TITLE:
CLIENT: Sociedad Minera Cerro Verde S.A.A. MI09H060-260-3-LM-001
PROJECT:
PROJECT N°: 15315 / MI09H060 15315-2600-42EL-001
Project Manager : Eng. José Luis Córdova H.
Project Engineer : Eng. César Gutiérrez
Lead : Eng. Juan Pablo Sotelo
Client : Eng. Carlos Requejo
Rev. By Description Date Checked Approved
A P. Benedetti 23.Ago.10 J. P. Sotelo
B F. Montoya 31.Ago.10 J. P. Sotelo
C P. Benedetti 07.Set.10 J. P. Sotelo
0 F. Montoya 10.Set.10 J. P. Sotelo
1 N. Martinez 17.Nov.10 J. P. Sotelo
Comments:
PAD 4B – FASE 1 ACTUALIZACIÓN DE INGENIERÍA DE DETALLE
PAD 4B - PHASE 1 DETAIL
ENGINEERING UPDATE
SNC - LAVALIN DOCUMENT NUMBER:
Emitido para Aprobación del Cliente
Emitido para Coordinación Interna
C. Gutiérrez
C. Gutiérrez
Approved by:
Sheet
1 of 30
SMCV DOCUMENT NUMBER:
LISTA DE MATERIALESESTRUCTURAS DE CONCRETO
BILL OF MATERIAL
CONCRETE STRUCTURES
Actualización de Metrados C. Gutiérrez
Emitido para Aprobación del Cliente
Emitido para Construcción C. Gutiérrez
C. Gutiérrez
2 of 30
Page N°
1.0 INTRODUCCIÓN / INTRODUCTION 3
1.1 ALCANCES / SCOPE 3
1.2 DESCRIPCIÓN / DESCRIPTION 3
2.0 RESUMEN DE METRADOS / SUMMARY OF QUANTITIES 4
3.0 APENDICES / APPENDICES
13APENDICE A - SUSTENTO DE METRADOS / APPENDIX A - SUSTENTATION OF QUANTITIES
TABLA DE CONTENIDOS / TABLE OF CONTENTS
SheetRevisionPAD 4B - PHASE 1
DETAIL ENGINEERING UPDATE
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
15315-2600-42EL-001
3 of 30
1.0 INTRODUCCIÓN / INTRODUCTION
1.1 ALCANCE / SCOPE
El presente documento reporta el listado de materiales para las estructuras de concreto que forman parte de las obras
electromecánicas del proyecto PAD 4B Fase 1.
The current document reports the bill of materials for the concrete structures that belongs to the electromechanical
works of the Project PAD 4B Phase 1
1.2 DESCRIPCIÓN / DESCRIPTION
1.1 MATERIALES A EMPLEARCONCRETO ESTRUCTURAL / STRUCTURAL CONCRETE
Cimentaciones de bombas y Estaciones de bombeo y medición.
Pump foundation and pumping & Control Stations. Kg/cm2
Cimentaciones en general, losas, vigas, columnas, pedestales y muros.
General foundations, slabs, beams, columns, pedestals & walls. Kg/cm2
Otras estructuras de concreto.
Other concrete structures. Kg/cm2
CONCRETO SIMPLE / SINGLE CONCRETE
Concreto ciclópeo, bando de ductos, veredas y rampas de acceso.
Cyclopean concrete, cuctbacks, sidewalks and access ramps. Kg/cm2
CONCRETO POBRE: SOLADOS / LEAN CONCRETE
Poor concrete, ductbanks, leveling concrete for foundations. Kg/cm2
CEMENTO / CEMENT
Resistente al ataque de Cloruros y sulfatos / Resistant to chlorides and sulfates Tipo V
ACERO DE REFUERZO / REINFORCEMENT STEEL
Esfuerzo de fluencia mínimo / Minimum yield stress Kg/cm2
RECUBRIMIENTO PARA EL REFUERZO / COVERING TO REINFORCEMENT
Concreto colocado contra el suelo / Concrete placed against earth cm.
Concreto expuesto al suelo o intemperismo / Concrete exposed to earth or weather
Barras # 6 o mayores / # 6 Bars or more cm.
Barras # 5 o menores / # 5 Bars or less cm.
15315-2600-42EL-001
5.00
4.00
350
4200
7.50
280
210
175
100
SheetRevisionPAD 4B - PHASE 1
DETAIL ENGINEERING UPDATE
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
4 of 30
15315-2600-42EL-001
SheetRevisionPAD 4B - PHASE 1
DETAIL ENGINEERING UPDATE
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
Concreto no expuesto al suelo o intemperismo / Concrete not exposed to earth or weather
Losas y muros / Slabs and walls cm.
Otros / Others cm.
PARRILLAS DE FIBRA DE VIDRIO / FIBER GLASS GRATING
REVESTIMIENTO POLIMÉRICO ANTIACIDO / ANTACID POLYMERIC COVER
GEOMEMBRANA / GEOMEMBRANE
Parrilla de Fibra de vidrio GR-15 SM (1.1/2" SM-PRFV) / Fiber Glass Grating GR-15 SM (1.1/2" SM-PRFV)
2.00
4.00
Insertos GSE Polylock ó similar a todo el contorno para soldar geomembrana
Polylock GSE or similar to contour for welding geomembrane.
Marca FIBRAQUIM ó similar, recubrimiento para losas de piso, muros, canaletas de drenaje y sumideros.
For ground slabs, walls, drainage channels and floor drain made FRIBRAQUIM or similar
Instalación de geomembrana de HDPE 1.5 mm lisa en canal de tuberías.
Smooth Geomembrane HDPE 1.5 mm on pipe channels.
5 of 30
1.3.1.1.1.2
1.3.1.1.1.3
1.3.1.1.1.41.3.1.1.1.51.3.1.1.1.6
1.3.1.1.21.3.1.1.2.1
1.3.1.1.2.2
1.3.1.1.2.3
1.3.1.1.2.41.3.1.1.2.51.3.1.1.2.61.3.1.1.2.71.3.1.1.2.81.3.1.1.2.91.3.1.1.2.10
1.3.1.1.2.11
1.3.1.1.2.121.3.1.1.2.13
1.3.1.2.1.1
1.3.1.2.1.21.3.1.2.1.31.3.1.2.1.4
1.3.1.2.2.1
1.3.1.2.2.21.3.1.2.2.31.3.1.2.2.4
1.3.1.3
1.3.1.4
1.3.1.4.1.1
Instalación de geomembrana de HDPE 1.5 mm lisa en canal de tuberías m2
25.64
12.00
8009.82
525.36
113.30
269.70
0.94
57.45
24.65
4.34
97.92
17.90
77.60
308.29
11557.53
284.63
44.89
54.39
16.04
48.00
18.86
14.78
m3
kg
m3
m3
kg
129.68
38.90
Superficie de rodadura, E=200mm
Relleno y compactación con material propio seleccionado para estructuras, al 95% del Próctor Modificado.
m3
m3
m3
m3
m
m2
56.85
7.66
m
m
Instalación de insertos Polylock en estructuras de concreto, bases de equipos, losas y recubrimiento de tuberías
1.3.1.2.1
1.3.1.2
1.3.1.2.2
Civil
Concreto
m2
kg
kg
m3
m3
m3
m3
m3
m3
m3
m3
A1-MI09H060-260-35-110
Planos
Excavación masiva en terreno natural o suelto para explanaciones
Protección del concreto con recubrimiento con concreto polimérico
SISTEMA DE IMPULSION
SISTEMA DE IMPULSION DE RIEGO ILS
ESTACIÓN DE MEDICIÓN DE ILS
Civil
Relleno con material préstamo para estructuras. al 95% del Próctor modificado.
Superficie de rodadura, E=200mm
Concreto
A1-MI09H060-260-35-111
30% DE EXCAVACIONES
A1-MI09H060-260-55-023
A1-MI09H060-260-58-200
A1-MI09H060-260-30-101
A1-MI09H060-260-58-209
Planos
A1-MI09H060-260-41-118A1-MI09H060-260-41-120
Planos
Civil
Concreto
TUBERIAS DE ILS DESDE PONDS 1 Y 2 HASTA PONDS 4
13064.00
Civil
ITEM
Revision
CANT. COMENTARIOSUND.
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
15315-2600-42EL-001
DESCRIPCION
Sheet
1
Suministro y colocación de pernos de anclaje ASTM A 36
Concreto f'c= 100 kg/cm2 para solados
Excavación local en terreno natural o suelto para estructuras
Parrilla GR-15 SM (1.1/2" SM-PRFV) Fibra de vidrio
TUBERIA PRINCIPAL ILS
m3 98.85
1.3.1.3.2
1.3.1.4.1
Excavación masiva en terreno natural o suelto para explanaciones
TUBERIAS SECUNDARIAS DE RIEGO DENTRO DEL PAD
Concreto f'c= 280 kg/cm2 para anclajes de tuberías, según lo indicado en planos
1.3.1.1.1.1
Excavación en terreno natural o suelto para estructuras (incluye excavación de cunetas en tierra y eliminación de material excedente).
Relleno con material propio seleccionado para estructuras (incluye excavación de cunetas en tierra y eliminación de material excedente) al 95% del Próctor modificado.
Concreto f'c= 210 Kg/cm2 para canaletas de drenaje, cimentaciones de cercos
Concreto f'c= 100 kg/cm2 para solados
Eliminación de material excedente
Eliminación de material excedente
Acero de refuerzo fy = 4200 kg/cm2
1.3
1.3.1
1.3.1.1
1.3.1.1.1
30% DE EXCAVACIONES
Acero de refuerzo fy = 4200 kg/cm2
Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, losa de piso y pedestales, según lo indicado en planos
Concreto f'c= 350 kg/cm2 para cimentaciones de equipos, losa de manifold y pedestales, según lo indicado en planos
Suministro y colocación de pernos de anclaje ASTM A 36
Suministro y colocación de grout cementicio E=25mm
Juntas de construcción (incluye juntas de contracción)
Juntas de expansión (incluye juntas de dilatación y aislamiento)
m3
m3
1.3.1.3.1
6 of 30
ITEM
Revision
CANT. COMENTARIOSUND.
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
15315-2600-42EL-001
DESCRIPCION
Sheet
1
1.3.1.4.1.2
1.3.1.4.1.3
1.3.1.4.1.41.3.1.4.1.5
1.3.1.4.1.6
1.3.1.4.1.7
1.3.1.4.2.1
1.3.1.4.2.21.3.1.4.2.31.3.1.4.2.4
1.3.2.1.1.1
1.3.2.1.1.21.3.2.1.1.3
1.3.2.1.1.4
1.3.2.1.1.5
1.3.2.2
1.3.3.1.1.5
1.3.3.1.2
A1-MI09H060-260-30-006
1.3.2.1.2 Concreto
Trabajos incluidos en 1.3.1.1
Instalación de geomembrana de HDPE 1.5 mm lisa en zanja para tuberías m2
Trabajos incluidos en 1.3.1.1
Trabajos incluidos en 1.3.3.1
Trabajos incluidos en 1.3.1.1
m3 2670.00
1150.00
Superficie de rodadura, E=200mm m3 12.00
Instalación de geomembrana de HDPE 1.5 mm lisa en zanja para tuberías
Excavación masiva en terreno natural o suelto para explanaciones m3 4600.00
m2
Relleno con material préstamo para estructuras, al 95% del Próctor modificado.
Eliminación de material excedente 25% DE EXCAVACIONESm3
Superficie de rodadura, E=200mm m3 27.00A1-MI09H060-260-41-118A1-MI09H060-260-41-120
A1-MI09H060-260-41-112
A1-MI09H060-260-41-113
A1-MI09H060-260-35-101
A1-MI09H060-260-35-102
204.79
16490.83
26.64
483.36
m3
m3
16.00
2414.28
18.14
m3 1627.79
m3
443.22
6067.93m3
m3
Planos
SISTEMA DE IMPULSION DE RIEGO REFINO
ESTACION DE BOMBAS
TUBERIA PRINCIPAL REFINO
1153.30
35863.90
13793.00
3266.00
6141.00
A1-MI09H060-260-35-10142.39
A1-MI09H060-260-35-100
25% DE EXCAVACIONES
m3
m2
m2
m3
m3
A1-MI09H060-260-35-102
A1-MI09H060-260-35-100
m3
Relleno y compactación con material propio seleccionado para bermas m3
Eliminación de material excedente m3
Civil
Concreto f'c= 100 kg/cm2 para solados m3
Acero de refuerzo fy = 4200 kg/cm2
1.3.1.4.2 Concreto
A1-MI09H060-260-41-118A1-MI09H060-260-41-120
Trabajos incluidos en 1.3.3.1
A1-MI09H060-260-41-118A1-MI09H060-260-41-120
A1-MI09H060-260-41-118A1-MI09H060-260-41-120
25% DE EXCAVACIONES
Concreto
Eliminación de material excedente
Excavación masiva en terreno natural o suelto para explanaciones
Relleno y compactación con material propio seleccionado para bermas
Relleno con material préstamo para estructuras, al 95% del Próctor modificado.
ESTACION DE BOMBEO Y MEDICION
Civil
1.3.2
1.3.2.1.1
Civil
Relleno y compactación con material propio seleccionado para bermas
1.3.2.1
1.3.2.2.1ESTACIÓN DE MEDICIÓN DE REFINO
Excavación local en terreno natural o suelto para estructuras
1.3.2.3
1.3.3.1.1
1.3.3.1
SISTEMA DE IMPULSION PLS A PLANTA
1.3.2.3.1 Civil
1.3.2.2.2
1.3.3
1.3.3.1.1.21.3.3.1.1.1
Protección del concreto con recubrimiento con concreto polimérico
1.3.3.1.2.2
1.3.3.1.1.3
1.3.3.1.1.4
1.3.3.1.1.6
1.3.3.1.1.7
1.3.3.1.1.8
1.3.3.1.2.4
1.3.3.1.2.1
Superficie de rodadura, E=200mm
Concreto f'c= 210 kg/cm2 para cimentaciones de cercos
1.3.3.1.2.5
Instalación de geomembrana de HDPE 1.5 mm lisa en zanja para tuberías
Concreto
Excavación local en terreno natural o suelto para estructuras m3 5.45A1-MI09H060-260-41-118A1-MI09H060-260-41-120
1.3.1.4.2 Concreto0.16 A1-MI09H060-260-41-119
Concreto f'c= 280 kg/cm2 para anclajes de tuberías, según lo indicado en planos m3 2.56
A1-MI09H060-260-41-120A1-MI09H060-260-41-121
kg 266.11 A1-MI09H060-260-41-121
Suministro y colocación de pernos de anclaje ASTM A 36 kg 43.78 A1-MI09H060-260-41-121
93.11A1-MI09H060-260-41-120A1-MI09H060-260-41-121
Instalación de insertos Polylock en estructuras de concreto, bases de equipos, losas y recubrimiento de tuberías m 83.88 A1-MI09H060-260-30-006
Concreto f'c= 100 kg/cm2 para solados
1.3.3.1.2.3 Concreto f'c= 280 kg/cm2 para anclajes de tuberías, según lo indicado en planos m3
Concreto f'c= 350 kg/cm2 para cimentaciones de equipos, losa de manifold y pedestales, según lo indicado en planos
7 of 30
ITEM
Revision
CANT. COMENTARIOSUND.
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
15315-2600-42EL-001
DESCRIPCION
Sheet
1
1.3.3.2.1.1
1.3.3.2.1.2
1.3.3.2.1.3
1.3.3.2.1.41.3.3.2.1.51.3.3.2.1.61.3.3.2.1.7
1.3.3.2.1.81.3.3.2.1.9
1.3.3.2.2.1
1.3.3.2.2.2
1.3.3.2.2.3
1.3.3.2.2.4
1.3.3.4.1.1
1.3.3.4.1.2
1.3.3.4.1.31.3.3.4.1.41.3.3.4.1.5
1.3.3.4.2.1
1.3.3.4.2.2
1.3.3.4.2.31.3.3.4.2.41.3.3.4.2.51.3.3.4.2.61.3.3.4.2.7
1.3.4.1.1.11.3.4.1.1.2
1.3.4.1.1.31.3.4.1.1.4
1.3.4.1.1.51.3.4.1.1.6
Planos
A1-MI09H060-260-35-131
A1-MI09H060-260-30-006
A1-MI09H060-260-30-006
A1-MI09H060-260-30-006
A1-MI09H060-260-22-007
A1-MI09H060-260-35-312A1-MI09H060-260-35-313
A1-MI09H060-260-35-31430% DE EXCAVACIONES
Planos
A1-MI09H060-260-30-006
A1-MI09H060-260-35-312
A1-MI09H060-260-35-313
A1-MI09H060-260-35-314
41.80
0.05
2456.09
29.45
4179.89
0.90
11.73
5.99
79.51
6025.81
7.80
330.97
38.02
64.0099.29
5.40
8.70
153.70
315.22
5112.00
26.03
2403.00
15.96
18.00
31783.02
128.60
1284.51
223.65
17.49
39.14
10.59
m2 15677.18
m3
m3
m3
m3
m3
m
kg
kg
m3
m
m3
m3
m3
m3
m3
m3
m3
m3
m3
kg
m
kg
kg
m3
m3
A1-MI09H060-260-35-100
38608.66
593.03
Excavación masiva en terreno natural o suelto para explanaciones
1.3.3.1.2.11
1.3.3.2
1.3.3.1.2.7
1.3.3.2.2
1.3.3.2.1
1.3.3.1.2.6
1.3.3.1.2.8
1.3.3.1.2.10
1.3.4.1.1
Concreto f'c= 100 kg/cm2 para soladosConcreto f'c= 280 kg/cm2 para anclajes de tuberías, según lo indicado en planos
Acero de refuerzo fy = 4200 kg/cm2
Suministro y colocación de pernos de anclaje ASTM A 36
SUBESTACION ELECTRICA BOMBAS
Civil
1.3.3.4.2
1.3.3.4
1.3.3.4.1
Concreto
Acero de refuerzo fy = 4200 kg/cm2
Suministro y colocación de pernos de anclaje ASTM A 36
Suministro y colocación de grout cementicio E=25mm
1.3.4
1.3.4.1
ÁCIDO SULFÚRICO
Juntas de expansión (incluye juntas de dilatación y aislamiento)
Superficie Final de rodadura, E=200mm
Relleno y compactación con material propio seleccionado para bermas, al 95% del Próctor Modificado.
Superficie de acceso transformador E=100mm, grava Ø3/4"
Eliminación de material excedente
Superficie de rodadura, E=200mm
Concreto
Relleno con material préstamo para estructuras, al 95% del Próctor modificado.
Juntas de construcción (incluye juntas de contracción)
Juntas de expansión (incluye juntas de dilatación y aislamiento)
TUBERIA PRINCIPAL A PLANTA
Civil
Excavación local en terreno natural o suelto para estructuras
m3
Excavación local en terreno natural o suelto para estructuras
Eliminación de material excedente m3
Instalación de geomembrana de HDPE 1.5 mm lisa en zanja para tuberías
Relleno con material préstamo para estructuras, al 95% del Próctor modificado.
m3
m3
kg
A1-MI09H060-260-35-1001.3.3.1.2.9 A1-MI09H060-260-35-100
m3
m3
0.44
1.56
Suministro y colocación de grout cementicio E=25mm
Suministro y colocación de grout epóxico E=50mm
Juntas de construcción (incluye juntas de contracción)
Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, muros, losa de piso y cimentación de cuarto de control, según lo indicado en planos
Concreto f'c= 100 kg/cm2 para solados
Eliminación de material excedente
ESTACIONES DE BOMBEO
CivilExcavación masiva en terreno natural o suelto para explanaciones
Excavación local en terreno natural o suelto para explanaciones
Relleno y compactación con material propio seleccionado para estructuras, al 95% del Próctor modificado.
