Moolarben Coal Complex Open Cut Optimisation Modification IPC Briefing 27 March 2019

Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

Moolarben Coal Complex

Open Cut Optimisation Modification

IPC Briefing

27 March 2019

Page 2: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

▪ Moolarben Coal Complex

▪ Modification Description

▪ Environmental Assessment

2

Overview

Page 3: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

3

Moolarben Coal Complex – Currently Approved

Stage 1 (PA 05_0117):

▪ Approved September 2007

▪ Construction 2009, operations 2010

▪ Open Cuts (OC1, OC2 & OC3)

▪ Underground (UG4)

▪ CHPP and rail loop

Stage 2 (PA 08_0135):

▪ Approved January 2015

▪ Open Cut (OC4)

▪ Underground (UG1 and UG2)

▪ ROM coal to Stage 1 CHPP

Current Operations

▪ OC1, OC2, OC4, UG1, CHPP

Approved Moolarben Coal Complex

UG4

CHPP

OC1

OC2

OC3

UG1

OC4

UG2

Stage 1 Stage 2

Page 4: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

▪ Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined)

▪ Realignment of OC3 infrastructure

▪ Revised OC3/OC2 pit limits

▪ OC2 to OC4 internal road

▪ Bypass conveyor

▪ Water treatment facility, revised EPL release point and release conditions

▪ Final landuse in OC2 and OC3 (proposed change to native vegetation from agricultural land)

▪ Other minor infrastructure changes within extent of approved disturbance

▪ No change to the approved underground mining operations

▪ No change to final voids

4

Modification Description – Overview Modification General Arrangement

Relocated EPL

Release Point

Bypass

Conveyor

OC2 to OC4

Internal Road

Realigned OC3

Infrastructure

and Pit Limits

Extension to

OC2 Pit Limit

Water Treatment

Facility

Proposed Modifications:

Page 5: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

The Modification would not change the currently approved:

5

Modification Description – Overview

▪ Underground operations (layouts and production limits)

▪ OC1 or OC4 pit limits

▪ Hours of operation

▪ Blasting frequency limits

▪ Site access

▪ Method of reject disposal

▪ Peak workforce

▪ Final voids

Page 6: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

Increased Open Cut Production Limits

6

Modification Description

▪ Stage 1 Project Approval open cut coal production limit:

• Currently 8 Mtpa combined total from OC1, OC2 and OC3

• The Modification seeks to increase this from 8 to 10 Mtpa

▪ Stage 2 Project Approval open cut coal production limit:

• Currently 12 Mtpa from OC4

• The Modification seeks to increase this from 12 to 16 Mtpa

▪ Combined Stage 1 and Stage 2 open cut production is currently limited to 13 Mtpa in total:

• The Modification seeks to increase annual open cut production limits from 13 to 16 Mtpa(Stages 1 and 2 combined)

▪ Associated production limit changes:

• Increased combined annual open cut and underground ROM coal production limits from 21 to 24 Mtpa

• Increased annual coal processing (washing limit) from 13 to 16 Mtpa

• Increased annual product coal limit from 18 to 22 Mtpa

Page 7: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

▪ Realigned OC2 to OC3 haul road

▪ Relinquishment of approved disturbanceand OC3 out of pit emplacement

▪ Relocated OC3 MIA

▪ OC3 revised pit limits

▪ OC2 revised pit limit

7

Modification Description

Modification Disturbance

Area

“Relinquishment”

Area

Extension to

OC2 Pit Limit

Approved Haul

Road and MIAModified Haul

Road

Modified MIA

OC3 Pit Limit

Extensions

Approved OC3

Emplacement

OC3 Pit Limit

Reductions

OC3 Infrastructure and OC2/OC3 Pit Limits

Page 8: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

▪ Unsealed internal road would be constructed between OC2 and OC4

▪ Not used to haul coal or overburden

▪ Used for the occasional transfer of mining equipment only

▪ Internal road would generally follow an existing track

Bypass Conveyor

▪ Bypass conveyor would be constructed to enable open cut ROM coal to bypass the CHPP

▪ Bypass would create additional marketing opportunities and reduce the production of rejects

▪ Associated minor infrastructure upgrades within approved disturbance limits

8

Modification Description

Internal RoadBypass Conveyor,

Realigned Haul Road

and Bypass Coal

Stockpile Area

Internal Road

Page 9: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

▪ OC2 is approved to be rehabilitated to a combination of agricultural land and native vegetation

▪ OC3 is approved to be rehabilitated to agricultural land

▪ This Modification proposes an increased proportion of OC2 and OC3 to be rehabilitated to native vegetation

▪ Revised rehabilitation outcomes would improve biodiversity and connectivity in the final landform

9

Modification Description

Final Land Use

Page 10: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

▪ Requirement identified through ongoing review of site water balance

▪ Avoids build up of mine water on-site in the long-term

▪ Ensures controlled releases in accordance with EPL water quality release limits

▪ Brine generated by the water treatment process managed in the first instance by diluting with stored water and used in dust suppression

