    sr.no Date task in charge status1 4/8/2014 prepare a ppt based on thesis sai rajesh compelete

    2 edit the ppt sai rajesh complete

    3 7-Aug mail d ppt sai rajesh complete

    8-Aug download opensource sw

  • 8/11/2019 Mohammad Fayyaz Task Report

    2/12

    task completion date5/8/2014

    8-Aug

    8-Aug

  • 8/11/2019 Mohammad Fayyaz Task Report

    3/12

    remarksfinal revision and mail it

    add architecture, video,align data properly,information of tools used

    he will come bak on it

    dwnloaded KNIME, BIRT, Rapidminer so far, started off with rapidminer

  • 8/11/2019 Mohammad Fayyaz Task Report

    4/12

    Work Sheet For the month of August 2014

    Week Date Task Estimated Time

    1st Week 4-Aug Understanding the "Simplify GDC_TC_Diagnostics_Tool" --

    --

    ----

    1st Week 5-Aug Study of Codes 1 Hr

    1 Hr

    1 Hr

    1 Hr

    1 Hr

    1 Hr

    1 Hr

    1st Week 6-Aug Preparing List & Study of Perl Scripts --

    1 Week

    1 Hr

    --

    1st Week 7-Aug Preparing List & Study of Perl Scripts --

    1 Hr

    --

    1st Week 8-Aug Preparing List & Study of Perl Scripts --

    ----

    2nd Week 11-Aug Preparing list only for TC 10.1 1 Hr

    --

    2nd Week 12-Aug Submitting the List for TC 10.1 Release 1 Day

    2nd Week 13-Aug Completing the List for all versions of TC 8 Hrs

    1 Hr

    --

    4 Hrs

    2nd Week 14-Aug

    Submitting list, Changing Sheet name & adding Display name

    column to it --

    1 Hr

    1 Hr

    1 Hr

  • 8/11/2019 Mohammad Fayyaz Task Report

    5/12

    2 Hr

    3rd Week 18-Aug Discussing the Task List & Started working on it. 1 Hr

    --

    3 Days

    3rd Week 19-Aug Working on ITK & Java Code 1 Hr--

    3rd Week 20-Aug Preparing the Test Environment 1 Hr

    1 Hr

    1 Hr

    3rd Week 21-Aug Fixing bugs in combined program for batch utility. --

    1 Hr

    1 Hr

    Failure

    3rd Week 22-Aug Error solving batch utility program 1 Hr

    1 Hr

    1 Hr

    Failure

    4th Week 25-Aug Fixing bugs in combined batch utility program 1 Hr

    1Hr

    --

    4th Week 26-Aug Combining and Testing of Perl Scripts as per TC Version 1 Hr

    1Hr

    --

    4th Week 27-Aug VC Project Build up 30 Min

    1Hr

    30 Min

    --

    4th Week 28-Aug Combining and Testing of Perl Scripts as per TC Version 1 Hr

    1Hr

    --

    5th Week 1-Sep Working On Perl Scripts --

    1 Hr

    1Hr

  • 8/11/2019 Mohammad Fayyaz Task Report

    6/12

    --

    1 Hr

    1 hr

  • 8/11/2019 Mohammad Fayyaz Task Report

    7/12

    Time taken

    Till 14:00 Hrs

    3 Hrs

    30 Mins30 Mins

    2 Hrs

    2 Hrs

    30 Mins

    1 Hr

    30 Mins

    1 Hr

    1 Hr

    30 Mins

    5 Hrs

    1 Hr

    1 Hr

    5 Hrs

    1 Hrs

    1 Hr

    4 Hrs

    2 Hrs1 Hr

    30 Min

    1 Hr

    6 Hr

    Whole Day

    5 Hrs

    30 Min

    30 Min

    2 Hrs

    3 Hrs

    2 Hrs

    1 Hr

    1 Hr

  • 8/11/2019 Mohammad Fayyaz Task Report

    8/12

    1 Hr

    2 Hrs

    1 Hr

    5 Hrs

    2 Hrs6 Hrs

    2 Hrs

    4 Hrs

    2 Hrs

    2 Hrs

    2 Hrs

    4 Hrs

    2 Hrs

    2 Hr

    4 Hrs

    2 Hrs

    1 Hr

    5 Hrs

    2 Hrs

    1 Hr

    1 Hr

    4 Hrs

    1 Hr

    1 Hr

    1 Hr

    1 Hr

    4 Hrs

    30 Min

    1 Hr

    1 Hr

    5 Hrs

    3 Hrs

    30 Min

    1 Hr

  • 8/11/2019 Mohammad Fayyaz Task Report

    9/12

    1 Hr

    30 Min

    2 Hrs

  • 8/11/2019 Mohammad Fayyaz Task Report

    10/12

    Office hours on an Avgerageof 8 hrs/day

    remarks

    1) Was waiting to get a machine in C V Raman Hall

    2) Reading doucuments and bat files. Understanding the concepts of GDC_TC_Diagnostic_tool

    3) Downloading & Installing necessary tools on machine4) Browsing the shared folder 'Simplify Diagnostics' and understanding their use.

    1) Details study of gdc_ada_report_tc_diagnostics_main.cxx file

    2) Details study of gdc_ada_report_cemli_mainPre83_with_license.cxx file

    3) Understanding the execution of same and study of its output.

    4) Detail study of RAC code (GdcTcDiagnosticsReport.java)

    5) Detail study of LCData Parser.cpp

    6) Searched books on Perl Script and Tools to execute a perl programs

    7) Clearing doubts from cxx program file (CPP terminologies)

    1) Tried simple programs in Perl scripting

    2) Preparing the list of Obsolete and Deprecated functions of Teamcenter according to their versionss

    3) Reading Chapter 1 of Perl Script book by Simon Cousinzs

    4) Trying handson perl programs

    1) Preparing the list of Obsolete and Deprecated functions of Teamcenter according to their versionss

    3) Reading Chapter 2 of Perl Script book by Simon Cousinzs

    4) Trying handson perl programs

    1) Preparing the list of Obsolete and Deprecated functions of Teamcenter according to their versionss

    2) Trying handson perl programs3) Helping collegous in C programming concepts

    1) Started with Perl 3rd Chapt.

    2) Meeting with Manish Agarwal & Devraj.

    3) Started preparing a complete list of all deprecated & obsolete functions of only Teamcenter 10.1

    1) Finilizing the list only for 10.1 and submitting it to Manish.

    1) Started with the pending work of preparing list for all TC versions

    2) Formatting the perl code for different arrays based on TC Versions.

    3) Helping Collegous in C Programming

    4) Checking the final list with ITK html help

    1) Cross checking of list such that no API is left

    2) Formatting it to standard and making it a single file

    3) Modifying code to add Sheet name as :Overall Data Model"

    4) Modifying code to add new column to have "Display name of Templates"

  • 8/11/2019 Mohammad Fayyaz Task Report

    11/12

    5) Comparing the pre 8.3 cxx file and post 8.3 cxx file

    1) Noted down all the doubts to be cleared from Manish

    2) Discussion with Manish and taking note of all comments & suggestions.

    3) Started working on Code.

    1) Modifying Code to behave as per the version selected from Jcombobox list.2) Combining the ITK code to act for both pre and post 8.3 versions of TC.

    1) Discussion with Milind Mulay, Anik Triphati, Hasrsha Posani and Abdul Nasar.

    2) Getting VM for TC 9.1

    3) Getting License and preparing fully furnished TC Environment for testing

    1) Combining the ITK code to act for both pre and post 8.3 versions of TC.

    2) Comipile & Linking Script and modifying accordingly.

    3) Comipile & Linking of ITK Code and modifying accordingly.

    No success in ITK Code [ Still have errors to resolve ]

    1) Solved compilation errors Code

    2) Solved Linking errors in ITK Code

    3) Generated exe but its not working displaying an error

    No success in ITK Code [ EXE not working ]

    1) Searched over net to solve error.

    2) Discussion with Sumit on error solving

    3) Tried all the tricks suggested by Sumit; Still no success.

    1) Modifying Perl script TC Version as input.

    2) Testing output of Perl Script. Strpcmp Exe Error.

    3) Discussion with Sumit on error solving. Project creation in VC

    4) Exe builds successfully from cmd prompt but still not working displaying an eror at runtime.

    1) Creating a VC Project with all Settings.

    2) Solving Compilation Error

    3) Reporting Saurabh Sen Gupta

    3) Solving Linking Errors

    4) Exe builds successfully but still not working dsiplaying an eror at runtime.

    1) Discussion With Subhashish.

    2) Modifying Perl Script accordingly. Failure.

    3) Discovering Source folder.

    4) Working on Perl.

    1) Perl Script modification.

    2) Discussion With Manish A

    3) Modifying Perl Script accordingly. All Success.

  • 8/11/2019 Mohammad Fayyaz Task Report

    12/12

    4) Searching Help on Perl Excel Parsing

    5) Working on packages required for parsin

    6) Running Sample code and Modifying Original Perl Code for excel output.