaeological Preliminary Field
AssessmentEagle Vision Geomatics &Archaeology Ltd.
Appendix I Archaeological Overview Assessmentof Landscape Units R03, R07, R08,R18 and R20, Columbia Forest District
Wayne Choquette
Appendix J Correspondence with RevelstokeSnowmobile Club
Bruce Granstrom
Appendix K Correspondence with SnowmobileRevelstoke Society
Bruce Granstrom
Appendix L Correspondence with Revelstoke Rod
and Gun Club
Bruce Granstrom
Appendix M Correspondence with Revy Riders DirtBike Club
Bruce Granstrom
Appendix N Correspondence with City ofRevelstoke
Bruce Granstrom
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 91 of 162Page 91 of 162Page 91 of 162Page 91 of 162
7/27/2019 Moses Crreek IPP Project
6/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 1 April 2013
EXECUTIVE SUMMARY
Moses Creek Power Inc. is proposing a 4.0 MW run-of-river hydroelectric project on Moses
Creek, which is located approximately 10 km north of the city of Revelstoke in the southern
interior of British Columbia. The Proponent has submitted a water licence application to
FrontCounter BC to withdraw up to 1.70 m3/s from Moses Creek for the purpose of Power
General. Components of the proposed project include: a diversion weir and intake structure on
Beattie Creek, a 900 m long, 0.3 m diameter diversion conduit, a weir and intake structure on
Moses Creek, a 2,195 m long, 0.9 m diameter penstock, a powerhouse containing one 4.0 MW
Pelton type turbine/generator unit and associated controls, a 320 m long 25 kV powerline, 3.43
km of upgraded existing gravel roads and 586 m of new access roads. The entire project area is
situated on Crown Land over which the Proponent has a Crown Land tenure (Investigative
Licence).
Moses Creek has a 14 m set of falls, followed by a bedrock chute directly downstream of thesefalls, located approximately 150 m from its confluence with the Columbia River which constitutes
a complete barrier to upstream fish migration. Three years of fish sampling effort revealed no
resident fish populations in the creek upstream of the 14 m falls.
Beattie Creek has an approximately 30 m bedrock falls and a series of chutes located about
970 m upstream from its mouth that represent a complete barrier to upstream fish migration.
Two years of fish sampling efforts at two different sites revealed no resident fish populations in
the creek upstream of this barrier.
The nearest fish bearing reach in Moses and Beattie Creek is 1 km and 2.5 km downstream of
the diversion reach and intake, respectively.
The Proponent has endeavoured to contact and communicate with all identified stakeholder
groups with a potential interest in the proposed project including: land tenure holders and First
Nations groups, and will continue to consult with these groups as the project progresses. The
Proponent believes that the development of this low-impact renewable green source of power
generation will benefit all British Columbians and help the province of British Columbia meet the
goals outlined in its 2007 BC Energy Plan.
This report was prepared by Sigma Engineering Ltd., with material contributed by Moses Creek
Power Inc., Naito Environmental, Robert G. DEon Consulting Ltd., Eagle Vision Geomatics &
Archaeology Ltd., Lisa Larson and Wayne Choquette.
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 92 of 162Page 92 of 162Page 92 of 162Page 92 of 162
7/27/2019 Moses Crreek IPP Project
7/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 2 April 2013
1. PROJECT DEFINITION
1.1 PROPONENT
The Proponent for the Moses Creek Hydroelectric Project (the Project) is:
Moses Creek Power Inc.
Incorporation #: BC 0891497
Contact: Bruce Granstrom
1125 Pineridge Crescent
Revelstoke, BC V0E 2S1
Ph: (250) 837-7081
Email: [email protected]
The agent for the Project is:Sigma Engineering Ltd.
Contact: Sarah Wyness
400 1444 Alberni Street
Vancouver, BC V6G 2Z4
Ph: (604) 688-8271
Fax: (604) 688-1286
Email: [email protected]
1.2 DECISION REQUESTED
1.2.1 Water Act Application
A water licence application was filed with a priority date of November 4, 2010 for thediversion of water from Moses Creek for the purpose of Power General (File: 4005985).
The application has been made for 0.8 m3/s. On December 6, 2010, FrontCounter BC
concluded that sufficient information was submitted for the Proponent to proceed to Step 3
of the Guide for Waterpower Projects. The maximum diversion amount was revised to be
1.7 m3/s in July 2013.
1.2.2 Land Act Application
Tenure under the Land Actis required for the following components of the Moses Creek
Hydroelectric Project (Application for Crown Land, File: 4405108):
Beattie Creek diversion intake;
Diversion conduit; Moses Creek intake;
Penstock;
Powerhouse;
Access roads;
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 93 of 162Page 93 of 162Page 93 of 162Page 93 of 162
7/27/2019 Moses Crreek IPP Project
8/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 3 April 2013
Staging areas; and
Powerline.
The application for a Licence of Occupation was accepted by FrontCounter BC on
December 6, 2010.
Following a change to the Waterpower Crown Land Use Operational Policy in August
2011, an application for an Investigative Licence was submitted by the Proponent on April
22, 2012. The area and file number of the Investigative Licence application were the same
as for the original Licence of Occupation application.
The application for an Investigative Licence was accepted by FrontCounter BC on April
18, 2012 and offered on November 20, 2012.
1.3 DESCRIPTION OF LAND REQUIREMENTS
The site of the Project proposed by Moses Creek Power Inc. is in the interior of British
Columbia, approximately 10 km north of Revelstoke. The Project location is shown in
Figure 1.
The Moses Creek intake will be located approximately 3.8 km upstream of Moses Creeks
confluence with the Columbia River. The Moses Creek intake elevation will be
approximately 830 m above mean sea level (AMSL). The Beattie Creek tributary diversion
intake will be located approximately 3.4 km upstream of Beattie Creeks confluence with
the Columbia River at an elevation of approximately 930 m AMSL.
The Project layout (Figure 3) shows the diversion conduit and penstock alignment. The
diversion conduit will be approximately 0.25 m in diameter and 900 m long; it will direct
water from the Beattie Creek diversion intake into Moses Creek immediately upstream of
the Moses Creek intake. The penstock will be approximately 0.9 m in diameter and 2,195
m long; it will direct water from the Moses Creek intake to the powerhouse. Thepowerhouse will be located at approximately 532 m AMSL, as shown in Figure 3.
Access to the Project area will be from Revelstoke via Westside Road, Glacier Lane and
existing forest roads in the Moses Creek basin. The construction of two new permanent
gravel based roads will be required to access the Moses Creek intake and powerhouse
sites. An approximately 400 m long road will connect the powerhouse to Westside Road.
A second road of approximately 186 m in length will be constructed to access the Moses
Creek intake site from the existing forest road (Forest File ID: R07401). Additional
temporary roads/machine trails of approximately 580 m in total length will be required
during construction of the penstock (Figure 3).
Two aggregate extraction (borrow) areas, one adjacent to the proposed powerhouse site
will be used to supply the Project with gravel and/or rip rap. The quarry site near the
powerhouse is located entirely on Crown Land and is approximately 1 ha in size. Asecond quarry will be located near the intake and will be approximately 0.5 ha in size
(Figure 3).
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 94 of 162Page 94 of 162Page 94 of 162Page 94 of 162
7/27/2019 Moses Crreek IPP Project
9/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 4 April 2013
The general area of the Project has experienced a high degree of human disturbance in
the form of forest management (clear-cut logging and road construction) throughout the
majority of the Project footprint as well as gravel quarries, a 500 kV transmission linecorridor and cleared industrial land associated with the Revelstoke Dam construction and
operation at lower elevations of the Project area. There is an active Occupant Licence to
Cut (Forest File ID: L48334) that extends across the upper reaches of the Moses Creek
and Beattie Creek drainages, but does not overlap with any of the proposed Project
works.
