Detailed, Grouped by Each Number Submittal Transmittal LC3 (R-15-085-BF-0) Project # RUH-CP-1502 Tel: Fax: Date: 3/15/2016 Reference Number: 0514 Transmitted To: Transmitted By: Paul Teague Hadi Omar Harb SSEM AECOM P.O. Box 6341 Al Rashid Tower, 5th Floor Al Ma'athar Street 11442 Riyadh Tel: 4625511 Fax: 4627804 P.O. Box 58806 4 Floor, Tower 4, Tatweer Tower 11515 Riyadh Tel: Fax: Submittal Package No Description Due Date Package Action Qty Reviewed - Exceptions Noted Method Statement for Shoring Work 0119 - Special Conditions - 1 1 Transmitted For Delivered Via Tracking Number Hand Action Notes Item Action Items Description Qty 001 Method Statement for Shoring Work Reviewed - Exceptions Noted 1 Contact Name Copies Notes Company Name Cc: Remarks Reviewed Exceptions Noted, Resubmission Required. 1. Please see attached. Best Regards, Signature Signed Date Prolog Converge Printed on: 3/16/2016 Prolog KKIA Page 1

Method Statement for Shoring Work

Embed Size (px)

DESCRIPTION

Method Statement for Shoring Work

Citation preview

Page 1: Method Statement for Shoring Work

Detailed, Grouped by Each Number

Submittal Transmittal

LC3 (R-15-085-BF-0) Project # RUH-CP-1502

Tel: Fax:

Date: 3/15/2016 Reference Number: 0514

Transmitted To: Transmitted By: Paul TeagueHadi Omar Harb

SSEM AECOM

P.O. Box 6341

Al Rashid Tower, 5th Floor

Al Ma'athar Street

11442 Riyadh

Tel: 4625511

Fax: 4627804

P.O. Box 58806

4 Floor, Tower 4, Tatweer Tower

11515 Riyadh

Tel:

Fax:

Submittal Package No Description Due Date Package ActionQty

Reviewed -

Exceptions Noted

Method Statement for Shoring Work0119 - Special Conditions - 11

Transmitted For Delivered Via Tracking Number

HandAction

Notes Item ActionItems DescriptionQty

001 Method Statement for Shoring

Work

Reviewed - Exceptions

Noted

1

Contact Name Copies NotesCompany NameCc:

Remarks

Reviewed Exceptions Noted, Resubmission Required.

1. Please see attached.

Best Regards,

Signature Signed Date

Prolog Converge Printed on: 3/16/2016 Prolog KKIA Page 1

Page 2: Method Statement for Shoring Work

KINGDOM OF SAUDI ARABIA GENERAL AUTHORITY OF CIVIL AVIATION

CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0 Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

METHOD STATEMENT FOR SHORING WORK

Project Quality Manager : Project Manager :

ENGR. Amr Ibrahim Metwally ENGR. HADI OMAR HARB

Page 1 of 23

Page 3: Method Statement for Shoring Work

KINGDOM OF SAUDI ARABIA GENERAL AUTHORITY OF CIVIL AVIATION

CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0 Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

Table of Contents

1.0 Purpose ………………………………………………………………………………….. 03

2.0 Scope …………………………………………………………………………………….. 03

3.0 References and Standards …………………………………………………………… 03

4.0 Permits and Licenses …………………………………………………………………. 03

5.0 Equipment ………………………………………………………………………………..04

6.0 PPE Materials …………………………………………………………………………… 04

7.0 Resources and Manpower ……………………………………………………………. 04

8.0 Responsibilities of Key Personnel ………………………………………………….. 05

9.0 Methodology- Shoring Works ……………………………………………………….. 06

10.0 Health and Safety ………………………………………………………………………. 08

Appendices

Appendix 1.0- Job Risk Assessment ………………………………………………..09

Appendix 2.0- Related ITPs ……………………………………………………………11

Appendix 3.0- Checklist ………………………………………………………………. 12

Appendix 4.0- Pro forma Work Permit ………………………………………………23

Page 2 of 23

Page 4: Method Statement for Shoring Work

KINGDOM OF SAUDI ARABIA GENERAL AUTHORITY OF CIVIL AVIATION

CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0 Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

1.0 PURPOSE

The purpose of this method statement is to provide description of procedure and method for the construction and installation of shoring works when working in areas of loose and unstable soil condition. Also included are the necessary procedure to ensure health and safety of employees with the requirement stipulated in the Contract Documents, as well as those in Saudi Construction Specifications (ASTM and SASO-ISO)

2.0 SCOPE

This method statement covers the analysis, design and implementation of shoring structures to support loose soil during excavation works for the foundation of LC3 Building and the different trenches for underground utilities as part of the contract.

