Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
PRE-FEASIBILITY REPORT (As per Ministry of Environment and Forests Letter dated: 30-12-2010)
1. Executive Summary
Rajasthan State Mines & Minerals Limited (RSMML) engaged in
production of lignite from our existing Sonari Lignite Mines
(rated capacity of 1 MTPA) situated near village Sonari, Tehsil &
District Barmer, State Rajasthan.
This lignite block was allocated by Ministry of Coal ,Govt. of
India, New Delhi vide letter no. 48024/1/98-Lig. Dated
06.09.2004.
As per provisions of EIA notification 14 Sept, 2006 and
subsequent amendments, earlier EC was granted vide letter dated
17.07.2007 under section 12 of EIA Notification, 2006 and
subsequent amendments thereto and under para 2.1.1 of MoEF
Circular dated 13.10.2006 & In response to our application of
Consent to Operate, dated 30.01.2018, RSPCB vide its letter dated
31.05.2018 has informed us that our application has been kept
pending in view of the MoEF & CC Notification dated
06.04.2018. Further, pending clarification from MoEF & CC/
RSPCB with regards to validity of the existing EC and
applicability & provisions of MoEF & CC Notification dated
06.04.2018, project proponent is filing Form I & Pre- feasibility
Report for determination of ToR for Environmental studies.
Lease area is falls on Survey of India, toposheet No.- 40N/8, 40
O/5 & Mining area is located between Latitudes N 25° 57' 09” to
E 26° 00' 29” Longitudes N 71° 15' 42” to E 71° 17'14”. (Ref. Plate
2- Key Plan).
Sonari Block is approachable by tar road (about 6 km) from vishala
Village. Vishala is approachable from NH 15 (Harsani Phata) 15
kms and Harsani phata to Barmer town about 9 kms by National
Highway no. 15 joining Kandla port (in South) and Shri-
Ganganagar (in North). Barmer is the nearest Railway station; a
broad gauge track of Northern-Western Railway, Jodhpur is the
nearest Airport 200 km due east of Barmer town. Barmer town is
located at about 30 km from mines site.
Barmer is nearest railway station 30 kms./ Jodhpur is the nearest
Airport 200 km. Key Plan of the Sonari Lignite Mines is enclosed
(Plate-2)
The mining area spreads in an area of 1512.50 ha. , No forest land
is in ML area. Lease area of the mine is 1512.50 ha. About 1203.06
ha of land belongs to private khatedars includes un-irrigated
agriculture land , Govt. waste land is 226.41 ha, Govt. grazing land
73.87 ha & others land like village area etc 9.16 ha.(Aabadi land)
The Mining plan has been prepared with a entire mine life for a
peak rated capacity of 1.0 MTPA and same was approved by MoC
on dated 16 Jan. 2006.
In course of mining 60.00 Mm3 of overburden (including 0.74
Mm3 of top soil, 0.4 Mm3 as per plan) was generated up to first 5
years & 589.5 Mm3 generated in entire mine life, Out of this
20.40 Mm3 (including 0.74 Mm3 of top soil) has stacked in
external dump and balance 569.10 Mm3 is to be used to backfill
the de-coaled area.
At the end of mining operation land degraded on account of
mining & overburden dumping, will be reclaimed. This includes
800 ha for mining and 90 ha. External dump & 775 ha of internal
dump. Plantation would be raised over reclaimed area (775 ha.).
Total water requirement for mine site has been assessed as 198 m3
/day. This includes 150 m3/day for potable purposes & 48 m3/day
for industrial purposes. Presently the water is supplied to the mine
from Giral overhead tank of RSMM, which receives water
supplies from Nimla located at 7 km from the mine, where RSMM
has tube well to tap groundwater with permission from PHED. In
future the water requirement will be met from water reservoir of
Giral thermal power plant located at a distance of 9 km through
pipe line. The water supply to Giral TPP comes from IGNP.
Run of mine directly loaded into trucks and transported to linked
to Thermal power Plant of M/s RVUNL- Unit –2 capacity 125
MW at village Giral.
