Massachusetts Water Resources Authority Metropolitan Tunnel Redundancy Program Update December 16, 2020

Metropolitan Tunnel Redundancy Program Update

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Metropolitan Tunnel Redundancy Program Update

Massachusetts Water Resources Authority

Metropolitan Tunnel Redundancy Program Update

December 16, 2020

Page 2: Metropolitan Tunnel Redundancy Program Update

• Program Staffing

• Preliminary Design, Geotechnical Investigation and

Environmental Impact Report

• Community and Stakeholder Outreach

• Expert Review Panel (ERP)

• Other Ongoing Program-Wide Activities

Program Update

Page 3: Metropolitan Tunnel Redundancy Program Update

• Build staff capacity to match Program needs– Bring expertise and experience necessary to support the

Program– Plan for the future of the Tunnel Department – Grow with the Program– Consistent with Expert Review Panel recommendations– Approach is consistent with Boston Harbor Project and

MetroWest Tunnel

• Tunnel Department staff are assisting with non-tunnel projects where their expertise is helpful

Tunnel Department Staffing Approach

Page 4: Metropolitan Tunnel Redundancy Program Update

* Start Date: January 2021

The shaded boxes are filled positionsand the white boxes are vacant positions.

**Reports to the Executive Office

Notes:

Director Tunnel Redundancy Kathleen Murtagh

NU/17

Administrative Systems Coord Karen Reardon

1/20

Communications Manager**Kristin MacDougall

6/12

Manager, Geotech & TunnelingVivian Chan

NU/14

Sr. Program Manager, Geology*BradfordMiller

9/30

Project Manager, Geotechnical

9/25

Sr. Geotech EngineerDavid Abt

9/25

Director, Design & Construction Frederick Brandon

NU/16

Manager, DesignColleen Rizzi

NU/14

Program Manager, Design

9/29

Project EngineerGabrielle Marrese

9/21

Staff Engineer

9/19

Deputy Director, Design & Construction*PaulSavard

NU/15

Project Controls Specialist

6/12

Tunnel Redundancy Department Organization Chart

Page 5: Metropolitan Tunnel Redundancy Program Update

Preliminary Design Began in July 2020:

• Duration of 3.5 years • File Environmental Notification Form (ENF) in early 2021

– ENF will propose Program Study Area for Tunnel Alignment Alternatives Evaluation

• Evaluation of Alternatives (2021 – 2022) - Select Shaft and Connection Locations• Extensive Public Engagement – Working Group (early 2021 – 2023)• Geotechnical Investigations (begin early 2021)• Mapping and Survey• Environmental Impact Reports (Fall 2022)• Preliminary Design (complete by Dec 2023)

Preliminary Design Key Activities

Page 6: Metropolitan Tunnel Redundancy Program Update

• Technical Assistance: 2023• Field work – borings, survey, etc.• Other “data” collection

• Final Design: begin in 2024 • Two or more final design contracts• Additional geotechnical investigation, survey, State and

local permitting• Preparation of bid documents

• Construction Manager: begin in 2025• Evaluating # of contracts• Provides management and inspections of all

construction work• Experienced with rock tunnel construction

• Construction: begin in 2026 or 2027• Two or more tunnel construction packages• Each contract lasts 5 years+/-

Tunnel Redundancy Program Schedule

Page 7: Metropolitan Tunnel Redundancy Program Update

Program Study Area

Belmont

Brookline

Boston

Dedham

Needham

Wellesley

Weston

Newton

Watertown

Waltham

Program Study Area

Conceptual Tunnel Alignment

Page 8: Metropolitan Tunnel Redundancy Program Update

• Includes all 10 communities

– One (or more) representative from each community

– Initial Working Group for this Program will consist to 10 to 12 members

• Transparent process for evaluating and selecting shaft sites and tunnel alignments

• First Working Group meeting in early 2021, prior to filing ENF

• Monthly meetings through the evaluation of alternatives (Winter 2021 – Spring 2022)