A1-MI09H060-260-22-005
A1-MI09H060-260-30-006
25% DE EXCAVACIONES
m
A1-MI09H060-260-35-100
A1-MI09H060-260-35-100
A1-MI09H060-260-35-100
m3 745.66 30% DE EXCAVACIONES
Relleno y compactación con material propio seleccionado para bermas
Relleno con material préstamo para estructuras, al 95% del Próctor modificado.
Instalación de insertos Polylock en estructuras de concreto, bases de equipos, losas y recubrimiento de tuberías m
Parrilla GR-15 SM (1.1/2" SM-PRFV) Fibra de vidrio m2
Acero de refuerzo fy = 4200 kg/cm2
Suministro y colocación de pernos de anclaje ASTM A 36
8 of 30
ITEM
Revision
CANT. COMENTARIOSUND.
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
15315-2600-42EL-001
DESCRIPCION
Sheet
1
1.3.4.1.1.71.3.4.1.1.8
1.3.4.1.1.9
1.3.4.1.2
1.3.4.1.2.1
1.3.4.1.2.2
1.3.4.1.2.31.3.4.1.2.41.3.4.1.2.51.3.4.1.2.61.3.4.1.2.71.3.4.1.2.81.3.4.1.2.9
1.4
1.4.1
1.4.1.11.4.1.1.11.4.1.1.1.11.4.1.1.1.21.4.1.1.1.3
1.4.1.1.1.4
1.4.1.1.1.51.4.1.1.21.4.1.1.2.11.4.1.1.2.2
1.4.1.1.2.3
1.4.1.1.2.41.4.1.1.2.51.4.1.1.2.61.4.1.1.2.71.4.1.1.2.81.4.1.1.2.91.4.1.3
1.51.5.11.5.1.1
1.5.1.1.1.1
1.5.1.1.1.2
1.5.1.1.1.3
1.5.1.1.1.4
1.5.1.1.1.5
1.5.1.1.1.61.5.1.1.1.7
A1-MI09H060-260-35-121
A1-MI09H060-260-35-121
Planos
A1-MI09H060-260-35-121
Planos
A1-MI09H060-260-35-310
A1-MI09H060-260-35-307
A1-MI09H060-260-35-310
A1-MI09H060-260-35-308
A1-MI09H060-260-35-310
A1-MI09H060-260-35-310
A1-MI09H060-260-30-006
A1-MI09H060-260-35-310
A1-MI09H060-260-35-310
A1-MI09H060-260-35-310
A1-MI09H060-260-35-310
m3
Concreto
Concreto f'c= 100 kg/cm2 para solados
1.5.1.1.1
3.74
A1-MI09H060-260-35-309
A1-MI09H060-260-35-121
A1-MI09H060-260-35-121
A1-MI09H060-260-35-121
A1-MI09H060-260-35-121
A1-MI09H060-260-41-104 A1-MI09H060-260-41-301
A1-MI09H060-260-35-310
A1-MI09H060-260-35-121
A1-MI09H060-260-30-005 A1-MI09H060-260-35-200
A1-MI09H060-260-35-201 A1-MI09H060-260-35-202
A1-MI09H060-260-35-203 A1-MI09H060-260-35-204
A1-MI09H060-260-35-223 A1-MI09H060-260-41-100
1747.41
9.00
1656.45
9.00
1377.42
6385.14
604.51
3.17
160.80
318.90
337.55
22086.36
394.07
0.90
3.97
59.21
7.20
211.39
143.80
0.07
9.60
0.16
17.14
98.78
1848.98
6.67
12.00
8633.81
75.56
m3
m3
m3
m3
m3
m3
m3
m
kg
m3
m3
m
m
m3
m3
kg
m3
m3
m3
m3
m3
m2
kg
kg
m3
m3
m3
m2
m3
Instalación de insertos Polylock en estructuras de concreto, bases de equipos, losas y recubrimiento de tuberías m
Suministro y colocación de pernos de anclaje ASTM A 36
Parrilla GR-15 SM (1.1/2" SM-PRFV) Fibra de vidrio
Superficie de rodadura, E=200mm
m2
Instalación de geomembrana de HDPE 1.5 mm lisa en zanja para tuberías
Protección del concreto con recubrimiento con concreto polimérico
Acero de refuerzo fy = 4200 kg/cm2
Concreto f'c= 210 kg/cm2 para anclajes de tuberías, según lo indicado en planos
Concreto f'c= 350 kg/cm2 para cimentaciones de equipos, losa de piso y pedestales, según lo indicado en planos
Suministro y colocación de grout cementicio E=25mm
Juntas de construcción (incluye juntas de contracción)
m3
SISTEMA AIREACION PILA
SISTEMA DE AIREACION PILA
7.14
121.76
575.72
Concreto f'c= 210 kg/cm2 para cimentaciones de cercos
ConcretoEliminación de material excedente
ESTACION DE SOPLADORESCivil
Excavación en terreno natural o suelto para estructuras
Excavación masiva en terreno natural o suelto para explanaciones
Relleno con material préstamo para estructuras, al 95% del Próctor modificado.
Concreto f'c= 100 kg/cm2 para solados
Excavación local en roca para estructuras
Acero de refuerzo fy = 4200 kg/cm2
Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, losa de piso y pedestales, según lo indicado en planos
Juntas de expansión (incluye juntas de dilatación y aislamiento)
Suministro y colocación de pernos de anclaje
Suministro y colocación de grout cementicio E=25mm
Suministro y colocación de grout epóxico E=50mm
Juntas de construcción (incluye juntas de contracción)
SUBESTACION ELECTRICA SOPLADORESCivil
N/A trabajos incluidos en 1.4.1.1
SISTEMA DE MANEJO DE MATERIALESEQUIPOS MECANICOSFAJA TRANSPORTADORA CV-007ACivil
Excavación masiva en terreno natural o suelto para explanaciones
Excavación local en terreno natural o suelto para estructuras
Remoción de durmientes de concreto y eliminación de materiales existentes.
Relleno y compactación masivo material seleccionado para mejoramiento de suelo
Relleno para estructuras con material de préstamo, al 95% del Próctor modificado.
Relleno y compactación masivo con material seleccionado para caminos de acceso de la faja CV-007A, incluye bermas.
Eliminación de material excedente
30% DE EXCAVACIONES
A1-MI09H060-260-30-006
A1-MI09H060-260-35-121
25% DE EXCAVACIONES
A1-MI09H060-260-35-310
9 of 30
ITEM
Revision
CANT. COMENTARIOSUND.
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
15315-2600-42EL-001
DESCRIPCION
Sheet
1
1.5.1.1.1.81.5.1.1.21.5.1.1.2.1
1.5.1.1.2.21.5.1.1.2.31.5.1.1.2.41.5.1.1.2.5
1.5.1.21.5.1.2.1
1.5.1.2.1.11.5.1.2.1.21.5.1.2.1.3
1.5.1.2.1.4
1.5.1.2.1.5
1.5.1.2.1.6
1.5.1.2.1.7
1.5.1.2.1.81.5.1.2.1.9
1.5.1.2.1.10
1.5.1.2.1.11
1.5.1.2.1.12
1.5.1.2.1.14
1.5.1.2.1.15
1.5.1.2.1.161.5.1.2.2
1.5.1.2.2.1
1.5.1.2.2.2
1.5.1.2.2.3
1.5.1.2.2.4
1.5.1.2.2.5
1.5.1.2.2.6
1.5.1.2.2.7
1.5.1.2.2.8
1.5.1.2.2.9
1.5.1.2.2.10
1.5.1.4
1.5.1.4.11.5.1.4.1.11.5.1.4.1.2
1.5.1.4.1.3
1.5.1.4.1.41.5.1.4.1.51.5.1.4.1.6
A1-MI09H060-260-42-309 A1-MI09H060-260-35-204
A1-MI09H060-260-41-310
A1-MI09H060-260-41-103 A1-MI09H060-260-41-104
A1-MI09H060-260-42-304 A1-MI09H060-260-42-305
A1-MI09H060-260-42-306
A1-MI09H060-260-35-211 A1-MI09H060-260-35-212
A1-MI09H060-260-35-211 A1-MI09H060-260-35-212
A1-MI09H060-260-41-101A1-MI09H060-260-42-305
A1-MI09H060-260-41-102
A1-MI09H060-260-42-307
A1-MI09H060-260-41-105 A1-MI09H060-260-42-300
A1-MI09H060-260-41-310
A1-MI09H060-260-30-005
A1-MI09H060-260-41-102
A1-MI09H060-260-30-005
A1-MI09H060-260-42-308
A1-MI09H060-260-35-305
Planos
A1-MI09H060-260-35-303
A1-MI09H060-260-22-005
A1-MI09H060-260-35-30478.79
60.0079.42
8.68
114.73
150.01
524.24
135.90
112.90
226.00
392.64
73806.56
539.18
0.86
25.04
134.02
19.58
514.75
226.76
2158.94
2655.00
113.38
63340.31
47.45
30694.01
74297.75
3515.23
856.51
0.60
318.19
22521.78
60.30
21.12
m3
m3
m3
m3
m3
m3
m
m
m
kg
kg
m3
m
m3
m3
m3
m2
m
m3
m3
m
m3
m3
m3
m3
m3
m3
m2
kg
kg
m3
m3
m3
m3
Instalación de insertos Polilock en estructuras de concreto, bases de equipos, losas y recubrimiento de tuberías
Relleno y compactación masivo material seleccionado en zona de culvert, al 95% del Próctor modificado.
Superficie de rodadura, E=200mm en accesos y plataformas
Superficie de rodadura, E=300mm en camino minero
Instalación de geocompuesto para drenaje tipo MacDrain de Maccaferri o similar
Suministro y colocación de estructura metálica Super Span Multiplate-MP152 - Arco 35A5.49
Eliminación de material excedente
Relleno y compactación masivo con material seleccionado en zona de camino minero, incluye bermas.
Superficie de rodadura, E=200mm en accesos y plataformas
ConcretoConcreto f'c= 100 kg/cm2 para solados
Concreto f'c= 280 kg/cm2 para cimentaciones de fajas transportadoras y plataformas
Acero de refuerzo fy = 4200 kg/cm2
Concreto f'c= 280 kg/cm2 para cimentaciones del culvert
Acero de refuerzo fy = 4200Kg/cm2
Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, canaletas eléctricas y losas de piso
Suministro y colocación de pernos de anclaje ASTM A 36
Suministro y colocación de grout cementicio E=25mm
FAJA TRANSPORTADORA CV-008Civil
Relleno y compactación masivo con material seleccionado para caminos de acceso de la faja CV-008, incluye bermas.
Concreto f'c= 100 kg/cm2 para solados
ConcretoTubería de drenaje PVC Ø6" C/ agujeros 3/16"@ 75mm
SUBESTACION ELECTRICA DE TRASPASO
Civil
Suministro y colocación de pernos de anclaje ASTM A 36
Suministro y colocación de grout cementicio E=25mm
Juntas de construcción (incluye juntas de contracción)
Juntas de expansión (incluye juntas de dilatación y aislamiento)
Sello de agua con bulbo intermedio 6"
Concreto f'c= 280 kg/cm2 para cimentaciones de fajas transportadoras y plataformas
20% DE EXCAVACIONES
Planos
A1-MI09H060-260-35-202 A1-MI09H060-260-35-203
A1-MI09H060-260-42-301 A1-MI09H060-260-42-303
Excavación local en terreno natural o suelto para estructuras
Excavación local en roca para fines de cimentación m3
279301.86
229.68
37170.00
41.11
Preparación de sub-rasante en plataforma
m3Excavación masiva en terreno natural o suelto para explanaciones
Superficie de acceso transformador E=100mm, grava Ø3/4"
Relleno y compactación masivo con material seleccionado, al 95% del Próctor modificado. m3
Excavación masiva en terreno natural o suelto para explanaciones
Excavación local en terreno natural o suelto para estructuras
Relleno con material préstamo para estructuras, al 95% del Próctor modificado.
Superficie de rodadura, E=200mm Eliminación de material excedente 30% DE EXCAVACIONES
A1-MI09H060-260-22-005
10 of 30
ITEM
Revision
CANT. COMENTARIOSUND.
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
15315-2600-42EL-001
DESCRIPCION
Sheet
1
1.5.1.4.21.5.1.4.2.1
1.5.1.4.2.2
1.5.1.4.2.31.5.1.4.2.41.5.1.4.2.51.5.1.4.2.61.5.1.4.2.71.5.1.4.2.8
1.5.1.5.11.5.1.5.1.11.5.1.5.1.2
1.5.1.5.1.3
1.5.1.5.1.41.5.1.5.1.51.5.1.5.1.6
1.5.1.5.21.5.1.5.2.1
1.5.1.5.2.2
1.5.1.5.2.3
1.5.1.5.2.41.5.1.5.2.51.5.1.5.2.61.5.1.5.2.71.5.1.5.2.8
1.7
1.7.1
1.7.1.1
1.7.1.1.1
1.7.1.1.1.1
1.7.1.1.1.2
1.5.1.2.1.3
1.7.1.1.1.4
1.7.1.1.1.51.7.1.1.1.61.7.1.1.1.7
1.7.1.1.21.7.1.1.2.11.7.1.1.2.2
1.7.1.1.2.3
1.7.1.1.2.4
1.7.1.1.2.51.7.1.1.2.61.7.1.1.2.7
A1-MI09H060-260-22-008
A1-MI09H060-260-35-300
A1-MI09H060-260-35-301
A1-MI09H060-260-35-30230% DE EXCAVACIONES
A1-MI09H060-260-35-318
Planos
A1-MI09H060-260-41-103 A1-MI09H060-260-41-104
A1-MI09H060-260-22-004
1.5.1.5 Planos
A1-MI09H060-260-35-317
A1-MI09H060-260-22-008 A1-MI09H060-260-35-316
A1-MI09H060-260-35-320
A1-MI09H060-260-22-008
132.96
16.63
152.71
9738.17
41.11
80.00161.29
8.43
0.15
6.60
34.66
2.25
38.60
51.00
9.60
12.45
81.33
9884.41
196.34
95.72
80.0095.62
122.40
5713.49
29.40
0.05
5.70
22.70
9.06
58.85
5.67
kg
kg
m3
m3
m3
m3
m3
m3
m3
m3
m3
m3
kg
m2
m
m
m3
m3
m3
kg
m3
m3
m3
m
m3
m3
Suministro y colocación de grout cementicio E=25mm
Juntas de construcción (incluye juntas de contracción)
Juntas de expansión (incluye juntas de dilatación y aislamiento)
Concreto f'c= 210 kg/cm2 para canaletas de drenaje, cimentaciones de cercos, banco de ductos y buzones
Excavación local en roca para fines de cimentación
Excavación local en terreno natural o suelto para estructuras
Relleno con material préstamo para estructuras, al 95% del Próctor modificado.
Superficie de rodadura, E=200mm
SUBESTACION ELECTRICA DE DISTRIBUCION DE MATERIALES
Civil
ConcretoConcreto f'c= 100 kg/cm2 para solados
Acero de refuerzo fy = 4200 kg/cm2
Suministro y colocación de pernos de anclaje ASTM A 36
Concreto f'c= 210 kg/cm2 para canaletas de drenaje, cimentaciones de cercos, banco de ductos y buzones
Superficie de rodadura, E=200mm
Excavación masiva en terreno natural o suelto para explanaciones
Excavación local en terreno natural o suelto para estructuras
ConcretoConcreto f'c= 100 kg/cm2 para solados
Acero de refuerzo fy = 4200 kg/cm2
Suministro y colocación de pernos de anclaje ASTM A 36
Concreto f'c= 210 kg/cm2 para canaletas de drenaje, cimentaciones de cercos, banco de ductos y buzones
Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, muros, losa de piso y cimentación de sala de tableros, según lo indicado en planos
SUBESTACION ELECTRICA PRINCIPAL 22.9kV
Eliminación de material excedente
141.74
395.90
192.02
m3
m3
56.70
Superficie de acceso transformador E=100mm, grava Ø3/4" m3 10.48
Relleno con material préstamo para estructuras, al 95% del Próctor modificado.
Suministro y colocación de grout cementicio E=25mm
Juntas de construcción (incluye juntas de contracción)
Juntas de expansión (incluye juntas de dilatación y aislamiento)
PATIO DE LLAVES
Civil
SUBESTACION ELECTRICA PRINCIPAL 22.9kV
m
Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, muros, losa de piso y cimentación de sala de tableros, según lo indicado en planos m3
kg
kg
m3
Concreto
Superficie de acceso transformador E=100mm, grava Ø3/4"
Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, muros, losa de piso, según lo indicado en planos
Suministro y colocación de grout cementicio E=25mm
Concreto f'c= 100 kg/cm2 para solados
Concreto Ciclópeo f'c= 140 kg/cm2 + 30% Piedra Mediana
Acero de refuerzo fy = 4200 kg/cm2
Suministro y colocación de pernos de anclaje ASTM A 36
30% DE EXCAVACIONES
Eliminación de material excedente m3
Excavación masiva en terreno natural o suelto para explanaciones
m3
11 of 30
ITEM
Revision
CANT. COMENTARIOSUND.
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
15315-2600-42EL-001
DESCRIPCION
Sheet
1
1.7.1.2
1.7.1.2.11.7.1.2.1.11.7.1.2.1.2
1.7.1.2.1.3
1.7.1.2.1.4
1.7.1.2.1.51.7.1.2.1.6
1.7.1.2.21.7.1.2.2.11.7.1.2.2.2
1.7.1.2.2.31.7.1.2.2.41.7.1.2.2.51.7.1.2.2.61.7.1.2.2.71.7.1.2.2.8
Planos
A1-MI09H060-260-22-008
A1-MI09H060-260-35-319
A1-MI09H060-260-35-320
A1-MI09H060-260-41-103 A1-MI09H060-260-41-104
30% DE EXCAVACIONES
252.87
40.32
275.30
141.05
80.00
16.99
158.45
5.90
48.03
88.48
83.11
8877.98
2.24
1.20m
m
m3
kg
kg
m2
m3
m3
m3
m3
m3
m3
m3
Superficie de rodadura, E=200mm
Concreto
SALA ELECTRICA
CivilExcavación masiva en terreno natural o suelto para explanaciones
Excavación local en terreno natural o suelto para estructuras
Eliminación de material excedente
Excavación local en roca para fines de cimentación
Concreto f'c= 100 kg/cm2 para solados
Concreto Ciclópeo f'c= 140 kg/cm2 + 30% Piedra Mediana
Concreto f'c= 280 kg/cm2 para cimentacion de sala eléctrica, según lo indicado en planos
Acero de refuerzo fy = 4200 kg/cm2
Suministro y colocación de pernos de anclaje ASTM A 36
Suministro y colocación de grout cementicio E=25mm
Juntas de construcción (incluye juntas de contracción)
Juntas de expansión (incluye juntas de dilatación y aislamiento)
m3
Relleno con material préstamo para estructuras, al 95% del Próctor modificado.
