Milestone DeliverablesA Guide to Managing IT Implementation Projects
8/8/2019 Milestonedeliverables
2/8
1
Milestone Deliverables
A Guide to Managing IT Implementation Projects
Contents
Introduction ..................................................................................... 2
Drive One Leg at a Time: the 14 Milestone Trip ..................................... 3
Why Milestone Deliverables Succeeds Where Other Methodologies Fail ..... 4A Methodology that Works for Any Implementation in Any Industry ......... 5
How You Can Master the Milestone Deliverables Methodology ................. 6
About the Author .............................................................................. 7
8/8/2019 Milestonedeliverables
3/8
2
Introduction
When Pemeco was founded in 1978, the firm decided to distinguish itself from other
consulting firms by committing itself to flawless project management. Weunderstood that the only way our firm would stand the test of time was by setting
and meeting high expectations relating to project time, quality and cost.
Our proprietary Milestone Deliverables implementation methodology was born out
of this commitment. The methodology has evolved over the last 30-plus years, but
its core remains the same. Equally important: our commitment to the methodology
has never wavered.
As a result, since 1978, we have completed 50 large IT implementation and
countless smaller ones with ZERO failures. This means that all of our projects have
met key metrics relating to on-time delivery, within-budget delivery and client
satisfaction.
The Milestone Deliverables methodology succeeds where other methodologies fail
because it is a cut-to-the-chase approach to implementation. It slices through the
touchy-feely paralysis by analysis and endless dialogue of consultant-speak.
Instead, it is focused on clearly defined process and tangible results.
Since the late 1970s, scores of Pemecos clients have implemented complex IT
systems. As the projects and companies became progressively more complex, our
team members avoided floundering by focusing on scope definition, rigorous
change control, and tightly monitored phase execution.
A clearly defined project roadmap is central to our Milestone Deliverables
methodology. Each roadmap is drawn using periodic signposts. At every stage of a
project, our team and the clients can look up the signposts to determine whether
theyre on the right track. Also, these signposts help them decide on detours and
corrections with minimal disruption.
The Milestone Deliverables methodology evolved from this roadmap analogy. It
provides a framework that structures the myriad tasks into a simple, deliverable-oriented model.
8/8/2019 Milestonedeliverables
4/8
3
Drive One Leg at a Time: the 14 Milestone Trip
Each project, like a well-organized road-trip, is broken downs into legs, or phases.
This way, the driver can focus on identifiable landmarks instead of on animperceptible final destination.
Specifically, the project is broken down into manageable tasks. Project tasks are
accompanied by 14 tangible deliverables, strategically sprinkled throughout the
projects phases. Completing a deliverable signifies the completion of a particular
milestone. And this completion is often a prerequisite to the start of the next
phase.
The format of these deliverables is not set in stone . In fact, this methodology does
not intend to limit the choice of ERP, CRM, SCM, PLM, project support software,networking gear, or any other IT technology. Nor does it intend that the sample
reports be used without modification. What is important is faithfulness to the
principle that the project team be managed to produce high-quality, tangible results
in a timely fashion.
Without further ado, the 14 Milestone Deliverables are:
1. Project and Subsidiary Plans to list project objectives and scope2. Kickoff Presentation to signal the start of implementation execution3. Core Team Training Courses to teach IT overviews and details4. Business Scenario Liststo list each departments processes5. Blueprint White Papersto document each departments operations6. Gaps and Issues Database for tracking and reporting of gaps and issues7. Change Management Planto lay out end users skills upgrades8. Walkthrough Presentations ofeach departments business processes9. 80% and 20% Scenario Scripts to detail end pilot user instructions10.User Training Courses to teach new operating methods and technology11.User Documentation of all deliverables
12.IT Specifications to detail customizations, interfaces, and special projects
13.Migration Plan to map out tasks for conversion and entry of legacy data
14.Cutover Planto document the project final weeks tasks
8/8/2019 Milestonedeliverables
5/8
4
Why Milestone Deliverables Succeeds Where Other Methodologies Fail
The Milestone Deliverables premise is simple and powerful: If you provide
managers and their teams with an ability to measure the project outputs, you willbe rewarded with an organizational culture that is focused on deliverables and
results.