Tunnel Working Group Concept

Page 9: Metropolitan Tunnel Redundancy Program Update

• November 2019 – Program Kick-Off– Program management, staffing,

communications, tunneling and geotechnical challenges, contract practices

• September 2020 – Risk Management Plan

• September 2020 – Preliminary Design Work Plan and Schedule

• January 2021– Geotechnical Investigation Work Plan (Ph1A)

Expert Review Panel Meetings

Page 10: Metropolitan Tunnel Redundancy Program Update

Other Program Activities

Completed Program-Wide Guidelines and Standards

• Program Risk Management Plan• Program Quality Management Plan• Program Delineation Report• Existing Geotechnical Data Report• Geotechnical Field Manual• Geotechnical Data Management Plan• Hydraulic Analysis• Program Management Plan• Document Control Plan• Style Guide• Program Web Page

Ongoing Program-Wide Activities

• Expert Review Panel• Program Guide Specifications• Program Budget Analysis• Program Schedule Development• Project Controls• Contract Practices• Community and Stakeholder Outreach• Industry Outreach

Page 11: Metropolitan Tunnel Redundancy Program Update

Plan to update Board at key milestones through Preliminary Design• Proposed tunnel alignment and shaft sites (late 2021/early 2022)• Draft Environmental Impact Report (mid 2022)• Geotechnical program progress (TBD)• Preliminary Design (multiple, mid-late 2023)

– Cost estimate– Schedule– Contract packaging

Additional updates – topics/dates TBD

Future Board Updates

Page 12: Metropolitan Tunnel Redundancy Program Update

Thank You

Page 13: Metropolitan Tunnel Redundancy Program Update

Welcome Ashland and Burlington!

13

Page 14: Metropolitan Tunnel Redundancy Program Update

Massachusetts Water Resources Authority

FY22 Proposed Capital Improvement Program

December 16, 2020

Page 15: Metropolitan Tunnel Redundancy Program Update

• FY22 Proposed CIP complies with the Cap requirements

• Focus on Asset Protection and Long-Term Redundancy

• Metropolitan Tunnel Redundancy

FY22 Proposed CIP

15

Page 16: Metropolitan Tunnel Redundancy Program Update

16

FY22 Proposed CIP - FY19-23 vs. Base-Line Cap

$ 984.8 $ 983.9

$ 905.1 $ 888.1

-

100.0

200.0

300.0

400.0

500.0

600.0

700.0

800.0

900.0

1,000.0

FY19 Baseline FY20 FY21 FY22 Proposed

Total Cap by Fiscal Year$ in millions

Page 17: Metropolitan Tunnel Redundancy Program Update

17

FY22 Proposed CIP – Projected Expenditures

$0.0

$100.0

$200.0

$300.0

FY19 FY20 FY21 FY22 FY23FY19 Baseline 179.2 276.1 251.3 194.9 150.4FY20 161.5 199.5 268.4 243.0 214.3FY21 142.9 158.3 266.2 251.9 236.0FY22 Proposed 142.9 159.0 184.8 260.5 283.0

Projected Expenditures by Fiscal Year$ in millions

Page 18: Metropolitan Tunnel Redundancy Program Update

FY22 Proposed CIP – Asset Protection and Water Redundancy

18

38.0%

54.4%68.2%

29.8%

19.7%

19.2%11.0% 1.0%

21.1% 24.9%12.6%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

FY14-18 FY19-23 FY24-28

CIP Spending By Category% of Total

Other

CSO

Water Redundancy

Asset Protection

Page 19: Metropolitan Tunnel Redundancy Program Update

19

FY22 Proposed CIP – Top Projects Excluding Loans FY19-23 Cap Period Spending

Project Subphase

FY19-23 Spending

$s in Millions

% of Total

Deer Island Treatment Plant Asset Protection Clarifier Rehab Phase 2 - Construction $75.3 7.3%Corrosion & Odor Control NI Odor Control HVAC Imp Construction Phase 2 $58.3 5.7%Facil ity Asset Protection Chelsea Creek Upgrades - Construction $51.9 5.0%Facil ity Asset Protection Prison Point Rehab - Construction $42.5 4.1%SEH Redundancy & Storage Redundancy Pipeline Sect 111 - Construction 3 $20.2 2.0%NIH Redundancy & Storage Section 89 & 29 Redundancy Construction Phase $19.8 1.9%Deer Island Treatment Plant Asset Protection Gravity Thickener Rehab $19.6 1.9%Deer Island Treatment Plant Asset Protection Fire Alarm System Replacement - Construction $15.8 1.5%Metro Tunnel Redundancy Prelm Des & MEPA Review $14.4 1.4%SEH Redundancy & Storage Redundancy Pipeline Sect 111 - Construction 2 $14.2 1.4% Top Spending Subphase FY19-23 $331.9 32.2%