A 25 kV powerline, approximately 320 m in length, will connect the powerhouse to the
existing BC Hydro 25 kV powerline that runs alongside Westside Road, subject to review
by BC Hydro.
The land tenure area applied for in the Land Application (File No. 4405108) for the Project
is 208.3 ha (Figure 14). Note that this area is far larger than that which is anticipated for
the final land requirement in order to accommodate further changes to the design.
Based on the preliminary design illustrated in the Drawings, the estimated land
requirements for specific Project components are as follows:
Beattie Creek diversion intake = 0.35 ha
Diversion conduit/road = 2.81 ha
Moses Creek intake = 0.43 ha
Penstock/road = 6.52
Powerhouse = 0.54 ha
Power line/road = 0.79 ha
Other access roads (including temporary penstock access) = 5.02 ha
Laydown areas = 1.53 ha
The total estimated land requirement for the Project is therefore approximately 17.99 ha,which includes areas disturbed during construction. Final design will aim to minimize
unnecessary land disturbance, clearing will be kept to a minimum during construction, and
disturbed areas will be re-vegetated with native species immediately following construction
completion.
1.4 GENERALARRANGEMENT OF WORKS
Figure 3 shows the Project layout. The preliminary design for the Project is described in
the sections below. The proposed designs will be reviewed and revised as required
following further surveying and detailed design.
1.4.1 Moses Creek Weir and Intake
Layout
The Moses Creek intake will be located approximately 3.8 km upstream of the creek
mouth at an elevation of approximately 830 m AMSL. The intake plan is shown in Figure
4.
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 95 of 162Page 95 of 162Page 95 of 162Page 95 of 162
7/27/2019 Moses Crreek IPP Project
10/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 5 April 2013
The intake will consist of a weir and an intake structure. The weir will be approximately 1.5
m high and 20 m long; it will span the creek and create a small headpond to ensure
adequate intake submergence. The concrete intake will direct water from the headpondinto the penstock. The intake structure will include a bypass valve that will provide the
minimum instream flow release, a sluice gate, trashracks to block large debris and
stoplogs to isolate the intake structure for maintenance. The intake and weir will be
designed to pass the 200-year peak instantaneous flow.
Basedon preliminary field measurements, the headpond created above the intake will
have an approximate area of 150 m2. It is anticipated that the maximum depth will not
exceed the seasonal high-water mark. The depth of the headpond will vary from 1.5 m
deep at the weir to the pre-Project depth at the upstream end of the impoundment. The
total headpond volume would therefore be approximately 113 m3. At the design flow (1.65
m3/s), this would create 1 minute of total storage.
Construction
The construction sequence will be left to the discretion of the contractor. The concrete
intake structure and weir will be constructed in the dry. Building in the dry will minimize the
input of sediment to Moses Creek.
Operation
The water level at the intake and in the creek upstream of the weir will be kept stable
during most flow conditions by controlling the rate of flow at the turbine. At flows less than
the design flow, a level control sensor at the intake will regulate turbine discharge in order
to maintain the operating water level approximately equal to the height of the weir. An
instream flow release valve will provide the minimum instream flow. When creek flow
exceeds the sum of the design flow and the minimum instream flow, any excess water will
pass over the weir.
The intake structure will include a sluice gate to release sediment (bedload) that
accumulates at the intake structure. Any large boulders transported during significant flow
events and deposited in the intake area and interfere with the operation of the intake will
be removed with a machine, and if feasible, returned to the creek below the weir.
It is expected that much of the larger debris (i.e. logs and other woody debris) will move
downstream during high flow events and will therefore pass over the weir. Smaller debris
that passes downstream during flows of less than the design flow plus minimum instream
flow will accumulate on the trashracks. This debris will be removed by plant personnel
during routine maintenance and returned to the creek downstream of the weir.
There will be stoplogs between the intake channel and sluice channel to allow
maintenance to the sluice channel to occur in the dry. There will be a slide gate at the inlet
to the penstock, which during normal operation would be left open. This gate would beclosed for maintenance to allow work to occur in the dry.
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 96 of 162Page 96 of 162Page 96 of 162Page 96 of 162
7/27/2019 Moses Crreek IPP Project
11/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 6 April 2013
1.4.2 Penstock
LayoutThe penstock alignment will be as shown in Figure 3. The penstock will be approximately
0.9 m in diameter and 2,195 m long; it will direct water from the Moses Creek intake to the
powerhouse. The majority (1,610 m) of the penstock will be buried under the intake
access road and existing forest roads. Typical road cross-sections showing the buried
penstock are shown in Figure 6. The remaining 585 m of penstock will be buried within an
excavated trench. An approximately 60 m long section of penstock where it travels down a
steep slope toward the powerhouse and crosses Moses Creek may require placement
above ground. Every effort will be made to bury the penstock wherever feasible. The
penstock crossing of Moses Creek will utilize a pipe bridge; a typical pipe bridge is shown
in Figure7. The penstock profile is shown in Figure 5.
Pipe materials will be a combination of high-density polyethylene (HDPE) and steel. The
HDPE pipe will be used in the low-pressure section of the penstock and the steel pipe inthe higher pressure section.
Construction
Approximately 585 m of the pipe alignment will require clearing. To minimize clearing, the
penstock alignment will follow the access road and existing forest roads where possible.
A pipe fusion machine will be used to join the HDPE pipe sections and the steel pipe
sections will be welded. The HDPE pipe can be pulled into its final alignment using mobile
equipment. Where the penstock route is accessible by truck, steel pipe sections will be
hauled by truck and placed with an excavator. In non-accessible sections such as the 60
m long section near the powerhouse where the penstock travels down a steep slope, the
steel pipe will be high-lined into place from uphill and placed manually.
The Moses Creek penstock crossing near the powerhouse site will be a clear span above
the 200-year flood level and creek flows will not be disturbed during construction. The
remainder of the penstock route does not cross any tributaries to Moses Creek. Best
management practices during construction will minimize erosion and sedimentation to the
creek. Disturbed areas will be re-vegetated with native species.
1.4.3 Powerhouse
Layout
The generation facilities will be located at approximately 532 m AMSL. The Project will
yield a gross head of 298 m. The powerhouse will be a metal clad steel frame building on
concrete foundation, measuring approximately 18 m by 8 m by 10 m high and will house a
single Pelton turbine/generator unit producing a total of 4.0 MW, controls and atransformer. The control room will provide a complete interface as necessary for remote
operation, and all electrical control equipment. Figures 8.1 and 8.2 show the preliminary
layout of the powerhouse area.
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 97 of 162Page 97 of 162Page 97 of 162Page 97 of 162
7/27/2019 Moses Crreek IPP Project
12/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 7 April 2013
The tailrace channel will be an open channel. It will transport discharged water back to
Moses Creek. The tailrace cross-section and slope will be designed to reduce the
potential scour from turbine discharge and rip-rap will be placed, as required, to provideerosion protection.
Construction
Access to the powerhouse will be via the access road shown in Figure 3 and described
below. Best management practices during construction will minimize erosion and
sedimentation into Moses Creek.
