MINI ES Battery Base

Installation Manual MINIES-B3-R1

Page 2: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

I

Content

1. Introduction ...................................................................................................................... 1

1.1 Brief description ...................................................................................................... 1

Functions ............................................................................................................... 2

1.2 Disoperation predictable ................................................................................. 2

1.3 About this manual ................................................................................................... 2

Declaration ............................................................................................................ 2

Target Readership ................................................................................................. 2

Manual keeping ..................................................................................................... 2

Alarm signs ............................................................................................................ 2

1.4 Abbreviations .......................................................................................................... 3

1.5 Specification ........................................................................................................... 4

2. Safety Requirements ....................................................................................................... 5

2.1 Responsibilities of the installer ............................................................................... 5

2.2 Qualified electrician ................................................................................................ 5

Qualification ........................................................................................................... 5

Responsibilities ..................................................................................................... 6

2.3 Requirements for the installation location .............................................................. 6

The installation room environmental requirements ............................................... 6

Room size ............................................................................................................. 7

Ceiling, ground and wall requirements ................................................................. 7

Temperature and humidity requirements. ............................................................. 7

Access authority .................................................................................................... 7

Protection grade .................................................................................................... 8

2.4 Safety signs on the device ..................................................................................... 8

2.5 Basic safety information ......................................................................................... 8

Risk of fatal injury: General ................................................................................... 8

Risk of fatal injury: Inverter.................................................................................... 9

Risk of fatal injury: Battery .................................................................................... 9

Risk of injury General .......................................................................................... 10

2.6 Other safety instructions ....................................................................................... 11

3. Transporting to the Installation Location ........................................................................ 13

4. Installation ...................................................................................................................... 13

4.1 Safety instructions ................................................................................................ 13

4.2 Installation site safety check ................................................................................ 14

4.3 Check the package ............................................................................................... 15

4.4 Remove the enclosure ......................................................................................... 15

Check out the packing list ................................................................................... 15

4.5 MINIES battery base fixing ................................................................................... 16

Installation of MINI ES 3kWh/3kW &MINI ES battery base ................................ 16

4.6 Wiring .................................................................................................................... 21

Remove the side panels of MINI ES battery base. ............................................. 21

Close the breaker ................................................................................................ 27

Page 3: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

II

4.7. Trial operation of device ...................................................................................... 28

Check before trial operation ................................................................................ 28

Supply power and start ....................................................................................... 28

Configure MINI ES 3kW/3kWh &MIINI ES battery base ..................................... 29

4.8 Reassemble the MINI ES ..................................................................................... 34

Install left and right side covers of MINI ES 3kW/3kWh and battery base ......... 35

Fixing the cable protective cover of electrical connection hole .......................... 39

Clean up the site. ................................................................................................ 42

Start operation ..................................................................................................... 42

Daily maintenance ............................................................................................... 42

4.9 Attached list .......................................................................................................... 43

Tool list................................................................................................................. 43

5. About BYD ..................................................................................................................... 44

Page 4: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

1

1. Introduction

Dear customer:

Thank you very much for purchasing the MINI energy storage base supplied by BYD Auto

Industry Company Limited. We sincerely believe that our products meet your needs. We

value your feedback on the product performance, appearance and function and we strive

to continually improve our product.

1.1 Brief description

To meet the 3kW/3kWh household energy storage system (MINI ES) capacity expansion

demand, BYD integrated years of development and operation experience launched the

3kW/6kWh household energy storage solution: [3kW/3kWh MINI ES] +3kWh battery base

system.

The system highlighted the overall technology advantages of intellectualization and

integration, set of BYD Iron-Phosphate Battery, PCS, distributed BMS, monitoring system

and other advanced technology, realize remote monitoring through the APP (support iOS

and Android system). With high reliability, high safety, high efficiency, energy conservation

and environmental protection, etc. Small volume, light weight, easy installation and

maintenance.

figure1. Installation effect drawing

Note: MINIES 3kWh battery base is used together with MINIES P30B3-AU-R2, it can be

extended to 3kW/6kWh MINIES system.

Page 5: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

2

Functions

Functions of the MINI ES battery base are shown as below:

When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can

extend to be 3kW/6kWh MINIES system.

When grid power is unavailable, battery base will cooperate with MINIES P30B3-AU-

R2 supply power to essential loads, such as computer, phone, TV general lighting, etc.

1.2 Disoperation predictable

Any operation of the storage system beyond the description of correct operation may be

considered as improper use.

