84
M/s Tamilnadu Cements Corporation Ltd. Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 1 MODIFICATIONS TO THE APPROVED MINING PLAN ALONGWITH PROGRESSIVE MINE CLOSURE PLAN OF ANANDAVADI LIMESTONE MINES G.O.Ms.No.624 Dated 23.09.1998 EXTENT-110.68.5 HA. SENDURAI TALUK & ARIYALUR DISTRICT (UNDER RULE 12 OF MCDR 1988) Introduction M/s Tamilnadu Cement Corporation Ltd was incorporated in the year 1962 with the Register of the companies, Chennai, Tamilnadu. Copy of Certificate of incorporation is enclosed as Annexure No - 1 M/s. Tamilnadu Cement Corporation Limited belong to Government of Tamilnadu enterprise is having two cement units, one at Alangulam and another at Ariyalur. The installed capacity of the Ariyalur cement unit is 5 lakh tonnes per annum. It is a modern dry process plant. TANCEM has expanded the capacity of Ariyalur Works from 5 lakh tones per annum to 15 lakh tones per annum by installing the Green field plant and proposed to commission the unit on August 2018. Details of Mining leases held by Tamilnadu Cement Corporation – Ariyalur Unit G.O.No &Date Area in Hectares Area in Acres Lease validity Period up to Status Name of the Villages Kallankurichi – Periyanagalur limestone mines. G.O.Ms.344 dated 10.03.2080 240.61.0 594.32 26.04.2001 Deemed renewal Under rule 24 (A)6 of MCR 1960 Kallankurichi, Khairulabad Ameenabad. G.O.Ms.456 dated 16.05.1985 194.16.5 479.91 12.11.2005 Periyanagalur Kallankurichi Khairulabad Ameenabad. G.O.Ms.469 dated 21.05.1985 66.11.0 163.29 12.11.2005 Kurumbanchavadi Khairulabad Ameenabad Total 501.02.0 1237.52 G.O.No &Date Area in Hectares Area in Acres Status Name of the Villages G.O.Ms.624 dated 23.09.1998 110.68.5 273.39 Live Anandavadi

MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 1

MODIFICATIONS TO THE APPROVED MINING PLAN

ALONGWITH PROGRESSIVE MINE CLOSURE PLAN OF

ANANDAVADI LIMESTONE MINES

G.O.Ms.No.624 Dated 23.09.1998

EXTENT-110.68.5 HA.

SENDURAI TALUK & ARIYALUR DISTRICT

(UNDER RULE 12 OF MCDR 1988)

Introduction

M/s Tamilnadu Cement Corporation Ltd was incorporated in the year 1962 with the Register of the

companies, Chennai, Tamilnadu. Copy of Certificate of incorporation is enclosed as Annexure No - 1

M/s. Tamilnadu Cement Corporation Limited belong to Government of Tamilnadu enterprise is having

two cement units, one at Alangulam and another at Ariyalur. The installed capacity of the Ariyalur

cement unit is 5 lakh tonnes per annum. It is a modern dry process plant. TANCEM has expanded the

capacity of Ariyalur Works from 5 lakh tones per annum to 15 lakh tones per annum by installing the

Green field plant and proposed to commission the unit on August 2018.

Details of Mining leases held by Tamilnadu Cement Corporation – Ariyalur Unit

G.O.No &Date Area in

Hectares Area in Acres

Lease validity

Period up to

Status Name of the

Villages

Kallankurichi – Periyanagalur limestone mines.

G.O.Ms.344 dated 10.03.2080 240.61.0 594.32 26.04.2001

Deemed renewal

Under rule 24 (A)6 of MCR 1960

Kallankurichi, Khairulabad Ameenabad.

G.O.Ms.456 dated 16.05.1985

194.16.5 479.91 12.11.2005

Periyanagalur Kallankurichi Khairulabad Ameenabad.

G.O.Ms.469 dated 21.05.1985 66.11.0 163.29 12.11.2005

Kurumbanchavadi Khairulabad Ameenabad

Total 501.02.0 1237.52

G.O.No &Date Area in Hectares

Area in Acres

Status Name of the Villages

G.O.Ms.624 dated 23.09.1998 110.68.5 273.39

Live Anandavadi

Page 2: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 2

History of Mining Lease:

Details of Mining lease:

The mining lease was initially granted for a period of 20 years and approved vide letter no. G.O.

(MS) No. 624 dated 23.09.1998, for the period of 30 years.

Subsequently the lease deed was executed on 16.03.2000, and got registered on 13.07.2001

and the period is valid up to 16.03.2030,

As per the section 8 A (5) of new MMDR amendment act 2015, the validity of this lease is

deemed to be extended till 16.03.2050.

The copy of G.O. and Mining Lease deed are enclosed as Annexure-2 & Annexure-3

respectively.

DETAILS OF MINE PLAN /SCHEME OF MINING:

S. No. Mining plan /

Scheme of Mining

Under MCR or

MCDR

Approval letter No. Date

01 Mining Plan Under Rule 22 (4) of MCR 1960

TN/PBR/Lst-MP/916-SZ dated 18.10.2000.

02 Scheme of Mining Under Rule 12 (3) of MCDR 1988

TN/PBR/Lst-MS/396-SZ dated 06.10.2006

03 Scheme of Mining Under Rule 12 of MCDR 1988

TN/ALM/LST/MS-662-MDS, Dated, 27.04.2012.

04 Scheme of Mining Under Rule 12 of MCDR 1988

TN/ALM/LST/MS-1300-MDS, Dated, 25.01.2016.

Refer Annexure No – 4 for approval letter of approved Scheme of Mining.

Environmental Clearance from MOEF:

Environmental clearance has been obtained from Ministry of Environment & Forest vide their

letter No –No.J-11015/15/99-IA II(M) dated 22.11.1999 over an extent of 110.68.5 Ha for

production capacity of 0.26 Million TPA of limestone at village Anandavadi , Sendurai Taluk ,

Ariyalurl District, Tamilnadu State.

The copy of MoEF clearance letter is enclosed as Annexure No-5.

Reason for Modification

The applicants already carried out the detailed exploration during the year 1984.

New expansion plant capacity of 1.0 Million ton per annum and expected to commission

in the month of august 2018.

The applicant company has proposed to enhance the clinker production from 5.0LTPA to

15.0LTPA. Hence to meet required limestone the applicant company has proposed to enhance

Page 3: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 3

the limestone production from 2.60 Lakhs tons to 15.0 Lakhs tons per annum from 2018-19 to

2020-2021.

The Scheme of Mining for G.O.Ms.No. 624, dated 23.09.1998 over an extent of 110.68.5 Ha has

been approved by Indian Bureau of Mines under Rule 12(3)of MCDR 1988 for the period 2016-17

to 2020-2021 vide approval No.TN/ALM/LST/MS- 1300 -MDS, dated, 25.01.2016

Hence, the present Modification to the Approved Mining Plan is prepared for the period 2018-19 to

2020-21 Under Rule 17(3) of MCR-2016.

(B.Gangatharan)

Qualified Person

Page 4: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 4

MINING LEASE DETAIL SUNDER TANCEM ARIYALUR UNIT

S.N

G.O.No & date

Total Area (in Hec)

Location Minerals Working/

Non Working Status Details

1. 344/ dated 10-03-1980

146.45.0 61.38.0 32.78.5

240.61.5

Kallankurichi Ameenabad Kairulabad

Limestone Non Working Lease expired on 26-04-2001. Renewal application submitted

Lr.No and date of approval of Mining Scheme(For G.O344) TN/PBR/MS/LST-1257-SZ Dt.19-01-2001.

2. 456/dated 16-05-1985

31.70.0 3.86.0

71.96.5 86.77.0

194.16.5

Periyanagalur Ameenabad Kairulabad

Kallankurichi

Limestone

Non Working Lease expired on 12-11-2005. Renewal application submitted

Lr.No and date of approval of Mining Scheme (For G.O.456) TN/PBR/LST-MS-86-SZ Dt.29-03-2001

3. 469/ dated 21-05-1985

10.16.0 8.49.0

32.47.0 14.98.0 66.11.0

Ariyalur Ameenabad Kallankurichi Kairulabad

Limestone

Non Working Lease expired on 12-11-2005. Renewal application submitted

Lr.No and date of approval of Mining Scheme(For G.O. 469) TN/PBR/LST-MS-86-SZ Dt.29-03-2001

4.

624/dated 23-09-1998

110.68.5

Anandavadi

Limestone

Working

Lease executed on 16.03.2000. Valid for50 years.

Lr.No and date of approval of Mine Plan (For G.O.624) TN/TCR/MP/LST-916-SZ Dt.18-10-2000

ALANGULAM UNIT SNo

G.O.No & date Total Area (in Hec)

Location Minerals Working/ Non

Working

Status Details

1.

871/MMD2 dated 20-08-1990

233.99.5 176.56.0 9.69.5 ------------ 420.25.0

Lakshmipuram Gopalapuram

Vadakarai

Limestone Non - Working

(Renewal application submitted)

Lr.No and date of approval of Mine Plan TN/TNL/MP/L.St-1122-SZ. Dt 10-02-2004

2.

595/Ind dated 03-04-1972

179.19.5 1.63.5 ------------ 180.83.0

Alangulam Lakshmipuram

Limestone Non - Working

(Renewal application submitted)

Lr.No and date of approval of Mine Scheme TN/VDN/L.St/MS-74/SZ dated 13-03-2005

3.

427/Ind dated 19-03-1980

113.50.0 57.62.5 3.80.5 76.20.0 11.51.0 6.16.0 ------------ 268.80.0

Alangulam Pernaickenpatti

Duraisamypuram Edrikottai

Narayanapuram Lakshmipuram

Limestone Non - Working

(Renewal application submitted)

Lr.No and date of approval of Mine Scheme TN/VDN/L.St/MS-74/SZ dated 13-03-2005

4.

729/Ind dated 19-07-1980

24.32.5 Pandapalli Limestone Non - Working

(Renewal application submitted)

Lr.No and date of approval of Mine Scheme TN/TNL/L.St/MS-360/SZ dt 17-05-2006

5.

G.O. 3 D.No 107/Ind dt 11-07-1997

4.91.5 2.64.0 --------- 7.55.5 ----------

Pandapalli Thenmalai

Limestone Non - Working

(Renewal application submitted)

Lr.No and date of approval of Mine Scheme TN/TNL/MP/L.St- 149/SZ dated 18-05-2006.

Page 5: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 5

VIRUDHACHALAM UNIT 1.

G.O.M.S. No 409/Ind dt 12-10-1993

6.61.5 Panikuppam Clay Non Working

(Renewal application submitted)

Lr.No and date of approval of Mining Plan (For G.O.2127) TN/SA/FC-15-SZ Dt.25-02-1991.

2.

G.O.M.S. No .198/Ind dt 26-02-1986

12.30.0 Theranipalayam Clay Non Working

(Renewal application submitted)

Lr.No and date of approval of Mining Scheme (For G.O.198) TN/TCR/FC/MS-108-MDS dt 04-07-2001.

Page 6: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 6

1.0 GENERAL

a) a) Name of applicant /lessee/Rule 45 registration no. IBM/7446/2011

Registered Office : M/s. Tamilnadu Cements Corporation Ltd

(A Govt. of Tamilnadu Undertaking) 735, Anna Salai,

L.L.A Building, IInd

Floor, Chennai-600 002, Tamilnadu. Telephone No. : 044 28525461 044 28525471

044 28525230 044 28591735

Telegraph : TANCEM. Fax : 044 28523991 E-mail : [email protected]

Address of authorized : Mrs. D.Sabita, I.A.S, Principal Secretary/Managing Signatory Director/Nominated Owner

Registered Office : M/s. Tamilnadu Cements Corporation Ltd

(A Govt. of Tamilnadu Undertaking) Ariyalur Cement Factory, Ariyalur-621 729.

Ariyalur District, Tamilnadu. Telephone No. : 04329 228531 Telegraph : TANCEM. Fax : 04329 228776 E-mail : [email protected]

Copy of photo identity card of leassee with permanent address proof & certified true copy of the Board

resolution is enclosed as annexure-4. List of Board of Directors is enclosed as annexure-5

b) Status of applicant/lessee

The lessee is a Government of tamilnadu Enterprises, engaged in mining and manufacture of

cement.

The company manufactures Portland cement and other various blended cements.

For the purpose of Acts and Rules connected with mining operations Smt Sbita, IAS, has been

nominated as the authorized signatory for all the mines coming under M/s Tamilnadu Cements

Corporation Ltd.

Board of Directors of the company is enclosed as Annexure No- 6.

Page 7: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 7

A copy of the resolution of Board of Directors nominating the owner is enclosed vide Annexure No-

7.

Photo Id of the authorized signatory is also enclosed as Annexure No – 8.

c) Mineral(s) which is / are included in the prospecting license (For Fresh grant)

N.A

d) Mineral(s) which is / are included in the lease deed

LIMESTONE

e) Mineral(s) which is the applicant /lessee intends to mine:

LIMESTONE

f) Name of Recognized Person under employed under clause (c) of Sub rule (1) of rule 42 of

MCDR, 1988 (Applicable for Scheme of Mining only):

Name : Shri.B.Gangatharan Address : M/s Sai Geo Survey Consultant, 10 A,Palayam Bazaar, Woraiyur , Trichy- 620003. Phone : 0431- 2765071 Fax : Nil

Email : [email protected]

Mobile No. : 94431-01165, 9788842209

The copy of Qualified Person Education certificate and having of experience in this field is enclosed

as annexure-9.

Page 8: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 8

2.0 LOCATION AND ACCESSIBILITY

a) Lease Details (Existing Mine)

Name of mine : ANANDAVADI LIMESTONE MINES

The mining lease area falls in the Survey of India Topo-sheet no. 58 M/4 and bounded by following co-

ordinates

Date of grant of lease : 23.09.1998 Period/Expiry : 30 years from 13.07.2001 to 12.07.2031

Period/Expiry Date : This lease period is valid for 30 years and the expiry

Date is 16.03.2030 and lease period will be extended up

To 31.03.2050 as per Section 8 A (5) of Mines and

Minerals (Development and Regulations) Amendment

Act 2015.

Owner : M/s Tamilnadu Cement Corporation Ltd.

Name of Lessee M/s. Tamilnadu Cements Corporation Ltd Registered Office : (A Govt. of Tamilnadu Undertaking)

735, Anna Salai, L.L.A Building, IInd Floor,

Chennai-600 002, Tamilnadu. Telephone No. : 044 28525461 044 28525471

044 28525230 044 28591735

Telegraph : TAMCEM. Fax : 044 28523991 E-mail : [email protected]

Address of the Works Tamilnadu Cement Corporation Limited,

Ariyalur Cement Works,

Ariyalur – 621 729.

Ariyalur District,

Tamilnadu.

Phone 04329 222131, 222132, 222068

Fax 04329 – 222467

Grams TANCEM – ARIYALUR

E-Mail [email protected]

Details of lease area with location map (mine)

Latitude Longitude

11011’12” – 11

011’27”

79010’54” – 79

011’56”

Page 9: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 9

Forest Non-forest

Area (ha) Area (ha)

Forest (specify)

NIL

(i) waste land, (ii) grazing land,

(iii) Agriculture land, (iv)others(specify

Dry Land

110.68.5

The details of the S.F.Nos.are shown on authenticated lease sketch and is enclosed as

Plate No – 2. Further details of the Survey Nos are enclosed as Annexure No – 2 & 3

Total lease area : 110.68.5 Hectares

District : Ariyalur & State : Tamilnadu

Taluka : Sendurai Village: Anandavadi

Whether the area falls under Coastal Regulation Zone (CRZ)? If yes, details thereof.

No

Existence of public road/railway line, if any nearby and approximate distance .

Road

The mining lease area is situated 10 Km from Ariyalur on Ariyalur – Sendurai - Jayankondam road

Railway Line

Ariyalur railway station is located at a distance of 12 kms from this mine site.

Toposheet No. with latitude & longitude of all corner boundary point/pillar

The area of Mining lease falls in Survey of India Toposheet No.58 M/4.

The mining lease area falls in the

Survey of India Topo-sheet no.

58 M/4 and bounded by following

co-ordinates

Villages Longitude Lattitude

Anandavadi 11011’12” –

11011’27”

79010’54” –

79011’56”

Details of Latitude and Longitude of the three permanent ground control points situated outside lease

area.

Page 10: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 10

Photograph of the lease area and Ground Control Stations – Annexure -11.

c) Attach a general location map showing area and access routes. It is preferred that the area

be marked on a Survey of India topographical map or a cadastral map or forest map as the

case may be. However, if none of these are available, the area may be shown on an

administrative map.

Plate No.:1

3.0 DETAILS OF APPROVED MINING PLAN / SCHEME OF MINING (if any) 3.1 Date and reference of earlier approved MP/SOM.

S.No. Mining plan /

Scheme of Mining

Under MCR or

MCDR

Approval letter No. Date

01 Mining Plan Under Rule 22 (4) of MCR 1960

TN/PBR/Lst-MP/916-SZ dated 18.10.2000.

02 Scheme of Mining Under Rule 12 (3) of MCDR 1988

TN/PBR/Lst-MS/396-SZ dated 06.10.2006

03 Scheme of Mining Under Rule 12 of MCDR 1988

TN/ALM/LST/MS-662-MDS, Dated, 27.04.2012.

04 Scheme of Mining Under Rule 12 of MCDR 1988

TN/ALM/LST/MS-1300-MDS, Dated, 25.01.2016.

Copy of IBM approval letter is enclosed as annexure no.4. 3.2 Details of last modifications if any (for the previous approved period) of approved MP/SOM, indicating date of approval, reason for modification

NIL

Ground Control Point: Lat – Long Bearing

GCP - 1 Transformer N 11°11’22.5” E79°10’47.9” 419m NW from GCS -1

Elevation : 101m

GCP - 2 Burial Ground N 11°11’12.7” E 79°10’53.3” 98m W from GCS - 1

Elevation : 97m

GCP –3 Variattan Koil N 11°11’15.7” E 79°10’54.0” 137m NW from GCS -1

Elevation : 97m

Ground Control Station

GCS –1 Boundary Pillar Near Burial Ground

N 11°11’11.8” E 79°10’56.3”

Elevation : 95m

GCS –2 Boundary Pillar Near Anandavadi to Irumbulikurichi

Road

N 11°11’26.8” E 79°10’54.9”

Elevation : 99m

Page 11: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 11

3.3 Give review of earlier approved proposal (if any) in respect of exploration, excavation, reclamation etc.

3.3.1(a):Exploration:

Director of Geology & Mining along with TANCEM carried out systematic exploration of the

area in the year 1984-85. By exploratory core & Noncore boreholes were drilled covering

almost the entire strike length. The drill holes were drilled regular grid pattern.

The geological mapping was done on the topographic plan, which is the base map, prepared

on a scale of 1: 4000, with a contour interval of 1 meter. .

