Millennium Pipeline Proposal

Embed Size (px)

Citation preview

  • 8/19/2019 Millennium Pipeline Proposal

    1/184

  • 8/19/2019 Millennium Pipeline Proposal

    2/184

    ENVIRONMENTAL REPORT

    Eastern System Upgrade Project

    FERC Docket No. PF16-3-000

    VOLUME II – PUBLIC

    Resource Reports 1 and 10Initial Pre-filing Drafts

    February 2016

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    3/184

    EASTERN SYSTEM UPGRADE PROJECT

    RESOURCE REPORT 1General Project Description

    FERC Docket No. PF16-3-000

    Pre-Filing DraftFebruary 2016

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    4/184

    Resource Report 1 – General Project Description i Eastern System Upgrade Project

    TABLE OF CONTENTSSection Page

    1.0 RESOURCE REPORT 1 – GENERAL PROJECT DESCRIPTION ........................................... 1-1 1.1 Introduction ................................................................................................................................... 1-1 1.2 Purpose and Need ......................................................................................................................... 1-2 1.3 Location and Description of Project Facilities .............................................................................. 1-4

    1.3.1 Pipeline Facilities ............................................................................................................. 1-5 1.3.2 Aboveground Facilities .................................................................................................... 1-6

    1.3.2.1 Compressor Stations .................................................................................... 1-7 1.3.2.2 Meter Station ................ .................. .................. ................. .................. ......... 1-8 1.3.2.3 Additional Aboveground Facilities .................. .................. ................. ......... 1-8

    1.3.3 Design Standards ............................................................................................................. 1-9 1.3.4 Status of Field Surveys .................................................................................................... 1-9

    1.4 Land Requirements ..................................................................................................................... 1-10 1.4.1 Pipeline Facilities ........................................................................................................... 1-12

    1.4.1.1 Construction Right-of-Way ........................................................................ 1-12 1.4.1.2 Additional Temporary Workspace ................. .................. .................. ......... 1-13 1.4.1.3 Access Roads ................. .................. ................. .................. .................. ...... 1-14 1.4.1.4 Pipe / Contractor yards and Staging Areas .................... .................. ......... 1-14 1.4.1.5 Operational Easement .................. .................. ................. .................. ......... 1-15

    1.4.2 Aboveground Facilities .................................................................................................. 1-15 1.5 Construction Schedule and Compliance Procedures .................................................................. 1-15

    1.5.1 Construction Schedule ................................................................................................... 1-15 1.5.2 Compliance Assurance Measures .................................................................................. 1-16

    1.6 Construction Procedures ............................................................................................................. 1-18 1.6.1 Pipeline Facilities ........................................................................................................... 1-18

    1.6.1.1 Typical Upland Pipeline Construction Procedures ......................... .......... 1-20 1.6.1.2 Wetland Construction Procedures .............................. .................. ............. 1-25 1.6.1.3 Waterbody Construction Procedures .................. ................. .................. .... 1-26 1.6.1.4 Road and Railroad Crossings ................. .................. .................. ............... 1-31 1.6.1.5 Foreign Utility Crossings ................ ................. .................. .................. ...... 1-32 1.6.1.6 Residential Areas ................. .................. ................. .................. .................. 1-32 1.6.1.7 Commercial and Industrial Areas .................. ................. .................. ......... 1-33 1.6.1.8 Agricultural Areas ............... .................. .................. .................. ................. 1-33

    1.6.1.9 Other Construction Procedures .................. .................. ................. ............ 1-34 1.6.2 Exceptions to the FERC Plan and Procedures ............................................................... 1-34 1.6.3 Aboveground Facilities .................................................................................................. 1-35

    1.6.3.1 General Construction Procedures .............................................................. 1-35 1.6.4 Restoration ..................................................................................................................... 1-36

    1.6.4.1 Pipeline Right-of-Way ................................................................................ 1-36 1.6.4.2 Aboveground Facilities .................. ................. .................. .................. ....... 1-37 1.6.4.3 Access Roads ................ .................. ................. .................. .................. ....... 1-37

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    5/184

    Resource Report 1 – General Project Description ii Eastern System Upgrade Project

    1.6.4.4 Pipe / Contractor Yards and Staging Areas ................ .................. ............. 1-37 1.7 Operations and Maintenance Procedures .................................................................................... 1-37

    1.7.1 Pipeline .......................................................................................................................... 1-38 1.7.2 Aboveground Facilities .................................................................................................. 1-39

    1.8 Future Plans and Abandonment .................................................................................................. 1-39 1.9 Public Outreach ........................................................................................................................... 1-40

    1.9.1 Federal and State Agencies ............................................................................................ 1-40 1.9.2 Landowners .................................................................................................................... 1-40 1.9.3 Public Participation ........................................................................................................ 1-40 1.9.4 Environmental Complaint Resolution Procedure .......................................................... 1-41

    1.10 Permits and Approvals ................................................................................................................ 1-42 1.11 Non-Jurisdictional Facilities ....................................................................................................... 1-42 1.12 Cumulative Impacts .................................................................................................................... 1-42 1.13 References ................................................................................................................................... 1-44

    LIST OF TABLES

    TABLE 1.1-1 Existing Compressor Stations on the Millennium Pipeline and associated Natural GasCapacities ......................................................................................................................... 1-2

    TABLE 1.3-1 Summary of Eastern System Upgrade Facilities.............................................................. 1-4 TABLE 1.3-2 Proposed Pipeline Facilities for the Eastern System Upgrade ......................................... 1-5 TABLE 1.3-3 Proposed Aboveground Facilities for the Eastern System Upgrade ................................ 1-6 TABLE 1.3-4 Non-Surveyed Areas Eastern System Upgrade ............................................................. 1-10 TABLE 1.4-1 Summary of Land Requirements for the Huguenot Loop .............................................. 1-11 TABLE 1.4-2 Summary of Land Requirements for Aboveground Facilities a ...................................... 1-11 TABLE 1.4-3 Summary of Land Requirements for the Eastern System Upgrade Land Impacts outside

    of Existing Millennium Pipeline Right-of-Way............................................................. 1-12 TABLE 1.4-4 Pipe / Contractor Yards and Staging Areas ................................................................... 1-14 TABLE 1.6-1 Potential HDD Installation Locations for the Huguenot Loop ...................................... 1-29 TABLE 1.6-2 Roads Crossed by the Eastern System Upgrade ............................................................ 1-31 TABLE 1.6-3 Foreign Utilities Crossed by the Eastern System Upgrade Project ................................ 1-32 TABLE 1.6-4 NYSDAM Plan Sections incorporated into the Project ECS ......................................... 1-33

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    6/184

    Resource Report 1 – General Project Description iii Eastern System Upgrade Project

    LIST OF FIGURES

    Figure 1.1-1 Eastern System Upgrade Project General Location Map ................................................. 1-3 Figure 1.6-1 Typical Pipeline Construction Sequence ....................................................................... 1-19

    LIST OF APPENDICES

    APPENDIX 1A Supplemental TablesTABLE 1A-1 Construction Right-of-Way Widths for the Eastern System UpgradeTABLE 1A-2 Additional Temporary Workspace for the Eastern System UpgradeTABLE 1A-3 Permanent and Temporary Access RoadsTABLE 1A-4 Proposed Deviations to FERC Plan and ProceduresTABLE 1A-5 Permits and ApprovalsTABLE 1A-6 Projects with Potential Cumulative Impacts on Resources within the General

    Area of the Eastern System Upgrade

    APPENDIX 1B Project Compliance and Mitigation Plans

    Project Environmental Construction Standards [Note: Not included in this draft]Horizontal Directional Drill Contingency Plan [Note: Not included in this draft]Bedrock Blasting Plan [Note: Not included in this draft]Environmental Complaint Resolution Procedures [Note: Not included in this draft]

    APPENDIX 1C Maps and Figures

    USGS Quadrangle ExcerptsProjects with Potential Cumulative Impacts on Resources within the General Area ofthe Eastern System Upgrade [Note: Not included in this draft]Oversized Maps and Drawings [Note: Not included in this draft]

    Pipeline Alignment Sheets (Scale 1-inch = 200 feet)Hydrostatic Pressure Test PlanSite-Specific HDD PlansResidential Construction DrawingsTypical Right-of-Way Configurations andAccess Road DrawingsLauncher/Receiver Station Plot PlansFull Size USGS Quadrangle MapsFull Size National Wetland Inventory (NWI) Maps

    APPENDIX 1D Agency Correspondence

    APPENDIX 1E Public Participation Plan

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

    http://0.0.0.0/http://0.0.0.0/http://0.0.0.0/http://0.0.0.0/http://0.0.0.0/

  • 8/19/2019 Millennium Pipeline Proposal

    7/184

  • 8/19/2019 Millennium Pipeline Proposal

    8/184

    Resource Report 1 – General Project Description v Eastern System Upgrade Project

    RESOURCE REPORT 1—GENERAL PROJECT DESCRIPTION

    Filing Requirement

    Location in

    EnvironmentalReport

    Provide a detailed description and location map of the project facilities (§380.12(c)(1)).