12 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"
1.3 SISTEMA DE IMPULSION1.3.1 SISTEMA DE IMPULSION DE RIEGO ILS1.3.1.1 ESTACIÓN DE MEDICIÓN DE ILS
1.3.1.1.1 CIVIL1.3.1.1.1.1 Excavación masiva en terreno natural o suelto para explanaciones 284.63
Plataformado General 33.00 34.50 0.25 1 284.63
1.3.1.1.1.2Excavación en terreno natural o suelto para estructuras (incluye excavación
de cunetas en tierra y eliminación de material excedente). 44.89Cimentación B-13 1.35 2.60 0.15 3 1.58Cimentación B-10 1.80 1.60 1.15 3 9.94Cimentación B-11 1.80 1.60 1.15 6 19.87Cimentación SL3 1.50 1.50 1.20 5 13.50
1.3.1.1.1.3Relleno con material propio seleccionado para estructuras (incluye
excavación de cunetas en tierra y eliminación de material excedente). 54.39Cimentación B-10 6.80 0.25 0.40 3 2.04Cimentación B-11 6.80 0.25 0.40 6 4.08Canaleta 1 18.25 2.35 0.35 1 15.01Canaleta 2 17.30 1.35 0.70 1 16.35Sumidero 1 1.35 1.35 0.75 1 1.37Sumidero 2 0.80 0.90 0.75 1 0.54Cimentación SL3 12.00 0.25 1.00 5 15.00
1.3.1.1.1.4 Relleno con material préstamo para estructuras 16.04Canaleta 1 18.25 2.35 0.30 1 12.87Sumidero 1 1.35 1.35 1.25 1 2.28Sumidero 2 0.80 0.90 1.25 1 0.90
1.3.1.1.1.6 Superficie de rodadura, E=200mm 48.00Acceso Vehicular 4.00 60.00 0.20 1 48.00
1.3.1.1.2 CONCRETO1.3.1.1.2.1 Concreto f'c= 100 kg/cm2 para solados 18.86
Canaleta 1 17.85 1.95 0.05 1 1.74Losa 1 15.77 17.85 0.05 1 14.07Losa 2 6.80 5.20 0.05 1 1.77Cimentación B-13 2.00 0.75 0.05 3 0.23Cimentación B-10 1.40 1.20 0.05 3 0.25Cimentación B-11 1.40 1.20 0.05 6 0.50Cimentación SL3 1.00 1.20 0.05 5 0.30
1.3.1.1.2.2Concreto f'c= 210 kg/cm2 para canaletas de drenaje, cimentaciones de
cercos 14.78Canaleta 1 17.85 1.95 0.25 1 8.70
17.85 0.25 1.15 1 5.131.65 0.25 1.15 2 0.95
1.3.1.1.2.3Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, losa de piso y
pedestales, según lo indicado en planos 17.90Canaleta 2 16.90 0.95 0.15 1 2.41
16.90 0.15 1.35 1 3.4216.90 0.20 1.70 1 5.750.60 0.20 1.35 2 0.32
Cimentación SL3 1.20 1.00 1.00 5 6.00
1.3.1.1.2.4Concreto f'c= 350 kg/cm2 para cimentaciones de equipos, losa de manifold y
pedestales, según lo indicado en planos 77.60Losa 1 13.05 17.85 0.25 1 58.24Losa 2 6.80 5.20 0.15 1 5.30Sardinel 13.05 0.20 0.25 1 0.65
6.35 0.20 0.25 1 0.3217.85 0.20 0.20 1 0.7115.80 0.15 0.80 1 1.90
Cimentación B-1 1.20 0.50 0.50 2 0.60Cimentación B-2 1.00 0.50 0.65 3 0.98Cimentación B-3 1.20 0.40 0.50 2 0.48Cimentación B-4 1.20 0.40 0.55 8 2.11Cimentación B-5 1.20 0.40 0.55 2 0.53Cimentación B-5A 1.20 0.40 0.50 1 0.24Cimentación B-6 1.00 0.40 0.55 4 0.88Cimentación B-7 1.00 0.40 0.55 12 2.64Cimentación B-7A 1.00 0.40 0.55 3 0.66Cimentación B-8 1.00 0.40 0.55 2 0.44Cimentación B-9 1.00 0.40 0.55 1 0.22Sumidero 1 0.95 0.95 0.15 1 0.14
0.95 0.15 1.35 1 0.190.95 0.20 1.70 1 0.32
Sumidero 2 0.40 0.50 0.15 1 0.030.40 0.50 0.10 1 0.02
1.3.1.1.2.5 Protección del concreto con recubrimiento polimérico 308.29Losa 1 13.05 17.85 1.00 1 232.94Sardinel 13.05 0.20 1.00 1 2.61
6.35 0.20 1.00 1 1.2717.85 0.20 1.00 1 3.5715.80 0.15 1.00 1 2.37
Cimentación B-1 3.40 0.50 1.00 2 3.40Cimentación B-2 3.00 0.65 1.00 3 5.85Cimentación B-3 3.20 0.50 1.00 2 3.20Cimentación B-4 3.20 0.55 1.00 8 14.08Cimentación B-5 3.20 0.55 1.00 2 3.52Cimentación B-5A 3.20 0.50 1.00 1 1.60Cimentación B-6 2.80 0.55 1.00 4 6.16Cimentación B-7 2.80 0.55 1.00 12 18.48Cimentación B-7A 2.80 0.55 1.00 3 4.62Cimentación B-8 2.80 0.55 1.00 2 3.08Cimentación B-9 2.80 0.55 1.00 1 1.54
1.3.1.1.2.6 Acero de Refuerzo fy=4200 Kg/cm2 11557.53Losa 1 1/2" 184 13.4 2441 2562.99
1/2" 136 18.2 2450 2572.97Losa 2 1/2" 35 5.5 190.6 200.10
1/2" 27 7 187.1 196.47Sardinel 1/2" 13.05 2 25.84 27.13
1/2" 6.35 2 12.57 13.201/2" 17.85 2 35.34 37.111/2" 186.3 0.7 129.1 135.521/2" 3 15.8 46.93 49.271/2" 79 0.6 46.93 49.27
Cimentación B-1 2 1/2" 1.2 16 38.02 39.922 1/2" 3.4 8 53.86 56.55
Cimentación B-2 3 1/2" 1 16 47.52 49.903 1/2" 3 8 71.28 74.84
Cimentación B-3 2 1/2" 1 16 31.68 33.262 1/2" 3.2 8 50.69 53.22
Cimentación B-4 8 1/2" 1 16 126.7 133.06
SUBTOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
13 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
8 1/2" 3.2 8 202.8 212.89Cimentación B-5 2 1/2" 1 16 31.68 33.26
2 1/2" 3.2 8 50.69 53.22Cimentación B-5A 1 1/2" 1 16 15.84 16.63
1 1/2" 3.2 8 25.34 26.61Cimentación B-6 4 1/2" 1 16 63.36 66.53
1 1/2" 3.2 8 25.34 26.61Cimentación B-7 12 1/2" 1 16 190.1 199.58
12 1/2" 3.2 8 304.1 319.33Cimentación B-7A 3 5/8" 11 16 818.4 859.32
3 5/8" 3 2.8 39.06 41.01Cimentación B-8 2 5/8" 11 16 545.6 572.88
2 5/8" 3 2.8 26.04 27.34Cimentación B-9 1 5/8" 14 16 347.2 364.56
1 5/8" 16 1.6 39.68 41.665/8" 16 2.05 50.84 53.383/8" 12 3.2 21.5 22.58
Canaleta 2 1/2" 9 17.1 152.4 159.981/2" 85 2 168.3 176.721/2" 7 17.1 118.5 124.431/2" 85 1.7 143.1 150.211/2" 5 17.1 84.65 88.881/2" 85 1.35 113.6 119.28
Sumidero 1 1/2" 9 1.15 10.25 10.761/2" 5 2 9.9 10.401/2" 7 1.15 7.97 8.371/2" 5 1.7 8.415 8.841/2" 5 1.15 5.693 5.981/2" 5 1.35 6.683 7.02
Sumidero 2 1/2" 6 0.5 2.97 3.121/2" 6 0.5 2.97 3.12
Cimentación SL3 5 5/8" 4.4 16 545.6 572.885 5/8" 6.8 16 843.2 885.36
1.3.1.1.2.7 Suministro y colocación de pernos de anclaje ASTM A36 N° 269.70B-1 T2 - 111 2 3/4" 4 0.385 6.899 7.38B-2 T2 - 111 3 5/8" 8 0.3 11.16 11.88B-3 T2 - 111 2 3/4" 4 0.385 6.899 7.38B-4 T2 - 111 8 3/4" 4 0.385 27.6 29.52B-5 T2 - 111 2 1" 4 0.55 17.51 17.99B-5A T2 - 111 1 3/4" 8 0.385 6.899 7.14B-6 T2 - 111 4 3/4" 4 0.385 13.8 14.76B-7 T2 - 111 12 3/4" 4 0.385 41.4 44.28B-7A T2 - 111 3 3/4" 8 0.385 20.7 21.42B-8 T2 - 111 2 3/4" 4 0.385 6.899 7.38B-9 T2 - 111 1 3/4" 4 0.385 3.45 3.69B-10 T2 - 111 3 3/4" 4 0.385 10.35 11.07B-11 T2 - 111 6 3/4" 4 0.385 20.7 22.14B-13 T2 - 111 3 3/4" 6 0.385 15.52 16.24B-14 T2 - 111 2 1/2" 4 0.25 1.98 2.46SL3 T2 - 111 5 1" 4 0.55 43.78 44.98
1.3.1.1.2.8 Suministro y colocación de grout cementicio E=25mm 0.94Cimentación B-1 1.20 0.50 0.03 2 0.03Cimentación B-2 1.00 0.50 0.03 3 0.04Cimentación B-3 1.20 0.40 0.03 2 0.02Cimentación B-4 1.20 0.40 0.03 8 0.10Cimentación B-5 1.20 0.40 0.03 2 0.02Cimentación B-5A 1.20 0.40 0.03 1 0.01Cimentación B-6 1.00 0.40 0.03 4 0.04Cimentación B-7 1.00 0.40 0.03 12 0.12Cimentación B-7A 1.00 0.40 0.03 3 0.03Cimentación B-8 1.00 0.40 0.03 2 0.02Cimentación B-9 1.00 0.40 0.03 1 0.01Cimentación B-10 1.40 1.20 0.03 3 0.13Cimentación B-11 1.40 1.20 0.03 6 0.25Cimentación B-13 2.00 0.75 0.03 3 0.11Cimentación B-14 0.30 0.25 0.03 1 0.00
1.3.1.1.2.9 Juntas de Construcción (incluye juntas de Contracción) 57.4513.20 1.00 1.00 3 39.6017.85 1.00 1.00 1 17.85
1.3.1.1.2.10 Juntas de Expansión 24.6517.85 1.00 1.00 1 17.856.80 1.00 1.00 1 6.80
1.3.1.1.2.11 Instalación de geomembrana de HDPE 1.5 mm lisa en canal de tuberías 113.30Canaleta 1 17.85 1.95 1.00 2 69.62
17.85 1.12 1.00 2 39.981.65 1.12 1.00 2 3.70
1.3.1.1.2.12Instalación de insertos Polylock en estructuras de concreto, bases de
equipos, losas y recubrimiento de tuberías 56.85Canaleta 1 17.85 1.00 1.00 1 17.85
17.85 1.00 1.00 2 35.701.65 1.00 1.00 2 3.30
1.3.1.1.2.13 Parrilla GR-15 SM (1.1/2" SM-PRFV) Fibra de vidrio 7.66Canaleta 2 0.40 17.85 1.00 1 7.14Sumidero 1 0.60 0.60 1.00 1 0.36Sumidero 2 0.40 0.40 1.00 1 0.16
1.3.1.2 TUBERÍA PRINCIPAL ILS
1.3.1.2.1 CIVIL1.3.1.2.1.1 Excavación local en terreno natural o suelto para estructuras 129.68
Soportes de concreto Tipo SL4 3.50 0.95 1.30 30.00 129.68
1.3.1.2.1.2Relleno con material propio seleccionado para estructuras (incluye
excavación de cunetas en tierra y eliminación de material excedente). 25.64Soportes de concreto Tipo SL4 3.50 0.95 1.30 30 129.68
3.40 0.85 -1.20 30 -104.04
1.3.1.2.1.3 Superficie de rodadura, E=200mm 12.00Acceso Vehicular 3.00 20.00 0.20 1 12.00
1.3.1.2.2 CONCRETO1.3.1.1.2.1 Concreto f'c= 100 kg/cm2 para solados 4.34
Soportes de concreto Tipo SL4 3.40 0.85 0.05 30 4.34
1.3.1.2.2.2Concreto f'c= 280 kg/cm2 para anclajes de tuberías según lo indicado en
planos 97.92Soportes de concreto Tipo SL4 3.40 0.80 1.20 30 97.92
1.3.1.1.2.3 Acero de Refuerzo fy=4200 Kg/cm2 N° 8009.82Soportes de concreto Tipo SL4 30 1/2" 4 12 47.52 1496.88
30 1/2" 3 12 35.64 1122.6630 5/8" 9.2 6 85.56 2695.14
14 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
30 5/8" 9.2 6 85.56 2695.14
1.3.1.1.2.4 Suministro y colocación de pernos de anclaje ASTM A36 N° 525.36Soportes de concreto Tipo SL4 30 1" 8 0.55 17.51 525.36
1.3.1.3 TUBERÍAS SECUNDARIAS DE RIEGO DENTRO DEL PAD
1.3.1.4 TUBERIAS DE ILS DESDE PONDS 1 Y 2 HASTA PONDS 4
1.3.1.4.1 CIVIL1.3.1.4.1.1 Excavación masiva en terreno natural o suelto para explanaciones 13064.00
Canaleta 2300.00 4.40 1.20 1 12144.00Trincheras de anclaje 2300.00 0.50 0.40 2 920.00
1.3.1.4.1.2 Excavación local en terreno natural o suelto para estructuras 5.45Cimentación SL3 1.10 1.10 0.90 5 5.45
1.3.1.4.1.3Relleno y compactación con material propio seleccionado para bermas, al
95% del Próctor Modificado. 6141.00Trincheras de anclaje 2300.00 0.50 0.50 2 1150.00Bermas 2300.00 1.55 0.70 2 4991.00
1.3.1.4.1.4Relleno con material préstamo para estructuras, al 95% del Próctor
Modificado. 1153.30Trincheras de anclaje 2300.00 0.50 0.50 2 1150.00Cimentación SL3 4.40 0.15 1.00 5 3.30
1.3.1.4.1.6 Superficie de rodadura, E=200mm 27.00Acceso Vehicular 4.50 30.00 0.20 1 27.00
1.3.1.4.1.7 Instalación de geomembrana de HDPE 1.5 mm lisa en zanja para tuberías 35863.90Canaleta 2300.00 10.84 1.00 1 24938.90Poncho canaleta 2300.00 4.75 1.00 1 10925.00
1.3.1.4.2 CONCRETO1.3.1.4.2.1 Concreto f'c= 100 kg/cm2 para solados 0.16
Cimentación SL3 0.80 0.80 0.05 5 0.16
1.3.1.4.2.2Concreto f'c= 280 kg/cm2 para canaletas de drenaje, cimentaciones de
cercos 2.56Cimentación SL3 0.80 0.80 0.80 5 2.56
1.3.1.4.2.3 Acero de Refuerzo fy=4200 Kg/cm2 266.11Cimentación SL3 5 1/2" 3.2 8 126.7 133.06
5 1/2" 3.2 8 126.7 133.06
1.3.1.4.2.4 Suministro y colocación de pernos de anclaje ASTM A36 N° 43.78Soportes de concreto SL3 5 1" 4 0.55 8.756 43.78
1.3.2. SISTEMA DE IMPULSION DE RIEGO REFINO1.3.2.1 ESTACION DE BOMBAS
1.3.2.1.1 CIVIL1.3.2.1.1.1 Excavación masiva en terreno natural o suelto para explanaciones 4600.00
Canaleta 1000.00 3.50 1.20 1 4200.00Trincheras de anclaje 1000.00 0.50 0.40 2 400.00
1.3.2.1.1.2Relleno y compactación con material propio seleccionado para bermas, al
95% del Próctor Modificado. 2670.00Trincheras de anclaje 1000.00 0.50 0.50 2 500.00Bermas 1000.00 1.55 0.70 2 2170.00
1.3.2.1.1.4 Superficie de rodadura, E=200mm 12.00Acceso Vehicular 3.00 20.00 0.20 1 12.00
1.3.2.1.1.5 Instalación de geomembrana de HDPE 1.5 mm lisa en zanja para tuberías 13793.00Canaleta 1000.00 9.94 1.00 1 9943.00Poncho canaleta 1000.00 3.85 1.00 1 3850.00
1.3.3 SISTEMA DE IMPULSION PLS A PLANTA1.3.3.1 ESTACIÓN DE BOMBEO Y MEDICIÓN
1.3.3.1.1 CIVIL1.3.3.1.1.1 Excavación masiva en terreno natural o suelto para explanaciones 6067.93
Plataformado 33.00 52.50 0.25 1 433.13Canaleta 2 800.00 6.55 1.00 1 5240.00
800.00 0.50 0.40 2 320.00Canal Línea RAFF Prog. 0+000 - 0+040 40.00 1.70 1.10 1 74.80
1.3.3.1.1.2 Excavación local en terreno natural o suelto para estructuras 443.22Pase Tub. 18.75 3.81 1.25 1 89.30Buzón de Inspección 6.00 3.80 1.75 1 39.90Canaleta 26.90 1.60 0.70 1 30.13Cimentación Bombas 3.40 3.40 1.25 5 72.25
3.29 1.45 3.15 5 75.03Cajón de Línea 4.90 4.80 1.20 1 28.22
1.35 4.80 0.40 1 2.59Durmientes de Concreto
Soportes tipo SL1 2.50 1.30 1.30 17 71.83Soportes tipo SL2 2.50 1.30 1.10 9 32.18
Sumidero de Drenaje 1.50 1.50 0.80 1 1.80
1.3.3.1.1.3Relleno y compactación con material propio seleccionado para bermas, al
