103
The Pennsylvania State University The Graduate School Department of Architectural Engineering METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM IDENTIFICATION AND OPERATION OF AN EXPERIMENTAL HVAC SYSTEM A Thesis in Architectural Engineering by Li Cui 2013 Li Cui Submitted in Partial Fulfillment of the Requirements for the Degree of Master of Science May 2013

METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

The Pennsylvania State University

The Graduate School

Department of Architectural Engineering

METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM IDENTIFICATION

AND OPERATION OF AN EXPERIMENTAL HVAC SYSTEM

A Thesis in

Architectural Engineering

by

Li Cui

2013 Li Cui

Submitted in Partial Fulfillment

of the Requirements

for the Degree of

Master of Science

May 2013

Page 2: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

ii

The thesis of Li Cui was reviewed and approved* by the following:

Stephen Treado

Associate Professor of Architectural Engineering

Thesis Advisor

James D. Freihaut

Professor of Architectural Engineering

Jelena Srebric

Professor of Architectural Engineering

Chimay Anumba

Department Head & Professor of Architectural Engineering

*Signatures are on file in the Graduate School

Page 3: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

iii

ABSTRACT

It is well known that building control systems rarely function as designed, contributing to

excessive energy use and poor environmental control performance. In addition, most

conventional building control systems do not incorporate many energy efficient functions thereby

missing potential energy savings opportunities. Part of the reason for this problem is the lack of

effective modeling and simulation tools for building control systems, and the difficulty in

obtaining the information required to accurately model specific HVAC components and systems,

along with the difficulty of implementing and exercising the models at the design stage. Also,

models that have been verified by laboratory or field measurements are lacking, putting into

doubt the validity of simulation results when they are undertaken.

In order to address these issues, this project will focus on the design and construction of

an HVAC experimental system with control capability, system performance identification and

development of components characteristics. The facility consists of an air handling unit with

heating and cooling coils, a water heater, a chiller and a chilled water storage tank. Two

customized chambers are constructed for both outdoor and indoor air simulation which allows the

system to be operated under various realistic conditions. Tests will be conducted using the facility

first for system performance identification, and second to develop and evaluate different

component characteristics.

This document includes a literature review about different HVAC control strategies and

an overview of several HVAC control test centers in the United States. The procedure of design

and constructing an experimental HVAC system and the performance identification are also

presented.

Page 4: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

iv

TABLE OF CONTENTS

LIST OF FIGURES ........................................................................................................... vi

LIST OF TABLES ........................................................................................................... viii

Chapter 1 INTRODUCTION ............................................................................................. 1

1.1 Background ............................................................................................................................ 1

1.2 Objectives .............................................................................................................................. 5

Chapter 2 LITERATURE REVIEW .................................................................................. 7

2.1 HVAC Control ....................................................................................................................... 7

2.1.1 Classical Control ............................................................................................................. 7

2.1.2. Auto-tuning PID Control ............................................................................................... 8

2.1.3 Optimal Control .............................................................................................................. 9

2.1.6 Direct Digital Control (DDC) ....................................................................................... 10

2.1.4 Non-linear Control ........................................................................................................ 10

2.1.5 Fuzzy Logic Control ..................................................................................................... 11

2.1.7 MIMO Robust Control .................................................................................................. 12

2.2 HVAC System Simulation ................................................................................................... 13

2.3 HVAC System Modeling ..................................................................................................... 15

Chapter 3 REVIEW OF HVAC SYSTEM TEST CENTERS ......................................... 16

3.1 Iowa Energy Center-Energy Resource Station (ERS) ......................................................... 16

3.2 Lawrence Berkeley National Laboratory (LBNL) ............................................................... 19

3.2.1 Building Controls Virtual Test Bed .............................................................................. 19

3.2.2 Modelica Buildings Library .......................................................................................... 20

3.3 Syracuse University-Full Scale Thermal and Air Quality Research Facility ...................... 21

Chapter 4 EXPERIMENTAL HVAC AND CONTROL SYSTEM ............................... 23

4.1 HVAC System Design ......................................................................................................... 24

4.1.1 Load Calculation ........................................................................................................... 24

4.1.2 Pipe and Duct Sizing ..................................................................................................... 26

4.1.3 Control System Design ................................................................................................. 30

4.2 HVAC and Control System Setup ....................................................................................... 31

4.2.1 Equipment ..................................................................................................................... 31

4.2.2 Piping and Ducting ....................................................................................................... 37

4.2.2 Control Instruments ...................................................................................................... 41

Page 5: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

v

4.2.3 Control Modules Installation and Power Enclosure ..................................................... 46

4.2.4 Insulation for the HVAC System .................................................................................. 49

4.3 Software Development for Control Operation and Data Acquisition .................................. 50

4.3.1 Control System Setup in MAX and LabVIEW ............................................................. 53

Chapter 5 SYSTEM OPERATION AND PERFORMANCE IDENTIFICATION ........ 58

5.1 Equipment and System Operation ....................................................................................... 58

5.1.1 Chilled Subsystem Operation ....................................................................................... 58

5.1.2 Hot Water Subsystem Operation .................................................................................. 60

5.1.3 Air Handler Unit Operation .......................................................................................... 62

5.1.4 AHU Cooling/Heating Coil Subsystem Operation ....................................................... 64

5.1.5 HXZ and HXO Subsystem Operation ........................................................................... 65

5.2 System Performance Identification ...................................................................................... 67

5.2.1 Steady State Verification .............................................................................................. 67

5.2.2 Energy Balance Identification ....................................................................................... 70

5.3 Characteristics of the System Components .......................................................................... 78

5.3.1 Outdoor Box ................................................................................................................. 78

5.3.2 Indoor Box .................................................................................................................... 80

Chapter 6 ANALYSIS AND DISCUSSION ................................................................... 82

6.1 Experimental HVAC System Design vs. Actual Operation ................................................ 82

6.2 Measurement Uncertainty and Sensor Calibration .............................................................. 82

6.3 System Control Capability ................................................................................................... 83

Chapter 7 CONTRIBUTIONS AND RECOMMENDATIONS ..................................... 84

7.1 Contribution to HVAC Control Test Facility ...................................................................... 84

7.2 Future Work Recommendations .......................................................................................... 84

Appendix LABVIEW PROGRAMMING ...................................................................... 86

REFERENCES ................................................................................................................. 91

Page 6: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

vi

LIST OF FIGURES

Figure 1 Building Share of U.S. Primary Energy Consumption (Percent) ...................................... 1

Figure 2 Major Fuel Consumptions by End Use for All Buildings, 2003 ....................................... 2

Figure 3 PID control (McDowall 2009) ........................................................................................... 8

Figure 4 Schematic Diagram of System Model (House and Smith 1995) ....................................... 9

Figure 5 Comparison of the performances between the fuzzy controller and the PI controller on a

non-linear model (Ying et al. 1990) ............................................................................................... 12

Figure 6 Diagram of the experimental system and interface signals (M. Anderson et al. 2007) ... 13

Figure 7 Block Diagram of the Serial Communication (Modified) Virtual Instrument (Liew 2003)

....................................................................................................................................................... 14

Figure 8 HVAC Plan for Test Rooms (Iowa Energy Center 2010) ............................................... 17

Figure 9 Typical Test Room AHU (Iowa Energy Center 2010) .................................................... 19

Figure 10 Ptolemy II system model that links an actor with MatLab (LBNL 2011) ..................... 20

Figure 11 Full Scale Thermal and Air Quality Research Facility (BEEL at SU 2010) ................. 21

Figure 12 HVAC System Scheme ................................................................................................. 23

Figure 13 System and Pump Curves .............................................................................................. 28

Figure 14 HVAC System 3D Layout ............................................................................................. 28

Figure 15 Sensor Placement Scheme ............................................................................................. 30

Figure 16 Portable Air Cooled Chiller ........................................................................................... 32

Figure 17 SPI Control of the Chiller .............................................................................................. 32

Figure 18 Hot Water Heater ........................................................................................................... 33

Figure 19 Expansion Tank and Water Filters ................................................................................ 33

Figure 20 Side Glass for the Storage Tank .................................................................................... 34

Figure 21 Air Handling Unit .......................................................................................................... 35

Figure 22 Outdoor Box .................................................................................................................. 36

Figure 23 Outdoor Box .................................................................................................................. 36

Figure 24 Indoor Box ..................................................................................................................... 37

Figure 25 Copper Piping and Components ................................................................................... 38

Figure 26 Filters ............................................................................................................................. 38

Figure 27 Circulating Pump ........................................................................................................... 39

Figure 28 Leakage Test .................................................................................................................. 39

Figure 29 Support Base for Water Heater ...................................................................................... 40

Figure 30 Adjustable Clamps ......................................................................................................... 40

Figure 31 3-Way Control Valve .................................................................................................... 41

Figure 32 RTD ............................................................................................................................... 42

Figure 33 RTD Calibration ............................................................................................................ 42

Figure 34 Water Flow Meter .......................................................................................................... 43

Figure 35 Air Flow Station Control Panel ..................................................................................... 44

Figure 36 Air Flow Station Sensor Probe ...................................................................................... 44

Figure 37 Partition of Supply and Return Ducts ............................................................................ 45

Figure 38 Partition of Outdoor Duct .............................................................................................. 45

Figure 39 NI Control Modules ....................................................................................................... 47

Page 7: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

vii

Figure 40 Power Distribution Unit ................................................................................................ 48

Figure 41 System Control Desk ..................................................................................................... 49

Figure 42 Insulation of the HVAC System .................................................................................... 49

Figure 43 Measurement and Automation Explorer (MAX) Operation Window ........................... 53

Figure 44 Controller Configurations in LabVIEW ........................................................................ 54

Figure 45 Main Operation VI for the Summer Condition.............................................................. 55

Figure 46 Chilled Water Storage Subsystem Operation VI ........................................................... 55

Figure 47 Water Temperature Indicators ....................................................................................... 56

Figure 48 TDMS File for Water Temperatures ............................................................................. 57

Figure 49 Supply Water Temperatures .......................................................................................... 68

Figure 50 Water Flow Rates ......................................................................................................... 68

Figure 51 Air Temperatures ........................................................................................................... 69

Figure 52 Air Flow Rates ............................................................................................................... 70

Figure 53 Installed Valve Characteristics for HXO Hot Water ..................................................... 78

Figure 54 Installed Valve Characteristic for HXO Chill ............................................................... 79

Figure 55 Output and Process Variable Chart ............................................................................... 80

Figure 56 Installed Valve Characteristic for HXZ Hot Water ....................................................... 81

Figure 57 Installed Valve Characteristic for HXZ Chill ................................................................ 81

Figure 58 Data Logging Main VI .................................................................................................. 86

Figure 59 Chilled Water Storage Control VI ................................................................................. 86

Figure 60 System Monitor VI ........................................................................................................ 87

Figure 61 Summer Operation Main VI .......................................................................................... 88

Figure 62 Summer Monitor VI ...................................................................................................... 89

Figure 63 Winter Operation VI ...................................................................................................... 90

Page 8: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

viii

LIST OF TABLES

Table 1 Design Conditions ............................................................................................................. 25

Table 2 Load Calculation ............................................................................................................... 25

Table 3 Pipe Sizing ........................................................................................................................ 27

Table 4 Equipment Schedule ......................................................................................................... 29

Table 5 Sensor Schedule ................................................................................................................ 31

Table 6 Signal Schedule ................................................................................................................. 46

Table 7 Control Modules Specification ......................................................................................... 47

Table 8 System Outputs ................................................................................................................. 51

Table 9 Test Conditions - Summer ................................................................................................ 70

Table 10 Test Conditions - Winter ................................................................................................. 71

Table 11 Outdoor Simulation Heat Exchanger Load Calculations – Summer (Heating) .............. 71

Table 12 Outdoor Simulation Heat Exchanger Load Calculations – Winter (Cooling) ................ 72

Table 13 Indoor Simulation Heat Exchanger Load Calculations – Summer (Heating) ................. 73

Table 14 Indoor Simulation Heat Exchanger Load Calculations – Winter (Cooling) ................... 74

Table 15 AHU Heat Exchanger Load Calculations – Summer (Cooling) ..................................... 75

Table 16 AHU Heat Exchanger Load Calculations – Winter (Heating) ........................................ 76

Table 17 Overall System Energy Balance ..................................................................................... 77

Page 9: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

ix

ACKNOWLEDGEMENTS

I would like to thank my advisor Dr. Treado whose instruction and expertise in HVAC

control is the central driver of my research and graduate study. The plentiful guidance,

encouragement and assistance he gave me are deeply appreciated.

I am also grateful to my committee member Dr. James Freihaut and Dr. Jelena Srebric

who helped to identify this topic and provided me this great research opportunity.

