Upload
vuongnga
View
270
Download
6
Embed Size (px)
Citation preview
METHOD STATEMENT Sika®Drain-850 Geo 3/6/2016 / 1 / SIKA LTD, UK / ALEX BURMAN
WATERPROOFING
Method Statement UK
Sika®Drain-850 Geo Waterproofing
3/6/2016, 1
2/8
TABLE OF CONTENTS 1 Scope 3
2 System Description 3
2.1 Uses 3 2.2 Characteristics / Advantages 3 2.3 References 3 2.4 Limitations 3
3 Product Information 3
3.1 Appearance / Colour 3 3.2 Shelf Life 4 3.3 Storage Conditions 4 3.4 Thickness 4 3.5 Unit weight 4 3.6 Packaging 4
4 Installation 5
4.1 General 5 4.2 Lapping 5
4.2.1 Lap at edge of roll (Flat Edge) 5
4.2.2 Lap on a cut edge (No Flat Edge) 6
4.3 Accessories 6 4.4 Fixing 7 4.5 Corners and Edges 7 4.6 Drainage Pipe 7
5 Legal Note 8
Method Statement UK
Sika®Drain-850 Geo Waterproofing
3/6/2016, 1
3/8
1 SCOPE
This method statement describes the step by step procedure for installing Sika®Drain-850 Geo
2 SYSTEM DESCRIPTION
Sika®Drain-850 Geo is a heavy duty drainage and protection sheet produced from high density polyethylene
(HDPE) with dimples 10 mm high and a filtration layer of polypropylene (PP) geotextile bonded on the top.
2.1 USES
As a protection and drainage sheet for preformed sheet membrane waterproofing systems, liquid applied
membranes and with the Sika® White Box concept for waterproofing retaining walls and heavy duty
roofs/podiums.
2.2 CHARACTERISTICS / ADVANTAGES
High drainage capacity
High mechanical/impact resistance
Integral filtration layer
Resistant to all natural aggressive mediums in ground water and soil
Suitable for contact with soft water (aggressive to concrete)
Can be installed on damp and wet substrates
Sika®Drain-850 Geo forms a drainage channel in the space between structural elements and
backfill/soil/substrate to allow water to be drained away and, when linked to a maintainable land drain,
will prevent hydrostatic pressure acting against the structure
2.3 REFERENCES
EN 13252
2.4 LIMITATIONS
Sika®Drain-850 Geo is not resistant against exposure to permanent weathering and UV-light. When used in combination with PVC membranes, a separation (geotextile) must be used between the materials. Maximum installation depth: 10m.
3 PRODUCT INFORMATION
3.1 APPEARANCE / COLOUR
Black HDPE sheet with 10mm deep dimples and a black geotextile filtration layer bonded on the top.
Method Statement UK
Sika®Drain-850 Geo Waterproofing
3/6/2016, 1
4/8
3.2 SHELF LIFE
The product does not expire during correct storage.
3.3 STORAGE CONDITIONS
Rolls must be stored in their original packaging, in cool and dry conditions. They must be protected from direct sunlight, rain, snow and ice, etc.
3.4 THICKNESS
10.0 (+/- 1.0) mm (EN ISO 9863-1)
3.5 UNIT WEIGHT
850 (+/- 5%) g/m2 (Dimpled Sheet) (EN 9864)
125 (+/- 20%) g/m2 (Geotextile)
3.6 PACKAGING
Roll size: 2.44 m x 12.50 m Weight: 975 g/m
2
Roll weight: ~30kg Consideration: Sika®Drain-850 Geo is delivered with 6 rolls packed vertically on a pallet (L x W x H): 1150mm x 850mm x 2550mm. Special offloading and storage space should be arranged to handle this height unit.
6ft (1.8m)
8ft (2.5m)
Method Statement UK
Sika®Drain-850 Geo Waterproofing
3/6/2016, 1
5/8
4 INSTALLATION
4.1 GENERAL
If the installation depth is less than 2.44m (height of the rolls), the Sika®Drain-850 Geo may be rolled out
horizontally along the wall and fastened on the top. This method reduces the number of vertical laps required.
If the installation depth is greater than 2.44m (height of the rolls), the Sika®Drain-850 Geo may be rolled out
starting from the top to the bottom.
4.2 LAPPING
Adjacent sheets should overlap by a minimum of 60mm.