Remaining FY19-23 Spending $698.3 67.8% Total Projected FY19-23 Spending $1,030.2 100.0%

Page 20: Metropolitan Tunnel Redundancy Program Update

20

FY22 Proposed CIP – Top Projects Excluding Loans FY22 Spending

Project SubphaseFY22 $s

in Millions

% of Total

Corrosion & Odor Control NI Odor Control HVAC Improvement Construction Phase 2 $22.9 8.8%Deer Island Treatment Plant Asset Protection Clarifier Rehab Phase 2 - Construction $21.8 8.4%Facil ity Asset Protection Prison Point Rehab - Construction $21.2 8.2%Deer Island Treatment Plant Asset Protection Fire Alarm System Replacement - Construction $7.8 3.0%NIH Redundancy & Storage Section 89 & 29 Replacement - Construction $5.8 2.2%Metro Tunnel Redundancy Preliminary Des & MEPA Review $5.4 2.1%Metro Redundancy Interim Improvement WASM 3 CP-1 $5.2 2.0%Central Monitoring System CWTP SCADA Upgrade Construction $5.0 1.9% Total Contracts > $5 million $95.1 36.5% Other Project Spending $165.3 63.5% Total FY22 Spending $260.5 100.0%

Page 21: Metropolitan Tunnel Redundancy Program Update

FY22 Proposed CIP – Proposed FY22 Contract Awards

21

$s in millions

Waterworks25

44%

Wastewater21

37%

Business and Ops11

19%

Contract Awards

Wastewater14

25%

Waterworks33

59%

Business & Ops9

16%

Contract Awards

Wastewater$33.723%

Waterworks$105.6

71%

Business & Ops$9.76%

Contract Value

56 contracts projected to be awarded in FY22 for $149 million.

