29
TOLL Free Tel: 877-830-9803 Email: [email protected] Website: www.metreel.com MET-TRACK ® Workstation Bridge Cranes FLOOR MOUNTED Installation & Maintenance Instructions

MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

TOLL Free Tel: 877-830-9803 Email: [email protected] Website: www.metreel.com

MET-TRACK® Workstation Bridge Cranes FLOOR MOUNTED

Installation & Maintenance Instructions

Page 2: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 2 of 29

CONTENTS

Introduction ............................................................................................................................................ 3

Preparation ............................................................................................................................................. 3

Column and Header Installation ............................................................................................................ 4-5

Runway Installation .............................................................................................................................. 6-8

Bridge & End Truck Options and Parts Breakdown ................................................................................ 9-17

Hoist Trolley and Bridge Festoon Installation .......................................................................................... 18

Festoon Storage Extensions (FSE) ...................................................................................................... 19-20

Hoist Trolley Installation ........................................................................................................................ 20

Service Connections .............................................................................................................................. 21

Final Steps ............................................................................................................................................ 21

Warning, Safety or Capacity Labels ........................................................................................................ 21

Load Testing ......................................................................................................................................... 21

Sway Bracing (Optional) ........................................................................................................................ 22

Operator Instructions ................................................................................................................... 23-24

Inspection and Maintenance Schedule ........................................................................................ 25-28

Warranty Statement ......................................................................................................................... 29

Page 3: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 3 of 29

INTRODUCTION

Thank you for choosing a MET-TRACK® Floor Mounted Workstation Kit Crane from Metreel. We really appreciate your choice and are confident that, when installed correctly this product will provide you with a superior materials handling solution. All of our cranes are designed and engineered for a powered hoist operation, however manual hoists, balancers and any other lifting equipment can be used as long as the duty is within our standard capacity. If you are unsure about his point then please contact our technical team on Toll Free 877-830-9803 or email [email protected]

Within our design criteria we have allowed 15% for the weight of the hoist, for example with a 500lb crane, the hoist unit itself should be no heavier than 75lb. There is also an allowance with the design for normal impact loading caused by the bridge and hoist movement.

To ensure that you continue to get many years of service from the MET-TRACK® Workstation Crane we advise that a good inspection / maintenance routine according to our procedures detailed herein must be adopted.

Dimensions contained in this document and any literature is for guidance only and may differ from the crane delivered. Please ensure you refer to the General Arrangement Drawing for actual dimensions.

PREPARATION

Before starting the install of this crane it is recommended that you ensure that you have all the materials required.

We recommend you follow the following steps and confirm you have all items.

1) Confirm all the following documents are present, these will be found in the component box marked “Contains Documentation” a) Packing List b) Installations & Maintenance Manual c) General Arrangement Drawing

2) Check all items against the packing list

3) Check that you have the correct anchors bolts, refer to Page 2. These are supplied with the crane kit

4) Check that the area in which the crane is to be installed is clean and free of obstructions

5) Check that you have all the required tools and materials needed to assemble the crane, these will

typically include: a) Torque Wrench b) General Tools c) Measure d) Chalk Line e) Level f) Shims g) Heavy duty drill & bits h) Steps/Ladders/Man Lifts i) Lifting equipment for heavier sections

Page 4: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 4 of 29

COLUMN & HEADER INSTALLATION

1) Layout and mark the area where the crane is to be installed (refer to the General Arrangement Drawing for dimensions)

2) Mark out the floor BEFORE drilling using the column bas plate as a template (or refer to the General Arrangement Drawing for dimensions). Brush away the dust and debris

3) Bolt the first set of columns to the floor, ensuring they are aligned correctly to receive the header (in

case of rectangular columns, ensure the column rotation is as shown in fig1) a) 4 off ¾” Ø bolts grade 5 or greater MUST be used per column (See fig 2) b) These MUST be embedded at least 4” into a minimum 6” thick reinforced concrete floor (See fig 3) c) A minimum of two threads MUST be visible above the nut after tightening d) Chemical anchor bolts are recommended (not supplied)

4) Check that the column is plumb and level, if not loosen the hardware and place steel shims (not included) or grout (not included) under base of column until plumb. Once plumb retighten hardware.