2. Introduction of the project Background information
i. Identification of project
and project proponent. In
case of mining project, a
copy of mining lease/letter
of intent should be given.
This lignite block was allocated by Ministry of Coal ,Govt. of
India, New Delhi vide letter no. 48024/1/98-Lig. Dated
06.09.2004.Annexure –I.
Name of the project: Sonari Lignite Mines Village: Sonari, Tehsil
& District: Barmer, Rajasthan.
Project Proponent: Rajasthan State Mines & Mineral Limited (A
Government of Rajasthan Enterprise).
Rajasthan State Mines & Minerals Limited (RSMML) is one of the
premier public sector enterprises of the Government of Rajasthan,
primarily engaged in mining and marketing of industrial minerals
in the State.
Address: Registered office : Rajasthan State Mines & Minerals Limited
C-89-90, Janpath, Lal Kothi Scheme,
Jaipur-302015 Rajasthan. Email: [email protected]
SBU & PC –Lignite Office : Rajasthan State Mines & Minerals Limited
KHANIJ BHAWAN, TILAK MARG
‘C’ SCHEME, JAIPUR- 302005
RSMML presently operates three Lignite Mines, namely:
1. Giral Lignite Mine , Distt. Barmer , 1.0 MTPA , linked to
Thermal power Plant of M/s RVUNL- Unit-1, capacity 125
MW at village Giral.
2. Kasnau-Matasukh Lignite Mine, Distt. Nagaur, 1.0 MTPA,
linked to mercantile usage by industries.
ii. Brief description of
nature of the project.
Lignite is the only solid fossil fuel available in the State and it is
prudent to utilize this potential to the best advantage. After
analyzing various factors like lignite availability, transport
facilities, cost and quality parameters revealed that lignite based
power generation offers the most economical option for meeting
the power demand in Rajasthan. Lignite is brownish-black in
color and has a carbon content of around 23-29%, a high inherent
moisture content sometimes as high as 38.7%, and an ash content
ranging from 15% to 18%. Lignite, often referred to as brown
coal, is a soft brown fuel with characteristics that put it
somewhere. Lignite has a high content of volatile matter which
makes it easier to convert into gas and liquid petroleum products
than higher ranking coals. Lignite can be separated into two types.
The first is lignite or fossil wood and the second form is the
compact lignite or perfect lignite. The lignite is multi-seam
deposit and split into 6 to 8 sub seams.
Exploration :
Sonari Lignite block is explored by DMG/MECL respectively as
under:
Details of drilling carried out by above agencies are as under :
Block Period of
Expln.
BH’s Meterage
(m)
Exploration
agencies
Sonari 1992 47
5813.30 MECL
Sonari 2004 12 1717.30 MECL
Total 59 7530.60
Block Period of Expln. Agency
Sonari Commenced on dated
24th December 1992
Mineral
Exploration
Corporation
Limited
Exploration report of above blocks was obtained from NLC.
No. of boreholes drilled within the mining lease area are 59 with
overall borehole density of 3.9/Sq.km. Grid pattern in is 400 m x
400 m & 200m x 200 m in part.
Details of overburden, inter-burden, cumulative thickness of O.B.
(overburden + inter-burden) and thickness of lignite seam are as under :
Thickness of Overburden
Thickness of inter-burden
Thickness of Lignite Seam
Cumulative Thickness of Lignite Seam
Thickness of OB & IB
Thickness (in meter)
Minimum 12
Maximum 172
Average 92
Thickness (in meter)
Minimum 0
Maximum 55.45
Average 28
Thickness (in meter)
Minimum 0.05
Maximum 1.80
Average 0.92
Thickness (in meter)
Minimum 0.8
Maximum 12.8
Average 6.8
Thickness (in meter)
Minimum 13.40
Maximum 212.00
Average 112.5
Quality:
The quality of lignite based on analysis of core samples obtained
during the exploratory drilling, the average quality of Lignite
available in this deposit are given below:
Moisture % - 38.7%
Ash % - 15.47%
V.M.% - 22.8%
Fixed Carbon % - 23.9%
Sulphur % - 4%
C.V. Kcal/Kg. - 2800 to 3200
Geological reserves & Life of Project :
Geological reserves of Sonari lignite mines within the lease area
are 42.56 million tonne, out of which 29.52 million tone (upto 150
m depth) are mineable.