Diamond drill holes and Wagon drill holes were placed at closer intervals (i.e.) 400 M and

200M respectively. The bore holes within the lease area were drilled in grid pattern running

NE-SW direction. Geological cross sections were prepared, on a scale of 1: 2000, along -the

dip direction, joining the diamond drill holes drilled along the grid line (Please refer Plate-3 &

3a).

The details of drilling, sampling and other exploration done in the area of GO MS 624 are given

below.

S. No Details of Exploration Quantity of

Work Grid interval Remarks

01 Diamond drilling (a) No. of holes completed 27 400 Mtrs Location of

BH /WDH are shown in the Geological Plan-Plate-3

(b) Metreage 845.75 02 Wagon drilling (a) No. of holes completed 19 400 Mtrs

(b) Metreage 206

03 Total No. of samples collected

850

The exploration of the area reveals the presence of limestone and associated litho units of

varying thickness throughout the area.

During the scheme period 2016-17 to 2020-2021, the exploration proposals has been made in

the regular grid and will be put in between the earlier bore holes to know the deposit and

further enhancement of reserves. As per the discussions had the company officials, at the

present period of scheme of mining the company has proposed the total of 20 nos. coring bore

holes from the year 2017-18 to 2020-21 at the rate of 5 bore holes in every proposal period as

per the UNFC guidelines.

Page 12: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 12

Sl.No. Year of Proposals

No. of Bore hole Type Proposed depth of BH

Achieved Depth of BH

1. 2017-18 PBH-1 to PBH-5 Coring 125.0m Nil

Total 5 Nos. 125.0m

Reason for deviation:

Due to employment / agitation made by land given people and local villagers to the company,

there was no production during the year 2016-17 and at the end of year 2017-18 in the month

of February second 2018; the company has started mining operation.

3.3.1(b): Mine Development:

Year

Proposed development

(in tons)

Achieved development (in tons)

Top soil

Sand stone/Waste

Top soil

Sand stone/Waste

2016-17 Nil 130000 Nil Nil

2017-18 (03.02.2018 to 31.03.2018)

Nil 130000 Nil 13900

Total Nil 260000 Nil

During scheme mining period, the production was commenced in the year 2016-17 to tune of

260000 tons only. There is no production from this lease due to local social problem by

previous land owners and demanding their permanent employment with the company. Due to

employment / agitation made by land given people and local villagers to the company, there

was no production during the year 2016-17 and at the end of year 2017-18 in the month of

February second 2018; the company has started mining operation.

3.3.1C: Exploitation of Mineral:

Page 13: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 13

In the previous approved scheme of mining, the production was projected as 2.60 lakh Tons

per annum for five year period from the year 2016-17 to 2020-21.

Year

Proposal Production

(in tons)

Achieved Production

(in tons)

2016-17 260000 Nil

2017-18(03.02.2018 to 31.03.2018)

260000 58514.56

Total 520000

It may be seen from above that production could not be achieved as per the targeted

production of the previous scheme period year 2016-17 and 2017-18, are due to the following

reasons

---Cost of Mining & Transportation

---Administrative issues of M/s. TANCEM due to the local social problem by previous land

owners and demanding their permanent employment with the company. Due to employment /

agitation made by land given people and local villagers to the company, there was no

production during the year 2016-17 and at the end of year 2017-18 in the month of February

second 2018; the company has started mining operation.

.

Actual grade of limestone found during production is as follows.

Blast /Bench

Sample SiO2 Al2O3 Fe2O3 CaO

I Limestone 10.15 2.97 1.20 44.58 II Limestone 16.4 3.24 2.28 34.30

3.3.1(d): Method of mining:

The method of working is opencast (A category fully mechanized) adopting non-conventional

method by deploying rock breaker for primary and secondary breaking eliminating drilling and

blasting thus adopting eco-friendly mining.

Primary and Secondary Breaking: Mega Rock Breaker of 150 TPH capacity will be deployed

for primary breaking and dilution of oversize boulders which will totally eliminate drilling and

blasting.

Page 14: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 14

Loading and hauling: Excavator will be used for loading the material on to the tippers

(hauling units) which will be used for transportation of mineral from the mines to crusher at

plant site and for handling the overburden / reject.

Rock breaker will be used for primary breaking wherever required and also for reduction of

oversize boulders instead of secondary blasting.

BENCH PARAMETERS:

Bench height - 6m

Bench Width - 8m

Ultimate Pit Slope - 450

Depth of Mining - 21 m maximum up to 80 RL.

Present pit dimension is as follows.

Name of the Pit Length (M) Width (M) Depth (M) RL(M)

North pit 180 230 12 85

South pit 100 80 12 85

No Deviation in method of Mining Method

The thickness of topsoil is meager and will be stacked for the purpose of afforestation. The

benches shall be sloped at an angle of 45o individual bench in limestone shall also be of 6 m

height and the width of the benches shall always be maintained more than the height.

Present pit dimension : 180M (Length) x 230 M (Width) x 12 (Depth)

RL 97.0 M to 85.0 M

Bench parameters. For North pit:

Bench parameters.

No. Bench Top R.L Bottom R.L Height L x W

I st Bench Topsoil & sandstone

100 M 94 M 6.0 M 210 M x 145 M

II nd Bench 92 M 88 M 6.0 M 100M x 60M

Page 15: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 15

For South pit:

3.3.1(e): Drilling and Blasting:

No drilling and blasting is envisaged during the modifications to the approved mining plan

during 2018-19 to 2020-21.

3.3.1(f): Disposal of waste:

The nature of top soil is Black cotton soil and has been removed and dumped all along the

mine lease boundary for the Afforestation purposes. No sub-grade ore or mineral rejects is

generated during the scheme period.

During the year 2016-17 to year 2017-18 of the plan period, no top soil was proposed. The

entire topsoil in the mineable area of the lease area will be removed and will be utilised

straight away for afforestation/ green belt purpose.

The mineral reject generated during mining will also be stacked along the western boundary in

a separate dump yard.

Dimensions of the waste dump are given below :

Dump Length (m) Width (m) Height (m)

Waste Dump-1 100 60 18

Waste Dump-1 80 40 12

3.3.1(g): Environment Management:

There is no production from this lease due to local social problem by previous land owners and

demanding their permanent employment with the company.

During scheme of mining period, impact of mining activities on the environment was very less.

The mining operation was started in the year 03.02.2018; subsequently the production was

commenced in the year 2018-19 to the tune of 260000 tons only.

During the previous scheme period of mining afforestation proposals were made, however it

No. Bench Top R.L Bottom R.L Height L x W

I st Bench Topsoil & sandstone

100 M 94 M 6.0 M 100 M x 60M

II nd Bench 92 M 88 M 6.0 M 80M x 60M

Page 16: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 16

could not be achieved since the mining operation was commenced in the year 2018-19, due to

the local issues.

Proposed Afforestation programme for five years period:

Year No. of

Saplings

Area

Covered

(Ha)

Survival

rate

Places of

plantation

Species

Achieved

2016-17 1500 1.00.0 80% Safety zone

barrier

Eucalyptus &

Caurina

Nil

2017-18 1500 1.00.0 80% -Do- -Do- Nil

Total 3000 2.00.0

Review of Environmental proposals and the status of compilation at the end of the Mining plan

period.

SL

NO.

ITEM

PROPOSALS AS PER APPROVED

SCHEME OF MINING

POSITION AT THE END OF

SCHEME OF MINING PERIOD

1 2 3 4

1.

Top soil storage

Total quantity of top soil proposed to be

handled is Nil. The existing dumping

Proposals were made in the non

mineral bearing adjoining to the working

pit and in eastern side of the lease area.

Store it separately for future use in

spreading afforestation areas

Since production was not met that

target. The top soil handled Nil.

Topsoil is stored separately on the

designated place so far. There is no

deviation from the proposal

2.

Land reclamation and

rehabilitation

No proposals for reclamation and

rehabilitation in the approved scheme of

mining are given, as limestone would

not be exhausted.

The mining is not yet reached the

basement and the production

achieved during the period is very

meager 0.58 Lakh tonnes.

3.

Waste dump

management

Proposals were to store topsoil & waste

sandstone separately and places were

earmarked for the purpose.

Topsoil, and waste rock sandstone is

being stacked at the designated

places separately. No deviation from

approved scheme of mining

4.

Afforestation programme

with precautions for

survival and protection

of plantation

In the approved mining scheme 7500No

of trees are proposed to cover an area

of 5.0 Ha.

Till date eucalyptus & casurina is

planted about 80.0 Ha having tie up

with TNPL.

5.

Quality of air.

Periodical environmental monitoring of

air quality to be conducted.

Periodical environmental monitoring

of air quality conducted as per

IBM/MoEF norms quarterly

The latest environmental monitoring

Page 17: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 17

reports is enclosed as annexure-2

6.

Quality of water.

Periodical environmental monitoring of

Water quality to be conducted.

Periodical environmental monitoring

of water quality conducted as per

IBM/MoEF norms quarterly

7.

Noise level

Periodical environmental monitoring of

noise level to be conducted.

Periodical environmental monitoring

of noise level conducted as per

IBM/MoEF norms quarterly

8.

Ground vibration.

Periodical environmental monitoring of

Noise level to be conducted.

Periodical environmental monitoring

of Noise level conducted as per

IBM/MoEF norms quarterly

9.

Treatment of mine water

including surface and

ground water.

There was no proposal to treat ground

or surface water.

Monitoring and study was made and

there will be no toxic effluent that will

be discharged from the mine hence,

no treatment of ground and surface

water.

10.

Re-circulation of treated

water.

No proposal in the approved scheme of

mining for re-circulation of treated water

as there was any need to treat water in

the mine.

No re-circulation of treated water

done. This was not applicable.

3.4 : Status of compliance of violations pointed out by IBM.

Indian Bureau of Mines has pointed out following violations under MCDR’ 1988. Compliance

position thereof is also discussed below.

Description of Violation Rule

No.

Compliance Position Date of

Compliance

The scheme of mining was approved vide letter

no TN/TCR/LST/ Ms/ -396-SZ dated

06.10.2006 for G.O.No. 624.

The five year proposals given in the scheme of

mining has been expired on 31.04.2010. As

such the scheme of mining has fallen due for

submission. The same has not been submitted

for approval to the Regional controller of

Mines, Indian Bureau of Mines, Chennai so far

Rule

2(3)

The applicant company requested

time for submission delay vides their

letter. The present scheme of mining

is prepared in view of compliance of

the above violation.

02.04.2010

Page 18: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 18

3.5 Indicate and give details of any suspension /closure/ prohibitory order issued by any

Government agency under any rule or Court of law .

NIL

3.6 In case the MP/SOM is submitted under rules 9 and 10 of the MCDR’88 or under rule 22(6) of the

MCR’1960 for approval of modification, specify reason and justification for modification under

these rules.

Since the applicant company has proposed to enhance the clinker production, to meet the required

limestone the applicant company, the company has proposed to start the expansion plant capacity from

0.5 million tons to 1.50 million tons per annum in the month of August 2018, the company ought to

enhance the limestone production from 2.60 lakhs tons to 15.0 lakh tons per annum for the period from

2018-19 to 2020-21. And hence the present modification to the approved mining plan is prepared under

17(3) of MCR 2016.

PART – A

1.0 GEOLOGY AND EXPLORATION:

a) Briefly describe the topography, drainage pattern, vegetation, climate, and rainfall data of the

area applied/mining lease area.

Topography

The Anandavadi Limestone mines is located in Anandavadi village, Sendurai Taluk, Ariyalur District.

The Anandavadi mine is located 10 Km North East of Ariyalur town. The mines can be reached by a

good motorable road on Ariyalur – Sendurai – Jayankondam road and forms part of the survey of India

Toposheet No.58M/4. The area has a slope towards south east.

Climate & Rainfall:

In this area the maximum temperature recorded during summer season is 400C and the minimum

temperature during the winter season is 250 C. The area is generally dry during summer and is

receiving a maximum of 900 cm of rainfall mostly between October and December during the north-

east monsoon. Water table in this area is far below 20 meters during monsoonal period and 25 metres

in summer. The main crops of the area are cashew and chillies.

Page 19: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 19

b) Brief descriptions of Regional Geology with reference to location of lease area.

Regional Geology:

The lease area forms part of the Trichy-cretaceous formations, have been studied in detail during the

past several decades in view of their Geological and paleontological interest.

The following geological sequence can be made out in this area.

Geological Age

Formations with Geological period

Lithology

Recent and Quaternary

- Alluviam, Kankar, Laterite, etc.

Palaeocene Niniyur (Danian Varigated clays with nodules of limestone and marl with occasional boulers of flint and chert.

Cretaceous

Ariyalur (Maestrichtian)

Upper White friable sandstone and purple clays

Lower

Loose conglomerates and yellow fossil ferrous limestone, marls and hard limestone clays and sandstone.

Trichinopoly (Turonian to Senonian)

Calcareous, gritty sandstone, shell limestone and conglomerate sandstone

The general trend of the rock formation is NNE – SSW with a low dip of 2 to 5° towards East.

Local / Mine Geology

The local geological sequence.

Arenaceous Limestone and Sandstone

Shell Limestone-1

Arenaceous Line stone and sandstone

Shell Limestone-11

Conglomerate bed.

Arenaceous Limestone and Sandstone

Green Siltstone

Clays

Page 20: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 20

. c) Detailed description of geology of the lease area such as shape and size of the mineral/ore

deposit, disposition various litho-units indicating structural features if any etc. (Applicable for

Mining Plan for grant & renewal and not for Scheme of Mining/Modifications in the approved

mining plan/scheme of Mining).

Not applicable

d) (i) Name of prospecting /exploration agency : (i) Address: Department of Geology and Mining and TANCEM Govt. of Tamilnadu,

Guindy, Chennai -32

(ii) E mail : [email protected] and phone no. : 044-28525461 Fax :044-28523991

(iii) Address : M/s. Tamilnadu Cements Corporation Ltd, Anna Salai, Chennai.

e) Details of prospecting/exploration already carried out:

Details of Exploration work:

Director of Geology & Mining along with TANCEM carried out systematic exploration of the

area in the year 1984-85. By exploratory core & Non core boreholes were drilled covering

almost the entire strike length. The drill holes were drilled regular grid pattern.

Diamond drill holes and Wagon drill holes were placed at closer intervals (i.e.) 400 M and

200M respectively. The bore holes within the lease area were drilled in grid pattern running

NE-SW direction. Geological cross sections were prepared, on a scale of 1: 2000, along -the

dip direction, joining the diamond drill holes drilled along the grid line.

The details of drilling, sampling and other exploration done in the area of GO MS 624 are given

below.

Sl.No. Details of Exploration Quantity of

Work Grid interval Remarks

01 Diamond drilling (a) No. of holes completed 27 400 Mtrs Location of

BH /WDH are shown in the Geological Plan-Plate-3

(b) Metreage 845.75 02 Wagon drilling (a) No. of holes completed 19 400 Mtrs

(b) Metreage 206

03 Total No. of samples collected

850

Page 21: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 21

i) Number of pits and trenches indicating dimensions, spacing etc along and across the strike/ foliation

with reference to geological plan.

Details of samples analysis indicating type of sample (surface/sub-surface from pits/trenches/borehole

etc) complete chemical analysis for entire strata for all radicals may be undertaken for selected

samples from a NABL accredited Laboratory or Government laboratory or equivalent.

Refer litho log Annexure -6a.

IV) Expenditure incurred in various prospecting operations.

Rs.15 Lakhs.

Exploration Proposals:

During the scheme period 2016-17 to 2020-2021, the exploration proposals has been made in the

regular grid and will be put in between the earlier bore holes to know the deposit and further

enhancement of reserves. As per the discussions had the company officials, at the present period of

modifications to the approved mining plan, the company has proposed the total of 15 nos. coring bore

holes from the year 2018-19 to 2020-21 at the rate of 5 bore holes in every proposal period as per the

UNFC guidelines.

Sl.No. Year of Proposals

No. of Bore hole Type Proposed depth of BH

2. 2018-19 PBH-6 to PBH-10 Coring 125.0m

1. 2019-20 PBH-11 to PBH-15 Coring 125.0m

1. 2020-21 PBH-16 to PBH-20 Coring 125.0m

Total 15 Nos. 375.0m

f) The surface plan of the lease area may be prepared on a scale of 1: 1000 or 1: 2000 with

contour interval of maximum of 10 m depending upon the topography and size of the area duly

marked by grid lines showing all features indicated under Rule 28(1)(a) of MCDR 1988.

Plate No.4

g) For preparation of geological plan, surface plan prepared on a scale of 1: 1000 or 1: 2000

scale specified under para 1.0 (f) of Part A of the format may be taken as the base plan. The

details of exploration already carried out along with supporting data for existence of mineral,

locations proposed exploration, various litho units along with structural features,

mineralized/ore zone with grade variation if any may be marked on the geological plan along

with other features indicated under Rule 28 (1)(b) of MCDR 1988.

Geological Plan Plate No.3:

Page 22: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 22

h) Geological sections may be prepared on natural scale of geological plan at suitable interval

across the lease area from boundary to boundary.

Geological Cross Section: Plate No.3A

i) Broadly indicate the future programme of exploration with due justification(duly marking on

Geological plan year wise location in different colours) taking into consideration the future

tentative excavation programme planned in next five years as in table below: -

The Anandavadi limestone deposit can be classified as a simple deposit as given in the CRI(NCBM)

guide norms for prospecting, exploration, reserve estimation and technological assessment of cement

grade limestone deposits

The exploration of the area reveals presence of limestone and associated litho units of varying

thickness throughout the area.

Considering the available data and the observation of the exposed mine pits by the other companies

all around this lease. The additional bore hole has been proposed during this scheme period as given

in the page no.22.

j) Reserves and Resources as per UNFC with respect to the threshold value notified by IBM may be

furnished in a tabular form as given below: (Area explored under different level of exploration may be

marked on the geological plan and UNFC code for area considered for different categories of

reserve/resources estimation may also be marked on geological cross sections).

Submit a feasibility/pre-feasibility study report along with financial analysis for economic viability

of the deposit as specified under the UNFC field guidelines may be incorporated.

Feasibility report Annexure -12.

k) Furnish detailed calculation of reserves/resources section wise (When the mine is fully

mechanized and deposit is of complex nature with variation of size , shape of mineralized

zones, grade due to intrusion within ore zone etc, an attempt may be made to estimate

reserves/resources by slice plan method). In case of deposits where underground mining is

proposed, reserve/resources may be estimated by level plan method, as applicable, as per the

proposed mining parameters.

As per previous Mining Plan Reserve are as follows.

As the deposit is technically feasible and economically viable for mining the total proved reserves

Page 23: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 23

come under UNFC- 111 & 122. After deleting reserve locked up (221) in the safety barrier zone

and bench formation,

Reserves as on 31.03.2016.

ABSTRACT

UNFC Code Grade Total Qty

(in mill. Tons)

111

High Grade 14903343 14.90

Low Grade 3725836 3.73

221

High Grade 2574149 2.57

Low grade 643537 0.64

Total 21846865 21.84

Depletion of Reserves are as follows:

Year Limestone

(in MT) 2016-17 Nil 2017-18

(From03.02.2018 to 31.03.2018)

58514.56

Total 58514.56

After depletion reserves as on April 2018 are as follows.