    • Include all pipeline and aboveground facilities.• Include support areas for construction or operation.• Identify facilities to be abandoned.

    Sections 1.1, 1.3Figure 1.1-1

    Describe any non-jurisdictional facilities that would be built in association with the project. (§ 380.12(c)(2)).

    • Include auxiliary facilities (See § 2.55(a)).• Describe the relationship to the jurisdictional facilities.•

    Include ownership, land requirements, gas consumption, megawatt size,construction status, and an update of the latest status of Federal, state, and local permits/approvals.

    • Include the length and diameter of any interconnecting pipeline.• Apply the four-factor test to each facility (see § 380.12(c)(2)(ii)).

    Section 1.11

    Provide current, original United States Geological Survey (USGS) 7.5-minuteseries topographic maps with mileposts showing the project facilities (§380.12(c)(3)).

    • Maps of equivalent details are acceptable if legible (check with staff).• Show locations of all linear project elements, and label them.• Show locations of all significant aboveground facilities, and label them.

    Appendix 1C

    Provide aerial images or photographs or alignment sheets based on these sourceswith mileposts showing the project facilities.(§ 380.12(c)(3)).

    • No more than 1-year old• Scale no smaller than 1:6,000

    Appendix 1C

    Provide plot/site plans of compressor stations showing the location of the nearestnoise-sensitive areas (NSA) within 1 mile (§ 380.12(c)(3,4)).

    • Scale no smaller than 1:3,600• Show reference to topographic maps and aerial alignments provided above.

    Appendix 9X

    Describe construction and restoration methods. (§ 380.12(c)(6)). Section 1.6 Identify the permits required for construction across surface waters.

    (§ 380.12(c)(9)).•

    Include the status of all permits.• For construction in the Federal offshore area be sure to include consultation

    with the MMS. File with the MMS for rights-of-way grants at the same time or before you file with FERC.

    Section 1.10

    Provide the names and addresses of all affected landowners as required and certifythat all affected landowners will be notified;

    • Affected landowners are defined in § 157.6(d)(2)• Provide an electronic copy directly to the environmental staff.

    Appendix 1F, VolumeIII,

    (Filed as Privileged)

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    9/184

    Resource Report 1 – General Project Description vi Eastern System Upgrade Project

    RESOURCE REPORT 1—GENERAL PROJECT DESCRIPTION

    Filing Requirement

    Location in

    EnvironmentalReport

    Additional Information Often Missing and Resulting in Data Requests

    Describe all authorizations required to complete the proposed action and the statusof applications for such authorizations, including actual or anticipated submittaland receipt dates.

    Section 1.10 andTable 1A-5

    Provide plot/site plans of all other aboveground facilities that are not completelywithin the right-of-way.

    Appendix 1C andAppendix 1G,

    Volume IV (Filed asCEII)

    Provide detailed typical construction right-of-way cross-section diagrams for each

    proposed right-of-way configuration showing information such as widths andrelative locations of existing rights-of-way, new permanent rights-of-way, andtemporary construction rights-of-way. Clearly identify any overlap of existingrights-of-way for projects involving collocation. Identify by pipeline facility andmilepost where each right-of-way configuration would apply.

    Appendix 1C andResource Report 8

    Summarize the total acreage of land affected by construction and operation of the project.

    Section 1.4

    Describe cathodic protection system; include associated land requirements asappropriate.

    [TBD]

    Describe construction and restoration methods for offshore facilities as well asonshore facilities.

    Section 1.6

    For proposed abandonments, describe how the right-of-way would be restored,who would own the site or right-of-way after abandonment, who would beresponsible for facilities that would be abandoned in place, and whetherlandowners were given the opportunity to request removal.

    Not Applicable

    If Resource Report 5 - Socioeconomics is not provided, provide the start and enddates of construction, the number of pipeline spreads that would be used, and theworkforce per spread.

    Section 1.5.1

    If project includes construction in the federal offshore area, include in thediscussion of required authorizations and clearances the status of consultationswith the Bureau of Ocean Energy Management, Regulation and Enforcement. Filewith the Bureau of Ocean Energy Management, Regulation and Enforcement forright-of-way grants at the same time or before filing the Federal Energy Regulatory

    Commission (FERC) application.

    Not Applicable

    For project involving the import or export of natural gas/liquefied natural gas andconstruction of liquefied natural gas facilities, include in the discussion of requiredauthorizations and clearances the status of consultations and authorizationsrequired from the U.S. Department of Energy, U.S. Coast Guard, and the FederalAviation Administration, as applicable.

    Not Applicable

    Send two (2) additional copies of topographic maps and aerial images/photographsdirectly to the environmental staff of the Office of Energy Projects (OEP).

    Appendix 1C

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    10/184

  • 8/19/2019 Millennium Pipeline Proposal

    11/184

    Resource Report 1 – General Project Description viii Eastern System Upgrade Project

    LIST OF ACRONYMS AND ABBREVIATIONS

    Algonquin Algonquin Gas Transmission, LLCAPI American Petroleum InstituteATWS additional temporary workspaceCFR Code of Federal RegulationsECS Environmental Construction StandardsFERC or Commission Federal Energy Regulatory CommissionFERC Plan Upland Erosion Control, Revegetation, and Maintenance PlanFERC Procedures Wetland and Waterbody Construction and Mitigation ProceduresHancock CS Hancock Compressor StationHDD horizontal directional drillHDD Plan Horizontal Directional Drill Contingency PlanHighland CS Highland Compressor Station

    hp horsepowerHUC hydrologic unit codeHuguenot M&R Huguenot Meter StationMillennium Millennium Pipeline Company, L.L.C.MP milepost

    NEPA National Environmental Policy Act NYSDAM New York State Department of Agriculture NYSDEC New York State Department of Environmental ConservationProject Eastern System UpgradeRamapo M&R Ramapo Meter and Regulator StationU.S. United StatesUSACE U.S. Army Corps of EngineersUSDOT U.S. Department of TransportationUSGS U.S. Geological SurveyWesttown M&R Westtown Meter Station

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    12/184

    Resource Report 1 – General Project Description 1-1 Eastern System Upgrade Project

    1.0 RESOURCE REPORT 1 – GENERAL PROJECT DESCRIPTION

    1.1 INTRODUCTION

    Millennium Pipeline Company, L.L.C. (Millennium) is seeking authorization from the Federal EnergyRegulatory Commission (FERC or Commission) pursuant to Section 7(c) of the Natural Gas Act toconstruct, install, operate, and maintain the Eastern System Upgrade (Project). The Project includesconstruction of approximately 7.8 miles of 30- and 36-inch pipeline loop in Orange County, New York.Millennium proposes to locate a majority of the pipeline loop overlapping with and adjacent to the right-of-way associated with its existing mainline (Millennium Pipeline). Additionally, as part of the Project,Millennium proposes to construct and operate (1) a new compressor station (Highland CS) in SullivanCounty, New York, (2) additional horsepower (hp) at the existing Hancock Compressor Station (HancockCS) in Delaware County, New York, (3) modifications to the existing Ramapo Meter and RegulatorStation (Ramapo M&R) in Rockland County, New York, and (4) additional pipeline appurtenant facilities

    at the existing Huguenot Meter Station (Huguenot M&R) and Westtown Meter Station (Westtown M&R)in Orange County, New York. Dependent upon receipt of necessary approvals, construction of theProject would be anticipated to commence in the Fall of 2017 to meet a target in-service date inSeptember 2018.

    On January 19, 2016 Millennium requested approval from the FERC to initiate the Pre-filing NationalEnvironmental Policy Act (NEPA) Review Process for the Project. The FERC issued its approval ofMillennium’s Pre-filing request on February 5, 2016 in Docket No. PF16-3-000. The Pre-filing ReviewProcess will allow for active participation by interested stakeholders throughout the Project development

    process while maintaining a coordinated schedule and ensuring the timely review and decision on the

    certificate application. The Pre-filing Review Process will also allow Millennium and the FERC to haveopen communication during the planning stages of the Project and will greatly improve the FERC’sability to identify issues early and address them as part of its environmental review assessment. Uponcompletion of the Pre-filing Review Process, Millennium will file an application with the Commission fora Certificate of Public Convenience and Necessity to construct, install, operate, and maintain the Project.

    The FERC’s comprehensive NEPA review process requires an applicant to submit an EnvironmentalReport consisting of up to 13 individual resource reports. Each resource report addresses a particularaspect of the environment in the Project area and evaluates the potential effects of the construction andoperation of the Project on that particular aspect. This Resource Report 1 (General Project Description)identifies the purpose and need for the proposed Project, the locations and descriptions of Project

    facilities, and the land requirements associated with the construction and operation of the proposedfacilities. This report also discusses: the proposed construction procedures; construction schedule; workforce, operation and maintenance procedures; potential plans for future expansion of the proposedfacilities; agency consultation and landowner notification; permits and approvals required to construct andoperate the Project; status of field surveys; proposed non-jurisdictional facilities; and an assessment ofcumulative impacts from other reasonably foreseeable future projects.