Operation
Water from the penstock will pass through a pipe, turbine inlet valve, needle valve nozzle
jets, and turbine runner before discharging into the tailrace. A single Pelton turbine will be
used for the Project; this type of turbine does not require a minimum tailrace elevation be
maintained for submergence. Powerhouse operations will be monitored remotely from the
Proponents office. A local operator will visit the powerhouse as required to monitoroperation. The tailrace will be a rip-rap lined open channel conveying discharged water
back to Moses Creek during operations.
1.4.4 Beattie Creek Diversion Weir and Intake
Layout
The Beattie Creek diversion intake will be located on the northern-most tributary of Beattie
Creek, approximately 760 m upstream of the confluence with the first main tributary of
Beattie Creek at an elevation of approximately 930 m AMSL. The intake plan is shown in
Figure 9. The Beattie Creek intake is designed to transfer the proposed flow to Moses
Creek immediately upstream of the Moses Creek intake.
The diversion intake will consist of a weir and a lateral intake structure on the left bank ofthe creek. The weir will be approximately 1.5 m at its highest point and 10 m long; it will
span the creek and create a smallheadpond to ensure adequate intake submergence.
The concrete intake will direct water from the headpond into the diversion conduit. The
intake will be equipped with a bypass gate that will provide the minimum instream flow
release, a sluice gate, trashracks to block large debris and stoplogs to isolate the intake
structure for maintenance. The intake and weir will be designed to pass the 200-year peak
instantaneous flow.
Basedon preliminary field measurements, the headpond created above the intake will
have an approximate area of 75 m2. It is anticipated that the maximum depth will not
exceed the seasonal high-water mark. The depth of the headpond will vary from 1.5 m
deep at the weir to the pre-Project depth at the upstream end of the impoundment. The
total headpond volume would therefore be approximately 56 m3. At the design flow (0.3m3/s), this would create less than a minute of total storage.
Construction
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 98 of 162Page 98 of 162Page 98 of 162Page 98 of 162
7/27/2019 Moses Crreek IPP Project
13/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 8 April 2013
The construction sequence will be left to the discretion of the contractor. The concrete
intake structure and weir will be constructed in the dry. Building in the dry will minimize the
input of sediment to Beattie Creek.Operation
The water level at the intake and in the creek upstream of the weir will be kept stable
during most flow conditions. It will be designed to provide the minimum flow through an
instream flow valve under all flow conditions and the excess flow above that valve will be
diverted into the diversion pipe up to the limit of the capacity of the pipe. Any excess
water will pass over the weir. The diversion weir flows will not be controlled by the rate of
flow at the turbine.
The intake structure will include a sluice gate to release sediment (bedload) that
accumulates at the intake structure. Any large boulders transported during significant flow
events and deposited in the intake area that interfere with the operation of the intake will
be removed using machinery, and if feasible, returned to the creek below the weir.It is expected that much of the larger debris (i.e. logs and other woody debris) will move
downstream during high flow events and will therefore pass over the weir. Smaller debris
that passes downstream during flows of less than the design flow plus minimum instream
flow will accumulate on the trashracks. This debris will be removed by plant personnel
during routine maintenance and returned to the creek downstream of the weir.
There will be stoplogs between the intake channel and sluice channel to allow
maintenance to the sluice channel to occur in the dry. There will be a slide gate at the inlet
to the penstock, which during normal operation would be left open. This gate would be
closed for maintenance to allow work to occur in the dry.
1.4.5 Diversion Conduit
Layout
The diversion conduit alignment will be as shown in Figure 3. The conduit will be
approximately 0.3 m in diameter and 900 m long; it will direct water from the Beattie Creek
diversion intake to the Moses Creek intake. The majority of the conduit will be buried
under the existing forest road. Typical road cross-sections showing the buried penstock
are shown in Figure 11. The remaining 130 m of conduit, which runs due north from the
forest road to the Moses Creek intake, will be incorporated into the upgrade of an existing
remnant drainage ditch (Refer to Section 1.4.6). The conduit will carry a design flow of
0.25 m3/s of water from the Beattie Creek tributary to Moses Creek.
The pipe material will be high-density polyethylene (HDPE).
Construction
Approximately 130 m of the pipe alignment will require clearing. To minimize clearing, the
conduit alignment will follow the existing forest road where possible.
A pipe fusion machine will be used to join the HDPE pipe sections. The HDPE pipe will be
pulled into its final alignment using mobile equipment.
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 99 of 162Page 99 of 162Page 99 of 162Page 99 of 162
7/27/2019 Moses Crreek IPP Project
14/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 9 April 2013
The conduit route does not cross any tributaries to either Beattie Creek or Moses Creek.
Best management practices during construction will minimize erosion and sedimentation
to the creeks. Disturbed areas will be re-vegetated with native species.
1.4.6 Roadside Drainage Ditch
A remnant drainage ditch currently travels the approximate route proposed for the last 200
m of the diversion conduit and is thought to have been constructed in previous decades to
divert water away from the existing gravel quarry immediately down slope of this location.
The ditch drains runoff from an area of approximately 0.406 km2 between Moses and
Beattie Creeks (Figure 2). Through a combination of upgraded ditching and perforated
pipe, the ditch runoff will be collected and incorporated into the diversion conduit. The
diversion conduit will be routed slightly above the existing ditch line in order to deliver the
water upstream of the Moses Creek intake.
1.4.7 Power Line
A 25 kV power line will connect the powerhouse to the existing BC Hydro 25 kV power line
that currently runs alongside the eastern side of Westside Road, subject to review by BC
Hydro. The total power line length will be approximately 320m. The existing BC Hydro
power line at the point of interconnection is a three-phase line.
The power line route will include one crossing of an unnamed tributary to Moses Creek
(Figure 3). This is a small tributary that may have been previously diverted or represent
ditch drainage along the eastside of the existing road. Further site assessment will be
conducted to confirm. The crossing will be clear span above the 200-year flood level and
tributary flows will not be disturbed during construction. Best management practices and
Fisheries and Oceans Canada (DFO) Operational Statement for Overhead Line
Construction will be followed during construction to minimize impacts to riparian habitat
and to prevent erosion and sedimentation to the creek.
1.4.8 Access Roads
Layout
Access to the intake, powerhouse and majority of the penstock route will be from existing
forest roads in the vicinity of Moses Creek and two new gravel roads. The powerhouse
access road will originate approximately 10 km north along Westside Road from
Revelstoke and is approximately 400 m in length. The majority of the new powerhouse
access road will follow an abandoned road routing and therefore minimize the extent of
clearing required. The intake access road is approximately 180 m in length and will branch
off of an existing Frisby Forest Service Road (Forest File ID: R07401) that runs along the
southwestern side of the Moses Creek basin. Both the powerhouse and intake accessroads will be kept for operation and maintenance access following Project construction.
Temporary access roads/machine trails totalling approximately 360 m in length will also be
required during construction to access the portions of the penstock route that do not follow
existing/proposed roads. Following construction, these temporary access roads will be
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 100 of 162Page 100 of 162Page 100 of 162Page 100 of 162
7/27/2019 Moses Crreek IPP Project
15/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 10 April 2013
deactivated (i.e. recontoured) and disturbed areas will be re-vegetated with native
species.
Construction
New roads will be designed and constructed using best management practices to
minimize sedimentation and erosion. The roads will include ditching and draining for local
runoff. Roads will be designed and constructed in general accordance with the Forest
Road Engineering Guidebook.
1.4.9 Staging and Borrowing Areas
Three laydown areas are proposed for construction (Figure 3). Laydown areas will be
located at both intake sites and along the penstock route. The estimated size of each
laydown area is as follows:
Beattie Creek Diversion Intake: 10 m x 20 m = 200 m2 (0.02 ha)
Moses Creek Intake: 15 m x 20 m = 300 m2 (0.03 ha)
Penstock: 20 m x 30 m = 600 m2 (0.06 ha)
The total estimated land required for laydown areas is therefore 1,100 m 2 (0.11 ha). All
three laydown areas are located on Crown Land.
