MGB MC 2000-38 Denial

Embed Size (px)

Citation preview

  • 8/6/2019 MGB MC 2000-38 Denial

    1/2

  • 8/6/2019 MGB MC 2000-38 Denial

    2/2

    2. Curriculum vitae and track records in mining operation and environmentalmanagement of the technical personnel who shall undertake the activities inthe submitted Work Program/s; and

    3. Affidavit as per Annex A of DMO No. 99-10.

    b. The mining application of a mining applicant who has complied with the

    abovestated requirements but has exceeded the maximum area that may beapplied for or held under an EP, MA or FTAA shall likewise be subject todenial/rejection. For this purpose, the mining application that was filed later bythe mining applicant that resulted in exceeding the maximum area that may beapplied for shall have the first order of priority for denial/rejection by the CentralOffice/concerned Regional Office.

    Section 3. Procedure for the Denial of Mining Applications

    After thoroughly determining that there is/are ground(s) for denial of the miningapplication pursuant to Section 2 hereof, the Central Office/concerned Regional Officeshall issue the Order of Denial duly signed by the Director/concerned Regional Directorand the pertinent Notice of Issuance of the Order, and sent to the mining applicantthrough Registered Mail.

    The Central Office/concerned Regional Office is enjoined to post the Orderimmediately upon issuance on its Bulletin Boards for two (2) consecutive weeks.

    The Order of Denial shall be in accordance with the proforma Order of Denial as

    shown in Annex A.

    The concerned mining applicant may file its Motion for reconsideration with theCentral Office for Mineral Reservation areas or concerned Regional Office for non-Mineral Reservation areas, or appeal with the DENR Secretary for Mineral Reservationareas or with the MGB Director for non-Mineral Reservation Areas, within fifteen (15)days upon receipt of the Order of Denial.

    Areas covered by the mining application of which is subject of an Order of Denialshall be open to other mining applications if no Motion for reconsideration or Appeal isfiled within fifteen (15) days upon receipt by the mining applicant of the pertinent Orderof Denial.

    Section 4. Effectivity

    This Memorandum Circular shall take effect immediately.

    (Sgd.) HORACIO C. RAMOS

    Director