3.0 REFERENCES AND STANDARDS

Excavation works will be executed in accordance to the following references & standards:

a. Saudi Arabia Construction Specification.

b. Employers requirements, Materials Specification

c. Geotechnical Report, Material and Workmanship Specifications for Earthworks.

d. Master Plan.

e. Approved with Comments (AWC) construction drawings.

f. Approved ITP for excavation works.

g. SSEM HSE plan and Job Safety Analysis.

h. SSEM excavation works procedure and OHSA standards.

i. Approved Quality Control & Quality Assurance.

4.0 PERMITS AND LICENCES

a. Work Permit

b. Excavation Permit

c. Entrance Permit

d. Barricade Permit

e. Equipment Permit

Page 3 of 23

GalceranR
Callout
other work related permits should be identified by the contractor.
AzaresA
Text Box
"ALL" work related shall be define and identified by the contractor. Then it shall be submitted and secure an approval from the Authority Having the Jurisdiction prior to any work implementation on-site.
AzaresA
Text Box
Contractor shall provide the following: 1. Specific code and standards to be used for this for the above mentioned works. 2. Where are supposed to be survey and geotechnical report which are part of the due diligence of the contractor? 3.Contractor to provide the copy of the approval of all mentioned documents that is already been approved. 4. Contractor shall provide reference number of the SSEM HSE plan aubmitted or approved. 5. Contractor shall provide copy of all the drawings submiital with ENGINEER approval and comments. 6. Contractor shall provide copy of submitted ITP and its approval. 7. Contractor shall provide the copy of the mentioned "Master Plan" All the above comments shall be provided by the contractor with the copy of the approval before it can be used as a reference and standard documents.
Page 5: Method Statement for Shoring Work

KINGDOM OF SAUDI ARABIA GENERAL AUTHORITY OF CIVIL AVIATION

CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0 Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

5.0 EQUIPMENT

The contractor (SSEM) will provide the following equipment in the implementation of Shoring activities alongside excavation works.

Type of Equipment Units (No.) Excavator 1 Crow Bars 6 Steel mallet, 2 kg. 2 Carpenter’s Basic Tools 1 lot

Table I. Equipment Intended for Excavation and Shoring Works.

6.0 PPE MATERIALS

Personal Protective Equipment (PPE) should be provided in order to perform all works in accordance with the safety procedures and taking into consideration the importance of proper preventive measures to ensure safety in the performance of work.

Type of Equipment Safety Helmet Safety Boots Safety Glasses Safety Masks Coveralls High Visibility Vests Hand Gloves

Table II. Personal Protective Equipment Intended for Excavation

7.0 RESOURCES AND MANPOWER

The workforce including foremen and technicians are all with sufficient qualification and experience. Equipment operators possesses applicable party certificates wherever applicable/relevant.

Sub-contractor will be employed if there is need to catch up shortfalls or to accelerate progress. List of subcontractor manpower will be made available once there company is prequalified/accepted by the Engineer.

Page 4 of 23

GalceranR
Callout
and Safety Equipment
GalceranR
Text Box
Any person required to undertake work associated with shoring works is accountable for: Complying with the requirements of risk assessment management plan, any permits for work Using personal protective equipment and safety equipment provided Assisting in assessing risk Attending training when required. Only undertaking tasks they are competent to undertake (or are in training to undertake with appropriate supervision) Following reasonable instructions related to work associated with shoring
Page 6: Method Statement for Shoring Work

KINGDOM OF SAUDI ARABIA GENERAL AUTHORITY OF CIVIL AVIATION

CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0 Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

CONTRACTOR (SSEM) Construction Manager Site Engineer Safety Engineer Equipment Operators Carpenters Laborers First Aiders

Table III. Manpower for Shoring Works

8.0 RESPONSIBILITIES OF KEY PERSONNEL

8.1 Construction Manager

The Construction Manager must mobilized the required materials, equipment and manpower to do the job as required, and will monitor the activities. He must take note existing shortfall and problems and discuss the same with the Project Manager. Corrective solutions must be identified and applied to compensate for the shortfalls.

8.2 QA/QC Engineer

The QA/QC Engineer will be responsible for the quality aspects of the works. He will assure that the QA and QC plan will be implemented. The required SIR, WIR shall be submitted to The Engineer. All required procedure in shoring works shall be followed to have a safe working condition and quality requirements attained. He will proactively coordinate with the site engineer and issue appropriate internal SOR when he see that performance of works deviate from the approved.

8.3 Site Engineer

The Site Engineer will be in charge for the supervision and implementation of all activities as required in the specifications and drawing, especially in giving orders to Site foremen. Site engineer is also in charge for the preparation and filing of reports.