Spoil area locations and size will be determined as the Project design advances and
reasonable estimates of the material volume become available.
The Project will endeavour to keep the quantity of borrowed materials to a minimum. A
small (~ 1 ha) quarry immediately adjacent to the powerhouse and ~0.5 ha quarry near
the intake are being proposed as part of the Project. The proposed location of the quarries
are within heavily disturbed sites which were previously logged and cleared. The quarry
area near the powerhouse was used as a laydown and temporary storage site during theconstruction of the Revelstoke Dam. Two borrow pit areas are proposed for construction.
A borrow pit area will be located near the intake and near the powerhouse. The estimated
size of each borrow pit area is as follows:
Moses Creek Intake: 50 m x 100 m = 5000 m2 (0.5 ha)
Powerhouse: 50 m x 200 m = 10000 m2 (1 ha)
Any borrow areas will be stabilized and re-vegetated in accordance with the Construction
Environmental Management Plan (CEMP; Appendix A) and in consultation with the
Environmental Monitor.
1.5 GEOPHYSICAL CONSIDERATIONS
No geotechnical or slope stability issues have been identified as being of potential
concern in a preliminary assessment made by the Proponents general engineering
consultant. Due diligence geotechnical assessments of the construction areas including
the two intake sites and the powerhouse site as well as the penstock and access road
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 101 of 162Page 101 of 162Page 101 of 162Page 101 of 162
7/27/2019 Moses Crreek IPP Project
16/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 11 April 2013
routes will be conducted during detailed Project design. The goal of these assessments
will not be to determine the feasibility of the construction; rather they will be used by the
design engineers and contractors to fine tune the placement and dimensions of theProject works. These assessments will include a statement of the terrain stability in the
Project area.
The Project is not expected to negatively alter the relationship between flow, sediment and
channel form with associated impacts to fish habitat. Although the proposed Project will
reduce flows in Beattie Creek and the diversion reach of Moses Creek, peak flows during
spring freshet are expected to continue to reach in excess of 200% mean annual flow (for
a minimum of 7 days; furthermore, an average of 70 days/ year will have flows greater
than 200% MAF), which is sufficient to maintain sediment and debris movement (Naito
2013). Large debris (boulders and LWD) and sediment that accumulate in the headpond
of the Project will be returned to the creek downstream of the weir.
The potential for adverse geochemical issues such as metal leaching and acid rock
drainage have not been identified in relation to the Project. These issues are typically
associated with projects that have a tunnel (as opposed to buried penstock) where
significant volumes of sub-surface rock is removed during tunnel boring and stored for
prolonged periods of time on the surface in the vicinity of the creek. The Project does not
use a tunnel for water conveyance and any sub-surface rock exposed during Project
construction will be used for back fill and/or road construction. Should any significant
quantities of excavated rock require storing during Project construction, the Proponent will
incorporate prevention and mitigation measures for acid rock drainage, metal leaching,
and sedimentation into the Construction Environmental Management Plan.
1.6 SEISMIC CONSIDERATIONS
Although the west coast of Canada is an area of significant earthquake activity, seismicity
in the Southern Cordillera BC interior and Rocky Mountain region south of 60N drops
off rapidly1.
Moses Creek is located in an area that the Geological Survey of Canada classifies as an
area of relatively low earthquake hazard. To minimize the potential effects associated with
seismic activity, the Project powerhouse, intake and spillway will be designed to withstand
seismic loading as defined in the BC Building Code.
1.7 PARAMETERS FOR OPERATION OF WORKS
The Project will use flow from Beattie Creek and Moses Creek. The electricity generated
will be supplied to BC Hydro under a long-term Electricity Purchase Agreement (EPA). It is
expected that the Project will qualify for an EPA under BC Hydros Standing Offer
Program (SOP).
1Natural Resources Canada website. http://seismescanada.rncan.gc.ca/zones/westcan_e.php#Cascadia. Accessed
April 1, 2009.
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 102 of 162Page 102 of 162Page 102 of 162Page 102 of 162
7/27/2019 Moses Crreek IPP Project
17/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 12 April 2013
The expected commercial operation date (COD) of the Project is March 2016, based on
timely permitting and procurement of long lead-time items such as the turbine.
Project operations will be based on the sum total flow from the Beattie Creek diversionintake and Moses Creek intake. During periods of high flows, the Project will operate at full
capacity. During periods of low flows, when the available flow is less than the sum of the
minimum instream flows and the minimum turbine flow, the plant will be shut down. During
times of intermediate flow, the plant will operate at partial capacity. The Moses Creek
Hydroelectric Project Hydrology Report (Appendix B) provides more information about pre
and post-Project flows.
Details of operational parameters for the Project will be obtained during detailed design
and turbine procurement and become part of the operations manual for the Project.
These will be submitted to the Ministry of Forest, Lands and Natural Resource Operations
Resource Stewardship Division in a Parameters and Procedures Report (OPPR) prior to
diversion.
1.8 WATERSHED CHARACTERISTICS
Moses Creek (Watershed Code: 300-757000) and Beattie Creek (Watershed Code: 300-
754800-55000) are located approximately 10 km north of the city of Revelstoke in the
Southern Interior of British Columbia. The main channel of Moses Creek is approximately
6 km long and flows in a south-southeast direction into the Columbia River, just
downstream of the BC Hydro Revelstoke dam. The main channel of Beattie Creek is
approximately 4.7 km long and flows in an east southeast direction into the Columbia
River, approximately 4 km upstream of the City of Revelstoke. Beattie Creek historically
flowed into the Jordan River but was diverted east to its current route, the Columbia River
about 3 km upstream from Revelstoke, some time ago. Further to Beattie Creeks history
of diversion, the northern most Beattie Creek tributary (from which flow diversion for the
Project is proposed) originally flowed into Moses Creek approximately 1,800 m upstream
of the Columbia River confluence. The flows from the Beattie Creek tributary were
diverted to the current stream route (into Beattie Creek) during construction of the
Revelstoke dam (Figure 2).
At the proposed intake locations, the Moses Creek and Beattie Creek watersheds are
approximately 6.9 km2 and 1.29 km2, respectively. The additional drainage area between
the two watersheds and the flows from which will be captured by the roadside ditch is
approximately 0.406 km2. Elevations of the Moses Creek watershed range from a
maximum of 1,980 m AMSL atop the Frisby Ridge to approximately 460 m AMSL at the
confluence of Moses Creek with the Columbia River. The elevations of the proposed
Beattie Creek diversion intake, Moses Creek intake and powerhouse locations are 930 m,
830 m and 532 m AMSL, respectively.
The basins span two biogeoclimatic zones, the Interior Cedar Hemlock and Engelmann
Spruce Subalpine Fir, which are characterized by cool wet winters and long warm
summers that are kept moist by the presence of a slow-melting snowpack at higher
elevations.
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 103 of 162Page 103 of 162Page 103 of 162Page 103 of 162
7/27/2019 Moses Crreek IPP Project
18/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 13 April 2013
Fish and fish habitat within the watershed are described in Section 2.1.
1.9 WATER
AVAILABILITY
The Hydrology Study (Appendix B) reviews the regional hydrology, describes the available
flow data and daily flows used in the analysis, including monthly flows, peak and low flows
and flow duration curves.