The device shall not be operated:

In rooms smaller than 8m3

In rooms that contains flammable materials, fire, or in explosive atmospheres

In insufficient ventilated rooms under 8-25 m3

In areas with ambient temperature below0℃ above +40℃

Use the battery not authorized by BYD

In a damaged house

With any batteries other than approved by BYD

With defective cables

With parts that are clearly defective or damaged

1.3 About this manual

Declaration

This manual is applicable to the MINI ES battery base (MINI ES-B3-R1). Mainly

presentation the functions and attentions in transportation, assembling, installation,

commissioning and using of product.

This manual is applicable to transportation, assembling, installation and commissioning.

Target Readership

This manual is intended to be used by the accredited installer.

Manual keeping

This manual contains important information. Please read this manual carefully before

operating and servicing the MINI ES battery base.

Please strictly follow the manual instructions when operating the system, otherwise it may

cause the product to fail or cause personnel casualty or property loss.

This manual shall be stored and safely be accessible on site to the installer and service

technician at any time.

Alarm signs

Please keep several types of safety alarm signs in mind. Familiarize yourself with the

messages and the importance of the various signals as explained.

Page 6: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

3

Warning instructions identify safety information, which include the following:

Warning sign

Instructions to denote the level of risk

Details of the nature and source of the risk

Details of the potential risk if the warning instructions are disregarded

Risk management to prevent the danger or personnel casualty or material damage

The warning instructions are defined according to the following level of hazards

DANGER!

Denotes an extraordinarily hazardous situation

This warning symbol indicates an immediate danger, which can lead to severe

injury or death.

WARNING!

Denotes a very dangerous situation

This warning symbol indicates a potentially dangerous situation, which could lead

to severe injury or death.

CAUTION!

Denotes a dangerous situation

This warning symbol indicates a potentially dangerous situation, which could lead

to minor injury.

NOTICE!

Denotes a risk of material damage

This warning symbol indicates a situation that could lead to material damage.

1.4 Abbreviations

Abbreviation Description

Page 7: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

4

PV Photovoltaic system

APP Application software

CT Current transducer

DOD Depth Of Discharge

SOC State of Charge

1.5 Specification

NO. Type MINIES-B3-R1 Remark

Battery Parameter

1 Rated Voltage 52Vdc

Voltage Range:

44.8Vdc~57.6Vdc

2 Battery Type LiFePO4

3 Battery

Capacity 3kWh DC side

At +10℃~+30℃,

discharge at 0.5C

Protect Function

4

BMS

Short Circuit Protection

5 Under-temperature Protection

6 Over-temperature Protection

7 Under-voltage Protection

8 Over-voltage Protection

9 Over-current Protection

Other Parameter

10 Operation

Humidity 5%~95%

11 Altitude <2000m

12 Cooling Air Cooling

13 Noise <45dB

14 Communication

Interface CAN

15 Operation

Temperature 0~40℃

16 Store

Temperature -10℃~40℃

17 Size 698mm×477mm×200mm W×D×H

18 Weight 57kg

19 Protection

Level IP32

20 Usage Indoor(No Condensation,

Page 8: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

5

NO. Type MINIES-B3-R1 Remark

Environment Freeze, Direct Sunlight)

Design Standard

21 Battery

Standard UN38.3, IEC62619

2. Safety Requirements

2.1 Responsibilities of the installer

The installer must ensure that:

The safety protection equipment of the system is fully functioning

Any unclear warning and safety signage on the device shall be replaced immediately

Make sure there is no flammable items stored near the device

The device shall not be covered at any time

The device is required to be placed on a surface that can support the full weight of the

unit

Transportation, assembling, installation and commissioning of the device shall be

carried out by authorized personnel only

Transportation, assembling, installation and commissioning of the device shall be

carried out only under the specified conditions

The authorized installer shall be capable of evaluating the potential risk

Only authorized and trained electricians can perform installation, commissioning, and

change the settings and connect to the Router

Before installation and operation, any potential hazards shall be identified and the

necessary risk management should be applied onsite.

This manual and safety instructions shall be read and understood by the installer

before starting installation

Changes are not allowed to the software, housing and components of the device

without the manufacturer's approval. Otherwise, the liability and warranty may be

invalid.

The unit is not allowed to be opened except by authorized and trained electricians. If

the seal is broken due to unauthorized modification of the components, the warranty

will be invalid.