5) Lift and position header using appropriate lifting equipment and fasten the 5/8” x 2” bolt assemblies supplied (torque to 154ft.-lb) (See fig 4)

Page 5: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 5 of 29

6) Follow the same procedure for the remaining column and header sets

Fixings Parts List Column to Header Beam (per column) 4 x 5/8” x 2” Bolt 4 x 5/8” Nut 4 x Type B ‘Narrow’ 5/8” Washer 4 x Regular 5/8” Spring Washer All fixings must be UNC All fixings must be SAE Grade 5

Page 6: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 6 of 29

RUNWAY INSTALLATION

1) As the runway sections maybe different depending upon your span selection, check the General Arrangement Drawing to identify individual gantry sections

2) Being careful not to disturb the columns, lift the first set of runway sections into place (refer to the General Arrangement Drawing for position and dimension details)

3) Using the runway fixing brackets secure the runway to the header (see fig 5)

4) Do not alter the span (CBS) from that advised in the General Arrangement Drawing and take care to position the runway centrally or as per the dimensions provided

5) Do not cantilever the end of the runways further than the dimension stated in the General Arrangement Drawing

6) Check to ensure that the runways are parallel, failure to do so will prevent the bridge from running

smoothly

Fixings Parts List Runway to Header Fixing Kits (per column) 8 x 5/8” Nut 8 x Type B ‘Narrow’ 5/8” Washer 8 x Regular 5/8” Spring Washer 4 x Studding (length to suit) All fixings must be UNC All fixings must be SAE Grade 5

Page 7: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 7 of 29

7) Torque fasteners to 75ft.-lb and ensure at least two treads are visible after tightening

8) If you have no more runways to install then skip to step 16

9) Install Joint Kits to previously installed runway (See fig 6)

10) Install the next runway length by lifting and bringing together the runway ends and positioning according to the General Arrangement Drawing. The gap between the running profile MUST not exceed 1/16”

11) Attach the other end of the runway to the next header using the runway fixing brackets (See fig 7)

Fixings Parts List Track Joints (per Joints) 4 x ½” (length to suit) Bolt 4 x ½” Type B ‘Narrow’ Flat Washer 4 x ½” Nylon Nut, fixing torque 78ft.-lbs All fixings must be UNC All fixings must be SAE Grade 5

Page 8: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 8 of 29

12) Align the runway profile so that the running surfaces are level a) To adjust for smooth travel, use the bolts on the top of

the splice joint to force the track down into the base of the splice joint. Use the bolts on each side to level the track laterally (see fig 8)

13) Fix final hardware in the splice plates and secure

14) Once secure torque the runway fix bracket fasteners to 170ft.-lb and ensure at least two threads are visible after tightening

15) For additional runway sections refer to Step 9 through to Step 15 until runway installation is complete

16) Fit runway End Kits at one end of each runway, opposite to where the bridge will be installed (See fig 9)

17) Clean the inside of the runway flanges with a clean, dry cloth to remove grit or debris

Page 9: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 9 of 29

BRIDGE & END TRUCK OPTIONS AND PARTS BREAKDOWN Please ensure you have the correct End Truck Standard End Truck

Part No. 1454 1554 1654 1754 Cap.(lbs) 250 500 1000 2000 Bridge Length Upto 23ft

1454L End Truck

Description Qty Part No. 400 Series Splice Plate Weldment 1 23618 SHS for 400 Series Extended Trolley 2 23605 Trolley for 400 Series Extended Truck 2 23622 Plastic End Cap 4 GPN 260 Q 4040 4 End Truck Fixing Kit 2 2 28035 End Truck Fixing Kit 1 4 28034

1554L End Truck

Description Qty Part No. 500 Series Splice Plate Weldment 1 23619 SHS for 500 Series Extended Trolley 2 23606 Trolley for 500 Series Extended Truck 2 23623 Plastic End Cap 4 GPN 260 Q 5050 5 End Truck Fixing Kit 3 6 28036

Page 10: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 10 of 29

1654L End Truck

Description Qty Part No. 600 Series Splice Plate Weldment 1 23620 SHS for 600 Series Extended Trolley 2 23624 Trolley for 600 Series Extended Truck 2 23607 Plastic End Cap 4 GPN 260 Q 5050 5 End Truck Fixing Kit 3 6 28036

1754L End Truck

Description Qty Part No. 700/800 Series Splice Plate Weldment 1 23621 SHS for 700 Series Extended Trolley 2 23608 Trolley for 700 Series Extended Truck 2 23625 Plastic End Cap 4 GPN 260 Q 6060 5 End Truck Fixing Kit 4 6 28037

