Method Statement - Non Suspended Slab
STAGE 1
Casting the ground beam 25mm lower from original depth1.
Leveling and well-compacted sub-grade and crusher run2.
STAGE 2
Placing damp proof polythene sheet and followed by B.R.C. layer 1.
Casting the ground slab to required level as specified in theconstruction drawing
2.
STAGE 3
Leveling the slab with gradient to fall as specified in the construction
drawing
1.
Applying floor hardener finisher2.
STAGE 4
Forming a groove line by diamond cutter at both end of ground beam1.
Method Statement For Construction Of Non Suspended Slab
SUPPORT THIS BLOG FOR MORE INFORMATION
mny
Share thisblog withyourfriends.
View my completeprofile
ABOUT ME
2011 (10)
July (5)
Method Statement- BoredCast-In-PlacePiles
Inspection CheckList - GeneralEarthworkExcavati...
Inspection CheckList - StructuralWork(Reinforce...
Inspection Checklist - Piling Work
Method Statement- Non SuspendedSlab
June (5)
BLOG ARCHIVE
with Google Friend Connect
There are no members yet.Be the first!
Already a member? Sign in
JOIN AND REQUEST FOR MORE
Method Statement For Construction: Method Statement - Non Suspended... http://methodofconstruction.blogspot.com/2011/07/method-statement-no...
2 of 3 2/8/2011 10:54 PM
Newer Post Older PostHome
Subscribe to: Post Comments (Atom)
Posted by mny at 11:40 AM
Labels: Non Suspended Slab
*The illustration and information is for guidance only. Please refer to
your engineer or consultant for further advise.