All operators of the energy storage system shall follow the user manual, installation and

service manuals and quality guarantee. Any damage to equipment caused by ignoring and

misreading the user manual, installation and service manuals and quality guarantee will

invalidate the product warranty.

2.2 Qualified electrician

Qualification A qualified electrician is a person who possesses the required knowledge, technical

training and experience, to conduct the following:

Setting up, activating, deactivating, disconnecting, grounding, short-circuiting and

Page 9: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

6

repairing electrical circuits and devices.

Standard maintenance and use of protective devices defined in the safety standards.

Administering first-aid to injured parties.

Compliance with local regulations, applicable standards and directives.

Responsibilities

The electrician shall ensure that:

The general information, step-by-step instructions and the safety instructions

regarding assembling and installation are read and followed at all times

Neither the physical size nor the rated current value of fuses can be changed

Before any electrical work is performed, ensure that equipment completely without

electricity and suitable measuring equipment shall be used to ensure that the device

is in accordance with applicable directives

The device shall never be opened during operation

2.3 Requirements for the installation location

Always select a suitable location before installation. The installer shall ensure that the

installation location meets the following conditions:

NOTICE!

Material damage due to inadequate ventilation

Individual components is not cooling fully as inappropriate or clogged ventilation,

will case components aging in advance, this will produce irreversible damage to

the device. Ensure full air circulation during the closing operation.

· Sufficiently ventilate the installation room

· Install all components according to the instructions

· Do not stack anything on the device.

· Operate the device only when it is closed

The installation room environmental requirements

The room must be kept dry and enclosed.

Protected against penetrating water.

Remove irrelevant items.

Always install away from highly flammable (e.g. paper) or explosive materials (e.g.

fuel, paint)

Sufficient ventilation (max humidity of 95%)

When the system is running, it will produce a trace of noise, recommended do not

install in the bedroom and other living areas, better in the garage, storage room, tool

room and other areas where do not affect the users.

Page 10: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

7

Room size

Room no less than 8.00 m³.

Room from 8 to 25 m³: passive or active ventilation is required (at 8 m³: air exchange

rate is 12 m³/h).

Rooms larger than 25 m³: do not need separate ventilation.

Space required.

Min. base surface area is 2.00 m²

Min. height is 2.00 m

Min. depth is 2.00 m

Ceiling, ground and wall requirements

Ceiling made from non-flammable material

Ground capable of supporting the total weight of the device: 153kg (3kW/3kWh system

96kg, 3kWh battery base 57kg.)

Minimum clearance from the wall is 15 cm

figure2. Schematic diagram of the installation gap

Temperature and humidity requirements.

Room temperature of 0℃ to + 40℃

Max. humidity of 95%

Access authority

Children shall be accompanied by an adult if they are in the installation room

Children shall not operate the storage system

Page 11: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

8

Protection grade

IP32

2.4 Safety signs on the device

Item Description

Be aware of dangerous voltage/ electric shock

Follow the guidelines of all relevant documents

Do not dispose the device in the bin

Point of connection for grounding protection

Hot surface

2.5 Basic safety information

This chapter contains the basic safety instructions. Failure to follow the safety instructions

in this manual can result in accidents which can lead to serious injury and/or death, as well

as serious components damage.

Risk of fatal injury: General

DANGER!

Risk of fatal injury due to lack of assistance

In the event of an accident a second person can switch off the power supply and

provide assistance.

· Only perform the work if a secondary installer is presented.

Page 12: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

9

DANGER!

Due to disregard of safety instructions

If the safety instructions and/or installation are not followed , the product may be

permanently damaged and electrical accidents with serious consequences may

occur.

· Follow the safety instructions

Risk of fatal injury: Inverter

DANGER!

Risk of fatal injury due to residual voltages

The inverter capacitors may still discharge even after the device is switched off.

· Ensure external and internal switches are disconnected.

· After switching off the device, always wait 10 minutes before direct contact with

the unit.

· Use a certified multimeter to check if the device is still energized in accordance

with applicable guidelines

DANGER!

Risk of fatal injury from arcing

Arcing may occur in the event of faults or if fuses and plugs are not properly

connected.

· Always use components in accordance with the instructions of the respective

manual

Risk of fatal injury: Battery

Page 13: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

10

DANGER!

Risk of injury due to electric shock

Batteries can generate significant amounts of short-circuit current due to incorrect

operation ,which can cause electric shock and lead to serious injury and/or death.