1854L End Truck

Description Qty Part No. 700/800 Series Splice Plate Weldment 1 23621 SHS for 800 Series Extended Trolley 2 23609 Trolley for 800 Series Extended Truck 2 23626 Plastic End Cap 4 GPN 260 Q 6060 5 End Truck Fixing Kit 4 6 28037

Page 11: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 11 of 29

1554-400 End Truck

Description Qty Part No. 400 Series Splice Plate Weldment 1 23618 Packer Plates for End Truck Designs 4 23629 Plastic End Cap 4 GPN 260 Q 5050 5 Trolley for 500 Series Extended End Truck 2 23623 SHS for 1554-400 & 1554 End Trucks 2 28024 End Truck Fixing Kit 3 6 28036

1654-400 End Truck

Description Qty Part No. 400 Series Splice Plate Weldment 1 23618 Packer Plates for End Truck Designs 8 23629 Plastic End Cap 4 GPN 260 Q 5050 5 600 Series Extended End Truck 2 23624 SHS for 1654-400 & 1654 End Trucks 2 28025 End Truck Fixing Kit 4 6 28036

1754-400 End Truck

Description Qty Part No. Truck Plate Weldment for 1754-400 End Truck 1 28029 Packer Plates for End Truck Designs 16 23629 Trolley for 700 Extended End Truck 2 23625 SHS for 1754-400 End Truck 2 28027 Plastic End Cap 4 GPN 260 Q6060 5 End Truck Fixing Kit 4 6 28037

Page 12: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 12 of 29

1654-500 End Truck

Description Qty Part No. 500 Series Splice Plate Weldment 1 23621 Packer Plates for End Truck Designs 4 23629 Plastic End Cap 4 GPN 260 Q 5050 5 600 Series Extended End Truck 2 23624 SHS for 1654-400 & 1654 End Trucks 2 28025 End Truck Fixing Kit 3 6 28036

1754-500 End Truck

Description Qty Part No. 500 Series Splice Plate Weldment 1 23619 Packer Plates for End Truck Designs 12 23629 Plastic End Cap 6 GPN 260 Q 6060 5 Trolley for 700 Extended End Truck 4 23625 SHS for 1754-500 & 1754-600 End Trucks 2 28026 End Truck Fixing Kit 4 6 28037

1754-600 End Truck

Description Qty Part No. 600 Series Splice Plate Weldment 1 23620 Packer Plates for End Truck Designs 8 23629 Plastic End Cap 4 GPN 260 Q 6060 5 Trolley for 700 Extended End Truck 2 23625 SHS for 1754-500 & 1754-600 End Trucks 2 28026 End Truck Fixing Kit 4 6 28037

Page 13: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 13 of 29

1554L-500 End Truck

Description Qty Part No. 400 Series Splice Plate Weldment 1 23618 Packer Plates for End Truck Designs 4 23629 Plastic End Cap 4 GPN 260 Q5050 5 Trolley for 600 Series Extended End Truck 2 23623 SHS for 1654-400 & 1654 End Trucks 2 23606 End Truck Fixing Kit 3 6 28036

1654L-400 End Truck

Description Qty Part No. 400 Series Splice Plate Weldment 1 23618 Packer Plates for End Truck Designs 4 23629 Plastic End Cap 4 GPN 260 Q 5050 5 Trolley for 500 Extended End Truck 2 23623 SHS for 1554-500 & 1554 End Trucks 2 23624 End Truck Fixing Kit 3 6 28036

1754L-400 End Truck

Description Qty Part No. Truck Plate Weldment for 1754-400 End Truck 1 28029 Packer Plates for End Truck Designs 16 23629 Plastic End Cap 4 GPN 260 Q 6060 5 Trolley for 700 Extended End Truck 2 23625 SHS for 700 Series Extended Trolley 2 23608 End Truck Fixing Kit 4 6 28037

Page 14: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 14 of 29

1654L-500 End Truck

Description Qty Part No. 500 Series Splice Plate Weldment 1 23619 Packer Plates for End Truck Designs 4 23629 Plastic End Cap 4 GPN 260 Q5050 5 600 Series End Truck 2 23624 SHS for 600 Series Extended Trolley 2 23607 End Truck Fixing Kit 3 6 28036