95% del Próctor Modificado. 2414.28Plataformado 33.00 52.50 0.15 1 259.88Trincheras de anclaje 800.00 0.50 0.50 2 400.00Bermas 800.00 1.55 0.70 2 1736.00Canal Línea RAFF Prog. 0+000 - 0+040 40.00 0.20 1.15 2 18.40
1.3.3.1.1.4 Relleno y compactación con material prestamo para estructuras 18.14Buzón de Inspección 6.00 3.80 0.75 1 17.10Sumidero de Drenaje 6.00 0.15 1.15 1 1.04
1.3.3.1.1.6 Superficie de rodadura, E=200mm 16.00Acceso Vehicular 4.00 20.00 0.20 1 16.00
1.3.3.1.1.7 Instalación de geomembrana de HDPE 1.5 mm lisa en zanja para tuberías 16490.83Canaleta 800.00 13.29 1.00 1 10634.40Poncho canaleta 800.00 7.20 1.00 1 5760.00Canal Línea RAFF Prog. 0+000 - 0+040 40.00 2.30 1.00 1 92.00Sumidero de Drenaje - base 0.97 0.97 1.00 1 0.94Sumidero de Drenaje - paredes 3.88 0.90 1.00 1 3.49
1.3.3.1.1.8Instalación de insertos Polylock en estructuras de concreto, bases de
equipos, losas y recubrimiento de tuberías 83.88Canal Línea RAFF Prog. 0+000 - 0+040 40.00 1.00 1.00 2 80.00
15 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
Sumidero de Drenaje - paredes 3.88 1.00 1.00 1 3.88
1.3.3.1.2 CONCRETO1.3.3.1.2.1 Concreto f'c= 100 kg/cm2 para solados 26.64
19.00 7.70 0.05 1 7.3220.00 15.27 0.05 1 15.27
Cajón de Línea 4.90 4.80 0.05 1 1.18Canal Línea RAFF Prog. 0+000 - 0+040 40.00 1.40 0.05 1 2.80Sumidero de Drenaje - paredes 1.27 1.27 0.05 1 0.08
1.3.3.1.2.2Concreto f'c= 210 kg/cm2 para canaletas de drenaje, cimentaciones de
cercos 42.39Canaleta 26.00 0.70 0.15 1 2.73
26.00 0.45 0.15 2 3.5126.00 0.05 0.10 2 0.26
Tapa 2.59 0.50 0.25 35 11.33Canal Línea RAFF Prog. 0+000 - 0+040 - planta 40.00 1.40 0.28 1 15.40Canal Línea RAFF Prog. 0+000 - 0+040 - muros 40.00 0.73 0.15 2 8.70Sumidero de Drenaje - base 1.27 1.27 0.15 1 0.24Sumidero de Drenaje - paredes 1.42 0.15 1.00 1 0.21
1.3.3.1.2.3 Concreto f'c= 280 kg/cm2 para cimentaciones de equipos 93.11Cajón de Línea 4.90 4.80 0.30 1 7.06
4.15 4.05 0.15 -1 -2.5212.80 0.15 0.90 1 1.735.60 0.15 1.40 1 1.181.00 2.00 0.25 2 1.00
Durmientes de ConcretoSoportes tipo SL1 2.40 1.20 1.20 17 58.75Soportes tipo SL2 2.40 1.20 1.00 9 25.92
1.3.3.1.2.4Concreto f'c= 350 kg/cm2 para cimentaciones de equipos, losa de manifold y
pedestales, según lo indicado en planos 204.79Losa 1 19.00 7.75 0.30 1 44.18
2.90 5.10 0.30 -1 -4.44Sardinel 1 34.10 0.15 0.30 1 1.53Buzón de Inspección 5.10 2.90 0.20 1 2.96
5.10 0.20 1.85 2 3.772.50 0.20 1.85 2 1.85
15.00 0.50 0.20 1 1.50Losa 2 20.00 14.55 0.30 1 87.30
2.50 2.50 0.30 -5 -9.38Sardinel 2 48.80 0.15 0.30 1 2.20Cimentación B-1 0.45 0.45 0.40 1 0.08Cimentación B-2 1.20 0.40 0.55 2 0.53Cimentación B-3 1.30 0.40 0.55 2 0.57Cimentación B-4 1.00 0.40 0.50 5 1.00Cimentación B-4A 1.40 0.45 0.50 2 0.63Cimentación B-6 1.40 0.45 0.50 2 0.63Cimentación B-7 1.00 0.40 0.55 4 0.88Cimentación B-8 1.00 0.40 0.55 1 0.22Cimentación B-9 1.00 0.40 0.50 5 1.00Cimentación B-10 0.85 0.40 0.60 2 0.41Cimentación B-11 0.85 0.40 0.60 1 0.20Cimentación B-12 1.10 0.40 0.55 5 1.21Cimentación B-13 1.10 0.40 0.55 4 0.97Cimentación B-13A 1.10 0.40 0.55 4 0.97Cimentación Bombas B-5 2.50 2.50 1.75 5 54.69
0.82 1.00 1.75 -5 -7.151.81 1.00 2.85 5 25.860.82 1.00 2.85 -5 -11.641.81 1.00 0.25 5 2.27
1.3.3.1.2.5 Protección del concreto con recubrimiento polimérico 483.36Losa 1 8.42 19.00 1.00 1 159.98
2.90 5.10 1.00 -1 -14.79Losa 2 20.00 14.55 1.00 1 291.00
2.50 2.50 1.00 -5 -31.25Sardinel 2 48.80 1.00 0.30 1 14.64Cimentación B-1 1.80 0.45 1.00 1 0.81Cimentación B-2 3.20 0.40 1.00 2 2.56Cimentación B-3 3.40 0.40 1.00 2 2.72Cimentación B-4 2.80 0.40 1.00 5 5.60Cimentación B-4A 3.70 0.45 1.00 2 3.33Cimentación B-6 3.70 0.45 1.00 2 3.33Cimentación B-7 2.80 0.40 1.00 4 4.48Cimentación B-8 2.80 0.40 1.00 1 1.12Cimentación B-9 2.80 0.40 1.00 5 5.60Cimentación B-10 2.50 0.40 1.00 2 2.00Cimentación B-11 2.50 0.40 1.00 1 1.00Cimentación B-12 3.00 0.40 1.00 5 6.00Cimentación B-13 3.00 0.40 1.00 4 4.80Cimentación B-13A 3.00 0.40 1.00 4 4.80Cimentación Bombas B-5 2.50 2.50 0.50 5 15.63
1.3.3.1.2.6 Acero de Refuerzo fy=4200 Kg/cm2 38608.66Tapa 1 5/8" 910 1.5 2116 2221.54
3/8" 210 3 352.8 370.44Losa 1 1/2" 172.8 8.1 1386 1454.97
1/2" 72 19.4 1383 1451.97Sardinel 1 1/2" 170 0.7 117.8 123.70
1/2" 3 35 104 109.15Buzón de Inspección 1/2" 30 5.4 160.4 168.40
1/2" 52 3.4 175 183.781/2" 52 2.6 133.8 140.541/2" 104 2.6 267.7 281.081/2" 3 15 44.55 46.781/2" 75 1.4 104 109.15
Canaleta 1/2" 131 2 259.4 272.351/2" 10 26.4 261.4 274.43
Losa 2 1/2" 131.4 20.4 2654 2786.441/2" 180 14.9 2655 2787.94
Sardinel 2 1/2" 245 0.7 169.8 178.271/2" 3 49 145.5 152.81
Cimentación B-1 1 1/2" 1.2 16 19.01 19.961 1/2" 3.4 8 26.93 28.27
Cimentación B-2 1 1/2" 1 16 15.84 16.631 1/2" 3 8 23.76 24.95
Cimentación B-3 2 1/2" 1 16 31.68 33.262 1/2" 3.2 8 50.69 53.22
Cimentación B-4 2 1/2" 1 16 31.68 33.262 1/2" 3.2 8 50.69 53.22
Cimentación B-4A 5 1/2" 1 16 79.2 83.165 1/2" 3.2 8 126.7 133.06
Cimentación B-6 2 1/2" 1 16 31.68 33.262 1/2" 3.2 8 50.69 53.22
Cimentación B-6 2 1/2" 1 16 31.68 33.262 1/2" 3.2 8 50.69 53.22
Cimentación B-7 4 1/2" 1 16 63.36 66.53
16 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
4 1/2" 3.2 8 101.4 106.44Cimentación B-8 1 5/8" 11 16 272.8 286.44
1 5/8" 3 2.8 13.02 13.67Cimentación B-9 5 5/8" 11 16 1364 1432.20
5 5/8" 3 2.8 65.1 68.36Cimentación B-10 2 5/8" 14 16 694.4 729.12
2 5/8" 16 1.6 79.36 83.33Cimentación B-11 1 1/2" 1 16 15.84 16.63
1 1/2" 3.2 8 25.34 26.61Cimentación B-12 5 5/8" 11 16 1364 1432.20
5 5/8" 3.2 2.8 69.44 72.91Cimentación B-13 4 5/8" 11 16 1091 1145.76
4 5/8" 3.2 2.8 55.55 58.33Cimentación B-13A 4 5/8" 14 16 1389 1458.24
4 5/8" 3.2 1.6 31.74 33.33Cimentación Bombas 1/2" 60 2.8 166.3 174.64
1/2" 60 2.1 124.7 130.981/2" 8 3.6 28.51 29.941/2" 15 3.6 53.46 56.131/2" 15 4.2 62.37 65.491/2" 20 3.8 75.24 79.001/2" 20 3.2 63.36 66.531/2" 32 1.6 50.69 53.22
Cajón de Línea 1/2" 50 5.6 277.2 291.061/2" 98 1.3 126.1 132.431/2" 8 19.6 155.2 162.995/8" 22 3.6 122.8 128.905/8" 10 5.6 86.8 91.14
Durmientes de concretoSoporte SL1 17 3/4" 4.4 12 2011 2111.16
17 3/4" 6.8 20 5179 5437.8217 1/2" 3.2 12 646.3 678.5917 1/2" 6.8 20 2289 2403.32
Soporte SL2 9 3/4" 4.4 12 1064 1117.679 3/4" 6.8 20 2742 2878.859 1/2" 3.2 12 342.1 359.259 1/2" 6.8 20 1212 1272.35
Sumidero de Drenaje - base 1 1/2" 7 3.14 21.76 22.851 1/2" 7 3.14 21.76 22.85
Sumidero de Drenaje - paredes 1 1/2" 7 3.14 21.76 22.851 1/2" 7 3.14 21.76 22.85
1.3.3.1.2.7 Suministro y colocación de pernos de anclaje ASTM A36 N° 593.03B-1 T2 - 111 1 5/8" 4 0.3 1.86 2.10B-2 T2 - 111 2 1 1/4" 8 0.65 82.26 82.74B-3 T2 - 111 2 1 1/4" 8 0.65 82.26 82.74B-4 T2 - 111 5 3/4" 4 0.385 17.25 18.45B-4A T2 - 111 2 1 1/4" 8 0.65 82.26 82.74B-5 T2 - 111 5 3/4" 4 0.385 17.25 18.45B-6 T2 - 111 2 1 1/4" 8 0.65 82.26 82.74B-7 T2 - 111 4 5/8" 4 0.36 8.928 9.89B-8 T2 - 111 1 1" 4 0.55 8.756 9.00B-9 T2 - 111 5 5/8" 8 0.36 22.32 23.52B-10 T2 - 111 2 3/4" 4 0.385 6.899 7.38B-11 T2 - 111 1 5/8" 8 0.36 4.464 4.70B-12 T2 - 111 5 1 1/4" 4 0.65 102.8 104.03B-13 T2 - 111 4 3/4" 8 0.385 27.6 28.56B-13A T2 - 111 4 1" 4 0.55 35.02 35.98
1.3.1.1.2.8 Suministro y colocación de grout cementicio E=25mm 0.44Cimentación B-1 0.45 0.45 0.03 1 0.01Cimentación B-2 1.20 0.40 0.03 2 0.02Cimentación B-3 1.30 0.40 0.03 2 0.03Cimentación B-4 1.00 0.40 0.03 5 0.05Cimentación B-4A 1.40 0.45 0.03 2 0.03Cimentación B-6 1.40 0.45 0.03 2 0.03Cimentación B-7 1.00 0.40 0.03 4 0.04Cimentación B-8 1.00 0.40 0.03 1 0.01Cimentación B-9 1.00 0.40 0.03 5 0.05Cimentación B-10 0.85 0.40 0.03 2 0.02Cimentación B-11 0.85 0.40 0.03 1 0.01Cimentación B-12 1.10 0.40 0.03 5 0.06Cimentación B-13 1.10 0.40 0.03 4 0.04Cimentación B-13A 1.10 0.40 0.03 4 0.04
1.3.1.1.2.9 Suministro y colocación de grout epóxico E=25mm 1.56Cimentación Bombas B-5 2.50 2.50 0.05 5 1.56
1.3.3.1.2.10 Juntas de Contracción 128.607.80 1.00 1.00 3 23.40
16.00 1.00 1.00 1 16.0020.00 1.00 1.00 3 60.0014.60 1.00 1.00 2 29.20
1.3.3.1.2.11 Juntas de Expansión 153.7024.60 1.00 1.00 2 49.2010.00 1.00 1.00 5 50.0010.90 1.00 1.00 5 54.50
1.3.3.2 TUBERÍA PRINCIPAL A PLANTA
1.3.3.2.1 CIVIL1.3.3.2.1.1 Excavación masiva en terreno natural o suelto para explanaciones 5112.00
Canaleta 900.00 4.40 1.20 1 4752.00Trincheras de anclaje 900.00 0.50 0.40 2 360.00
1.3.3.2.1.2 Excavación local en terreno natural o suelto para estructuras 26.03Botas de Concreto 2.50 0.40 0.65 30 19.50Cimentación SL3 1.10 1.10 0.90 6 6.53
1.3.3.2.1.3Relleno y compactación con material propio seleccionado para bermas, al
95% del Próctor Modificado. 2403.00Trincheras de anclaje 900.00 0.50 0.50 2 450.00Bermas 900.00 1.55 0.70 2 1953.00
1.3.3.2.1.4Relleno con material préstamo para estructuras, al 95% del Próctor
Modificado. 15.96Botas de Concreto 2.50 0.40 0.40 30 12.00Cimentación SL3 4.40 0.15 1.00 6 3.96
1.3.3.2.1.6 Superficie de rodadura, E=200mm 18.00Acceso Vehicular 4.50 20.00 0.20 1 18.00
1.3.1.2.1.7 Instalación de geomembrana de HDPE 1.5 mm lisa en zanja para tuberías 15677.18Canaleta 900.00 11.74 1.00 1 10568.70Poncho canaleta 900.00 5.65 1.00 1 5085.00Canaletas 1 17.26 0.60 1.00 2 20.71Canaletas 2 2.31 0.60 1.00 2 2.77
17 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
1.3.1.2.1.8Instalación de insertos Polylock en estructuras de concreto, bases de
equipos, losas y recubrimiento de tuberías 39.14Canaletas 1 17.26 1.00 1.00 2 34.52Canaletas 2 2.31 1.00 1.00 2 4.62
1.3.1.2.1.9 Parrilla GR-15 SM (1.1/2" SM-PRFV) Fibra de vidrio 10.59Sumideros 24.60 0.40 1.00 1 9.84Sumideros 1.88 0.40 1.00 1 0.75
1.3.3.2.2 CONCRETO1.3.3.2.2.1 Concreto f'c= 100 kg/cm2 para solados 17.49
17.85 2.91 0.05 1 2.60Soportes de concreto 3 2.60 2.00 0.05 20 5.20Anclajes de concreto 1 4.00 4.00 0.05 10 8.00Botas de Concreto 2.50 0.40 0.05 30 1.50Cimentación SL3 0.80 0.80 0.05 6 0.19
1.3.3.2.2.2Concreto f'c= 280 kg/cm2 para canaletas de drenaje, cimentaciones de
cercos 223.65Pase Tub. - Losa 17.90 2.91 0.30 1 15.63Pase Tub. - Muro largo 17.85 0.30 0.66 2 7.07Pase Tub. - Muro ancho 17.85 0.15 0.25 2 1.34
2.31 0.25 0.90 2 1.04Soportes de concreto 3 2.60 2.00 0.50 20 52.00
2.60 0.50 1.00 20 26.00Anclajes de concreto 1 4.00 4.00 0.50 10 80.00
2.60 0.50 1.50 10 19.50Botas de Concreto 2.50 0.40 0.60 30 18.00Cimentación SL3 0.80 0.80 0.80 6 3.07
1.3.3.2.2.3 Acero de Refuerzo fy=4200 Kg/cm2 31783.02Pase Tub. 1/2" 180 3.3 588.1 617.46
1/2" 20 18.3 362.3 380.461/2" 20 18.3 362.3 380.461/2" 180 1.4 249.5 261.951/2" 180 1.55 276.2 290.021/2" 8 18.3 144.9 152.181/2" 180 0.9 160.4 168.401/2" 13 1 12.87 13.511/2" 6 2.4 14.26 14.97
Soportes de concreto 3 20 5/8" 32 3.2 158.7 3333.1220 5/8" 22 6 204.6 4296.6020 5/8" 12 6 111.6 2343.6020 5/8" 30 2.5 116.3 2441.25
Anclajes de concreto 1 10 3/4" 40 5 448 4704.0010 3/4" 40 5 448 4704.0010 5/8" 18 6 167.4 1757.7010 5/8" 30 3 139.5 1464.75
Botas de Concreto 30 3/4" 10 3 67.2 2116.8030 3/8" 44 2.4 59.14 1862.78
Cimentación SL3 6 1/2" 3.2 12 228.1 239.506 1/2" 3.2 12 228.1 239.50
1.3.3.2.2.4 Suministro y colocación de pernos de anclaje ASTM A36 N° 315.22Soportes de concreto SL3 6 1" 4 0.55 52.54 315.22
1.3.3.4 SUBESTACION ELECTRICA BOMBAS
1.3.3.4.1 CIVIL1.3.3.4.1.1 Excavación local en terreno natural o suelto para estructuras 330.97
Cimentación TR-10MVA 6.40 5.10 1.20 1 39.17Canaleta 1 6.20 2.15 1.50 1 20.00Canaleta 2 4.90 2.30 1.50 1 16.91Muro Cortafuego 1 7.00 3.50 1.90 1 46.55Muro Cortafuego 2 5.40 3.50 1.90 1 35.91B-9 2.10 2.10 0.25 3 3.31B-5 2.70 2.70 2.20 9 144.34B-8 2.70 2.70 1.50 1 10.94B-6 2.10 3.30 1.00 2 13.86
1.3.3.4.1.2 Relleno con material préstamo para estructuras 38.02Cimentación TR-10MVA 6.40 5.10 0.50 1 16.32Muro Cortafuego 1 7.00 3.50 0.50 1 12.25Muro Cortafuego 2 5.40 3.50 0.50 1 9.45
1.3.1.4.1.4 Superficie final de rodadura, E=200mm 64.00Acceso Vehicular 4.00 80.00 0.20 1 64.00