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    13/184

    Resource Report 1 – General Project Description 1-2 Eastern System Upgrade Project

    The existing Millennium system extends from the Town of Independence in Steuben County, New Yorkto the Town of Ramapo in Rockland County, New York, generally consisting of approximately 240 milesof mostly 30-inch-diameter pipeline. Existing compressor stations on the Millennium Pipeline andassociated horsepower are identified in Table 1.1-1.

    TABLE 1.1-1Existing Compressor Stations on the Millennium Pipeline and associated

    Natural Gas Capacities

    Station ID Installed Horsepower

    Corning Compressor Station 15,900

    Hancock Compressor Station 15,900

    Minisink Compressor Station 12,260

    The Millennium system is directly connected to five storage facilities and 14 interconnecting interstate

    and intrastate pipelines. The Millennium system serves customers along its route in the Southern Tier of New York and helps meet the energy needs of Northeast markets.

    A checklist showing the status of the FERC filing requirements for Resource Report 1 is includedfollowing the table of contents. Required drawings and maps showing the proposed Project facilities arelocated in Appendix 1C. Refer to Figure 1.1-1 for a Project overview map that shows the location of all

    proposed facilities and their association with Millennium’s existing pipeline facilities.

    1.2 PURPOSE AND NEED

    The purpose of the Project is to permit Millennium to transport an incremental volume of approximately200,000 dekatherms per day (Dth/dy) of natural gas from Millennium’s Corning Compressor Station to anexisting interconnect with Algonquin Gas Transmission, L.L.C. located in Ramapo, New York. All of thenew capacity is subscribed under long-term, firm contracts. Therefore, the Project is needed to meet thisexpress market demand for new natural gas transportation capacity.

    The Project facilities have been specifically designed to meet the demand for an additional 200,000Dth/dy of firm transportation, as well as to maintain current operating pressures at intermediate delivery

    points following the construction of the Project, to continue to meet customer demand on Millennium’ssystem during the summer months, and to ensure continued deliveries to interconnecting pipelines.

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    14/184

    14 Gabriel D Augusta, ME

    Created:2/10/2016

    !.

    ")

    ")

    !.

    !.

    XW

    ")

    XW

    ")

    Delaware County

    Ulster County

    Sullivan County

    Orange County

    RocklanCounty

    Ramapo Meter Station(Modifications)

    Hancock Compressor Station(Modifications)

    Highland Compressor Station(Proposed)

    Huguenot Meter Station(Modifications)

    Westtown Meter Station(Modifications)

    Wagoner Interconnect(Existing)

    Minisink Compressor Station(Existing) Ramapo

    Interconnect

    Huguenot Loop (Proposed)

    !.

    ")

    !.!.XW")XW

    ")

    K0 105

    Miles

    ") Proposed Compressor Station

    ") Existing Compressor Station Modifications

    ") Existing Compressor Station

    XW Existing Interconnect!. Existing Meter Station Modifications

    Proposed Loop

    Existing Algonquin Gas

    Existing Millennium Pipeline

    Eastern System UpgradeGeneral Location Map

    urces: ESRI, Millenium, and TRC

    Figure 1

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    15/184

  • 8/19/2019 Millennium Pipeline Proposal

    16/184

    Resource Report 1 – General Project Description 1-5 Eastern System Upgrade Project

    TABLE 1.3-1Summary of Eastern System Upgrade Facili ties

    Facility New/Modif ied Length (miles) County

    Huguenot Modified Not Applicable OrangeWesttown Modified Not Applicable Orange

    Ramapo M&R Modified Not Applicable Rockland

    Additional Aboveground Facilities

    Pig Launcher / Receiver New Not Applicable Orange

    Alternate Interconnect New Not Applicable Orange

    1.3.1 Pipeline Facilities

    The Project includes approximately 7.8 miles of 30- and 36-inch diameter new natural gas pipeline loop(Huguenot Loop) that will extend from an interconnection with the existing Millennium Pipeline at theexisting Huguenot M&R Station in the town of Deerpark, New York, extending southeast through thetown of Greenville, to an interconnect with the Millennium Pipeline at the existing Westtown M&RStation in the town of Minisink, New York. Table 1.3-2 provides a summary of the Huguenot Loopincluding milepost (MP) designations within each town. All MPs throughout this report refer to locationsalong the proposed Huguenot Loop, unless preceded by “Millennium”, which denotes an MP locationalong the existing Millennium Pipeline. The Huguenot Loop will have a maximum allowable operating

    pressure and a maximum operating pressure of 1,200 pounds per square inch gauge. To the extent practicable, the Huguenot Loop will be constructed overlapping with and adjacent to the permanent right-of way associated with the existing Millennium Pipeline. Based on current design, approximately 94

    percent of the total length of the new pipeline will be co-located with Millennium’s existing rights-of-

    way. Tables 8A-3 and 8A-4 in Resource Report 8 will identify existing rights-of-way adjacent to theHuguenot Loop and locations where the Huguenot Loop would be more or less than 25 feet from theexisting Millennium Pipeline, respectively [Note: Not Included in the draft].

    TABLE 1.3-2Propos ed Pipeline Facili ties for th e Eastern System Upgrade

    Pipe Diameter MilepostBegin Milepost End Length (Miles) Town County

    Huguenot Loop

    30 0.00 0.11 0.11 Deerpark Orange

    36 0.11 1.79 1.68 Deerpark Orange

    36 1.79 6.04 4.25 Greenville Orange36 6.04 7.75 1.71 Minisink Orange

    Total Miles a 7.75

    a: Mileposts are reference points and may not equal total length due to rounding.

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    17/184

    Resource Report 1 – General Project Description 1-6 Eastern System Upgrade Project

    1.3.2 Aboveground Facilities

    Aboveground facilities for the Project will consist of the new Highland CS, modifications to the existingHancock CS, modifications to the existing Ramapo M&R, and the addition of pipeline appurtenantfacilities at the existing Huguenot M&R and Westtown M&R. Table 1.3-3 provides a summary bylocation of all new and modified station facilities associated with the Project. These facilities are depictedon the full-size USGS maps and aerial-based alignment sheets and the USGS map excerpts provided inAppendix 1C [Note: Full-size USGS maps and aerial-based alignment sheets not included in this draft] .

    TABLE 1.3-3Proposed Aboveground Facilities for the Eastern System Upgrade

    Facility Type andName

    App roximateMilepost Town, County Description

    Compressor Stations

    Highland CS (New) Millennium MP 135 Highland, Sullivan Construct a new compressor station withone 22,400 hp Solar Titan 130Ecompressor unit.

    Hancock CS Millennium MP107.8 Hancock, Delaware

    Install a new Solar Titan 130E compressorunit, totaling 22,400 hp, and re-stage theexisting Solar Mars compressors (15,900hp), for a total of 38,300 hp.

    Meter Stations

    Huguenot M&R MP 0.0 Deerpark, Orange

    Remove existing 30-inch pig receiver,extension of 30-inch Millennium Pipeline.Installation of new regulator facilities and anew 24-inch pig launcher for the existing24-inch Millennium Pipeline.

    Westtown M&R MP 7.8 Minisink, Orange

    Install a new 36-inch pig receiver for theHuguenot Loop. Install a new 24-inchreceiver to the existing 24-inch MillenniumPipeline and a new 30-inch pig launcher forthe existing 30-inch Millennium Pipeline.

    Ramapo M&R Millennium MP190.2 Ramapo, RocklandInstall new filter/separators, meters, heater,and flow and pressure control regulation atthe existing Ramapo M&R.

    Additional Aboveground Facilities

    Pig Launcher /Receiver MP 0.1 Deerpark, Orange

    Install a new 30-inch pig receiver and anew 36-inch pig launcher for the HuguenotLoop.

    Alternate Interconnect MP 7.7 Minisink, OrangeInstall a 12-inch side tap on the 36-inchHuguenot Loop and tie-in to the 12-inchValley Lateral.

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    18/184

    Resource Report 1 – General Project Description 1-7 Eastern System Upgrade Project

    Compressor Stations1.3.2.1

    Highland CS (New)

    The Highland CS is a proposed, new compressor station located in Sullivan County, approximately 25miles east of the existing Hancock CS in Delaware County. Millennium proposes to install one 22,400 hpSolar Titan 130E compressor at the new station.