1754L-500 End Truck

Description Qty Part No. 500 Series Splice Plate Weldment 1 23619 Packer Plates for End Truck Designs 4 23629 600 Series End Truck 2 23624 SHS for 600 Series Extended Trolley 2 23607 Plastic End Cap 4 GPN 260 Q5050 5 End Truck Fixing Kit 3 6 28036

1754L-600 End Truck

Description Qty Part No. 600 Series Splice Plate Weldment 1 236120 Trolley for 700 Series Extended End Truck 2 23625 SHS for 700 Series Extended Trolley 2 23608 Plastic End Cap 4 GPN 260 Q6060 5 Packer Plates for End Truck Designs 8 23629 End Truck Fixing Kit 4 6 28037

Page 15: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 15 of 29

1854 End Truck

Description Qty Part No. 700/850 Series Splice Plate Weldment 1 23621 Trolley for 800 Series Extended End Truck 2 23626 Plastic End Cap 4 GPN 260 Q5050 5 SHS for 1854 End Truck 2 28033 End Truck Fixing Kit 4 6 28037

When building this End Truck, care must be taken to ensure all four pairs of running wheels are in contact with the runway at all times.

Page 16: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 16 of 29

1) If a festoon system has been selected for this workstation crane then it may be necessary to put the appropriate number of festoon trolleys, end clamps and festoon storage extension (FSE) on to one of the runway’s prior to the bridge being installed. This depends upon where the power source is located, ideally the end clamp of the festoon should be positioned as close to the power source as possible.

2) Slide the End Trucks over the end of the bridge (Refer to the General Arrangement Drawing for the positional dimensions).

3) Using the bolts on the top of the sleeve of one of the End Trucks, clamp the bridge (if a conductor system is being installed this should be the End Truck on the side where the powerfeed will be positioned).

4) Remove or leave free the bolts on the sleeve of the other End Truck, see fig 10. (This is to allow for the

bridge to float taking up the slight deviation of the installed runways).

5) Install an End Stop to the end of the bridge opposite to the festooning (where appropriate) see fig 11. Being careful not to allow the free End Truck to slip off, lift up the bridge and insert the end Trucks into the open ends of the runways. If appropriate make sure the festooning end of the bridge is oriented with the festoon or conductor system on the runway.

6) Slide End Truck into the runways and immediately install the End Stop Kit in the open ends of the

runway to prevent bridge from falling back out the system.

Page 17: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 17 of 29

Fixings Parts List End Stop Kits All fixings must be UNC All fixings must be SAE Grade 5

400 Series 500 Series 600 Series 700 / 800 Series 1 x RB45 Sleeve 1 x RB45 Sleeve 1 x RB67 Sleeve 1 x RB67 Sleeve 2 x ½” x 3” Bolt 2 x ½” x 3.5” Bolt 2 x 5/8” x 4.5” Bolt 2 x 5/8” x 5” Bolt 2 x ½” NYLOC Nut 2 x ½” NYLOC Nut 2 x 5/8” NYLOC Nut 2 x 5/8” NYLOC Nut 4 x Type B ‘Narrow’ ½” Washer 4 x Type B ‘Narrow’ ½” Washer 4 x Type B ‘Narrow’ 5/8” Washer 4 x Type B ‘Narrow’ 5/8” Washer

7) Check the position of the bridge, there must be a minimum of 2” between the end of the bridge and the column upright

8) Clean the inside of the bridge flanges with a clean, dry cloth to remove grit or debris

9) Run the bridge down the complete length of the runway to check for smooth travel. If the bridge movements is not smooth, check the runways are level and parallel, check that the End Trucks are only clamped on one side. Make sure the inside running faces of all profiles are clean and all debris has been removed

Page 18: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 18 of 29

HOIST TROLLEY AND BRIDGE FESTOON INSTALLATION

Install hoist trolley and festoon trolleys on crane bridge track, if applicable, as shown in fig 12. Secure End Stop bolts and rubber bumpers, also shown in fig 12. Install the festoon cable/hose on the festoon trolleys at equal spacing, ensure festoon has correct loop depth (refer to the General Arrangement Drawing).

Once installation is completed, the bridge and runways should be levelled. The total system should then be checked for tightness of all nuts and bolts.