· While working with batteries, always remove watches, rings and other metal

equipments.

· Only use tools that have insulated handles

· Do not place or store tools or other metal objects on the batteries

· Always disconnect the charging and discharging source first before working on

the battery connections· Reconnect the unit only after comprehensive check of all connections and terminals,

ensure the wiring Is correct.

DANGER!

Risk of explosion due to using incompatible battery typesIf other battery types not approved for the device are used, the existing and unapproved

batteries may explode.

· Only use batteries that have been approved by the manufacture

· Check with the manufacturer before installation

Risk of injury General

WARNING!

Risk of injury due to unauthorized installation

Installation and commissioning of this storage system requires BYD authorized

training and relevant accreditation.

· Installation, cabling and commissioning must only be carried out by authorized,

trained electricians.

· The device operating temperature may reach up to 100℃, do not touch the hot

surface.

· After switching off the device, you must wait for 10 minutes before touching any

components.

Page 14: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

11

WARNING!

Risk of injury due to heavy weight

The heavy weight of components may cause injury during installation,

disassembling, transportation.· Transportation and installation requires a minimum of two people.

· Transport the device with appropriate lifting equipment.

WARNING!

Risk of injury due to incorrect installation procedure

If the sequence specified in the instructions is not followed during the installation of

the components, this can cause injury or material damage.

· Read the installation manual carefully and follow the installation procedure.

WARNING!

Risk of injury due to sharp edges

The components have sharp edges, which can cause injury if they are not handled

carefully.

· Wear protective equipment.

· Install the system with a minimum of two people.

WARNING!

Risk of incorrect use of the batteries

Eye and skin injuries can be caused by opening or damaging the batteries.

Never open or damage the batteries

· Do not short-circuit the batteries

· Do not reverse the polarity of the batteries

· Do not overcharge the batteries

2.6 Other safety instructions

Page 15: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

12

WARNING!

· Climbing on the equipment is prohibited. Please do not pace accessories on or

inside the device.

· Decomposition, reconstruction, repair of equipment without the manufacture

permission is prohibited.

· Internal electrical maintenance of equipment by any non-professional is

prohibited. When maintenance is needed, please contact the authorised

provider.

· Blocking the ventilation of the device is prohibited.

· Do not put any objects inside the equipment.

· Do not touch, pull or cut off the internal cables coming from the device.

· Do not place heat source near the device (such as electric furnace and other

heating equipment).

· Do not wipe the device with a damp cloth or chemicals (such as detergent).

· Do not pull the power cord of the device.

· Do not set the device close to any high frequency machines, wireless machines,

radio, television or the electrical equipment which will disturb signals.

· Do not apply heavy impact or tilt the device.

· Do not spray any liquid on equipment.

· Do not install the device in areas with electrostatic charge or noise.

· The essential loads will experience a short period blackout (less than 5

seconds) when grid drop off before MINIES supplying power.

· Please do not connection medical equipment to essential loads as MINIES is

not a UPS device.

· When the device itself or parts are damaged, do not attempt to repair or move

the device, consult a suitably qualified installer.

NOTICE!

· Avoid direct contact with the device during severe weather condition.

· The device is prohibited to use for medical equipment.

· If equipment appears deformed, broken or has abnormal sounds or smells,

please contact BYD authorised service provider immediately.

· If equipment malfunctions or cannot run normally, please contact the authorised

service provider immediately.

· Keep minimum space requirements for inspection and service.

· If regular maintenance is needed, please contact BYD authorised service

provider.

· If the device is not used for a long time, please keep the system fully charged.

· When the device needs to be relocated, please contact BYD authorised service

provider.

· This equipment is limited to indoor installation, please do not install outdoors.

· This product is limited to use in Australia, If there is any other special

requirements, please contact the manufacture for prior approval.

Page 16: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

13

3. Transporting to the Installation Location

WARNING!

Risk of injure due to heavy weight

The weight of the components may cause injury during installation, disassembling

and transportation.

· Please remove tripping hazard before installation.

· Transport and install the components with a minimum of two people.

· Transport the device with a appropriate lifting device.

WARNING!

Material damage caused by condensationIf the device is moved from a cold environment to the installation location,

condensation may occur and cause damage to the electronics.

· Only transport the device at temperature between 0 °C to +50 °C.

· A maximum relative humidity of 95% (non-condensing)

· Before commissioning, the device must be in a dry condition.

CAUTION!

