META Corporation
Public Company Limited
Opportunity Day
12 Jun 2018
Page 2
Strictly Confidential Information
Cautionary Note Regarding Forward-looking Statements
The information contained in this document has not been independently verified and no representation or warrantyexpressed or implied is made as to, and no reliance should be placed on, the fairness, accuracy, completeness or
correctness of this information or opinions contained herein.
Certain statements contained in this document may be statements of future expectations and other forward-lookingstatements that are based on management‘s current view and assumptions and involve known and unknown risks anduncertainties that could cause actual results, performance or events to differ materially from those expressed or
implied in such statements.
None of META Corporation Public Company Limited or any of its affiliates, advisors or managements shall have anyliability whatsoever (in negligence or otherwise) for any loss howsoever arising from any use of this document or itscontent or otherwise arising in connection with this document.
This document does not constitute an offer or invitation to purchase or subscribe for any shares and neither it nor anypart of it shall form the basis of or be relied upon in connection with any contract or commitment whatsoever.”
Disclaimer
Page 3
Strictly Confidential Information
Agenda
1 Overview
2 Project Portfolio
3 Financial Performance
Page 4
Strictly Confidential Information
Overview
To emerge as one of leading players in the Asian
energy sector, with fully integrated energy
business and well diversified power plant portfolio located across ASEAN and Japan
Vision
Phase 1 : Expansion of Core Business
Master Development Plan
Phase 2 : Integration of Power Plant Development
Business
Phase 3 : Fully Integrated Power Business
To transition the mechanical and electrical
engineering services to EPC contractor for power plants and other infrastructures
To integrate the existing business with
power plant development business as a foundation for the long term business plan
To add related businesses such as O&M
service and feedstock trading businesses to complete the targeted business goal
Existing BU
M&E Engineering
Additional BU
EPC Contractor
Existing BU
1 M&E Engineering
2 EPC Contractor
Additional BU
Power Plant Development
Existing BU
1 M&E Engineering
2 EPC Contractor
3 Power Plant
Development
Additional BU
O&M ServicesFeedstock
Trading
5 years development
Page 5
Strictly Confidential Information
Rapid decrease in
global coal price
Key Milestones
• Established as Vintage
Technology Limited company
• Conducted mechanical and electrical engineering
business
• Changed the name to Vintage Engineering
Company Limited
• Listed on Stock
Exchange of Thailand’s Market for Alternative
Investments (MAI)
• Initiation of Coal Mining
Business
• Impairment of the
investment in SMI (Coal Mine)
2016 : Turn-around!
• Initiation of EPC Contractor Business EPC contractor for 220 MW
Minbu Solar Power Project
in Myanmar EPC contractor for 25 MW
Biliran Solar Power Project
in Philippines
• Highest annual revenue and net income since
establishment
• Impairment of the investment
in BJCM (Coal Marketing Right)
• Initiation of Power Plant Development Business 12% investment in 220 MW
Minbu Solar Power Project
in Myanmar
100% TK investment in 1.17MW Kagoshima Solar
Power Project in Japan
• Start of
Construction of Phase I 50MW
Minbu Solar Power Plant
1992 -
20102011 2013 2014 20162015 2017 2018
• Changed the
name to META
Corporation
Public Company
Limited
Page 6
Strictly Confidential Information
100%
Company Structure
META Corporation Public Company Limited
Engineering and Construction
Business
Vintage EPC Company Limited
VTE International Construction
Company Limited
Off-shore EPC : International Projects
On-shore EPC : International Projects
Power Plant Development Business
Vintage Holding Japan
Company Limited
Green Earth Power (Thailand)
Company Limited
Developer of Power Plants in Japan
Developer of Power Plant in Myanmar
Construction Period
Others
WorldMax Management
Company Limited
Feedstock trading business
PT Sunhub Mining International
Company Limited
Coal mining and trading business*
100%
100% 12%
100%
25%
Basic Energy Corporation (BSC)
Strategic Partnership to pursue the
development of Renewable Energy
Projects in the Philippines
9%
NOVA Asia
Company Limited
Financial Advisory
100%
Page 7
Strictly Confidential Information
Education and Achievement
Bachelor degreeNihon University
45th Food Industry
Achievement Award
Kochi Mayer Commendation
Award
Management Profile
Honorary Chairman
Mr. Katsuyuki Takeuchi
Mr. Katsuyuki Takeuchi was appointed to be a Honorary Chairman of META, with a rich
experience in food industry in Japan from working in Asahi Shokuhin Co., Ltd. as a top management
level for more than 40 years. Not only experience in food industry, he also has knowledge in various
investment activities in energy sector as currently he is serving one of the power company inJapan, Shikoku Electric Power Co. Inc. as Audit & Supervisory Board Member.