The study utilized 33 years of flow data from the Water Survey of Canada (WSC) gauge:
Kirbyville Creek near the mouth (WSC 08ND019). Flows at the Moses Creek intake,
Beattie Creek diversion intake and within the roadside ditch were synthesized from the
Kirbyville WSC record by prorating flows based on drainage areas and then multiplying by
monthly adjustment factors to account for anticipated differences in annual unit runoff.
The mean annual flow (MAF) at the Moses Creek intake including the runoff from the
0.406 km2 area between Moses and Beattie Creeks collected by the roadside ditch and
diverted upstream of the intake is 0.394 m3
/s. An average of 0.055 m3
/s (with a maximumof 0.25 m3/s) will be diverted from Beattie Creek to Moses Creek through the diversion
conduit. The MAF at the Moses Creek intake is therefore expected to be 0.449 m3/s.
(Appendix B; Figure 5) shows the monthly flow variation. Mean monthly flows at the
Moses Creek intake range from 0.01 m3/s in February to 1.81 m3/s in June.
The installed capacity of the Project will be 4.0 MW based on a gross head of 298 m, a
design flow of 1.65 m3/s, and a turbine/generator efficiency of 87.36%. The annual
generation is expected to be 7.5 GWh. The minimum turbine flow will be 10% of the
design flow (0.165 m3/s).
The Proponent installed a water level gauge on Moses Creek in October 2010. Water
level and temperature data are recorded every 15 minutes. Specific details regarding the
gauge installation site, development of a stage-discharge curve (Appendix E) and
comparison of the 2010, 2011 and 2012 in situ flow record with the records of four WSCgauges are presented in the Moses Creek Hydroelectric Project Hydrology Report
provided as Appendix B. In summary, the Moses Creek flows are similar to the average
annual unit flows of two active WSC gauge records and the non-active long term flow
record of the Kirbyville Creek gauge (Appendix B; Figure 4). Therefore, the 2011
measured Moses Creek flows are similar to the long term average at Kirbyville Creek and
by extension to the long term average at Moses Creek. Once a statistically significant
number of years (at least 3) of measured flows become available, the long term estimated
flows will be reviewed and adjusted using the in situ flow data. However, the Moses
Creek hydrograph is different from that of Kirbyville Creek, as the peak flows at Moses
occur in May June, whereas at Kirbyville Creek the peak flows are in June July.
1.10 MARKET FOR THE PRODUCTThe electricity generated by the Project will be supplied to BC Hydro under a long-term
EPA. It is anticipated that, once permitting is complete, the Project will qualify for an EPA
under the BC Hydro Standing Offer Program.
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 104 of 162Page 104 of 162Page 104 of 162Page 104 of 162
7/27/2019 Moses Crreek IPP Project
19/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 14 April 2013
Electricity generated by the Project will be supplied to the BC Hydro grid through a 25 kV
power line that currently runs alongside Westside Road. The point of interconnection will
be approximately 320 m from the Projects powerhouse.
1.11 EFFECTS OF PROJECT ON RIGHTS OF OTHERS
The Project should not have any significant negative effects on the rights of other users.
Section 2 includes a detailed assessment of potential impacts to users resulting from the
proposed Project, including: other land tenures, recreation, mining and First Nations.
1.12 PROJECT DEVELOPMENT SCHEDULE
A project development schedule is attached as Appendix C.
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 105 of 162Page 105 of 162Page 105 of 162Page 105 of 162
7/27/2019 Moses Crreek IPP Project
20/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 15 April 2013
2. IMPACT ASSESSMENT
2.1 FISH AND FISH HABITAT
Preliminary fish and fish habitat surveys of Moses Creek and Beattie Creek were
completed by Naito Environmental in September 2010. Further field studies were
conducted during September 2011 and August 2012 (Appendix D). The purpose of these
surveys was to identify the aquatic resources of Moses and Beattie Creek and to
determine the potential impact of the Project on these resources. A background literature
search found no existing fisheries information for Moses or Beattie Creek in the web-
based Fisheries Inventory Data Queries Tool (MOE 2012b) or EcoCat, the Ministry of
Environments ecological reports catalogue (MOE 2012a).
2.1.1 Fish Habitat
Moses Creek (Watershed Code: 300-757000) is a second order stream flowing generallysoutheast into the Columbia River just downstream of the Revelstoke Dam. It is located
approximately 5 km north-northwest of Revelstoke in the Jordon Range of the Monashee
Mountains in the southern interior of British Columbia.
Moses Creek has a watershed area of 11.7 km2 and a stream length of approximately 6
km. Its peak elevation is at approximately 1900 m at the top of Frisby Ridge. The average
gradient of Moses Creek is between 10-23%. Moses Creek represents a high energy
watershed.
Beattie Creek (Watershed Code 300-754800-55000) is the adjacent drainage south of
Moses Creek, and flows generally southeast for approximately 4.7 km. Historically,
Moses Creek flowed into the Jordan River but was diverted some time ago and now
enters the Columbia River approximately 4 km upstream. In addition, the northern-most
Beattie Creek tributary (from which flow diversion for the Project is proposed) originallyflowed into Moses Creek approximately 1.8 km upstream from the mouth of Moses Creek;
however, flows from this tributary were diverted from Moses to Beattie Creek during
construction of the Revelstoke dam.
Moses Creek has a 14 m set of falls (Moses Falls) followed by a bedrock chute directly
downstream located approximately 150 m from its confluence with the Columbia River
which constitutes a total barrier to upstream fish migration. Fish sampling efforts did not
detect any fish upstream of this barrier located in Reach 1. Numerous barriers exist
upstream of this first set of falls and include numerous steep sections, falls, and bedrock
chutes within the diversion reach of Moses Creek. Fish from the Columbia River can
access the first 150 m of the 370 m long Reach 1. Further upstream passage is blocked
by Moses Falls.
Beattie Creek has an approximately 30 m bedrock falls and chutes that are located about
970 m upstream from the mouth and represent a total barrier to upstream fish migration.
Two years of fish sampling efforts at two different sites did not detect any fish upstream of
this barrier located 80 m into Reach 3.
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 106 of 162Page 106 of 162Page 106 of 162Page 106 of 162
7/27/2019 Moses Crreek IPP Project
21/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 16 April 2013
Stream habitat was characterised for eight reaches on Moses Creek and five reaches on
Beattie Creek.
Moses Creek Reaches
During the 2010 field program, eight reaches were delineated from the mouth of Moses
Creek to upstream of the proposed intake (Appendix D, Figure 5). With the exception of a
short reach with 6-8% gradient, the diversion section of Moses Creek had a gradient of
10-23%. The majority of the diversion section had an entrenched channel or canyon
dominated by bedrock. Reaches 1 and 2 are downstream of the Project. Reaches 3,4,5
and 6 comprise the diversion section of Moses Creek and reaches 7 and 8 are upstream
of the proposed Project intake. Some field sampling took place in reaches 7 and 8 during
2011 when an alternative intake option was being investigated.
Reach 1 extends from the Columbia River to about 100 m upstream of Westside Road.
About 20 years ago, BC Hydro undertook a tailrace excavation project to improve power
production at Revelstoke Dam, such a reduction in bed level of the Columbia Riverresulted in the mouth of Moses Creek being perched several meters higher than the
Columbia River. Consequently, a channel was excavated to direct Moses Creek flows
upstream along the edge of the Columbia River at a reduced gradient suitable for fish
spawning. In effect, the forebay area of Moses Creek contains extensive gravel deposits
that extend approximately 50 m upstream at which point, the streambed becomes boulder
and the gradient increases to about 5%. Bed material in Reach 1 is dominated by cobble,
with boulder subdominant and boulder is the main cover type. Upstream of the first 50 m,
fish habitat quality in Reach 1 is low for spawning due to a lack of gravel, low for
overwintering due to limited low velocity areas with cover, and low for rearing due to a lack
of deep pools.