Material damage due to crash

Electronic equipment can be damaged due to improper transportation.

· Be gentle and careful during transportation and installation.

4. Installation

4.1 Safety instructions

WARNING!

Risk of injury due to lack of experience

Installing and commissioning the storage system requires training, as well as

accreditation.

· Installation, wiring and commissioning must only be carried out by authorised,

trained electricians

Page 17: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

14

WARNING!

Risk of injury due to incorrect installation procedures

If the sequence specified in the instructions is not followed during the installation of

the components, this can cause injury or material damage.

· Read the installation manual carefully and follow the installation procedure.

WARNING!

Risk of injure due to heavy weight

The weight of the components may cause injury during installation, disassembling

and transportation.

· Please remove tripping hazard before installation.

· Transport and install the components by minimum two people.

· Transport the device with appropriate lifting device.

DANGER!

Risk of injury due to electric shock

Batteries can generate significant amount of short-circuit current due to incorrect

operation ,which can cause electric shock and lead to serious injury and/or death.

· While working with batteries, always remove watches, rings and other metal

equipments.

· Only use tools that have insulated handles

· Do not place or store tools or other metal objects on the batteries

· Always disconnect the charging and discharging source first before working on

the battery connections· Reconnect the unit only after comprehensive check of all connections and terminals

and ensure the wiring is correct.

4.2 Installation site safety check

Refer to section 2.3 “Requirements for the installation location” to select the installation

location.

Ensure the grid is disconnected before installation.

Page 18: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

15

DANGER!

Risk of injury due to electric shock

· Ensure the grid is disconnected to the electrical circuit board before installation.

4.3 Check the package

The MINI ES battery base has been carefully inspected and packed before dispatch.

But it is still possible it may be damaged during transportation.

DANGER!

If the external package has been damaged, it is possible the device or the internal

components have also be damaged during the transportation.

· Make a record and check the packing list carefully after removing the external

package.

· If the component is lost or damaged, the customer has the right to reject or ask

the service provider for replacement.

4.4 Remove the enclosure

Check out the packing list

The MINI ES is enclosed in a wooden case which includes other goods to be delivered. It

is forbidden to open the wooden case during transportation to the installation site. If

components are lost or damaged, the customer has the right to reject or ask for a

replacement. The packing list is shown as below:

Number Item Quantity Description

1 MINI ES battery base 1

2 User Manual 1

3 Factory Inspection Report 1

4 Certificate of Qualification 1

5 Fittings for Cabinet

combination connecting

1 Cables, Cable protective cover

Page 19: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

16

NOTICE!

· Confirm the MINI ES battery base model number you received is in accordance

with the one you ordered.

· Please keep all components well.

4.5 MINIES battery base fixing

Installation of MINI ES 3kWh/3kW &MINI ES battery base Lift the device into the position above the expansion bolts, make sure the bolt holes

on the device corresponding with the bolts on the MINI ES battery base, shown as

below.

figure3. Place the 3kW/3kWh MINI ES on the battery base

The left and right side panels of MINI ES 3kW/3kWh shall be removed before fixing

the bolt. The procedure is as follows

Identify the six screws on the left side, the left three screws (Near the wiring

interface side) need to be removed with Philips head screwdriver, the right three

don't need to be completely removed, just had them loosen. The direction of

rotation as shown.

Page 20: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

17

figure4. Remove side cover

Firstly slid down the side cover, then pull out from left side , as shown

figure5. Remove side cover

Disconnect the grounding cable which is on the bottom of the left side cover,

shown as below:

Page 21: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

18

figure6. Remove grounding cable

Identify the six screws on the right side, the right three screws (Near the wiring

interface side) need to be removed with Philips head screwdriver, the left three

don't need to be completely removed, just had them loosen. The direction of

rotation as shown.

figure7. Remove side cover

Firstly slid down the side cover, then pull out from right side , as shown

figure8. Remove side cover

Disconnect the grounding cable on the right side cover, shown as below:

Page 22: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

19

figure9. Remove grounding cable

figure10. Two side panels are removed

At the bottom of MINIES 3kW/3kWh and battery base, there are nut holes with a

protective cover for convenient fixing at the top of the fixed bolt. Remove the

protective cover and use a spanner (M14) to fix the nut (M8) and the torque

standard is 20N/m.

Page 23: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

20

figure11. Fixing the system

Using a spanner fixing the screws from the side

figure12. Fixing the system

NOTICE!