8.4 Site Foreman

The Site Foreman will be in charge for the supervision and implementation of various steps in shoring works, as instructed by the Site engineer. The Site Foreman shall also keep record of all work schedules, work production and daily safety issues.

Page 5 of 23

AzaresA
Callout
change to "shall"
KakilalaD
Arrow
KakilalaD
Strike-Out
KakilalaD
Strike-Out
KakilalaD
Strike-Out
KakilalaD
Arrow
AzaresA
Text Box
Contractor shall include in the QA/QC Engineer scope " That workmanship shall not compromise the health and safety of the worker."
AzaresA
Text Box
Contractor shall include to the Site Engineer responsibility the submission and secure the approval of all site work related permits. Prior to the implementation of works on-site.
AzaresA
Text Box
change to "shall"
KakilalaD
Arrow
KakilalaD
Strike-Out
Page 7: Method Statement for Shoring Work

KINGDOM OF SAUDI ARABIA GENERAL AUTHORITY OF CIVIL AVIATION

CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0 Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

8.5 Safety Engineer

Conduct the safety induction course to all personnel involved in the work.

Monitor and supervise the risk assessment.

Ensure that necessary Permit to Work is available.

Ensure that the project’s method statement and risk assessment are understood and understood, complied and applied in the worksite.

Ensure that all workers are provided with sufficient information regarding workplace hazards and planned control measures.

8.6 Safety Officer

Supervision of equipment handling, oversee the installation of shoring.

Ensure that relevant work permit is secured prior to start of work.

Ensure that equipment is operational and certified.

Ensure that all drivers/operators are qualified to operate the machines/equipment.

Regular inspection and maintenance of the equipment.

Perform other duties as instructed by the safety engineer.

8.7 Professional Engineer (Deep Excavation Shoring)

The Professional Engineer will be in charge for the design in compliance with project specification and standards.

The engineer may designate an experienced person on the worksite to conduct a regular inspection.

The designated person should adhere his comments (if any) to the contractor for immediate rectification prior for final inspection. The engineer then issues an inspection report and certification.

9.0 METHODOLOGY-SHORING WORKS

9.1 Sequence of Work

9.1.1 Design of proposed shoring, if needed against load to be supported.

9.1.2 Fabricate shoring, if needed according to drawing, height of excavation.

9.1.3 For trench excavation which needs shoring, install shoring at side of once initial excavation starts.

Page 6 of 23

GalceranR
Strike-Out
GalceranR
Strike-Out
AzaresA
Callout
shall
KakilalaD
Strike-Out
Page 8: Method Statement for Shoring Work

KINGDOM OF SAUDI ARABIA GENERAL AUTHORITY OF CIVIL AVIATION

CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0 Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

9.1.3.1 Push the shoring down as the excavation become deeper.

9.1.3.2 Once the desired depth is attained stabilize the side slope to provide collapse.

9.1.4 For open excavation, fix the shoring if required once the desired depth is reached.

9.1.5 Proceed with construction when the side slope has been stabilized or if needed install the shoring.

9.1.6 After completion of work, slowly remove the shoring and proceed with backfilling work.

9.2 The hazards posed to workers working in excavation pit and trenches are potentially fatal. Excavation failures can, however, be largely avoided by installing an adequately designed support system. No worker should be permitted to work in an unsupported trench if the existing soil structure is loose. Other precautions include the avoidance of external load from construction vehicles and excavated spoil being stockpiled too close to the trench.

9.3 The use of adequate shoring, benching and side sloping is essential to control the risk of a collapse or failure of open excavation. Construction of shoring system should consider the following:

The size and strength of the component members of the shoring

Existing and changing ground conditions

The loads and types of ground or soil conditions to be shored

Static loads near excavation, e.g. spoil pile, buildings and structures

Dynamic loads near excavation, e.g. traffic and excavation equipment

Ground vibration, e.g. heavy traffic, mobile plant, and other activities.

Difficulties or risks that other services may pose i.e. existing or proposed underground services

Location of utility services

Safety during installation and removal.

9.4 Shoring of trench excavation should be constructed and implemented strictly in accordance with the design and contract specifications.

9.4.1 In ground composed of moderately firm to firm soil, vertical trench sides may stand unsupported for a considerable period of time, and hence installing of shoring may be disregarded. However, moderate side slope must be provided to make the excavation wall stable.

Page 7 of 23

GalceranR
Highlight
Page 9: Method Statement for Shoring Work

KINGDOM OF SAUDI ARABIA GENERAL AUTHORITY OF CIVIL AVIATION

CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0 Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

9.4.2 When the ground condition is poor and has little or no “free-standing” time, shoring/trench wall support should be installed in such a way that the trench wall will not collapse.