Duration Company Position
Present META Corporation Public Co., Ltd. Honorary Chairman
Present Shikoku Electric Power Co., Inc. Audit & Supervisory Board Member
2016 - Present Asahi Shokuhin Director and Advisor
2012 Asahi Shokuhin (New Establishment) Chairman of the Board
2012 Asahi Shokuhin Holdings Chairman of the Board
2004 Asahi Shokuhin Chairman of Board
1995 Asahi Shokuhin President
1988 Asahi Shokuhin Vice President
1981 Asahi Shokuhin Managing Director
Page 8
Strictly Confidential Information
Chairman of the Board
Education and Achievement
Bachelor of Engineering
Thonburi Institute of
Technology
Master of Marketing
Kasetsart University
Management Profile
Mr. Soraj Rojanabenjakul
Mr. Soraj Rojanabenjakul is one of the founders of Vintage Engineering Public Company Limited,
and had been Chief Executive Officer since 1992. He also serves as its Managing Director,
Chairman of the Board, Chief of Executive Board and Member of Executive Board. Mr. Soraj has
more than 25 years of experience in the field of engineering business. Under his guidance, VTEgrew and expand to assume its present leading position and is on its way to becoming one of the
leading utility and engineering firms in SEAsia. In addition, Mr. Soraj is well connected with wide
range of both domestic and international leading firms among various industries.
Duration Company Position
Present META Corporation Public Co., Ltd. Chairman of the Board and Director
1992 – 2017 Vintage Engineering Public Co., Ltd. Chairman and Chief Executive Officer
2012 – Present Inno Products Co., Ltd. Director
2012 – Present WorldMax Management Co., Ltd. Director
2012 – Present Capital Core Co., Ltd. Director and Management Director
Page 9
Strictly Confidential Information
Mr. Supasit Pokinjaruras
Mr. Supasit Pokinjaruras started his career at HSBC (Thailand) developing relationships and
managing investment portfolios for high net worth individuals. His subsequent careers took him
anywhere from being a well-experienced entrepreneur, involved in brokerage businesses, to
participating in the entertainment industry. His first foray into the Renewable Energy Industrybrought him to develop one of the most innovative and advance Solar Power Plant project in Japan.
Soon after he became the head of Green Earth Power (Thailand) Co., Ltd., and co-developed a
220MW Solar Farm in Minbu, Myanmar. Mr. Supasit places strong emphasis on the financial aspect
of the operation, while also being well-versed in Solar Power technologies.
Duration Company Position
Present META Corporation Public Co., Ltd. Chief Executive Officer
2015 – 2017 Vintage Engineering Public Co., Ltd. Executive Director / Director
2014 – Present AVA Asia Ltd. Co-Founder and President
2013 – Present Good Deal Entertainment Co., Ltd. Co-Founder and Managing Director
2012 – Present Green Earth Power (Thailand) Co., Ltd. Managing Director
2011 – 2014 Green Earth Power Japan Co., Ltd. Executive Director
2013 – 2014 RSB OSK Securities (Thailand) PCL Senior Vice President
2012 – 2013 Trinity Securities Group Vice President
2011 – 2012 Finansia Syrus Securities PCL Senior Assistant Vice President
2007 – 2010 HSBC Assistant Vice President
Chief Executive Officer
Education and Achievement
Bachelor of Business
Administration (International
Program), Thammasat University
Master of Science in
Financial Analysis,
University of San Francisco
Management Profile
Page 10
Strictly Confidential Information
Education and Achievement
B.A. Economics and
International Relations
Boston University
Master of Science Finance
and Economics,
London School of Economics
and Political Science
Master of Science Real
Estate Finance
New York University
Management Profile
Mr. Aung Thiha
Mr. Aung Thiha one of VTE’s Directors, is a seasoned investment professional with significant
professional experiences that include extensive sourcing, underwriting, structuring and restructuring
of investments that range from power plants to real estate in the United States, Brazil, Thailand and
Myanmar. His immersive career path lends him an ability to pinpoint opportunity and risk in themarket with clarity and assurance. After his successful ventures in Investment Banking and Private
Equity, together with Mr. Supasit, he went on to tackle the Renewable Energy Industry in Japan and
later on culminated in the founding of Green Earth Power (Thailand) Co., Ltd, and spearheaded the
development of a 220MW Solar Farm in Minbu, Myanmar, one of the largest power plants of its kind.