Be careful not to break the paint of the MINI ES when installing the bolts, otherwise

it may causes the surface of the MINI ES to rust.

Page 24: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

21

4.6 Wiring

The side panel of the MINI ES 3kW/3kWh and battery base shall be removed before wiring.

The MINI ES 3kW/3kWh side panel removal steps please refer to 4.6.Wiring order

Remove the side panels of MINI ES battery base. Remove the right side panel:

Identify the four screws on the right side which need to be removed with Philips

head screwdriver. After removing the screws, it is advisable to remove the right

side panel.

figure13. Remove the right side panel

Note: After removing the right side panel, the battery circuit breaker within the battery base

can be seen. Before any internal operation, the battery breaker must be disconnected.

figure14. Disconnect the battery circuit breaker

Remove the left side panel:

Identify the four screws on the left side which need to be removed with Philips

head screwdriver. After removing the screws, it is advisable to remove the left

side panel.

Page 25: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

22

figure15. Remove the left side panel

figure16. Remove the cable protection knobs

Firstly remove the cable protection knobs of MINI ES 3kW/3kWh & MINI ES

battery base before wiring.

Page 26: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

23

figure17. Installation diagram of cable

Before wiring, the cable must pass through the cable protection knobs first, then

slightly fixed, no need to tighten.

Note: There are three cable protection knobs should cooperate to install the fixing

frame of cable protective cover. Details as below

figure18. Install the fixing frame of cable protective cover

Page 27: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

24

figure19. Fixing the fixing frame of cable protective cover

QDYC 12V

RYC

KA+

KAYC

KA-

12V

PCS

FU

QF

FU

QF

RYC

KAYC

QD+ 12V

KA+

KA-

QD+ 12V

QDYC

QD- 12V

DC+

DC1+

DC-

DC1-

DC2

+

DC2

-

L1

L2

N1

N2

GRID

LOAD

PV

Charger

BA1

BA2

BA1

BA2

MINIES

3kWh

Battery Base

3kWhQD- 12V

figure20. Wiring diagram

Wiring according to the interface definition in figure21, figure22, and in accordance with

Page 28: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

25

the defined hole position to insert the corresponding cable.

+-①

+

LN

PE

L

PE

N

LOAD AC

PORT

GRID AC

PORT

black

white

GND of MINIESenclosure

-

BA

CAN

TCP/IP

CT1

CT2

MINI ESElectrical adapter board

CT3

⑥⑦

black

white

11

BARS485#1

RS485#2

13

figure21. Internal interface instruction of MINI ES 3kW/3kWh

Number Name Description

④ RS485#2 Remote control interface

⑥ TCP/IP Ethernet port, connect to the customer’s router

⑧ CT2 Port for PV inverter’s connection

⑨ CT1 Port for grid CT’s connection

⑩ GRID AC PORT

Connect to the circuit breaker on the general

distribution board. Connect the earthing cable to the

shell of the MINI ES

LOAD AC PORT Connect to the circuit breaker on the essential

distribution board

13 Earthing PE connect with the external cover of the MINI ES

Reserved interfaces

① DC+/ DC- Reserved ( BYD authorized products can access)

② 12V power Reserved ( BYD authorized products can access)

11

Page 29: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

26

Number Name Description

③ RS485#1 Reserved ( BYD authorized products can access)

⑤ CAN Reserved ( BYD authorized products can access)

⑦ CT3 Reserved ( BYD authorized products can access)

figure22. Internal interface instruction of MINI ES battery base

No. Item Remark

① CAN1 Reserved ( BYD authorized products can access)

② 12V POWER MINI ES Battery base 12V POWER interface

③ CAN MINI ES Battery base communication interface

④ DC1+ MINI ES Battery base positive interface

⑤ DC2+ Reserved ( BYD authorized products can access)

⑥ DC1- MINI ES Battery base negative interface

⑦ DC2- Reserved ( BYD authorized products can access)

Page 30: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

27

DC+

DC-

12V

CAN

figure23. Total wiring diagram

Close the breaker After finishing all the connections, comprehensively check and ensure cables are well

connected. Then close the MINI ES 3kW/3kWh &MINI ES battery base breaker.

Shown as below:

Page 31: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

28

figure24. the position of circuit breaker on MINI ES battery base

NOTICE!

· Please ensure wago connectors are not under strain to avoid bad connection. A

comprehensive checking is required after completing the connection.