1.3.3.4.2 CONCRETO1.3.3.4.2.1 Concreto f'c= 100 kg/cm2 para solados 5.99
Cimentación TR-10MVA 5.50 4.20 0.05 1 1.16Canaleta 1 5.30 1.25 0.05 1 0.33Losa para Celdas 2.70 3.48 0.05 1 0.47
5.90 0.25 0.05 1 0.071.00 2.03 0.05 1 0.10
Canaleta 2 4.00 1.40 0.05 1 0.28Muro Cortafuego 1 2.50 6.00 0.05 1 0.75Muro Cortafuego 2 2.50 4.40 0.05 1 0.55B-3 1.75 1.75 0.05 1 0.15B-9 1.20 1.20 0.05 3 0.22B-5 1.80 1.80 0.05 9 1.46B-8 1.80 1.80 0.05 1 0.16B-6 1.20 2.40 0.05 2 0.29
1.3.3.4.2.2Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, muros, losa de
piso y cimentación de cuarto de control, según lo indicado en planos 79.51Cimentación TR-10MVA 5.50 4.20 0.55 1 12.71
18.60 1.00 0.20 1 3.723.50 2.20 1.10 1 8.47
Canaleta 1 5.30 1.25 0.15 1 0.995.30 1.40 0.30 1 2.230.95 1.40 0.15 2 0.40
Losa para Celdas 2.70 3.48 0.20 1 1.885.90 0.25 0.20 1 0.301.00 2.03 0.20 1 0.415.90 0.25 0.20 1 0.30
Canaleta 2 4.00 1.40 0.15 1 0.844.00 1.40 0.30 1 1.680.95 1.40 0.15 2 0.40
Muro Cortafuego 2.50 4.40 0.40 2 8.800.30 4.40 5.35 2 14.12
B-3 1.40 1.40 0.15 1 0.29B-9 1.20 1.20 0.50 3 2.16B-5 1.80 1.80 0.40 9 11.66
0.40 0.40 2.43 9 3.49B-8 1.80 1.80 0.40 1 1.30
0.40 0.40 1.65 1 0.26B-6 1.20 2.40 0.40 2 2.30
0.35 0.35 1.10 4 0.54
18 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
Tapa Canaleta 1.00 0.33 0.08 11 0.27
1.3.3.4.2.3 Acero de Refuerzo fy=4200 Kg/cm2 6025.81Cimentación TR-10MVA 1/2" 23 5.9 134.3 141.06
1/2" 18 4.6 81.97 86.071/2" 44 2.2 95.83 100.621/2" 34 2.2 74.05 77.751/2" 10 3.9 38.61 40.541/2" 15 2.6 38.61 40.541/2" 25 1.6 39.6 41.581/2" 4 11.4 45.14 47.401/2" 4 14.6 57.82 60.711/2" 75 1.7 126.2 132.541/2" 10 19.4 192.1 201.66
Canaleta 1 1/2" 7 5.3 36.73 38.571/2" 27 1.55 41.43 43.501/2" 14 5.3 73.46 77.131/2" 54 1.7 90.88 95.431/2" 12 1.2 14.26 14.97
Losa para Celdas 1/2" 28 4.8 133.1 139.711/2" 44 3.1 135 141.791/2" 64 1 63.36 66.53
Canaleta 2 1/2" 7 4 27.72 29.111/2" 20 1.7 33.66 35.341/2" 14 4 55.44 58.211/2" 40 1.7 67.32 70.691/2" 12 1.2 14.26 14.97
Muro Cortafuego 5/8" 48 4.8 357.1 374.985/8" 72 3.1 346 363.265/8" 72 6.1 680.8 714.805/8" 80 4.8 595.2 624.96
B-3 1/2" 16 1.2 19.01 19.96B-9 1/2" 48 1.4 66.53 69.85B-5 5/8" 54 2.5 209.3 219.71
5/8" 54 2.5 209.3 219.715/8" 54 2.5 209.3 219.715/8" 54 2.5 209.3 219.715/8" 72 3.225 359.9 377.913/8" 180 1.6 161.3 169.343/8" 153 1.2 102.8 107.96
B-8 5/8" 6 2.5 23.25 24.415/8" 6 2.5 23.25 24.415/8" 6 2.5 23.25 24.415/8" 6 2.5 23.25 24.415/8" 8 2.45 30.38 31.903/8" 13 1.6 11.65 12.233/8" 10 1.2 6.72 7.06
B-6 5/8" 16 1.9 47.12 49.485/8" 16 1.9 47.12 49.485/8" 16 1.9 47.12 49.485/8" 16 1.9 47.12 49.485/8" 32 1.9 94.24 98.953/8" 36 1.4 28.22 29.643/8" 24 1.05 14.11 14.82
Tapa Canaleta 3/8" 55 1 30.8 32.341/4" 55 0.35 4.813 5.05
1.3.3.1.2.4 Suministro y colocación de pernos de anclaje ASTM A36 N° 41.80T2 - 312 1 1" 4 0.5 7.96 8.20
P-1 T2 - 314 10 5/8" 4 0.3 18.6 21.00P-2 T2 - 314 6 5/8" 4 0.3 11.16 12.60
1.3.3.4.2.5 Suministro y colocación de grout cementicio E=25mm 0.05B-5 0.40 0.40 0.03 9 0.04B-8 0.40 0.40 0.03 1 0.00B-6 0.35 0.35 0.03 4 0.01
1.3.3.4.2.6 Juntas de Contracción 5.402.70 1.00 1.00 2 5.40
1.3.3.4.2.7 Juntas de Expansión 8.702.70 1.00 1.00 2 5.403.30 1.00 1.00 1 3.30
1.3.4 ÁCIDO SULFÚRICO1.3.4.1 ESTACIONES DE BOMBEO
1.3.4.1.1 CIVIL1.3.4.1.1.1 Excavación masiva en terreno natural o suelto para explanaciones 2456.09
Plataformado General 6.80 6.80 0.20 1 9.25Canaleta 2022.79 1.00 1.00 1 2022.79Tricheras de anclajes 1000.00 0.50 0.40 2 400.00Canal de línea de Acido Prog. 0+000 - 0+037m 37.00 1.00 0.65 1 24.05
1.3.4.1.1.2 Excavación local en terreno natural o suelto para explanaciones 29.45Cimentación B-7 1.35 2.60 0.15 2 1.05Soportes de concreto SL3 Tubo 20" 1.20 1.20 1.20 1.00 1.73Soportes de concreto SL3 Tubo 12" 1.20 1.20 1.20 4.00 6.91Soportes de concreto SL3 Tubo 18" 1.20 1.20 1.20 11.00 19.01Sumidero de Drenaje 1.29 1.29 0.45 1 0.75
1.3.4.1.1.3Relleno con material propio seleccionado para estructuras (incluye
excavación de cunetas en tierra y eliminación de material excedente). 11.73Cimentación B-7 1.35 2.60 0.15 2 1.05Sumidero 2 0.80 0.90 1.25 1 0.90Soportes de concreto SL3 Tubo 20" 0.80 0.20 1.00 1 0.16Soportes de concreto SL3 Tubo 12" 0.80 0.20 1.00 4 0.64Soportes de concreto SL3 Tubo 18" 0.80 0.20 1.00 11 1.76Canal de línea de Acido Prog. 0+000 - 0+037m 37.00 0.30 0.65 1 7.22
1.3.4.1.1.4 Relleno y compactación con material propio seleccionado para bermas 4179.89Canaleta 1000.00 1.50 1.00 1 1500.00
1786.59 1.50 1.00 1 2679.89
1.3.4.1.1.5 Relleno con material de préstamo para estructuras 0.90Sumidero 2 0.80 0.90 1.25 1 0.90
1.3.4.1.1.7 Superficie de rodadura, E=200mm 12.00Acceso Vehicular 3.00 20.00 0.20 1 12.00
1.3.4.1.1.8 Instalación de geomembrana de HDPE 1.5 mm lisa en zanja para tuberías 8633.81Canaleta 1000.00 6.00 1.00 1 6000.00
1000.00 2.60 1.00 1 2600.00Canal de línea de Acido Prog. 0+000 - 0+037m 37.00 0.90 1.00 1 33.30Sumidero de Drenaje - base 0.39 0.39 1.00 1 0.15Sumidero de Drenaje - paredes 1.20 0.30 1.00 1 0.36
19 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
1.3.3.1.1.9Instalación de insertos Polylock en estructuras de concreto, bases de
equipos, losas y recubrimiento de tuberías 75.56Canal de línea de Acido Prog. 0+000 - 0+037m 37.00 1.00 1.00 2 74.00Sumidero de Drenaje - paredes 1.56 1.00 1.00 1 1.56
1.3.4.1.2 CONCRETO1.3.4.1.2.1 Concreto f'c= 100 kg/cm2 para solados 3.74
Losa 2 6.80 5.20 0.05 1 1.77Cimentación B-7 1.60 0.80 0.05 2 0.13Soportes de concreto SL3 Tubo 20" 1.00 1.00 0.05 1 0.05Soportes de concreto SL3 Tubo 12" 0.80 0.80 0.05 4 0.13Soportes de concreto SL3 Tubo 18" 0.80 0.80 0.05 11 0.35Canal de línea de Acido Prog. 0+000 - 0+037m 37.00 0.70 0.05 1 1.30Sumidero de Drenaje - paredes 0.69 0.69 0.05 1 0.02
1.3.4.1.2.2Concreto f'c= 280 kg/cm2 para canaletas de drenaje, cimentaciones de
cercos 17.14Soportes de concreto SL3 Tubo 20" 1.00 1.00 1.20 1 1.20Soportes de concreto SL3 Tubo 12" 0.80 0.80 0.80 4 2.05Soportes de concreto SL3 Tubo 18" 0.80 0.80 0.80 11 5.63Canal de línea de Acido Prog. 0+000 - 0+037m - planta 37.00 0.70 0.15 1 3.89Canal de línea de Acido Prog. 0+000 - 0+037m - muros 37.00 0.38 0.15 2 4.16Sumidero de Drenaje - base 0.00 1.27 0.15 1 0.00Sumidero de Drenaje - paredes 1.42 0.15 1.00 1 0.21
1.3.4.1.2.3Concreto f'c= 350 kg/cm2 para cimentaciones de equipos, losa de manifold y
pedestales, según lo indicado en planos 6.67Losa 2 6.80 5.20 0.15 1 5.30Sardinel 6.35 0.20 1.00 1 1.27Sumidero 2 0.40 0.50 0.15 2 0.06
0.40 0.50 0.10 2 0.04
1.3.4.1.2.4 Protección del concreto con recubrimiento polimérico 98.78Losa 1 4.80 4.90 1.00 1 23.52Sardinel 4.80 4.90 0.80 4 75.26
1.3.4.1.2.5 Acero de Refuerzo fy=4200 Kg/cm2 1848.98Losa 2 1/2" 35 5.5 190.6 200.10
1/2" 27 7 187.1 196.47Sardinel 1/2" 13.05 2 25.84 27.13
1/2" 6.35 2 12.57 13.201/2" 17.85 2 35.34 37.11
Sumidero 2 1/2" 6 0.5 2.97 3.12N° 1/2" 6 0.5 2.97 3.12
Soportes de concreto SL3 Tubo 20" 1 1/2" 3.2 12 38.02 39.921 1/2" 3.2 12 38.02 39.92
Soportes de concreto SL3 Tubo 12" 4 1/2" 3.2 12 152.1 159.674 1/2" 3.2 12 152.1 159.67
Soportes de concreto SL3 Tubo 18" 11 1/2" 3.2 12 418.2 439.0811 1/2" 3.2 12 418.2 439.08
Sumidero de Drenaje - base 1 1/2" 7 3.14 21.76 22.851 1/2" 7 3.14 21.76 22.85
Sumidero de Drenaje - paredes 1 1/2" 7 3.14 21.76 22.851 1/2" 7 3.14 21.76 22.85
1.3.4.1.2.6 Suministro y colocación de pernos de anclaje ASTM A36 N° 143.80B-1 T2 - 111 2 3/4" 4 0.36 3.226 3.71Soportes de concreto SL3 Tubo 20" T2 - 111 1 1" 4 0.55 8.756 8.76Soportes de concreto SL3 Tubo 12" T2 - 111 4 1" 4 0.55 8.756 35.02Soportes de concreto SL3 Tubo 18" T2 - 111 11 1" 4 0.55 8.756 96.32
1.3.4.1.2.7 Suministro y colocación de grout cementicio E=25mm 0.07Cimentación B-1 1.20 0.30 0.05 4 0.07
1.3.4.1.2.8 Juntas de Contracción 9.604.80 1.00 1.00 2 9.60
1.3.4.1.2.9 Parrilla GR-15 SM (1.1/2" SM-PRFV) Fibra de vidrio 0.16Sumidero 2 0.40 0.40 1.00 1 0.16
1.4 SISTEMA DE AIREACIÓN PILA1.4.1 SISTEMA DE AIREACIÓN PILA1.4.1.1 ESTACIÓN DE SOPLADORES
1.4.1.1.1 CIVIL1.4.4.1.1.1 Excavación masiva en terreno natural o suelto para explanaciones 575.72
Plataformado General - Estación Sopladores N° 1 39.65 24.20 0.20 1 191.91Plataformado General - Estación Sopladores N° 2 39.65 24.20 0.20 1 191.91Plataformado General - Estación Sopladores N° 3 39.65 24.20 0.20 1 191.91
1.4.1.1.1.2 Excavación local en terreno natural o suelto para estructuras 7.14Estación Sopladores N° 1
B-5 2.30 2.30 0.45 1 2.38Estación Sopladores N° 2
B-5 2.30 2.30 0.45 1 2.38Estación Sopladores N° 3
B-5 2.30 2.30 0.45 1 2.38
1.4.1.1.1.3 Excavación local en terreno natural o suelto para estructuras 121.76Estación Sopladores N° 1
B-1 1.20 0.45 0.20 3 0.32B-2 1.20 0.45 0.20 2 0.22B-2A 1.20 0.45 0.20 2 0.22B-2B 1.20 0.45 0.20 4 0.43B-3 1.00 1.00 0.40 4 1.60B-4 4.80 2.40 0.25 4 11.52B-6 10.40 0.60 1.45 1 9.05Canaleta 1 14.2 0.7 0.7 1 6.96Canaleta 2 3.95 0.90 1.30 1 4.62
Estación Sopladores N° 2
B-1 1.20 0.45 0.20 3 0.32B-2 1.20 0.45 0.20 2 0.22B-2A 1.20 0.45 0.20 2 0.22B-2B 1.20 0.45 0.20 4 0.43B-3 1.00 1.00 0.40 4 1.60B-4 4.80 2.40 0.50 4 23.04B-6 10.40 0.60 1.45 1 9.05Canaleta 1 14.2 0.7 0.7 1 6.96Canaleta 2 3.95 0.90 1.30 1 4.62
Estación Sopladores N° 3
B-1 1.20 0.45 0.20 3 0.32B-2A 1.20 0.45 0.20 2 0.22B-2B 1.20 0.45 0.20 3 0.32B-3 1.00 1.00 0.40 4 1.60B-4 4.80 2.40 0.50 3 17.28B-6 10.40 0.60 1.45 1 9.05Canaleta 1 14.2 0.7 0.7 1 6.96Canaleta 2 3.95 0.90 1.30 1 4.62
20 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
1.4.1.1.1.4 Relleno con material préstamo para estructuras 3.97Estación Sopladores N° 1
B-5 2.30 2.30 0.25 1 1.32Estación Sopladores N° 2
B-5 2.30 2.30 0.25 1 1.32Estación Sopladores N° 3
B-5 2.30 2.30 0.25 1 1.32
1.4.1.1.2 CONCRETO1.4.1.1.2.1 Concreto f'c= 100 kg/cm2 para solados 59.21
Estación Sopladores N° 1
29.65 14.20 0.05 1 21.05Estación Sopladores N° 2
29.65 14.20 0.05 1 21.05Estación Sopladores N° 3
24.10 14.20 0.05 1 17.11
1.4.1.1.2.2 Concreto f'c= 210 kg/cm2 para cimentaciones de cercos 7.20Estación Sopladores N° 1
0.40 0.40 0.50 30 2.40Estación Sopladores N° 2
0.40 0.40 0.50 30 2.40Estación Sopladores N° 3
0.40 0.40 0.50 30 2.40
1.4.1.1.2.3Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, losa de piso y
pedestales, según lo indicado en planos 337.55Estación Sopladores N° 1
Losa piso 1 23.20 14.20 0.15 1 49.424.80 2.40 0.15 -4 -6.91
Sardinel 1 57.70 0.15 0.25 1 2.16Losa piso 2 5.75 14.20 0.15 1 12.25
2.30 2.30 0.15 -1 -0.793.95 0.90 0.15 -1 -0.53
Sardinel 2 39.20 0.15 0.25 1 1.47B-1 1.20 0.60 0.50 3 1.08B-2 1.40 0.45 0.50 2 0.63B-2A 1.40 0.45 0.55 2 0.69B-2B 1.00 0.45 0.50 4 0.90B-3 1.00 1.00 0.25 4 1.00B-4 4.80 2.40 0.85 4 39.17B-5 2.30 2.30 0.20 1 1.06
8.60 0.15 0.65 1 0.841.00 1.00 0.85 1 0.85
B-6 10.40 0.60 0.80 1 4.9910.40 0.15 3.10 1 4.84
Canaleta 1 14.2 0.7 0.15 1 1.4914.2 0.7 0.3 1 2.980.4 0.7 0.15 2 0.08
Canaleta 2 3.95 0.90 0.15 1 0.533.95 0.90 0.30 1 1.070.60 0.90 0.15 2 0.16
Estación Sopladores N° 2
Losa piso 1 23.20 14.20 0.15 1 49.424.80 2.40 0.15 -4 -6.91
Sardinel 1 57.70 0.15 0.25 1 2.16Losa piso 2 5.75 14.20 0.15 1 12.25
2.30 2.30 0.15 -1 -0.793.95 0.90 0.15 -1 -0.53
Sardinel 2 39.20 0.15 0.25 1 1.47B-1 1.20 0.60 0.50 3 1.08B-2 1.40 0.45 0.50 2 0.63B-2A 1.40 0.45 0.55 2 0.69B-2B 1.00 0.45 0.50 4 0.90B-3 1.00 1.00 0.25 4 1.00B-4 4.80 2.40 0.85 4 39.17B-5 2.30 2.30 0.20 1 1.06
8.60 0.15 0.65 1 0.841.00 1.00 0.85 1 0.85
B-6 10.40 0.60 0.80 1 4.9910.40 0.15 3.10 1 4.84
Canaleta 1 14.2 0.7 0.15 1 1.4914.2 0.7 0.3 1 2.980.4 0.7 0.15 2 0.08
Canaleta 2 3.95 0.90 0.15 1 0.533.95 0.90 0.30 1 1.070.60 0.90 0.15 2 0.16
Estación Sopladores N° 3