ABSTRACT

UNFC Code Grade Total Qty

(in mill. Tons)

111 Cement Grade

14848343 14.85

18.58

3725836 3.73

221

Cement Grade

2574149 2.57

3.21

643537 0.64

Total 21846865 21.84 21.79

Page 24: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 24

l) Mineral Reserves/Resources:

Mineral Resources: (Mineral resources may be estimated purely based on level of exploration, with

reference to the threshold value of minerals declared by IBM)

Level of Exploration Resources in million tons Grade

G1 - Detailed exploration 18.580 Cement

G2 - General Exploration 3.210 Cement

G3 - Prospecting

G4 - Reconnassance

Resources and Reserves within the lease may be arrived after applying results feasibility/pre-

feasibility study and economic evaluation of deposit based on various factors such as:

a) Mining method, Recovery factor, mining losses, processing loss etc.

b) Cut off grade, Ultimate pit depth proposed.

Cut-off grade

The Mining Lease area is located in the state of Tamil nadu the threshold value and cut off grade of

limestone as per circular 3/2010 of IBM (Indian Bureau of Mines) is given below:

Limiting Values CaO% MgO% SiO2

Threshold values 35.00 4.00 18.00

Cut Off Grades 35.00 1.00 18.00

Keeping in view the exploitation of limestone for the manufacture of cement, the process parameters

of LSF (Lime Saturation Factor), SM (Silica Modulus) and AM (Alumina Modulus) should also be

satisfied from the material being fed to the plant. The expected range of the as above parameters is

as follows:

Parameters Range

LSF 0-85 – 1.10

SM 2.20 – 2.80

AM 1.20 – 2.50

From the grade of limestone given above it can be observed that the limestone from this leasehold

satisfied all the requisite parameters required for manufacture of cement.

Grade control:

Page 25: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 25

As per the norms prescribed by NCBM (National council for Cement and Building Materials) the broad

chemical specifications of cement grade ROM limestone are as follows:

CaO%

Acceptable range for manufacture of OPC 44-52

Limiting values taking into consideration Min. 40

type of cements, scope of beneficiation and blending

Thus, limestone with at least 44% CaO is required in the ROM for manufacture of cement and

limestone above 40% CaO can be used if beneficiation is provided or higher grade limestone is

available which can be blended to upgrade the lower grade limestone upto 44% CaO. The quality of

available high grade ore in Anandavadi limestone is of 47.5% CaO content and having less Fe2 O3 &

MgO, and this can be blended well with the Kallankurichi deposit limestone materials which are having

high Fe2 O3 and less SiO2. The present blending technique and raw mix design is given below.

During the enhancement of limestone production and Cement capacity of plant, the blending

technique and raw mix design will be modified according to the available grade of limestone and

limestone from new mining leases in future.

Grade of Limestone:

The limestone is yellow color fine to medium grain bedded in nature and fossiliferous. The marl is pale

yellow and powder in nature overlained by red soil. The purity of limestone is about 70 to 80% TCO3

with little MgCO3. The SiO2 content is ranging from 10-18% in the entire mining area.

The variation in the chemical behavior of this limestone & marl is summarized below

SiO2 (%) Al2O3 (%) Fe2O3 (%) CaO (%) SO3 (%)

Red soil 40.0- 43.0 10.0-13.0 13.0-15.0

18.0 -

20.0 10.0-13.0

Kankar /

Blendable

Limestone

10.0-18.0 3.0-4.0 3.0-4.5 43.0-

45.0

0.3 – 0.5

Marl 25.0-35.0 5.0-7.0 5.5-8.0 35.0-

37.0

0.4-0.6

Page 26: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 26

Raw Mix Design:

Name of the mine % of

Contribution Sio2 Fe2O3 CaO MgO

G.O.No.344 25 9.4 4.0 46.3 0.6

G.O.No.456 1 6.5 3.6 48.0 0.5

G.O.No.469 15 16.4 4.6 40.3 1.0

G.O.No.624 60 11.80 0.75 47.5 1.50

Clay (Additive) 04 59.5 7.0 5.0 1.5

c) Mineral/ ore blocked dues to benches, barriers, pillars, road, railway, river, nala, reservoir, electric

line and other statutory barriers etc, under forest, sanctuaries etc. where necessary permissions are

not available.

As the deposit is technically pre feasible and economically viable for mining the total proved reserves

come under UNFC- 111 & 122. After deleting reserve locked up (221) in the safety barrier zone and

bench formation,

GEOLOGICAL AXIS:

Rock type

Average Thick ness (in m)

Physical characteristics

Chemistry

SiO2 Al2O3 Fe2O3 CaO LSF

Top Soil Red soil

0.0-0.5 Loose, friable & absorbent

42.76 12.94 14.19 18.78 13.00

OB 5.0-8.0 Soft yellowish clay soil

27.50 8.77 9.55 12.50 6.25

Kankar / Bedded Limestone 10.0-15.0

Yellow medium grained fossiliferous

10.18 2.97 3.20 44.58 130.80

Marl Loose pale yellow friable

21.08 6.33 5.85 35.42 52.12

Bottom Conglomeratic - sandstone

Below 15.0 Greyish yellow coarse grained

41.61 15.81 19.96 14.84 10.00

Page 27: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 27

Refer Feasibility Report: Annexure -12

FEASIBILITY AXIS:-

Refer Feasibility Report: Annexure -12

ECONOMIC AXES:

Refer Feasibility Report: Annexure -12

Based on the above and the Economic axis has been fulfilled all the aspects of UNFC

classification, the limestone reserves of the Anandavadi limestone deposit can be categorized

“111“.

Refer Feasibility Report Annexure:12

Insitu Reserves of Anandavadi Limestone Mine (As on 01.04.2018):

UNFC Code Quantity in million tons

Grade

A. Total Mineral Reserve 111 18.58 Cement Proved Mineral Reserve 121 and 122 Probable mineral Reserve B. Total Remaining Resources Feasibility mineral Resource 211 Prefeasibility mineral resource Measured mineral resource

221 and 222, 331

3.21 Cement

Indicated mineral resource 332 Inferred mineral resource 333 Reconnaissance mineral resource 334 Total Reserves + Resources 21.79 Cement

Page 28: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 28

2.0 MINING

A. OPEN CAST MINING: a) Briefly describe the existing as well as proposed method for excavation with all design

parameters indicating on plans /sections.

The method of working is opencast mining considering various technical parameters like

surface topography, continuation of limestone deposit, quality variations, geo-technical

aspects, required rate of production etc.,

The method of working is opencast fully mechanized adopting non-conventional method

by developing rock breaker for primary and secondary breaking eliminating drilling and

blasting thus adopting eco-friendly mining.

It is proposed to work this deposit by adopting 6.0 m bench height. The width of working

benches will be 8.0m

The ultimate pit slope of the pit is 450

The ramp gradient shall be kept minimum of 1 in 16.

The Following are the steps involved for winning limestone.

Primary and Secondary Breaking: Mega Rock Breaker of 150 TPH capacity will be deployed for

primary breaking and dilution of oversize boulders which will totally eliminate drilling and blasting.

Loading and hauling: Excavator will be used for loading the material on to the tippers (hauling units)

which will be used for transportation of mineral from the mines to crusher at plant site and for handling

the overburden / reject.

Rock breaker will be used for primary breaking wherever required and also for reduction of oversize

boulders instead of secondary blasting.

BENCH PARAMETERS:

Bench height - 6m

Bench Width - 8m

Ultimate Pit Slope - 450

Depth of Mining - 21 m maximum up to 80 RL.

Operating cost:

a) Mining (Wages , purchase cost , Explosives)

b) Over head cost (Stores, spares, electricity ) Rs.240.85

Page 29: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 29

c) Depreciation, Royalty

d) Transportation Rs. 85.80

e) NMET Rs. 16.00

f) DMF Rs. 24.00

Total Rs.366.65

Limestone cost/t Rs.366.65/T

b) Indicate year-wise tentative Excavation in Cubic Meters indicating development,

ROM, pit wise as in table below.

Following table shows year wise development and estimated production figures for this plan period. I. Insitu Tentative Excavation

Year Pit No. Total tentative Excavation

cum

Top Soil (Cu m)

OB/SB/IB (Cum)

ROM (Cu m) Total waste (Cum)

ROM/ Waste Ratio Ore

cum Mineral reject (Cum)

1 2 3 4 5 6 7 8 9

2018-19 North pit 450000 Nil 150000 300000 Nil 150000 1:0.50

South Pit 675000 225000 450000 225000

Total 1125000 375000 750000 375000

2019-20 North pit 450000 Nil 150000 300000 Nil 150000 1:0.50

South Pit 675000 225000 450000 225000

Total 1125000 375000 750000 375000

2020-21 North pit 450000 Nil 150000 300000 Nil 150000 1:0.50

South Pit 675000 225000 450000 225000

Total 1125000 375000 750000 375000

Total 3375000 1125000 2250000 Nil 1125000

Bulk Density of Limestone=2.0, Waste rock (Sandstone) =2.0

Detailed calculation of Year wise production table with size of pit, level of working and with bench

parameters is enclosed as annexure 13.

Quality of Reject / Waste generated during the development:

Rock type

Average Thick ness (in m)

Physical characteristics

Chemistry

SiO2 Al2O3 Fe2O3 CaO LSF

Top Soil Red soil

0.0-0.50 Loose, friable & absorbent

42.76 12.94 14.19 18.78 13.00

OB / Interstitial reject materials

0.50-8.0 Soft yellowish clay soil and interstitial reject

27.50 8.77 9.55 12.50 6.25

Page 30: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 30

II. Dump re handling (for the purpose of recovery of mineral): Estimated available material (Cum)

No dump re handling

Dump identification/ no

Year wise handling (Cum)

Estimated recovery of saleable material

(Cum) *

Reject (Cum)

Nil Nil Nil Nil

c) Enclose Individual year wise development plans and sections showing pit layouts, dumps,

stacks of mineral reject, if any, etc in case of 'A' category mines.

Refer Plate No. 6A to 6C)

d) Describe briefly giving salient features of the proposed method of working indicating

Category of mine.

The method of working is opencast mining considering various technical parameters like

surface topography, continuation of limestone deposit, quality variations, geo-technical

aspects, required rate of production etc.,

The method of working is opencast (A Category fully mechanized) adopting non-

conventional method by deploying rock breaker for primary and secondary breaking

eliminating drilling and blasting thus adopting eco-friendly mining.

It is proposed to work this deposit by adopting 4.0 m bench height. The width of working

benches will be 6.0m

The ultimate pit slope of the pit is 450

The ramp gradient shall be kept minimum of 1 in 16.

The main work comprises of overburden removal, using rock breaker for mining kankar & limestone.

The Following are the steps involved for winning limestone.

Primary and Secondary Breaking: Mega Rock Breaker of 150 TPH capacity will be deployed for

primary breaking and dilution of oversize boulders which will totally eliminate drilling and blasting.

Loading and hauling: Excavator will be used for loading the material on to the tippers (hauling units)

which will be used for transportation of mineral from the mines to crusher at plant site and for handling

the overburden / reject.

Rock breaker will be used for primary breaking wherever required and also for reduction of oversize

boulders instead of secondary blasting.

Page 31: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 31

BENCH PARAMETERS:

Bench height - 6m

Bench Width - 8m

Ultimate Pit Slope - 450

Depth of Mining - 14 m maximum up to 80 RL.

e) Describe briefly the layout of mine workings, pit road layout, the layout of faces and sites

for disposal of overburden/waste along with ground preparation prior to disposal of waste,

reject etc. A reference to the plans and sections may be given. UPL or ultimate size of the pit is

to be shown for identification of the suitable dumping site.

Present Pit dimension as follows:

For North pit:

For South pit:

A sump is being developed in the Eastern side of the pit to collect the surface water.

Presently in view of supplying raw material to the cement field, yearly production from this mine is

proposed to adopt A category fully mechanized method of mining.

The nature of top soil is Black cotton soil and the same has been removed and dumped all along the

mine lease boundary. No sub-grade ore or mineral rejects is generated during the modifications to

the approved mining plan period.

Refer plate No: 6A to 6C

f) Conceptual Mine planning up to the end of lease period taking into consideration the present

available reserves and resources describing the excavation, recovery of ROM, Disposal of

No. Bench Top R.L Bottom R.L Height L x W

I st Bench Topsoil & sandstone

100 M 94 M 6.0 M 210 M x 145 M

II nd Bench 92 M 88 M 6.0 M 100M x 60M

No. Bench Top R.L Bottom R.L Height L x W

I st Bench Topsoil & sandstone

100 M 94 M 6.0 M 100 M x 60M

II nd Bench 92 M 88 M 6.0 M 80M x 60M

Page 32: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 32

waste, back filling of voids, reclamation and rehabilitation showing on a plan with few relevant

sections.

Refer Plate No.8

The following factors have been considered for arriving at the ultimate pit limits.

Ultimate pit limit has been determined based on the mineral economics and quality of limestone from

the bore hole data. The ultimate size of the pit is ------- ha.

This ultimate pit limit is marked on the Geological plan and conceptual plan.

Ultimate pit Dimension :

Leaving safety barriers on all sides as per rules, the rest of the lease area will be worked out.

Ultimate pit limit has been determined and demarcated on surface plan and geological plan

Ultimate Pit size

Pit Length Width No. of

Benches Height Pit slope

North 850 M 430 M 4 25M 450

South 1100 M 700 M 3 25M 450

The total excavated area shall be around 60.685Ha at the end of mining operations. It is proposed

to convert part of the mined out area as an artificial pond to store rainwater and the remaining by

back filling with rejects (sandstone). The area is arid and has a low rainfall about 900mm/yr.

Therefore the water stored from rainfall could be used as reservoir in the locality helping the

neighboring villagers. The reservoir will have an enough potential to store water. The water in the

reservoir thus located shall improve bore well irrigation.

The undisturbed virgin lease area along the mining lease boundary shall be utilized for agricultural

purposes by developing the area with eucalyptus and causurina plants with co ordination of Forest

department and TNPL. This work shall be done after the cessation of mining operations.

This aspect has been considered in detail. Accordingly conceptual mining plan is drawn. There is

adequate space for dumping waste rock. After the mine reaches the ultimate depth waste stacked

in the ear marked location will be spread as top capping in the reclaimed area to improve the

growth of vegetation.

The total quantity of top soil black cotton soil material has been stacked all along the mining lease

boundary and in the eisting top soil dump location area earmarked in the plated no. 6A to 6C

Page 33: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 33

As the mining has not yet reached the ultimate pit limit, there is no proposal for reclamation during

this modification period.

Mineable reserve and anticipated life of the mines:

The proved mineral reserves are 18.58 Mil.T of limestone, having the proposed exploitation fo

mineral of 1.5 million tons per annum, the life of the mine will come around 12.38 years, say 13

years. Hence the life of mine is 13 years only with respect to the proposed production rate..

However the life of the mining may be extended in future depending upon the availability of other

fresh leases.

B. UNDERGROUND MINING

Not Applicable

ix) Extent of mechanization

Describe briefly with calculation for adequacy and type of machinery and equipment proposed

to be used in different activities of drilling, material handling in development and stope,

hauling, hoisting to surface, surface transportation and any other operation.

Justification of Mining for Mining Machinery Requirements.

The method of working is opencast mining considering various technical parameters

like surface topography, continuation of limestone deposit, quality variation, geo-

technical aspects, required rate of production etc.,

It is proposed to work this deposit by adopting 6.0m bench height . the width of working

benches will also be 6m.

The ultimate pit slope of bench is kept at 45%

The ramp gradient shall be kept minimum of 1 in 16.

EXTENT OF MECHANISATION:

For the proposed production of 1.50 MTPA)

Production per day : 1500000/300 = 5000 TPD

(1) Primary Breaker

(1) Primary Breaker

Nos Bucket Capacity in TPH Make

04 150 TPH Atlas Copco

Proposed production per day : 5000 t

Number of shifts = 2

Page 34: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 34

Effective working hours = 6

Output per hour = 150 TPH

Output per machine per shift = 900 TPD

No of Machines required = 1

Considering 80% as availability 1 rock breakers are sufficient to handle the production.

However one more rock breaker will be kept as standby.

(2) Loading equipment (Production and development)

Type Nos. Bucket capacity in Cu.m

Make H.P

Excavator 04 1.9 Tata Hitachi

198

Excavating Parametres:

C = Bucket Capacity = 1.90 m3

F = Bucket fill factor = 0.85

S = Swell Factor (at 25% swell) = 0.8

t = Time cycle per pass at 900 swing = 20 sec

e = Overall efficiency for three working shift = 0.80

T = Seconds per hour = 3600

n = Number of working shifts/day = One

h = hours per shift = 8

W = Working days in a year = 300

A = Availability of machine = 0.35

U = Utilization factor = 0.80

b) Rate of Production

Output / Shovel/ hour = (C * F * S * T)/ (t) 1.5 * 0.85 * 0.80 * 3600 / 20

= 183.6 m3 say 184 m3

Output/ Shovel/ Year = 184*h*n*w*e*A*U

= 184*8*1*300*0.80*0.85*0.80

Page 35: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 35

= 240230 or 480460 or 4.80 Lac Tones.

c) Number of Excavators

Quantity of material to be handled per day : 7500 Tones

No.of working days : 300 days

Maximum handling of material required = 2250000 tones.

Number of excavator (Shovels) required = 4 no.

Four machine is just sufficient to handled both production and development. However one more

machine will be kept as standby.

(3) Haulage and transport equipment

(a) Haulage within the mining lease-hold.

Type Nos. Bucket capacity in Cu.m

Make H.P

Tippers 33 20 T AMV/TATRA/MAN 112 The company has proposed to set up the mobile screening plant for the production of 500Tons per

day.

Hauling units for Production:

Quantity to be handled – T/day : 7500T

No.of Shifts per day : 2

Capacity of tipper : 20T

Distance of handling : 28 kms (to and fro distance)

Total quantity of ore handled by tipper / hr : 20 T

Effective working hours : 6

Total quantity of ore handled by Tipper / shift : 150 T

No.of Tippers required : 33

No.of spare tippers : 7

Total no of tippers : 40

List of Mining Machineries

The Miscellaneous equipments like Explosive van, water tanker and jeeps are provided for effective

workings.

Page 36: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 36

S.No Name of Machinery Nos T/Hr Capacity Model H.P Mobile Screening

Plant 1 500 To be Installed

1 Excavator 2 200 2.2 Tata Hitachi 200 Excavator 2 300 2 Rock break 2 150 TPH - Atlas Copco 3 Tippers ( Production) 24 480 20 T AMV / TATRA / MAN 4 Jeeps 1 - - Mahindra - 5 Water Sprinkler 1 - 4000 Its Tractor with tanker

mounted -

3. MINE DRAINAGE a) Minimum and maximum depth of water table based on observations from nearby wells and

water bodies .

Ground water is the main source in this area, apart from rain in the monsoon period. The water table is

intersected 30 to 35 meters from the surface

b) Indicate maximum and minimum depth of Workings.