    The auxiliary facilities will include the compressor building, and will be constructed of a rigid steel framewith sheet metal roofs and walls. A controls building and an auxiliary building will house station controlsand communications equipment as well as an emergency electrical power generator and compressed airsystem. The proposed facilities will also include valves, a fuel gas heater, parking and access areas, and afence enclosure. Utilities that will be supplied from local utility companies are electric power andcommunications circuits. These utilities will require minor construction to bring the services into the

    station property. No new utility right-of-way is anticipated to be needed. The station site work willinclude a self-contained on-site water well and sanitary sewer system (e.g., on-site septic).

    The site for the Highland CS has several thousand feet of frontage on Route 12/55; however, the facilitywill be set back from the road far enough so that the grade of the terrain and existing wooded vegetation

    provides adequate visual screening for the facility from the road. No additional screening is proposed.The outdoor lighting for the new compressor station will be limited during un-manned night timeoperation to the minimum amount required for security. The station security system incorporates outdoorvideo cameras that must have sufficient outdoor lighting to record clear images at night. The station maingate along with the station yard and all building entry and exit doors will have lighting for security.These lights will have directional control or they will be positioned in a manner that minimizes theirvisibility in the direction of local residences.

    Hancock Compressor Station (Modified)

    Millennium proposes to add a new Solar Titan 130E compressor unit, totaling 22,400 hp and to re-stagethe existing Solar Mars compressors (15,900 hp) at its existing Hancock Compressor Station in DelawareCounty, New York. Installation of the new compressor unit will require construction of a newcompressor building and auxiliary building. The modifications will also include installation of gas after-coolers; filter separator; additional MCC cabinets; fuel gas heater; valves, etc., some of which may be

    built outside of the current station footprint. Minor construction will be required to upgrade the existingelectric power utility service into the station, but no new rights-of-way are required for the upgrade. Noadditional visual screening is planned beyond existing on-site visual screening. The outdoor lighting forthe existing compressor station is limited during un-manned night time operation to the minimum amountrequired for security. The station security system incorporates outdoor video cameras that must havesufficient outdoor lighting to record clear images at night. New outdoor lighting may be required in thearea around the new compressor building. If new lights are installed, the lights will have directionalcontrol or they will be positioned in a manner that minimizes their visibility in the direction of localresidences.

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    19/184

    Resource Report 1 – General Project Description 1-8 Eastern System Upgrade Project

    Meter Station1.3.2.2

    Huguenot Meter Station (Modified-MP 0.0)

    Work at the existing Huguenot M&R will include the removal of the existing Millennium 30-inch pipeline receiver stub-up piping assembly and the extension of the 30-inch Millennium pipeline across themeter yard and ultimately to the new 30-inch receiver facility located at MP 0.0. Work will also includethe installation of new regulator facilities to reduce the MAOP from the existing Millennium 30-inch

    pipeline (1,200 psig) to the existing Millennium 24-inch pipeline (936 psig), and the installation of a new permanent 24-inch pig launcher to the existing Millennium 24-inch launcher stub-up piping assembly.All new facilities will be located within the existing Huguenot Meter Station site except for the extensionof the 30-inch pipeline to the new pig launcher / receiver at MP 0.0.

    Westtown Meter Station (Modified)

    Work at the existing Westtown M&R will include the installation of a new 36-inch pig receiver at theterminus of the new 36-inch Huguenot Loop line. The existing Westtown M&R site will be expanded byadding a 35 foot wide by 125 foot long extension to the west side of the existing Westtown M&R fenced-in site. Work will also include the installation of a new 24-inch pig receiver to the existing Millennium24-inch pig receiver stub-up piping assembly and a new 30-inch pig launcher to the existing Millennium30-inch pig launcher stub-up piping assembly, all within the existing Westtown Meter Station site.

    Ramapo Meter Station (Modified)

    The existing Ramapo Meter Station is located at Millennium’s interconnect with the Algonquin GasTransmission, LLC (Algonquin) pipeline system approximately one half-mile southwest of the Algonquinright-of-way crossing of Sky Meadow Road in Ramapo, New York. The proposed modifications would

    be generally located within the limits of the meter station facility and includes a new filter/separator, over pressure protection / back feed to existing facility, in-line heater, and ultrasonic meters and flow/pressurecontrol valves to control the required capacity of natural gas through the station.

    Millennium intends to use the permanent access road to the station for the period of construction and foroperation. Millennium is currently in the process of upgrading this access road for its operational needs.Millennium is also currently in the process of obtaining a permanent easement from Orange County for

    placement of the new filter/separators and / or other new equipment including but not limited to new

    meters, heater, flow and pressure control regulation.

    Additional Aboveground Facilities1.3.2.3

    Launcher and Receiver (MP 0.1)

    A new 65 foot wide by 150 foot long fenced in facility will be installed along the existing Millennium 24-inch pipeline right-of-way at MP 0.1 and will include a new 30-inch pig receiver and a new 36-inch pig

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    20/184

    Resource Report 1 – General Project Description 1-9 Eastern System Upgrade Project

    launcher for the Huguenot Loop. This new facility site is required because there is insufficient room atthe existing Huguenot M&R to accommodate the new receiver / launcher facilities. The new facility islocated partially within Millennium’s existing / proposed permanent easement. A launcher/receivertypical detail is included in Appendix 1C [Note: Not included in this draft].

    Alternate Interconnect (MP 7.5)

    A 12-inch side tap will be installed on the 36-inch Huguenot Loop and tied into the 12-inch ValleyLateral to provide an alternate interconnect to supply gas to the Valley Lateral in the event that the 24-inch Millennium pipeline is taken out-of-service. This facility will be a below grade valve with only anextension stem/wheel operator located above grade. There will be no security fence or crushed rock atthis location. It will be located on land owned by Millennium and currently maintained for the existingMillennium Pipeline right-of-way.

    1.3.3 Design Standards

    All pipeline facilities and associated appurtenances will be designed, constructed, tested, operated, andmaintained to conform to or exceed the requirements of the U.S. Department of Transportation (USDOT)in 49 Code of Federal Regulations (CFR) Parts 191 and 192, Transportation of Natural and Other Gas byPipeline, Minimum Safety Standards, Annual Reports, Incident Reports, and Safety-related ConditionReports; 18 CFR § 380.15, Site and Maintenance Requirements; and other applicable federal and stateregulations.

    The pipeline will be constructed of carbon steel pipe that has been manufactured in accordance with theAmerican Petroleum Institute’s (API) specifications for seamless and welded steel line pipe for use inconveying gas in the natural gas industries (API 5L) with a fusion-bonded epoxy coating.

    1.3.4 Status of Field Surveys

    Detailed civil, biological and cultural field surveys began in October 2015 within a 100- to 300-foot-widesurvey corridor to accommodate the construction/permanent rights-of-way, ATWS, and minor routerealignments that may be required for site-specific features. Environmental components of the survey

    program include delineations of wetlands and waterbodies, identification of threatened and endangeredspecies or their habitat, surveys for cultural resources within the area of potential effect, and identificationof nearby water supply wells and residences.

    As of February 1, 2016 civil, biological, and cultural surveys have been completed on land where survey permission has been granted (approximately 83 percent of the construction right-of-way, the pipe /contractor yards, staging areas, and all access roads). More detailed information on the methodologiesused, and the status and results of surveys completed to date will be included in Resource Report 2 (WaterUse and Quality); Resource Report 3 (Vegetation and Wildlife, including threatened and endangeredspecies); and Resource Report 4 (Cultural Resources) in the draft Environmental Report to be submittedin April 2016. A summary of non-surveyed areas for the Project is included in Table 1.3-4.

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    21/184

    Resource Report 1 – General Project Description 1-10 Eastern System Upgrade Project

    TABLE 1.3-4Non-Surveyed Areas Eastern System Upgrade

    Facility/Tract ID Nearest Milepost Extent(acres not surveyed)Huguenot Loop

    [TRACT ID TBD] 0.10 27.62

    0.62 8.03

    0.91 1.18

    1.28 0.78

    1.29 0.08

    1.36 0.08

    1.36 0.46

    1.44 1.25

    1.49 0.071.55 0.08

    2.27 18.82

    2.99 0.44

    3.84 0.45

    3.87 1.03

    4.99 0.10

    5.07 0.10

    5.14 0.10

    7.03 2.17

    Aboveground FacilitiesSurvey Complete

    Percent not surveyed a 17.4

    a: Percent not surveyed based on the limits of the survey corridor.

    1.4 LAND REQUIREMENTS

    Construction and operation of the pipeline loop will require acquisition of construction work areasconsisting of the temporary construction right-of-way, ATWS, access roads from public roadways to theconstruction work areas, pipe / contractor yards, and staging areas. Following construction, all

    construction work areas will be restored and revegetated. Millennium will increase its existing permanenteasement by 25 feet to accommodate operation of the Huguenot loop. For portions of the Huguenot Loopthat are not co-located with the existing Millennium Pipeline, a new 50-foot permanent right-of-way will

    be obtained for operation of the new pipeline loop.