Duration Company Position
2015 – Present META Corporation Public Co., Ltd. Executive Director / Director
2014 – Present AVA Asia Ltd. Co-Founder and CEO
2012 – Present Green Earth Power (Thailand) Co., Ltd. Executive Director
2011 – 2014 Green Earth Power Japan Co., Ltd. Executive Director
2009 – 2012 Ava Capital Management Managing Director
2009 – 2011 Algon Group Restructuring Advisor
2008 – 2009 Brookfield Asset Management Associate
2007 – 2008 Nomura Credit and Capital, New York Office Assistant Vice President
2005 – 2007 CW Capital, Fortress Investment Group Securitization Associate
Executive Director
Page 11
Strictly Confidential Information
Agenda
1 Overview
2 Project Portfolio
3 Financial Performance
Page 12
Strictly Confidential Information
Engineering and Construction Projects (EPC)
Biliran
Myanmar
Project 220.00MW Minbu Solar Power Plant
Status Under Construction
Role Turn-key EPC
Location Minbu District, Magway Region, Myanmar
Scope of Work Turn-key EPC Contractor
Construction Timeline Expected Start: April, 2018
Expected Completion: July, 2021
Expected Revenue USD 1.285 mm per MW
Operating Margin (%) ~ 7.00%
Philippines
Project 25.56MW Biliran Solar Power Plant (Under Contract Revision
by Owner)*
Status Under Construction
Role Off-shore EPC
Location Biliran Province, Eastern Visayas Region, Philippines
Scope of Work Off-shore Contractor
Construction Timeline Expected Start: August, 2016Expected Completion: Within 2019
Expected Revenue USD 1.29 mm per MW*
Operating Margin (%) ~ 8.00%
Active Projects
Minbu
Page 13
Strictly Confidential Information
Power Plant Projects
Myanmar
Project 220.00MW Minbu Solar Power Plant
Status Under Construction (COD first 50MW in January, 2019)
Role Owner
Location Minbu District, Magway Region, Myanmar
Tariff / PPA Term USD 0.1275 per kWh/ 30 Years with extension option
Equity IRR 8% - 10%
Project cost ~ USD 293 mm
Active Projects
Minbu
Japan
Project 25.00MW Saga Biomass Power Plant
Status Deposit was placed in 2016, Pre-Construction, Permits
fully obtained, COD 2021
Role Owner
Location Karatsu City, Saga Prefecture, Japan
Tariff / PPA Term JPY 24 per kWh/ 20 Years
Equity IRR 9% - 11%
Project cost ~ USD 75 mm
Saga
Japan
Project 25.00MW Wakayama Biomass Power Plant
Status Securing Developing Rights
Role Owner
Location Wakayama Prefecture, Japan
Tariff / PPA Term JPY 24 per kWh/ 20 Years
Equity IRR 9% - 11%
Project cost To be confirmed
Wakayama
Page 14
Strictly Confidential Information
Power Plant Projects
Potential Pipeline Projects
Kitakyushu
Japan
Project 288.00MW Kitakyushu Wind Power Project
Status Development Stage
Role Owner
Location Kitakyushu City, Fukuoka Prefecture, Japan
Tariff / PPA Term JPY 36 per kWh/ 20 Years
Equity IRR 10% - 11%
Project cost To be confirmed
Japan
Project 50.00MW Saga Biomass Power Plant
Status Deposit was placed in 2016, Pre-Construction, Permits
fully obtained, COD 2022
Role Owner
Location Karatsu City, Saga Prefecture, Japan
Tariff / PPA Term JPY 24 per kWh/ 20 Years
Equity IRR 9% - 11%
Project cost To be confirmed
Japan
Project 25.00MW Saga Biomass Power Plant
Status Deposit was placed in 2016, Pre-Construction, Permits
fully obtained, COD 2021
Role Owner
Location Karatsu City, Saga Prefecture, Japan
Tariff / PPA Term JPY 24 per kWh/ 20 Years