4.7. Trial operation of device

Check before trial operation Please refer to chapter 4.3 in the MINI ES 3kW/3kWh installation manual check before

operation.

Supply power and start

CAUTION!

Before startup the System, the installer need to disconnect the circuit

breaker and carry out the following inspection:

· Double check and make sure the connection is correct according to the manual

instruction.

· Ensure that MINI ES3kW/3kWh and MINI ES battery is fixed tightly

DANGER!

Risk of short circuit

Incorrect wiring may cause short circuit.

Short circuit test shall be performed before system commissioning.

Only close the MINI ES circuit breaker on grid supply to system.

Press “Power” button for 10s, and start the system

Note: Long press "POWER" button for about 5seconds, "power" lamp ring light ( press the

"power" button for about 10 seconds, "power" lamp ring turn off, system shutdown.)

It’s a normal phenomenon that during the start-up process that "power" for "local" "remote"

lamp ring will flicker at the same time when waiting for circle power lamp ring light.

After “POWER" lamp ring light, “POWER” indicator light flashes around 1-2 minutes, this

is a normal phenomenon that self-test process during the system start-up time. After self-

inspection ended, “POWER" and "LOCAL" indicator lights will keep lighting, then the

system is completed start-up.

Check “POWER”“LOCAL” indicator light;

Normal condition:“POWER”indicator light is always on, at the same time“LOCAL”

indicator light is always on. Display as follow.

Page 32: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

29

POWERLOCALREMOTE

figure25. Normal state

Fault state: "POWER" indicator light is flashing. (MINI Battery base and MINI ES

3kW/3kWh did not connect successfully)

"LOCAL" indicator light is flashing. (Not connect to grid or no electricity power from grid)

Record results are as follows:

Configure MINI ES 3kW/3kWh &MIINI ES battery base

CAUTION!

· work can be carried out only after the wiring of MINI ES 3kW/3kWh and MINI ES

battery base finished.

· Ensure that the circuit breaker of MINI ES 3kW/3kWh and MINI ES battery base

have been closed and the system start-up before configuration.

Note: More information can be viewed "MINIES monitoring software using manual"

After the completion of the MINIES external wiring work, start-up the MINIES, and use the

monitoring software provided by BYD to configure MINIES

figure26. Monitoring software icon

Double-click the icon to open the MINIES monitoring software.

Page 33: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

30

figure27. Monitoring software startup page

After the success of the software initialization into the 【main interface】, at the same

time serial port configuration window Popup:

figure28. Serial port configuration window

Confirm that the UT-850 converter has been connected to the computer and MINIES.

Choose UT-850 actual occupation port of COM, set up the station address (slave

address) 4, baud rate 9600 b and other data default, click on "open serial port", then you

can open the serial communication.

If the communication parameters are not configured properly, or the converter is

connected with problem, the interface will pop up prompt box that the communication

timeout, please double check the communication parameter configuration or the

converter line connection.

figure29. Communication timeout prompt box

Page 34: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

31

figure30. MINI ES monitoring software main interface

Click on the "users" - "login" in the menu bar,

figure31. User login interface

Only after the user login that the configuration of MINI ES 3kW/3kWh &MINI ES battery

base can be proceeded.

Click on “Control” on the upper left corner of the select page, and choose the “Parameter

Config” in the drop-down menu.

Page 35: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

32

figure32. Set the BECU number

figure33. Select “Parameters config”

Set the number of BECU to 2, keep other parameters to the factory default parameters.

figure34. Set the BECU number to 2

After finish the configuration, need shutdown MINI ES, and disconnect the circuit

breakers of MINI ES 3kW/3kWh and MINI ES battery base. After completing the closing

action, once again closed the circuit breakers of MINI ES 3kW/3kWh and MINI ES battery

Page 36: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

33

base, and restart the system. Then re-enter into the BECU configuration interface, if the

number of BECU display is 2, the configuration is successful. And check the “Group

Status” on the home page, if the status display b00000001, said that currently only MINI

ES 3kW/3kWh merged. If the status display b00000010 said that only MINI ES battery

base merged currently; if the status display b00000011 said MINI ES 3kW/3kWh and

MINI ES battery base has been successfully incorporated.

figure35. Check the “Group Status”

Check running information of MINI ES 3kW/3kWh and MINI ES battery base.