    Table 1.4-1 and Table 1.4-2 summarize land requirements for construction and operation of the Project.Table 1.4-3 summarizes land impacts outside of the existing Millennium Pipeline right-of-way for

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    22/184

  • 8/19/2019 Millennium Pipeline Proposal

    23/184

    Resource Report 1 – General Project Description 1-12 Eastern System Upgrade Project

    TABLE 1.4-3Summary of Land Requi rements for th e Eastern System Upgrade

    Land Impacts outside of Existing Millennium Pipeline Right-of-Way

    Facility

    Land AffectedDuring

    Construction(Acres)

    Land AffectedDuring Operation

    (Acres)Total

    Pipeline right-of-way [TBD] [TBD] [TBD]

    Additional Temporary Workspace [TBD] [TBD] [TBD]

    Access Roads [TBD] [TBD] [TBD]

    Pipe / Contractor yards [TBD] [TBD] [TBD]

    Staging Areas [TBD] [TBD] [TBD]

    Aboveground Facilities

    Hancock CS [TBD] [TBD] [TBD]

    Highland CS [TBD] [TBD] [TBD]

    Huguenot M&R [TBD] [TBD] [TBD]

    Westtown M&R [TBD] [TBD] [TBD]

    Ramapo M&R [TBD] [TBD] [TBD]

    Additional Aboveground Facilities [TBD] [TBD] [TBD]

    Total a [TBD] [TBD] [TBD] Notes:a: The numbers in this table have been rounded for presentation purposes. As a result, the totalsmay not reflect the sum of the addends.

    1.4.1 Pipeline Facilities

    The following sections describe the various components of the construction work areas and land that will be maintained for operation of the Project.

    Construction Right-of-Way1.4.1.1

    Appendix 1C includes typical right-of-way cross-sections for construction in uplands, agricultural land,and wetlands [Note: Not included in this draft]. Millennium is proposing to use a construction right-of-way width that will provide for safe working conditions and efficient pipe installation while also

    protecting sensitive environmental resources. The dimensions of Millennium’s typical constructionrights-of-way are based on the following considerations.

    • Construction Work Area: The equipment work area typically will require approximately125 feetfor efficient pipe installation and to accommodate:

    o Automatic welding – Millennium may use automatic welding to weld the pipe jointstogether before lowering the pipe into the trench. This involves use of portable shelters,commonly referred to as “sheds” or “shacks,” that are leapfrogged down the right-of-way

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    24/184

    Resource Report 1 – General Project Description 1-13 Eastern System Upgrade Project

    by sidebooms during mainline welding operations. The standard width of these sheds is between 10 and 12 feet, not including maneuvering room for the sideboom to move thesheds down the right-of-way.

    o A travel lane – The travel lane is essential for efficient pipeline construction and allowsequipment and support crews to pass around construction activities. During pipe layingactivities, the travel lane allows sidebooms to leapfrog along the right-of-way, allowingfor longer segments of pipe to be installed. For short distances and in environmentallysensitive areas, the travel lane can be reduced, although ATWS is often required outsideof the sensitive areas for pipe makeup and/or spoil storage.

    The majority of the Huguenot Loop is co-located with the existing Millennium Pipeline in this area.Typically, Millennium will utilize 45 feet of the existing permanent right-of-way for the MillenniumPipeline and an additional 80 feet of new construction right-of-way for the Huguenot Loop.

    The construction right-of-way width and temporary land requirements for installation of the pipeline willdiffer according to the type of terrain encountered, construction methods that will be used, andenvironmental sensitivity of the land being crossed. The typical right-of-way cross-sections are providedin Appendix 1C [Note: Not included in this draft]. Based on construction experience involvingcomparable installations, and evaluation of the environmental sensitivity of the land being crossed,Millennium is proposing use of the following typical construction right-of-way widths:

    • 175 feet in agricultural land (i.e., full right-of-way topsoil segregation);• 125 feet in upland areas;• 75 feet in wetland areas; and• Up to 185 feet in areas of steep side slope.

    Table 1A-1 summarizes the locations, by milepost, where the standard construction right-of-way would be 175, 125, 75, or 185 feet wide [Note: Not included in this draft].

    Additional Temporary Workspace1.4.1.2

    ATWS will be required where an obstacle prevents the normal placement of spoil and the placement of pipe sections immediately adjacent to the pipe trench (for example, at a waterbody crossing or roadcrossing), where additional volumes of spoil will be generated in areas where a reduced right-of-way is

    being used (for example, at wetland crossings), or where additional construction operations will be performed (for example, at HDDs).

    ATWS typically will be required on both sides of road, wetland, and waterbody crossings, at truckturnarounds, at hydrostatic test water withdrawal pump locations, at pipe tie-ins, at HDD entry and exit

    points, at foreign pipeline or other utility crossings, and for staging and fabrication of drag sections. Thesize and configuration of each ATWS is unique and dependent upon the existing conditions at each worklocation (e.g., available or accessible space, the presence of buildings and other structures, crossing angle,

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    25/184

    Resource Report 1 – General Project Description 1-14 Eastern System Upgrade Project

    crossing depth, length of crossing, terrain, or the presence of trees or sensitive habitat). See Table 1A-2for the proposed location and purpose of each ATWS [Note: Not included in this draft].

    Access Roads1.4.1.3

    Access roads are used to transport construction workers, equipment and materials to the constructionwork area from public interstate, state, county and local highways/roads. These access roads include

    private roads and/or two-tracks that may require minor modification or improvement to safely support theexpected loads associated with the movement of construction equipment and materials to and from the

    public roadways to the construction right-of-way. Modifications or improvements to these access roadsmay include grading or other minor maintenance to prevent rutting during use, placement of additionalgravel or crushed stone on the existing surface, enlargement to accommodate the pipeline equipment,such as stringing trucks, and/or installation of board or timber mats that will be removed upon completionof construction. Table 1A-3 provides access road locations, length, existing surface type, and existing

    land use [Note: Not included in this draft].

    Pipe / Contractor yards and Staging Areas1.4.1.4

    Pipe / contractor yards and staging areas are needed for various uses, such as stockpiling pipe, fabricatingconcrete weights and piping assemblies, staging construction operations, storing construction materials,

    parking equipment, and for temporary construction offices. Three pipe / contractor yards and four stagingareas have been identified for use during construction of the Project. In general, the pipe / contractoryards and staging areas will require minimal improvements, primarily in the form of a graded gravel baseto stabilize the ground surface and allow for motor vehicle traffic, delivery and storage of pipe andassociated equipment and materials, and placement of storage trailers and on-site office trailers. Land forPipe / Contractor Yard 2 and 3 will be owned by Millennium. Land for the remaining pipe / contractoryard and staging areas will be leased by Millennium during construction. The pipe / contractor yards andstaging areas are included in Table 1.4-4 and a map of the locations is included in Appendix 1C.

    TABLE 1.4-4Pipe / Contr actor Yards and Staging Areas

    Name Location Town/CountySize

    (acres)Land Use

    Pipe /Contractor

    Yard 1MP 0.2 Deerpark, Orange 8.64 Open Land

    Staging Area 1

    MP 2.9 Greenville, Orange 4.08 Open Land, Upland Forest

    Staging Area 2

    MP 4.7 Minisink, Orange 4.51 Agricultural Land

    Pipe /Contractor

    Yard 2MP 7.5 (northeast) Minisink, Orange 3.38

    Agricultural, UplandForest

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    26/184

    Resource Report 1 – General Project Description 1-15 Eastern System Upgrade Project

    TABLE 1.4-4Pipe / Contr actor Yards and Staging Areas

    Name Location Town/CountySize

    (acres)Land Use

    Pipe /Contractor

    Yard 3MP 7.5 (southwest) Minisink, Orange 6.79

    Industrial/Commercial,Open Land, Upland Forest

    Staging Area 3

    MP 7.7 (west) Minisink, Orange 2.31 Agricultural Land, Open

    Land

    Staging Area 4

    MP 7.7 (east) Minisink, Orange 2.38 Agricultural Land,

    Industrial/CommercialLand, Open Land

    TOTAL: 32.10

    Operational Easement1.4.1.5

    Following construction of the pipeline, in areas where Millennium can co-locate the Huguenot Loop withits existing right-of-way, Millennium will retain an additional 25 feet of the construction right-of-way as a

    permanent easement to allow for inspection and maintenance of the pipeline during operation. In areaswhere co-location is not possible Millennium will retain 50 feet of the construction right-of-way as a

    permanent easement to allow for inspection and maintenance of the pipeline during operation.

    1.4.2 Aboveground Facilities

    Table 1.4-2 above summarizes land requirements for construction and operation of the proposed new andmodified aboveground facilities. See Resource Report 8 for additional information on property size and

    new land requirements for the new and modified aboveground facilities [Note: Not included in this draft].Millennium already owns the land required for construction and operation of the new compressor buildingat the Hancock CS. Millennium owns the property where the new Highland CS will be located.Millennium will obtain an agreement or license with the landowner for use of the land required forconstruction and operation of the modifications at the Westtown M&R and Ramapo M&R. Millenniumis in the process of obtaining a permanent easement from Orange County for the new land required at theRamapo M&R.