The mine is designed for production 1.0 million tonnes of lignite
per annum as per the end uses of the lignite mineral.
Accordingly life of mine has been worked out:-
1. Overburden excavation over the life: 589.5 million M3
2. Total extractable lignite reserves: 29.52 million tonnes
3. Initial production for the first five years: 1.93 million tonnes
4. Balance reserves after initial 5 years: 27.59 million tonnes
5. Rated mine capacity: 1.0 MT per annum.
6. Total life of the mine: 31 years.
7. The estimated capital cost of the project is Rs. 212.70 crore only.
iii. Need for the project
and its importance to
the country and or
region
iv. Demand-Supply Gap
The Rajasthan state is deficient in power generation. A large gap
exists between state level generation of power & its demand. The
state has hardly any known hydro-power potential that can be
tapped. Capacity addition from nuclear sources is bound to be
slow due to high cost and long gestation period. Under the
situation, conventional thermal power plants provide perhaps the
best option for bridging the gap. Coal based Thermal Power
Plants are less acceptable due to non-availability of coal reserves
in Rajasthan state and coal transport over long distance to
Rajasthan being difficult and costly, whereas exploitation of
available lignite deposits in Rajasthan is expected to be more
suitable.
Due to sulphur content (4%), the lignite produced from this mine
utilized by thermal power plant & industries for mercantile usage.
The lignite produced from this mine offers good sources of
employment & source of income generation for local people. This
project contributes socio-economic development of the region &
nation. The project will also contribute to economy by way of
royalty, sales tax and additional levy.
Power is the most used energy form in India. Indeed, it is the
fulcrum on which rests the future pace of growth and
development. As the tempo of development increases, the demand
for electricity also increases. Rajasthan, being a power deficit
State, can contribute to a large extent to nation in achieving self
sufficiency in power by developing new lignite mine and its
linkage to Thermal Power Plant & mercantile usage by industries.
This will reduce the gap between demand & supply of lignite to a
greater extent.
Lignite is the only solid fossil fuel available in the State and it will
be prudent to utilize this potential to the best advantage.
3. Project Description
i. Type of project
including interlinked
and interdependent
projects, if any.
The existing mine is extract lignite at the rated capacity of 1.0
MTPA. The total project area is 1512.50 ha. The mineable/
extractable reserve is 29.52 million tonnes. The lignite produced
from this mine consumed by thermal power plant & industries
for mercantile usage.
ii.Location (map showing
general location,
specific location, and
project boundary &
project site layout)
with coordinates.
Name of the project: Sonari Lignite Mines
Vill: Sonari
Tehsil : Barmer
District: Barmer
State: Rajasthan
Location map and Key plan showing lignite block area
is enclosed as Plate -1 & Plate -2.
Mining lease area is located between Latitudes N 25° 57' 09” to
E 26° 00' 29” Longitudes N 71° 15' 42” to E 71° 17'14”.
Lease area of the mine is falls on Survey of India, toposheet
40N/8, 40 O/5.
v. Imports vs. Indigenous
production
vi. Export Possibility
vii.Domestic/export
Markets
In order to avoid import of coal for thermal power station &
mercantile usage by industries, the existing mine is to bridge the
gap between demand & supply.
No export of Lignite is envisaged from this mine. The lignite
produced from this mine has consumed by thermal power plant &
industries for mercantile usage. So, there is no possibility of export
of lignite produced from the mine.
There is no any export from the mine as the entire lignite
consumed in thermal power plant & industries for mercantile
usage.
iii. Details of alternate
sites considered and
the basis of selecting
the proposed site,
particularly the
environmental
considerations gone
into should be
highlighted.
Mining activities has been carried out based on local geology and
availability of the mineral.
Mining is carried out by mechanized open cast mining method
using conventional mining equipments such as hydraulic
excavators / shovel in combination with matching capacity
dumpers along with ancillary equipments such as dozers, road
grader etc.