Equity IRR 9% - 11%
Project cost ~ USD 75 mm
Saga
Page 15
Strictly Confidential Information
No ProjectPeriod
StatusAmount
(MB)Start End
1 Rama IX Museum 31/5/17 10/11/18 Ongoing 69.43
2 KU @ Kampangsean 16/1/16 3/7/18 Ongoing 284.11
3 Biliran Project 22/9/16 1/12/18 Ongoing 331.52*
4 Minbu Project by
VEPC
Nov 2016 Jan 2022 Ongoing 6,455.68*
5 Minbu Project by
VINTER
Nov 2016 Jan 2022 Ongoing 1,418.88*
Total 9,497.22
Backlog Project
*FX USD 1 = THB 32
Page 16
Strictly Confidential Information
Minbu Project: Press Visit
Page 17Confidential
Minbu Project: Press Visit
Page 18Confidential
H.E. U Win Khaing
(Minister, Ministry
of Electricity &
Energy)
H.E. Dr Aung Moe
Nyo (Chief
Minister, Magway
Regional
Government)
Minbu Project: Commencement Date
Page 19Confidential
Mr. Aung Thiha, Chairman and MD of GEP
(Myanmar) and Green Earth Power (Thailand)
Minbu Project: Commencement Date
Page 20Confidential
Minbu Project: Commencement Date
Page 21Confidential
Minbu Project: Commencement Date
Page 22
Strictly Confidential Information
Minbu Project
Page 23Confidential
The EPC Contractor completed leveling at HHV Substation area on 15 May 2018. The work started end of March 2018.
The EPC contractor started to build the drainage system on 1 May 2018 and expects to complete by end of June 2018.
Minbu Project
Page 24Confidential
Pictures from GEP Myanmar (“GEPM”) and Electric Power Generation Enterprise (“EGPE”) participated in Factory Acceptance Test (FAT) executed at Siemens Italy between 14 – 16 March 2018.
Minbu Project
Page 25
Strictly Confidential Information
Agenda
1 Overview
2 Project Portfolio
3 Financial Performance
Page 26
Strictly Confidential Information
659.6
2
229.0
8
938.67
2017 3M17 3M18
Revenue
58.78
25.75
77.59
2017 3M17 3M18
Gross Profit
-269.74
-
47.81
24.53
2017 3M17 3M18
Net Profit
0.39
1.351.19 1.12
2015 2016 2017 3M2018
D/E Ratio
Current Asset,
2.22
Current Asset,
0.97
Non-Current
Asset, 3.16
Non-Current
Asset, 0.92
As of 31 Dec 2017 As of 31 Mar 2018
Total Equity,
1465.71
Total Equity,
1921.97
Current Liab.,
1.53Current Liab.,
2.14
Financial Performance
-
269.4
9
-16.9
80
2017 3M17 3M18
EBITDA
Page 27
Strictly Confidential Information
Financial Performance
0
500
1000
1500
2000
2015 2016 2017 3M2017 3M2018
Revenue Structure
Advisory EPC Coal M&E and Construction
460.00
1,629.08
659.62
229.08
938.67
Million Baht
15.05% 14.26%8.91% 11%
8%
-15%
3%
-40.86%
3%
2%
-23.07%
3.06%
-40.89%
-21%
3%
-50.00%
-40.00%
-30.00%
-20.00%
-10.00%
0.00%
10.00%
20.00%
2015 2016 2017 3M2017 3M2018
Statement of Comprehensive Income
GPM EBITDA Margin NPM
Page 28
Strictly Confidential Information
Q&A
Page 29
Strictly Confidential Information
Expenditure Amount (THB)
Financial Cost1 90,599,053
Loss on written-off exclusive marketing right2 44,329,242
Bad debts and doubtful accounts3 35,570,440
Loss on impairment investment in associates4 31,436,999
B/E Issuing Fee 30,426,974
Total 232,361,808
Extra Expenditure as of 31/12/17
Remark:
(1) Financial cost amount 90.60 MB was caused by B/E and Debenture issuing in 2016 and 2017, respectively.
(2) It’s the loss on written-off for PT Huashia Project, which is the exclusive marketing right for coal product, amounted 44.33 MB.
(3) It’s the Company’s doubtful account of construction business.
(4) FX loss.