Upload
engr-saleem-chandio
View
215
Download
0
Embed Size (px)
Citation preview
7/28/2019 Model Question Paper - I - Or - 5TH SEM
http://slidepdf.com/reader/full/model-question-paper-i-or-5th-sem 1/7
M.S. RAMAIAH INSTITUTE OF TECHNOLOGY, BANGALORE – 54(Autonomous Institute, Affiliated to VTU)
DEPARTMENT OF INDUSTRIAL ENGINEERING AND MANAGEMENT
MODEL QUESTION PAPER – 1
OPERATIONS RESEARCH – IM504Time: 3 hrs Max.
Marks: 100
NOTE: 1) PART A is Compulsory2) PART B Answer five full questions choosing one from
each unit
PART – A
1) The mathematical technique for finding the best use of limited resourcesin an optimum
manner is known as
(a) Operations Research (b) Linear Programming (c) Network Analysis (d)Queuing Theory
2) A linear programming problem is called so, because in that problem(a) all the functions expressing the constraints are linear (b) the
objective functionshould also be linear (c) both (a) & (b) above (d) none of the
above.
3) Linear programming can be applied to(a) steel industry (b) oil industry (c) chemical industry (d) all of the above
4) In the graphical method of linear programming problem, every corner of the feasible polygon
indicates(a)a basic feasible solution (b) optimum solution (c) both (a) & (b) above(d) none of the above.
5) In canonical form of linear programming model(a) all the inequalities indicating the constraints are in the same manner
(b) the right-handside of the inequation are constraints (c) all the variables are non-
negative(d) all of the above
6) The simplex method is the basic method for(a) value analysis (b) operations research (c) linear programming (d)
model analysis
7) In the simplex method, the variables which have not been assigned thevalue zero, during an
iteration, are called as
7/28/2019 Model Question Paper - I - Or - 5TH SEM
http://slidepdf.com/reader/full/model-question-paper-i-or-5th-sem 2/7
(a)basic variable (b) artificial variable (c) slack variable (d) none of theabove.
8) A basic feasible solution in simplex method is one, when(a) all the decision variables are in the base (b) all the decision variables
and surplus variablesare assigned zero values (c) all the base variables are non – negative (d)
all the base variables
satisfy the constraint equations.
9) Graphical method, simplex method and transportation method areconcerned with
(a) value analysis (b) linear programming (c) break-even analysis (d)queuing theory
2
10) Artificial variable is introduced in the simplex method to(a) determine the IBFS, when surplus variable is present (b) convert the
inequation with the
sign greater than or equal to, in the form of an equation (c) apply Big- Mmethod for
solution to LPP (d) indicate the sensitivity of surplus variable.
11) Dual of the dual is the(a) dual (b) primal (c) either dual or primal (d) none of the above
12) At the optimum level (i.e., final iteration) the values of the slack variablesin the primals are
(a) positive (b) negative (c) zero (d) none of the above
13) In transportation problem, during an iteration, the total no. of allocationshould not be
more than(a)m + n (b) m + n + 1 (c) m + n – 1 (d) m – n – 1
14) The IBFS can be determined by the application of (a) northwest corner method (b) least cost method (c) vogel’s
approximation method(d) all the above
15) Optimality is reached when all the index values are(a) zero (b) negative (c) positive (d) none of the above
16) In assignment model(a) degeneracy always present in all the problems (b) no. of resources is
equal to no. of jobs(c) only one unit of the ith source can be assigned to any one of its
destinations(d) all the above
7/28/2019 Model Question Paper - I - Or - 5TH SEM
http://slidepdf.com/reader/full/model-question-paper-i-or-5th-sem 3/7
17) In an n x n matrix of an assignment problem, the optimality is reachedwhen the minimum
number of straight lines scoring all the zeros is(a)n2 (b) 1 / n (c) n (d) none of the above
18) In pert network, some times dummy activities are introduced to(a) prevent cycling of network (b) maintain network logic of precedence
(c) avoid crossing of
activities in the network (d) have an activity with zero duration of time
19) A pert activity has an optimistic tie of 3 days, pessimistic time of 15 daysand the expected
time is 7 days. The most likely time of the activity is(a)5 days (b) 6 days (c) 7 days (d) 9 days
20) The estimated duration of times for an activity, in the PERT networkunder the worst and
best environment are 9 days and 3 days. The variance of this activity is(a)6 days (b) 1 day (c) 2 days (d) none of the above
21) In a M/M/1 Queue, the service rate is(a) poisson (b) exponential (c) linear (d) none of the above
3
22) M/M/1 model is(a) a single channel & single service unit (b) a “First come, First serve
basis”(c) a system having probability distribution independent of time (d) all of
the above
23) Queue length (Lq) is equal to
(a)ς
ς
−1(b)
ς
ς
−1
2
(c) )1(
1
ς
ς
λ −
(d) )1(
1
ς
ς
− M
24) A situation is termed as competitive situation when(a) the action of one depends on the action of the other (b) the action of
one does notdepend on the action of the other (c) the action of one does not follow
any logic(d) none of the above
25) A pay-off, which is an outcome of all combination of courses of action is(a) positive (b) negative (c) zero (d) all of the above
PART – B
UNIT – I
1 a) What is OR? Describe briefly its applications.5
7/28/2019 Model Question Paper - I - Or - 5TH SEM
http://slidepdf.com/reader/full/model-question-paper-i-or-5th-sem 4/7
b) The manager of an oil refinery has to decide upon the optimal mix of 2possible blending
processes of which the inputs and outputs per production run are asfollows 10
Input OutputProcess Crude A Crude B Gasoline X Gasoline Y
1 5 3 5 82 4 5 4 4
The maximum amounts available of Crude A & B are 200 units and 150units
respectively. Market requirements shows that at least 100 units of gasoline X and 80
units of gasoline must be produced. Profits per production run fromprocess 1 & process
2 are Rs.30 & Rs.40 respectively. Formulate the LPP & solve itgraphically.