9.4.3 After excavation works has been completed, proceed with next activities while checking the integrity of shoring from time to time.

9.4.4 Where existing services crossing a trench or excavation line are encountered, timber board support should be provided the services to prevent possible collapse or damage.

9.4.5 After the works are completed, the support system will be extracted / dismantled in the reverse order of its installation. Persons performing the work in the excavation will not work outside the protection of the ground support system

10.0 HEALTH AND SAFETY

During the process of shoring and excavation works, the necessary welfare facilities shall be provided at the project site. The workers shall be provided with safe drinking water, toilets, place to eat their food and place to store their clothes.

Tower lights will be used during night time works and is essential for the safety of workers, the equipment and the proper execution of work. Barriers around excavation area shall be installed.

10.1 Issues

The HSE Engineer has the responsibility for providing help advice to the supervisor who is responsible for the work safety.

No one shall enter an excavation unless it has been inspected and considered a safe place to work in by immediate supervisor.

Ensure that there is safe access to and from all excavation.

Beware of slipping when using ladders in wet conditions.

All employees must wear the appropriate personnel protective equipment.

No person is allowed under loads handled by power shovels/excavators. Banks men must be assigned to monitor the activities.

Prior to start shoring/excavation, it must be determined whether underground utilities i.e., electric, telephone, sewer lines, etc. will be encountered.

Proper slopes to be provided at sides of excavation.

Provide protective barriers, shield systems complying with applicable standards.

Support of shoring must be periodically checked to assure integrity of the system.

Page 8 of 23

GalceranR
Callout
frequency of inspections
GalceranR
Text Box
Emergency and rescue procedures or strategy incident or accidents related to shoring works. monitoring and evaluation Risk Assessment Risk control
AzaresA
Text Box
All work related training and safety induction for this specific work shall be identified and define in this document by the contractor.
Page 10: Method Statement for Shoring Work

KINGDOM OF SAUDI ARABIA GENERAL AUTHORITY OF CIVIL AVIATION

CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0 Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

JOB RISK ASSESSMENT:

Page 9 of 23

AzaresA
Text Box
Contractor shall identify and define all the work related risk on the shorin works.
Page 11: Method Statement for Shoring Work

KINGDOM OF SAUDI ARABIA GENERAL AUTHORITY OF CIVIL AVIATION

CONSTRUCTION OF LOAD CENTER -3

METHOD STATEMENT FOR SHORING

First Rev. A B CONTRACT #: R-15-085-BF-0 Issue Date: 18.01.16 20.02.2016 DOCUMENT NUMBER: LC3.KKIA-UN-MSM-GEN-CV-0020-B

Page 10 of 23

Page 12: Method Statement for Shoring Work

CONSTRUCTION OF LOAD CENTER 3 (LC-3) AT KING KHALED INTERNATIONAL AIRPORT (KKIA)

INSPECTION TEST PLAN FOR CIVIL WORKS CONTRACTOR: SAUDI SERVICES ELECTRO MECHANICAL WORKS. CO. (SSEM) (Close Joint Stock Company) ITP Ref. No.: ISSUANCE: 01 CONTRACT NO.: R-15-085-BF-0 Sec No.: REVISION: 00

TITLE: CIVIL WORKS Sec Title.: Date: October 2015

Activity

No. Activity Description

Inspection / Test Requirements Reference Documentation Method of

Verification Demonstrated Evidence

Report/Checklist Test or Inspection Performed Stage / Frequency Test Required Code/Spec/Etc. Acceptance Criteria SSEM AECOM

ABBREVIATIONS: N/A – NOT APPLICABLE W- WITNESS PONT S – SURVEILLANCE AECOM- Consultant

Note: H – HOLD POINT RR – REVIEW OF REPORT SSEM- Contractor

Page 1 of 1

2.0 EXCAVATION AND BACKFILLING

2.1 EXCAVATION

2.1.1 Availability of permit Verification of Permit Prior to Proceed for Excavation SSEM CHECK Tender Requirements Valid Permit H R Checklist Form IC-C-002

2.1.2 Location and Layout of area to be excavated Check Approved Survey Data Layout

Prior to Proceed for Excavation SSEM CHECK Technical Specification Approved Construction

Drawings H W Checklist Form IC-C-002

2.1.3 Checking and grading and elevation for conformity to drawing Visual Inspection/Survey Prior to Proceed for

Excavation SSEM CHECK Technical Specification Civil Works

Approved Construction Drawings H W Checklist Form IC-C-002

2.1.4 Check the excavated area for freedom from extraneous materials and water Visual Inspection Prior to Proceed for

Excavation SSEM CHECK Technical Specification Civil Works Project Specification W S Checklist Form IC-C-002