Reach 2 extends from about 100 m upstream of Westside Road to the large pond that is
designated at Reach 2.1. It is a 1 km long, low gradient (1-2%) section of stream thatflows out of the larger of two ponds that occur along the route of Moses Creek. The
dominant bed material is cobble with gravel subdominant and small woody debris
comprises the main cover type. Fish habitat quality was assessed as moderate to good,
with spawning capability limited by the high percentage of fines in the substrate. Rearing
and overwintering habitat was assessed as good due to the presence of pools with
abundant small and large woody debris cover and low velocity flows.
Reach 2.1 (Pond #1) is a 200 m long, 1 ha pond, which appears to be the result of
artificial impoundment and is bounded on the downstream side by a paved roadway.
Moses Creek exits the pond through a large diameter culvert under the roadway. The
perched culvert and steep, rocky outlet channel is an additional barrier to fish migration.
Reach 3 is 1.2 km long and extends between the upper and lower ponds on Moses Creek.
The proposed powerhouse and tailrace will be at the downstream end of this reach. Withthe exception of a short section of lower gradient at the downstream end of this reach, the
reach has an average slope of between 14-20% and is entrenched with boulder and
bedrock the dominant and subdominant materials, respectively. Throughout the reach
there are a series of 1-2 m falls and chutes in addition to an approximately 4 m waterfall
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 107 of 162Page 107 of 162Page 107 of 162Page 107 of 162
7/27/2019 Moses Crreek IPP Project
22/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 17 April 2013
about 200 m upstream from the upper reach boundary. Cover types are dominated by
boulder and large woody debris. Fish habitat quality was assessed as good for rearing
and holding due to the presence of deep pools formed by the cascade channel, buthabitat was only fair for spawning due to the limited gravel. Overwintering habitat was
assessed as low due to a lack of low velocity edge habitat.
Reach 3.1(Pond #2) represents the smaller of the two in-line ponds on Moses Creek. This
pond is 130 m long, 0.8 ha and appears to be at least partially the result of artificial
impoundment because it is bounded on the downstream side by an unpaved roadway.
Moses Creek exits the pond partially via a 900 mm diameter culvert under the roadway,
and at other points appears to flow right through the angular rock of the road base. An
approximate 10 m drop in elevation from the pond to the creek downstream would prohibit
upstream fish passage, if fish were present.
Reach 4 is a 230 m long, low gradient section (6-8%) that flows into Pond #2. Reach 4 is
highly variable, with cobble riffle at its downstream end as well as sections of bedrock and
boulder/cobble throughout. Cobble is the dominant bed material with boulder
subdominant and the main cover type. Canopy closure was low at less than 20%. Fish
habitat quality was assessed at low-moderate.
Reach 5 is 625 m long with a confined bedrock channel and steep gradient (up to 23%)
which includes numerous chutes, drops, and waterfalls. The channel morphology is step-
pool formed by rock and the dominant cover type is deep pool. Fish habitat quality was
assessed as good for holding and rearing due to the presence of deep pools, but
spawning habitat was only fair due to the limited gravel in pool tailouts. Overwintering
habitat was assessed as fair with some pool habitat but a lack of cover and/or low velocity.
Reach 6 is 150 m long and extends from the Reach 5 upstream to a main tributary
referred to as Tributary A. Tributary A enters Reach 6 from the right bank immediately
upstream of the proposed intake. Reach 6 has a gradient of 12-16% and a cascade-poolchannel morphology that is maintained by boulder and large woody debris. The dominant
bed material is cobble, with boulder subdominant and the dominant cover type. Cover
type included large woody debris and deep pool. Fish habitat quality was assessed as
good for rearing and holding due to deep pools and pockets, moderate for spawning with
occasional gravel patches, and moderate for overwintering pools.
Reach 7 extends 590 m upstream from the confluence with Tributary A to the confluence
with a major left bank tributary, Tributary C. Channel morphology is cascade-pool and the
stream gradient is 9-11% in this section. The dominant bed material is boulder, with
cobble subdominant. Boulder and overhanging vegetation comprised the dominant and
subdominant cover types, respectively. Fish habitat quality was assessed as low for
spawning in limited isolated pockets of gravel but moderate for rearing and overwintering
in pools with boulder and large woody debris cover.Reach 8 extends upstream from the confluence with Tributary C. Reach 8 has a stream
gradient of 8-11% which creates cascade-pool channel morphology. The dominant bed
material is boulder, with cobble subdominant. Boulder is the dominant cover type. Fish
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 108 of 162Page 108 of 162Page 108 of 162Page 108 of 162
7/27/2019 Moses Crreek IPP Project
23/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 18 April 2013
habitat quality was assessed as low for spawning and overwintering but high for rearing
due to the presence of pocket pools with boulder cover.
Beattie Creek
Of the five reaches delineated on Beattie Creek from the mouth up to the vicinity of the
proposed tributary intake, Reaches 1 and 2, and the lower 80 m of Reach 3 appear to be
accessible to fish from the Columbia River. Further upstream passage is blocked by an
impassable falls 1 km from the mouth of Beattie Creek.
Reach 1 is a 225 m long steep section where the diverted stream has cut a channel from
the riverside terrace down to river level, at the Columbia River, about 30 m below. The
Reach 1 stream gradient ranges from ~5-11%. The dominant bed material in Reach 1 is
boulder, with cobble subdominant. Boulder is the main cover type. Fish habitat quality in
Reach 1 was assessed as moderate, with patches of gravel for spawning, pockets behind
boulders for rearing, and boulder cover for overwintering, but fish production capability
may be limited by lack of flow. The lower portion of the Reach is a moderate gradient(~5%) while the upper half is steep (10-11%) and represents a series of cascades (when
streamflow is present) which form a difficult section for upstream fish passage.
Reach 2 is a 270 m straight channelized section downstream of the Westside Road
culvert that continues upstream of the 60 m long culvert for an additional 360 m. The
dominant bed material is cobble, with gravel subdominant. Boulders are the main cover
type. Fish habitat quality was assessed as moderate with good spawning potential in
frequent patches of gravel but rearing and overwintering was limited due to the lack of
deep pools and low water velocity, respectively. However, rearing and overwintering
habitat quality was low in the channelized section downstream of Westside Road, where
there was minimal cover and the only deep pool was located at the culvert outlet. The 30
cm drop located at the outlet of the Westside Road culvert would only limit passage of
juvenile fish or smaller. The downstream half of the culvert has a gradient of about 1%(suitable for fish passage) but the upper half of the culvert has a gradient of about 5%
which could represent a potential velocity barrier to fish.
Reach 3 is a confined, boulder and bedrock section with a 30 m high falls observed 80 m
upstream from the lower reach boundary that is a complete barrier to upstream fish
passage. It is a steep canyon reach that extends for 700 m and has a gradient of ~ 23%.
There are 1-2 m falls and chutes throughout Reach 3. Downstream end surveys indicate
the dominant bed material is boulder, with cobble subdominant; however, bedrock is likely
prevalent throughout the reach. The main cover type is boulder. Fish habitat quality was
assessed as moderate, with good rearing and holding habitat in deep pools formed in the
cascade-pool channel, but only fair spawning potential in pockets of gravel. Overwintering
habitat was limited due to the lack of low velocity refuges.