    1.5 CONSTRUCTION SCHEDULE AND COMPLIANCE PROCEDURES

    1.5.1 Construction Schedule

    Millennium plans to commence construction in September 2017, pending receipt of all applicable permitsand clearances. The duration of construction for the proposed new Highland CS is estimated to be 8 to 10months. The duration of construction for proposed modifications at the existing Hancock CS andRamapo M&R is estimated to be 4 to 8 months. The Project is scheduled to be in service by September2018.

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    27/184

    Resource Report 1 – General Project Description 1-16 Eastern System Upgrade Project

    Millennium will install the pipeline using one construction spread for the pipeline, and smaller workcrews for the HDDs, meter stations, and launcher and receiver. The order in which each facility will beconstructed may vary, depending upon the capabilities of each contractor, weather, available workforceand optimized construction logistics. Separate construction crews will be used for each of the proposedaboveground facilities with the exception of the tie-in valves and launcher/receiver. The estimated peakProject construction work force is expected to be approximately 220 workers. Millennium anticipatesapproximately 60 percent of the construction workforce for the pipeline and approximately 40 percent ofthe construction workforce for the aboveground stations will be local hires.

    1.5.2 Compliance Assurance Measures

    To ensure that construction of the Project facilities will comply with mitigation measures identified inMillennium’s applications and supporting documentation, the FERC’s environmental conditions, and therequirements of other applicable permitting agencies, Millennium will include, whenever appropriate,

    environmental requirements in its construction drawings and / or specifications. To solicit accurate bidsfor pipeline construction, Millennium will provide these specifications and advance versions of theConstruction Drawing Packages to qualified prospective pipeline contractors. Contractors selected to

    perform work on the Project will receive copies of specifications and a Construction Drawing Packagecontaining pipeline and aboveground facility drawings designated as being approved for construction.

    For those mitigation measures that address pre-construction surveys and clearances, Millennium willinclude pertinent correspondence documenting compliance with these mitigation measures in theConstruction Drawing Package. For those mitigation measures that address permit conditions fromapplicable regulatory agencies, Millennium will include copies of permits and related drawings in theConstruction Drawing Package. For those mitigation measures that, in part, address post-constructionrequirements, Millennium will include instructions and documentation that will be provided to operating

    personnel following the completion of construction. These maintenance instructions will include copiesof pertinent permits with particular reference to long-term permit conditions and reporting requirements.

    Millennium will require the selected contractors to install the proposed facilities according toMillennium’s standard specifications, the Construction Drawing Package, and the terms of a negotiatedcontract. To support the application of proper field construction methods, Millennium has generallyincorporated the FERC’s Upland Erosion Control, Revegetation and Maintenance Plan (FERC Plan) andFERC’s Waterbody and Wetland Construction and Mitigation Procedures (FERC Procedures) into theProject’s Environmental Construction Standards (ECS) to address the site-specific conditions in the

    Project area (see Appendix 1B) [Note: Not included in this draft]. Any deviations from, or additions to,the FERC Procedures have been identified in Section 1.6.2 for FERC approval prior to implementation.

    Appendix 1B includes the following plans that Millennium will implement during construction of theProject:

    • Project ECS (including Spill Prevention and Response Procedures that provide procedures forhazardous materials transportation, handling, storage, spill prevention, and spill response);

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    28/184

    Resource Report 1 – General Project Description 1-17 Eastern System Upgrade Project

    • Horizontal Directional Drill Contingency Plan (HDD Plan) [Note: Not included in this draft] that provides procedures to be followed during HDD operations to minimize the potential for releaseof drilling fluids, containment and cleanup of inadvertent releases of drilling fluids should theyoccur, and steps that will be followed if the HDD cannot be completed as planned;

    • Bedrock Blasting Plan [Note: Not included in this draft]; and

    • Environmental Complaint Resolution Procedures so that landowners and stakeholders may reportenvironmental complaints or concerns, and a process for resolving these concerns [Note: Notincluded in this draft].

    In addition, Millennium will implement its Procedures Guiding the Discovery of Unanticipated CulturalResources and Human Remains in the event that unanticipated cultural resources or human remains areencountered during construction. These procedures are included in Resource Report 4, Appendix 4B ofthis Environmental Report [Note: Not included in this draft].

    Millennium will conduct environmental training sessions for all Millennium construction managementand contractor personnel prior to and during the pipeline installation and aboveground facilityconstruction. While this training will focus on implementation of best management practices contained inthe plans in Appendix 1B, it will also include instructions on construction work area limits, permitrequirements, and other mitigation measures, as appropriate.

    Millennium will employ a minimum of one full-time Environmental Inspector for the duration of Projectconstruction. The Environmental Inspector(s) will have duties consistent with those contained inParagraph II.B. (Responsibilities of Environmental Inspectors) of the FERC Plan, including ensuringcompliance with environmental conditions attached to any Certificate issued by the FERC for the Project,

    Project environmental designs and specifications, and environmental conditions attached to other permitsor authorizations. Millennium will provide training for its Environmental Inspector(s) regarding properfield implementation of the FERC Plan and FERC Procedures, hazardous materials management, andother mitigation measures included in Appendix 1B.

    For purposes of quality assurance and compliance with mitigation measures, other applicable regulatoryrequirements, and Millennium specifications, Millennium also will be represented on the constructionsites by a Chief Construction Inspector, and one or more Craft Inspectors. Millennium’s Engineering andProject Management personnel will be responsible for designing and constructing the facilities incompliance with regulatory and non-regulatory requirements and agreements. The Construction SiteManager will address any issues of noncompliance with mitigation measures or other regulatoryrequirements. If technical or management assistance is required, the Chief Inspector will requestassistance from the appropriate Millennium personnel. Millennium’s Operator, Columbia PipelineGroup, will be responsible for long-term Project operation, maintenance and regulatory compliance.

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    29/184

    Resource Report 1 – General Project Description 1-18 Eastern System Upgrade Project

    1.6 CONSTRUCTION PROCEDURES

    1.6.1 Pipeline Facilities

    Construction of the Project will follow industry-accepted practices and procedures, as further described below. Generally, construction of the Project pipeline will follow a set of sequential operations as shownin Figure 1.6-1, Typical Pipeline Construction Sequence. In this typical pipeline construction scenario,the construction spread proceeds along the pipeline right-of-way in one continuous operation. The entire

    process will be coordinated in such a manner as to minimize the total time a tract of land is disturbed andtherefore exposed to erosion and temporarily precluded from normal use.

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    30/184

    Resource Report 1 – General Project Description 1-19 Eastern System Upgrade Project

    FIGURE 1.6-1 Typical Pipeline Construction Sequence

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    31/184

    Resource Report 1 – General Project Description 1-20 Eastern System Upgrade Project

    To minimize the impacts of construction disturbance, Millennium will implement the Project ECS. Thefollowing sections provide descriptions of activities along a typical construction spread, as well as otherspecialized construction methods that will be used to install the pipeline at waterbody and road crossings,and in wetland, residential, and agricultural areas.

    Typical Upland Pipeline Construction Procedures1.6.1.1

    The Project will be constructed in compliance with applicable federal regulations and guidelines, and thespecific requirements of the necessary permits (see Section 1.10, Permits and Approvals). Key federalrequirements and guidelines include:

    • 18 CFR Part 380 – FERC’s Regulations Implementing the National Environmental Policy Act(including § 380.15 - Siting and Maintenance Requirements);

    • 49 CFR Part 192 – Transportation of Natural Gas and Other Gas by Pipeline: Minimum FederalSafety Standards; and

    • The FERC Plan and FERC Procedures.

    The following sections provide descriptions of activities along a typical construction spread, as well asother specialized construction methods that will be used to install the pipeline at waterbody, road, and inwetland, residential, and agricultural areas.

    Surveying

    The initial step in preparing the right-of-way for construction is the civil survey. Affected landowners

    have been contacted and requested to permit Millennium agents to enter property prior to surveying andstaking of the centerline and workspaces for construction.

    The civil survey crew will stake the outside limits of the construction right-of-way, the centerline locationof the pipeline, drainage centerlines and elevations, highway crossings, and any ATWS, such as in laydown areas or at stream crossings. The “811” underground utility location system will be contacted toallow state and local utility operators to verify and mark all underground utilities (e.g., cables, conduits,and pipelines) located within the construction work areas. To further minimize the potential for damageto buried facilities, field instrumentation, or test pits excavated using “soft digging” techniques (such asexcavation by hand), will be used to locate utilities.