2.1.5 Disposal of excavated materials Visual Inspection During Excavation SSEM CHECK Technical Specification Civil Works

Approved Designated Disposal Area W S Checklist Form IC-C-002

2.2 BACKFILLING

2.2.1 Check fill materials for conformity to specifications Soil Classification Approved Stock File Third Party Test Technical Specification

Civil Works A9010 Part I Sec.2.1 Test Result Compliance w/

the Project Specification H R Checklist Form IC-C-002

2.2.2 Check foundation for Bitumen coating for polyethylene covering Visual Inspection Before Backfilling SSEM CHECK Technical Specification

Civil Works Project Specification H W Checklist Form IC-C-002

2.2.3 Check thickness of Backfill layer and Compaction

Field Density Test (ASTM D1556) Nuclear Density Test

(ASTM D2922)

4 Random FDT at least per lot of 2,500 sq.m. Third Party Test Technical Specification

Civil Works A9010 Part I Sec.2.1 Project Specification S/H W Checklist Form IC-C-002

3.0 TRENCHING AND BACKFILLING OF

PIPELINES

3.1 TRENCHING

3.1.1 Availability of permit Verification of Permit Prior to Proceed for Trenching SSEM CHECK Tender Requirements Valid Permit H R Checklist Form IC-C-003

3.1.2 Location and Layout of area to be trenched and mark the routing of existing underground utilities Visual Inspection/Survey Prior to Proceed for

Trenching SSEM CHECK Technical Specification Civil Works

Approved Construction Drawings/Client As-Built

Drawings H W Checklist Form IC-C-003

3.1.3 Checking grading and elevation for conformity to drawing Visual Inspection/Survey Prior to Proceed for

Trenching SSEM CHECK Technical Specification Civil Works

Approved Construction Drawings H W Checklist Form IC-C-003

3.1.4 Ensure proper care to avoid damages to existing utilities Visual Inspection During Trenching SSEM CHECK Technical Specification

Civil Works Client Engineering

Standard S W Checklist Form IC-C-003

3.1.5 Check the excavated area for freedom from extraneous materials and water Visual Inspection During Trenching SSEM CHECK Technical Specification

Civil Works Project Specification H W Checklist Form IC-C-003

3.1.6 Disposal of excavated materials Visual Inspection After Excavation SSEM CHECK Technical Specification Civil Works

Approved Designated Disposal Area S/H S Checklist Form IC-C-003

Page 11 of 23

Page 13: Method Statement for Shoring Work

CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL

AIRPORT

EXCAVATION, BACKFILLING and SPOILING CHECKLIST

Project: Construction of New Load Center-3 IC Checklist No.: 085-IC-C-002 Contract No.: R-15-085-BF-O ITP Ref. No.: 085-ITP-C-2.0 Facility Name: Sec.: Drwg. No. / Line No.: Area/Location: Work / item for Inspection: Item

Activity

SSEM Engr.

SSEM QC

GACA/AECOM Representative

Corr. Sign Off

Remarks A R N/A

1 EXCAVATION 1.1 Excavation Permit 1.2 Location, Layout of area to be

excavated

1.3 If any existing service lines, utilities & utility structures which are to remain in service are uncovered or encountered during operations, they shall be safeguard, protected from damage and supported

1.4 Provide bracing, shoring, sheeting, sheet piling, underpinning or other retaining structures necessary to protect against any movement or settlement of existing structure or utilities near the excavation area

1.5 Line and grade of excavated area is as per plan & specification

1.6 Rock, loose rock, boulders and other material unacceptable for subgrade shall be excavated to an extra depth of minimum 250 mm below the top of the subgrade (the formation level) or as instructed by the Engineer.

1.7 The extra depth, that results due to rock removal or excavation of other unacceptable material, shall be

Page 12 of 23

Page 14: Method Statement for Shoring Work

CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL

AIRPORT

refilled with approved fill material, obtained from the specified excavation and shall be compacted as specified.

1.8 All loose or protruding rocks on the back slopes of the cuts shall be barred loose, or otherwise removed to the line of finished grade or slope.

1.9 Blasting, when necessary, will be permitted only when the operations are approved by the Engineer, all permissions are obtained (appropriate authorities) and proper precautions have been taken for the protection and safety of all persons, the work and the property. All damage done to the work or property shall be repaired at the contractor’s expense. Any approval given will not relieve the contractor of his responsibility in blasting operations.

1.10 Areas within the airport property where borrow excavation takes place shall be indicated in the drawings. They will only be available after a written agreement from the Engineer has been obtained.

1.11 When source for borrow excavation are outside the airport property, it shall be the contractor’s responsibility to locate the source and obtain the required permits, subject to the approval of the Engineer.