Losa piso 1 17.45 14.20 0.15 1 37.174.80 2.40 0.15 -3 -5.18
Sardinel 1 44.90 0.15 0.25 1 1.68Losa piso 2 5.75 14.20 0.15 1 12.25
2.30 2.30 0.15 -1 -0.793.95 0.90 0.15 -1 -0.53
Sardinel 2 39.20 0.15 0.25 1 1.47B-1 1.20 0.45 0.50 3 0.81B-2A 1.40 0.45 0.50 5 1.58B-2B 1.00 0.45 0.55 5 1.24B-3 1.00 1.00 0.25 3 0.75B-4 4.80 2.40 0.85 3 29.38B-5 2.30 2.30 0.20 1 1.06
8.60 0.15 0.65 1 0.841.00 1.00 0.85 1 0.85
B-6 10.40 0.60 0.80 1 4.9910.40 0.15 3.10 1 4.84
Canaleta 1 14.2 0.7 0.15 1 1.4914.2 0.7 0.3 1 2.980.4 0.7 0.15 2 0.08
Canaleta 2 3.95 0.90 0.15 1 0.533.95 0.90 0.30 1 1.070.60 0.90 0.15 2 0.16
1.4.1.1.2.4 Acero de Refuerzo fy=4200 Kg/cm2 22086.36Estación Sopladores N° 1
Losa piso 1 1/2" 61.2 23.7 1436 1507.731/2" 99.45 14.7 1447 1519.66
Sardinel 1 1/2" 289 0.7 200.3 210.291/2" 3 57.8 171.7 180.25
Losa piso 2 1/2" 64.8 6.2 397.7 417.631/2" 15.95 14.65 231.3 242.90
Sardinel 2 1/2" 196 0.7 135.8 142.621/2" 3 39.6 117.6 123.49
Cimentación B-1 3 1/2" 1.2 16 57.02 59.883 1/2" 3.4 8 80.78 84.82
Cimentación B-2 2 1/2" 1 16 31.68 33.262 1/2" 3 8 47.52 49.90
Cimentación B-2A 2 1/2" 1 16 31.68 33.262 1/2" 3.2 8 50.69 53.22
Cimentación B-2B 4 1/2" 1 16 63.36 66.53
21 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
4 1/2" 3.2 8 101.4 106.44B-3 1/2" 80 1.4 110.9 116.42B-4 5/8" 80 5.9 731.6 768.18
5/8" 160 3.5 868 911.40B-5 1/2" 48 2.6 123.6 129.73
1/2" 46 1.1 50.09 52.601/2" 3 6 17.82 18.711/2" 3 9.2 27.32 28.691/2" 10 3.4 33.66 35.34
B-6 1/2" 16 10.4 164.7 172.971/2" 52 4.1 211.1 221.62
Canaleta 1 1/2" 4 14.2 56.23 59.041/2" 71 1 70.29 73.801/2" 8 14.2 112.5 118.091/2" 142 1 140.6 147.61
Canaleta 2 1/2" 5 3.95 19.55 20.531/2" 20 1.2 23.76 24.951/2" 10 3.95 39.11 41.061/2" 40 1.2 47.52 49.90
Estación Sopladores N° 2
Losa piso 1 1/2" 61.2 23.7 1436 1507.731/2" 99.45 14.7 1447 1519.66
Sardinel 1 1/2" 289 0.7 200.3 210.291/2" 3 57.8 171.7 180.25
Losa piso 2 1/2" 64.8 6.2 397.7 417.631/2" 15.95 14.65 231.3 242.90
Sardinel 2 1/2" 196 0.7 135.8 142.621/2" 3 39.6 117.6 123.49
Cimentación B-1 3 1/2" 1.2 16 57.02 59.883 1/2" 3.4 8 80.78 84.82
Cimentación B-2 2 1/2" 1 16 31.68 33.262 1/2" 3 8 47.52 49.90
Cimentación B-2A 2 1/2" 1 16 31.68 33.262 1/2" 3.2 8 50.69 53.22
Cimentación B-2B 4 1/2" 1 16 63.36 66.534 1/2" 3.2 8 101.4 106.44
B-3 1/2" 80 1.4 110.9 116.42B-4 5/8" 80 5.9 731.6 768.18
5/8" 160 3.5 868 911.40B-5 1/2" 48 2.6 123.6 129.73
1/2" 46 1.1 50.09 52.601/2" 3 6 17.82 18.711/2" 3 9.2 27.32 28.691/2" 10 3.4 33.66 35.34
B-6 1/2" 16 10.4 164.7 172.971/2" 52 4.1 211.1 221.62
Canaleta 1 1/2" 4 14.2 56.23 59.041/2" 71 1 70.29 73.801/2" 8 14.2 112.5 118.091/2" 142 1 140.6 147.61
Canaleta 2 1/2" 5 3.95 19.55 20.531/2" 20 1.2 23.76 24.951/2" 10 3.95 39.11 41.061/2" 40 1.2 47.52 49.90
Estación Sopladores N° 3
Losa piso 1 1/2" 45.9 23.7 1077 1130.801/2" 74.59 14.7 1085 1139.75
Sardinel 1 1/2" 231.2 0.7 160.2 168.231/2" 2.4 57.8 137.3 144.20
Losa piso 2 1/2" 64.8 6.2 397.7 417.631/2" 15.95 14.65 231.3 242.90
Sardinel 2 1/2" 196 0.7 135.8 142.621/2" 3 39.6 117.6 123.49
Cimentación B-1 3 1/2" 1.2 16 57.02 59.883 1/2" 3.4 8 80.78 84.82
Cimentación B-2A 2 1/2" 1 16 31.68 33.262 1/2" 3.2 8 50.69 53.22
Cimentación B-2B 3 1/2" 1 16 47.52 49.903 1/2" 3.2 8 76.03 79.83
B-3 1/2" 80 1.4 110.9 116.42B-4 5/8" 60 5.9 548.7 576.14
5/8" 120 3.5 651 683.55B-5 1/2" 48 2.6 123.6 129.73
1/2" 46 1.1 50.09 52.601/2" 3 6 17.82 18.711/2" 3 9.2 27.32 28.691/2" 10 3.4 33.66 35.34
B-6 1/2" 16 10.4 164.7 172.971/2" 52 4.1 211.1 221.62
Canaleta 1 1/2" 4 14.2 56.23 59.041/2" 71 1 70.29 73.801/2" 8 14.2 112.5 118.091/2" 142 1 140.6 147.61
Canaleta 2 1/2" 5 3.95 19.55 20.531/2" 20 1.2 23.76 24.951/2" 10 3.95 39.11 41.061/2" 40 1.2 47.52 49.896
1.4.1.1.2.5 Suministro y colocación de pernos de anclaje ASTM A36 N° 394.07Estación Sopladores N° 1
B1 T2 - 310 3 1" 4 0.55 26.27 26.99B2 T2 - 310 2 1 1/4" 4 0.65 41.13 41.61B2A T2 - 310 2 1" 8 0.55 35.02 35.50B2B T2 - 310 4 3/4" 4 0.385 13.8 14.76B4 T2 - 310 4 1 3/8" 4 0.65 0.96B5 T2 - 310 1 1" 4 0.5 7.96 8.20Escalera Estación Sopladores N° 1 2 1" 4 0.5 15.92 16.40
Estación Sopladores N° 2
B1 T2 - 310 3 1" 4 0.55 26.27 26.99B2 T2 - 310 2 1 1/4" 4 0.65 41.13 41.61B2A T2 - 310 2 1" 8 0.55 35.02 35.50B2B T2 - 310 4 3/4" 4 0.385 13.8 14.76B4 T2 - 310 4 1 3/8" 4 0.65 0.96B5 T2 - 310 1 1" 4 0.5 7.96 8.20Escalera Estación Sopladores N° 2 2 1" 4 0.5 15.92 16.40
Estación Sopladores N° 2
B1 T2 - 310 3 1" 4 0.55 26.27 26.99B2A T2 - 310 2 1 1/4" 4 0.65 41.13 41.61B2B T2 - 310 3 3/4" 4 0.385 10.35 11.07B4 T2 - 310 4 1 3/8" 4 0.65 0.96B5 T2 - 310 1 1" 4 0.5 7.96 8.20Escalera Estación Sopladores N° 3 2 1" 4 0.5 15.92 16.40
1.4.1.1.2.6 Suministro y colocación de grout cementicio E=25mm 0.90Estación Sopladores N° 1
B-1 1.20 0.60 0.03 3 0.05B-2 1.40 0.45 0.03 2 0.03B-2A 1.40 0.45 0.03 2 0.03
22 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
B-2B 1.00 0.45 0.03 4 0.05B-5 2.30 2.30 0.03 1 0.13
Estación Sopladores N° 2
B-1 1.20 0.60 0.03 3 0.05B-2 1.40 0.45 0.03 2 0.03B-2A 1.40 0.45 0.03 2 0.03B-2B 1.00 0.45 0.03 4 0.05B-5 2.30 2.30 0.03 1 0.13
Estación Sopladores N° 3
B-1 1.20 0.45 0.03 3 0.04B-2A 1.40 0.45 0.03 5 0.08B-2B 1.00 0.45 0.03 5 0.06B-5 2.30 2.30 0.03 1 0.13
1.4.1.1.2.7 Suministro y colocación de grout epóxico E=25mm 3.17Cimentación B-4 4.80 2.40 0.03 11 3.17
1.4.1.1.2.8 Juntas de Contracción 160.80Estación Sopladores N° 1
23.20 1.00 1.00 2 46.402.70 1.00 1.00 4 10.80
Estación Sopladores N° 2
23.20 1.00 1.00 2 46.402.70 1.00 1.00 4 10.80
Estación Sopladores N° 3
17.80 1.00 1.00 2 35.602.70 1.00 1.00 4 10.80
1.4.1.1.2.9 Juntas de Expansión 318.90Estación Sopladores N° 1
14.40 1.00 1.00 4 57.6014.20 1.00 1.00 2 28.409.20 1.00 1.00 1 9.20
10.00 1.00 1.00 1 10.005.90 1.00 1.00 1 5.90
Estación Sopladores N° 2
14.40 1.00 1.00 4 57.6014.20 1.00 1.00 2 28.409.20 1.00 1.00 1 9.20
10.00 1.00 1.00 1 10.005.90 1.00 1.00 1 5.90
Estación Sopladores N° 3
14.40 1.00 1.00 3 43.2014.20 1.00 1.00 2 28.409.20 1.00 1.00 1 9.20
10.00 1.00 1.00 1 10.005.90 1.00 1.00 1 5.90
1.5 SISTEMA DE MANEJO DE MATERIALES1.5.1 EQUIPOS MECÁNICOS1.5.1.1 FAJA TRANSPORTADORA CV-007A
1.5.1.1.1 CIVIL1.5.1.1.1.2 Excavación local en terreno natural o suelto para estructuras 604.51
ZC1-A 1.55 2.35 0.95 2 6.92ZC1 4.25 5.56 1.60 1 37.81ZC2 2.95 4.33 1.30 3 49.82ZC3 2.95 4.41 1.10 3 42.93ZC4 8.01 6.20 1.15 1 57.11ZC5 3.15 5.08 1.00 3 48.01ZC6 3.15 5.45 1.00 2 34.34ZC7 1.65 1.65 0.90 1 2.45ZC8 4.25 3.65 1.00 2 31.03ZC9 14.35 10.45 1.45 1 217.44ZC14 8.85 8.25 1.05 1 76.66
1.5.1.1.1.3 Demolición de estructuras existentes 9.00Durmientes 1.20 0.30 0.25 100 9.00
1.5.1.1.1.5Relleno y compactación masivo material seleccionado para mejoramiento de
suelo 9.001.20 0.30 0.25 100 9.00
1.5.1.1.1.6 Relleno para estructuras con material de préstamo 1377.42Plataforma de traspaso CV-007A - CV008 19.70 15.20 4.60 1 1377.42
1.5.1.1.1.8 Superficie de rodadura, E=200mm en accesos y plataformas 60.30Camino de Acceso CV-007A 33.50 9.00 0.20 1 60.30
1.5.1.1.2 CONCRETO1.5.1.1.2.1 Concreto f'c= 100 kg/cm2 para solados 21.12
ZC1-A 1.10 1.90 0.05 2 0.21ZC1 3.80 5.11 0.05 1 0.97ZC2 2.50 3.88 0.05 3 1.46ZC3 2.50 3.96 0.05 3 1.49ZC4 7.56 5.75 0.05 1 2.17ZC5 2.70 4.63 0.05 3 1.88ZC6 2.70 5.00 0.05 2 1.35ZC7 1.20 1.20 0.05 1 0.07ZC8 3.80 3.20 0.05 2 1.22ZC9 13.90 10.00 0.05 1 6.95
0.60 2.80 0.05 1 0.08ZC14 8.40 7.80 0.05 1 3.28
1.5.1.1.2.2Concreto f'c= 280 kg/cm2 para cimentaciones de fajas transportadoras y
plataformas 318.19Z1 1.83 0.40 0.20 30 4.39Z2 1.83 0.40 0.20 16 2.34ZC1-A 1.10 1.90 0.30 2 1.25
0.25 0.35 0.80 4 0.28ZC1 3.80 5.11 0.50 1 9.71
0.72 0.50 1.35 2 0.97ZC2 2.50 3.88 0.50 3 14.55
0.72 0.50 1.15 6 2.48ZC3 2.50 3.96 0.50 3 14.85
0.72 0.50 0.95 6 2.05ZC4 7.56 5.75 0.80 1 34.78
0.50 0.50 0.70 4 0.70ZC5 2.70 4.63 0.50 3 18.75
0.50 0.50 0.70 6 1.05ZC6 2.70 5.00 0.50 2 13.50
0.77 0.50 0.70 4 1.08ZC7 1.20 1.20 0.40 1 0.58
0.40 0.40 0.70 4 0.45ZC8 3.80 3.20 0.40 2 9.73
0.50 0.40 0.70 4 0.56ZC9 13.90 10.00 1.00 1 139.00
0.60 2.80 1.00 1 1.68
23 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
0.70 0.70 0.70 4 1.370.40 0.40 0.70 4 0.45
ZC14 8.40 7.80 0.60 1 39.310.70 0.70 0.80 4 1.570.40 0.40 0.80 2 0.261.05 0.60 0.80 1 0.50
1.5.1.1.2.3 Acero de Refuerzo fy=4200 Kg/cm2 22521.78Z1 1/2" 120 2 237.6 249.48
3/8" 210 1.2 141.1 148.18Z2 1/2" 64 2 126.7 133.06
3/8" 112 1.2 75.26 79.03ZC1-A 5/8" 40 1.45 89.9 94.40
5/8" 24 2.25 83.7 87.895/8" 32 1.5 74.4 78.123/8" 28 1.2 18.82 19.76
ZC1 5/8" 42 4.4 286.4 300.765/8" 32 5.7 282.7 296.863/4" 20 1.9 85.12 89.383/8" 24 1.6 21.5 22.583/8" 12 0.9 6.048 6.35
ZC2 5/8" 96 3.1 461.3 484.345/8" 66 4.5 460.4 483.373/4" 60 2.2 295.7 310.463/8" 68 1.6 60.93 63.973/8" 32 0.9 16.13 16.93
ZC3 5/8" 96 3.1 461.3 484.345/8" 66 4.7 480.8 504.853/4" 60 2.1 282.2 296.353/8" 62 1.6 55.55 58.333/8" 30 0.9 15.12 15.88
ZC4 1" 34 8.8 1191 1250.361" 46 7 1282 1345.64
3/8" 29 8 129.9 136.423/8" 40 5.75 128.8 135.243/4" 32 1.9 136.2 143.003/8" 40 2 44.8 47.043/8" 24 1.6 21.5 22.58
ZC5 5/8" 72 3.3 368.3 386.695/8" 42 5.2 338.5 355.453/4" 72 3.3 532.2 558.843/4" 42 5.2 489.2 513.683/4" 48 1.5 161.3 169.343/8" 27 2 30.24 31.753/8" 21 1.6 18.82 19.76
ZC6 5/8" 80 3.3 409.2 429.665/8" 42 5.6 364.6 382.793/4" 80 3.3 591.4 620.933/4" 42 5.2 489.2 513.683/4" 40 1.5 134.4 141.123/8" 18 2.6 26.21 27.523/8" 14 2.2 17.25 18.11
ZC7 1" 16 1.7 108.3 113.675/8" 4 1.5 9.3 9.773/8" 7 1.6 6.272 6.59
ZC8 5/8" 32 4.6 228.2 239.575/8" 40 4 248 260.403/4" 32 4.6 329.7 346.213/4" 40 4 358.4 376.323/4" 12 1.5 40.32 42.343/8" 18 1.8 18.14 19.053/8" 14 0.7 5.488 5.76
ZC9 5/8" 140 11.8 2561 2688.635/8" 100 15.7 2434 2555.183/8" 140 10 784 823.203/8" 100 13.9 778.4 817.323/4" 32 2.3 164.9 173.113/8" 48 2.8 75.26 79.035/8" 16 2.4 59.52 62.503/8" 42 1.6 37.63 39.51
ZC14 3/4" 32 9.4 673.8 707.483/4" 34 8.8 670.2 703.723/8" 40 8.4 188.2 197.573/8" 42 7.8 183.5 192.633/4" 32 2 143.4 150.533/8" 44 2.8 68.99 72.443/8" 28 2.2 34.5 36.225/8" 8 2.4 29.76 31.253/8" 20 1.6 17.92 18.823/4" 12 2 53.76 56.453/8" 44 3.2 78.85 82.793/8" 28 2.4 37.63 39.51
1.5.1.1.2.4 Suministro y colocación de pernos de anclaje ASTM A36 N° 856.51Z1 T2 - 204 120 3/4" 4 0.36 387.1 415.87Z2 T2 - 204 64 3/4" 4 0.36 206.4 221.80ZC1-A T2 - 204 4 1" 4 0.5 31.84 32.80ZC1 T2 - 204 2 1" 4 0.5 15.92 16.40ZC2 T2 - 204 6 1" 4 0.5 47.76 49.20ZC3 T2 - 204 6 1 3/8" 4 0.55 1.44ZC4 T2 - 204 4 1" 4 0.5 31.84 32.80ZC5 T2 - 204 6 1" 4 0.5 47.76 49.20ZC6 T2 - 204 4 1 3/8" 8 0.55 0.96ZC7 T2 - 204 4 5/8" 4 0.3 7.44 8.40ZC8 T2 - 204 4 5/8" 4 0.38 9.424 10.38ZC9 T2 - 204 4 5/8" 4 0.3 7.44 8.40
T2 - 204 4 1 3/8" 4 0.72 0.96ZC14 T2 - 204 2 3/4" 4 0.36 6.451 6.93
T2 - 204 4 1 3/8" 2 0.55 0.96
1.5.1.1.2.5 Suministro y colocación de grout cementicio E=25mm 0.60Z1 0.30 0.30 0.03 60 0.14Z2 0.30 0.30 0.03 32 0.07ZC1-A 0.25 0.35 0.03 4 0.01ZC1 0.72 0.50 0.03 2 0.02ZC2 0.72 0.50 0.03 6 0.05ZC3 0.72 0.50 0.03 6 0.05ZC4 0.50 0.50 0.03 4 0.03ZC5 0.50 0.50 0.03 6 0.04ZC6 0.77 0.50 0.03 4 0.04ZC7 0.40 0.40 0.03 4 0.02ZC8 0.50 0.40 0.03 4 0.02ZC9 0.70 0.70 0.03 4 0.05
0.40 0.40 0.03 4 0.02ZC14 0.70 0.70 0.03 4 0.05
0.40 0.40 0.03 2 0.01
1.5.1.2 FAJA TRANSPORTADORA CV-008
24 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
1.5.1.2.1 CIVIL1.5.1.2.1.3 Excavación local en terreno natural o suelto para estructuras 229.68
ZC1-A 1.55 2.35 0.95 4 13.84ZC10 3.35 4.83 1.55 1 25.08ZC11 3.35 5.99 1.35 3 81.27ZC12 6.20 5.05 1.00 1 31.31ZC13 6.05 9.45 1.20 1 68.61Cola 10.35 1.00 0.93 1 9.57
1.5.1.2.1.4 Excavación local en roca para fines de cimentación 41.11ZC12 6.20 5.05 0.40 1 12.52ZC13 6.05 9.45 0.50 1 28.59
1.5.1.2.1.5Relleno y compactación masivo con material seleccionado, al 95% del