    Clearing and Grading

    Following surveying, the right-of-way will be cleared. Large obstacles such as trees, rocks, brush, andlogs will be removed. Trees will be felled by hand or mechanical means. When construction begins,timber and other vegetation debris may be chipped for use as erosion-control mulch, burned, sold, orotherwise disposed of in accordance with applicable state and local regulations, and landowner easement

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    32/184

    Resource Report 1 – General Project Description 1-21 Eastern System Upgrade Project

    agreements. Fences will be cut and braced along the right-of-way, and temporary gates will be installedto control livestock and limit public access.

    The right-of-way will then be graded where necessary to create a reasonably level working surface toallow safe passage of construction equipment and materials, and for operation of pipe fabrication andinstallation equipment. During the grading operation, temporary flume pipes will be installed asnecessary to maintain surface drainage. In upland areas, temporary erosion control measures such as siltfencing and interceptor dikes will be installed during topsoil and subsoil removal. Within 100 feet ofwetlands and waterbodies as well as within the 100-year floodplain, temporary erosion control measuressuch as silt fencing and interceptor dikes will be installed prior to conducting any grading activities.Conserved topsoil will typically be stockpiled along one side of the right-of-way, allowing the other sideto be used for access, material transport, and pipe assembly. Where the temporary workspace overlapswith the permanent easement associated with the existing Millennium mainline pipeline, topsoil andsubsoil will typically be stockpiled within the portion of the workspace located within the existing

    permanent easement.

    Trenching

    To bury the pipeline underground, it will be necessary to excavate a trench. The trench will be excavatedwith a rotary trenching machine, a track-mounted backhoe, or similar equipment. Generally, the trench

    bottom will be excavated at least 12 inches wider than the diameter of the pipe. The sides of the trenchwill be sloped with the top of the conventional lay trench up to 20 feet across, or more, depending uponthe stability of the native soils and the depth of cover. The trench will be excavated to a sufficient depthto allow a minimum of 3 feet of soil cover between the top of the pipe and the final land surface after

    backfilling. Additional cover will be provided at crossings of wetlands and waterbodies, agriculturallands and roads. Excavated soil will typically be stockpiled along the trench (the “spoil” side) and awayfrom the construction traffic and pipe assembly area (the “working” side). Where the pipeline is adjacentto an existing pipeline, the spoil will be placed on the same side of the trench as the existing pipeline. Noworking equipment will operate over the active pipeline unless the pipeline is adequately protected inaccordance with the foreign pipeline company’s standards. When trenching near foreign buried utilities,soft digging methods (hand excavation or an excavator bucket without teeth or side cutters) will be usedto fully excavate any foreign line (see Section 1.6.1.5). Millennium will execute a one call prior toconstruction in a foreign utility location. If a foreign line is accidentally damaged during construction, aMillennium representative will shut down activities and evacuate the area. Millennium will make alleffort to have a foreign line representative onsite during excavation to facilitate quicker shut down in the

    event of accidental damage. Millennium will implement the Project ECS (Appendix 1B) duringconstruction in the vicinity of overhead electric lines.

    • Trench Depth

    o Trench depths are dependent on the size of pipe and the minimum cover requirements. Itis currently anticipated that trench depths in upland areas, where 36 inches of cover is to

    be maintained, will be approximately six to eight feet in depth.

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    33/184

  • 8/19/2019 Millennium Pipeline Proposal

    34/184

    Resource Report 1 – General Project Description 1-23 Eastern System Upgrade Project

    filter bag. Filter bags will not be used within 100 feet of wetlands or waterbodies. The dewateringstructure will be removed as soon as possible after completion of the dewatering activities. Trench plugswill be used where necessary to separate the upland trench from adjacent wetlands or waterbodies to

    prevent the inadvertent draining of the wetland or diversion of water from the waterbody into the pipetrench.

    Stringing

    Steel pipe will be procured in nominal 40-foot, 60-foot, and/or 80-foot lengths, or “joints,” protected withan epoxy coating applied at the factory or at a coating yard (the beveled ends will be left uncoated forwelding) and shipped to strategically located materials storage areas, or “pipeyards.” The individual

    joints will be transported to the right-of-way by truck and placed along the excavated trench in a single,continuous line, easily accessible to the construction personnel on the working side of the trench,typically opposite the spoil side. This will allow the subsequent lineup and welding operations to proceed

    efficiently. At stream crossings, the amount of pipe required to span the stream will be stockpiled inATWS on one or both banks of the stream.

    Pipe Bending

    The pipe will be delivered to the job site in straight joints. While some induction bends may be used,some bending of pipe will be required to allow the pipeline to follow natural grade changes and directionchanges of the right-of-way. Prior to welding, selected joints will be bent in the field by track-mountedhydraulic bending machines.

    Pipe Assembly and Welding

    Following stringing and bending, the joints of pipe will be placed on temporary supports, adjacent to thetrench. The pipe joints will be carefully aligned with clamps and welded together using multiple passesfor a full penetration weld. Only qualified welders will be allowed to perform the welding. Welders andwelding procedures will be qualified according to applicable American Society for Mechanical Engineers,API, and 49 CFR Part 192 Standards.

    Non-Destructive Examination and Weld Repair

    To ensure that the assembled pipe will meet or exceed the design strength requirements, 100 percent ofthe pipeline girth welds will be visually inspected and tested for integrity using non-destructiveexamination methods such as radiography (X-ray) or ultrasound, in accordance with API standards.Welds displaying unacceptable slag inclusions, void spaces, or other defects will be repaired or cut out,re-welded, and re-inspected.

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    35/184

    Resource Report 1 – General Project Description 1-24 Eastern System Upgrade Project

    Coating Field Welds, Inspection, and Repair

    Following welding, the previously uncoated ends of the pipe at the joints will be cleaned and epoxycoated in accordance with Millennium’s specifications. The coating on the completed pipe section will beinspected and any damaged areas will be repaired and re-inspected.

    Lowering-In

    The completed section of pipe will be lifted off the temporary supports and lowered into the trench byside-boom tractors or equivalent equipment. Prior to lowering the pipe, the trench will be inspected toensure that it is free of rocks and other debris that could damage the pipe or the coating, and that thetrench and pipe configurations are compatible, and then the pipe will be lowered-in. In rocky areas, if the

    bottom is not smooth, a layer of soil or sand may be placed on the bottom of the trench to protect the pipeand coating from damage. Concrete coating and/or set-on or saddle bag type weights will be used as

    required to maintain negative buoyancy in areas of saturated soils.

    Padding and Backfilling

    After the pipe is lowered into the trench, the trench will be backfilled. Previously excavated materialswill be pushed back into the trench using bladed equipment or backhoes. Where the previously excavatedmaterial contains large rocks or other materials that could damage the pipe or coating, the subsoil will besifted to remove any rock greater than one inch from the padding material, or clean fill and/or protectivecoating (rock shield) will be placed around the pipe prior to backfilling. Segregated topsoil, whereapplicable, will be placed after backfilling the trench with subsoil. Following backfilling in agriculturalland, grassland, and open land, or in specified areas, a small crown may be left in certain areas if

    requested by a landowner to account for any future soil settling that might occur. Excess soil will only bedistributed in upland areas evenly on the right-of-way, while maintaining existing contours.

    A caliper pig run will be completed after backfill to ensure there are no dents or damage to the pipe as aresult of the construction and backfill process.

    Hydrostatic Test and Final Tie-In

    Following backfilling of the trench, the pipeline will be hydrostatically tested in a manner that meets orexceeds the requirements of 49 CFR Part 192 to ensure that it is capable of safely operating at the design

    pressure. Millennium proposes to use approximately 2.1 million gallons of water for hydrostatic testingon the Huguenot Loop. Millennium is currently identifying potential source water for hydrostatic testingactivities. Water will be obtained and discharged within the Lower Hudson Watershed, no inter-basintransfer of water is anticipated. A table identifying the total amount of water that would be used for theProject, potential source water, and milepost locations is included in Resource Report 2 [Note: Notincluded in this draft].

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    36/184

    Resource Report 1 – General Project Description 1-25 Eastern System Upgrade Project

    The pipeline will be capped and filled with water and the current plan is to test it in multiple test sectionsdue to elevation changes. The water in the pipe will be pressurized and held for a minimum of eighthours in accordance with the Pipeline and Hazardous Materials Safety Administration requirementsidentified in 49 CFR Part 192. Any loss of pressure that cannot be attributed to other factors, such astemperature changes, will be investigated. Any leaks detected will be repaired and the segment will beretested.

    The test water will be discharged through an energy-dissipating device in compliance with the FERCProcedures and any state-specific requirements included in the applicable state discharge permits. Oncethe pipe has been successfully tested and dried to the specified dew point, the test cap and manifold will

    be removed.

    Millennium will implement applicable requirements of the FERC Procedures regarding hydrostatictesting, as well as any specifications listed in individual state permits. Unless expressly permitted or

    approved, there will be no direct discharge into state-designated exceptional value waters or scenic rivers.