1.12 The Contractor shall notify the Engineer sufficiently in advance of the beginning of borrow excavation so that the necessary measurements and test can be made.

Page 13 of 23

Page 15: Method Statement for Shoring Work

CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL

AIRPORT

1.13 All borrow pits shall be opened up to expose the vertical face of various strata of acceptable material, to enable obtaining a uniform product. All work involved with clearing, stripping and removal of unacceptable materials from borrow pits shall be excavated to regular lines to permit accurate measurements and shall be drained and left in a neat and presentable condition with all slopes dressed uniformly.

1.14 All suitable material from drainage excavation shall be placed in specified fill areas and unsuitable material shall be used, for topsoiling purpose of, as instructed.

2 BACKFILLING 2.1 Material for backfilling approved 2.2 For structure, check first the

foundation for bitumen coating or polyethylene cover before backfilling

2.3 Compaction of finish surface to receive fill material is in accordance with the specification

2.4 Fill structures shall be constructed with acceptable material, as specified, placed in successive horizontal layers of not more than 200 mm in loose depth, for the full width of the cross section, unless otherwise approved by the Engineer.

2.5 The grading operations shall be conducted, to produce a soil structure as shown on the typical cross section or as directed. Material such as brush, hedge, roots, stumps, grass and other organic matter,

Page 14 of 23

Page 16: Method Statement for Shoring Work

CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL

AIRPORT

shall not be incorporated or buried in the fill structure

2.6 Stones or fragmentary rocks larger than 100 mm in their greatest dimensions shall not be allowed in the top 150 mm of the fill structure.

2.7 The material in the layers shall be within ±2% of the optimum moisture content before rolling to obtain the specified compaction. Wetting or drying of the material and manipulation to secure a uniform moisture content throughout the layer may be required. Should the material be too wet to permit proper compaction or rolling, all work on all of the affected portions of the fill structure shall be delayed until the material has dried to the required moisture content. Sprinkling of dry material to obtain the proper moisture content shall be done with the approved equipment that will satisfactory distribute water. Sufficient equipment to furnish the required water shall be available at all times.

2.8 Compaction areas shall be kept separate and no layer shall be covered by another layer until the proper density shall be obtained. Rolling operations shall be continued until all layers are compacted to not less than the specified compaction.

2.9 Any areas inaccessible to a roller shall be compacted by mechanical tampers.

2.10 During construction of fill the Contractor shall route his

Page 15 of 23

Page 17: Method Statement for Shoring Work

CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL

AIRPORT

equipment at all times, both when loaded and when empty, over the layer as they are placed and shall distribute the traffic evenly over the entire width of the fill.

2.11 Fill operations shall be suspended at any time when satisfactory results cannot be obtained because of adverse weather or other unsatisfactory conditions in the field.

2.12 Tests shall be taken at specified intervals. Based on this tests the Contractor shall make corrections and adjustments in work method or moisture content in order to achieve the specified compaction.

2.13 Any area found to lack the required compaction shall be further compacted or watered and/or scarified, or otherwise manipulated as the Engineer may instruct, until the specified compaction is obtained.

2.14 Rock fill shall be brought up in layers not exceeding 0.60 mm and every effort shall be made to fill the voids with the finer material to form a dense, compact mass.

2.15 Each (rock) layer shall be levelled and smoothed with the suitable grading equipment and by distribution of spalls and finer fragments of rock.

2.16 Rock fill shall not be applied in the top 1.2 meters of the finished subgrade.

2.18 Density requirements will not apply to portions of fill structure constructed of materials which cannot be tested in accordance

Page 16 of 23

Page 18: Method Statement for Shoring Work

CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL

AIRPORT

with specified methods (like rock fill).

2.17 Proceed backfilling to another layer if preceding layer is in accordance with the required density, lines and grade

3 SPOILING 3.1 The Contractor shall during his

Site inspection in the tender period, contact the employer to obtain information regarding the destination of unacceptable materials and surplus materials. These materials remain the property of the Employer unless the Employer transfers his ownership to the Contractor.

3.2 Unacceptable materials and surplus materials that are released by the Employer, shall become the property of the Contractor. They shall not be spoiled or stockpiled on site and shall be removed off the airport property.

3.3 The Contractor shall make his own arrangements with other public agencies, the municipality or private companies or landowners for the spoiling of unacceptable and surplus materials that became his property.

3.4 The surface elevation of spoil areas shall not extend above the surface elevation of adjacent areas. The spoil material shall be placed/spoiled and compacted to a reasonable density as instructed by the Engineer. All spoil areas shall be graded to allow positive drainage of the area itself and of adjacent areas. If required, the spoil area and adjacent

Page 17 of 23

Page 19: Method Statement for Shoring Work

CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL

AIRPORT

areas shall be put into condition acceptable for seeding or planting.