Each team member benefits from managing by deliverables. Working with their
personalized work package in a simple intuitive framework, they gain instant clarity
on the scope of their assignments and associated deliverables.
And the deliverables themselves are like a good wine they constantly improve
with age throughout the projects lifecycle. As the team gathers more information,
and resolves outstanding problems and issues, the deliverables evolve into better
and more complete versions of themselves.
This Milestone Deliverables methodology is a process-oriented approach to
managing people, objectives, and tasks. It has evolved continuously over 30-plus
years and assumes that people are more effective and better motivated when
working towards smaller, finite goals. Completion of these goals is signified by the
production of tangible end products. And with this feedback, managers are
empowered to keep the project on track.
8/8/2019 Milestonedeliverables
6/8
5
A Methodology that Works for Any Implementation in Any Industry
IT systems implementations are extremely complex and touch all aspects of a
business operations. The Milestone Deliverables methodology has been used toimplement all kinds of IT projects in a variety of companies around the world,
including:
A multi-national provider to the worldwide nuclear power market A diversified multi-national manufacturing provider to aerospace, ground
defense, railroad, and fire & rescue industries
A multi-national designer and manufacturer of pressure relief and safetyrelief valves, air driven pumps, boosters, power units, and nitrogen productboosters
A global leader in the animal agriculture industry, providing goods andservices to the leading commercial food producers worldwide
A leading provider of voice technologies, systems that manage patientinformation, and recording solutions for contact centers, public safety and
correctional facilities
A medium-sized plastic and fabric manufacturer and distributor A multi-national manufacturer and distributor of security and banking
systems
A manufacturer and distributor of truck bodies A multi-national manufacturer and distributor of printer ribbons An international manufacturer of computer components An international manufacturer and distributor of bathroom accessories An international manufacturer and distributor of forestry equipment An international manufacturer and distributor of electronic musical
instruments
8/8/2019 Milestonedeliverables
7/8
6
How You Can Master the Milestone Deliverables Methodology
You can learn the complete Milestone Deliverables process and how to customize
it to your organizations needs at Pemecos two-day seminar Managing a
Successful IT Project Implementation.
By participating in this event, youll learn how to:
Drive your project to success where most fail Break the implementation project into easily managed tasks making
it easier to keep your team focused and motivated
Develop accurate budget projections and ferret out the hidden coststhat cause most budget overruns
Develop a realistic project timeline and keep the project running onschedule
Manage scope creep and other project changes that distract your team without sacrificing your deadlines or budget
Guarantee your IT application enhances productivity and that itworks exactly as envisioned
Help change your companys cultureand the way employees work soyou get the biggest return on your ERP investment
Build credibility with top management so you get the support youneed for a successful IT implementation
And much more. Full details about this event can be found athttp://www.pemeco.com/seminar
Attend & receiveA FREE HALF-DAY IT PROJECT CONSULTATION. The
consultation will help you analyze your organizations readiness to implement your IT
project, to spot the wrinkles and flaws in your implementation plan, or to get your
implementation project back on track.
http://www.pemeco.com/seminarhttp://www.pemeco.com/seminarhttp://www.pemeco.com/seminar8/8/2019 Milestonedeliverables
8/8
7
Learn more about the Milestone Deliverables Implementation Methodology and
Pemecos services: including IT readiness assessments, IT action plans.
Call: (514) 910-5079 Email:[email protected] Website: www.pemeco.com
About the Author
Peter Gross. Pemecos President, has over 30 years of management consulting and
information processing experience. His cross-sector expertise in IT system
selection, business planning, corporate restructuring, and project management
spans the globe. Peter developed Pemecos proprietary Milestone Deliverables
implementation methodology. His book, Milestone Deliverables: The Hands-
On Approach to Implementing IT Projects sells in more than 40 countries.