    Cleanup and Restoration

    Post-construction restoration activities will be undertaken in accordance with the applicable measures inthe FERC Plan and FERC Procedures, other permit or agency requirements, and requirements in thelandowner easement agreements. After a segment of pipe has been installed and backfilled, the right-of-way, ATWS, and other disturbed areas will be finish-graded, and the construction debris will be disposedof properly. The surface of the right-of-way disturbed by construction activities will be graded to matchoriginal contours and to be compatible with surrounding drainage patterns, except at those locationswhere permanent changes in drainage will be required to prevent erosion, scour, and possible exposure ofthe pipeline. Segregated topsoil will be returned to its original horizon, unless otherwise requested by thelandowner. Temporary and permanent erosion and sediment control measures, including silt fencing,diversion terraces, and vegetation, will be installed at that time. Temporary erosion and sedimentcontrols, including silt fence and other non-biodegradable measures, will be removed once disturbed areashave been stabilized. Private and public property, such as fences, gates, driveways, and roads, whichhave been disturbed by the pipeline construction, will be restored to original or better condition.

    Wetland Construction Procedures1.6.1.2

    Millennium has considered minimizing potential impacts to wetlands during selection of its proposed

    route and will avoid or minimize wetland disturbance to the extent practicable. Where wetlands cannot be avoided, crossings of jurisdictional wetlands will be done in accordance with applicable permits andapprovals, and the FERC Procedures, including any deviations requested by Millennium and approved bythe FERC.

    Operation of construction equipment in wetlands will be limited to that needed to clear the right-of-way,excavate the trench, fabricate and install the pipe, backfill the trench, and restore the right-of-way.Millennium will segregate the topsoil over the trench up to 12 inches in depth in wetlands where

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    37/184

    Resource Report 1 – General Project Description 1-26 Eastern System Upgrade Project

    hydrologic conditions permit this practice. Segregated topsoil will be piled a minimum of two feet fromsubsoil and replaced in the trench following subsoil backfilling. In accordance with the FERCProcedures, with the exception of pumps required for dewatering, fuel and/or equipment will not bestored within 100 feet of wetlands or other waterbodies unless otherwise approved by the FERC.Restoration and monitoring of wetland crossings will be conducted in accordance with the FERCProcedures to ensure successful wetland revegetation.

    Unsaturated Wetland Crossings

    In crossing unsaturated wetlands (wetlands without standing water or saturated soils), construction will besimilar to the typical upland construction described above, with additional measures to protect wetlandresources. If normal construction equipment begins to rut or would result in mixing of wetland topsoiland subsoil, low ground pressure equipment will be used, or temporary board or timber equipment matswill be installed to allow passage of equipment with minimal disturbance of the surface and vegetation.

    Trees will be cut to grade, but stumps will only be removed from the trench line and from the workingside where necessary for safety. Topsoil over the pipe trench will be segregated from subsoils and piled aminimum of two feet apart. A vegetation buffer zone may be left between the wetland and the uplandconstruction areas, except for the pipe trench and travel lane and as site-specific conditions warrant.Erosion control measures such as silt fences, interceptor dikes, and straw/hay bale structures will beinstalled and maintained to minimize sedimentation into off-right-of-way areas. Trench plugs will beinstalled where necessary to prevent the unintentional draining of water from the wetland. Uponcompletion of construction, the right-of-way will be restored and a 10-foot-wide strip centered on the

    pipeline will be maintained in an herbaceous state.

    Saturated Wetland Crossings

    For saturated wetlands, including those with standing water at the time of construction, topsoilsegregation may not be practical. Equipment mats or timber mats will be used to facilitate equipmentmovement through and work within the wetland. Otherwise, construction will be similar to that describedabove for unsaturated wetlands.

    Waterbody Construction Procedures1.6.1.3

    Millennium will follow the FERC Procedures to limit water quality and aquatic resource impacts duringand following construction. Construction activities will be scheduled so that the pipeline trench isexcavated as close to pipe laying activities as reasonably possible. In accordance with the FERCProcedures and where the pipeline will not be installed using HDD, the duration of construction across

    perennial waterbodies will be limited to 48 hours (24 hours to cross the waterbody and 24 hours forrestoration) across minor waterbodies (10 feet wide or less) and intermediate waterbodies (between 10and 100 feet wide). Banks will be returned to as near to pre-construction conditions as possible within 24hours of completion of each open-cut crossing. Any deviations in timing that would result in extendedcrossing durations will be identified in advance by Millennium and notification made to FERC with site-specific justification.

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    38/184

    Resource Report 1 – General Project Description 1-27 Eastern System Upgrade Project

    Construction methods at waterbody crossings will vary with the characteristics of the waterbodyencountered, and will be performed consistent with applicable permits and authorizations. Pipe will beinstalled to provide a minimum of five feet of cover from the waterbody bottom to the top of the pipeline.The bottom of the pipeline trench will be excavated to a width of at least 12 inches greater than thediameter of the pipe or to a greater width to allow proper backfill beneath and along the sides of the

    pipeline.

    Trench spoil will be placed on the bank above the high water mark for use as backfill. Excavated spoilthat is stockpiled in the construction right-of-way will be at least 10 feet from the stream bank or inapproved ATWS, and will be surrounded by sediment control devices to prevent sediment from returningto the waterbody. Where the pipeline is prefabricated for installation across the waterbody, the pipelinesegment will be long enough to extend for a minimum of 10 feet past the high banks on each side of thewaterbody before raising in elevation to the normal trench level. All adjacent pipelines will be protected

    as necessary.

    Normal backfill cover requirements will be met and backfill compacted so that it will be equal to or abovethat of the adjacent undisturbed areas. Trench plugs of sandbags or similar material may also be used tokeep backfill from sloughing in toward the center of the waterbody. All waterbody banks will be restoredto as close to the original grade as reasonably possible, while preventing long-term erosion. All erosioncontrol materials or other materials used for the crossing will be removed from the waterbody, andexcavated material not required for backfill will be removed and disposed of at an upland site.

    The proposed crossing method for each waterbody is provided in Table 2A-1 in Resource Report 2 [Note: Not included in this draft]. Millennium will use the dry waterbody crossing method for waterbodies withno discernible flow at the time of crossing and the dry-ditch (i.e., dam and pump or flume) crossingmethods for minor and intermittent waterbodies where there is discernable flow within the waterbody atthe time of crossing. The dry-ditch waterbody crossing method used at each specific crossing (dam and

    pump or flume) will be dependent upon the conditions encountered at the time of construction. Onemajor waterbody crossing (i.e., those greater than 100 feet wide) is proposed, the Neversink River (MP0.3). Millennium is currently evaluating the use of a trenchless crossing technique for the NeversinkRiver. A site-specific crossing plan for this waterbody is included in Appendix 1C (Site-specific HDD

    plans) [Note: Not included in this draft].

    Dry Waterbody Crossing Method

    A dry waterbody crossing will use methods similar to conventional upland open-cut trenching. The drywaterbody construction method will involve excavation of the pipeline trench across the dry stream bed,installation of a prefabricated segment of pipe, and backfilling of the trench with native material.Depending upon the width of the crossing and the reach of the excavating equipment, excavation and

    backfilling of the trench will generally be accomplished using backhoes or other excavation equipmentoperating from one or both banks of the dry streambed. If necessary for reach, the equipment mayoperate within the dry streambed. Equipment in the dry streambed will be limited to that needed to

    20160219-5211 FERC PDF (Unofficial) 2/19/2016 4:31:10 PM

  • 8/19/2019 Millennium Pipeline Proposal

    39/184

    Resource Report 1 – General Project Description 1-28 Eastern System Upgrade Project

    complete the crossing. All other construction equipment will cross the dry streambed using equipment bridges, unless otherwise allowed by the FERC Procedures for minor waterbody crossings.

    The “dry waterbody” crossing method shall only be used in streams that have no discernable flow duringthe time of construction, provided that a contingency plan is developed that prescribes measures to betaken in case of a storm event during trenching. Measures shall include, but are not limited to: monitoringweather conditions closely during work within the stream channel; moving equipment and materialsoutside of the stream channel if a storm event is predicted; installing a temporary waterbody crossingmethod prior to the predicted storm event; and temporarily stabilizing the stream channel.

    Dam and Pump Crossing Method

    The dam and pump method involves installation of temporary dams upstream and downstream of thewaterbody crossing. The temporary dams typically will be constructed using sandbags and plastic

    sheeting. Following dam installation, appropriately sized pumps will be used to dewater and transport thestream flow around the construction work area and trench. Intake screens will be installed at the pumpinlets to prevent entrainment of aquatic life, and energy dissipating devices will be installed at the pumpdischarge point to minimize erosion and stream bed scour. Trench excavation and pipeline installationwill then commence through the dewatered portion of the waterbody channel. Following completion of

    pipeline installation, backfill of the trench, and restoration of stream banks, the temporary dams will beremoved, and flow through the construction work area will be restored. This method is generally onlyappropriate for those waterbody crossings where pumps can adequately transfer the stream flow volumearound the work area and there are no concerns