2 a) List and explain the important phases of OR study.6
b) Solve the following LPP graphically9
Maximize Z = 2x1 + x2
Subject to x2 ≤ 102x1 + x2 ≤ 60
x1 + x2 ≤ 183x1 + x2 ≤ 44x1, x2 ≥ 0
4
UNIT – II
3) Solve the following LPP by Simplex method15
Maximize Z = 5x1 + 2x2 + 10x3
Subject to x1 – x3 ≤ 10x2 – 3x3 ≥ 10x1 + x2 + x3 ≤ 10
x1, x2, x3 ≥ 0
4) Solve the following LPP by using the dual simplex method15
Maximize Z = 6x1 + 7x2 + 3x3 + 5x4
Subject to 5x1 + 6x2 – 3x3 + 4x4 ≥ 12x2 + 5x3 - 6x4 ≥ 102x1 + 5x2 + x3 + x4 ≥ 8
x1, x2, x3, x4 ≥ 0
7/28/2019 Model Question Paper - I - Or - 5TH SEM
http://slidepdf.com/reader/full/model-question-paper-i-or-5th-sem 5/7
UNIT – III
5 a) What are the rules to determine degeneracy?3
b) Freshwater is supplied through 3 reservoirs with daily supply capacities of 15,20 & 25 million ltrs
of water respectively. On each day supply must be provided for 4 cities A, B, C& D whose demands
are 8, 10, 12 & 15 million litres respectively whose costs are given below:12
Cities
A B C D1 2 3 4 5
Reservoirs 2 3 2 5 2
3 4 1 5 2
Use the transportation algorithm to determine the cheapest pumping
schedule, if excesswater can be disposed of at no cost.
6) A firm produces a component and distributes them to 5 wholesalers at afixed price of Rs.
10/unit. Sales forecast indicate that monthly demand will be 3,000, 3,000,1,000, 5,000 and 4,000 units at wholesale dealers a, b, c, d & e
respectively. The monthlyproduction capacities are 5,000, 1,000 & 10,000 at plants A, B & C
respectively. Theproduction costs are Rs. 2, Rs. 1 & Rs. 3 at plants A, B & C respectively.
The unittransportation cost in rupees between the plants and wholesalers are
given in the followingtable
15
WholesalesPlants a b c d e
A 0.5 0.5 1.0 1.5 1.5B 1.0 0.5 1.0 1.0 1.5
C 1.0 1.0 0.5 1.5 1.0Determine the transportation schedule between plants and wholesalers
in order tomaximize the total profit per month. Use VAM to obtain the IBFS.
5
UNIT – IV
7 a) The owner of a machine shop has 4 machinists available to assign to jobs for that day. Five
7/28/2019 Model Question Paper - I - Or - 5TH SEM
http://slidepdf.com/reader/full/model-question-paper-i-or-5th-sem 6/7
jobs are offered with expected profit for each machinist on each job asfollows 9
A B C D E
1 60 76 48 99 802 69 82 59 71 573 85 90 109 69 79
4 46 62 85 75 78
Determine the optimum assignment schedule. Which job should bedeclined?b) The following table gives the activities of a construction project and otherrelevant
information10
Activity 1 – 2 1 – 3 2 – 3 2 – 4 3 – 4 4 – 5
Duration 20 25 10 12 6 10
(i) Draw the network for the project (ii) Find critical path
8) The following table lists the jobs of a network along with their timeestimates 15
Duration in days Jobs
Optimistic Most likely Pessimistic
1 – 2 3 6 152 – 3 6 12 302 – 4 5 11 173 – 4 3 9 273 – 5 1 4 75 – 6 2 5 83 – 6 4 19 284 – 6 2 5 14
(i) Draw the network and calculate the length and variance of criticalpath
(ii) What is the probability that jobs on critical path will be completedby the due date of 40 days?
(iii) What is your estimate of the probability that the entire project willbe completed by the due date?
7/28/2019 Model Question Paper - I - Or - 5TH SEM
http://slidepdf.com/reader/full/model-question-paper-i-or-5th-sem 7/7
6
UNIT – V
9 a) Explain Kendal – lee notation for M/M/1 Model3
b) The arrival of customers at a banking counter follows poissondistribution with a mean of
45 per hour12
(i) What is the probability of having zero customer in the system (Po)?(ii) What is the probability of having 5 customers in the system?
Probability of having 10customers in the system.
(iii) Determine the steady state performance statistics, namely, Ls, Lq, Ws
& Wq?
10 a) Define the following
3 (a) Saddle Point (b) Fair gameb) The following matrix represents the payoff to P1 in a rectangular game
between twopersons P1 & P2
12
8 15 - 4 - 219 15 17 160 20 15 5
By the notion of dominance, reduce the game to 2 x 4 game & thensolve it graphically.