Blasting is not required, as the OB strata are soft in nature.
iv. Size or magnitude of
operation.
The total production in the first five years 1.93 million tonnes. The
targeted production is 1.0 Million tonne per annum. The lignite
extracted for the five years has been 1.93 million tonnes and
overburden removed including top soil has been 20.40 million
M3.
v. Project description
with process details
(a schematic diagram,
flow chart showing
the project layout,
components of the
project etc. should be
given)
Sonari Lignite Mines spreads in an area of 1512.50 ha. Area is
mostly barren, with a flat terrain and is covered with sandy and
rocky fragments with negligible soil cover and minor undulations.
Higher elevations are observed in the south-eastern, central and
north-western parts of the area separated by low lying flat area. The
altitude in the area ranges from 197 to 205 m. Sand dunes of low
relief are observed on the eastern side of lease area.
The average elevation of the area varies from 197 m to 205 m
above MSL.
Sequence of mining :
There is first open up the mine by constructing an Initial Mining
Cut (IMC) near South-West of ML boundary. The lignite seam
touched at a depth of 44 m from the surface.
Method of mining:
Mining is carried out by mechanized open cast mining method
using conventional mining equipments such as hydraulic
excavators / shovel in combination with matching capacity
dumpers along with ancillary equipments such as dozers, road
grader etc. Since the over burden strata is soft in nature, hence it
does not require any blasting and can be easily excavated by
hydraulic excavators. The open cast working was carried out by
forming suitable size benches of 3 m in height and final width
around 6 m during the working of the pit. However, the
progressive bench width of 9 m. But the ultimate dimension of the
benches kept as 3 m in height, 6 m width, with 700 bench face
slope & over all pit slope angle of 220 56’ say 230).
The proposed production of lignite and generation of
overburden for Sonari mines is as under:
Year Lignite in lakh
tonnes
OB in lakh m3 Stripping
ratio
Phase – I
1 year 0.0 50 -
2 year 5.0 100 1:20
3 year 10.0 150 1:15
4 year 10.0 150 1:15
5 year 10.0 150 1:15
Sub total 35.00 600 17.14
6-10 year 50.0 900 1:18
11-15 year 50.0 900 1:18
Total 135.0 2400.0 17.78
Phase –II
16-20 year 50.0 1100 1:22
21-25 year 50.0 1100 1:22
26-31 year 60.20 1295 1:21.57
Grand total 295.20 5895.0 1:19.97
vi. Raw material required
along with estimated
quantity, likely source,
marketing area of final
products, Mode of
transport of raw Material
and Finished Product.
vii. Resource optimization
/ recycling and reuse
envisaged in the project,
if any, should be briefly
outlined.
The mining is carried out by mechanized open cast mining method
by using conventional mining machinery (HEMM) using a
combination of hydraulic shovels (excavator) and dumper
combination in association with ancillary equipments like dozer,
motor grader, water sprinkler, fuel browser etc.
Marketing area of final product:
Total quantity of production has been supplied to thermal power
plant & consuming industries.
Mode of Transportation of Finished Product (Lignite):
The lignite produced from the mine has been directly loaded into
dumper & trucks for transportation to thermal power plant
consuming industries respectively.
Lignite being soft in nature can be easily excavated with the help
of hydraulic excavator without using blasting technique.
The total OB/ waste (alluvium/ soil) generated, used in
backfilling in the worked out area simultaneously. During the
first three years of mining OB is dumped outside. However from
3th year onward, the overburden so generated was backfilled in
the void created in the mining pit.
No processing / beneficiation of the mineral “Lignite” are
envisaged. The resources which are used in the mining are
recycled by various methods. Spent oil from transformers, once
in one or two years will be sold to the authorized vendors.
viii. Availability of water
its source,
Energy/power
requirement and
source should be
given.
Water :
The drinking water as well industrial consumption is sourced from
Public Health Engineering Department of Rajasthan State.
The total requirement of water and sewage generation would be
as under:
Sl.
No.