▪ Residual brine permanently stored within the UG4 void (following UG4 mining)

10

Modification Description

Water Treatment Facility

Brine

Dams

Water Treatment

Plant

Raw Water

Dam

Page 11: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

▪ EPL 12932 discharge point (EPL ID1) relocated from current location (into Bora Creek) to environmentally superior location at the confluence of Bora Creek and the Goulburn River

▪ Discharge water would be piped from the water treatment facility to the relocated discharge point

▪ Proposed discharge point avoids potential erosion from controlled releases along Bora Creek

11

Modification Description

Relocation of EPL Release Point

Revised EPL

Release Point

Approved EPL Release

Point (EPL ID1)

Indicative

Pipeline

Goulburn River

Diversion at the

confluence with

Bora Creek

Bora Creek

(looking

downstream) -

avoided

Water Treatment

Facility

Page 12: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

12

Environmental Assessment – Surface Water

Controlled Releases

▪ MCO’s existing EPL (12932) authorises:

• Up to 10 ML/day controlled release

• Salinity limit of 900 µS/cm (maximum)

▪ Modification proposes:

• Relocation of existing EPL authorised release point (EPL ID1) to an environmentally superior location

• Increased controlled release volume during certain periods of the mine life

▪ Collaborative development of proposed release limits with the EPA and DPE:

• Reduction in existing EPL 12932 salinity limit from 900 µS/cm to 685 µS/cm

▪ Revised limit of 685 µS/cm developed in consultation with EPA and DPE per ANZECC process

• No change to existing EPL 12932 volume limit for the majority of the mine life:

▪ No change to existing 10 ML/day limit up to the commencement of mining operations in UG4 and following completion of mining operations in UG4

▪ Up to 15 ML/day during mining operations in UG4

▪ Greater than 15 ML/day during prolonged wet periods, with the approval of EPA

Page 13: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

13

Environmental Assessment – Biodiversity

Disturbance and Offsets

▪ Modification Proposes:

• Disturbance of ~80 ha in the Modification Area (comprising 39 ha native vegetation and 41 ha non-native vegetation)

• “Relinquishment” of 34.5 ha of vegetation previously approved for clearing (including 15 ha of native vegetation)

• Additional land-based offset (known as “Gilgal”)

▪ OEH has reviewed and accepted the offset calculations as presented in the Biodiversity Assessment Review

▪ The DPE Assessment Report considers the proposed impacts to be acceptable, subject to the identified avoidance, mitigation and offsetting measures

▪ MCO would secure the Gilgal biodiversity offset area in accordance with the draft modified conditions of approval

▪ “Gilgal” is owned by MCO and abuts nature reserve Existing Biodiversity

Offset AreaGilgal

National

Park

Page 14: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

14

Environmental Assessment – Air Quality

Air Quality Assessment

▪ The Modification proposes increased annual production limits and minor increases in disturbance areas

▪ The Air Quality Assessment for the Modification predicted no exceedances of relevant PM10, PM2.5, total suspended particulates or dust deposition criteria at any privately-owned receptors due to emissions from the Moolarben Coal Complex incorporating the Modification

▪ The DPE Assessment Report considered that predicted air quality would be similar to the existing approved levels and can be effectively managed under the existing conditions of approval

▪ MCO would continue the operation of real-time and proactive air quality management system

▪ MCO would install a real-time PM2.5 monitor as part of its Air Quality Monitoring Program

Page 15: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

15

Environmental Assessment – Noise

Noise Assessment

▪ The proposed optimisations to open cut operations (including production increase to 16Mtpa ROM) can be achieved with no material change to the existing mining fleet

▪ The Noise Assessment for the Modification predicts:

• The Moolarben Coal Complex would continue to comply with the existing noise limits at all private residences

• Rail noise along the Sandy Hollow-Gulgong Railway would continue to comply with the relevant criteria of the Rail Infrastructure Noise Guideline

▪ The DPE Assessment Report considers that predicted noise levels would be similar to the approved levels and can be effectively managed under the existing conditions of approval

▪ MCO would continue the operation of its real-time and proactive noise management system

Page 16: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

16

DPE Assessment Report

Conclusions

▪ The DPE Assessment Report made the following conclusions:

• Any additional impacts from the Modification would be minor, including cumulative impacts

• Controlled releases would be as per ANZECC and would be at the currently approved release rate for the majority of the mine life

• Additional vegetation clearing would be relatively small and compensated by a significant land based offset (and other approved mechanisms)

• Amenity impacts (i.e. noise and air quality) can be managed under the existing conditions of approval

▪ DPE has proposed draft modified conditions of Project Approvals (05_0117 and 08_0135) with input from other agencies

▪ MCO accepts DPE’s draft modified conditions

Page 17: Moolarben Coal Complex Open Cut Optimisation Modification...OC2 OC3 UG1 OC4 UG2 Stage 1 Stage 2 Increased open cut production limits from 13 to 16 Mtpa (Stages 1 and 2 combined) Realignment

Presentation end