Próctor modificado. 47.45ZC1-A 1.55 2.35 0.25 4 3.64ZC10 3.35 4.83 0.25 1 4.05ZC11 3.35 5.99 0.25 3 15.05ZC12 6.20 5.05 0.25 1 7.83ZC13 6.05 9.45 0.25 1 14.29Cola 10.35 1.00 0.25 1 2.59
1.5.1.2.1.8 Relleno para estructuras con material de préstamo 3515.23Camino minero - Culvert 113.03 9.00 5.25 1 5340.67
113.03 16.15 -1.00 1 -1825.43
1.5.1.2.1.10 Superficie de rodadura, E=200mm en accesos y plataformas 2158.94Camino de acceso vehicular 90.00 7.00 0.20 1 126.00
118.50 7.00 0.20 1 165.90Acceso Faja CV008 550.00 12.46 0.20 1 1370.60Camino de servicio 137.90 9.00 0.20 1 248.22Camino de Acceso CV-007A 137.90 9.00 0.20 1 248.22
1.5.1.2.1.11 Superficie de rodadura, E=300mm en camino minero 2655.00Camino de acceso minero 295.00 30.00 0.30 1 2655.00
1.5.1.2.1.12Suministro y colocación de estructura metálica Super Span Multiplate-MP152
- Arco 35A5.49 113.38Camino de acceso minero 113.38 1.00 1.00 1 113.38
1.5.1.2.1.14Instalación de geocompuesto para drenaje tipo MacDrain de Maccaferri o
similar 514.75Camino de acceso minero 113.38 2.27 1.00 2 514.75
1.5.1.2.1.15Instalación de insertos Polilock en estructuras de concreto, bases de
equipos, losas y recubrimiento de tuberías 226.76Camino de acceso minero 113.38 1.00 1.00 2 226.76
1.5.1.2..16 Tubería de drenaje PVC Ø6" C/ agujeros 3/16"@ 75mm 226.00Camino minero - Culvert 113.00 1.00 1.00 2 226.00
1.5.1.2.2 CONCRETO1.5.1.2.2.1 Concreto f'c= 100 kg/cm2 para solados 25.04
Losa1 - Polea Motriz 5.02 8.98 0.05 1 2.25Losa Contrapeso 5.70 3.90 0.05 1 1.11ZC1-A 1.10 1.90 0.05 4 0.42ZC10 2.90 4.38 0.05 1 0.64ZC11 2.90 5.54 0.05 3 2.41ZC12 5.75 4.60 0.05 1 1.32ZC13 5.60 9.00 0.05 1 2.52Cola 9.00 1.00 0.05 1 0.45Camino Minero - Culvert 113.03 1.60 0.05 1 9.04
113.03 0.40 0.05 1 2.26113.03 0.25 0.05 1 1.41
1.30 0.25 0.05 74 1.20
1.5.1.2.2.2Concreto f'c= 280 kg/cm2 para cimentaciones de fajas transportadoras y
plataformas 134.02Z2A 2.00 0.40 0.30 8 1.92Z2B 2.00 0.40 0.30 154 36.96P3B 0.50 0.50 0.30 4 0.30ZC1-A 1.10 1.90 0.30 4 2.51ZC10 2.90 4.38 0.45 1 5.72
0.50 0.72 1.25 2 0.90ZC11 2.90 5.54 0.50 3 24.10
0.72 0.77 1.00 6 3.33ZC12 5.75 4.60 0.60 1 15.87
0.40 0.40 0.90 6 0.860.80 0.52 0.90 2 0.75
ZC13 5.60 9.00 0.60 1 30.240.85 0.55 1.20 4 2.24
Cola 9.00 1.00 0.93 1 8.33
1.5.1.2.2.3Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, canaletas
eléctricas y losas de piso 19.58Losa1 - Polea Motriz 5.02 8.98 0.15 1 6.76
7.30 1.00 0.15 -1 -1.100.50 0.50 0.15 -4 -0.15
28.00 0.25 0.25 1 1.75Sardinel 1 28.00 0.20 0.45 1 2.52Losa 2 - Polea Motriz 7.30 1.00 0.50 1 3.65Losa Contrapeso 5.70 3.90 0.15 1 3.33
44.00 0.23 0.15 1 1.49Sardinel 2 44.00 0.20 0.15 1 1.32
1.5.1.2.2.4 Concreto f'c= 280 kg/cm2 para cimentaciones del culvert 392.64Camino Minero - Culvert 113.03 1.60 0.60 2 217.02
113.03 4.04 0.20 1 91.33113.03 0.25 1.30 2 73.47
1.30 0.25 0.45 74 10.82
1.5.1.2.2.5 Acero de Refuerzo fy=4200 Kg/cm2 73806.56Z2A 1/2" 32 2.2 69.7 73.18
3/8" 64 1.4 50.18 52.68Z2B 1/2" 616 2.2 1342 1408.73
3/8" 1232 1.4 965.9 1014.18Losa1 - Polea Motriz 3/8" 46 5.3 136.5 143.35
3/8" 26 9.3 135.4 142.18Sardinel 1 3/8" 140 1.8 141.1 148.18
3/8" 140 0.8 62.72 65.863/8" 10 28 156.8 164.64
P3B 3/4" 32 2.1 150.5 158.053/8" 44 2 49.28 51.743/8" 36 1.6 32.26 33.87
ZC1-A 5/8" 80 1.45 179.8 188.795/8" 48 2.25 167.4 175.775/8" 32 1.5 74.4 78.123/8" 28 1.2 18.82 19.76
ZC10 5/8" 32 5.1 253 265.61
25 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
5/8" 44 3.7 252.3 264.963/4" 20 1.8 80.64 84.673/8" 18 2 20.16 21.173/8" 14 2 15.68 16.463/8" 14 1 7.84 8.23
ZC11 3/4" 27 6.3 381 400.083/4" 48 3.7 397.8 417.723/4" 60 6.3 846.7 889.063/4" 111 3.7 920 965.973/4" 60 1.6 215 225.793/8" 42 2 47.04 49.393/8" 36 2 40.32 42.343/8" 36 1 20.16 21.17
Losa Contrapeso 3/8" 20 6.3 70.56 74.093/8" 29 4.5 73.08 76.73
ZC12 3/4" 38 6.5 553.3 580.943/4" 48 5.4 580.6 609.645/8" 24 1.9 70.68 74.213/8" 54 1.6 48.38 50.803/4" 20 2 89.6 94.083/8" 84 2 94.08 98.783/8" 72 2 80.64 84.67
ZC13 1" 26 6.4 662.3 695.391" 17 9.8 663.1 696.221" 31 6.4 789.6 829.111" 19 9.8 741.1 778.13
3/4" 40 2.4 215 225.793/8" 13 2.8 20.38 21.403/8" 13 2.2 16.02 16.82
Cola 5/8" 100 5 775 813.755/8" 50 4.3 333.3 349.913/4" 8 1.7 30.46 31.993/8" 8 2.8 12.54 13.173/8" 8 2 8.96 9.41
Camino Minero - Culvert 5/8" 2268 2.1 7382 7751.465/8" 1134 1.25 2197 2306.983/4" 567 3.75 4763 5000.943/4" 567 4.04 5131 5387.685/8" 567 4.04 3551 3728.083/4" 1134 3.05 7747 8134.861/2" 56 124.6 6909 7254.965/8" 40 124.6 7727 8113.413/4" 42 124.6 11725 12311.45
1.5.1.2.2.6 Suministro y colocación de pernos de anclaje ASTM A36 N° 539.18Z2A T2 - 204 8 5/8" 4 0.36 17.86 19.78Z2B T2 - 204 154 5/8" 4 0.36 343.7 380.69P3B T2 - 204 4 5/8" 4 0.36 8.928 9.89ZC1-A T2 - 204 8 1" 4 0.5 63.68 65.60ZC10 T2 - 204 2 1" 4 0.5 15.92 16.40ZC11 T2 - 204 6 1 3/8" 8 0.55 1.44ZC12 T2 - 204 4 1" 4 0.5 31.84 32.80
T2 - 204 2 3/4" 2 0.36 3.226 3.71T2 - 204 2 5/8" 8 0.3 7.44 7.92
ZC13 T2 - 204 4 1 3/8" 4 0.72 0.96
1.5.1.2.2.7 Suministro y colocación de grout cementicio E=25mm 0.86Z2A 0.35 0.35 0.03 8 0.02Z2B 0.35 0.35 0.03 154 0.47P3B 0.35 0.35 0.03 4 0.01ZC1 0.35 0.35 0.03 2 0.01ZC2 0.40 0.40 0.03 6 0.02ZC3 0.40 0.40 0.03 6 0.02ZC4 0.40 0.40 0.03 4 0.02ZC5 0.40 0.40 0.03 6 0.02ZC6 0.40 0.40 0.03 4 0.02ZC7 0.40 0.40 0.03 4 0.02ZC8 0.40 0.40 0.03 4 0.02ZC9 0.40 0.40 0.03 8 0.03ZC10 0.50 0.72 0.03 2 0.02ZC11 0.72 0.77 0.03 6 0.08ZC12 0.40 0.40 0.03 6 0.02
0.80 0.52 0.03 2 0.02ZC13 0.40 0.40 0.03 4 0.02ZC14 0.40 0.40 0.03 4 0.02
1.5.1.2.2.8 Juntas de Contracción 524.24Camino minero - Culvert 22.58 1.00 1.00 23 519.34
4.90 1.00 1.00 1 4.90
1.5.1.2.2.9 Juntas de Expansión 135.902.00 1.00 1.00 4 8.001.60 1.00 1.00 6 9.601.80 1.00 1.00 1 1.801.80 1.00 1.00 2 3.60
Camino minero - Culvert 22.58 1.00 1.00 5 112.90
1.5.1.2.2.10 Sello de agua con bulbo intermedio 6" 112.90Camino minero - Culvert 22.58 1.00 1.00 5 112.90
1.5.1.4 SUBESTACION ELECTRICA DE TRASPASO
1.5.1.4.1 CIVIL1.5.1.4.1.1 Excavación masiva en terreno natural o suelto para explanaciones 114.73
Plataformado General 35.30 13.00 0.25 1 114.73
1.5.1.4.1.2 Excavación local en terreno natural o suelto para estructuras 150.01TR-3 3.90 3.80 0.90 1 13.34Canaleta 1 3.60 1.30 1.45 1 6.79Canaleta 2 7.55 1.40 1.45 1 15.33B-7 1.80 1.80 2.55 9 74.36B-8 1.20 1.20 1.25 2 3.60B-9 2.10 1.20 1.25 1 3.15B-10 1.20 1.20 0.20 2 0.58B-2 2.50 2.50 0.40 1 2.50Muro Cortafuego B-6 2.50 5.60 1.55 1 21.70Muro Cortafuego B-5 1.00 5.60 1.55 1 8.68
1.5.1.4.1.3 Relleno con material préstamo para estructuras 78.79TR-3 3.90 3.80 0.50 1 7.41Canaleta 1 3.60 1.30 0.80 1 3.74Canaleta 2 7.55 1.40 0.80 1 8.46B-7 1.80 1.80 1.30 9 37.91B-8 1.20 1.20 0.75 2 2.16B-9 2.10 1.20 0.75 1 1.89B-10 1.20 1.20 0.10 2 0.29B-2 2.50 2.50 0.20 1 1.25Muro Cortafuego B-6 2.50 5.60 0.80 1 11.20
26 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
Muro Cortafuego B-5 1.00 5.60 0.80 1 4.48
1.3.1.1.1.5 Superficie de rodadura, E=200mm 60.00Acceso Vehicular 4.00 75.00 0.20 1 60.00
1.5.1.4.2 CONCRETO1.5.1.4.2.1 Concreto f'c= 100 kg/cm2 para solados 5.67
Losa para celdas e interruptor B-3 3.00 6.65 0.05 1 1.00TR-3 3.90 3.80 0.05 1 0.74Canaleta 1 3.60 1.30 0.05 1 0.23Canaleta 2 7.55 1.40 0.05 1 0.53B-7 1.80 1.80 0.05 9 1.46B-8 1.20 1.20 0.05 2 0.14B-9 2.10 1.20 0.05 1 0.13B-10 1.20 1.20 0.05 2 0.14B-2 2.50 2.50 0.05 1 0.31Muro Cortafuego B-6 2.50 5.60 0.05 1 0.70Muro Cortafuego B-5 1.00 5.60 0.05 1 0.28
1.5.1.4.2.2Concreto f'c= 210 kg/cm2 para canaletas de drenaje, cimentaciones de
cercos, banco de ductos y buzones 9.06Canaleta 1 3.60 1.30 0.15 1 0.70
3.60 1.40 0.30 1 1.511.00 1.40 0.15 2 0.42
Canaleta 2 7.55 1.40 0.15 1 1.597.55 1.40 0.30 1 3.171.10 1.40 0.15 5 1.16
Tapa Canaleta 1.00 0.33 0.08 21 0.51
1.5.1.4.2.3Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, losa de piso y
pedestales, según lo indicado en planos 58.85TR-3 3.90 3.80 0.40 1 5.93
2.30 1.80 1.10 1 4.553.90 0.20 1.00 2 1.563.40 0.20 1.00 2 1.36
Losa para celdas e interruptor B-3 3.00 3.85 0.20 1 2.3110.40 0.25 0.20 1 0.521.70 1.50 0.20 1 0.511.30 0.90 0.20 1 0.234.20 0.25 0.20 1 0.21
B-7 1.80 1.80 0.40 9 11.660.40 0.40 2.45 9 3.53
B-8 1.20 1.20 0.40 2 1.150.35 0.35 1.10 2 0.27
B-9 2.10 1.20 0.40 1 1.010.35 0.35 1.10 2 0.27
B-10 1.20 1.20 0.50 2 1.44B-4 1.40 1.40 0.15 1 0.29B-2 2.50 2.50 0.20 1 1.25
1.00 1.40 0.40 1 0.5610.40 0.20 0.35 1 0.73
Muro Cortafuego B-6 2.50 5.60 0.40 1 5.600.30 5.60 5.35 1 8.99
Muro Cortafuego B-5 1.00 5.60 0.30 1 1.680.15 5.60 3.85 1 3.23
1.5.1.4.2.4 Acero de Refuerzo fy=4200 Kg/cm2 5713.49TR-3 1/2" 16 4.3 68.11 71.52
1/2" 16 4.2 66.53 69.851/2" 14 3.5 48.51 50.941/2" 10 1.8 17.82 18.711/2" 8 2.8 22.18 23.281/2" 16 1.7 26.93 28.271/2" 16 1.7 26.93 28.271/2" 3 11 32.67 34.301/2" 33 1.8 58.81 61.751/2" 64 1.5 95.04 99.791/2" 64 1.5 95.04 99.791/2" 8 16.1 127.5 133.89
Losa para celdas e interruptor B-3 1/2" 40 3.5 138.6 145.531/2" 32 4.3 136.2 143.041/2" 56 1.1 60.98 64.031/2" 8 3.05 24.16 25.361/2" 16 2.1 33.26 34.931/2" 8 1.7 13.46 14.141/2" 14 1.1 15.25 16.01
Canaleta 1 1/2" 7 3.6 24.95 26.201/2" 18 1.6 28.51 29.941/2" 14 3.6 49.9 52.391/2" 36 1.7 60.59 63.62
Canaleta 2 1/2" 7 7.55 52.32 54.941/2" 38 1.7 63.95 67.151/2" 14 7.55 104.6 109.881/2" 76 1.7 127.9 134.30
B-7 5/8" 54 2.5 209.3 219.715/8" 54 2.5 209.3 219.715/8" 54 2.5 209.3 219.715/8" 54 2.5 209.3 219.715/8" 72 3.25 362.7 380.843/8" 180 1.6 161.3 169.343/8" 153 1.2 102.8 107.96
B-8 5/8" 8 1.9 23.56 24.745/8" 8 1.9 23.56 24.745/8" 8 1.9 23.56 24.745/8" 8 1.9 23.56 24.745/8" 16 1.9 47.12 49.483/8" 18 1.4 14.11 14.823/8" 12 1.05 7.056 7.41
B-9 5/8" 4 2.8 17.36 18.235/8" 7 2.8 30.38 31.905/8" 4 1.9 11.78 12.375/8" 7 1.9 20.62 21.655/8" 16 1.9 47.12 49.483/8" 18 1.4 14.11 14.823/8" 12 1.05 7.056 7.41
B-4 1/2" 10 1.7 16.83 17.67B-2 1/2" 32 2.8 88.7 93.14
1/2" 26 3.4 87.52 91.891/2" 58 0.65 37.32 39.191/2" 8 2.4 19.01 19.961/2" 6 2.8 16.63 17.46
Muro Cortafuego B-6 5/8" 46 3.1 221 232.085/8" 22 6.2 211.4 221.995/8" 46 7.5 534.8 561.495/8" 44 6.2 422.8 443.98
Muro Cortafuego B-5 1/2" 29 4.3 123.5 129.631/2" 20 5.8 114.8 120.581/2" 28 1.3 36.04 37.841/2" 8 6 47.52 49.90
27 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
Tapa Canaleta 3/8" 105 1 58.8 61.741/4" 105 0.35 9.188 9.65
1.5.1.4.2.5 Suministro y colocación de pernos de anclaje ASTM A36 N° 29.40P-1 T2 - 305 10 5/8" 4 0.3 18.6 21.00P-2 T2 - 305 4 5/8" 4 0.3 7.44 8.40
1.5.1.4.2.6 Suministro y colocación de grout cementicio E=25mm 0.05B-7 0.40 0.40 0.03 9 0.04B-8 0.35 0.35 0.03 2 0.01B-9 0.35 0.35 0.03 2 0.01
1.5.1.4.2.7 Juntas de Construcción 5.705.70 1.00 1.00 1 5.70
1.5.1.4.2.8 Juntas de Expansión 22.705.70 1.00 1.00 1 5.703.40 1.00 1.00 5 17.00
1.5.1.5 SUBESTACION ELECTRICA DE DISTRIBUCION DE MATERIALES
1.5.1.5.1 CIVIL1.5.1.5.1.1 Excavación masiva en terreno natural o suelto para explanaciones 122.40
Plataformado General 25.50 19.20 0.25 1 122.40
1.5.1.5.1.2 Excavación local en terreno natural o suelto para estructuras 196.34TR-7.5 5.15 4.25 0.90 1 19.70Canaleta 1 3.85 1.75 1.45 1 9.77Canaletas 2 12.15 1.75 1.45 1 30.83Canaletas 3 13.10 1.35 1.15 1 20.34Z-1 1.55 1.55 1.2 3 8.65Z-2 1.55 1.55 1.4 7 23.54Muro Cortafuego 2.95 7.45 1.90 2 83.51
1.5.1.5.1.3 Relleno con material préstamo para estructuras 95.72TR-7.5 5.15 4.25 0.45 1 9.85Canaleta 1 3.85 1.75 0.70 1 4.72Canaletas 2 12.15 1.75 0.70 1 14.88Canaletas 3 13.10 1.35 0.60 1 10.61Z-1 1.55 1.55 0.6 3 4.32Z-2 1.55 1.55 0.7 7 11.77Muro Cortafuego 2.95 7.45 0.90 2 39.56
1.5.1.5.1.5 Superficie de rodadura, E=200mm 80.00Acceso Vehicular 4.00 100.00 0.20 1 80.00
1.5.1.5.2 CONCRETO1.5.1.5.2.1 Concreto f'c= 100 kg/cm2 para solados 9.60
