ID Task Name Duration Start Finish Predecessors 1 PIER FABRICATION & ERECTION 731 days Feb 27 '16 Jun 28 '18 2 Preliminary works 641 days Mar 12 '16 Mar 29 '18 35 Pier Fabrication 473 days Feb 27 '16 Aug 31 '17 36 PIER 20 149 days Feb 27 '16 Aug 18 '16 724 PIER 30 214 days Mar 10 '16 Nov 14 '16 1910 PIER 60 208 days Jul 15 '16 Mar 14 '17 2598 PIER 40 235 days Apr 12 '16 Jan 10 '17 4116 PIER 50 240 days May 24 '16 Feb 27 '17 5302 Trestles Fabrication 379 days Jun 16 '16 Aug 31 '17 5303 Trestle 41 to 49 Foot matching cone 205 days Jun 16 '16 Feb 9 '17 5311 Trestle 41 & 49 182 days Feb 1 '17 Aug 31 '17 5484 Trestle 42 & 48 158 days Mar 1 '17 Aug 31 '17 5593 Trestle 43 & 47 130 days Apr 2 '17 Aug 31 '17 5638 Trestle 44 & 46 53 days Jul 1 '17 Aug 31 '17 5651 Pier Erection 612 days Jul 15 '16 Jun 28 '18 5652 Pier Erection-S20 67 days Jul 15 '16 Sep 30 '16 5715 Pier Erection-S30 120 days Aug 15 '16 Dec 31 '16 5792 Pier Erection-S60 104.63 days Mar 2 '17 Jul 1 '17 5855 Pier Erection-S40 76.13 days Jan 2 '17 Mar 31 '17 6001 Temporary pier erection over S40 24 days Apr 1 '17 Apr 29 '17 6003 Pier Erection-S50 63.25 days Feb 1 '17 Apr 15 '17 6121 Temporary pier erection over S50 16 days Apr 15 '17 May 4 '17 6123 Trestle Erection 41 & 49 74.5 days Dec 26 '17 Mar 22 '18 6173 Trestle Erection 42 & 48 52.5 days Dec 26 '17 Feb 24 '18 6209 Trestle Erection 43 & 47 41 days Feb 24 '18 Apr 13 '18 6231 Trestle Erection 44 & 46 65.5 days Apr 13 '18 Jun 28 '18 6246 Balance Pier Erection 40 days Jan 9 '18 Feb 23 '18 Qtr 3 Qtr 1 Qtr 3 2011 2020 2 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Progress Deadline PIER FABRICATION & ERECTION 1 of 1 Project: 2.3.16 Date: Jun 1 '16

Microsoft Project - R2

Embed Size (px)

DESCRIPTION

Microsoft Project - R2

Citation preview

ID Task Name Duration Start Finish Predecessors

1 PIER FABRICATION & ERECTION 731 days Feb 27 '16 Jun 28 '18

2 Preliminary works 641 days Mar 12 '16 Mar 29 '18

35 Pier Fabrication 473 days Feb 27 '16 Aug 31 '17

36 PIER 20 149 days Feb 27 '16 Aug 18 '16

724 PIER 30 214 days Mar 10 '16 Nov 14 '16

1910 PIER 60 208 days Jul 15 '16 Mar 14 '17

2598 PIER 40 235 days Apr 12 '16 Jan 10 '17

4116 PIER 50 240 days May 24 '16 Feb 27 '17

5302 Trestles Fabrication 379 days Jun 16 '16 Aug 31 '17

5303 Trestle 41 to 49 Foot matching cone 205 days Jun 16 '16 Feb 9 '17

5311 Trestle 41 & 49 182 days Feb 1 '17 Aug 31 '17

5484 Trestle 42 & 48 158 days Mar 1 '17 Aug 31 '17

5593 Trestle 43 & 47 130 days Apr 2 '17 Aug 31 '17

5638 Trestle 44 & 46 53 days Jul 1 '17 Aug 31 '17

5651 Pier Erection 612 days Jul 15 '16 Jun 28 '18

5652 Pier Erection-S20 67 days Jul 15 '16 Sep 30 '16

5715 Pier Erection-S30 120 days Aug 15 '16 Dec 31 '16

5792 Pier Erection-S60 104.63 days Mar 2 '17 Jul 1 '17

5855 Pier Erection-S40 76.13 days Jan 2 '17 Mar 31 '17

6001 Temporary pier erection over S40 24 days Apr 1 '17 Apr 29 '17

6003 Pier Erection-S50 63.25 days Feb 1 '17 Apr 15 '17

6121 Temporary pier erection over S50 16 days Apr 15 '17 May 4 '17

6123 Trestle Erection 41 & 49 74.5 days Dec 26 '17 Mar 22 '18

6173 Trestle Erection 42 & 48 52.5 days Dec 26 '17 Feb 24 '18

6209 Trestle Erection 43 & 47 41 days Feb 24 '18 Apr 13 '18

6231 Trestle Erection 44 & 46 65.5 days Apr 13 '18 Jun 28 '18

6246 Balance Pier Erection 40 days Jan 9 '18 Feb 23 '18

Qtr 3 Qtr 1 Qtr 32011 2020 2029

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Progress

Deadline

PIER FABRICATION & ERECTION

1 of 1

Project: 2.3.16Date: Jun 1 '16