Special recognition is due to Mr. Paul Kremer who provided useful guidance and

assistance throughout the HVAC system construction and control program development. Thanks

are also due to fellow research assistant Samuel Fonseca Soto for his assistance during the

construction of the project, configuration of the control modules, especially the assembly of

electrical facilities, to Ke Xu and Yan Chen for their assistance on the control system design and

LabVIEW development, and to Hiroki Ota whose assistance and encouragement throughout the

project.

I would also like to thank all the other fellow graduate students who provided me with

great moral support and assistance.

Page 10: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

x

DEDICATION

To my parents

Page 11: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

1

Chapter 1

INTRODUCTION

1.1 Background

In recent years, building energy consumption is in a rising trend, as shown in Figure 1.

Building sectors consumed 33.8% of the total primary energy use in 1980 which increased to 40%

by the year 2008. These primary energy consumptions include industry and manufacturing,

transportation and building sectors. 84% of energy consumed is attributed to building operations

such as heating, cooling and lighting. The sharp increase in building energy consumption raises

concerns of energy savings in building operation.

Figure 1 Building Share of U.S. Primary Energy Consumption (Percent)

HVAC system energy usage has a significant impact on buildings’ fuel consumption by

end use, as shown in Figure 2. One of the ways to realize sizable decrease in building energy

consumption is applying better HVAC control systems.

30.0%

32.0%

34.0%

36.0%

38.0%

40.0%

42.0%

Per

cen

tage

Year

Building Share of U.S. Primary Energy Consumption

Page 12: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

2

Figure 2 Major Fuel Consumptions by End Use for All Buildings, 2003

A wide range of equipment is involved in HVAC systems, to name a few general

components: chillers, compressors, boilers and pumps. HVAC control systems aim to operate the

equipment efficiently as well as provide a high quality environment. In operation, each HVAC

system should be suitable for the requirements in the facility; in combination, HVAC system

controls provide the link between varying thermal loads and maintaining suitable indoor

environmental conditions. The designed HVAC system will not operate as expected without an

adequately designed and properly functioning control system (McDowall 2009). A control loop

generally includes a controller, a sensor and a control device. The controller compares the data

from sensors with the set point or the desired value, relaying a command to the controlled device,

which passes to the process plant. The command will have an effect on the controlled variable

and then the process will start all over again.

Space Heating, 36%

Lighting, 20%

Cooling, 8%

Ventilation, 7%

Water Heating, 8%

Cooking, 3%

Refrigeration, 6%

Office Equipment, 1%

Computers, 2%

Other, 9%

Page 13: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

3

Over a century ago, the first control device-the bimetallic strip was applied for space-

heating systems. It controlled boiler output or air combustion damper, which were known as

regulators. These regulators, now called thermostats are used to control temperature in various

circumstances and functions, such as cars, restaurants, and houses. In the 1950’s, pneumatic

sensors and controllers were used in commercial buildings to control the heated or cooled air flow.

At that time the pneumatic controllers had to be installed and supervised by the controls

manufacturer resulting in highly expensive implementation that could not easily be used

nationwide. Improved pneumatic control systems were widely used in industry by the 1960’s.

Electronic HVAC control systems appeared in the 1970’s which was known as micro-

chip analog electric controls. These controllers were used to connect or break an electric circuit

that turns on a fan or pump, as well as switch a valve or damper. Initial computer based systems

were costly and performed minimal control functions. The need for affordable controllers led to

the development of pneumatic controls in favor of electrical controls.

In the late 20th century, the development and use of computers and microprocessors have

triggered great changes in HVAC control systems. Microprocessors made it possible for remote

data acquisition and direct digital control. Computers were used as on-site controllers and became

efficient tools in an integrated HVAC control system.

There are basically five control types today: self-powered controls are that controllers do

not require an external power source such as electricity or pneumatic control air. These systems

generally used on small HVAC systems or individual units. The most common and basic

controller is one of the electric controllers called thermostat. Electric controls are most typically

two positions, using thermostats, humidistats, or pressure-stats where the controlled variable is

sensed and compared to the set point and a contact is opened and closed accordingly. The other

Page 14: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

4

kind of electric controls is modulating controllers, which are used as a bridge circuit. Pneumatic

controls use compressed air as the power source. They are simple and cheap, which make it ideal

for temperature, humidity and pressure control. Analog electric controls are known as typical

modern controls. Several electric controllers are packaged in a single zone for controlling the

whole system. However, they are not as popular as pneumatic controls for commercial buildings

due to their high cost and lack of standardization. Digital control is the most advanced control

which means the microprocessors can operated on a series of pulses just as the typical PC.

Intelligent control strategies focus on providing a better control of indoor environment

while using less energy. As processing capabilities increased, more and more studies focused on

advanced HVAC controllers such as fuzzy control and robust control. However, most of the

studies are based on simulation and modeling results, while this may indicate the potential

benefits of advanced control strategies, translating the predictive performance into an actual

installation is not guaranteed. In order to prove the effectiveness of new control strategies and

designs, it is necessary to conduct validation testing using real HVAC systems. Verification of the

accuracy of dynamic models of actual HVAC systems also plays an essential role in controller

design and calibration.

There are a number of HVAC control system modeling and simulation tools currently

available with varying degrees of complexity and capability. Many of the tools impose significant

simplifying assumptions and idealizations that make them easier to use but also limit their ability

to realistically model control system performance. At the other extreme, a few tools require very

specialized knowledge and skill to use, two attributes that are generally not part of the normal

skill set HVAC control designs. Several general purpose simulation tools are being proposed for

use on this project.

Page 15: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

5

MatLab (Matrix Laboratory) is a high-level technical computing language and interactive

environment for algorithm development, data analysis and numerical computation. MatLab can

be applied in a wide range of fields such as control design, test and measurement, modeling and

simulating processes. Architectural engineers can use it to develop dynamic models of HVAC

systems for controller development and calibration.

Simulink is a commercial tool for simulation, model based design of dynamic systems. The

interactive graphic environment and a set of block libraries enable engineers and scientists to

design, simulate, implement and test a variety of time-varying systems such as communications,

controls and signal processing.

LabVIEW (short for Laboratory Virtual Instrumentation Engineering Workbench) is a

graphical programming environment used by engineers and scientist to develop sophisticated

measurement, test, and control systems by using graphic icons and wires that resemble a

flowchart. The purpose of this programming is automating the usage of processing and measuring

equipment in any laboratory setup. LabVIEW is commonly used for data acquisition, instrument

control, and industrial automation on a variety of platforms including Microsoft Windows,

various versions of UNIX, Linux, and Mac OS X. The latest version of LabVIEW is version

LabVIEW 2011, released in August 2011.

1.2 Objectives

An experimental HVAC system will be designed, constructed, configured, and

commissioned, including a control and a data acquisition system. The HVAC system is designed

for both heating and cooling conditions, using two chambers for outdoor and indoor condition

simulations. An air handler, electric heater, air cooled chiller, heat exchangers and 3-way valves

are the basic components of the experimental HVAC system. An integrated software environment

Page 16: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

6

will be created for data acquisition and control using LabVIEW. During the system identification

stage, tests will be conducted to enable the development of dynamic models of each of the

components. Different model types will be investigated and compared relative to their level of

effort to complete and their accuracy and performance. Several goals will be achieved in this

project:

Design, construct and commission an experimental HVAC system for control

performance evaluation

Develop test facility control and data acquisition software:

o Providing system control functions

o Conducting dynamic tests

o Collecting and processing measured data

Conduct system performance tests to provide measured data for system and components

identification

Determine component characteristics for modeling

Page 17: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

7

Chapter 2

LITERATURE REVIEW

There are a wide array of articles pertaining to HVAC controls studies. A brief literature

review is completed and presented in the following.

2.1 HVAC Control

The HVAC control history consists of classical control and advanced control according to

the control requirement. The common purpose on various control modes is to maintain the

controlled variable at the desired set point.

2.1.1 Classical Control

Classical control is known as the traditional and most economic control modes. There are

two subgroups in classical control: On/Off control and PID (proportional, integral plus derivative)

control.

On/Off control is also called two-position control which only provides two outputs, on or

off (Harrold and Lush 1988). It is widely used in residential houses for starting or stopping a

thermostat. Ahn and Song (2010) studied the on/off control characteristics and heating

performances for a radiant slab heating system in residential apartments (Ahn and Song 2010).

The fact is that the control doses not maintain the indoor air set point and creates a fluctuation in

temperature. They concluded it is important to set the proper point and use a differential gap.

PID control (see Figure 3) is generally applied to systems with continuous or modulating

capacity capability, it may also be applied to systems with staged capacity capability to improve

the accuracy versus two-position control logic (McDowall 2009).

Page 18: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

8

Figure 3 PID Control (McDowall 2009)

Classic controllers have the relatively acceptable function and low cost. However, with

regard to the efficiency and energy consumption, advanced controllers are more cost and energy

effective.

2.1.2. Auto-tuning PID Control

Turning a PID controller requires an accurate model of a process and an effective

controller design rule. Auto-tuning relieves the pain of manually tuning a controller. PID auto-

tuning means automatically determine PID parameters without human intervention (McDowall

2009)

(Ya-Gang Wang et al. 2001) developed a PID auto-tuner and presented its application to

HVAC systems. They found that the PID turning rules with accurate identification method has a

better control performance than the standard relay auto-tuner.

Although auto-tuning control can offer many advantages and are normally superior to the

PID control, this approach is limited to large range applications because model identification is

Page 19: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

9

required as initial step, together with model parameter identification in real time mode (Mirinejad

et al. 2008).

2.1.3 Optimal Control

The goal of optimal control is to determine the minimum energy usage or operating cost

for the system to achieve the desired comfort level. In comparison to conventional control

strategies, optimal control has been demonstrated to have the potential for energy savings of 12 to

30 percent (Nizet et al. 1984).

A comparison of optimal control with conventional control for a two-zone building and

HVAC system (Figure 4) is presented in (House and Smith 1995). The utility cost for the

optimum case is 11 percent less than the utility cost for the conventional cost. This difference is

mainly attributed to the cooling coil energy term and cost even less by allowing the temperature

in the zones to float within a predefined comfort range.

Figure 4 Schematic Diagram of System Model (House and Smith 1995)

Page 20: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

10

(Komareji et al. 2008) established a HVAC system which is made of two heat exchangers

and the optimal control structure was designed and implemented. Dynamic model of the system

was developed. The results of applying the developed control system showed that the system

respected optimal control policy while it had the perfect tracking of the set point of the inlet air

temperature. However, there is a problem with the bypass flow which cannot satisfy the

optimization criteria. A controller is then introduced to deal with this problem in (Komareji et al.

2009) and a simplified control structure is finally proposed for optimal control of the HVAC

system.

2.1.6 Direct Digital Control (DDC)

DDC systems can reduce energy cost by enabling mechanical systems to operate at peak

efficiency. The DDC technology can be used in diverse applications, such as commercial HVAC,

surgical suites, and laboratory clean rooms (McDowall 2009).

(Swanson 1993) discussed the most common deficiencies of conventionally controlled

HVAC systems and advantages of DDC systems. DDC offers an array of features to correct some

of the operation and maintenance problems identified, while also reducing HVAC system energy

consumption. A case study retrofit from pneumatic control to digital control is also studied in this

paper. By avoiding the cost of installing a new HVAC system, the applied DDC system realized

annual savings and improved indoor air quality.

2.1.4 Non-linear Control

Since HVAC systems are essentially a non-linear system, a number of Non-linear

Controllers are designed and utilized in HVAC systems since the 80’s (Mirinejad et al. 2008).

(Bing Dong 2010) introduces several non-linear optimal controllers for a single zone

heating system in buildings. MatLab/ Simulink response optimizer and non-linear programming

Page 21: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

11

are applied into optimal controller design and the results are compared. Linearization makes the

controller design easier but results in the fan consuming more energy. The non-linear

programming results in much less energy cost for both the fan and pump. This conclusion is not

only useful in the optimal controller design but also in the predictive controller design when real-

time weather files could be forecasted.

A back-stepping controller for a non-linear, MIMO HVAC system is demonstrated by

(Semsar et al. 2003). Using feedback linearization method, heat and moisture loads can be

compensated, considering them as measureable disturbances. The simulation results are brought

to show the ability of the method to present a controller with high disturbance decoupling and

good tracking properties.

2.1.5 Fuzzy Logic Control

The main problem in HVAC systems are variable conditions, intense non-linear factors,

interaction between climatic parameters, variation in system parameters and impossibility of

accurate modeling of the system (Mirinejad et al. 2008). With regard to the problems, fuzzy logic

control will be an excellent controlling choice.

(Ying et al. 1990) compared the function of the fuzzy controller with a non-fuzzy linear

PI controller. The control performances of the two controllers were almost the same; however, the

fuzzy controller could control the time-delay process model and non-linear process model

significantly better than the non-fuzzy linear PI controller (see Figure 5).