Use Water requirement
m3 / day
1. Labour at mine site 18
2. Population in project colony 150
3. Dust suppression & green
belt development
30
Total 198
Power:
There is 11 KV overhead transmission line from nearby grid
substation of Rajasthan Vidhyut Vitran Nigam, to the mines
substation is located near mines. 85 KW power used per day.
ix. Quantity of wastes to
be generated (liquid
and solid) and
scheme for their
Management/
disposal.
Solid Wastes:
Overburden management :
Overburden strata mainly consist of Sand, kankar and clay. The
overburden excavation over the life to be 589.5 Million M.3
The waste generated from the mining operations during the first
three year plan period is proposed to stack partially as out side
dump and partially in decoaled area. Outside dump is within lease
on non lignite bearing area. The total land degradation due to out
side dump is 90.00 hectare.
x.Schematic
representations of the
feasibility drawing
which give information
of EIA purpose.
Topsoil Management
The topsoil thickness in the lease hold area is approximately less
than half meter. The topsoil stacking is proposed on barren land
to be stacked separately.
Total 7.4 lac m3 of top soil was generated up to first 5 year of
mine operation. The same spread on backfilled area of 9.6 ha. The
top soil stockpiles have growth of grasses to preserve the soil
fertility. The grass will serve as an excellent binder and would
control soil erosion from the top soil stack pile, till it is reused as
a cover material at overburden disposal sites. These include its
use for growing plants along the fringes of the site, roads and
reclamation of backfilled and external dump areas.
No liquid effluents generated due to the proposed mining activity.
As per Terms of Reference (TOR), all the conditions mentioned
will be fulfilled and incorporated in the EIA report.
4. Site Analysis
i. Connectivity. Sonari Block is approachable by tar road (about 6 km) from
vishala Village Vishala is approachable from NH 15 (Harsani
Phata) 15 kms and Harsani phata to Barmer town about 9 kms by
National Highway no. 15 joining Kandla port (in South) and Shri-
Ganganagar (in North). Barmer is the nearest Railway station; a
broad gauge track of Northern-Western Railway, Jodhpur is the
nearest Airport 200 km due east of Barmer town. Barmer town is
located at about 30 km from mines site.
The nearest railway station Barmer, is about 30 Km from the
mines.
Jodhpur is the nearest Airport 200 km from Barmer town.
ii. Land Form, Land use
and Land ownership.
PRE-MINING LAND USE:
Sl.
No.
Description Area (ha.)
1 Excavation Area 93.50
2 Top soil dump 9.6
3 OB Dump area* 90.00
4 Contractor Camp & Diesel
Pump Station
2.08
5 Mines Office 0.42
Sub Total (1-5) 195.60
6 Undisturbed area 1316.90
Total 1512.5
The Proposed land use at mine closure stage will be as follows:
Sl.
No.
Particulars of area to be
used for various purposes
Area
(Ha.)
1. Excavation 800.0
2. Storage of top soil 9.60
3. OB Dump 90.00
4. Infrastructure 1.5
5. Green belt 60.0
6. Undisturbed area 551.40
Total 1512.5
No forest land is in ML area. Lease area of the mine is 1512.50 ha.
About 1203.06 ha of land belongs to private khatedars includes un-
irrigated agriculture land , Govt. waste land is 226.41 ha, Govt.
grazing land 73.87 ha & others land like village area etc 9.16
ha.(Aabadi land).
iii. Topography (along
with map).
Area is mostly barren, with a flat terrain and is covered with sandy
and rocky fragments with negligible soil cover and minor
undulations. Higher elevations are observed in the south-eastern,
central and north-western parts of the area separated by low lying
flat area. The altitude in the area ranges from 197 to 205 m. Sand
dunes of low relief are observed on the eastern side of lease area.
The altitude of the M.L. area ranges from 300 to 305 m.
iv. Existing land use
pattern (agriculture, non-
agriculture, forest, water
bodies (including area
under CRZ)), shortest
distances from the
periphery of the
project to periphery of
sanctuary, eco from the
HFL industrial area, be
given.
v. Existing Infrastructure
vi. Soil classification
Type of the land in the area is partly agriculture. Most of the area
is found with partial vegetation. After monsoon most of the area is
used for grazing and cultivation. The entire area falls under the
category of non-forest land.
