METHODOLOGY FOR PUMP & SUMP ROOM Scope: Construction of RCC work in pump and sump room Reference: Drawings no: ssidc/pwitc/wd/sd-113 and Technical Specifications Responsibility: Site Engineer and site supervisor Checked By: Site In-charge and QA Engineer Procedure: 01. Safety Precautions: as per EHS. 02. PCC 1:4:8 of 100mm thick is laid as per drawing and detailed specifications. 03. Surface cleaning and marking for raft is to be done. 04. Reinforcement tying is done for Raft & Wall verticals. 05. Shuttering is done with proper supports. 06. M30 grade concrete is poured with proper vibrating up to raft level. 07. Reinforcement & concrete for Raft, And Wall up to 300 mm will be done monolithically. 08. Wall reinforcement horizontal are tied up to 1 st lift i.e. sump is 1.2m height & pump is 2.4m height. 09. PVC water stopper is tied to steel frame work through eyelets by means of small wire (binding wire) to keep it in proper position where 50% width of bar should be below the 1 st lift concrete level. 10. Form work is fixed for wall at both sides of wall. 11. M30 grade concrete is poured with proper vibrating.

Methodology for Pump and Sump Room (2)

Embed Size (px)

DESCRIPTION

during the construction phase the methodology of building up of the pump and sump room

Citation preview

METHODOLOGY FOR PUMP & SUMP ROOMScope: Construction of RCC work in pump and sump roomReference: Drawings no: ssidc/pwitc/wd/sd-113 and Technical SpecificationsResponsibility: Site Engineer and site superisorCec!e" #y: Site !n-charge and "# EngineerProce"$re:1. Safety Precautions: as per EHS. 2. PCC1:4:8of 100mmthick is laidas per drain!anddetailedspeci"cations.#. Surface cleanin! and markin! for raft is to $e done.4.%einforcement tyin! is done for %aft & 'all (erticals.). Shutterin! is done ith proper supports.*. +#0 !rade concrete is poured ith proper (i$ratin! up to raft le(el.,. %einforcement & concrete for %aft- .nd'all up to #00 mm ill $edone monolithically.8. 'all reinforcement hori/ontal are tied up to 1st lift i.e. sump is 1.2mhei!ht & pump is 2.4m hei!ht.0. P1Cater stopper is tied tosteelframe ork throu!h eyelets $ymeansof small ire2$indin!ire3 tokeepit inproper positionhere )04 idth of $ar should $e $elo the 1st lift concrete le(el. 10. 5orm ork is "6ed for all at $oth sides of all. 11. +#0 !rade concrete is poured ith proper (i$ratin!.12. 5irst onehalf of theater stopisem$eddedintheconcretelea(in! the second half e6tended.1#. Shutterin! $oard is remo(ed after 24hrs of concrete done. 14. Shorin! $oard is also remo(ed.1). 5illin! ith crusher dust is done at East side and part of northside up to e6istin! drain $ottom.%emainin! area "llin! ill $e doneith a(aila$le morrum and proper consolidation is done.1*. Proper sta!in! is done for second lift concrete ork.1,. 'all reinforcement (ertical laps&hori/ontal aretiedupto2ndlift 7sla$ le(el.18. 5orm ork is "6ed for all at $oth sides of all.10. +#0 !rade concrete is poured ith proper (i$ratin!. Second halfof the ater stopper is also em$edded in the concrete. 20. Shutterin! $oard is remo(ed after 24hrs of concrete done. 21. Curin! shall $e done at all concrete le(els for 14days.22. %e8uired plum$in! and pipin! ork ill $e done ith the respecti(e(endors.