Minimum depth of mine working is 21 m and maximum depth 25m

c) Quantity and quality of water likely to be encountered, the pumping arrangements and

places where the mine water is finally proposed to be discharged .

The main source of ground water in the area is rainfall. The average rainfall per year in the area is

900mm. At the end of the plan period of excavated area, the water encountered in the mine shall be

collected in a sump which shall be at a level lower then the actual mine floor and the collected water

sump shall be utilized for spraying on the haul roads and for plantation. The resident water shall be

pumped out in to a channel to the nearby pond.

d) Describe regional and local drainage pattern. Also indicate annual rain fall, catchments

area, and likely quantity of rain water to flow through the lease area, arrangement for arresting

solid wash off etc.

Ground water is the main source in this area, apart from rain in the monsoon period. The water table is

intersected 40 to 45 meters from the surface. The ground water will be collected in the sump for the

deposition of solid particles. Once the suspended particles are deposited it will be pumped out for

domestic purpose, dust suppression system, gardening and Afforestation purpose. The excess water

only will be pumped out to the nalla /closer water bodies – pond after the deposition of solid particles.

There are no toxic elements found in the sump water.

The water table is found at a depth of 30 metres in rainy season and at 35m in dry season. To cope up

with storm water and seepage water, an energy efficient electrical pump of 20H.P capacity will be

installed and the discharge will be let-out in the nallah/Pond.

Garland drains will be made all along the periphery of dumpsites to prevent the water carrying the

Page 37: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 37

wash-offs from the dumps and topsoil yard entering into the mines. The water collected in the garland

drains will flow towards a settling tank formed near by the dumpsite. The water will be allowed to settle

the wash offs from the dumps in the settling tank and pure & clear water will be utilized for

afforestation purposes and for wetting of haul roads to arrest the dust generation.

Average rainfall in this area during Northeast Monsoon is around 900 mm.

4.0 STACKING OF MINERAL REJECT /SUB GRADE MATERIAL AND DISPOSAL OF WASTE

a) Indicate briefly the nature and quantity of top soil, overburden / waste and Mineral

Reject to be disposed off.

The mining lease area is covered by Red soil of 0.0 to o.50 Mtrs. thickness. The test results of soil

samples collected from this area prove that the soil cover over is suitable for agriculture and for

afforestation purpose.

The chemical composition of top soil and waste rock as follows.

Nature and Quality of Top soil

There will be no handling of Topsoil & overburden during the scheme period. The top soil of very

meager quantity encountered will be temporarily stacked along the mining lease boundary and

consumed parallely for the afforestation purposes.

The waste generated during the mining operations is topsoil & waste rock sandstone. The nature of

the waste is sandstone. The chemical composition of waste is as follows.

LOI SiO2 Al2O3 Fe2O3 CaO MgO 13.80 59.50 11.70 7.20 5.20 1.30

The Topsoil removed during the year 2000-01 to 2010-11 around 1.12 lakh Tons is dumped in the

existing dumpyard given in the eastern side of the lease area. During the last scheme fperiod no top

soil and waste has been generated due to the quality and technical constriants of the deposit.

GENERATION OF WASTE IN THIS SCHEME PERIOD

YEAR Topsoil (in Metric tons.)

Waste rock / (sandstone) In Metric tons)

2018-19

750000

2019-20

750000

2020-21

750000

Total

2250000

.

Page 38: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 38

The total quantity of about 2250000 tons of reject / waste will be generated during the proposed

production of limestone in this modification period. This quantity will be stacked in the existing dump

yard as well as in the proposed dump yard with in the mining lease area. The location of existing and

proposed dump yards is shown in the plate No.3, 4 & 6.

b) The proposed dumping ground within the lease area be proved for presence or

absence of mineral and be outside the UPL unless simultaneous backfilling is

proposed or purely temporary dumping for a short period is proposed in mineralized area

with technical constraints & justification.

Dumping will be done in advancing method. During the last Eleven-year plan 1.12 lakh tons of Top soil

/ waste rock has been removed and has been stacked in the existing dump in non mineral bearing

area earmarked in the lease hold area and top soil has been utilized for stacking in the safety barrier

zone all along the mining lease boundary for Afforestation purpose. The total quantity of about

2250000 tons of waste will be generated during the proposed production of limestone in this

modification to the approved mining plan period. This quantity will be stacked in the existing dump

yard as well as in the proposed dump yard with in the mining lease area. The location of existing and

proposed dump yards is shown in the plate No.3 & 5 to 9.

c) Attach a note indicating the manner of disposal of waste, configuration and sequence of

year wise build up of dumps along with the proposals for protective measures.

Dumping will be done in advancing method. During the last Eleven-year plan 1.12 lakh tons of Top soil

/ waste rock has been removed and has been stacked in the existing dump in non mineral bearing

area earmarked in the lease hold area and top soil has been utilized for stacking in the safety barrier

zone all along the mining lease boundary for Afforestation purpose.

Location of Dump:

The overburden and the interstitial rejects are disposed by dumping them in the dump yards. The

reject dump yards are located in the barren, non-mineral bearing areas in the mining lease area. The

dump yards have been planned and formed in such a manner so as to facilitate safe and convenient

dumping operations as per the guidelines give by IBM.

The angle of repose of the dump yard is 450. The proposed dumps are located within the distance of

about 100 to 200 mts from the respective working mines. The proposed dumps are shown in the year

Page 39: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 39

wise production and development plan (Plate No. 6A to 6C).

Maximum Spread and Height of Dumps:

The total quantity of Top soil / waste rock of about 1.12 Lakh Ton ( 75000 M3) generated during the

last 11 years period and it was used concurrently for the afforestation purpose and the remaining

quantity is stacked temporarily in the dump yard and Safety Zone.

Existing top soil / waste rock Dump Configuration along the periphery.

Dump Length (m) Width (m) Height (m)

Waste Dump-1 100 60 18

Waste Dump-1 80 40 12

Proposed Top soil and waste dump configurations are shown in the year wise and developmental

plans and sections in plate nos. 6A to 6C.

Stabilization and vegetation of dumps

During the previous years of operation, the quantity of topsoil / waste rock dumped is meager and with

minimum height of 1 metre to 1.5 metre there will not be possibility for slope instability. Hence the

question of vegetation of dumps does not arise. Moreover, the dumped topsoil during mining operation

will be removed and used for afforestation purposes.

Measures to control erosion / sedimentation

There is no any major nallahs nearby the workings. So there will not be any problem regarding

erosion. Moreover there is no major dumps, which may be exposed to erosion, and hence no

sedimentation also. If at all the water course filled with sediments, it will be cleared every year after

monsoon. Only the surface wafer, which is a source of erosion, is diverted by forming the bunds.

5.0 USE OF MINERAL AND MINERAL REJECT

The following are to be furnished in the interest of mineral conservation.

a) Describe briefly the requirement of end-use industry specifically in terms of physical and

chemical composition.

Page 40: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 40

The entire mineral mined will be used for the manufacture of different types of cements in the our own

captive cement plant located at Ariyalur, Ariyalur Taluk and District along with limestone received from

other leases.

The limestone mined from all of captive limestone mines will be utilized for the cement manufacturing

only. Raw mix parameters required to be maintained for the manufacture of cement is as follows,

The variation in the chemical behavior of this limestone is summarized below.

Minerals Sio2 (%) Al2O3 (%) Fe2O3 (%) CaO (%)

Limestone 8.0 - 13.0 2.70 -4.50 1.80 -3.50 42.0 -47.0

Grade control:

As per the norms prescribed by NCBM (National council for Cement and Building Materials) the broad

chemical specifications of cement grade ROM limestone are as follows:

Basically the qualities of raw mix parameters are controlled on the basis of the LSF, SM & AM.

Depending upon the quality of coal used in the plant the quality of the ROM will vary in terms of LSF

between 90 to 100

The quality of limestone from various leases in varies in composition because of inherent geological

characteristics. Based on the available average analysis of limestone from different leases the M/s.

Tamilnadu cement Corporation Limited has to mine the limestone from this Mine lease area in the

above rate to meet out the required raw mix parameters,

Plant capacity of the Ariyalur Works. : 1.5 million tons / annum

Requirement of Limestone : 2.5 Million tons /annum

Limestone from G.O.624 : 1.5 million tons / annum

Balance quantity of limestone will meet from other limestone mines.

Raw Mix Design:

Name of the mine % of

Contribution Sio2 Fe2O3 CaO MgO

G.O.No.344 25 9.4 4.0 46.3 0.6

Page 41: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 41

G.O.No.456 41 6.5 3.6 48.0 0.5

G.O.No.469 15 16.4 4.6 40.3 1.0

G.O.No.624 15 11.80 0.75 47.5 1.50

Clay (Additive) 04 59.5 7.0 5.0 1.5

b) Give brief requirement of intermediate industries involved in up gradation of mineral before

its end-use.

The entire limestone is used for own cement manufacturing purpose and the end product is cement

c) Give detail requirements for other industries, captive consumption, export, associated

industrial use etc.

The mined out limestone will be exclusively for captive use in the company’s cement plant.

d) Indicate precise physical and chemical specification stipulated by buyers .

The mineral limestone to be raised from this mine shall be solely for captive use for the manufacture of

cement. The limestone is not for sale nor shall it be exported

e) Give details of processes adopted to upgrade the ROM to suit the user requirements.

The limestone is of cement grade and no sub-grade mineral is encountered. Hence, the company will

consume it in it’s own cement plant.

6.0 PROCESSING OF ROM AND MINERAL REJECT

a) If processing / beneficiation of the ROM or Mineral Reject is planned to be conducted, briefly

describe nature of processing / beneficiation. This may indicate size and grade of feed

material and concentrate (finished marketable product), recovery etc.

Page 42: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 42

No processing or beneficiation of the ore or mineral mined is planned to be conducted on site or

adjacent to the extraction areas. The mined material shall be loaded and transported to the crusher

located at the plant. Apart from crushing no processing or beneficiation of the mineral is involved.

b) Give a material balance chart with a flow sheet or schematic diagram of the processing

procedure indicating feed, product, recovery, and its grade at each stage of processing.

No processing or beneficiation of the ore

c) Explain the disposal method for tailings or reject from the processing plant.

No processing or beneficiation of the mineral is involved.

d) Quantity and quality of tailings /reject proposed to be disposed, size and capacity of tailing

pond, toxic effect of such tailings, if any, with process adopted to neutralize any such effect

before their disposal and dealing of excess water from the tailings dam.

No processing or beneficiation of the mineral is involved.

e) Specify quantity and type of chemicals if any to be used in the processing plant.

No processing / beneficiation is proposed to be conducted, therefore, no chemical(s) shall be used

f) Specify quantity and type of chemicals to be stored on site / plant.

No chemicals shall be stored at site / plant

g) Indicate quantity (cum per day) of water required for mining and processing and sources of

supply of water, disposal of water and extent of recycling Water balance chart may be given.

No water shall be required for processing. Water shall be required in mining for dust suppression at

faces and on the haul roads, cleaning and washing of HEME and plantation. Apart from the above

water shall also be required for drinking and cleaning purposes. The estimated quantum of water

requirement shall be to the tune of 40 m3/day. Ground water pumped out through tube wells and as

the mine develops the water accumulated in the dump shall be utilized to meet the above requirement.

No waste water is likely to be generated from the mines. Only water used under high pressure for

cleaning of HEME in the workshop can be guided and passed into the green belt. The water used for

spraying the mine face or haul road shall either absorbed by the ground or get evaporated. Thus no

recycling of water in the mines is foreseen.

7.0 OTHER

a) Site services:-

Page 43: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 43

The site services include (a) mines office, (b)rest shelter,(c) first aid center, (d)store room, water tank,

public convenience, water-man-shed Road – for adjacent mines and factory Drinking water- Bore wells

are dug to cater the need of the drinking water ,Telephone line etc.

All the above structures is of semi-permanent / temporary in nature.

b) Employment potential:

Employment potential of Anandavadi Mines

The anticipated employment, likely to be generated, is given in the table below. It includes managerial

& supervisory staff directly employed by the company and skilled, semi skilled workers through

contractual.

Therefore, total strength of workforce in the mine is = 41 (Direct-7& Indirect-34)

Additional Requirement:

Transportation of Limestone.

The following additional contractual man power required for handling of limestone apart from

above departmental manpower. .

Tarus Drivers : 35 Nos (Skilled)

Spotters & Helpers : 02 Nos (UN Skilled)

Manpower calculation for Anandavadi Limestone Mines

Sl.No. Operations No. of Persons

required per day

1 Mines Manager 1

2 Asst.Mines Manager cum Mining Engineer

2

3 Geologist 1

4 Mech.Engineer 1

5 Mines Foreman 2

Sub-total 7

9 H.E.O 8

10 Drivers 18

11 Mechanic 2

12 Helpers, Mazdoors 3

13 Clerk 1

14 Un Skilled 2

Sub-total 34

Grand total 41

Page 44: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 44

ORGANISATION CHART FOR MINING DEPARTMENT

8.0 PROGRESSIVE MINE CLOSURE PLAN UNDER RULE 23 OF MCDR’2017

8.1 Environment Base line information: Attach a note on the status of baseline

Managing Director

General Manager- Tech

Deputy General Manager – Tech/Unit Head

Asst. Manager

Mines

Asst. Manager

Mines

Sr.Foreman (Mines)

Sr. Asst. Manager

Mines / Asst. Manager

Asst. Manager

Geologist

Manager (Mines)

Dy. Manager (Mines)

Sr.Foreman (Mines) Surveyor

Geologist

Page 45: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 45

Information with regard to the following.

Hence environmental impact due to limestone production up to 15.0 lakh tons / annum during the

forthcoming years, M/S Tamilnadu Cement Corporation Ltd has engaged an environmental

consultant for seasonal monitoring. The company has appointed the environmental consultant for

preparing the EIA report for the enhanced quantity of 15.0 lakhs tons per annum of limestone. The

.copy of work order issued to environmental consultant for preparing EIA / MOEF report is

enclosed as Annexure-.14.

Existing land use pattern indicating the area already degraded due to quarrying, dumping

processing plant, workshop, township etc., in a tabular form.

(i) Land-use pattern:

Present Land use pattern.

(ii) Water regime

The Nallah is passing across the lease area and flowing from NNE to SW of the lease area. It

drains the area and joins the local water body in the south and western portion of the ML area.

The Nallah is not perennial. It is dry during the major part of the year but is subject to occasional

flash floods.

No Details As on date (in Ha.)

1 Area under mining 3.045

2 Storage of topsoil 0.500

3 Overburden/dump 1.000

4 Mineral storage 0.000

5 Infrastructure 0.150

6 Road 0.200

7 Railways 0.000

8 Green belt 25.000 9 Tailing pond 0.000

10 Effluent treatment plant 0.000

11 Mineral separation plant 0.000

12 Township 0.000

13 Unused virgin land 80.790

Grand Total 110.685

Page 46: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 46

The ground water table is about 30 to 35 metres below the ground during the summer and it

raises during rainy season.

(iii) Flora & Fauna:

Flora: The area adjacent to the mining lease is occupied by vegetation and other species. In the

buffer-zone area of five kilometers, we find neem, babul etc., on bunds. Natural vegetation like

grasses and wild shrubs grow during the monsoon, which is useful for grazing and in the summer,

they dry out. Density of flora will be around 100 trees / hectare.

Fauna: The fauna that is obtained within the buffer zone are common varieties like foxes,

jackals, mongoose and rats etc. In the amphibian and reptile category monitor lizard, cobra, viper,

krait, chameleons are found. The insects are honey bee, wasp, beetle, termites, bugs,

mosquitoes, scorpion, red ants etc.

The fauna found in the area are of common variety and thus no endangered species are found in

the study area.

Base line data generation for air, noise level, ground vibration will be discussed in detail after the

completion of one season monitoring. Presently the various environmental parameters are

discussed based on the available data.

(iv) Quality of air:

Generally the dust level in the air is kept within the limit. The maximum concentration of air

pollutants at different- stations during the study indicates that the highest 24 hour concentration of

S P.M. was 260.6mg/m3 at TAI Station (Anandavadi village) and well within the CPCB limits .

The maximum 24 hour concentration of SO2 was 7.6 mg/m3 at station TA4 (Sendurai) and is well

within the prescribed limits of CPCB (80mg/m3).

Similarly the maximum 24 hour concentration of NOX was 16.8 mg/m3 at station TA2 (Maruvathur)

and is well within the prescribed CPCB limits (120 mg/m3).

Hence there will not be any bad impact on Air quality by mining, to the entire life of the mine.

In case of source samples, the SPM level recorded has been a maximum of 1659.6.50

micrograms /m3 near haulage road (source sample) requiring suitable management measures.

The CO level in the ambient air samples was found to be below detecting level.

Page 47: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 47

A summary of ambient quality monitoring results for 24 hours average concentration are given

below:

Sl. No

Sampling station TSPM µg/m

3

PM10 µg/m

3

So2 µg/m

3

NOx µg/m

3

HC ppm

CO Ppm

A1 Mining lease area-1 132.9 38.8 8.1 11.6 <1 <1 A2 Mining lease area-2 129.6 34.9 6.9 10.0 <1 <1 A3 Near Pit-3 132.9 38.5 7.9 11.1 <1 <1 A4 Venkataramanapuram 90.3 24.8 5.9 8.6 <1 <1 A5 Ottakoil 91.8 23.3 5.9 7.0 <1 <1 A6 Kallankurichi 90.4 25.8 5.9 7.9 <1 <1 A7 Kadugur 88.9 23.4 5.8 8.0 <1 <1 A8 Kovilankudikadu 91.3 25.8 5.8 8.1 <1 <1 A9 Chinnanagalur 105.0 26.6 6.0 8.2 <1 <1 A10 Reddipalayam 96.3 25.6 6.0 7.8 <1 <1

(v) Noise level:

Noise level is kept under check. Adequate measures will be taken up to control the noise level and

also to provide appliances to the operators to avoid noise pollution if any.

The maximum and average of this noise levels in the 0 - 3 KM zone are 90 dB(A) and 74 dB(A)

respectively. Whereas in 3-8 KM zone the same have been reported to be 71 dB(A) and 52 dB(A)

respectively. In the 8-10 KM zone the maximum noise level recorded is 68 dB(A) and the average

is 51 dB(A).

Hence there will not be any damage risk for hearing loss, by the mining activities, upto the mine life

period.

Location of the Noise Level survey.

Sl. No

Sampling station Day Leq dB(A)

Night Leq dB(A)

A1 Mining lease area-1 49.8 41.5

A2 Mining lease area-2 48.0 44.6

A3 Near Pit-3 50.3 45.8

A4 Venkataramanapuram 49.5 44.3

A5 Ottakoil 50.1 45.0

A6 Kallankurichi 48.7 43.5

A7 Kadugur 50.2 41.9

A8 Kovilankudikadu 48.0 41.0

A9 Chinnanagalur 48.3 42.3

A10 Reddipalayam 47.6 40.6

Page 48: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 48

To reduce the noise level efforts will be made by proper maintenance schedule, placement of

compressors away from the workers. However, in addition to this, earmuffs are also being provided

to the workers to prevent them from the noisy environment.