4 TOLERANCES 4.1 In those areas upon which any

pavement construction is to be placed, the top of the subgrade shall not vary from the design levels by more than 15 mm. The finished levels shall be determined by taking level in a grid of 10 by 10 percent of the measurements exceed the specified tolerance, but are less than 20 mm.

4.2 In areas outside pavement constructions the top of the formation shall not vary from the design levels shall be determined by taking levels in a grid of 20 x 20 meters or less. A lot will be accepted for grade if not more than 10 percent of the measurements exceed the specified tolerance, but are less than 40 mm.

4.3 The size of a lot shall be between 2,500-5,000 m2.

4.4 Any deviation in excess of the above tolerances shall be corrected by reshaping and compaction of the material.

GACA/AECOM Representative Remarks: Legend: A=Acceptable; R=Rejected; N/A=Not Applicable

SSEM QC Representative GACA / AECOM Representative Sign: Sign: Name: Name: Date: Date:

Page 18 of 23

Page 20: Method Statement for Shoring Work

CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL

AIRPORT

TRENCHING AND BACKFILLING OF PIPELINES CHECKLIST

Project: Construction of New Load Center-3 IC Checklist No.: 085-IC-C-003 Contract No.: R-15-085-BF-O ITP Ref. No.: 085-ITP-C-3.0 Facility Name: Sec: Drwg. No. / Line No.: Area/Location: Work / item for Inspection:

Item

Activity

SSEM

Engr.

SSEM

QC

GACA/AECOM Representative

Corr. Sign Off

Remarks A R N/A

1 TRENCHING 1.1 Obtaining permit of excavation 1.2 Location and layout of area to

be excavated

1.3 Trenches may be excavated manually or with mechanical trenching equipment. Walls of trenches shall be essentially vertical so that a minimum of surfaced is disturbed.

1.4 Graders, scrapers or bulldozers shall not be used to excavate the trench.

1.5 The bottom surface of trenches shall be essentially smooth and free from coarse aggregate. Unless otherwise specified, trenches shall be excavated to a design depth for the pipe lines. Trenches for piping and utilities shall not be less than 400 mm nor more than 600 mm wider than the outside diameter of the pipe to be laid therein. Bottoms of the trenches shall be accurately graded with bell holes scooped out to provide uniform bearing and support of pipe and utilities on undisturbed soil throughout their entire length except where other means of supporting pipe are indicated. Rock materials shall be excavated to 150 mm below

Page 19 of 23

Page 21: Method Statement for Shoring Work

CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL

AIRPORT

pipe invert and bed backfilled with fine sand and well tamped in place.

1.6 When rock excavation is encountered, the rock shall be removed to a depth of at least 0.8 m below finished grade. Rock excavation shall consist of the removal of boulders and detached rock ½ cubic meter in volume or greater, and of all rock in place in ledges or masses which can be removed only by the use of bars and sledges or by blasting.

1.7 Before any rock is removed the Engineer shall have the opportunity to obtain the necessary data to determine the quantity.

1.8 The Contractor shall excavate the trenches to a width not less than 0.3 m.

1.9 At all times during the construction, the trenches shall be kept free of standing water.

1.11 Grading and elevation conformed to drawing

1.10 Disposal of excavated material 2.0 EXCAVATION NEAR EXISTING FACILITIES 2.1 These trenches shall be

excavated manually in order to avoid damages to existing cables and utilities

2.2 Any damage to existing cables or utilities shall be immediately reported to the Engineer and the relevant Authorities, and shall be promptly repaired or replaced by the Contractor at his own expense and in a manner and with materials as required by the Engineer or the Authorities.

2.3 If the Authorities required that

Page 20 of 23

Page 22: Method Statement for Shoring Work

CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL

AIRPORT

the repair of damaged cables or utilities shall be carried out by their own workmen or by other Contractors, then the Employer shall be entitled to recover from the Contractor the cost thereof or may deduct the cost from any payment due or that become due to the Contractor.

2.4 Special attention shall be paid to the sections of existing cables, which have to remain in use or be re-used for intermediate power supply upon completion of the works. Therefore, the Contractor shall determine the exact location of these cables, whether indicated on the drawings or not, before staring any of his operation in a particular area.