4.2.1 LAP AT EDGE OF ROLL (FLAT EDGE) The edges of each roll have a flat area with loose geotextile. One side is 60mm wide; the other is 45mm wide.
The lap is created by:
Wider 60mm Flat Edge
Narrower 45mm Flat Edge
1. Fold back the loose fleece on the wider (60mm) flat edge
2. Add a strip of double-sided tape (e.g. SikaProof FixTape-50) along the flat section
3. Lap the narrower flat edge onto the tape and press firmly
4. Double-sided tape, or similar, may be required to hold the loose fleece in place
5. Fold the loose fleece over and press firmly
Method Statement UK
Sika®Drain-850 Geo Waterproofing
3/6/2016, 1
6/8
4.2.2 LAP ON A CUT EDGE (NO FLAT EDGE) If you need to create a lap on the edge of a roll that has been cut, there will be no flat edge to connect to, in which
case the recommended solution is as follows.
Note: Single-sided tapes can be used for sealing the laps as an alternative to the process above using double-sided
tape. Sika CD corner seal tape (115330) or Sika CD plaster tape (115331) single sided tapes can close the geotextile
at the laps.
4.3 ACCESSORIES
Description Dimensions Material Code Image
SikaProof FixTape-50
20mm x 20m 424701
Sika CD corner seal
10m 115330
Sika CD plaster tape
25m 115331
1. Peel back the geotxtile from the edge of one sheet (3 dimples is
approximately 60mm)
2. Lap the other sheet over the top, so that the dimples fit
together
3. Add a strip of double-sided tape over the fleece
4. Fold the loose fleece back over the lap and press into the tape
Method Statement UK
Sika®Drain-850 Geo Waterproofing
3/6/2016, 1
7/8
4.4 FIXING
The product can be fixed along the top edge (above the waterproofing membrane) and
draped down the concrete face. Fix along the top with a nail and washer system every
250mm to prevent sagging or pulling at the nails.
Strips of double-sided butyl tape (such as SikaProof FixTape-50) can be used if
additional fixings are required across the main area of the sheet.
Do not nail through the main area of the sheet if placed against a waterproofing
membrane.
Sheets may also be temporarily propped to provide support whilst backfill is placed,
with props removed once backfill is deep enough to provide support.
Single-sided tape or a separate piece of geotextile should be used to close the top
termination edge to prevent material entry.
4.5 CORNERS AND EDGES
Care should be taken when forming Sika®Drain-850 Geo around sharp corners or edges to prevent the flow
channel becoming blocked.
For external corners, the geotextile may need to be cut and a tape applied to seal the geotextile once the sheet
has been folded. For internal folds no special treatment is required.
4.6 DRAINAGE PIPE
To continue the geotextile around the drainage pipe, peel back sufficient geotextile from the sheet and form over
the drainage pipe. Any excess dimple sheet can be cut back as required.
It is recommended to cover the pipe with crushed stones before covering with the geotextile. See the picture
about a typical installation.
Method Statement UK
Sika®Drain-850 Geo Waterproofing
3/6/2016, 1
8/8
Figure 1 - Typical installation of Sika®Drain-850 Geo with SikaProof
5 LEGAL NOTE
The information, and, in particular, the recommendations relating to the application and end-use of Sika products,
are given in good faith based on Sika's current knowledge and experience of the products when properly stored,
handled and applied under normal conditions in accordance with Sika’s recommendations. in practice, the
differences in materials, substrates and actual site conditions are such that no warranty in respect of
merchantability or of fitness for a particular purpose, nor any liability arising out of any legal relationship
whatsoever, can be inferred either from this information, or from any written recommendations, or from any
other advice offered. The user of the product must test the products suitability for the intended application and
purpose. Sika reserves the right to change the properties of its products. The proprietary rights of third parties
must be observed. All orders are accepted subject to our current terms of sale and delivery. Users must always
refer to the most recent issue of the local Product Data Sheet for the product concerned, copies of which will be
supplied on request.
FOR MORE SIKA®DRAIN-850 GEO INFORMATION: Please visit the Sika waterproofing website at www.sikawaterproofing.co.uk
Sika Ltd, UK
Waterproofing
Version given by
Alex Burman
Phone:
Fax:
Mail:
© 2
01
3 Si
ka S
erv
ices
AG
/ N
r 85
0 7
3 0
5
SIKA METAL WATERBAR