Fuzzy modeling methods for non-linear system identification and control design from

process data were reviewed and attention was paid to the choice of a suitable fuzzy model

structure for the identification task by (Babuška and Verbruggen 1996). An algorithm has also

been proposed for FLC design. A control policy for non-linear system was generated by

Page 22: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

12

developing a number of local linear models and designing optimal control policies for each of

these local models (J. Singh et al. 2006).

Figure 5 Comparison of the performances between the fuzzy controller and the PI

controller on a non-linear model (Ying et al. 1990)

2.1.7 MIMO Robust Control

Robust control theory addresses the effects that discrepancies between the model and the

physical system may have on the design and performance of linear feedback systems. (M.

Anderson et al. 2007) created an experimental HVAC system consisting of two air dampers, a

variable speed blower, and a heating coil and applied MIMO robust control strategies to the

system (Figure 6). As a result, the robust controller was able to make a coordinated change in

several actuators to achieve essentially independent control over the reference variables.

Page 23: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

13

Figure 6 Diagram of the experimental system and interface signals (M. Anderson et al. 2007)

An adaptive and robust controller was design by (Ming-Li Chiang and Li-Chen Fu 2006)

for a non-linear MIMO HVAC system which is modeled with some unknown parameters and

uncertainties. The robust controller can tolerance system uncertainties and made the tracking

error to converge residue set.

2.2 HVAC System Simulation

Various control assist tools have been developed for HVAC simulation. Mathworks

provides a large number of tools and toolboxes such as MatLab, Simulink and FemLab. (Clarke

et al. 2002) gave a synthesis on the use of MatLab/Simulink for the improvement of buildings and

HVAC systems. An overview on the related tools than can be applied and the issues solved by

using them is also studied.

A complete code for solving a 2-D steady state heat transfer problem and the results are

given by (van Schijndel 2003) in order to show how FemLab works. FemLab models can be

exported and connected with MatLab/Simulink models, creating a flexible simulation

Page 24: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

14

environment for combined PDE (partial differential equation) and ODE (ordinary differential

equation) based models.

(Liew 2003) used LabVIEW to do remote control of HVAC system. LabVIEW is chosen

instead of other programming languages because of its ease of programming and debugging.

LabVIEW is a graphical programming language (Figure 7). Almost other programming languages

use lines of text codes to create applications which make it difficult to create an application.

Figure 7 Block Diagram of the Serial Communication (Modified) Virtual Instrument

(Liew 2003)

Page 25: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

15

2.3 HVAC System Modeling

Models for HVAC components, particularly heat exchangers, have been the subject of a

number of articles over the past thirty years (M. L. Anderson 2001). The ASHRAE publication

Reference Guide for Dynamic Models of HVAC Equipment (ASHRAE 1996) provides a concise

overview of the dynamic models available for HVAC related equipment such as air and water

handling, heating and cooling coils and control equipment.

(Platt et al. 2010) studied adaptive HVAC zone modeling for sustainable buildings. This

paper focuses on real-time HVAC zone model fittings and prediction techniques based on

physical principles, as well as the use of genetic algorithms for optimization.

EnergyPlus is a new building performance and energy simulation program with a lot of

capabilities. (“EnergyPlus” 2000) gives an introduction of EnergyPlus and its applications in

building simulation.

Page 26: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

16

Chapter 3

REVIEW OF HVAC SYSTEM TEST CENTERS

3.1 Iowa Energy Center-Energy Resource Station (ERS)

The ERS was established for the purpose of examining various energy-efficiency

measures and demonstrating HVAC concepts. It is the only public facility in the United States

with the ability to simultaneously test and demonstrate multiple, full scale commercial building

systems in a real world environment (Iowa Energy Center 2010).

There are four matched pairs of test rooms allow for side-by-side comparisons of systems

in real time and in a controlled environment (see Figure 8). ERS has three separate air handling

units with three separate hydronic piping loops, which makes it possible for a wide variety of

performance testing options:

constant and variable air volume

dual duct

ventilation air only

perimeter heating

fan powered variable air volume

low temperature air distribution

unit ventilator

fan coil unit

custom system configurations

Page 27: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

17

Figure 8 HVAC Plan for Test Rooms (Iowa Energy Center 2010)

Several different types of testing and research have been done in energy efficiency and

building controls:

fault detection and diagnostics testing

reverse airflow testing

Page 28: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

18

validation and optimization of building energy control systems

building energy simulation software

testing of an adaptive fuzzy logic controller for HVAC applications

day lighting research projects

effect of return air configuration on building energy and indoor air quality

testing of lighting circuit power reducers

For the data acquisition and control system, ERS has one DDC system for general area

and two individually controlled systems for test rooms. The general control system for ERS is an

Ethernet network which allows the operator workstation or a remote workstation to communicate

with network controllers. There are several different components for the test room system. Each

test room is equipped with an air distribution system with VAV or reheat coil (see Figure 9).

Several control sequences were implemented in the test room controls: air handling unit

control sequence, outside air injection fan control sequence, variable air volume control sequence

and fan coil control sequence. Detailed operation of each control sequence can be found in (Iowa

Energy Center 2010). On/Off and PID controllers were applied to the whole control system and

intelligent control strategies have been rarely used in this system.

Page 29: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

19

Figure 9 Typical Test Room AHU (Iowa Energy Center 2010)

3.2 Lawrence Berkeley National Laboratory (LBNL)

3.2.1 Building Controls Virtual Test Bed

The Building Controls Virtual Test Bed (BCVTB) is a software environment that allows

expert users to couple different simulation programs for co-simulation (LBNL 2011).

Typical applications of the BCVTB include:

Performance assessment of integrated building energy and controls systems.

Development of new control algorithms.

Formal verification of controls algorithms prior to deployment in a building in order to

reduce commissioning time.

Page 30: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

20

The BCVTB is based on the Ptolemy II software which can link various simulation

programs such as Energy Plus and MatLab (see Figure 10). Ptolemy II’s graphical modeling

environment allows model development of control systems, physical devices and communication

systems.

Figure 10 Ptolemy II system model that links an actor with MatLab (LBNL 2011)

3.2.2 Modelica Buildings Library

The Modelica Buildings library is a free open-source library with dynamic simulation

models for building energy and control systems. The primary use of the library is for flexible and

fast modeling of building energy and control (LBNL 2011). The library is particularly suited for:

Rapid prototyping of new building systems

Analysis of the operation of existing building systems

Development, specification, verification and development of building controls within a

model-based design process

Page 31: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

21

Reuse of models during operation for functional testing, for verification of control

sequences, for energy-minimizing controls, fault detection and diagnostics.

The control systems include continuous time controls and discrete time controls. Both of

the two controls have various models. The Modelica Buildings library also has a large variety of

dynamic models for heating and cooling systems which can be implemented to this project. The

system configuration and set points descriptions can be found at (LBNL 2011).

3.3 Syracuse University-Full Scale Thermal and Air Quality Research Facility

The full scale thermal and air quality research facility is a coupled indoor/outdoor

environmental simulator which has three main components (see Figure 13):

An indoor environmental chamber (16ft by 12ft by 10 t high)

An outdoor climate chamber (6.5ft by 12ft by 10ft high)

An removable “separation wall” or “test wall” between the indoor environmental

chamber and the outdoor climate chamber

Figure 11 Full Scale Thermal and Air Quality Research Facility (BEEL at SU 2010)

Page 32: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

22

The indoor environment chamber is capable of simulating various indoor environmental

conditions including air temperature, relative humidity, air change rate and room air distribution.

The climate chamber is capable of simulating a wide range of outdoor weather conditions from

cold and dry winters to hot and humid summers, including air temperature, relative humidity and

dynamic wind pressure (BEEL at SU 2010). Both of the chambers use programmable DDC

control system which can evaluate the performance of the sensors and controllers. However, this

test facility is mainly focused on the indoor air quality and particle research, few experiments

have been done on the controller side.

Page 33: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

23

Chapter 4

EXPERIMENTAL HVAC AND CONTROL SYSTEM

An experimental HVAC system with both simulated indoor and outdoor environment

chambers was built in Architectural Engineering Lab (see Figure 12). The system consists of an

air handling unit (AHU) with both heating coil (HC) and cooling coil (CC); an air-cooled portable

chiller connects to a storage tank and an electrical hot water heater. Each of the simulated

chambers includes two heat exchangers (HXO and HXZ). The system is designed to mimic the

operation of a typical HVAC system providing space conditioning including ventilation to a

single zone. Currently, there is a limitation on latent loads, but this feature is expected to be

added at a future time. The primary purpose of the experimental HVAC test facility is to develop

and demonstrate advanced control strategies on real systems. Thus, considerable operating

flexibility has built in to the facility.

Figure 12 HVAC System Scheme

Page 34: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

24

In summer conditions, the AHU supplies 58.6°F (dry bulb temperature) air flowing

through the indoor chamber (HXZ), removing heat load and returning to the AHU. A part of the

return air mixed with the outdoor air goes through the cooling coil and then supplies to the zone

(HXZ). Chilled water goes through the cooling coil, cooling the mixed air. Hot water goes

through the outdoor chamber (HXO, in this study the laboratory air will be fed into the HXO),

heating the lab air to the simulated outdoor temperature. The heat load of the HXZ is also

supplied by the hot water.

In winter conditions, chilled water goes through the HXO, cooling the lab air to the

simulated outdoor temperature. Amount of the return air mixed with simulated outdoor air being

heated to 106.4°F and supplied to the HXZ. Chilled water also goes in the HXZ to simulate the

heat loss. The storage tank for chilled water is used to simulate thermal storage option.

4.1 HVAC System Design

4.1.1 Load Calculation

The load calculation is based on the design condition of the air handler unit. In addition,

the design temperatures and humilities are listed in Table 1, which are referring to ASHRAE

Fundamentals. The Philadelphia weather data is used as outdoor air conditions. The load

calculation results are listed in Table 2. The selection of the outdoor heat exchangers uses log-

mean temperature method. Since the lowest supply chilled water is 45 °F, the simulated outdoor

air temperature in winter condition can be as low as 47.6 °F.

Page 35: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

25

Table 1 Design Conditions

Weather Data 1%

Philadelphia DB (°F) MCWB (°F) HR

Cooling 90.6 74.5 0.0166

Heating DB 99% (°F)

Heating 16.9

Design Indoor Conditions Heating (°F) Cooling (°F) HR

Indoor temp 68 75 0.0092

Indoor relative humidity N/A 50%

Table 2 Load Calculation

Sensible Load

CASE Amount of

OA (%)

Water Heater

Capacity (MBh)

Chiller Capacity

(MBh)

Heating Coil

Capacity (MBh)

Cooling Coil

Capacity (MBh)

To (F) Tz (F) Ts (F)

Cooling

0% 7.078 7.078 0 7.078 90.6 75 58.59

10% 8.424 7.751 0 7.751 90.6 75 58.59

20% 9.770 8.424 0 8.424 90.6 75 58.59

30% 11.116 9.097 0 9.097 90.6 75 58.59

40% 12.462 9.770 0 9.770 90.6 75 58.59

Heating

0% 9.490 9.490 9.490 0 47.6 68 90

10% 11.043 12.897 11.043 0 47.6 68 90

20% 12.595 16.305 12.595 0 47.6 68 90

30% 14.148 19.713 14.148 0 47.6 68 90

40% 15.701 23.120 15.701 0 47.6 68 90

Latent Load

CASE Amount of

OA (%)

Water Heater

Capacity (MBh)

Chiller Capacity

(MBh)

Heating Coil

Capacity (MBh)

Cooling Coil

Capacity (MBh)

HR_o HR_z HR_s

Cooling

0% 0.774 0.774 0.774 0.774 0.0166 0.0092 0.0096

10% 1.742 0.658 1.742 0.658 0.0166 0.0092 0.0096

20% 4.259 2.091 4.259 2.091 0.0166 0.0092 0.0096

30% 6.776 3.524 6.776 3.524 0.0166 0.0092 0.0096

40% 9.293 4.956 9.293 4.956 0.0166 0.0092 0.0096

Page 36: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

26

4.1.2 Pipe and Duct Sizing

Equivalent length method was applied for pipe sizing in this project as shown in Table 3.

Besides, equal-friction method was used to sizing the duct system. Pumps are selected depending

on the total pressure drops calculated form the pipe sizing chart. The piping system and pump

curve are shown in figure 14. The supply and return ducts are sized to be 8 x 10 inches according

to the pressure drop. The system was designed in Revit MEP; equipment arrangements and

system layout depend on available lab space (Figure 13). The indoor environment simulation

chamber is 1m³ with an exhaust on one side and two heat exchangers to simulate the

cooing/heating load. The size of the outdoor air simulation chamber is based on the heat

exchangers. Detailed specifications of each component are listed in Table 4.