There is no National Park, wildlife Sanctuary, notified Eco-
Sensitive Area within 15 Km of periphery of project area.
The type of land of core zone is tabulated below:
Sl. No. Details of land use Area in Ha.
1. Agriculture land 1203.06
2. Waste land 226.41
3. Grazing land 73.87
4. Others including village
area
9.16
Total 1512.5
There is no infrastructure in the mining lease area.
Project is covered in the alluvium soil with sand.
vii. Climatic data from
secondary sources. The climatological parameters of Barmer station reveals that the
general average day temperature varies from 10.10c to 24.70c.
However the highest temperature goes as high as 490c, whereas
lowest temperature in the winter goes down to 10.10c. Relative
humidity ranges from 24% to 27%.
The lignite deposit of Sonari is in the famous Thar desert,
Characterized by desert climate.
Rainfall
The annual rainfall is poor, the major portion of which is received
during monsoon months (July-August). Annual average rainfall
recorded is around 259.6 mm by the district Meteorological
Department, Barmer.
Humidity
The relative humidity in this area is 24-27%, except in monsoon
season.
Wind
The winds are generally moderate except from moderate to
strong during the period from May to August. The evaporation
is generally very high during summer and low in winter.
Vegetation
The area falls in the “Great Indian Thar Desert” and described
locally as “ Marusthal” due to scarcity of rainfall. The trees like
Khejri, Babul, Ker, Jal, Rohira, Phog, Bui, Ber, Akada, etc. are
found in the area. The Shrubs, bushes and herbs found in the area
are of typical xerophytes flora. Wild animal like Deer, Rabbits,
Neelgay & birds like Peacock, Peahen can also be spotted in this
area. The crop cultivated during normal monsoon are mainly
Bazara, Mung, Moth, Ganwar etc. Neither sufficient ground water
nor surface water is available hence; the area has a single crop
cultivation culture. (Rain fed).
viii. Social Infrastructure
available. Sonari lignite Mines is located in Tehsil & District- Barmer at a
distance of 30 km in South direction.
All the social infrastructural facilities like hospitals, Dispensaries,
schools, colleges, financial institutions (Banks) with ATM & etc.
are available nearby Barmer town.
5. Planning Brief
i. Planning Concept
(type of industries,
transportation etc)
Town and Planning/
Development
authority
Classification.
Mining :
The gross geological reserve from the mine is estimated as
42.56 million tonne and 29.52 million tonne mineable reserve
& Ore and OB ratio is 1:19.97.
The area does not fall under any industrial estate / industrial park
/ Special Economic Zone and in the jurisdiction of town planning
/ Development authority.
Transportation:
The lignite produce from the mine is being directly loaded into
dumpers & trucks and transported to thermal power plant &
various industries respectively by road only.
ii. Population Projection
iii. Land use planning
(breakup along with green
belt etc).
There influx of people during construction and operation stage.
About 1550 persons directly/indirectly are required for the mine
project. All the people will be sourced from neighboring villages.
LAND USE DURING MINING (AT THE END OF 5TH YEAR AND END OF MINING
OPERATION 31TH YEAR)
Sl.
No.
Description During Mining
5th Year Conceptual
(31th Year)
1. Mining /Excavation (void only) 93.5 775.00
2. External OB dumps 90.00 90.00
3. Top Soil Dump 9.60 9.60
4. Plantation/Green
belt development
4.0 60.00
5. Infrastructure :Built-up area 2.5 1.5
6. Roads 1.5 1.5
7. Water bodies : Pond 0 25.00
8. Undisturbed 1311.4 549.9 Total 1512.50 1512.50
A total mining lease area is 1512.50 ha. The entire area falls under the category of non-
forest land.
iv. Assessment of
Infrastructure
Demand (Physical &
Social).