Page 22: Metropolitan Tunnel Redundancy Program Update

Total Proposed FY22 Expenditures: $260.5 million

FY22 Proposed CIP – Proposed FY22 Expenditures

22

$s in millions

Wastewater$145.2

56%

Waterworks$95.036%

BOS$20.2

8%

FY22 Spending

Page 23: Metropolitan Tunnel Redundancy Program Update

Nut Island Odor Control and HVAC Improvements Construction

FY 22 Budget : $22.9MTotal Contract: $58.3MNTP: February 2020SC: December 2022

FY22 CIP – FY22 Top Spenders - Asset Protection

23

Page 24: Metropolitan Tunnel Redundancy Program Update

FY22 Proposed CIP – FY22 Top Spenders – Asset Protection

24

Clarifier Rehabilitation Phase 2 Construction

FY22 Budget: $21.8M Total Contract: $137.2MNTP: January 2021SC: May 2025

Page 25: Metropolitan Tunnel Redundancy Program Update

Prison Point Rehabilitation Construction

FY 22 Budget: $21.2M

Total Contract: $42.5MNTP: March 2021SC: March 2023

FY22 Proposed CIP – FY22 Top Spenders – Asset Protection

25

Page 26: Metropolitan Tunnel Redundancy Program Update

FY22 Proposed CIP – FY22 Top Spenders – Asset Protection

26

Deer Island Fire Alarm System Replacement Construction

FY22 Budget: $7.8M

Total Contract: $28.8MNTP: June 2021SC: October 2024

Page 27: Metropolitan Tunnel Redundancy Program Update

Northern Intermediate High Redundancy Sections 89 and 29

FY 22 Budget: $5.8MTotal Contract: $28.9MNTP: January 2021SC: December 2025

FY22 CIP – FY22 Top Spenders - Redundancy

27

Page 28: Metropolitan Tunnel Redundancy Program Update

28

Preliminary Design & MEPA Review

FY22 Budget: $5.4MTotal Contract: $15.7MNTP: July 2020SC: January 2024

FY22 Proposed CIP – FY22 Top Spenders – Redundancy

North Tunnel

South Tunnel

Program Study Area

Conceptual Tunnel Alignment

Page 29: Metropolitan Tunnel Redundancy Program Update

FY22 Proposed CIP – FY22 Top Spenders – Redundancy

29

WASM 3 CP-1

FY22 Budget: $5.2M ` Total Contract: $19.5M

NTP: October 2020SC: August 2024

Page 30: Metropolitan Tunnel Redundancy Program Update

Historic and Projected Capital Improvement Spending

31

$196

$304

$413

$504

$608

$580

$437

$377

$447

$498

$392

$333

$365

$297

$194

$168

$152

$178

$196

$182

$211

$139

$138

$155

$102

$104

$95 $1

33

$151

$143

$159

$185

$260

$283

$338

$428

$431

$359

$328

$0

$100

$200

$300

$400

$500

$600

$700

$ m

illio

ns

Actual Projected

FY90-20 Average $269M/year

FY21-28 Average $326M/year

Page 31: Metropolitan Tunnel Redundancy Program Update

Historic and Projected Capital Improvement Spending by Utility

32

$79

$286

$389

$463

$590

$564

$395

$282

$273

$245

$199

$146

$143

$117

$92

$89

$102 $1

20 $147

$124 $1

53

$92

$76

$74

$56 $7

5

$64

$72

$65

$75 $9

7 $123 $1

45

$152 $1

89

$265

$241

$198

$172

$117

$18

$24

$41

$18

$16

$43

$95

$174

$253

$193

$187 $2

22

$180

$102

$79

$50 $5

6 $46

$53 $5

0

$39

$55 $7

5

$41

$23

$27

$63 $8

3

$66 $5

8 $48

$95 $1

19

$138

$157

$186

$160

$155

$0

$100

$200

$300

$400

$500

$600

$700

$ in

mill

ions

Wastewater Improvements Waterworks Improvements

Actual Projected

FY90-20 Water $82M/yr

Wastewater $185M/yr

FY21-28 Average Water $132M/yr

Wastewater $186M/yr

Page 32: Metropolitan Tunnel Redundancy Program Update

Level of MWRA Indebtedness

33

$0

$100

$200

$300

$400

$500

$600

$700

FY86

FY88

FY90

FY92

FY94

FY96

FY98

FY00

FY02

FY04

FY06

FY08

FY10

FY12

FY14

FY16

FY18

FY20

FY22

FY24

FY26

FY28

FY30

FY32

FY34

FY36

FY38

FY40

FY42

FY44

FY46

FY48

FY50

FY52

FY54

$ in M

illion

sCurrent Debt Service vs. FY16 Debt Service

Current Debt Service 2016 Peak Years Debt Service

Current cap period debt service is projected tobe $558.0 million less than in FY16.

Page 33: Metropolitan Tunnel Redundancy Program Update

Level of MWRA Indebtedness

34

$2,000,000,000

$2,500,000,000

$3,000,000,000

$3,500,000,000

$4,000,000,000

$4,500,000,000

$5,000,000,000

$5,500,000,000

$6,000,000,000

$6,500,000,000

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023

Outstanding Debt on June 30 by Fiscal YearFY12-FY23

$5.85B$5.73B $5.60B

$5.39B$5.21B

$5.11B $5.07B $4.92B $4.86B $4.84B $4.82B

$5.94B

Page 34: Metropolitan Tunnel Redundancy Program Update

• Lessons learned from Chelsea Headworks Upgrades• Continue Asset Protection• Metropolitan Tunnel Redundancy

Looking Ahead

35

Page 35: Metropolitan Tunnel Redundancy Program Update

36

FY19-23 Projected Expenditures

Contract Name Start/ Duration (years)

Contract Budget

(millions)

FY19-23 Spending (millions)