Enter the “Debugging” interface, click on “Debug Advanced” at the bottom right corner,

set the number of PCS to 1, BECU number to 2 and click “Confirm”.

figure36. Set the PCS and BECU number

Page 37: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

34

After completing the above configuration, enter the “info Device”, you can view the

running information of MINI ES 3kW/3kWh and MINI ES battery base.

figure37. Check the MINI ES 3kW/3kWh running information

figure38. Check the MINI ES battery base running information

If there are special changes needed, please contact BYD authorized engineer or agent.

If the software used is not consistent with the software in the manual, please contact BYD

and ask for the latest version of the software.

4.8 Reassemble the MINI ES

Before reassemble the MINI ES, please make sure the grid supply has been disconnected

by the circuit breaker, turn off the system and had CT removed. Running again after

cleaned up the site, then reclose CT.

Page 38: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

35

Install left and right side covers of MINI ES 3kW/3kWh and battery base

DANGER!

· Before installing sideboard, please make sure the energy storage system has

already been turned off and deenergised.

Before install the left side panel, connect the grounding cable which is on the bottom

of the left side cover, shown as below:

figure39. Install grounding cable at left side

When installing left side cover, firstly move to the right and then move upward, make

sure the holes are aligned, then can fasten side cover.

Page 39: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

36

figure40. Install left side board

Then tighten six screws(related tool: Phillips head screwdriver)

figure41. Install left side board

Before install the right side panel, connect the grounding cable which is on the

bottom of the left side cover, shown as below:

Page 40: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

37

figure42. Install grounding cable at right side

When installing right side cover, firstly move left and then move upward make sure

the holes are aligned, then can fasten side cover.

figure43. Install right side board

Then tighten six screws(related tool: Phillips head screwdriver)

Page 41: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

38

figure44. Install right side board

figure45. Install left side board of battery base

Page 42: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

39

figure46. Install right side board of battery base

Fixing the cable protective cover of electrical connection hole The cable protective cover of MINI ES 3kW/3kWh and the battery base in the following

figure must be fixed tightly (related tools: spanner).

WARNING!

In order to prevent water and small insect from entering the internal system, what’s

more ,to prevent the internal cables of the system from bearing too much tension,

the cable protective cover of electrical connection hole cover must be fixed firmly.

Page 43: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

40

figure47. Fixing the cable protective cover

figure48. Diagram of electric connection holes’ location

Page 44: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

41

figure49. Install the cable protective cover

figure50. Fixing the frame of the cable protective cover

Page 45: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

42

figure51. The effect picture after installation is completed

Clean up the site.

Clean out rubbish and packing on site

Clean up the room and clean out the rubbish generated during installation.

Start operation

Close all related circuit breakers, the system will be switched on, then the system will

automatically run; and then inform the customer that installation is complete.

Daily maintenance

1. Do not block the product inlet / outlet. The inlet and outlets should be cleaned every six

(6) months.

2. When the product is likely to sit idle, please ensure that the product has sufficient battery

power. (Via long press "LOCAL" and "REMOTE" 2 buttons for charging the battery. Once

fully charged, the product will automatically shut down. Then turn off the power grid

connecting to the MINI ES).

Page 46: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

43

NOTICE!

Beyond the prescribed time limit or not in accordance with the requirements

of operation, may cause the risk of battery over-discharge. This kind of

damage to battery is beyond the scope of warranty.

· When the product is likely to sit idle, please operate in accordance with the

content step2 in "Daily maintenance" . Once fully charged, placement time shall

not exceed 6months

· As system do not access to the grid resulting in automatic shutdown, product

placement time shall not exceed 1 months.

4.9 Attached list

Tool list

No. Tool name Tool type Functions

1 Stanley knife

2 Phillips head screwdriver

3 Flat-bladed screwdriver

4 Small flat-bladed screwdriver CT terminal

5 Spanner M14 Fix anchor bolts

6 Electric drill and drill bit NO.10 drill Punch anchor bolts

7 Hammer

8 Long-nose pliers

9 Wire strippers

10 Wire crimpers

11 Crimping modular plier

12 Multi-meter

13 Adjustable wrench

14 Scissors

15 Tape

16

Other auxiliary tools that might

be used (for example:

Insulating gloves, insulating

shoes, insulating tape, etc.)

All installation

process

Page 47: MINI ES USER MANUAL - Ultra Green Energy · 2019. 11. 4. · When MINIES 3kWh battery base is used with 3kW/3kWh MINIES together, it can extend to be 3kW/6kWh MINIES system. When

44

5. About BYD

For any assistance about BYD product, please contact BYD by: