Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
METRO Orange Line UpdateFebruary 21, 2017
Rebecca Fabunmi, Principal EngineerChristina Morrison, Project Manager
Natalie Westberg, Planner
1metrotransit.org/orangeline
2
Agenda
• 2016 Update
• Station renderings
• Southbound American Boulevard Station
• American Boulevard/Knox Avenue intersection
• Knox Avenue Transitway renderings and wall concepts
3
2016 Progress• Submitted project information in September to the federal Small Starts grant program
• Completed all Orange Line environmental work
• Secured an additional $39.63 million of funding in 2016
• Began engineering and completed 30% design, with all design to be completed in 2017
4
American Boulevard Station
Night view of Stations 98th Street, Bloomington
5
6
Knox Avenue Intersection - Existing Design
7
Knox Avenue Intersection - Potential Redesign
Reduces crossing distances by 30-50% in each segment, improving pedestrian safety
8
Southtown Existing Conditions
9
Knox Avenue Transitway Visualization
10
Southtown Existing Conditions
11
Knox Avenue Transitway Visualization
12
Knox Avenue Existing Conditions
13
Knox Avenue Transitway Visualization
14
Knox Avenue Transitway Visualization
Grand Rounds – I-35W Underpass at Minnehaha Pkwy
15
Form liner precedents
16
Form liner precedents
17
Lighting precedents – Target Field Station
18
Lighting precedents – Philadelphia Garage
19
Custom wall effects – photo concrete
20