Mineral Resources in the Republic of Serbia – 8 th Annual Conference 13 November 2018 Environmental Protection Challenge: Managing Mine Waste Richard Elmer, Knight Piésold Consulting, London

Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Mineral Resources in the Republic of Serbia – 8th Annual Conference 13 November 2018

Environmental Protection Challenge: Managing Mine Waste Richard Elmer, Knight Piésold Consulting, London

Page 2: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Introduction

Common Challenges

Design Considerations

Examples: Olovo Mine - Bosnia

Cononish Mine - Scotland

Managing Mine Waste

Page 3: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Introduction

Page 4: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Introduction About Knight Piésold

Overview

• Established in 1921 • Offices in 15

countries • Over 850

professionals • Re-established in

the UK in 2013

Industries

• Mining • Power • Water Resources • Infrastructure • Oil & Gas

Tailings

• Designing Tailings Management Solutions Since the 1940’s

• Over 500 Tailings projects in the last 20 years

KP London

• Dedicated team of geotechnical engineers

• In 5 years: • Over 50 mines /

projects • 40 client

organisations • 30 countries

Managing Mine Waste

Page 5: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Managing Mine Waste

Mine Waste (Tailings)

Space – Projects often have limited space to accommodate tailings. Each project looked at individually to create optimum space saving solutions

Cost – Staged approach to spread the cost i.e. low CAPEX and higher OPEX for when finance is more available during production

Contamination Risks – Designs for the safe storage of mine waste according to local requirements and international best practice on all facilities

Mine Waste as an Afterthought – Often mine waste is only considered at a very late stage in the process. However, without a safe mine waste storage facility there is no mine.

Common Challenges

Page 6: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Managing Mine Waste

Mine Waste (Tailings)

Standards: ICOLD, ANCOLD, CDA, EU Waste Directive, local requirements BAT

Location: decision based on engineering (eg topography, water return requirements), environmental (eg sensitive receptors, climate) and economic factors (eg distance from plant, CAPEX, OPEX)

Site characterisation: ground investigation including geotechnical and hydrogeological

Tailings characterisation: physical (eg PSD, SG, consolidation, compaction) and geochemical (eg potential acid generation, metal leaching)

Capacity: Life of Mine requirements (typically 10 to 25 years); staged raise to spread cost; 3D modelling (eg Muck3D, AutoCAD Civils 3D)

Deposition modelling: distribution pipeline sizing and routing; spigot spacing (Muck3D)

Design Considerations

Page 7: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Managing Mine Waste

Mine Waste (Tailings)

Confining embankment design: material source, zonation / filter relationships; raise design; drainage

Seepage and stability: eg Slide, Slope/W, FLAC - including static / pseudo static & liquefaction assessment

Lining design: regulatory requirements, permeability requirements, drainage – hydrogeological risk assessment

Surface water management: diversion channels; seepage collection and treatment

Operation: OMS manual, instrumentation (eg piezometers, survey, inspection / audit)

Closure design: progressive restoration, wet or dry storage, monitoring, innovative designs, post closure use eg grazing, photovoltaics, parkland

Design Considerations (Cont.)

Page 8: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Examples

Page 9: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Managing Mine Waste

Small Scale Stacked Tailings

Small scale Cerussite Mine in Bosnia, LoM 15 years, approximately 2.2MT Tailings expected.

Located in a narrow valley with boundary constraints

Ground water supplies the local town of Olovo

Geology is Karst Limestone with visible solution features on the surface

Olovo Lead Mine, Bosnia and Herzegovina

Page 10: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Small Scale Stacked Tailings

Options study looked at a conventional tailings slurry with dam, filtered tailings “dry” stack, and a combination

Assessed lining of facility (clay vs HDPE or combination)

Small scale site investigation to assess the karst nature

Stacked filtered tailings chosen for final design based on environmental stability, restoration options and aesthetics.

Olovo Lead Mine, Bosnia and Herzogovina – Options

Page 11: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Managing Mine Waste

Small Scale Stacked Tailings Cononish Gold Mine, Scotland

Gold mine located in Scotland, UK

– Small output - 36,000 tpy

– LoM 16 years, total tailings 0.5 Mt

Sensitive location - in a national park

Previous design:

– Conventional cross-valley TMF

– Slurry tailings

– Downstream water collection pond

– Significant river diversion

– High CAPEX

Page 12: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Managing Mine Waste

Small Scale Stacked Tailings Cononish Gold Mine, Scotland

Stacked Tailings Concept

Revised concept using moraine shaped filtered tailings stacks

Sympathetic to the existing landscape during construction and closure

Avoids watercourse diversion - 30 m standoff from water courses, catchment

runoff intercepted and diverted (upstream of stacks)

- rainfall on stacks captured and stored in settlement pond

- water discharged to meet current standards Initial basal drainage layers Geotextile separator Filtered tailings placed in 300 mm layers and

compacted to 95% OMC Provides a cost effective solution to the project

Page 13: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Managing Mine Waste

Managing Mine Waste

Filtered stacked tailings not just for major projects in dry climates

Cost and environmental advantages for small scale operations in sensitive locations

Minimises need for expensive surface water management

Spreads cost of tailings management through life of mine as a continuous process (not big steps in costs for initial dams and subsequent raises)

Can be higher cost per tonne of tailings, but cost is spread

Appeals to regulators – amendable to progressive restoration

Opportunities for small scale narrow vein high grade mining in remote locations as a low cost tailings solution

Conclusions

Page 14: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Richard Elmer [email protected]

Q&A

Page 15: Mineral Resources in the Republic of Serbia – 8th Annual ... · Small Scale Stacked Tailings Options study looked at a conventional tailings slurry with dam, filtered tailings “dry”

Richard Elmer [email protected]