Page 37: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

27

Table 3 Pipe Sizing

Section Size (in)

Flow rate (gpm)

Length

Fittings

Accessory ∆P/L ( ft.H2O/100' pipe)

Equiv Length of Fittings (ft.)

Frictional ∆P (ft. H2O)

Valve ∆P (ft.H2O)

Coil ∆P (ft.H2O)

Total ∆P (ft.H2O)

Transition Elbow Tee

1 3/4'' 4 1' 1''-3/4'' (1) 1 3-way control valve for chiller

4.60 0.00

2 3/4'' 4 5' 3 4.60 0.00

3 3/4'' 4 1'10'' 1 4.60 60.00 1.50 1.50

4 1/2'' 2.32 1'10'' 1 6.00 20.00 0.54 0.54

5 1/2'' 2.32 6'4'' 1 Control Valve AHU 6.00 30.00 0.81 7.36 1.84 10.01

6 1/2'' 2 11'8'' 2 2-way control valve HXO 5.00 60.00 1.62 6.42 6.93 14.97

7 1/2'' 2 16'4'' 4 3-way control valve HXZ 5.00 120.00 3.24 6.42 9.24 18.90

8 1/2'' 2 17' 4 check valve 5.00 180.00 4.86 4.86

9 1/2'' 2.32 5'9'' 1 1 check valve 6.00 90.00 2.43 2.43

10 1/2'' 2 11'2'' 3 check valve 5.00 90.00 2.43 2.43

11 1/2'' 2.32 1'2'' 1 6.00

12 3/4" 4 3' 3-way valve for chiller,

strainer, pump 4.60

13 3/4" 4 5' 1''-3/4'' (1) 1 1 4.60

14 3/4" 4 4'5'' 2 Ball valve 4.60

15 3/4" 4 1' Process bypass valve 4.60

1 3/4'' 4 4' 3/4''-1/2'' (1) 1 1 Air separator ,ball valve 4.60 90 2.25 2.25

2 1/2'' 2 7'10'' 2 2-way control valve HXO 6.00 60 1.62 6.42 6.93 14.97

3 1/2'' 2 2'8'' 1 6.00 20 0.54 0.54

4 1/2'' 1.58 6'8'' 1 Control Valve AHU 3.50 30 0.81 7.36 1.52 9.69

5 1/2'' 2 17'8'' 4 3-way control valve HXZ 6.00 120 3.24 6.42 9.24 18.90

6 1/2'' 2 17' 4 1 check valve 6.00 180 4.86 4.86

7 1/2'' 1.58 7' 1 check valve 3.50 90 2.43 2.43

8 1/2'' 2 3'2'' 1 6.00 60 1.62 1.62

9 1/2'' 2 8' 3 check valve 6.00 90 2.43 2.43

10 3/4" 4 4' 3/4''-1/2'' (1) 1 Ball valve 4.60

Page 38: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

28

Figure 13 System and Pump Curves

Figure 14 HVAC System 3D Layout

0

20

40

60

80

100

120

140

0 2 4 6 8

Tota

l He

ad, f

t

Flow Rate, gpm

Pump

System

Page 39: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

29

Table 4 Equipment Schedule

Name Description Numbers Specification

Air Handling Unit Supply hot and cool air to the simulated

indoor chamber

1 Cooling capacity: 11630 Btu/hr;

Heating capacity: 15780 Btu/hr;

Supply chilled water: 45°F, 2.32 gpm;

Supply hot water: 180°F or 150°F, 1.58gpm

Chiller Produce chilled water and deliver it to

storage tank or system

1 Capacity: 19640 Btu/hr;

Supply 45°F chilled water, 55°F return;

Flow rate 4.8 gpm;

208VAC, 60Hz;

Pipe connection: 3/4''

Electric hot water

heater

Produce hot water 1 Capacity; 15780 Btu/hr;

Supply 180°F hot water (could also use 150°F ), return 160°F (if use 150°F supplied

then return is 130°F);

Flow rate5.58 gpm; pipe connection: 3/4''

HXO (Outdoor heat

exchanger)

Simulate outdoor air using ambient lab air 2 Heating air case: capacity 3860 Btu/hr,

Water temperature: 180°F to 160°F ( or 150°F to 130°F),

Air temperature:75°F to 85°F

Cooling air case: capacity 3640 Btu/hr,

Water temperature: 45F to 55°F, air 75°F to 50°F

HXZ (Indoor heat

exchanger )

Simulate indoor environment using heat

exchanger or other panels

2 Heating air case: capacity 15780 Btu/hr,

Water temp 180°F to 160°F ( or 170°F to 150°F), in coming air temperature:59°F;

Cooling air case: capacity 11630 Btu/hr, water temp 45°F to 55°F, in coming air

106.38°F

Storage tank Store chilled water and then deliver to the

system

1 80 gallon for 20min supply, based on the chiller flow rate

Water connection size: 3/4''

Pumps Circulate chilled/heated water to system 1 Based on the total requirement of system, 25 psi for 4 gpm

Pipe size:3/4''

3 way control valves Change between chiller and storage modes 3 Used for chilled water supply and return

2-way control valves Control water flow rate goes through HXO 2 Control the water flow rate go into the heat exchangers

3-way control valves Control the flow rate in the AHU and HXZ 4 Hot and chilled water supply pipes of the AHU

Page 40: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

30

4.1.3 Control System Design

For the control system design, the measurement points were determined first. The sensor

locations are shown in Figure 15. Since this project intends to achieve accurate control results,

RTD temperature sensors and air flow stations were chosen for parameter measurements. Control

valves were selected based on the water flow rate and temperature. Control modules used for

sensor connection and data acquisition were sized according to the sensor and control valve

wiring diagram. This sensor layout gave the ability of knowing the water temperature goes in and

out of each heat exchanger, heater and chiller and the flow rate goes in each heat exchanger as

well as the air flow rate and temperature of supply, return and outdoor air. All the sensor

specifications are listed in Table 5.

Figure 15 Sensor Placement Scheme

Page 41: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

31

Table 5 Sensor Schedule

Sensors Specified Requirements

Name Description Range Accuracy Notes

Tc Chilled water temperature sensor (40-60)°F 1°F Analog Output

Th Hot water temperature sensor (60-190)°F 1°F Analog Output

Fw Water meter 0 to 3 gpm 0.1 gfm Analog Output

Tz Zone air temperature sensor (45-120)°F 1°F Analog Output

Fa Air flow station 0-500cfm ±2% Analog Output

4.2 HVAC and Control System Setup

After designing the system, a market research and purchases of all the equipment and

components for the project were done. Next will be the equipment assembling, piping and control

system construction. Once the system is finished, the power box and electrical wires need to be

all hooked up and connected to the controller.

4.2.1 Equipment

The main components of the HVAC system are the chiller, air handling unit, storage tank,

heater and heat exchangers. The selection of that equipment based on the schedule and

calculation which were done in the system design stage.

Since the chiller should be easily fit in a lab space and be able to connect to the control

module. A portable air cooled chiller with communication capabilities, which can accept inputs

and deliver outputs was selected as shown in Figure17. The chilled has 2 tons of cooling load and

a 1 hp pump designed for 5 gpm at 39 psi. The design flow rate is 5 gpm and design chilled water

temperature is 50°F, which can be cooled as low as 40°F. In addition, the following

Page 42: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

32

communications are supported: process temperature set point; high temperature deviation; low

temperature deviation; to process temperature and process status.

Figure 16 Portable Air Cooled Chiller

Figure 17 SPI Control of the Chiller

An 80 gallons commercial electrical hot water heater is shown in Figure 18. It has two

elements of 6KW and the hot water temperature can range from 120°F to 180°F. An expansion

tank and two water filters installed as shown in Figure 19.

Page 43: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

33

Figure 18 Hot Water Heater

Figure 19 Expansion Tank and Water Filters

In addition, an 80 gallons commercial storage tank was implemented for the chilled water

storage. In order to see the water level in the storage tank, a side glass was installed on the side of

Page 44: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

34

it. Figure 20 shows the position of the side glass. All the extra holes on the tank were sealed to

prevent leakage.

Figure 20 Side Glass for the Storage Tank

As shown in Figure 21, the air handling unit consists of a vertical blower coil with

hydronic cooling and heating and a mixing box with damper actuators. The fan has a variable

speed frequency drive (VFD) which gives the capability of providing different air flow rates. The

air handling unit also comes with two 3-way control valves for the cooling and heating coils

which can be controlled through the controller. For the automatic control capability, the VFD and

damper actuators can communicate with a remote controller.

Page 45: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

35

Figure 21 Air Handling Unit

Two heater exchangers were used to simulate the outdoor condition. They are tube-fin

liquid to air heat exchangers with 4500 BTU/Hour capacity. Figure 22 shows the outdoor box

which was built based on the size of the heat exchangers and the shape the heat exchangers.

Another two 10900 BTU/Hour heat exchangers were used for simulating the indoor loads.

They are also tube-fin water to air heat exchangers and the maximum temperature is 400°F.

Figure 23 shows the heat exchanger and their position in the indoor box.

Page 46: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

36

Figure 22 Outdoor Box

The indoor box is a 1m³ sheet metal box which has two heater exchangers of 10900

BTU/Hour in the middle (as shown in Figure 24). The supply air goes from the top of the box and

the return is on the bottom. There is an exhaust on the bottom of the box used for air balance.

Figure 23 Outdoor Box

Page 47: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

37

Figure 24 Indoor Box

4.2.2 Piping and Ducting

The piping in this project is cooper tube with pro-press connector, which is easily

attached and has more flexibility. Unions and shut off valves were used on each side of the

components, which gave the capability of un-attach the components if there is a problem (Figure

25). The other components used in the water line are water filters and circulating pumps.

Page 48: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

38

Figure 25 Copper Piping and Components

Filters were used for the chilled and hot water (Figure 26). The chilled water filters are

located before and after the chiller. The maximum pressure and temperature are 150 psi and

100°F and the micron rating is 5. The hot water filters are located before and after the hot water

heater. The maximum pressure and temperature are 250 psi and 250°F.

Figure 26 Filters

Page 49: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

39

As shown in Figure 27, two circulating pumps were used for the chilled and hot water

distribution. The maximum flow rate and pressure are 256 gph and 150 psi. The hot water pump

head was customized for hot water.

Figure 27 Circulating Pump

Soap water was used for the leakage test of the water pipes. Referring Figure 28, if there

are bulbs on the connections, which means it needs to be fixed.

Figure 28 Leakage Test

Page 50: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

40

Every facility has its own support with casters which means that the equipment can be

moved right away (Figure 29). The pipes are supported by strut and adjustable clamps (Figure 30).

Figure 29 Support Base for Water Heater

Figure 30 Adjustable Clamps

Page 51: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

41

4.2.2 Control Instruments

The control instruments include control valves, damper actuators, VFD for the fan, water

temperature sensors and flow meters, air flow stations, humidity sensors and air temperature

sensors in the indoor box.

There are two 3-way control valves in the chilled water storage and two 2-way control

valves for the outdoor box piping (see Figure 31). The valves are all proportional and run

between 2 to 10 volts. The run time of these valves are 90 seconds. The 3-way control valves of

the indoor box are used to bypass the rest of the flow. There are also one 3-way floating control

valve and two proportional valves for the chilled water storage loop used for the chiller and the

storage tank.

Figure 31 3-Way Control Valve

The damper actuators and VFD are as described in 4.2.1. The temperature sensors used

for the water system are RTD sensors with high accuracy (±0.12%). As shown in Figure 32, the

sensor includes a stainless steel probe stem and 1/8 NPT mounting fitting which fit for the cooper

fitting used in the water system. The other end of the sensor is an electrical terminal which can be

connected to the control module.

Page 52: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

42

Figure 32 RTD

A rotating plate with a magnet and a RTD calibrator as shown in Figure 33 were used for

the calibration of the RTD sensors. By putting the calibrator and the RTD sensor in water, the

difference between them will record and a correct factor will be used if the difference is greater

than the accuracy of the RTD sensors.

Figure 33 RTD Calibration

The water meter is a piston type, variable area flow meter with solid state circuitry

including non-contact sensor electronics, electronic signal conditioning circuit, digital flow rate

and total indication and proportional analog output. The water flow rates were measured using

flow meter with analog outputs which can be connected to the control modules. As shown in

Page 53: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

43

Figure 34, the flow meter also has a digital flow rate indicator so people can see the flow rate

directly from the flow meter. The measurement range is 0.5 to 5 gpm and with a 2% full scale

accuracy.

c

Figure 34 Water Flow Meter

Three air flow stations were implemented for the supply, return and outdoor air flow rate

and temperature measurements. The air flow station has analog output transmitter which includes

the capability for dedicated independent linear outputs for temperature and flow rate (see Figure

35). There are certain restrictions should be considered when installing the air flow stations such

as the air flow linearization in the ducts. The placement of the probes according to the

duct/plenum sensor probe placement procedure in the air flow station manual.