(vi)Ground vibrations:

Three number of blasts have been conducted at source area from close distances and found that

the peak particle velocities were found to be less than 3mm / sec. The readings are taken from the

blast site at different distance in the three blasts. During the first blast, around 600 kgs of

explosives were blasted with a charge per delay of 202 kgs, the PPV value was measured at a

distance of 500m from the blasting site, which showed a value of 1.5 mm/sec. During the second

and third blast, the ppv values were measured at a distance of 150m and 75m respectively, in

which we recorded a PPV value of 1.5 and 2.9 mm/sec.

Ground vibrations were measured near the mine site at different directions at the time of blasting

and readings were found to be very less.All the mining area is isolated, and no residential

structures are nearby. Due to ground vibrations while blasting, nearby dwellings will not be affected

because of very low particle velocity.

Protective measures for ground vibrations / airblast

Ground vibration is an important consideration, so that public should not be affected. The following

measures are taken to minimize ground vibrations and air blast by blasting.

1. A delay interval of 25 milliseconds, between holes is maintained using delay detonators.

2. Individual delays for each hole is used with card relays.

3. We will minimize the use of detonating fuse within the hole and other portions will be covered

with drill cuttings and there will not be air blast.

4. Peak particle velocity will be kept very low, by using non-el-system as a special case.

5. For larger blasts, sequential timer will be used in the blasting operations to avoid noise and

vibration.

6. Proper spacing and burden is maintained according to the bench heights to control blasting

with low particle velocity and low noise.

Page 49: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 49

7. Adequate care is taken to minimize the ground vibration by proper selection and usage of

explosive depending upon the strata to be blasted.

However, displacement due to blasting was measured using a vibration meter at a distance of 500

m from the mine and the displacement noticed was only 0.2 micron which is very minimal which

will not cause any damage.

Monitoring Locations and Methodology

Water samples from surface water source and ground water sources were collected from identified

locations as per details given in following table in sterilized plastic cans to assess the existing

water quality of the study area twice during the study period. The samples were analyzed for

physical, chemical and bacteriological parameters as per the bureau of India Standards IS:10500

specifications, However, additional parameters like chemical and Bio chemical Oxygen Demand,

Total suspended solids, Oil & Grease, and Ferric and Ferrous ion were also analyzed. The

samples were analyzed as per standard procedure / method given in IS : 3025 (different parts) and

standard method for examination of water and waste water ED 20, published jointly by

APHA,WWA and WPCF.

Detail of water sampling locations

Results and observations

The detailed physico- chemical characteristics of surface and ground water samples collected

within the study area are presented in Annexure –8 and described hereunder.

Ground Water

pH values varied between 7.12 to 8.10 while turbidity ranged from 2.3 to 3.5 NTU. Dissolved solids

varied between152.359 mg/l and 1995 701 mg/l and total hardness varied from 160.0 to 295.7

S.I.

No.

Location Sample

No.

Arial Distance

from mines

(KM)

Direction

From Mines

Type and

Sources of

water

1 Kallankurichi PW1 SW 4 Bore Well

2 Periyanagalur PW2 0 0 Mine Water

3 Kairullbad PW3 NE 4.7 Bore Well 4 Amenabad PW4 SE 1.75 Bore Well

Page 50: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 50

mg/l. Chloride values varied between 29.9 mg/l and 4956 mg/l. Calcium values varied between

54.5 mg/l and 75.2 mg/l and Magnesium values varied between 27.4 mg/l and 32.6 mg/l. Sulphate

values varied from 28.7 to 480 mg/l and Nitrate values varied from 0.4 to 1.7 mg/l. Cyanide has

been observed as nil while Arsenic, Cadmium, Lead, Copper, Chromium, Selenium and Zinc have

been observed below detection limit.

Surface Water

pH values varied between 7.64 to 8.0 while turbidity ranged from 8.8 to 9.5 NTU. Dissolved Solids

varied between 338 mg/l and 542 mg/l while total suspended solids varied from 31.7 to 36.7. Total

hardness varied from 235.1 to 295.3 mg/l. Chloride values varied between 18.2 mg/l to 25.1 mg/l.

Calcium values varied between 71.5 mg/l to 77.2 mg/l and Magnesium values varied between

32.6mg/l and 33.6 mg/l. Sulphate values varied from 27.6 to34.8 mg/l and Nitrate values varied

from 0.4 to 1.7 mg/l and Nitrate values varied from 1.1 to 1.3 mg/l. Cyanide has been observed as

nil while Arsenic, Cadmium, Lead, Copper, Chromium, Selenium and Zinc have been observed

below detection limit. MPN Coliform (per 100 ml) values have been observed within limit.

From the above results, the prescribed limit of IS 10500, it is found that ground water of the study

area is fit for drinking purposes as alternate source.

There would not be any toxic effluent from mine hence there in no need for any treatment of water

from mine.

Control measures to be adopted are

The peripheral bunds will help that soils is not carried away by storm water. Stabilization of bund

slope to prevent erosion and this shall be done by providing dense plantation along the bund

slopes.

During dewatering operations the pumped out water will be let out in the nearby natural courses.

(viii) Climatic conditions

A meteorological station was set up in all three season to collect micro meteorological data for the

area.

The average annual rain fall in this area is about 900 mm. The area receives maximum rainfall

during N.E. Monsoon (i.e.) between October to December and precipitation also occur during S.W.

monsoon between July and September.

Page 51: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 51

The rains are not generally heavy enough to hamper mining operations for more than one or two

days at a time. Ho disastrous floods have been recorded in this area. The maximum temperature

in summer months is 40° C. In the winter months (December to February) the minimum

ternperature would be about 300 C. Cyclone and storms are rare in this area. The main wind

directions are as follows. Winds are mainly from directions between North and North East from

November to February. In March winds are mostly from directions North East and South East, to

the morning and afternoon they are either Northerly to North Easterly or Southerly to South

Easterly. During April to October winds blow mostly from directions between South and South

Western in the morning, in the afternoons they are between South West and South East.

The area is well outside the known earthquake belt of the country and no earthquakes or

sympathetic shocks have been reported since historical times.

(ix) Human settlements:

The mining lease area is surrounded by few small villages. The main occupation of the people in

this part is agriculture. The lands in these areas are very fertile. Besides agriculture there are no

major industries.

.Rehabilitation

Within the Mine lease area, there is no a village or human settlement. Hence there is no

question of any evacuation and resettlement of people elsewhere.

Socio Economic Studies

It is well known fact, that industrialization will affect directly or indirectly the life styles, social

structure and economics of the persons who are living in the region. A study of the existing

baseline date on these aspects will help to force the impact of mining in future.

For this study the area has been divided into 2 zones namely core and buffer, while the 5KMs belt

around the mine lease area constituted the core zone the area up to 10 Kms distance from the

periphery of the lease has been considered as buffer zone. Baseline data and socioeconomic

environment in the core and buffer zone were combined from the senses. The data covers various

constituents such as demo graphs, literacy, employment, land classification, availability of

educational, medical and communication facilities etc.

DEMOGRAPHIC PROFILE

Village Population Distance Direction Sendurai 4637 1.4 Km SW Maruvattur 2761 3.1 Km SE Periakurichi 3253 3.9 Km NE

Page 52: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 52

Nakkambadi 2679 2.6 Km NW Vanjinapuram 2798 3.0 Km NW

Public Buildings, Places and Monuments:

There are no historical places of interest monuments, pilgrimage centers around the Mining lease

area.

Sanctuary is located in the vicinity of leasehold.

No Sanctuary is located in the vicinity of leasehold.

8.2 Impact Assessment: Attach an Environmental Impact Assessment Statement describing

the impact of mining and beneficiation on environment on the following:

ENVIRONMENT IMPACT ASSESSMENT STATEMENT

The environmental impact due to the enhancement of limestone production up to 15.0 lakhs tons

per Annum during the proposed modification period has been taken in to considerations while

preparing impact assessment statement.

Due to the increase in the cement production from 5 lakhs to 15 lakhs tons, the company has

engaged the EIA consultant for the enhanced proposed production of limestone from this G.O. 624

will be 15.0 lakhs tons per annum.

The address of the EIA consultant who prepares the EIA report for the MOEF clearance is as

follows,

M/s Mantec Consultants Pvt. Ltd, D-35 & 36, sector-6, Noida, Pin- 201 301 India. Tel: +91 1412751801/802/803, Fax: 2751806 E-Mail: [email protected] url: www.cegindia.com

The copy of work order issued to EIA consultant is enclosed as annexure no.15, the same after

completion will be submitted to IBM.

ENVIRONMENT IMPACT ASSESSMENT STATEMENT:

i) LAND ENVIRONMENT:

Land use pattern after five years

Page 53: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 53

a) Land and Land Subsidence:

Any mining operation is likely to alter the already existing topography. Scheduled reclamation of

the mined out areas will eventually represent a better landscape with even topography, which

would be amenable for farming etc.

b) Aesthetic Environment and Tourist Spots (if any)

The Mining lease area neither endowed with environmentally aesthetic attributes not is an

attractive place for tourists.

c) Soil and Land use Pattern

Opencast mechanized mining operations in this area would not cause discernible changes in the

soil characteristics since mining operations will not result in any kind of toxic effluents nor would

there be any solid waste generation.

The existing land use pattern is mainly cultivation for rotational/seasonal crop harvest. In the M.L.

area, most of the area is agricultural land and the remaining part comprises of grazing lands and

scrub jungle. Most of the plants are armed with spines and hooks. The prevailing land use pattern

in the post-mining period would not altogether get altered. Novel and extensive schemes of

afforestation will be implemented so as to minimize the effect of current land use.

d) Agriculture

No Details

As on date (in Ha.)

At end of scheme period (in Ha.)

At the end of life of the mines (in Ha.)

1 Area under mining 3.045 7.045 60.685

2 Storage of topsoil 0.500 0.500 0.000

3 Overburden/dump 1.000 2.900 0.000

4 Mineral storage 0.000 0.000 0.000

5 Infrastructure 0.150 0.200 1.000

6 Road 0.200 0.500 0.500

7 Railways 0.000 0.000 0.000

8 Green belt 25.000 27.500 48.500 9 Tailing pond 0.000 0.000 0.000

10 Effluent treatment plant 0.000 0.000 0.000

11 Mineral separation plant 0.000 0.000 0.000

12 Township 0.000 0.000 0.000

13 Unused Virgin lands 80.790 72.040 0.000

Grand Total 110.685 106.685 110.685

Page 54: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 54

The proposed mining methods will not cause any harm to the agricultural field in the surroundings.

With the commencement of mining operations employment (both direct and indirect) opportunities

will inherently force a change in the occupational structure partially. Consequently with increased

economic status, modernized agricultural practices would be adopted which will result in not only

better crop yield, but also reduce the pressure on particular operation.

Additionally, the wastelands and fallow lands upon mining and suitable reclamation will result in

beneficial rehabilitation of the derelict lands. Emphasis will be on restoration of mined out lands

to agricultural practices.

e) Forest

The Mining lease area does not include any forest area.

f) Flora and Fauna

The area under mining lease is not a habitat for wild life or bird sanctuary etc. Therefore mining

would not cause any effect on existing flora and fauna. There is no rare/endangered species of

flora in the area. Mining operations will not involve any felling of trees etc. as most of the area

selected for mine working is devoid of trees/plants etc. There is no wild life sanctuary in the vicinity

of mining lease area. So no rare/endangered or wild species is likely to be affected by the mining

project.

AIR:

A number of activities have an impact of ambient air quality of the area. These includes industries,

domestic fuel consumption, traffic emission etc. Major pollutants are SPM, Nox and So2. The main

source of air pollutant in SPM is mining activities. The generation of Nox and So2 results obtained

are well within the limits prescribed by CPCB for areas meant for industrial use.

Air pollution impact analysis is of prime concern. Dust is a particulate contaminant suspended in

the atmosphere. The upper size limit of dust particles is governed by gravitational effects. While

the distinction between the respirable and non respirable dust is scientifically valid it is clear that

both sizes can impair lung functions when inhaled over a time.

Deployment of diesel powered equipment for mining may produce emissions that are known to be

hazardous, viz unburnt hydrocarbons, oxides of nitrogen, particulates, phynols, aldehydes, oxides

Page 55: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 55

of sulphur, trace elements, smoke and hydrocarbons. These pollutants are known to cause

respiratory ailments.

Use of protective equipments to reduce the exposure of personnel to excessive concentrations of

dust, dust suppressive techniques along haul tracks and drilling sites are practiced to minimize

negative impacts.

Ambient air quality Monitoring was carried out for summer season (April, May and June). The

parameters selected for analyzing ambient air quality status were Respirable Particulate Matter

(RPM), Suspended Particulate Matter (SPM) Oxides of Nitrogen (Nox), Sulphur diaoxide (SO2). A

summary of ambient quality monitoring results for 24 hours average concentration are given below:

Locations Values SPM

µg/m3

RPM

µg/m3

SO2

µg/m3

NOx

µg/m3

Anandavadi

lease site

Min 67.60 33.740 7.00 6.00

Max 74.20 41.30 12.00 10.00

Mean 71.57 38.98 9.63 8.13

Control Measures for Air Quality / Dust Suppression

The main activities for air pollution are drilling, Blasting, loading, unloading, transportation and

heavy duty mobile equipments. Suppression measures like water spraying along haul road,

roadside plantation to provide canopy of foliage and regular use of water ejecting system to

dampen and control the dust during the course of drilling will be undertaken.

The proposed measures to control air quality within the limits are detailed below,

Mobile equipments

Dust emanated due to the movement of equipments is generally suppressed by the

following ways:

Surfacing of internal roads.

Dust suppression by water sprays

Dust generated in the mines will be suppressed by sprinkling water on haul roads with the help of

mobile water tanker with sprinkling arrangement. As there is not much of water seepage and

accumulation in the pits, permanent pipe line connection for spraying water on haul road for dust

suppression cannot be carried out immediately. However your advice & suggestion will be

Page 56: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 56

considered in future.

Rows of trees would be planted

ii) WATER ENVIRONMENT:

a) Surface Water:

The Nallah is passing across the lease area and flowing from NNE to SW of the lease area. It

drains the area and joins the local water body in the south and western portion of the ML area.

The Nallah is not perennial. It is dry during the major part of the year but is subject to occasional

flash floods.

The ground water table is about 15 to 20 metres below the ground during the summer and it raises

during rainy season.

b) Ground Water

Ground water is the main source in this area, apart from rain in the monsoon period. The water

table is intersected 15 to 20 meters the surface. The ground water will be collected in the sump for

the deposition of solid particles. Once the suspended particles are deposited it will be pumped out

for domestic purpose, dust suppression system, gardening and Afforestation purpose. The excess

water only will be pumped out to the nalla /closer water bodies – pond after the deposition of solid

particles. There are no toxic elements found in the sump water.

The water table is found at a depth of 15metres in rainy season and at 20m in dry season. To cope

up with storm water and seepage water, an energy efficient electrical pump of 20H.P capacity will

be installed and the discharge will be let-out in the nallah/Pond.

Garland drains will be made all along the periphery of dumpsites to prevent the water carrying the

wash-offs from the dumps and topsoil yard entering into the mines. The water collected in the

garland drains will flow towards a settling tank formed near by the dumpsite. The water will be

allowed to settle the wash offs from the dumps in the settling tank and pure & clear water will be

utilized for afforestation purposes and for wetting of haul roads to arrest the dust generation.

(v) Noise level:

Noise level is kept under check. Adequate measures will be taken up to control the noise level and

also to provide appliances to the operators to avoid noise pollution if any.

The maximum and average of this noise levels in the 0 - 3 KM zone are 90 dB(A) and 74 dB(A)

respectively. Whereas in 3-8 KM zone the same have been reported to be 71 dB(A) and 52 dB(A)

Page 57: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 57

respectively. In the 8-10 KM zone the maximum noise level recorded is 68 dB(A) and the average

is 51 dB(A).

Hence there will not be any damage risk for hearing loss, by the mining activities, upto the mine life

period.

Location of the Noise Level survey.

Sl. No

Sampling station Period Day Leq dB(A)

Night Leq dB(A)

A1 Mining lease area-1 Nov-10 49.8 41.5

A2 Mining lease area-2 Nov-10 48.0 44.6

A3 Near Pit-3 Nov-10 50.3 45.8

A4 Venkataramanapuram Nov-10 49.5 44.3

A5 Ottakoil Nov-10 50.1 45.0

A6 Kallankurichi Nov-10 48.7 43.5

A7 Kadugur Nov-10 50.2 41.9

A8 Kovilankudikadu Nov-10 48.0 41.0

A9 Chinnanagalur Nov-10 48.3 42.3

A10 Reddipalayam Nov-10 47.6 40.6

To reduce the noise level efforts will be made by proper maintenance schedule, placement of

compressors away from the workers. However, in addition to this, earmuffs are also being provided

to the workers to prevent them from the noisy environment.

(vi)Ground vibrations:

Three number of blasts have been conducted at source area from close distances and found that

the peak particle velocities were found to be less than 3mm / sec. The readings are taken from the

blast site at different distance in the three blasts. During the first blast, around 600 kgs of

explosives were blasted with a charge per delay of 202 kgs, the PPV value was measured at a

distance of 500m from the blasting site, which showed a value of 1.5 mm/sec. During the second

and third blast, the ppv values were measured at a distance of 150m and 75m respectively, in

which we recorded a PPV value of 1.5 and 2.9 mm/sec.

As such there is no need to go for 30 readings to be taken, as the values in either in the village or

in the close vicinity do not warrant such an exercise.

Monitoring Locations and Methodology

Water samples from surface water source and ground water sources were collected from identified

locations as per details given in following table in sterilized plastic cans to assess the existing

Page 58: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 58

water quality of the study area twice during the study period. The samples were analyzed for

physical, chemical and bacteriological parameters as per the bureau of India Standards IS:10500

specifications, However, additional parameters like chemical and Bio chemical Oxygen Demand,

Total suspended solids, Oil & Grease, and Ferric and Ferrous ion were also analyzed. The

samples were analyzed as per standard procedure / method given in IS : 3025 (different parts) and

standard method for examination of water and waste water ED 20, published jointly by

APHA,WWA and WPCF.

Acid mine drainage, if any

No acid mine drainage

Socio-economics

Educational Facilities:-

Tamil medium state board higher secondary school and an English medium matriculation school

are available at Ariyalur to cater the need of the education to employee’s children and the other

villager’s children living in and around the factory and mines. Scholarship facilities for employee’s

children as well as to the school toppers are given for pursuing higher education.

Hospital:

The hospital is located at Ariyalur and at Kadugur in a well-constructed building. Medical

treatments including supply of specialist care, medicines are given to the employees and other

persons living in and around the mines and factory at free of cost E.C.G facility is also provided in

the dispensary. Phone facilities will be arranged in the mines to contact the Doctors and the

Hospital round the clock. Ambulance has also been provided which can be summoned

immediately over phone. Staffs are provided in the dispensary round the clock to attend to the

emergency cases.

Health care facilities:

Regularly health camps are organized at our dispensary to cater to the need of the persons living

in and around the mines area and factory area at free of cost. Specialist from various

health fields like eye, cardiac care, diabetes, ortho etc are called from Ariyalur, Trichy &

Perambalur hospitals to give specialized health care to the people.

For the welfare of the children of the employees and villagers living around mines and factory,

vaccination camps are regularly organized at our dispensary.

Drinking water facility:

Bore wells are dug in the villages in and around the mines at our company’s cost to cater to the

Page 59: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 59

need of the villagers for drinking water. For the nearby villages, sintex water tanks are kept in

prominent locations which are filled up daily with drinking water supplied through a water tanker

from the factory.

The lakes in and in around villages are deepened with our mine machineries regularly every year

just before the onset of monsoon season in order to accumulate and store the rain water in the

lakes for the use of villagers for their domestic purposes.

Road & Bridges constructions:

For the villages in around the mines and factory permanent roads laying works are taken from time

to time by the company.

Children’s park:

A park for the children of employees residing in the colony will be provided with a good lawn and

sliding board and other playing mutes.

Quality of life:

The standard of living of the villagers has drastically improved as most of them are employed in the

factory or in the mines. Because of this they are able to provide good education to their children

and improve their quality of life. Most of the employees who are presently employed in the mines

and factory are the third generation in the family working for the factory and mines continuously.

Indirect employment opportunities are created for the local people living in around the mines area

motivating them by giving suitable contractual jobs like transportation of limestone from mines to

factory, Afforestation work at mines etc.

Community centre:

Community center is constructed at our colony premises to organize marriage functions and other

traditional rituals of our mine employee’s family and other villagers at a nominal rate.

Temple renovation work:

Company is taking utmost interest & contributing in renovating the existing temples in around the

mines area and factory at company’s cost enabling the villagers to celebrate their temple functions

every in a grand manner. The management grants donations to various temples for conducting

scheduled annual poojas.

Rainwater harvesting:

Recently our company has initiated the rain water harvesting practices inside our company and

colony premises to store the rainwater and effectively use the same during the summer season.

Occupational Health and Safety

Page 60: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 60

As regards occupational health and safety are concerned, the employed staff would be provided

with adequate safety implements and also be periodically trained in the VT programmes to observe

and use them. Strict vigil would be maintained as is our usual practice for observance of safety

aspects in working atmosphere. Health of workers is of primary concern in our organization.

Regular medical checkup for the workers will be conducted as per statutory requirements.

Public Buildings, Places and Monuments:

There are no historical places of interest monuments, pilgrimage centers around the Mining lease

area.

Review of Environmental proposals and the status of compilation at the end of the plan period.

SL NO.

ITEM

PROPOSALS AS PER APPROVED SCHEME

OF MINING

POSITION AT THE END

OF SCHEME OF MINING PERIOD

PROPOSALS FOR

NEXT THREE YEARS MODIFICATION

PERIOD

1 2 3 4 5

1.

Top soil storage

Total quantity of top soil proposed to be handled is 2.31 Lakh tons. Dumping Proposals were made in the mineral bearing adjoining to the working pit. Store it separately for future use in spreading afforestation areas

Since production was not met that target. The top soil handled upto the 31

st march 2011 is 1.25

Lakh tones. Topsoil is stored separately on the designated place so far. There is no deviation from the proposal

No generation of top soil is proposed.

2.

Land reclamation and rehabilitation

No proposals for reclamation and rehabilitation in the approved scheme of ,as limestone would not be exhausted.

The mining is not yet reached the basement and the production achieved during the period is very meager 2.60 Lakh tonnes.

The mine will not be exhausted of limestone in the next five years so no reclamation or rehabilitation of full or part of the quarry is proposed.

3.

Waste dump management

Proposals were to store topsoil & waste sandstone separately and places were earmarked for the purpose.

Topsoil, and waste rock sandstone is being stored at the designated places separately. No deviation from approved scheme of mining

22.5 Lakh tones off sandstone envisaged during this period will be stacked separately at ear marked locations..

4.

Afforestation programme with precautions for survival and protection of plantation

In the approved mining scheme 3880 No of trees are proposed to cover an area of 4.15 Ha..

Till date eucalyptus & casurina is planted over 2.0 Ha at the rate of 1500 Trees / ha along the water body boundary.

It is proposed to plant about 4500 nos. of trees in five years at the rate of 1500 trees per year along the boundary and waste dump yard. Area covered will around 02.50 Ha.

Page 61: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 61

5.

Quality of air.

Periodical environmental monitoring of air quality to be conducted.

Periodical environmental monitoring of air quality conducted as per IBM/MoEF norms quarterly The latest environmental monitoring reports is enclosed as annexure-2

Periodical environmental monitoring of air quality conducted as per IBM/MoEF norms quarterly and the same to be continued

6.

Quality of water.

Periodical environmental monitoring of Water quality to be conducted.

Periodical environmental monitoring of water quality conducted as per IBM/MoEF norms quarterly

Periodical environmental monitoring of water quality conducted as per IBM/MoEF norms quarterly and the same to be continued

7.

Noise level

Periodical environmental monitoring of noise level to be conducted.

Periodical environmental monitoring of noise level conducted as per IBM/MoEF norms quarterly

Periodical environmental monitoring of Noise level conducted as per IBM/MoEF norms quarterly and the same to be continued

8.

Ground vibration.

Periodical environmental monitoring of Noise level to be conducted.

Periodical environmental monitoring of Noise level conducted as per IBM/MoEF norms quarterly

Periodical environmental monitoring of Noise level conducted as per IBM/MoEF norms quarterly and the same to be continued

9.

Treatment of mine water including surface and ground water.

There was no proposal to treat ground or surface water.

Monitoring and study was made and there will be no toxic effluent that will be discharged from the mine hence, no treatment of ground and surface water.

There will be no toxic effluent that will be discharged from the mine hence, no treatment of ground and surface water is proposed.

10.

Re-circulation of treated water.

No proposal in the approved scheme of mining for re-circulation of treated water as there was no need to treat water in the mine.

No re-circulation of treated water done. This was not applicable.

Not applicable as no toxic effluent is going to be produced or discharged from the mine.

Presently the company has registered the ONLINE application to TNPCB for the above quarterly

Monitoring study of Air, Water, and Noise during the scheme period. TNPCB will do the monitoring

study as per the date of registration and priority basis. After the completion of quarterly monitoring

study the same will be submitted to IBM for reference. The copy of EMP report and TNPCB consent

letter is enclosed as annexure no.14.

Page 62: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 62

8.3 Progressive reclamation Plan:

In the preceding chapter, an attempt was made to assess the likely impact on the environment due

to various mining activities. This chapter describes the scheme for environmental management,

the proposed abatement measures to minimize the likely environmental degradation that may be

caused due to the mining operations at proposed Mining Project.

Considering the scale and methodology of mining operations in the project area as discussed

earlier, no significant environmental degradation is expected. The micro level eco system and

socio economic setup of the villages is likely to improve. Environmental control measures and

techniques are discussed below to mitigate any adverse effect owing to the mining activities.

8.3.1. Mined-Out Land:

The total excavated area shall be around 60.685 Ha at the end of mining operations. It is

proposed to convert the mined out area as an artificial pond to store rainwater and as well as part

of the area will be refilled and subsequently afforested. The area is arid and has a low about

900mm/yr. Therefore the water stored from rainfall could be used as reservoir in the locality

helping the neighboring villagers. The reservoir will have an enough potential to store water. The

water in the reservoir thus located shall improve bore well irrigation.

The undisturbed virgin lease area along the mining lease boundary shall be utilized for agricultural

purposes by developing the area with guava, straw berry, fig fruit plants etc. This work shall be

done after the cessation of mining operations.

Justification Artificial Pond to Store Rain Water:

The sub-surface of the area is composed of hard rocky strata. So the rainwater is not directly and

effectively absorbed into the ground. Since no major water resources / reservoirs / lakes / ponds

etc, are present in the area, if we fully reclaim the mined out pits we would completely loose the

entire rainwater instead of being harvested in the mined out pits thereby increasing the level of the

water table in the area will get increased.

The undisturbed virgin lease area along the mining lease boundary shall be utilized for agricultural

purposes by developing the area with guava, straw berry, fig fruit plants etc. This work shall be

done after the cessation of mining operations.

Therefore, by proposing to utilize the mined out pits as water reservoirs, after entire mining

operations gets completed, we would be able to serve the following purposes:

Page 63: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 63

1) Sustain the water resources for the drought prone area of local villages.

2) Increase the level of water table in the adjacent area.

3) To meet the drinking water requirement of local villagers.

4) To afforestate the non-mining leases areas (earmarked for afforestation) with the

Stored water from these pits.

Therefore, considering the above facts, we propose not to reclaim the mined out pits after entire

mining is completed instead we would utilize them as water reservoirs which would be the need of

the prevailing hydrological atmosphere in the mining lease area.

Post Mining after cessation of mining activities

8.3.2 Topsoil Management:

During the three year modification period no topsoil will be generated and it will be in meager

quantity will be stacked all along the safety barriers of the lease area, and it will be utilized for the

afforestation purposes.separately in the 50M safety zone area along the odai.

The average thickness of the top soil is varying in thickness 1 to 0.5M in the mining lease area for

mining. The upper layer of top soil, which is oxidized and contains organic matter will be stripped

and used for spreading over the slopes of the peripheral bund to facilitate revegetation and also for

tree plantation over areas beyond the peripheral bund. Excess quantity of top soil remaining will

be stacked separately in a dump yard for the above stated purpose. The slopes of the dumpsites

No Details

As on date (in Ha.)

At end of scheme period (in Ha.)

At the end of life of the mines (in Ha.)

1 Area under mining 3.045 7.045 60.685

2 Storage of topsoil 0.500 0.500 0.000

3 Overburden/dump 1.000 2.900 0.000

4 Mineral storage 0.000 0.000 0.000

5 Infrastructure 0.150 0.200 1.000

6 Road 0.200 0.500 0.500

7 Railways 0.000 0.000 0.000

8 Green belt 25.000 27.500 48.500 9 Tailing pond 0.000 0.000 0.000

10 Effluent treatment plant 0.000 0.000 0.000

11 Mineral separation plant 0.000 0.000 0.000

12 Township 0.000 0.000 0.000

13 Unused Virgin lands 80.790 72.040 0.000

Grand Total 110.685 110.685 110.685

Page 64: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 64

will be terraced with grasses, legumes etc to arrest soil crossing to a great extent. The soil from

this dump yard and shall be rehandle and spread over the backfilled areas, once backfilling of the

mines out area commences.

During the modification period to plant about 1500 Nos. of saplings all along the boundary to

cover an area of 2.50.0 Ha and the survival rate of plantation is only 80%.

Existing Afforestation details as follows:

Existing afforestation

The non mined areas of the lease are afforested by planting saplings of casurina and Eucalyptus.

Afforestation is completed within the mining lease area. The existing afforestation within the lease

area is as follows.

Location Area in

Hectares

No. of

plants

Name of

species

Expected rate

of survival

Along the water

course and in the non

mining area by Forest

dept. and by TNPL

25.00 15,000 Eucalyptus and

Casurina 80%

This afforestation work is done with the co-ordination of Forest Department. After the contract

period is over the trees will be cut by the above department and again the non mining areas will

become virgin.

Proposed Afforestation programme for three years modification period:

Year No. of

Saplings

Area

Covered

(Ha)

Survival

rate

Places of

plantation

Species

2018-19 1500 0.833 80% Safety zone

barrier

Eucalyptus &

Caurina

2019-20 1500 0.833 80% -Do- -Do-

2020-21 1500 0.834 80% -Do- -Do-

Total 7500 2.50.0

Environmental Plan is enclosed. Refer Plate No. 7

8.3.3 Tailings Dam Management.

As such there is no beneficiation plant for processing of the mineral and hence there is no

Page 65: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

M/s Tamilnadu Cements Corporation Ltd.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 65

Disposal of waste/ tailing from the mine is envisaged.

8.3.4 Acid mine drainage, if any and its mitigative measures.

No acid mine drainage

8.3.5 Surface subsidence mitigation measures through backfilling of mine voids or by any

other means and its monitoring mechanism.

The information on protective measures for reclamation and rehabilitation works year wise may

be provided as per the following table.

SUMMARY OF YEARWISE PROPOSAL FOR ITEM NO. 8.3

Lime stone deposit was not exhausted and the quarry has not reached ultimate depth. So question

does not arise for reclamation and rehabilitation.

Page 66: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi
Page 67: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

Scheme of Mining of Anandavadi Limestone Mines

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 67

YEARLY PROPOSAL FOR ITEM NO. 8.3 OF PMCP FOR THE III YEAR (2018-19) FOR ANANDAVADI LIMESTONE MINES OVER AN EXTENT OF 110.685 HA.

Items Details Proposed Actual Remarks

Dump

management

Area afforested (ha) Nil

No of saplings planted Nil

Cumulative no of plants Nil

Cost including watch and care during the

year

Nil

Management

of worked out

benches

Area available for rehabilitation (ha) Nil

Afforestation done(ha) Nil

No of saplings planted in the year Nil

Cumulative no of plants Nil

Any other method of rehabilitation (specify) Nil

Cost including watch and care during the

year Nil

Reclamation

and Rehabilitation

by

backfilling

Void available for Backfilling (L x B x D) pit

wise /stope wise Nil

Void filled by waste /tailings Nil

Afforestaion on the backfilled area Nil

Rehabilitation by making water reservoir Nil

Any other means (specify) Nil

Rehabilitation

of waste land

within lease

Area available (ha) Nil

Area rehabilitated Nil

Method of rehabilitation-By afforestation Nil

Others

(specify)

Ambient Air Quality

Rs.

250,000/-

Water Quality

Noise level

Ground vibration

Green belt along mine periphery/Virgin area

(Ha)

0.833 (1500

saplings)

cost likely to

be incurred

– Rs. 75000

Total Rs. 325000

Page 68: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

Scheme of Mining of Anandavadi Limestone Mines

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 68

YEARLY PROPOSAL FOR ITEM NO. 8.3 OF PMCP FOR THE IV YEAR (2019-20) FOR ANANDAVADI LIMESTONE MINES OVER AN EXTENT OF 110.685 HA.

Items Details Proposed Actual Remarks

Dump

management

Area afforested (ha) Nil

No of saplings planted Nil

Cumulative no of plants Nil

Cost including watch and care during the

year

Nil

Management

of worked out

benches

Area available for rehabilitation (ha) Nil

Afforestation done(ha) Nil

No of saplings planted in the year Nil

Cumulative no of plants Nil

Any other method of rehabilitation (specify) Nil

Cost including watch and care during the

year Nil

Reclamation

and Rehabilitation

by

backfilling

Void available for Backfilling (L x B x D) pit

wise /stope wise Nil

Void filled by waste /tailings Nil

Afforestaion on the backfilled area Nil

Rehabilitation by making water reservoir Nil

Any other means (specify) Nil

Rehabilitation

of waste land

within lease

Area available (ha) Nil

Area rehabilitated Nil

Method of rehabilitation-By afforestation Nil

Others

(specify)

Ambient Air Quality

Rs.

250,000/-

Water Quality

Noise level

Ground vibration

Green belt along mine periphery/Virgin area

(Ha)

0.833 (1500

saplings)

cost likely to

be incurred

– Rs. 75000

Total Rs. 325000

Page 69: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

Scheme of Mining of Anandavadi Limestone Mines

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 69

YEARLY PROPOSAL FOR ITEM NO. 8.3 OF PMCP FOR THE V YEAR(2020-21) FOR ANANDAVADI LIMESTONE MINES OVER AN EXTENT OF 110.685 HA.

Items Details Proposed Actual Remarks

Dump

management

Area afforested (ha) Nil

No of saplings planted Nil

Cumulative no of plants Nil

Cost including watch and care during the

year

Nil

Management

of worked out

benches

Area available for rehabilitation (ha) Nil

Afforestation done(ha) Nil

No of saplings planted in the year Nil

Cumulative no of plants Nil

Any other method of rehabilitation (specify) Nil

Cost including watch and care during the

year Nil

Reclamation

and Rehabilitation

by

backfilling

Void available for Backfilling (L x B x D) pit

wise /stope wise Nil

Void filled by waste /tailings Nil

Afforestaion on the backfilled area Nil

Rehabilitation by making water reservoir Nil

Any other means (specify) Nil

Rehabilitation

of waste land

within lease

Area available (ha) Nil

Area rehabilitated Nil

Method of rehabilitation-By afforestation Nil

Others

(specify)

Ambient Air Quality

Rs.

250,000/-

Water Quality

Noise level

Ground vibration

Green belt along mine periphery/Virgin area

(Ha)

0.834 (1500

saplings)

cost likely to

be incurred

– Rs. 75000

Total Rs. 325000

Page 70: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

Scheme of Mining of Anandavadi Limestone Mines

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 70

8.4 Disaster Management and Risk Assessment:

The objective of onsite disaster management plan for the captive mine is to be a state of

perceptual readiness through training, development to immediately control and arrest any

emergency situation so as to avert a full fledged disaster and the consequence of human

and property damage and in the event of a disaster still occurring, to manage the same so

that the risk of the damage consequences to life and property is minimized

M/s Tamilnadu Cement Corporation Limited has formulated a disaster management plan

for Emergency Preparedness & Responses.

The salient features are elaborated as below:

Emergency response Organization

Communication System

Action on the site

Facilities available at site.

Emergency Response organization

Following officers of the mines will be responsible for co ordination in case of emergency

situated in any section of the mine.

Person Name Contact No. Responsibility

Head of the department Mr.K.Senthil kumar 9943844086 Site Controller

Section In charge Mr.T. Santhakumar

9047872442 Accident Controller/

Communication officer

Employee who gives the first

information about the accident/

Shift in charge

Mr.K.Senthil kumar 9943844086 Primary Controller

P & A Dep’t. (HOD)

Mr.Balachandar 8056902430 Liaison officer

Key Personnel and their responsibility:

Site Controller

The head of the department have overall responsibility for controlling the

incident/accident and directing the personnel.

To prepare full proof plan for control of accident like, landslides, subsidence flood

and other natural calamities

Page 71: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

Scheme of Mining of Anandavadi Limestone Mines

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 71

To inform statutory bodies of the State and central Government.

To inform communication officer about the emergency, control centre and

assembly point.

To provide all assistance and call for Fire Squad, Security Officer and other

services required for removing/control of danger.

To ensure that all necessary personnel to be assemble at assembly point.

Accident Controller/Section In charge

Mock rehearsal of plan prepared for accident.

To withdraw men/machines from the affected area with priority for safety of

personnel, minimize damage to the machines, environment and loss of material.

To act as accident controller to all the later arrived.

To make a report based on the facts and figure and submit to the Site Controller

Primary Controller/ Shift in charge

To inform the Accident Controller / shift in charge from the nearest means of

communication about the location and the nature of accident.

To assist in clearing any obstruction in relief of accident.

To carry out all instructions of accident controller.

Capability of Lessee: Following facilities are available at Mines.

Public addressing system

Telephones/ Mobile handsets

Runners/messenger

Emergency alarm

Fire fighting equipments & accessories with trained manpower

Full fledge dispensary

Training centre

Fire tender, Ambulance

Facilities available out side

Government Hospital at Ariyalur, Kadugur & Sendurai are available.

As per Risk Assessment studies, the possibility of “Offsite” emergency situation are ruled out

Page 72: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

Scheme of Mining of Anandavadi Limestone Mines

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 72

as proposed mine is not likely to pose any offsite emergency and hence does not call for any

preparation of an off-site emergency plan.

Further the residential quarters and living area are far from the mine.

However, considering extreme situation, District authority including police would be informed

about any offsite emergency if situation arises.

8.5 Care and maintenance during temporary discontinuance: An emergency plan for

the situation of temporary discontinuance due to court order or due to statutory

requirements or any other unforeseen circumstances may indicate measures of care,

maintenance and monitoring of status of discontinued mining operations expected to

re-open in near future.

When the mine is temporarily discontinuance due to any unforeseen circumstances the

following care and maintenance shall be carried out: -

Notice to be served to the all concerned authority

The mining pit area shall be covered by temporary fencing

All access roads / openings to the pit/face shall be closed by parapet wall as per

rule.

Warning shall be display on “Notice Board” at appropriate places

Security personnel shall be posted at every danger point.

No unauthorized person shall be allowed to enter into the mine without prior

permission of the management.

All men and machinery shall be withdrawn from the mine and shall be kept in a

compact and safe place.

All safety precautions shall be taken care off as per rule.

Page 73: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

Scheme of Mining of Anandavadi Limestone Mines

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 73

8.6 Financial Assurance:

Table indicating the Breakup of areas in the Mining lease for calculation of Financial

assurance. ( as per circular 4/2006)

Sl. No

Head Area put on use at start of Scheme of Mining

(in Ha.)

Additional requirement during plan period

(In Ha.)

Total (In Ha.)

Area considered as fully reclaimed & rehabilitated (in Ha.)

Net area considered for calculation (in Ha.)

A B C = A+B D E=C- D 1 Area under mining

3.045 4.000 7.045 0.000 7.045

2 Storage for topsoil 0.500 0.000 0.500

0.000 0.500

3 Waste dump 1.000 1.900 2.900

0.000 2.900

4 Mineral storage 0.000 0.000 0.000 0.000 0.000

5 Infrastructure 0.150 0.050 0.200 0.000 0.200

6 Road 0.200 0.300 0.500 0.000 0.500

7 Railways 0.000 0.000 0.000 0.000 0.000

8 Tailing pond 0.000 0.000 0.000 0.000 0.000

9 Effluent treatment plant

0.000 0.000 0.000 0.000 0.000

10 Mineral separation plant

0.000 0.000 0.000 0.000 0.000

11 Township 0.000 0.000 0.000 0.000 0.000

12 Others to specify Green belt

25.000 2.500 27.500 0.000 27.500

Grand Total 29.895 8.750 38.645 38.645

Area put to use for mining & allied services is about 38.645 Ha. for the modification period. As

per Rule 23(1) of MCDR 2017 an amount of Rs 1,15,93,500/-(Rupees One Crore Fifteen

Lakhs Ninety three thousand Five hundred only) @ Rs. 300000 per Ha. for “A” category mines

will be furnished after obtaining clearance from the Regional controller of mines.

The financial assurance in the form of Bank guarantee for the amount of Rs.9,66,125/- has

been submitted to IBM as per BG: No. The copy of BG is enclosed as annexure no.16.

The remaining amount of 1,06,27,375/- will be submitted after obtaining clearance from

regional Controller of Mines, Chennai.

Page 74: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

Scheme of Mining of Anandavadi Limestone Mines

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 74

The details of Bank Guarantee are given below:

Sl.

No

Bank Guarantee No. & date Amount

(in Rs.)

Validity

1 BG No.

18.02.2016

2 BG No.

Total

(B.Gangatharan)

Qualified Person

Page 75: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

363

302

303

304

361

360364

365

368

366

354357

367

345

372

371

370

369

362

421

420

419

429

423

422

307

306

305

359

326358

356353

351352

346

347

344

355

318

378 343

348

349

350 327

324

328

340

341

339

342

383

382

385

742

384

743

744

741

745746

733

748

734

733

755

756

754

757758

759

760

770

768

769

767

761

762

763

764765

766

750

751

747

749

752

753

338

336337

329 332

331

330

318317

333

334

335

316

315

320

321

322

323

314325

313

312

326

319Vathikaruppu kovil

Mariamman Kovil

Koppatti Kovil

Sellapaudayar kuttai

Applicant:

Scale 1:2000 SAI GEOSURVEY CONSULTANT

Qualified PersonB.GANGATHARAN

TAMILNADU CEMENTS CORPORATION LTD.,

ARIYALUR WORKS

ANANDAVADI LIMESTONE MINES

PLATE NO:2

LEASE PLAN

INDEX

MIING LEASE BOUNDARY

ROAD

KULAM / KUTTAI

CART TRACK

ODAI

BURIAL GROUND

+

+ +

+

+

Anandavadi Colony area

GO.No.624, dt.23.09.98

GCP-3

GCP-2

GCP-1

GCP-1

GCP-2

GCP-3

BP-33

BP-1

E 79' 10' 47.9" / N 11'11'22.5" /101.0

E 79' 10' 53.3" / N 11'11'12.7" / 97.0

E 79' 10' 54.0" / N 11'11'15.7" / 97.0

E 79' 10' 56.3" / N 11'11'11.8" / 95.0

E 79' 10' 54.9" / N 11'11'26.8" / 99.0

SE 419 M FROM BP-33

NEAR BURIAL GROUND

ON THE IRUMBULIKURICHI ROAD

SE 137M FROM BP-33

E 98M FROM BP-33

104m

104m

N

BP-1

BP-2

BP-3

BP-4

BP-5

BP-6

BP-7

BP-8BP-9

BP-10

BP-11BP-12 BP-13

BP-14

BP-15

BP-16BP-17

BP-20

BP-22

BP-21BP-25

BP-26BP-27

BP-28

BP-29BP-30

BP-31

BP-32

BP-33

BP-34BP-35

BP-36BP-37

SE 419 M FRO

M BP-33

E 98

M F

ROM

BP-

33

SE 1

37M

FRO

M B

P-33

Certified that "the plans & sections are preparedbased on lease map authenticated by state Govt."

BP-23

BP-24

BP-19 BP-18

Page 76: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

Pit No. 1

102m

104m

104m

102m

98m

96m

DUMP

96m94m

98m

AGD-1099.405

102m

100m

IDAYANKULAM

98m

96m

96.915AGD-5

AGD-497.080

AGD-396.220

94m

92m

92m

AGD-294.225

AGD-191.350

AGD-692.415

AGD-11100.595

100m

AGD-1A102.700

102m

AGD-17101.445

AGD-23104.090

AGD-22103.175

AGD-21102.450

KOVIL

AGD-20100.180

OFFICE

100m

98mKOVIL

AGD-1298.970

+

96m

++

+ ++

+ ++

94m

92m

92m AGD-993.095

94m

AGD-18

105.550100m

AGD-1598.710

AGD-1397.060

AGD-16100.735

AGD-24105.745

TO

CHO

LAN

KURI

CHI

TO IRUMBILIKURICHI

AGD-25107.00

AGD-794.225

AGD-896.080

TO IRUMBILIK

URICHI

INDEX

MIING LEASE BOUNDARY

QUARRY

ROAD

KULAM / KUTTAI

DIAMOND DRILL HOLE

CART TRACK

ODAI

BURIAL GROUND

WELL

+ + ++ +

AGD-14

Haul Road

HAUL ROAD

Applicant:

Scale 1:2000 SAI GEOSURVEY CONSULTANTQualified Person

B.GANGATHARAN

TAMILNADU CEMENTS CORPORATION LTD.,

ARIYALUR WORKS

Certified that "the plans & sections are prepared

ANANDAVADI LIMESTONE MINES

PLATE NO:3

GO.No.624, dt.23.09.98

SURFACE PLAN

CONTOUR LINE96m

100.2

101.5

99.0

98.1

BM

GCP-3

GCP-2

GCP-1

GCP-1

GCP-2

GCP-3

BP-33

BP-1

E 79' 10' 47.9" / N 11'11'22.5" /101.0

E 79' 10' 53.3" / N 11'11'12.7" / 97.0

E 79' 10' 54.0" / N 11'11'15.7" / 97.0

E 79' 10' 56.3" / N 11'11'11.8" / 95.0

E 79' 10' 54.9" / N 11'11'26.8" / 99.0

S33° E - 419 M FROM BP-33

NEAR BURIAL GROUND

ON THE IRUMBULIKURICHI ROAD

N15°W-148M FROM BP-33

N21°W-62M FROM BP-33

E 0 E 200 E 400 E 600 E 800 E 1000N 0

N 200

N 400

N 600

N 800

N 1000

N 1200

N 1400

N 1600

N 1800

N 2000

ADTH-199.200

ADTH-2100.34

ADTH-3101.40

ADTH-4102.095

ADTH-5102.990

ADTH-691.50

ADTH-794.60

ADTH-895.00

ADTH-9106

ADTH-1099.35

ADTH-1193.90

ADTH-1295.840

ADTH-1397.650

ADTH-1498.60

ADTH-1599.810

ADTH-1692.520

ADTH-1794.450

ADTH-1894.620

ADTH-1993.33

LIMESTONE OUTCROP

BP-1

BP-2

BP-3

BP-4

BP-5

BP-6

BP-7

BP-8 BP-9

BP-10

BP-11

BP-12BP-13 BP-14

BP-15

BP-16BP-17

BP-18BP-19

BP-20

BP-22

BP-21

BP-23

BP-24

BP-25BP-26

BP-27

BP-28

BP-29BP-30

BP-31

BP-32

BP-33

BP-34BP-35

BP-36BP-37

GCP GROUND CONTROL POINT

AGD

Eqalyptus plants by TNPL

Scale 1:200050040030020010040 60 80200

N

based on lease map authenticated by state Govt."

ACTIVE TOP SOIL DUMP YARD

104

102.1

156m, S84° W

419m, S33° E

148m, N

15° W

62m, N

21° W

Buildings

94.5 88.5

100.299.5

94.5

93.5

87.5

99.2

94.5

99.2

97.2

90.5

84.5

98.0

91.0

85.0

96.0

90

100.0

96.0

96.0

Date of survey 05.04.18

Pit No. 2

Page 77: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

102m

104m

104m

102m

98m

96m

96m

94m

98m

AGD-1099.405

102m

100m

98m

96m96.915AGD-5

AGD-497.080

AGD-396.220

94m

92m

92m

AGD-294.225

AGD-191.350

AGD-2692.415

AGD-11100.595

100m

AGD-1A102.700

102m

AGD-17101.445

AGD-23104.090

AGD-22103.175

AGD-21102.450

KOVIL

AGD-20100.180

OFFICE

100m

98mKOVIL

AGD-1298.970

+

96m

++

+ ++

+ ++

94m

92m

92m AGD-693.095

94m

AGD-18

105.550100m

AGD-1598.710

AGD-1397.060

AGD-16100.735

DUMP YARD

DUMP YARD

AGD-24105.745

TO

CHO

LAN

KURI

CHI

TO IRUMBILIKURICHI

AGD-25107.00

AGD-794.225

AGD-896.080

TO IRUMBILIK

URICHI

INDEX

MIING LEASE BOUNDARY

QUARRY

ROAD

KULAM / KUTTAI

DIAMOND DRILL HOLE

CART TRACK

ODAI

BURIAL GROUND

DIP & STRIKE

ULTIMATE PIT LIMIT

+ + ++ +

AGD-14

Haul Road

ACTIVE TOP SOIL DUMP YARD

HAUL ROAD

Applicant:

Scale 1:2000 SAI GEOSURVEY CONSULTANT

TAMILNADU CEMENTS CORPORATION LTD.,

ARIYALUR WORKS

ANANDAVADI LIMESTONE MINES

PLATE NO: 4

GEOLOGICAL PLAN

CONTOUR LINE96m

AGD-997.82

ADTH-199.200

ADTH-2100.34

ADTH-3

ADTH-4102.095

ADTH-5102.990

ADTH-691.50

ADTH-794.60

ADTH-895.00

ADTH-997.20

ADTH-1099.35

ADTH-1193.90

ADTH-1295.840

ADTH-1397.650

ADTH-1498.60

ADTH-1599.810

ADTH-1692.520

ADTH-1794.450

ADTH-1894.620

ADTH-1993.33

B

A'

C

D

E

F

G

H

A

I

I'

B'

C'

D' E'

F'

G'

H'

99.0

GO.No.624, dt.23.09.98

GCP-3

GCP-2

GCP-1

IDAYANKULAM

E 0 E 200 E 400 E 600 E 800 E 1000N 0

N 200

N 400

N 600

N 800

N 1000

N 1200

N 1400

N 1600

N 1800

N 2000

PBH-1

PBH-6

PBH-3

PBH-8

PBH-10

PBH-12

PBH-13

PBH-16

PBH-15

PBH-14

PBH-19

PBH-18

PBH-20

PBH-11

PBH-9PBH-7

PBH-17

BP-1

BP-2

BP-3

BP-4

BP-5

BP-6

BP-7

BP-8 BP-9

BP-10

BP-11

BP-12BP-13 BP-14

BP-15

BP-16BP-17

BP-18BP-19

BP-20

BP-22

BP-21

BP-23

BP-24

BP-25BP-26

BP-27

BP-28

BP-29BP-30

BP-31

BP-32

BP-33

BP-34BP-35

BP-36BP-37

AGD

PROPOSED BORE HOLEPBH

GCP GROUND CONTROL POINT

Scale 1:200050040030020010040 60 80200

N

LIMESTONE OUTCROP

INTERSTITIAL REJECTS

LIMESTONE WITH MARL

Eqalyptus plants by TNPL

Certified that "the plans & sections are preparedbased on lease map authenticated by state Govt."

PROPOSED DUMP YARD

GCP-1

GCP-2

GCP-3

BP-33

BP-1

E 79' 10' 47.9" / N 11'11'22.5" /101.0

E 79' 10' 53.3" / N 11'11'12.7" / 97.0

E 79' 10' 54.0" / N 11'11'15.7" / 97.0

E 79' 10' 56.3" / N 11'11'11.8" / 95.0

E 79' 10' 54.9" / N 11'11'26.8" / 99.0

S33° E - 419 M FROM BP-33

NEAR BURIAL GROUND

ON THE IRUMBULIKURICHI ROAD

N15°W-148M FROM BP-33

N21°W-62M FROM BP-33

Pit No. 1

100.2

101.5

99.0

98.1

94.5 88.5

100.299.5

94.5

93.5

87.5

99.2

94.5

99.2

97.2

90.5

84.5

98.0

91.0

85.0

96.0

90

DUMP106

104

102.1

100.0

96.0

96.0

54.7342

Pit No. 2

Qualified PersonB.GANGATHARAN

Date of survey 05.04.18

Page 78: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

AGD-6AGD-7

AGD-8AGD-9

AGD-10AGD-11

AGD-11A

0.0 200 400 600 800 1000 1200

96.0

92.0

88.0

84.0

80.0

76.0

72.0

68.0

64.0

93.094.095.0

63.062.061.0

100.0

102.0

Section along AGD-6 to AGD-11 & AGD-11A

ADTH-1ADTH-2

ADTH-3ADTH-4102.10

101.40100.14

99.5

24.00

20.0

16.50

10.40

ADTH-6

ADTH-7 ADTH-8

ADTH-9

ADTH-2

97.20

95.094.60

91.90

16.5

14.0

20.40

30.0

30.0

AGD-12AGD-13 AGD-14 AGD-15

AGD-16100.7

98.4098.697.40

96.57

29.50

30.65

41.60

31.0031.00

32.65 36.50

96.0

92.0

88.0

84.0

80.0

76.0

72.0

68.0

64.0

93.094.095.0

63.062.061.0

100.0

102.0

32.030.50

30.10

30.10 31.0030.90

38.70

93.09594.25

96.0897.82

99.04100.59

102.70

59.059.0

96.0

92.0

88.0

84.0

80.0

76.0

72.0

68.0

64.0

93.094.095.0

100.0

102.0

AGD-17

AGD-18105.05

101.45

96.0

92.0

88.0

84.0

80.0

76.0

72.0

68.0

64.0

93.094.095.0

63.062.061.0

100.0

102.0

59.0

57.0

55.0

104.0

106.0

102.0

102.0

0.0 200 400 600 800 1000 1200

Section along AGD -12 to AGD -18

96.0

92.0

88.0

84.0

80.0

76.0

93.094.095.0

100.0

102.0

0.0 200 400 600

96.0

92.0

88.0

84.0

80.0

76.0

93.094.095.0

100.0

102.0

0.0 200 400 600 800

96.0

92.0

88.0

84.0

80.0

76.0

72.0

68.0

64.0

93.094.095.0

100.0

102.0

AGD-1999.64

30.50

AGD-20AGD-21

AGD-22

AGD-23104.10

103.75102.50

101.7

AGD-24105.74

AGD-25107.10

SST

30.031.0

30.10

22.60

34.0

96.0

92.0

88.0

84.0

80.0

76.0

72.0

68.0

64.0

93.094.095.0

100.0

102.0

60.00.0 200 400 600 800 1000 1200

34.20

96.0

92.0

88.0

84.0

80.0

76.0

72.0

68.0

64.0

93.094.095.0

100.0

107.0

60.0

ADTH-1193.90

95.8497.65

98.6099.81

ADTH-12ADTH-13

ADTH-15ADTH-14

8.00

13.0015.00

15.0017.00

96.0

92.0

88.0

84.0

80.0

76.0

93.094.095.0

100.0

102.0

96.0

92.0

88.0

84.0

80.0

76.0

93.094.095.0

100.0

102.0

0.0 200 400 600 800

AGD-1 AGD-26

91.3592.45

96.0

92.0

88.0

84.0

80.0

76.0

93.094.095.0

100.0

102.0

72.0

38.038.45

68.0

64.0

60.0

56.0

52.0

48.0

96.0

92.0

88.0

84.0

80.0

76.0

93.094.095.0

100.0

102.0

72.0

68.0

64.0

60.0

56.0

52.0

48.0

TOP SOIL

LIMESTONE WITH MARL

SANDSTONE

ADTH-1692.52

ADTH-1794.45

ADTH-1894.260 ADTH-19

93.30

18.0 17.00

12.010.0

96.0

92.0

88.0

84.0

80.0

76.0

93.094.095.0

100.0

102.0

72.0

68.0

64.0

60.00.0 200 400 600

96.0

92.0

88.0

84.0

80.0

76.0

93.094.095.0

100.0

102.0

72.0

68.0

64.0

60.00.0 200

AGD-294.225

AGD-396.220

AGD-497.08

AGD-596.915

SST

SST

30.6031.0

30.20 30.25

96.0

92.0

88.0

84.0

80.0

76.0

93.094.095.0

100.0

102.0

72.0

68.0

64.0

60.00.0 200 400 600

96.0

92.0

88.0

84.0

80.0

76.0

93.094.095.0

100.0

102.0

72.0

68.0

64.0

60.0

Section along ADTH -1 to ADTH - 4

96.0

92.0

88.0

84.0

80.0

76.0

72.0

68.0

64.0

93.094.095.0

63.062.061.0

100.0

102.0

59.0

57.0

55.0

104.0

106.0

102.0

102.0 Section along ADTH -6 to ADTH - 9 & ADTH - 2

Section along AGD - 19 to AGD - 25

Section along ADTH - 11 to ADTH - 15

Section along AGD - 1 to AGD - 26

Section along ADTH - 16 to ADTH - 19Section along AGD - 2 to AGD - 5

2.0000

A

A'

A

BB'

C C'

D D'

E E'

F F'

G G'

I I'

H H'

( 50.0 m Safety zone barrier )

VERTICAL- 1CM = 5 MHORIZONTAL - 1CM = 50 M

Applicant:

SAI GEO SURVEY CONSULTANT

Qualified PersonB.GANGATHARAN

TAMILNADU CEMENTS CORPORATION LTD.,

ARIYALUR WORKS.