3 BACKFILL, PROTECTION AND DISPOSAL OF SURPLUS MATERIAL 3.1 Backfilling may proceed until all

required tests are performed & until the piping systems, as installed, comply with the requirements in the specifications

3.2 Bedding and fill materials conformed to specifications

3.3 Pipes are in correct position and restrained in place

3.4 Check thickness of backfill layers & compaction and compactness test

3.5 The tolerance of backfill is +25 / -25 mm

4.2 CLEANING UP OF SITE 4.3 All areas disturbed by the

trenching, storing of dirt, and other work shall be restored to its original condition. The restoration shall include any necessary top soiling, seeding or planting.

Page 21 of 23

Page 23: Method Statement for Shoring Work

CONSTRUCTION OF NEW LOAD CENTER-3 AT KING KHALED INTERNATIONAL

AIRPORT

GACA/AECOM Representative Remarks: Legend: A=Acceptable; R=Rejected; N/A=Not Applicable

SSEM QC Representative GACA / AECOM Representative Sign: Sign:

Name: Name:

Date: Date:

Page 22 of 23

Page 24: Method Statement for Shoring Work

SSEM-HSE/PERMIT/002/M07-11, Rev0.1, July2011 SHORING WORK PERMIT

DATE: ______________________PERIOD: __________________TO:__________________PERMIT NO.:_______________

EQUIPMENTS: _______________________________________________________WORK AREA: ______________________

DESCRIPTION OF WORK:_________________________________________________________________________________

NAME OF THE ORIGINATOR:

COMPANY: DEPARTMENT: SIGNATURE:

PERFORMING AUTHORITY NAME:

SIGNATURE & DATE:

CONTACT NO:

COMPLEMENTARY PERMITS YES NO N/A

DRIVING IN UNAUTHORISED AREAS

CLEARANCE FROM YERP AUTHORITY

CLEARANCE FROM ROYAL COMMISSION

CLEARANCE FROM OTHER DEPARTMENTS

RISK ASSESSMENT SAFETY PRECAUTUONS

YES NO N/A

ELECTRICAL ISOLATION METHOD STATEMENT / JSA ENOUGH ACCESS/EGRESS SUFFICIENT SCAFFOLDING/PLATFORMS

AREA CLEAR FROM COMBUSTIBLE SUBSTANCES

ANY OTHER WORKS ADJACENT ISOLATION FROM OTHER WORKS AREA CLEAR FROM TOXIC GASES EXISTING TEMPORARY OR PERMANENT UTILITIES

SUITABLE EQUIPMENT AND TOOLS AVAILABLE

YES NO N/A

PERSONAL PROTECTIVE EQUIPMENT (P.P.E)

BARRICADES AND WARNING SIGNS

AREA IS SUITABLE FOR CONCRETE REPAIR WORK

ADDITIONAL ILLUMINATION

PROPER ACCESS

ACCESS/EGRESS CLEAR FROM OBSTACLES

FIRE EXTINGUISER / FIRE WATCHMAN

LIFE LINES/ SAFETY HARNESS

BREATHING EQUIPMENT

EMERGENCY RESCUE TEAM AVAILABLE.

SLOPING OR SHIELDLING PROVIDED

NO MATERIAL KEPT NEAR THE EXCAVATION

GAS CYLINDERS KEPT OUT FROM THIS AREA

WORKERS AWARE OF HAZARDS AND PRECAUTUONS TO BE TAKEN

OTHER REQUIREMENTS (IF NECESSARY)

DECLARATION (to be filled by Performing Authority) And Competent Person

I, UNDERSIGNED HAVE CHECKED THE AREA AND COMPLIED TO ALL SAFETY PRECAUTIONS AND RISK ASSESSMENT AND WILL CARRY OUT ACTIVITY WITH APPROVED METHOD STATEMENT

NAME: SIGN: NAME: SIGN:

PERMIT VALIDITY (to be filled by Site Manager/Engineer) THE ABOVE WORK HAS BEEN APPROVED AND SHALL BE CARRIED OUT SAFELY. IT HAS TO BE ENSURED THAT THE EMPLOYEE EXECUTING THE JOB HAS A COPY OF THE PERMIT AT ALL TIMES DURING THE WORK.

NAME: SIGNATURE: DATE:

PERMIT CLEARANCE (to be filled by HSE/Safety Representative) I DECLARE THAT ALL WORK UNDER MY CONTROL HAS NOW BEEN COMPLETED AND THE AREA HAS BEEN CLEARED AND THAT ALL TOOLS AND OTHER EQUIPMENT HAVE BEEN REMOVED

NAME: SIGNATURE: DATE:

PERMIT CLOSED (to be filled by Performing Authority) THE ABOVE WORK WAS COMPLETED SAFELY AND THE WORK PERMIT SHALL BE CANCELLED

NAME: SIGNATURE : DATE:

SAFETY DEPARTMENT:

NAME: SIGNATURE: DATE:

Yellow- Site Blue - HSE office White - Client Office

Page 23 of 23