Page 54: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

44

Figure 35 Air Flow Station Control Panel

The outdoor air flow has two probes and the supply and return stations have one probe

each. The sensor accuracy of the probe is ±2% for the air flow and ±0.15°F for the air

temperature. The sensor range is 0 to +5,000 fpm for the air flow and -20°F to 160°F for the air

temperature. The sensor probe implements advanced thermal dispersion technology which relates

the velocity of the air to the power dissipation and rise in temperature of a heated element in a

moving air stream Figure 36.

Figure 36 Air Flow Station Sensor Probe

Page 55: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

45

An anemometer was using to calibrate the air flow rates measured by the air flow

stations. The equal area method was conducted referring to Figure 37 and 38. At first,

four small areas were made for the supply, return ducts and nine sections of the outdoor

duct. After comparing with the air flow station readings and the data measured by

anemometer, correction factors were being applied to the air flow station.

Figure 37 Partition of Supply and Return Ducts

Figure 38 Partition of Outdoor Duct

Page 56: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

46

4.2.3 Control Modules Installation and Power Enclosure

The signal inputs and outputs are listed in Table 6 and all these signals are connected to

certain control modules. Control modules’ selection is based on the signal lists.

Table 6 Signal Schedule

Control Analog Input Signals

Device Analog signal type Quantity

RTDs 100 Ω (at 0°C)-3 wire 23

Air Flow Meters 0-5 Vdc 3

Water Flow meters 4-10 mA 6

2-way proportional valves feedback signal 2-10 Vdc 2

3-way proportional valves feedback signal 2-10 Vdc 2

Control Analog Outputs Signals

Device Analog signal type Quantity

2-way proportional valves 2-10 Vdc 2

3-way proportional valve 2-10 Vdc 3

Damper actuator 2-10 Vdc 2

Fan and pump motor VFD 0-10V/4-20 mA/0-20 mA 2 wire RS485 via RJ45 3

Floating point On/Off Outputs

Device Analog signal type Quantity 3-way valves on/off 600 Ohms 3

There is a NI cRIO controller, two EtherCAT RIO chassis and 19 modules for the control

system. Table 7 shows the description of each module and Figure 39 shows the modules location.

The NI cRIO-9074 integrated system combines a real-time processor and a reconfigurable field-

programmable gate array (FPGA) within the same chassis for embedded machine control and

monitoring applications. The EtherCAT RIO is an expansion chassis and can provide high speed

I/O and control applications.

Page 57: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

47

Table 7 Control Modules Specification

Figure 39 NI Control Modules

The power connection for the chiller and heater come from one power box in the lab. All

the cables needed in the control system were brought overhead and connected to a power

Name NO. Description Application

NI 9217 5 4-Channel, 100 Ω RTD, 24-Bit Analog Input Module Water temperature measurements

NI 9481 2 4-Channel Relay [30 VDC (2 A), 60 VDC (1 A), 250 VAC (2 A)]

3-way floating control valves

NI 9263 2 4-Channel, 100 kS/s, 16-bit, ±10 V, Analog Output Module

Control the proportional valves

NI 9422 1 8 Ch, 24 V to 60 V, 250 µs, Sinking/Sourcing Digital Input

Optional module

NI 9205 1 32-Ch ±200 mV to ±10 V, 16-Bit, 250 kS/s Analog Input Module

Indicate water flow meter and air flow stations

NI 9474 1 8-Channel 5 to 30 V, 1 µs, Sourcing Digital Output Module

Control the circulating pumps

NI 9225 4 3-Channel, 300 Vrms Analog Input Module Voltage measurements

NI 9227 3 4-Channel Current Input C Series Module Current measurements

Page 58: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

48

enclosure which is shown in Figure 40. There are four power switches on the top panel of the

box which used for turning on the power supply for the control system. On the top of the back

panel, there are block connectors for distributing power. The orange, black and green blocks are

fuse holder for 24 VDC and 24 VAC. The lower part is all the connectors used for controlling or

receiving signals. On the cover side of the box, there are two CT coils used for current

measurement, two transformers, relays for the pumps and a NI PS-15 power supply of 5A, 24

VDC.

Figure 40 Power Distribution Unit

A computer acts as the host system for the whole HVAC system control was installed

neat the control rack as shown in Figure 41. The control modules and controllers can be

configured in Measurement and Automation Explorer (MAX) and all the control programming

was done in LabVIEW.

Page 59: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

49

Figure 41 System Control Desk

4.2.4 Insulation for the HVAC System

One inch wide fiber glass boards were used for the indoor, outdoor and ducts insulation

(figure 42).

Figure 42 Insulation of the HVAC System

Page 60: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

50

4.3 Software Development for Control Operation and Data Acquisition

As stated in the previous chapter, LabVIEW was used as the control interface. It is an

interactive graphic environment for modeling and simulating dynamic systems. The controller

and modules can be easily configured and programmed in LabVIEW. Routines for both data

acquisition and control purpose can also be applied graphically in LabVIEW.

There are several control tasks that were done in the project:

Project measurement and system operation monitoring

Equipment control including the chiller, air handling unit and the two simulated box for

indoor and outdoor conditions

Subsystem operations which consist of chilled water, hot water, cooling air and heating

air systems

Whole system control

The whole system control logic can be generalized as following:

System initialization/ start-up

Assign data to the setpoints and set operating conditions

Read and store data from the DAQ interface and set data filter

Calculate the room load, cooling/heating load, room load and the flow rate or temperature

needed

Change the flow rate of the HXZ to meet the design room load

Vary outdoor air and return air dampers’ position to meet the percentage of outdoor air

demand

Change the cooling/heating coil’s flow rate in the AHU to meet the supply air

temperature setpoint

Page 61: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

51

Change the fan speed to vary the supply air flow rate and tracking the power

consumption

Calculate the outdoor air load

Change the water flow rate to meet the outdoor air load

Results generation

All the inputs of the control system are listed in Table 8. There are temperature sensors,

flow meters, air flow stations and power measurement instruments.

Table 8 System Outputs

Name Description

Tcws_HXO Chilled water supply temperature for HXO

Tcwr_HXO Chilled water return temperature for HXO

Thws_HXO Hot water supply temperature for HXO

Thwr_HXO Hot water return temperature for HXO

Thws_AHU Hot water supply temperature for AHU

Thwr_AHU Hot water return temperature for AHU

Tcws_AHU Chilled water supply temperature for AHU

Tcwr_AHU Chilled water return temperature for AHU

Thws_HXZ Hot water supply temperature for HXZ

Thwr_HXZ Hot water return temperature for HXZ

Tcws_HXZ Chilled water supply temperature for HXZ

Tcwr_HXZ Chilled water return temperature for HXZ

Thwr Hot water return temperature

Thws Hot water supply temperature

Tcwr Return chilled water temperature

Tcwr Supply chilled water temperature

Tai_HXO Inlet air temperature for HXO

Page 62: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

52

Tao Outdoor air temperature

Tar Return air temperature

Tam Mixed air temperature

Tac Air temperature Leaving heating coil and entering cooling coil

Tas Supply air temperature

Taz Zone air temperature

Fcws_HXO Chilled water supply flow rate for HXO

Fhws_HXO Hot water supply flow rate for HXO

Fhwr_AHU Hot water return flow rate for AHU

Fcwr_AHU Chilled water return flow rate for AHU

Fhwr_HXZ Hot water supply flow rate for HXZ

Fcwr_HXZ Chilled water supply flow rate for HXZ

Fao Outdoor air flow rate

Fas Supply air flow rate

Icp Current of chiller pump

Icc Current of chiller compressor

Iwh Current of water heater

Ifm Current of VFD fan motor

Icw Current of chilled water pump

Ihw Current of hot water pump

Vcp Voltage of chiller pump

Vcc Voltage of chiller compressor

Vwh Voltage of water heater

Vfm Voltage of VFD fan motor

Vcw Voltage of chilled water pump

Vhw Voltage of hot water pump

Page 63: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

53

4.3.1 Control System Setup in MAX and LabVIEW

With MAX, the control devices and software can be configured and updated. Figure 43

shows the window of the cRIO and EtherCAT in MAX. The left side is a tree control of the

controllers and software while the right side is the configuration of the cRIO and EtherCAT.

Figure 43 Measurement and Automation Explorer (MAX) Operation Window

In order to implement control strategies to the system, a control interface was developed.

As shown in the Figure 44, the configuration of the system was uploaded in LabVIEW. In the

project explorer window, each of the devices with its modules is shown as a tree control and all

the files included in this project are shown as well.

Page 64: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

54

Figure 44 Controller Configurations in LabVIEW

A main operation VI was developed for the whole system which consists of system

monitoring, data logging and subsystem operation (Figure 45 and Figure 46). The system

configuration is shown in the main interface, the water and air flow rates and temperatures can be

seen on the screen and all the valves can be set to adjust the flow rates.

Page 65: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

55

Figure 45 Main Operation VI for the Summer Condition

Figure 46 Chilled Water Storage Subsystem Operation VI

Page 66: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

56

A system monitoring VI was developed in LabVIEW to show the values of the entire

measurement instrument. The water and air temperature and flow rates are shown in tab control

with graphs (Figure 47). The power consumption of each facility is also indicated in the front

panel.

Figure 47 Water Temperature Indicators

The data can be stored in TDMS file when running the data storage function. TDMS

means technical data management streaming which is the most common file format used by

national instruments software to store acquired data channels, and is also open to third party tool

such as excel. Figure 48 indicates a TDMS file for the water temperatures and the time.

Page 67: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

57

Figure 48 TDMS File for Water Temperatures

Page 68: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

58

Chapter 5

SYSTEM OPERATION AND PERFORMANCE IDENTIFICATION

5.1 Equipment and System Operation

This section lists the operation control specifications for equipment and the interactions

between them which including the measurement inputs, control outputs and equipment

initialization and alarm.

5.1.1 Chilled Subsystem Operation

Outputs and Calculations

Cooling load: (ṁCp∆T)_chiller

Power consumption: Power of Chiller Pump – (IV)_cp

Power of Chiller Compressor – (IV) _cc

Measurements

Tcws – Actual chilled water supply temperature (to process)

Tcwr – Chilled water return temperature

Fcw – Chilled water flow rate

Icp – Chiller pump current

Icc – Chiller compressor current

Vcp – Chiller pump voltage

Vcc – Chiller compressor voltage

Setpoints

Supply chilled water temperature (45⁰F to 55⁰F)

Specification

Page 69: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

59

The chiller subsystem consists of a portable chiller, a storage tank, a displacement

chilled water pump and two 3-way control valves. The chilled water supply flow rate is

constant. The supply temperature (to process) depends upon the chilled water return

temperature from HXZ, HXO and AHU and the supply temperature set point.

Normal Operation

Set the chilled water temperature; receive Tcws_p and Tcwr from the DAQ

interface. Using PI control to maintain the constant supply chilled water temperature.

For the power consumption measurement, receive date from the current and voltage

monitor.

The cooling load was calculated using the relative equations. Figure 2 shows the

normal operation VI will be used in LabVIEW.

Thermal Storage Mode

When switch to the chilled water storage state, change the 3-way valves

position and then turn on the chiller. After the tank is charged, the chiller will be

turned off. Referring to Figure 1, the high lever limit and low lever limit can be set.

Alarm

If the high temperature deviation is more than 10 degF or low temperature

deviation is lower than 5 degF, the chiller pump will shut down. When the

circulating pump pressure is more than 250 psi, the pump will shut down.

Start-up

When the chiller receives a start-up command, the system checks the valves

position (including the thermal storage mode 3-way valve and the summer, winter

condition valves). Also, check the supply chilled water temperature. If all the valves

are in the proper position, the chilled water temperature is higher than the setpoint

Page 70: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

60

and the circulating pump is shut down, the chiller will start; otherwise, the start-up

will halt.

Shutdown

The chiller starts to shut down when it receives the command through the

control system, or when the chiller detects an operational malfunction or component

failure. Before shutting down the chiller, turn off the circulating pump if it is in use.

5.1.2 Hot Water Subsystem Operation

Outputs

The data will plot on the screen and be stored in excel sheet every 10 seconds.

Heating load: (ṁCp∆T)_heater

Power consumption: Power of heater – (IV)_h

Measurements

The data will plot on the screen and be stored in excel sheet every 10 seconds.

Thws – Hot water supply temperature (to process)

Thwr – Hot water return temperature

Fhw – Hot water flow rate

Ih – Heater current

Vh– Heater voltage

Setpoints

Heat elements ON/OFF

Specification

The water heater subsystem consists of a hot water heater and a circulating water

pump. The hot water supply temperature (Thws) depends on the hot water return

Page 71: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

61

temperature (Thwr) and the power applied to the heater (Pwh). There is thermostat can be

adjust manually to set the hot water supply temperature (Thws). The hot water flow rate

discharged from the water heater is the sum of Fhwr_HXZ and Fhws_HXO in summer

condition and Fhwr_AHU in winter condition.