Losa para celdas e interruptor B-5 2.70 4.35 0.05 1 0.59Canaleta 1 5.70 0.90 0.05 1 0.26
1.59 0.90 0.05 1 0.074.50 0.90 0.05 1 0.206.95 1.40 0.05 1 0.495.66 1.40 0.05 1 0.40
Canaleta 1 3.40 1.30 0.05 1 0.22Losita 1 0.95 1.15 0.05 1 0.05Losita 2 2.45 0.45 0.05 1 0.06Losa de Piso 7.45 13.20 0.05 1 4.92Z-1 1.1 1.1 0.05 3 0.18Z-2 1.1 1.1 0.05 7 0.42Muro Cortafuego 2.50 7.00 0.05 2 1.75
1.5.1.5.2.2Concreto f'c= 210 kg/cm2 para canaletas de drenaje, cimentaciones de
cercos, banco de ductos y buzones 12.45Canaleta 1 3.40 1.30 0.15 1 0.66
L 3.40 1.40 0.30 1 1.43tap 1.00 1.40 0.15 2 0.42
Canaletas 2 11.70 1.30 0.15 1 2.28L 3.40 1.40 0.30 1 1.43
tap 1.00 1.40 0.15 1 0.21Canaletas 3 12.65 0.90 0.15 1 1.71
L 12.65 1.00 0.30 1 3.80tap 0.60 1.00 0.15 2 0.18
Tapa Canaleta 1.00 0.33 0.08 14 0.34
1.5.1.5.2.3Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, losa de piso y
pedestales, según lo indicado en planos 81.33TR-7.5 4.70 3.80 0.40 1 7.14
3.10 2.20 1.10 1 7.504.70 0.20 1.00 2 1.883.40 0.20 1.00 2 1.36
Losa para celdas e interruptor B-5 2.70 4.35 0.20 1 2.3513.20 0.25 0.20 1 0.66
Losita 1 0.95 1.15 0.20 1 0.221.80 0.25 0.20 1 0.09
Losita 2 2.45 0.45 0.20 1 0.22Losa de Piso 7.45 13.20 0.20 1 19.67
23.80 1.00 0.20 -1 -4.76Sardinel 1 40.00 0.15 0.15 1 0.90Z-1 1.1 1.1 0.4 3 1.45
0.5 0.45 1.1 3 0.74Z-2 1.1 1.1 0.4 7 3.39
0.5 0.45 1.3 7 2.05Muro Cortafuego 2.50 7.00 0.40 2 14.00
0.30 7.00 5.35 2 22.47
1.5.1.5.2.4 Acero de Refuerzo fy=4200 Kg/cm2 9884.41TR-7.5 1/2" 16 5.1 80.78 84.82
1/2" 19 4.2 79 82.951/2" 14 3.5 48.51 50.941/2" 10 2.6 25.74 27.031/2" 10 3.5 34.65 36.381/2" 10 2.6 25.74 27.031/2" 32 1.8 57.02 59.881/2" 38 1.8 67.72 71.101/2" 32 1.5 47.52 49.901/2" 38 1.5 56.43 59.251/2" 32 1.5 47.52 49.901/2" 38 1.5 56.43 59.251/2" 20 1.9 37.62 39.501/2" 28 1.9 52.67 55.301/2" 6 3.8 22.57 23.701/2" 6 4.7 27.92 29.311/2" 24 5.1 121.2 127.231/2" 24 4.2 99.79 104.78
Losa para celdas e interruptor B-5 1/2" 14 4.6 63.76 66.941/2" 14 4.8 66.53 69.851/2" 22 3 65.34 68.611/2" 22 3.2 69.7 73.18
28 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
1/2" 14 1.1 15.25 16.011/2" 22 1.1 23.96 25.16
Canaleta 1 1/2" 7 3.4 23.56 24.741/2" 17 1.6 26.93 28.271/2" 14 3.4 47.12 49.481/2" 34 1.7 57.22 60.08
Losa de Piso 1/2" 132 7.95 1039 1090.851/2" 76 13.7 1031 1082.331/2" 208 1.05 216.2 227.03
Sardinel 1 1/2" 208 0.65 133.8 140.54Canaletas 2 1/2" 7 11.7 81.08 85.14
1/2" 59 1.6 93.46 98.131/2" 14 11.7 162.2 170.271/2" 118 1.7 198.6 208.52
Canaletas 3 1/2" 5 12.65 62.62 65.751/2" 64 1.2 76.03 79.831/2" 10 12.65 125.2 131.501/2" 128 1.3 164.7 172.97
Z-1 5/8" 12 1.8 33.48 35.155/8" 12 1.8 33.48 35.155/8" 12 1.8 33.48 35.155/8" 12 1.8 33.48 35.151" 24 1.9 181.5 190.56
3/8" 27 1.9 28.73 30.163/8" 18 1.45 14.62 15.35
Z-2 5/8" 28 1.8 78.12 82.035/8" 28 1.8 78.12 82.035/8" 28 1.8 78.12 82.035/8" 28 1.8 78.12 82.031" 56 2.1 468 491.45
3/8" 77 1.9 81.93 86.023/8" 56 1.45 45.47 47.75
Muro Cortafuego 5/8" 116 3.1 557.4 585.255/8" 44 7.6 518.3 544.245/8" 116 7.5 1349 1415.935/8" 88 6.2 845.7 887.96
Tapa Canaleta 3/8" 70 1 39.2 41.161/4" 70 0.35 6.125 6.43
1.5.1.5.2.5 Suministro y colocación de pernos de anclaje ASTM A36 N° 34.66P-1 T2 - 302 10 3/4" 4 0.36 32.26 34.66
1.5.1.5.2.6 Suministro y colocación de grout cementicio E=25mm 2.25Z-1 0.5 0.45 1 3 0.68Z-2 0.5 0.45 1 7 1.58
1.5.1.4.2.7 Juntas de Contracción 38.6013.65 1.00 1.00 2 27.3011.30 1.00 1.00 1 11.30
1.5.1.4.2.8 Juntas de Expansión 51.0044.20 1.00 1.00 1 44.206.80 1.00 1.00 1 6.80
1.7 SUBESTACION ELECTRICA PRINCIPAL 22.9kV1.7.1 SUBESTACION ELECTRICA PRINCIPAL 22.9kV1.7.1.1 PATIO DE LLAVES
1.7.1.1.1 CIVIL1.7.1.1.1.1 Excavación masiva en terreno natural o suelto para explanaciones 141.74
Plataformado General 24.20 23.43 0.25 1 141.74
1.7.1.1.1.2 Excavación local en terreno natural o suelto para estructuras 395.90B-1 TR-40-50MV 10.80 7.00 3.50 1 264.60B-2 2.40 2.90 1.25 1 8.70B-3 1.40 7.40 1.25 2 25.90B-4 1.90 1.90 1.25 3 13.54ZC-1 4.40 5.40 3.50 1 83.16
1.7.1.1.1.3 Excavación local en roca para fines de cimentación 56.70B-1 TR-40-50MV 10.80 7.00 0.75 1 56.70
1.7.1.1.1.4 Relleno con material préstamo para estructuras 192.02B-1 TR-40-50MV 10.80 7.00 1.70 1 128.52B-2 2.40 2.90 0.60 1 4.18B-3 1.40 7.40 0.60 2 12.43B-4 1.90 1.90 0.60 3 6.50ZC-1 4.40 5.40 1.70 1 40.39
1.7.1.1.1.6 Superficie de rodadura, E=200mm 80.00Acceso Vehicular 4.00 100.00 0.20 1 80.00
1.7.1.1.2 CONCRETO1.7.1.1.2.1 Concreto f'c= 100 kg/cm2 para solados 8.43
TR-40-50MV 10.40 6.60 0.05 1 3.43B-2 2.00 2.50 0.05 1 0.25B-3 1.00 7.00 0.05 2 0.70B-4 1.50 1.50 0.05 3 0.34ZC-1 4.00 5.00 0.05 1 1.00B-5 1.00 1.00 0.05 1 0.05B-6 1.76 1.24 0.05 1 0.11B-7 2.80 3.75 0.05 1 0.53B-8 1.00 4.80 0.05 1 0.24B-9 3.00 2.77 0.05 1 0.41Canaleta 24.90 1.10 0.05 1 1.37
1.7.1.1.2.2 Concreto Ciclópeo f'c= 140 kg/cm2 + 30% Piedra Mediana 132.96TR-40-50MV 10.40 6.60 1.50 1 102.96ZC-1 4.00 5.00 1.50 1 30.00
1.7.1.1.2.3Concreto f'c= 210 kg/cm2 para canaletas de drenaje, cimentaciones de
cercos, banco de ductos y buzones 16.63
Canaleta 24.90 1.10 0.15 1 4.1124.90 1.35 0.30 1 10.08
Tapa Canaleta 1.00 0.33 0.08 100 2.44
1.7.1.1.2.4Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, losa de piso y
pedestales, según lo indicado en planos 152.71TR-40-50MV 10.40 6.60 0.70 1 48.05
49.20 0.20 1.60 1 15.748.00 4.20 1.60 1 53.76
B-2 2.00 2.50 0.40 1 2.000.30 0.30 1.10 4 0.40
B-3 1.00 7.00 0.40 2 5.600.30 0.30 1.10 6 0.59
29 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
B-4 1.50 1.50 0.40 3 2.700.90 0.90 1.10 3 2.67
ZC-1 4.00 5.00 0.60 1 12.001.60 0.80 1.10 2 2.82
B-5 1.00 1.00 0.20 1 0.203.40 0.15 0.25 1 0.13
B-6 1.76 1.24 0.2 1 0.445.4 0.15 0.25 1 0.20
B-7 2.80 3.75 0.20 1 2.1012.50 0.15 0.25 1 0.47
B-8 1.00 4.80 0.20 1 0.9611.00 0.15 0.25 1 0.41
B-9 3.00 2.77 0.20 1 1.6610.00 0.15 0.25 1 0.380.90 2.50 0.25 -1 -0.56
1.7.1.1.2.5 Acero de Refuerzo fy=4200 Kg/cm2 9738.17TR-40-50MV 5/8" 27 11.3 472.9 496.55
5/8" 42 7.5 488.3 512.661" 28 2.3 256.3 269.131" 68 2.3 622.5 653.60
5/8" 17 8.4 221.3 232.415/8" 32 4.6 228.2 239.575/8" 98 3.2 486.1 510.385/8" 6 24.4 226.9 238.271" 4 28.4 452.1 474.73
1/2" 266 2.6 684.7 718.923/8" 14 33 258.7 271.663/4" 8 5.2 93.18 97.84
B-2 5/8" 10 2.7 41.85 43.945/8" 8 2.7 33.48 35.155/8" 10 3.2 49.6 52.085/8" 8 3.2 39.68 41.665/8" 32 2 99.2 104.163/8" 36 1.2 24.19 25.403/8" 24 0.9 12.1 12.70
B-3 5/8" 56 1.7 147.6 154.945/8" 8 1.7 21.08 22.135/8" 56 7.7 668.4 701.785/8" 8 7.7 95.48 100.255/8" 48 2 148.8 156.243/8" 54 1.2 36.29 38.103/8" 36 0.9 18.14 19.05
B-4 1/2" 18 2.2 39.2 41.161/2" 18 2.2 39.2 41.161/2" 18 2.2 39.2 41.161/2" 18 2.2 39.2 41.165/8" 48 2.3 171.1 179.683/8" 27 3.6 54.43 57.153/8" 36 2.7 54.43 57.15
ZC-1 3/4" 20 5.1 228.5 239.903/4" 16 5.1 182.8 191.923/4" 20 6.1 273.3 286.943/4" 16 6.1 218.6 229.565/8" 36 2.2 122.8 128.903/8" 14 4.2 32.93 34.573/8" 8 4.2 18.82 19.763/8" 8 3.2 14.34 15.05
B-5 3/8" 8 1.4 6.272 6.593/8" 8 1.4 6.272 6.593/8" 12 1.1 7.392 7.76
B-6 3/8" 16 2.16 19.35 20.323/8" 10 1.64 9.184 9.643/8" 18 1.1 11.09 11.64
B-7 3/8" 24 3.2 43.01 45.163/8" 30 4.15 69.72 73.213/8" 42 1.1 25.87 27.17
B-8 3/8" 8 1.4 6.272 6.593/8" 40 5.2 116.5 122.303/8" 37 1.1 22.79 23.93
B-9 3/8" 19 3.4 36.18 37.983/8" 19 3.165 33.68 35.363/8" 31 1.1 19.1 20.05
Canaleta 1/2" 6 24.9 147.9 155.301/2" 115 1.5 170.8 179.311/2" 14 24.9 345.1 362.371/2" 230 1.75 398.5 418.40
Tapa Canaleta 3/8" 500 1 280 294.001/4" 500 0.35 43.75 45.94
1.7.1.1.2.6 Suministro y colocación de pernos de anclaje ASTM A36 N° 41.11P-1 T2 - 317 4 3/4" 4 0.36 12.9 13.86P-2 T2 - 317 3 3/4" 4 0.36 9.677 10.40P-3 T2 - 317 1 3/4" 4 0.36 3.226 3.47P-4 T2 - 318 2 3/4" 8 0.36 12.9 13.38
1.7.1.1.2.7 Suministro y colocación de grout cementicio E=25mm 0.15B-2 0.30 0.30 0.03 4 0.01B-3 0.30 0.30 0.03 6 0.01B-4 0.90 0.90 0.03 3 0.06ZC-1 1.60 0.80 0.03 2 0.06
1.7.1.2 SALA ELÉCTRICA
1.7.1.2.1 CIVIL1.7.1.2.1.1 Excavación masiva en terreno natural o suelto para explanaciones 252.87
Plataformado General 41.79 24.20 0.25 1 252.87
1.7.1.2.1.2 Excavación local en terreno natural o suelto para estructuras 275.30B-10 4.20 16.18 3.10 1 210.66B-11 2.55 2.55 2.30 3 44.87B-12 1.80 1.45 0.40 3 3.13B-13 2.40 2.40 2.30 1 13.25B-14 1.80 1.45 0.40 1 1.04B-15 1.80 1.45 0.60 1 1.57B-9 1.65 0.95 0.50 1 0.78
1.5.1.2.1.3 Excavación local en roca para fines de cimentación 16.99B-10 4.20 16.18 0.25 1 16.99
1.7.1.2.1.4 Relleno con material préstamo para estructuras 141.05B-10 4.20 16.18 1.60 1 108.73B-11 2.55 2.55 1.15 3 22.43B-12 1.80 1.45 0.20 3 1.57B-13 2.40 2.40 1.15 1 6.62B-14 1.80 1.45 0.20 1 0.52
30 of 30
ELEMENTO
POS. DENOMINACION LONG. ANCHO ALTURA DIAM. CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 1 1/4"SUB
TOTAL
ACERO DE REFUERZO
SUBTOTAL
DIMENSIONESCANT.
CONCRETODIMENSIONES DIÁMETRO PESO
KgVOLUMEN
m3
15315-2600-42EL-001
Revision Sheet
1
BILL OF MATERIALCONCRETE STRUCTURES
MI09H060-260-3-LM-001
PAD 4B - PHASE 1 DETAIL ENGINEERING UPDATE
APENDICE A / APPENDIX ASUSTENTO DE METRADOS / SUSTENTATION OF QUANTITIES
B-15 1.80 1.45 0.30 1 0.78B-9 1.65 0.95 0.25 1 0.39
1.7.1.2.1.6 Superficie de rodadura, E=200mm 80.00Acceso Vehicular 4.00 100.00 0.20 1 80.00
1.7.1.2.2 CONCRETO1.7.1.2.2.1 Concreto f'c= 100 kg/cm2 para solados 48.03
B-10 3.75 15.73 0.60 1 35.39B-11 2.10 2.10 0.40 3 5.29B-12 1.35 1.35 0.40 3 2.19B-13 1.95 1.95 0.40 1 1.52B-14 1.35 1.35 0.40 1 0.73B-15 1.35 2.70 0.60 1 2.19B-9 1.20 1.20 0.50 1 0.72
1.7.1.2.2.2Concreto f'c= 280 kg/cm2 para cimentaciones de equipos, losa de piso y
pedestales, según lo indicado en planos 83.113.75 15.73 0.60 1 35.390.40 0.40 2.40 4 1.54
11.98 0.35 4.40 1 18.4511.98 0.30 2.00 1 7.1911.98 0.25 1.60 1 4.79
B-11 2.10 2.10 0.40 3 5.290.40 0.40 2.58 3 1.24
B-12 1.35 1.35 0.40 3 2.190.40 0.40 1.10 3 0.53
B-13 1.95 1.95 0.40 1 1.520.40 0.40 2.58 1 0.41
B-14 1.35 1.35 0.40 1 0.730.40 0.40 1.10 1 0.18
B-15 1.35 2.70 0.60 1 2.190.40 0.40 2.40 2 0.77
B-9 1.20 1.20 0.50 1 0.72
1.7.1.2.2.3 Acero de Refuerzo fy=4200 Kg/cm2 8877.985/8" 63 4.85 473.6 497.285/8" 15 4.85 112.8 118.405/8" 63 16.83 1643 1725.625/8" 15 16.83 391.3 410.865/8" 32 3.5 173.6 182.283/8" 72 1.6 64.51 67.743/8" 60 1.2 40.32 42.345/8" 64 24.4 2420 2541.505/8" 96 9.4 1399 1468.665/8" 96 1.53 227.7 239.05
B-11 5/8" 21 2.8 91.14 95.705/8" 21 2.8 91.14 95.705/8" 21 2.8 91.14 95.705/8" 21 2.8 91.14 95.705/8" 24 3.375 125.6 131.833/8" 63 1.6 56.45 59.273/8" 54 1.2 36.29 38.10
B-12 5/8" 15 2.05 47.66 50.055/8" 15 2.05 47.66 50.055/8" 15 2.05 47.66 50.055/8" 15 2.05 47.66 50.055/8" 24 1.9 70.68 74.213/8" 27 1.6 24.19 25.403/8" 18 1.2 12.1 12.70
B-13 5/8" 7 2.65 28.75 30.195/8" 7 2.65 28.75 30.195/8" 7 2.65 28.75 30.195/8" 7 2.65 28.75 30.195/8" 8 3.375 41.85 43.943/8" 21 1.6 18.82 19.763/8" 18 1.2 12.1 12.70
B-14 5/8" 5 2.05 15.89 16.685/8" 5 2.05 15.89 16.685/8" 5 2.05 15.89 16.685/8" 5 2.05 15.89 16.685/8" 8 1.9 23.56 24.743/8" 9 1.6 8.064 8.473/8" 6 1.2 4.032 4.23
B-15 5/8" 9 2.45 34.18 35.895/8" 5 2.45 18.99 19.945/8" 9 3.8 53.01 55.665/8" 5 3.8 29.45 30.925/8" 16 3.5 86.8 91.143/8" 36 1.6 32.26 33.873/8" 30 1.2 20.16 21.17
B-9 1/2" 48 1.4 66.53 69.85
1.7.1.2.2.4 Suministro y colocación de pernos de anclaje ASTM A36 N° 40.32P-5 T2 - 319 8 3/4" 4 0.36 25.8 27.72P-6 T2 - 319 6 5/8" 4 0.3 11.16 12.60
1.7.1.2.2.5 Suministro y colocación de grout cementicio E=25mm 2.240.40 0.40 1.00 4 0.64
B-11 0.40 0.40 1.00 3 0.48B-12 0.40 0.40 1.00 3 0.48B-13 0.40 0.40 1.00 1 0.16B-14 0.40 0.40 1.00 1 0.16B-15 0.40 0.40 1.00 2 0.32
1.7.1.2.2.7 Juntas de Contracción 1.201.20 1.00 1.00 1 1.20
1.7.1.2.2.8 Juntas de Expansión 5.905.90 1.00 1.00 1 5.90
1.7.1.2.2.9 Concreto Ciclópeo f'c= 140 kg/cm2 + 30% Piedra Mediana 88.483.75 15.73 1.50 1 88.48