ANANDAVADI LIMESTONE MINES

PLATE NO: 5

GEOLOGICAL SECTIONS

GO.No.624, dt.23.09.98

748.1403

538.8625

( 111 )

( 221 )( 221 )

( 111 )

( 221 )( 221 )

( 111 ) ( 221 )( 221 )

( 111 )

( 221 )( 221 )

( 111 )

( 221 )( 221 )

( 111 )

( 221 )( 221 )

( 111 )

( 221 )( 221 )

( 111 ) ( 221 )( 221 )( 221 ) ( 111 ) ( 221 )

N

Area available for mining after leaving safety distance

Existing PitUPL

UPL

UPLUPL

UPLUPL

Certified that "the plans & sections are preparedbased on lease map authenticated by state Govt."

ULTIMATE PIT LIMIT

MINING LEASE BOUNDARY

INDEX

PBH-5 PBH-4PBH-3

PBH-2

PBH-1

PBH-6

PBH-7PBH-8

PBH-13PBH-12

PBH-11 PBH-10PBH-9

PBH-16PBH-15 PBH-14

PBH-19 PBH-18

PBH-20

EXISTING CORE DRILL BH

PROPOSED CORE DRILL BH

ADTH-15

PBH-9

Page 79: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

102m

104m

104m

102m

98m

96m

96m

94m

98m

102m

100m

98m

96m

94m

92m

92m

100m

102m

KOVIL

OFFICE

100m

98m

+

96m

++

+ ++

+ ++

94m

92m

92m

94m

100m

AGD-24105.745

TO

CHO

LAN

KURI

CHI

TO IRUMBILIKURICHI

AGD-25107.00

TO IRUMBILIK

URICHI

Haul Road

Applicant:

Scale 1:2000 SAI GEOSURVEY CONSULTANT

B.GANGATHARAN

TAMILNADU CEMENTS CORPORATION LTD.,

ARIYALUR WORKS

ANANDAVADI LIMESTONE MINES

PLATE NO: 6

C

B'

C'

99.0

GO.No.624, dt.23.09.98

IDAYANKULAM

E 0 E 200 E 400 E 600 E 800 E 1000N 0

N 200

N 400

N 600

N 800

N 1000

N 1200

N 1400

N 1600

N 1800

N 2000

BP-1

BP-2

BP-3

BP-4

BP-5

BP-6

BP-7

BP-8 BP-9

BP-10

BP-11

BP-12BP-13 BP-14

BP-15

BP-16BP-17

BP-18BP-19

BP-20

BP-22

BP-21

BP-23

BP-24

BP-25BP-26

BP-27

BP-28

BP-29BP-30

BP-31

BP-32

BP-33

BP-34BP-35

BP-36BP-37

Scale 1:200050040030020010040 60 80200

N

Certified that "the plans & sections are preparedbased on lease map authenticated by state Govt."

Pit No. 1

100.2

101.5

99.0

98.1

94.5 88.5

100.299.5

94.5

93.5

87.5

99.2

94.5

99.2

97.2

90.5

84.5

98.0

91.0

85.0

96.0

90

DUMP106

104

102.1

100.0

96.0

96.0

PRODUCTION PLAN FOR 2018-19YEARLY DEVELOPMENT &

INDEX

MIING LEASE BOUNDARY

QUARRY

ROAD

KULAM / KUTTAI

CART TRACK

ODAI

BURIAL GROUND

DIP & STRIKE

ULTIMATE PIT LIMIT

+ + ++ +

DUMP YARD

HAUL ROAD

CONTOUR LINE96m

LIMESTONE

2018- 19 Year Programme

Proposed Dumping area

Proposed Dumping Area

96.0

92.0

88.0

84.0

80.0

76.0

72.0

68.0

64.0

93.094.095.0

63.062.061.0

100.0

102.0

59.0

57.0

55.0

104.0

106.0

102.0

102.0

0.0 200 400 600 800 1000 1200

Section along C - C'

96.0

92.0

88.0

84.0

80.0

76.0

72.0

68.0

64.0

93.094.095.0

63.062.061.0

100.0

102.0

59.0

57.0

55.0

104.0

106.0

102.0

102.0

C C'

UPLUPLMLB

96.0

92.0

88.0

84.0

80.0

76.0

93.094.095.0

100.0

102.0

0.0 200 400 600

96.0

92.0

88.0

84.0

80.0

76.0

93.094.095.0

100.0

102.0

BB'

UPLUPLMLB MLB

Section along B - B'

B

Qualified Person

Page 80: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

102m

104m

104m

102m

98m

96m

96m

94m

98m

102m

100m

98m

96m

94m

92m

92m

100m

102m

OFFICE

100m

98m

+

96m

++

+ ++

+ ++

94m

92m

92m

94m

100m

AGD-24105.745

TO

CHO

LAN

KURI

CHI

TO IRUMBILIKURICHI

AGD-25107.00

TO IRUMBILIK

URICHI

Haul Road

Applicant:

Scale 1:2000 SAI GEOSURVEY CONSULTANT

B.GANGATHARAN

TAMILNADU CEMENTS CORPORATION LTD.,

ARIYALUR WORKS

ANANDAVADI LIMESTONE MINES

PLATE NO: 7

A'

C

D

A

C'

D'

GO.No.624, dt.23.09.98

IDAYANKULAM

E 0 E 200 E 400 E 600 E 800 E 1000N 0

N 200

N 400

N 600

N 800

N 1000

N 1200

N 1400

N 1600

N 1800

N 2000

BP-1

BP-2

BP-3

BP-4

BP-5

BP-6

BP-7

BP-8 BP-9

BP-10

BP-11

BP-12BP-13 BP-14

BP-15

BP-16BP-17

BP-18BP-19

BP-20

BP-22

BP-21

BP-23

BP-24

BP-25BP-26

BP-27

BP-28

BP-29BP-30

BP-31

BP-32

BP-33

BP-34BP-35

BP-36BP-37

Scale 1:200050040030020010040 60 80200

N

Certified that "the plans & sections are preparedbased on lease map authenticated by state Govt."

97.2

DUMP106

104

102.1

100.0

96.0

96.0

PRODUCTION PLAN FOR 2019-20YEARLY DEVELOPMENT &

INDEX

MIING LEASE BOUNDARY

QUARRY

ROAD

KULAM / KUTTAI

CART TRACK

ODAI

BURIAL GROUND

DIP & STRIKE

ULTIMATE PIT LIMIT

+ + ++ +

DUMP YARD

HAUL ROAD

CONTOUR LINE96m

LIMESTONE

2019- 20 Year Programme

Proposed Dumping area

Proposed Dumping Area

96.0

92.0

88.0

84.0

80.0

76.0

72.0

68.0

64.0

93.094.095.0

63.062.061.0

100.0

102.0

59.0

57.0

55.0

104.0

106.0

102.0

102.0

0.0 200 400 600 800 1000 1200

96.0

92.0

88.0

84.0

80.0

76.0

72.0

68.0

64.0

93.094.095.0

63.062.061.0

100.0

102.0

59.0

57.0

55.0

104.0

106.0

102.0

102.0

C C'

UPLUPLMLB

88.5 81.5

100.

2

91.5 84

.5

99

90.5

83.5

100

91.5

84.5

97.0

88.5

81.5

20.40

30.0

30.0

96.0

92.0

88.0

84.0

80.0

76.0

72.0

68.0

64.0

93.094.095.0

100.0

102.0

0.0 200 400 600 800

96.0

92.0

88.0

84.0

80.0

76.0

72.0

68.0

64.0

93.094.095.0

100.0

102.0

DD'UPLMLB UPL MLB

Section along C - C'

Section along D - D'

Proposed Dumping area

Qualified Person

Page 81: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

102m

104m

104m

102m

98m

96m

96m

94m

98m

102m

100m

98m

96m

94m

92m

92m

100m

102m

OFFICE

100m

98m

+

96m

++

+ ++

+ ++

94m

92m

92m

94m

100m

AGD-24105.745

TO

CHO

LAN

KURI

CHI

TO IRUMBILIKURICHI

AGD-25107.00

TO IRUMBILIK

URICHI

Applicant:

Scale 1:2000 SAI GEOSURVEY CONSULTANT

B.GANGATHARAN

TAMILNADU CEMENTS CORPORATION LTD.,

ARIYALUR WORKS

ANANDAVADI LIMESTONE MINES

PLATE NO: 8

A'

A

GO.No.624, dt.23.09.98

IDAYANKULAM

E 0 E 200 E 400 E 600 E 800 E 1000N 0

N 200

N 400

N 600

N 800

N 1000

N 1200

N 1400

N 1600

N 1800

N 2000

BP-1

BP-2

BP-3

BP-4

BP-5

BP-6

BP-7

BP-8 BP-9

BP-10

BP-11

BP-12BP-13 BP-14

BP-15

BP-16BP-17

BP-18BP-19

BP-20

BP-22

BP-21

BP-23

BP-24

BP-25BP-26

BP-27

BP-28

BP-29BP-30

BP-31

BP-32

BP-33

BP-34BP-35

BP-36BP-37

Scale 1:200050040030020010040 60 80200

N

Certified that "the plans & sections are preparedbased on lease map authenticated by state Govt."

97.2

DUMP106

104

102.1

100.0

96.0

96.0

PRODUCTION PLAN FOR 2020-21YEARLY DEVELOPMENT &

INDEX

MIING LEASE BOUNDARY

QUARRY

ROAD

KULAM / KUTTAI

CART TRACK

ODAI

BURIAL GROUND

DIP & STRIKE

ULTIMATE PIT LIMIT

+ + ++ +

DUMP YARD

HAUL ROAD

CONTOUR LINE96m

LIMESTONE

2020- 21 Year Programme

Proposed Dumping area

Proposed Dumping Area

88.5 81.5

100.

2

91.5 84

.5

99

90.5

83.5

100

91.5

84.5

97.0

88.5

81.5

Proposed Dumping area

Qualified Person

91

82.5

75.5

9485.5

78.5

F

F'

82.5

76.5

79

79.5

74.5

96.0

92.0

88.0

84.0

80.0

76.0

93.094.095.0

100.0

102.0

96.0

92.0

88.0

84.0

80.0

76.0

93.094.095.0

100.0

102.0

0.0 200 400 600 800

Section along F - F'

F F'

( 111 )

( 221 )( 221 )

UPLMLB UPL MLB

Page 82: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

102m

104m

104m

102m

98m

96m

96m

94m

98m

102m

100m

98m

96m

94m

92m

92m

100m

102m

KOVIL

OFFICE

100m

98mKOVIL

+

96m

++

+ +++ ++

94m

92m

92m

94m

100m

TO

CHO

LAN

KURI

CHI

TO IRUMBILIKURICHI

TO IRUMBILIKURICHI

INDEX

MIING LEASE BOUNDARY

ROAD

KULAM / KUTTAI

CART TRACK

ODAI

BURIAL GROUND

ULTIMATE PIT LIMIT

+ + ++ +

DUMP YARD

HAUL ROAD

Applicant:

Scale 1:5000 SAI GEOSURVEY CONSULTANT

RQP/MAS/120/98-AB.GANGATHARAN

TAMILNADU CEMENTS CORPORATION LTD.,

ARIYALUR WORKS

ANANDAVADI LIMESTONE MINES

PLATE NO:9

ENVIRONMENT PLAN

CONTOUR LINE96m

97.0

99.0

RESE

RVED

FO

REST

LA

ND

WA

STE

DRY

LA

ND

WASTE DRY LA

ND

WASTE DRY LAND

SW

NENE

GO.No.624, dt.23.09.98

GCP-3

GCP-2

GCP-1

IDAYANKULAM

E 0 E 200 E 400 E 600 E 800 E 1000N 0

N 200

N 400

N 600

N 800

N 1000

N 1200

N 1400

N 1600

N 1800

N 2000

WASTE DRY LAND

WA

STE

DRY

LA

ND

WASTE DRY LAND

500 M

500 M

60 M ZONE AREA

500 M ZONE AREA

BURIAL GROUND

E 0 E 200 E 400 E 600 E 800 E 1000N 0

N 200

N 400

N 600

N 800

N 1000

N 1200

N 1400

N 1600

N 1800

N 2000

Eaucalyptus plants by TNPL

WIND DIREC

TION

WIND DIREC

TION

N

Population Distance Direction

4637 1.4 km SW2761 3.1 km SE3253 3.9 km NE2679 2.6 km NW

2798 3.0 km NW

SenduraiMaruvatturPeriakurichiNakkambadiVanjinapuram

Village

Certified that "the plans & sections are preparedbased on lease map authenticated by state Govt."

Vegetation area within 60m

60M

RA

DIU

S

60M RA

DIUS

Pit No. 1

100.2

101.5

99.0

98.1

94.5 88.5

100.299.5

94.5

93.5

87.5

99.2

94.5

99.2

97.2

90.5

84.5

98.0

91.0

85.0

96.0

90

DUMP

106

104

102.1

100.0

96.0

96.0

Page 83: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

102m

104m

104m

102m

98m

96m

96m

94m

98m

102m

100m

98m

96m

94m

92m

92m

100m

102m

OFFICE

100m

98m

+

96m

++

+ ++

+ ++

94m

92m

92m

94m

100m

AGD-24105.745

TO

CHO

LAN

KURI

CHI

TO IRUMBILIKURICHI

AGD-25107.00

TO IRUMBILIK

URICHI

Applicant:

Scale 1:2000 SAI GEOSURVEY CONSULTANT

B.GANGATHARAN

TAMILNADU CEMENTS CORPORATION LTD.,

ARIYALUR WORKS

ANANDAVADI LIMESTONE MINES

PLATE NO: 10

A'

A

GO.No.624, dt.23.09.98

IDAYANKULAM

E 0 E 200 E 400 E 600 E 800 E 1000N 0

N 200

N 400

N 600

N 800

N 1000

N 1200

N 1400

N 1600

N 1800

N 2000

BP-1

BP-2

BP-3

BP-4

BP-5

BP-6

BP-7

BP-8 BP-9

BP-10

BP-11

BP-12BP-13 BP-14

BP-15

BP-16BP-17

BP-18BP-19

BP-20

BP-22

BP-21

BP-23

BP-24

BP-25BP-26

BP-27

BP-28

BP-29BP-30

BP-31

BP-32

BP-33

BP-34BP-35

BP-36BP-37

Scale 1:200050040030020010040 60 80200

N

Certified that "the plans & sections are preparedbased on lease map authenticated by state Govt."

97.2

DUMP106

104

102.1

100.0

96.0

96.0

INDEX

MIING LEASE BOUNDARY

QUARRY

ROAD

KULAM / KUTTAI

CART TRACK

ODAI

BURIAL GROUND

DIP & STRIKE

ULTIMATE PIT LIMIT

+ + ++ +

DUMP YARD

HAUL ROAD

CONTOUR LINE96m

LIMESTONE

Proposed Dumping area

Proposed Dumping Area

88.5 81.5

100.

2

91.5 84

.5

99

90.5

83.5

100

91.5

84.5

97.0

88.581.5

Proposed Dumping area

Qualified Person

91

82.5

75.5

9485.5

78.5

82.5

76.5

79

79.5

74.5

FINANCIAL AREA ASSURANC PLAN

GREENBELT DEVELOPMENT AREA

5th YEAR PIT LIMIT

Page 84: MODIFICATIONS TO THE APPROVED MINING PLAN …environmentclearance.nic.in/writereaddata/Online/TOR/05... · 2018. 6. 5. · Modifications to the Approved Mining Plan of Anandavadi

102m

104m

104m

102m

98m

94m

98m

102m

100m

98m

96m

94m

92m

92m

100m

102m

KOVIL

OFFICE

100m

98mKOVIL

+

96m

++

+ +++ ++

94m

92m

92m

100m

TO

CHO

LAN

KURI

CHI

TO IRUMBILIKURICHI

TO IRUMBILIK

URICHI

INDEX

MIING LEASE BOUNDARY

QUARRY

ROAD

KULAM / KUTTAI

CART TRACK

ODAI

BURIAL GROUND

ULTIMATE PIT LIMIT

+ + ++ +

HAUL ROAD

Applicant:

SAI GEOSURVEY CONSULTANT

B.GANGATHARAN

TAMILNADU CEMENTS CORPORATION LTD.,

ARIYALUR WORKS

ANANDAVADI LIMESTONE MINES

CONCEPTUAL PLAN & SECTIONS

CONTOUR LINE96m

97.0

RESE

RVED

FO

REST

LA

ND

WA

STE

DRY

LA

ND

WASTE DRY LA

ND

WASTE DRY LAND

X X'

A'A

YY'

BB'

85

65

55

75

95100

XWEST

X'

85

65

55

75

95100

EAST

37.0254

21.6759

85

65

55

75

95100

YSOUTH

Y'

85

65

55

75

95100

NORTH

PLATE NO:11

GO.No.624, dt.23.09.98

Scale 1:2000

IDAYANKULAM

E 0 E 200 E 400 E 600 E 800 E 1000N 0

N 200

N 400

N 600

N 800

N 1000

N 1200

N 1400

N 1600

N 1800

N 2000

N

Certified that "the plans & sections are preparedbased on lease map authenticated by state Govt."

GREEN BELT DEVELOPMENT AREA

5TH YEAR PIT LIMIT

PIT LIMIT A

T THE END OF L

IFE OF M

INE

PIT LIMIT AT THE END OF LIFE OF MINE

ACTIVE TOP SOIL DUMP100 x 25 x 3m

99.4

99.1

ACTIVE TOP SOIL DUMP YARD

PROPOSED WASTE DUMP YARD

PROPOSED WASTE DUMP

PROPOSED WASTE DUMP

PROPOSED WASTE DUMP

SANDSTONE

SECTION ALONG Y -Y'

SECTION ALONG X -X'

UPL

ML

UPL

ML

UPL

ML

UPL

ML

UPL

UPL

Proposed Waste dump

Qualified Person