Normal Operation

Start the hot water heater; receive the supply water temperature and flow rate

from DAQ interface. The heating load and power consumption will be calculated

using the relative equations above. Figure $ shows the normal operation and alarm

VI.

Alarm

When the hot water supply temperature is higher than the setpoint, the

heating elements will shut down to prevent overheating. If the circulating pump

pressure is higher than 250 psi, the pump will shut down.

Start-up

When the electrical heater receives a start-up command, the system checks

the valves position (including the summer, winter condition valves) and the supply

temperature. If all the valves are in the proper position, the supply temperature is

lower than the setpoint and the circulating pump is shut down, the electrical heater

will start; otherwise, the start-up will halt.

Shutdown

The electrical heater starts to shut down when it receives the command

through the control system, or when the heater detects an operational malfunction or

component failure. Before shutting down the heater, make sure the hot water

circulating pump is turned off.

Page 72: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

62

5.1.3 Air Handler Unit Operation

Outputs

The data will plot on the screen and be stored in excel sheet every 10 seconds.

Cooling/Heating air load: Sensible-1.08 q dt

Latent-4,840 q dwlb

Power consumption: Power of VFD fan – (IV)_fan

Measurements

The data will plot on the screen and be stored in excel sheet every 10 seconds.

Fas – Air supply flow rate

Pas – Supply air pressure

Fao – Outdoor air supply flow rate

Tam – Mixed air temperature

Tas – Supply air temperature

Tar – Return air temperature

Tao – Outdoor air temperature

Has – Supply air humidity

Hao – Outdoor air humidity

Setpoints

Supply air temperature (Taz)

VFD fan speed Cfs

Outdoor air damper position Cdo

Return air damper position Cdr

Specification

Page 73: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

63

The variable frequency drive (VFD) allows the centrifugal fan to change its speed,

varying the air flow rate goes through the system. Design air flow is 400 cfm. The

relationship of the flow rate and fan speed will be determined by experimental tests.

Constant Air Volume (CAV) Operation

The speed of the fan is constant during operation. Supply air temperature can

only be adjusted by the water subsystem. The water flow rate in the heating/cooling

coil is related to the zone temperature setpoint. Set the speed of the VFD and turn on

the fan. Receive data of the air flow rate. The power will be calculated and stored

for future use.

Variable Air Volume (VAV) Operation

By using VAV system, the air load can be changed by both the air flow rate

and temperature. Turn on the fan and vary the speed of the VFD to see the change of

the air flow rate according to the zone air temperature setpoint. Calculate and store

the power consumption data.

Two dampers are used for external and return air ducts. The dampers are

ganged together within the controller so as to collectively maintain a constant

opening area. This allowed the dampers to vary the mix of external and return air

with only small variations in the air flow rate. Use the experimental data to find the

relationship between the voltage and the damper position. Establish the damper

control equations used for the three operation conditions:

No Outdoor Air Operation

100% Outdoor Air Operation

Certain Amount of Outdoor Air Operation

Page 74: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

64

Normal Operation

Set the zone air temperature and the amount of outdoor air. Collecting data

from the DAQ interface and monitoring the power consumption of the VFD fan.

Change the fan speed and the amount of outdoor air depending on the variation of

zone load.

Alarm

If the pressure of the fan outlet is higher than, the fan will switched off.

Start-up

When the AHU receives the start-up command, the AHU will read all inputs to

determine the initial values. Also, the damper position will be checked and then the

fan will be turned on.

Shutdown

The AHU starts to shut down when it receives the command through the control

system, or when the AHU detects an operational malfunction or component failure.

5.1.4 AHU Cooling/Heating Coil Subsystem Operation

Outputs

The data will plot on the screen and be stored in excel sheet every 10 seconds.

Cooling coil load: (ṁCp∆T)_AHUcc

Heating coil load: (ṁCp∆T)_AHUhc

Measurements

The data will plot on the screen and be stored in excel sheet every 10 seconds.

Thws_AHU – Hot water supply temperature sensor for AHU

Thwr_AHU – Hot water return temperature sensor for AHU

Tcws_AHU – Chilled water supply temperature sensor for AHU

Page 75: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

65

Tcwr_AHU – Chilled water return temperature sensor for AHU

Fhwr_AHU – Hot water return meter for AHU

Fcwr_AHU – Chilled water return meter for AHU

Fas – Supply air flow rate

Tas – Supply air temperature

Specification

The AHU cooling/heating coil subsystem includes two coils and two control

valves. The flow rate goes through each coil will be controlled by 3-way control valves.

The heat energy transfer depends upon the physical properties of the heat exchanger and

is a function of the temperatures and flow rates of the air and water.

Normal operation

The flow rates goes into the coils is controlled by the valve position. When the

control valve receives a command, it will open or close depending on the signal. The

relationship between the voltage signal and the flow rate will be determined using

experiment tests data. Figure 7 shows the coiling/heating coil operation.

5.1.5 HXZ and HXO Subsystem Operation

Measurements

Tcws_HXO – Chilled water supply temperature sensor for HXO

Tcwr_HXO – Chilled water return temperature sensor for HXO

Thws_HXO – Hot water supply temperature sensor for HXO

Thwr_HXO – Hot water return temperature sensor for HXO

Thws_HXZ – Hot water supply temperature sensor for HXZ

Thwr_HXZ – Hot water return temperature sensor for HXZ

Tcws_HXZ – Chilled water supply temperature sensor for HXZ

AO Signal

Page 76: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

66

Tcwr_HXZ – Chilled water return temperature sensor for HXZ

Fcws_HXO – Chilled water supply meter for HXO

Fhws_HXO – Hot water supply meter for HXO

Fhwr_HXZ – Hot water supply meter for HXZ

Fcwr_HXZ – Chilled water supply meter for HXZ

Fao – Outdoor air flow rate

Fas – Supply air flow rate

Setpoints

Tao – Outdoor air temperature

Taz – Zone air temperature

Specification

Three types of valves are used in this system to control the water flow rate or direction.

Two-way Proportional Control Valve

Three-way Bypass Valve

Three-way On/Off Valve

The water temperature will be controlled by the chiller and the heater; the water rates

depend upon the air temperature desired and the air flow rate. HXZ is used to simulate the room

load and the HXO to simulate the outdoor air temperature.

The whole system operation logic was built after the development of the equipment and

subsystem control logic, which includes summer and winter operation.

Page 77: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

67

5.2 System Performance Identification

After the development of the system operation logic, the system performance should be

tested prior of any experiments. A serial of tests will be conducted to check the system

functionality and energy balance.

System initialization is very important to protect the equipment and system. The

followings are the steps should be done:

Turn on the power switches of the equipment and enclosure box

Open the operation VI in LabVIEW and set the outputs needed for the specific state

Check if the control valves are in the proper position or not

5.2.1 Steady State Verification

In order to verify the system’s stability, both the summer and winter conditions were run

for enough periods of time and the data were collected in excel file. Besides, in these operations,

the control valves are fully open or fully closed, which means there was no control of the system.

Figure 49 indicates the supply hot and chilled water temperatures which were set to

120 °F and 50 °F. After one hour of operation, the hot water temperature remains 123 °F to

125 °F and the chilled water temperature remains 50 °F.

Page 78: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

68

Figure 49 Supply Water Temperatures

The water flow rates of the air handler unit (AHU), the outdoor heat exchanger (HXO)

and the indoor heat exchanger (HXZ) are shown in Figure 50. There are 0.05 gpm variations in

the flow rates which due to the differences between the time constant of the flow meter and the

data storage speed of the program. Besides, the variations are within the flow meters’ accuracy

which is 0.09 gpm.

Figure 50 Water Flow Rates

0

20

40

60

80

100

120

140

0 1000 2000 3000 4000

Tem

per

atu

re (

°F)

Time (Sec)

Supply Water Temperatures

1S CHILLER 2S HEATER

1.5

1.7

1.9

2.1

2.3

2.5

0 500 1000 1500 2000 2500 3000 3500 4000

Flo

w R

ate

(GP

M)

Time (Sec)

Water Flow Rates

FM.1. AHU (GPM) FM.2.HXO (GPM) FM.2. HXZ (GPM)

Page 79: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

69

There are five air temperatures can be measured in the system: 402. Figure 51 indicates

the steady air temperatures. The simulated outdoor air temperature can go up to 102 °F and the

zone air temperature stays at 68 °F. While the supply air temperature is 66 °F, the return air

temperature is 70 °F and the mixing air temperature is 80 °F.

Figure 51 Air Temperatures

The air flow rates which can be seen from Figure 52 are stable in ± 20cfm. In this

operation, the return damper is fully open and the outdoor damper is 20% open. The sum of

return and outdoor air flow rates are less than the supply for about 20 cfm, which is in the

accuracy of the air flow station measurements.

50

60

70

80

90

100

110

0 500 1000 1500 2000 2500 3000 3500 4000

Tem

per

atu

re (

F)

Time (Sec)

Air Temperatures Supply Air (F) Return Air (F) Outdoor Air (F) Mixing Air (F) Zone Air (F)

Page 80: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

70

Figure 52 Air Flow Rates

5.2.2 Energy Balance Identification

In order to check the energy balance of the components and the whole system, load

calculations were conducted for the heat exchangers in the outdoor box, indoor box and the air

handler unit. The test conditions in these calculations are shown in Table 9 and Table 10.

Table 9 Test Conditions - Summer

Root Name Title Author Date/Time Groups

Operation Data Summer Operation Li Cui 12-12-2012 01:29:50 PM 8

Group Channels Time 1

Description

HXO 3

VFD 5V (50%)

AHU 3

VFD Speed 918 rpm

HXZ 3

Damper R 8.5V (100%)

HEATER 2

Damper O 6.5V (70%)

CHILL 1

Chiller Set Point 50F

Air 5 AF 3

0

50

100

150

200

250

300

350

400

450

0 500 1000 1500 2000 2500 3000 3500 4000

Flo

w R

ate

(CFM

)

Time (Sec)

Air Flow Rates AF.O.F (CFM) AF.R.F (CFM) AF.S.F (CFM)

Page 81: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

71

Table 10 Test Conditions - Winter

Root Name Title Author Date/Time Groups

Operation Data Winter Operation Li Cui 12-12-2012 02:39:34 PM 8

Group Channels

Time 1

Description

HXO 3

VFD 5V (50%)

AHU 3

VFD Speed 918 rpm

HXZ 3

Damper R 8.5V (100%)

HEATER 2

Damper O 6.5V (70%)

CHILL 1

Chiller Set Point 50F

Air 5

AF 3

5.2.2.1 Outdoor Air Simulation Box

Table 11 shows the sample data and the load calculations of the outdoor box in summer

condition. The average values are listed in bold in the last row of the table. From the results the

water load is 685 Btu/hr larger than the air side, which may due to the uncertainty of the air flow

rate measurements and the small water temperature differences.

Table 11 Outdoor Simulation Heat Exchanger Load Calculations – Summer (Heating)

Outdoor Water Side

2I HXO (F)

2O HXO (F)

FM.2.HXO (GPM)

T_dif_w_HXO (F)

FM.2.HXO (lb/hr)

Qw_HXO (BTU/hr) 10 Sample

120.071 117.795 2.015 2.277 1008.556 2296.041

120.108 117.772 2.011 2.336 1006.420 2350.775

120.087 117.854 2.008 2.233 1005.023 2243.865

120.117 117.862 2.020 2.255 1010.939 2279.846

120.105 117.832 2.010 2.273 1006.256 2287.459

120.007 117.495 2.022 2.513 1012.254 2543.583

120.132 117.756 2.018 2.376 1010.282 2400.523

120.164 117.839 2.009 2.325 1005.516 2337.506

120.151 117.855 2.025 2.296 1013.487 2327.015

120.158 117.802 2.016 2.356 1009.132 2377.044 2344.366

… … … … … … …

121.196 118.894 2.043 2.302 1022.73 2354.568

Page 82: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

72

Outdoor Air Side

T_lab (F)

Outdoor Air (F)

AF.O.F (CFM)

T_dif_a_HXO (F)

AF.O.F (lb/hr)

Qa_HXO (BTU/hr) 10 Sample

79.79 97.327 135.833 17.537 610.327 2568.743

79.79 97.427 135.734 17.637 609.885 2581.586

79.79 97.439 135.784 17.649 610.106 2584.253

79.79 97.510 135.652 17.720 609.516 2592.127

79.79 97.681 136.178 17.891 611.876 2627.332

79.79 98.012 136.621 18.222 613.868 2684.639

79.79 98.130 137.163 18.340 616.302 2712.766

79.79 98.272 137.622 18.482 618.367 2742.905

79.79 98.449 137.934 18.659 619.768 2775.492

79.79 98.455 137.918 18.665 619.695 2776.040 2664.588

… … … … … … …

79.79 100.209 138.011 20.419 620.115 3040.371 3040.117

The winter load calculations are indicated in Table 12. The average values are listed in

bold in the last row of the table. From the results the water load is 1183 Btu/hr larger than the air

side, which may due to the uncertainty of the air flow rate measurements and the small water

temperature differences. The heat exchange in summer is much better than it in winter condition.