RSMM Ltd, a Govt. of Rajasthan Enterprise operate this mine
and create infrastructure facilities. These included provisions for
roads and culverts; buildings required for non- residential; supply
of water for domestic and industrial use including water required
for dust suppression, power supply and telecommunication
system; first aid and emergency services etc.
v. Amenities / Facilities. A rest shelter with first aid kit, canteen, drinking water
arrangements, rest shelter, urinals etc facilities are provided
within ML area.
First-aid boxes is provided and maintained with specified
medicines. These are readily accessible during all working hours.
Sufficient number of toilets separate for males & females are
provided and maintained in a clean and sanitary condition at all
times.
Hospitals, school, community facilities are present in the nearby
town Barmer in buffer zone within 30 Km of lease area.
b
6.Proposed
Infrastructure
i. Industrial Area
(Processing Area)
The proposed project does not involve any processing. Out of the
1512.50 ha of the ML area, 800.00 ha is the mine area. An area of
4.0 ha is earmarked for Infrastructure facilities (non residential
building). Green belt is taken up along the project roads and in the
vacant areas wherever possible and also over existing dumps and
backfilled areas.
ii. Residential Area (Non
Processing Area)
All employees at the mines are provided accommodation at the
Barmer which is about 30.0 km from the mine site. Therefore the
provision of residential accommodation has not be required.
However, pucca dwelling structures is provided to the contractor’s
labour along with quality food, R.O water, electricity, water for
other uses etc., free of cost.
iii. Green Belt As one of the important components of EMP is greenbelt
development. The greenbelt development around and within the
mine area site undertaken to fulfill the following objectives:
- Mitigation of fugitive emissions;
- Noise control;
- Wastewater eco-environment;
- Aesthetics, and
- Optimum use of wasteland and environmental
conservation.
A total area of 60 ha is brought under greenbelt development
in the entire mine life.
The green belt initially was carried all around the project as
boundary plantation, along the approach roads as an avenue
plantation and also in the vacant places within the surface
infrastructure.
The plantation on the external OB dumps (90.00 ha.) and internal
OB dumps (775.00 ha) will be carried out stage wise, in
accordance with attaining the final profile of the dumps.
iv. Social Infrastructure The project is contributed to the social developmental and
infrastructural facilities as per CSR. Social Infrastructure facilities
available in adjoining area were cater the needs of the proposed
man power and population projection. However health care centre
& cultural centre are provided under CSR scheme under
consultation with local bodies.
v. Connectivity (Traffic
and Rail /Metro/
Water ways etc)
Road Link
Sonari Block is approachable by tar road (about 6 km) from
vishala Village. Vishala is approachable from NH 15 (Harsani
Phata) 15 kms and Harsani phata to Barmer town about 9 kms
by National Highway no. 15 joining Kandla port (in South) and
Shri-Ganganagar (in North). Barmer town is located at about 30
km from mines site.
Rail link
The Barmer is the nearest Railway station is about 30 km ; a
broad gauge track of Northern-Western Railway.
Air link
Jodhpur is the nearest Airport 200 km towards west of Barmer
town.
There is no well-developed drainage system in this area. There
is no significant surface water body like dam, lake.
vi. Drinking Water
Management (Source
water)
Presently the water is supplied to the mine from Giral overhead
tank of RSMM, which receives water supplies from Nimla located
at 7 km from the mine, where RSMM has tube well to tap
groundwater with permission from PHED. In future the water
requirement will be met from water reservoir of Giral thermal
power plant located at a distance of 9 km through pipe line. The
water supply to Giral TPP comes from IGNP.
vii. Sewerage System Sewage generated, is being channelized into septic tank followed
by soak pits. The total sewage generation is of the order of 134.3
m3/day. The same treated prior to disposal to avoid any adverse
impacts on water quality.
viii. Industrial Waste
Management
There is no industrial waste generated.
ix. Solid Waste
Management
Solid Wastes:
Top soil management
The top sand/soil is not to be mixed with the sand/clay/ formation.
The topsoil stacking is proposed on barren land to be stacked
separately. The area of top soil is 9.6 ha. It is proposed to have a
stack height of 5.0 m. with an overall natural slope angle.