Reach 4 extends for about 500 m upstream to the confluence of a major tributary thatenters from the west. Reach 4 is lower gradient (5-6%) but still a confined reach located
above the canyon section of Beattie Creek. The dominant bed material is cobble, with
boulder subdominant. Boulder is the main cover type, with large woody debris
subdominant. Fish habitat quality was assessed as good, with frequent gravel patches
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 109 of 162Page 109 of 162Page 109 of 162Page 109 of 162
7/27/2019 Moses Crreek IPP Project
24/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 19 April 2013
and good pocket pools and boulder cover but there was a lack of low velocity areas for
overwintering.
Reach 5 extends 1380 m up to and 3.7 km beyond the proposed Beattie Creek intake.The reach gradient varies between 5-20%. The 109 m section surveyed downstream of
the intake has cobble as its dominant bed material, with gravel subdominant. Upstream of
the intake, bedrock and boulder are prominent. Overhanging vegetation is the main cover
type, with large woody debris subdominant. Fish habitat quality was relatively poor due to
isolated gravel patches, lack of pools, and shallow depth of the reach. Historic mapping
shows that Reach 5 of Beattie Creek formerly flowed into Moses Creek from a point near
the proposed intake, and evidence of this former flow pattern includes map contours that
show Beattie Creek flowing across the slope instead of down the slope. There appears to
be a low berm where the stream was diverted to its present course. The area where the
stream formerly flowed was used as a borrow area for construction of the Revelstoke
Dam.
Barriers
An approximately 14 m set of falls located about 150 m from the mouth of Moses Creek
followed by a bedrock chute directly downstream represent a total barrier to upstream fish
migration. In addition, numerous other fish barriers were identified upstream of the falls
which include a steep section immediately downstream of Pond #1 (Reach 2.1) and
numerous falls and bedrock chutes within the diversion reach of Moses Creek. Fish
access to Moses Creek is downstream of the diversion reach and limited to Reach 1.
Approximately 970 m upstream from the mouth of Beattie Creek is a set of bedrock falls
and chutes with an estimated height of 30 m. No fish were detected upstream of this
barrier. In August 2012, there was no flow in the first 150 m of Beattie Creek, forming a
total barrier to fish migration. Approximately 100 m upstream of Beattie Creeks
confluence with the Columbia River there is a very steep boulder section that, whenstream flow is present, forms a section with very difficult upstream fish passage.
However, a high abundance of rainbow trout fry were observed upstream of this boulder
section and suggests that rainbow trout have been successful in migrating to spawn
upstream of this challenging section.
2.1.2 Fish Presence
Fish sampling efforts in 2010, 2011, and 2012 did not detect any fish in Moses Creek
upstream of the proposed tailrace location where flows will be returned to Moses Creek. It
is concluded that there were no fish present in the diversion section of Moses Creek and
upstream of the proposed intake. The only fish bearing reach of Moses Creek was 1 km
downstream of the tailrace. The nearest fish bearing reach to the Beattie Creek intake
was 2.5 km downstream, at which point the effect of the proposed flow diversion ismitigated by inflow from two major tributaries.
Fish sampling was conducted by minnow trapping and/or electrofishing at a total of 11
sites on Moses Creek and four sites on Beattie Creek during 2010-2012 sampling efforts.
Minnow traps were baited and set overnight for a period of between 18-48 hours.
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 110 of 162Page 110 of 162Page 110 of 162Page 110 of 162
7/27/2019 Moses Crreek IPP Project
25/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 20 April 2013
Electrofishing was not conducted on Beattie Creek in the area downstream of the fish
barrier at the upstream end of Reach 3 due to the observation of salmonids.
Rainbow trout fry and juveniles or small resident adults were captured downstream of thefirst barrier (30 m falls) on Beattie Creek at least 2.5 km downstream from the diversion
point and represent the only fish observed during the field sampling studies conducted
over the 2010, 2011, and 2012 sampling efforts. This may suggest that adult rainbow
trout from the Columbia River may be using the lower section of Beattie Creek to spawn.
No resident fish are known to be present in or within more than 1 km downstream of the
diversion reach. However, Kokanee, bull trout, and rainbow trout have been observed
utilizing the artificial channel at the mouth of Moses Creek (B. Gadbois, pers. Comm..),
and this stream section is likely used for spawning and limited stream-rearing by other
species such as sculpin and mountain whitefish present in Upper Arrow Lake and the
Columbia River.
Based on sampling in three years using two methods, no fish were present in thediversion reach of Moses Creek. Fish were only identified near the mouth of Beattie
Creek where flow effects will be minimal.
2.1.3 Invertebrate Data
As described in Appendix D, a benthic invertebrate sampling program, which was
conducted based on Beatty et al., (2006) was initiated on Moses and Beattie Creek in
2010. A benthic sampling program was selected because it was felt that the benthic
invertebrate population as a whole rather than just the drift was a better indicator of
stream health in the non-fish bearing diversion reach of the Project. Invertebrate samples
were collected at four sites as shown in Figure 5 of Appendix D. Benthic invertebrates
were collected in triplicate downstream of the powerhouse location, near the downstream
end of the diversion reach, upstream of the proposed Moses Creek intake, anddownstream of the Beattie tributary intake. In 2011, a benthic invertebrate sample was
collected in triplicate approximately 650 m upstream of the proposed Moses Creek intake.
Benthic samples were collected using a standard Surber Sampler (0.3 m x 0.3 m frame)
with 243 mesh. Following collection, samples were analysed by Sandpiper Biological
Consulting Ltd (Victoria, BC) for identification and enumeration of invertebrates. Samples
were processed by size-sorting and damp dry weights were measured.
Results of the benthic invertebrate sampling were highly variable. However, benthic
invertebrate sampling showed a consistent number of Orders were present (12 at four
sites and 13 at the other). The sample site upstream of the proposed Moses Creek intake
was consistently the highest on all measures (total mass/ total organisms/ total EPT
organisms) except for total number of orders.
An additional year of benthic drift data will be collected in 2013 to establish a baseline
invertebrate record. Post-construction benthic drift monitoring will be carried out for
benthic drift twice annually for five years, as recommended by Lewis et al., 2012.
More details regarding the benthic drift sampling program are provided in Appendix D.
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 111 of 162Page 111 of 162Page 111 of 162Page 111 of 162
7/27/2019 Moses Crreek IPP Project
26/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 21 April 2013
2.1.4 Instream Flows
The Moses Creek Streamflow Monitoring Report has developed a stage-discharge curvefor Moses Creek to determine flows at the intake and is provided as Appendix E. Depth
and velocity were collected at a total of ten and five representative channel cross-sections
within the diversion reach of Moses Creek and Beattie Creek, respectively. The channel
cross-section data were used to estimate the depth, velocity, and wetted perimeter that
result during average monthly flows and minimal flow releases (Appendix D; Appendix 5).
The pre and post-Project flows at the Moses Creek intake, assuming a 5% IFR, are
summarized in Figure 9 of Appendix B. Hydraulic calculations were carried out using
channel cross-sectional data to estimate changes in wetted perimeter that would result
from flow reduction in the diversion reach. Among 10 Moses Creek cross-sections, the
maximum predicted reductions in wetted perimeter ranged from 17% to 70%. Similar
percentage reductions in water depth and velocity are also predicted to occur in the
diversion reach. Among five Beattie Creek cross-sections, the maximum predictedreductions in wetted perimeter ranged from 8% to 78%, with the change less than 8% in
the fish bearing reach. Full results of the hydraulic calculations are provided in Appendix
D (Appendix 5).