The reason may be the water also absorbs heat from the ambient environment such as the metal of

the outdoor box.

Table 12 Outdoor Simulation Heat Exchanger Load Calculations – Winter (Cooling)

Outdoor Water Side

2I HXO (F)

2O HXO (F)

FM.2.HXO (GPM)

T_dif_w_HXO (F)

FM.2.HXO (lb/hr)

Qw_HXO (BTU/hr) 10 Sample

52.021 53.827 2.030 1.806 1015.952 1834.729

51.988 53.782 2.041 1.794 1021.622 1832.358

51.897 53.698 2.029 1.800 1015.459 1828.264

51.870 53.686 2.031 1.816 1016.856 1846.958

51.864 53.639 2.018 1.776 1010.118 1793.764

51.792 53.586 2.030 1.794 1016.198 1823.523

51.702 53.512 2.038 1.810 1020.389 1846.871

51.667 53.476 2.033 1.809 1017.431 1840.550

51.629 53.445 2.034 1.816 1018.171 1848.780

Page 83: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

73

51.641 53.401 2.037 1.761 1019.567 1795.277 1829.107

… … … … … … …

50.850 52.475 2.054 1.625 1028.404 1671.129 1671.053

Outdoor Air Side

T_lab (F)

Outdoor Air (F)

AF.O.F (CFM)

T_dif_a_HXO (F)

AF.O.F (lb/hr)

Qa_HXO (BTU/hr) 10 Sample

79.79 60.445 112.769 19.345 506.697 2352.482

79.79 60.392 112.769 19.398 506.697 2358.950

79.79 60.398 112.441 19.392 505.222 2351.366

79.79 60.362 111.883 19.428 502.714 2343.972

79.79 60.362 111.768 19.428 502.198 2341.565

79.79 60.321 111.965 19.469 503.083 2350.686

79.79 60.321 111.620 19.469 501.534 2343.449

79.79 60.226 111.555 19.564 501.239 2353.445

79.79 60.197 111.883 19.593 502.714 2363.936

79.79 60.055 111.801 19.735 502.345 2379.301 2353.915

… … … … … … …

79.79 56.108 111.829 23.682 502.473 2854.312 2854.187

5.2.2.2 Indoor Condition Simulation Box

The sample data and load calculations for the indoor simulation box of the summer

condition are shown in Table 13. The water side heat exchange is 861 Btu/hr larger than the air

side, which may due to the heat exchanger efficiency and the sensor uncertainty.

Table 13 Indoor Simulation Heat Exchanger Load Calculations – Summer (Heating)

Indoor Water Side

2I HXZ (F)

2O HXZ (F)

FM.2. HXZ (GPM)

T_dif_w_HXZ (F)

FM.2.HXZ (lb/hr)

Qw_HXZ (BTU/hr) 10 Sample

120.123 117.915 1.951 2.208 976.838 2156.905

120.117 117.943 1.946 2.174 974.373 2118.384

120.117 117.957 1.929 2.160 965.663 2086.018

120.113 117.966 1.946 2.146 974.044 2090.569

120.116 117.975 1.941 2.140 971.661 2079.786

120.120 117.987 1.954 2.133 977.906 2086.093

120.123 117.991 1.948 2.132 975.359 2079.309

120.130 117.992 1.945 2.138 973.387 2080.806

120.140 117.995 1.950 2.145 976.345 2094.486

Page 84: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

74

120.147 118.000 1.945 2.147 973.387 2089.510 2096.187

… … … … … … …

121.259 119.201 1.977 2.058 989.467 2035.865 2035.916

Indoor Air Side

Supply Air (F)

Return Air (F)

AF.S.F (CFM)

T_dif_a_HXZ(F)

AF.S.F (lb/hr)

Qa_HXZ (BTU/hr) 10 Sample

66.839 69.564 414.782 2.724 1863.707 1218.554

66.863 69.540 414.656 2.677 1863.139 1197.043

66.940 69.552 415.478 2.612 1866.836 1170.293

66.975 69.552 416.776 2.577 1872.666 1158.012

67.212 69.776 417.567 2.565 1876.222 1154.889

67.448 70.013 418.707 2.565 1881.341 1158.040

67.672 70.190 419.941 2.517 1886.887 1140.044

67.879 70.308 421.239 2.429 1892.717 1103.301

67.856 70.456 421.239 2.600 1892.717 1181.149

67.891 70.521 421.112 2.630 1892.149 1194.212 1167.554

… … … … … … …

67.422 70.035 416.864 2.613 1873.062 1174.833 1174.857

The winter load calculations are indicated in Table 14. The average values are listed in

bold in the last row of the table. From the results the water load is 1201 Btu/hr larger than the air

side, which may due to the uncertainty of the air flow rate measurements and the small water

temperature differences. The heat exchange in summer is much better than it in winter condition.

The reason may be the water also absorbs heat from the ambient environment such as the metal of

the indoor box.

Table 14 Indoor Simulation Heat Exchanger Load Calculations – Winter (Cooling)

Indoor Water Side

2I HXZ (F)

2O HXZ (F)

FM.2. HXZ (GPM)

T_dif_w_HXZ(F)

FM.2.HXZ (lb/hr)

Qw_HXZ (BTU/hr) 10 Sample

51.424 52.971 2.009 1.547 1005.680 1555.655

51.383 52.917 2.011 1.534 1006.420 1543.754

51.299 52.808 2.017 1.510 1009.871 1524.538

51.259 52.755 2.016 1.497 1009.049 1510.220

51.218 52.701 2.012 1.483 1007.406 1494.148

51.178 52.650 2.005 1.472 1003.544 1477.073

Page 85: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

75

51.098 52.548 2.014 1.450 1008.392 1462.238

51.056 52.501 2.025 1.445 1013.815 1465.064

51.015 52.455 2.027 1.440 1014.719 1461.047

50.977 52.407 2.012 1.430 1007.406 1440.515 1493.425

… … … … … … …

50.065 50.741 1.988 0.676 995.196 672.704 672.792

Indoor Air Side

Supply Air (F)

Return Air (F)

AF.S.F (CFM)

T_dif_a_HXZ (F)

AF.S.F (lb/hr)

Qa_HXZ (BTU/hr) 10 Sample

92.599 85.537 406.079 7.062 1824.601 3092.445

92.670 85.537 405.857 7.133 1823.605 3121.795

92.564 85.502 405.572 7.062 1822.326 3088.589

92.652 85.555 405.857 7.097 1823.605 3106.277

92.605 85.490 405.667 7.115 1822.752 3112.579

92.717 85.543 405.731 7.174 1823.037 3138.921

92.711 85.531 405.636 7.180 1822.610 3140.771

92.776 85.561 406.300 7.216 1825.596 3161.453

92.670 85.643 405.857 7.026 1823.605 3075.240

92.540 85.543 404.528 6.997 1817.633 3052.278 3109.035

… … … … … … …

96.684 92.559 421.604 4.125 1894.360 1872.710 1874.077

5.2.2.3 Air Handler Unit

Table 15 shows the sample data and the load calculations of the air handler unit in

summer condition. The average values are listed in bold in the last row of the table. The air side

heat exchange is 93% of the water side which is the best heat exchange rate of the three heat

exchangers. The temperatures before and after the fan were 64.5 °F and 67.3 °F which means the

heat increase across the fan was 1259 Btu/hr.

Table 15 AHU Heat Exchanger Load Calculations – Summer (Cooling)

AHU Water Side

1I AHU (F)

1O AHU (F)

FM.1. AHU (GPM)

T_dif_w_AHU(F)

FM.2.AHU (lb/hr)

Qw_AHU (BTU/hr) 10 Sample

59.716 65.529 1.910 5.813 956.131 5558.413

59.695 65.548 1.918 5.852 959.911 5617.686

Page 86: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

76

59.717 65.550 1.904 5.833 953.172 5559.875

59.744 65.557 1.892 5.813 947.174 5505.846

59.763 65.557 1.907 5.793 954.734 5531.118

59.734 65.549 1.903 5.815 952.762 5539.894

59.683 65.546 1.903 5.863 952.679 5585.862

59.609 65.546 1.914 5.937 958.103 5688.390

59.527 65.549 1.900 6.022 951.118 5727.353

59.456 65.546 1.888 6.090 945.284 5756.791 5607.123

… … … … … … …

58.852 64.968 1.940 6.115 971.345 5939.941 5939.722

AHU Air Side

Mixing Air (F)

Supply Air (F)

AF.S.F (CFM)

T_dif_a_AHU (F)

AF.S.F (lb/hr)

Qa_AHU (BTU/hr) 10 Sample

78.948 66.839 414.782 12.109 1863.707 5416.078

78.967 66.863 414.656 12.104 1863.139 5412.384

78.975 66.940 415.478 12.035 1866.836 5392.296

78.975 66.975 416.776 12.000 1872.666 5393.201

78.976 67.212 417.567 11.765 1876.222 5297.621

78.990 67.448 418.707 11.542 1881.341 5211.585

78.987 67.672 419.941 11.315 1886.887 5123.877

78.991 67.879 421.239 11.112 1892.717 5047.638

78.989 67.856 421.239 11.133 1892.717 5057.372

78.989 67.891 421.112 11.097 1892.149 5039.499 5239.155

… … … … … … …

79.762 67.422 416.864 12.340 1873.062 5545.120 5544.619

The winter condition for the air handler unit load calculation is shown in Table 16. The

water side heat exchange is 2634.6 Btu/hr less than the air side. The temperature difference

before and after the fan were 98 °F and 95.7 °F, which made 1045.687 Btu/hr heat loss.

Table 16 AHU Heat Exchanger Load Calculations – Winter (Heating)

AHU Water Side

1I AHU (F)

1O AHU (F)

FM.1. AHU (GPM)

T_dif_w_AHU(F)

FM.2.AHU (lb/hr)

Qw_AHU (BTU/hr) 10 Sample

119.837 113.761 1.844 6.077 923.097 5609.247

119.833 113.761 1.842 6.072 922.111 5598.894

119.828 113.766 1.834 6.062 918.085 5565.255

119.826 113.773 1.833 6.053 917.756 5555.097

Page 87: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

77

119.819 113.779 1.844 6.040 923.097 5575.618

119.817 113.779 1.840 6.038 921.043 5561.160

119.814 113.777 1.838 6.037 920.139 5554.421

119.814 113.775 1.841 6.039 921.618 5565.655

119.812 113.768 1.837 6.044 919.318 5556.613

119.808 113.760 1.833 6.048 917.592 5549.750 5569.171

… … … … … … …

119.538 113.616 1.850 5.922 925.899 5483.185 5486.391

AHU Air Side

Mixing Air (F)

Supply Air (F)

AF.S.F (CFM)

T_dif_a_AHU (F)

AF.S.F (lb/hr)

Qa_AHU (BTU/hr) 10 Sample

75.786 92.599 406.079 16.813 1824.601 7362.373

75.785 92.670 405.857 16.885 1823.605 7389.877

75.798 92.564 405.572 16.766 1822.326 7332.610

75.791 92.652 405.857 16.861 1823.605 7379.579

75.793 92.605 405.667 16.812 1822.752 7354.719

75.785 92.717 405.731 16.932 1823.037 7408.378

75.772 92.711 405.636 16.939 1822.610 7409.619

75.760 92.776 406.300 17.016 1825.596 7455.446

75.750 92.670 405.857 16.920 1823.605 7405.356

75.748 92.540 404.528 16.792 1817.633 7324.990 7382.295

… … … … … … …

78.829 96.684 421.604 17.855 1894.360 8120.275 8120.986

5.2.2.4 Overall System Energy Balance With and Without Outdoor Air

The system energy balance of the air side was verified after the calculation of each heat

exchanger. Table 17 shows the air side balance check results, which indicates that the energy

balance of the system with and without outdoor air.

Table 17 Overall System Energy Balance

HXO (Btu/hr)

AHU (Btu/hr)

HXZ (Btu/hr)

Fan (Btu/hr)

Sum (Btu/hr) Difference

With OA Summer 3040.371 -5545.120 1174.833 1258.698 -71.218 1.30%

With OA Winter -2854.312 8120.275 -1872.710 -1045.687 2347.573 33.8%

Without OA 0 -2058.47 1358.8 826.66 126.99 5.98%

Page 88: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

78

5.3 Characteristics of the System Components

In order to develop the control logic for the system, the characteristics of relative

components, which are the chiller, coils, dampers, control valves and the fan with VFD, should be

determined first. In this thesis, only the control valves of the outdoor and indoor boxes are tested

due to the time limitation.