Overburden management :
The waste generated from the mining operations during the first
three year plan period is proposed to stack as outside dump (30 m
height) and partially backfilled in de-coaled area. Outside dump is
proposed within lease areas on barren land covering an area of
90.00 ha.
In the first three years of mine operation, the overburden disposed
on outside dump. From the third year & onwards of mine
operations, backfilling would be done in de-coaled area.
Garland drain is proposed all around the waste dumps of adequate
size to arrest surface run off due to rain water.
x. Power Requirement &
Supply / Source
Reclamation programme :
Reclamation of mined out areas:
From 3th year onwards, the backfilling started. The reclamation
process was continuing from third year. A total area of 775.00 ha
to be reclaimed in the entire mine life, an area of 25.00 ha will
remain as pond. The depth of pond is 10 m.
Reclamation of overburden sites:
The overburden areas stabilized by growing trees and grasses. The
total overburden disposal area to be stabilized shall be 90.00 ha.
The total power requirement for the mine is 85 KW per day per day,
which is fulfill by 11 KV overhead transmission line from nearby
grid substation of Rajasthan Vidhyut Vitran Nigam to the mines
sub-station is located near mines.
In additional to this DG set is installed to provide emergency
power requirement for essential lighting in the mines, which is
required 34,000 liters of diesel per day.
7. Rehabilitation and Resettlement (R&R) Plan
i. Policy to be adopted RSMML has completed proceedings of land acquisition for
1512.50 ha. in which khadedari land has been acquired 1284.84*
ha under The Land Acquisition Act, 1894. In respect of land
compensation was paid Rs.188.42 Crore. to PAFs.
Type Acquired Area (In Ha.)
Government Land Area (Siwai Chak)
226.41
Charahgah Area
(Grazing Land)
73.87
Forest Area Nil
Other Govt. Department area Aabadi
9.16
Private land area (Khatedari Land)
1203.06*
Total Area 1512.50
*Actual land acquired 1284.84 ha, in which 1203.06 ha falling in ML area
& rest 81.78 ha falls outside lease. (for construction of office building.)
Under guidelines for Corporate Social Responsibility for Central
PSE’s , March 2010, RSMML provide following :
RSMML spend an amount of Rs. 1.25 crore on CSR activities
upto 2017-2018. The activities covered under CSR finalized in
consultation with the district administration and gram panchayats
of the project affected villages and the nearby villages.
Encourage and motivate the Gram Sabha to form co-operative
groups and for development of schemes, all technical and financial
assistance is being provided by RSMML.
We negotiate with villagers for developing local market and is
provide all financial and technical assistance.
We adopt some primary schools of the area.
Medical facilities to the villagers in the dispensary of the
Company.
(Central/ State) in
respect Of the project
affected persons
including home
oustees, land oustees
and landless laborers
(a brief outline to be
given).
8. Project Schedule & Cost Estimates
i. Likely date of start of
construction and
likely date of
completion (Time
schedule for the project
to be given).
ii. Estimated project cost
along with analysis in
terms of economic
viability of the project.
As existing mine project hence following buildings are
constructed:
Administrative office
Base camps
Time office
VT Centre
Store
Rest shelters
Pit head bath
Canteen
Dispensary
Water supply installations
Shed for DG set and electric sub-station
Workshop
Weigh bridge
(As existing mine project)
Project cost 212.70 Crore for 31 years has been computed
considering reserves of 29.52 million tonnes of Sonari Lignite
Mines supplied to thermal power plant & local industries for
mercantile usage.
Analysis of proposal (Final Recommendations)
i. Financial and social
benefits with special
emphasis on the
benefit to the local
people including tribal
population, if any, in
the area.
Direct as well as indirect employment opportunities are created.
For the mine workers, preference is given to local villagers as far
as possible. Standards of living were improved in this region due
to the existing project. Economic development of any region
depends largely upon the nature of activities undertaken in the
surrounding region. Corporate development invariably contributes
towards acceleration of the process of socio-economic upliftment
of the rural society.
Plate -1: Location map of Sonari Lignite Mines
Plate – 2 : Key Plan of Sonari Lignite Mines
Plate – 3 : Revenue Map of Sonari Lignite Mines