Program Support ServicesAwarded

FY19/9 $17.5 $8.1

Preliminary Design/MEPA

ReviewAwarded

FY21/3.5 $15.7 $14.4

Technical AssistanceAnticipated

Award January 2023

FY23/4 $4.1 $0.4

Metropolitan Tunnel Redundancy Program

North Tunnel

South Tunnel

Program Study Area

Conceptual Tunnel Alignment

Page 36: Metropolitan Tunnel Redundancy Program Update

• Work with the Advisory Board

• Finalize FY22 CIP

• Submit FY22 Final CIP to Board of Directors for approval in June 2020

37

Next Steps

Page 37: Metropolitan Tunnel Redundancy Program Update

FY22 Proposed CIP

38

Thank You!

Page 38: Metropolitan Tunnel Redundancy Program Update

Massachusetts Water Resources Authority

Wastewater COVID TestingBiobot Analytics

December 16, 2020

Page 39: Metropolitan Tunnel Redundancy Program Update

Current Data from MWRA.COM

40

Page 40: Metropolitan Tunnel Redundancy Program Update

OP-420 Selection

41

• Biobot is still the industry leader• Using an out of state laboratory adds an additional 1 – 2 days to the turnaround time from

sampling to results• Guaranteed comparability to our existing dataset, as well as the data Biobot is generating

for DPH and seven other Massachusetts communities

Firm Total Points Order of Preference* Total Score

Final Ranking

Biobot Analytics, Inc 523 6 1LuminUltra Technologies, LTD 501 13 2GoAigua Inc. 449 20 3CosmosID, Inc. 440 25 4Geosyntec Consultants 339.5 33 5120Water 383.5 38 6CDM Smith Inc. 367.5 42 7Pennoni Associates, Inc 356 41 8ALS Group USA, Corp. 294.5 49 9

Page 41: Metropolitan Tunnel Redundancy Program Update

Massachusetts Water Resources Authority

Ward Street and Columbus Park Headworks Upgrade

Design and Engineering Services During Construction

Contract 7429

December 16, 2020

Page 42: Metropolitan Tunnel Redundancy Program Update

Ward Street and Columbus Park Headworks Upgrade

Major upgrade of both facilities including:

• Screenings and grit collection replacement

• Resurfacing all channels, and influent and effluent shafts

• Odor control and HVAC systems replacements

• SCADA improvements

• Remediation of hazardous building materials (lead and asbestos)

• Building envelope improvements

Ward Street Headworks

Columbus Park Headworks

Page 43: Metropolitan Tunnel Redundancy Program Update

Major Facility Upgrades

Grit collection

Climber screen replacements

HVAC/Odor control

Page 44: Metropolitan Tunnel Redundancy Program Update

Scope of Services includes:

• Design of a new building over channels• Use 3D Laser Scanning • Perform destructive investigations to identify hidden conditions• Document existing conditions and sequencing requirements

Scope of Services

Page 45: Metropolitan Tunnel Redundancy Program Update

Evaluation of New Superstructure

Existing Ward Street Headworks Facility Conceptual Alternative for New Superstructure

Page 46: Metropolitan Tunnel Redundancy Program Update

• 3D Laser Scan of Nut Island Odor Control Room

3D Laser Scanning

Page 47: Metropolitan Tunnel Redundancy Program Update

• Expose existing conditions– CMU walls – interior and exterior– Areas above drop ceilings

Destructive Investigations

Page 48: Metropolitan Tunnel Redundancy Program Update

• Documentation of Existing Conditions– 3D Laser scanning– Identify each item as active or abandoned

• Sequencing of Equipment Removal/Replacement to Maintain Operations during Rehabilitation

Existing Conditions and Sequencing

Page 49: Metropolitan Tunnel Redundancy Program Update

Proposer Rank Cost Hours

CDM Smith Inc. 1 $28,896,530 160,866

Arcadis U.S., Inc. 2 $27,722,135 166,968

Engineer's Estimate $24,504,960 144,147

Procurement Process and Project Cost

• One step RFQ/P• Selection Committee recommends award to CDM Smith Inc.

Page 50: Metropolitan Tunnel Redundancy Program Update

67