5.3.1 Outdoor Box

The simulated outdoor air temperature in summer condition can reach 103 °F and can be

as low as 54 °F in winter condition. Figure 53 indicates the flow characteristic of the outdoor hot

water control valve, which is fitted to linear pattern. That is to say the flow capacity increases

linearly with valve travel, which can be used to modeling the control valve.

Figure 53 Installed Valve Characteristics for HXO Hot Water

Figure 54 indicate the installed valve characteristics for HXO chill, which is suited for

quick open characteristic. The valve provides large flow changes in a small percentage of valve

travel.

0

0.5

1

1.5

2

2.5

3

3.5

0% 20% 40% 60% 80% 100%

Flo

w R

ate

(gp

m)

% Open

Installed Valve Characteristic for HXO Hot Water

Measured

Linear Trendline

Page 89: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

79

Figure 54 Installed Valve Characteristic for HXO Chill

After determined the valve characteristic, control logics can be programmed and applied

on the valve. PID control was the simplest and easiest control strategy that can be tested first.

Figure 55 shows the open loop tuning process of the hot water valve.

1. Develop the PID control logic in LabVIEW using the PID control tool box

2. Set the controller in manual mode and the valve is fully close

3. Make a step change in output from 2v to 8v

4. Wait until the process variable to settle and record the process in excel

5. Determine the parameters will be used in the PID control:

Td – Deadtime in minutes = 1.33

T – Time constant in minutes = 3.67

K - Process Gain =

= 1.71

6. Calculate the PID value

0

0.5

1

1.5

2

2.5

0% 20% 40% 60% 80% 100%

Flo

w R

ate

(gp

m)

% Open

Installed Valve Characteristic for HXO Chill

Flow Rate (gpm)

Poly. 3 Trendline

Page 90: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

80

PB =

= 49.58

Reset = 2.00 Td = 2.66

Rate = 0.50 Td = 0.665

Figure 55 Output and Process Variable Chart

5.3.2 Indoor Box

The flow characteristic for the indoor hot water control valve is shown in Figure 55. It

can be treated as equal percentage pattern, which the flow rate increases exponentially with valve

trim travel. Besides, equal increments of valve travel produce equal percentage changes in the Cv,

which is 1.2 for this valve.

Page 91: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

81

Figure 56 Installed Valve Characteristic for HXZ Hot Water

Figure 56 indicate the installed valve characteristics for HXZ chill, which is suited for

quick open characteristic. The valve provides large flow changes in a small percentage of valve

travel.

Figure 57 Installed Valve Characteristic for HXZ Chill

0

0.5

1

1.5

2

2.5

3

3.5

0% 20% 40% 60% 80% 100%

Flo

w R

ate

(gp

m)

% Open

Installed Valve Characteristic for HXZ Hot Water

Flow Rate (gpm)

0

0.5

1

1.5

2

2.5

0% 20% 40% 60% 80% 100%

Flo

w R

ate

(gp

m)

% Open

Installed Valve Characteristic for HXZ Chill

Flow Rate (gpm)

Poly. 3 Trendline

Page 92: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

82

Chapter 6

ANALYSIS AND DISCUSSION

The experimental HVAC system construction, performance identification and

components characteristics were indicated in chapter 4 and 5. This chapter will evaluate the

capability and limitation of the experimental HVAC system and discuss the system performance.

6.1 Experimental HVAC System Design vs. Actual Operation

The system has the capability of perform summer and winter operations as described in

the objectives and it can reach a steady state after certain minutes of running. The overall energy

balance of the air side in summer condition is within 2%, however the subsystem heat exchangers

load balances are not as good as expected. There could be several reasons that cause the

differences between the water side load and the air side load:

The facilities efficiency is not as good as expected

The uncertainties of the system sensors, for example, the water temperature

differences across the heat exchangers are too close to be identified.

Heat loss and heat gain through the ambient environment

The latent load is not calculated during those tests

The designed outdoor air temperature in winter is 47.6 °F but the actual temperature can

only reach 54 °F. The reason for the difference may due to the size of the heat exchanger

efficiency and/or the heat loss through the ambient air.

6.2 Measurement Uncertainty and Sensor Calibration

Since there are lots of sensors in this system, the calibration of each sensor is very

important. As is known, air flow rate is more difficult to measure than the water flow rate, which

Page 93: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

83

due to the uncertainty of the air distribution in the ducts. In this thesis, the air flow stations were

calibrated using an anemometer and multiple tests were conducted to ensure the calibration

results. The water temperature RTD supposed to be the most reliable sensors in the project but it

turned out that the sensor is more easily to damage from the cable and the RTD module used to

record the values should be wired carefully in the right position.

6.3 System Control Capability

The control facilities of this experimental system are working properly and have the

ability of certain amount of control. The flow characteristics of the indoor and outdoor box

control valves provide good fits to standard control valve flow characteristic, such as linear, equal

percentage and quick open. However, the control valves of the air handler unit are floating valves

which have less control capabilities and need more effort to develop the control logics. Besides,

the circulating pumps of the systems are displacement pumps, which use bypass valves to adjust

the flow through each heat exchanger. This means less control capabilities compare to the

centrifugal pumps. The other limitation caused by the displacement pumps is the relationship

between the water flow rates in the same loop, for example, if reduce the flow rate in the outdoor

heat exchanger, the indoor flow rate will increase.

Page 94: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

84

Chapter 7

CONTRIBUTIONS AND RECOMMENDATIONS

7.1 Contribution to HVAC Control Test Facility

There are several HVAC control test beds in the United States but few of them have both

simulated indoor and outdoor air chambers, which make it more flexible for the amount of

outdoor air variations and the indoor load simulations. Besides, the experimental system has

chilled water storage capability which can model thermal storage for commercial buildings.

The integrated software environment built in LabVIEW for data acquisition, system

operation and control development is another significant improvement. All the control models are

compatible with LabVIEW and easily to configured and monitored.

7.2 Future Work Recommendations

In addition to the achievements in this thesis, there are still opportunities for further

system performance improvement and control development.

There are humidity sensors can be used to measure the humidity of the simulated outdoor

air and the supply air. Besides, the power measurement suit allows energy audit of the main

facilities such as the chiller, heater, fan VFD and dampers. These data can be applied to improve

system energy savings.

More tests should be conducted under different load situations and the energy balance can

be identified after each test. This will provide plenty of information for indicating the heat

exchange across the coils in each chamber.

System simulation and modeling can be conducted. The characteristics of components

such as the damper and VFD are important for component modeling and simulation. After the

Page 95: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

85

simulation of overall system, the performances of simulated system and the actual system can be

compared. In addition, the methodology of HVAC system simulation and modeling can be

indicated using the simulated and actual data.

Page 96: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

86

Appendix

LABVIEW PROGRAMMING

Figure 58 Data Logging Main VI

Figure 59 Chilled Water Storage Control VI

Page 97: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

87

Figure 60 System Monitor VI

Page 98: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

88

Figure 61 Summer Operation Main VI

Page 99: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

89

Figure 62 Summer Monitor VI

Page 100: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

90

Figure 63 Winter Operation VI

Page 101: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

91

REFERENCES

Ahn, B.-C., and Song, J.-Y. (2010). “Control characteristics and heating performance analysis of

automatic thermostatic valves for radiant slab heating system in residential apartments.”

Energy, 35(4), 1615-1624.

Anderson, M. L. (2001). “MIMO ROBUST CONTROL FOR HEATING VENTILATING

ANDAIR CONDITIONING (HVAC) SYSTEMS.”

Anderson, M., Buehner, M., Young, P., Hittle, D., Anderson, C., Tu, J., and Hodgson, D. (2007).

“An experimental system for advanced heating, ventilating and air conditioning (HVAC)

control.” Energy and Buildings, 39(2), 136-147.

ASHRAE. (1996). Reference Guide fot Dynamic Models of HVAC Equipment.

ASHRAE. (2009). Fundimentals.

Babuška, R., and Verbruggen, H. B. (1996). “An overview of fuzzy modeling for control.”

Control Engineering Practice, 4(11), 1593-1606.

BEEL at SU. (2010). “BUILDING ENERGY AND ENVIRONMENTAL SYSTEMS

LABORATORY (BEESL).” <http://beesl.syr.edu/facilities.htm> (Dec. 3, 2011).

Bing Dong. (2010). “Non-linear optimal controller design for building HVAC systems.” 2010

IEEE International Conference on Control Applications (CCA), IEEE, 210-215.

Clarke, J. ., Cockroft, J., Conner, S., Hand, J. ., Kelly, N. ., Moore, R., O’Brien, T., and Strachan,

P. (2002). “Simulation-assisted control in building energy management systems.” Energy

and Buildings, 34(9), 933-940.

“EnergyPlus: Energy simulation program.” (2000). ASHRAE Journal, 42(4), 49.

Harrold, M. V., and Lush, D. M. (1988). “Automatic controls in building services.” Electric

Power Applications, IEE Proceedings B, 135(3), 105-133.

Page 102: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

92

House, J. M., and Smith, T. F. (1995). “Optimal control of building and HVAC systems.”

American Control Conference, 1995. Proceedings of the, IEEE, 4326-4330 vol.6.

Iowa Energy Center. (2010). Iowa Energy Center Energy Resource Station Technical Description.

Komareji, M., Stoustrup, J., Rasmussen, H., Bidstrup, N., Svendsen, P., and Nielsen, F. (2008).

“Optimal model-based control in HVAC systems.” 2008 American Control Conference

(ACC ’08), 11-13 June 2008, 2008 American Control Conference (ACC ’08), IEEE,

Piscataway, NJ, USA, 1443-8.

Komareji, M., Stoustrup, J., Rasmussen, H., Bidstrup, N., Svendsen, P., and Nielsen, F. (2009).

“Simplified optimal control in HVAC systems.” 2009 IEEE International Conference on

Control Applications (CCA), 8-10 July 2009, 2009 IEEE International Conference on

Control Applications (CCA), IEEE, Piscataway, NJ, USA, 1033-8.

LBNL. (2011). “Modelica Buildings Library.”

<http://simulationresearch.lbl.gov/modelica/FrontPage> (Dec. 9, 2011).

Liew, Y.-L. (2003). “Remote control of heating, ventilating, and air conditioning system with

LabVIEW - OpenThesis.” <http://www.openthesis.org/documents/Remote-control-

heating-ventilating-air-118524.html> (Dec. 2, 2011).

McDowall, R. (2009). Fundamentals of HVAC Control Systems. Elsevier.

Ming-Li Chiang, and Li-Chen Fu. (2006). “Adaptive and Robust Control for Nonlinear HVAC

System.” IEEE International Conference on Systems, Man and Cybernetics, 2006.

SMC ’06, IEEE, 4982-4987.

Mirinejad, H., Sadati, S. H., Ghasemian, M., and Torab, H. (2008). “Control Techniques in

Heating, Ventilating and Air Conditioning (HVAC) Systems.” Journal of Computer

Sciences, J. Comput. Sci. (USA), 4(9), 777-83.

Nizet, J. L., Lecomte, J., and Litt, F. X. (1984). Optimal control applied to air conditioning in

buildings.

Page 103: METHODOLOGY FOR DESIGN, CALIBRATION, SYSTEM …

93

Platt, G., Li, J., Li, R., Poulton, G., James, G., and Wall, J. (2010). “Adaptive HVAC zone

modeling for sustainable buildings.” Energy and Buildings, 42(4), 412-421.

van Schijndel, A. W. M. (2003). “Advanced HVAC modeling with FemLab/Simulink/MatLab.”

Building Services Engineering Research & Technology, Build. Serv. Eng. Res. Technol.

(UK), 24(4), 289-300.

Semsar, E., Yazdanpanah, M. J., and Lucas, C. (2003). “Nonlinear control and disturbance

decoupling of an HVAC system via feedback linearization and back-stepping.”

Proceedings of 2003 IEEE Conference on Control Applications, 2003. CCA 2003, IEEE,

646- 650 vol.1.

Singh, J., Singh, N., and Sharma, J. K. (2006). “Fuzzy modeling and control of HVAC systems -

a review.” Journal of Scientific and Industrial Research, J. Sci. Ind. Res. (India), 65(6),

470-6.

Swanson, K. (1993). “Direct Digital Control- A Tool for Energy Management of HVAC Systems.”

Ya-Gang Wang, Zhi-Gang Shi, and Wen-Jian Cai. (2001). “PID autotuner and its application in

HVAC systems.” American Control Conference, 2001. Proceedings of the 2001, IEEE,

2192-2196 vol.3.

Ying, H., Siler, W., and Buckley, J. J. (1990). “Fuzzy control theory: A nonlinear case.”

Automatica, 26(3), 513-520.