Given that the Projects diversion reach does not support fish, an instream flow release
(IFR) of 0.039 m3/s (10% of mean annual flow) at the Moses Creek diversion weir is
proposed with the potential for implementing a lower minimum flow release based on
provincial regulatory approval of an Adaptive Management Plan. A summary of monthly
flows in Moses Creek for the Moses Creek Hydro Project under the minimum flow release
of 5% MAD (0.020 m3/s) is provided in Appendix B, Figure 9.
A minimum flow release of 0.0070 m3/s (10% of mean annual flow) at the Beattie Creek
diversion weir is proposed with the potential for implementing a lower minimum flow
release based on provincial regulatory approval of an Adaptive Management Plan. Theinstream flow release on Beattie Creek will be supplemented by local inflow from two main
tributaries that enter the Beattie Creek main stem approximately 760 m downstream of the
intake.
The rationale behind a 5% MAF IFR and how it will maintain fish habitat is discussed in
detail in Section 4 of Appendix D. Please note that at this time the Proponent is
proposing a 10% MAF IFR with the potential for reducing the IFR to 5% MAF as
previously specified.
2.2 WILDLIFE AND HABITAT
A Terrestrial Ecology and Wildlife Impact Assessment was prepared by Robert G. DEon
Consulting Ltd. of Nelson, BC. The main objectives of this report were to describe theterrestrial ecological conditions within the proposed Project footprint, identify and assess
potential Project-related impacts on Valued Ecosystem Components (VECs) and
terrestrial species at risk (particularly vascular plants), and provide recommendations and
direction on Project activities as well as feasible mitigation strategies.
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 112 of 162Page 112 of 162Page 112 of 162Page 112 of 162
7/27/2019 Moses Crreek IPP Project
27/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 22 April 2013
The following VECs were chosen for assessment:
1. Old growth forest
2. Species at risk
3. Habitat loss
4. Ungulate winter range
5. Riparian Habitat
A summary of the reports findings is presented in this section and the full report is
attached as Appendix F.
2.2.1 Terrestrial Habitat and Vegetation
The entire Project area, including all components, is located within the Wells Gray Wet
Cool Interior Cedar-Hemlock biogeoclimatic subzone variant, in the Interior Wet Belt of
British Columbia. Sites in and around the Project area can be generally characterized as
regenerating to young mixed coniferous forests, with scattered mature to old remnant
patches, typical of the post-harvest biogeoclimatic subzone variant. The area has been
heavily developed for commercial forest harvesting in past decades (~20-40 yrs ago), and
consequently represents a matrix of regenerating clear cuts accessible by a network of
existing gravel logging roads. Areas in and around the proposed powerhouse site have
also been heavily disturbed by construction activities related to the Revelstoke Dam,
which was completed in 1984. A summary of the general ecological conditions at select
locations within the proposed Project area can be found in Table 4 of Appendix F.
The proposed Project footprint does not overlap any provincially designated Old Growth
Management Areas (OGMA). The Project area is largely characterized as a post-harvest
regenerating area with an abundance of age-class 1 and 2 forest. Remnant patches of
older forest occur at two locations within the general Project area; 1) on the north side of
Moses Creek in the vicinity of the proposed Moses Creek intake site and 2) a strip of older
trees along Moses Creek in the vicinity of the penstock crossing. Access to the Moses
Creek intake site will be from the south side of the creek through an existing post-harvest
area, and therefore disruption to the stand of older trees on the north side of the creek will
be minimal (only what is required to install the weir). In the case of the penstock travelling
through the remnant strip of old trees near the penstock creek crossing, disturbance to the
stand will be minimized since only temporary access will be required for this section of the
penstock. The Proponent will endeavor to minimize disturbance and avoid tree clearing to
the greatest extent possible in this area. Overall Project effects on old growth forests
during construction and operation are expected to be not significant.
During field surveys, no obvious high-value site-specific habitat features (e.g. stick nests,
dens, licks, hibernacula) were observed within the Project footprint. No rare or
endangered plants were discovered during targeted rate-plant surveys.
Riparian and Wetland Habitat
There are no wetlands within the Project footprint.
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 113 of 162Page 113 of 162Page 113 of 162Page 113 of 162
7/27/2019 Moses Crreek IPP Project
28/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 23 April 2013
The only area with potentially significant riparian habitat values is the area surrounding the
powerhouse site where Moses Creek intersects with a pond that appears to have formed
as a result of the damming effect of the paved road forming its southern perimeter.However, there is no direct overlap between the Project footprint and the pond margin or
its intersection with Moses Creek. Additionally, a minimum setback of 30 m from the pond
margin, which is consistent with provincial riparian management guidelines, will be used
during detailed Project design and subsequent construction.
The Moses Creek intake and Beattie Creek diversion intake sites are largely within post-
harvest second-growth areas, which lack extensive stream-side riparian vegetation. The
penstock crossing of Moses Creek will involve minimal construction and consist of
concrete footings placed a minimum of 1 m from the high water perimeter of the creek.
Construction of the powerhouse site will occur using a minimum 5 m setback from the high
water perimeter of Moses Creek, and will therefore avoid moist soils and other sensitive
areas.
The Project will affect some riparian area by flooding at the headponds and construction of
the intakes, penstock crossing, and powerhouse. A very approximate area estimate is
1,700 m2, which will be refined when detailed design is complete (i.e. after permitting).
Field verification of the affected areas will be conducted following construction.
Compensation of the field-verified area will consist of riparian planting at a 2:1 ratio.
On this basis, the Projects potential impact on riparian and wetland habitat has been
assessed as low.
Species at Risk
A BC Conservation Data Centre database search identified three vascular plant species
with known occurrences within 10 km of the Project; Nahanni oak fern, slender spike rush
and western moonwort. An additional 34 vascular plant species at risk occurring within theInterior Cedar Hemlock biogeoclimatic subzones within the Columbia Forest District were
assessed for their potential occurrence or concern within the Project area. A list of these
plants is included in Appendix 2 of Appendix F. Of these, 10 species were considered
possible to occur in the Project area: dainty moonwort, mountain moonwort, least
moonwort, tender sedge, Sutherlands larkspur, crested wood fern, small-fruited
willowherb, Treleases hybrid willowherb, Joe-pye weed, and lance-leaved figwort.
None of the thirteen species mentioned above with possible occurrences in the Project
area were observed during field work and none were discovered in a targeted rare plant
survey. Considering the inherent rarity of these species, especially in the types of habitats
identified within the footprint of the proposed Project, the overall risk of damage or loss as
a result of vegetation clearing for Project construction is low.
Ungulate Winter Range
The Project footprint does not overlap with any designated Ungulate Winter Range (UWR)
for either caribou or mule deer. Additionally, radiotelemetry data for caribou and moose
show no use of the Project areas. This data along with UWR mapping correspond with the
AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.AgendaItem#9f.
Front Counter BC - Moses Creek
Hydro Electric Project Page 114 of 162Page 114 of 162Page 114 of 162Page 114 of 162
7/27/2019 Moses Crreek IPP Project
29/50
Moses Creek Hydroelectric Project Moses Creek Power IncDevelopment Plan
Sigma Engineering Ltd. 24 April 2013
current habitat suitability of the Moses Creek and Beattie Creek study areas, which
represent a largely regenerating post-harvest area with little to no older forests. The
Project has consequently been assessed as having virtually no effect on UWR values.
2.2.2 Wildlife
In a broad assessment of all potential species at risk within the Columbia Forest District a
total of 25 terrestrial vertebrate species were assessed for their potential to occur in
propo