Page 19: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 19 of 29

FESTOON STORAGE EXTENSIONS (FSE)

400 Series Festoon Extension (Must be welded to the runway – refer to the General Arrangement Drawing)

500 Series Festoon Extension

600 Series Festoon Extension

Page 20: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 20 of 29

700 & 800 Series Festoon Extension

HOIST AND TROLLEY INSTALLATION

Attach hoist to hoist trolley. Use washers on host mounting pin to centre hoist inside hoist trolley. Reinstall washer on outside of hoist trolley before installing or reinstalling cotter pin to secure hoist mounting pin. Replace cotter pin if worn or broken. Bend cotter pin around mounting pin. See fig 13

WARNING: Do not operate hoist or crane if cotter pin is not in place and properly bent over. Check regularly that the cotter pin is in place and securing the hoist on the hoist trolley.

Part No. 1418 1518 1618 1718 1818 Cap. (lbs) 250 500 1000 2000 4000

Page 21: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 21 of 29

SERVICE CONNECTIONS It is the responsibility of the customer to provide a suitable power supply. IF a festoon system has been chosen we will supply a 30” tail for connection to an isolator. For air supply it is the responsibility of the customer to provide a suitable clean air supply at the required rating to accommodate the working pressure. (hose to be supplied by others)

FINAL STEPS

• Check to make sure all bolts are tight and lock washers are compressed

• If necessary, touch up crane with paint provided

• Keep Packing List, Installation Manual, General Arrangement Drawing and any other documents

filed together in a safe place

WARNING, SAFETY AND CAPACITY LABELS If at any time these labels are lost, stolen, removed or become illegible please contact Metreel at [email protected] for replacements.

LOAD TESTING After the MET-TRACK® system has been installed, you should Load Test the equipment before operating and also after any modifications.

Page 22: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 22 of 29

SWAY BRACING (Optional)

Support assemblies are designed to AISC (American Institute of Steel Construction) specifications. If reduced movement of the support assemblies is desired, then sway bracing (not included) can be added. The installer or end user must determine the possible locations of the bracing based on the specific application.

Bracing can be added in one of three formats, or a combination of any three.

1) The most typical place to brace is directly to a building column. Providing a brace from a building column to the lateral (side) and longitudinal (lengthwise) axis of the support steel provides extreme rigidity throughout the system and requires only minimal locations (2 or 3 corners of the system is adequate).

2) Another method is to brace back to the ceiling above the crane. Again, bracing at the corners of the system on bother lateral and longitudinal direction is sufficient (see fig 14), providing the distance to the ceiling is not greater than 10ft. For distances greater than this additional points may need to be braced both laterally and longitudinally at the discretion of the end user and/or the installer.

3) Finally, if the system is located at the point where it is practical or possible to brace to the building

columns or the ceiling structure, cross bracing can be done. This can be added at the sides of the system (See fig 15) to control longitudinal sway, or across the system open ends to limit lateral motion (not shown). This can also be added to the top of the system but should be checked to make sure it does not interfere with the travel of the bridge.

It should be noted that the use of sway bracing is purely subjective because it is not a requirement of Metreel, Inc. No specifications exist detailing appropriate methods and the ultimate quantity and type is at the discretion of the user and installer.

If bracing always determine if the building structure is adequate.

Page 23: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 23 of 29

MET-TRACK® OPERATOR INSTRUCTIONS MET-TRACK® systems move materials and equipment over areas where other personnel are located. It is therefore vital for the MET-TRACK® operator to be fully trained in the use of the MET-TRACK® system and be fully aware of both the danger to life and or serious injury that may result from careless operation. Local and national legislation and regulations as well as plant safety and operating procedures must be followed at all times. In addition it is recommended that the following information is studied in order to understand safe lifting procedures specific for the MET-TRACK® system. The following notes are suggestions of good working practice, however it must be remembered that it is the responsibility of the MET-TRACK® owner to ensure that all personnel using the system are aware of all federal, state and local rules and legislation covering use of such systems as well as having specific training on the use of the MET-TRACK® system in question. OPERATOR QUALIFICATION Operators should comply rigidly with the safety rules and practices detailed in current ANSI and OSHA Safety standards. The safe and efficient use of MET-TRACK® system requires good operator skill, judgement, awareness and concentration. For these reasons the following categories of employee should not be permitted to operate a MET-TRACK® system: 1) Those who cannot understand the printed instructions

appertaining to use of the MET-TRACK® 2) Anyone who is under the required age to legally

operate the system 3) Those who have either impaired hearing or impaired

field of vision 4) Those who suffer from medical conditions which may

compromise the operators safe operation of the system (conditions may include heart problems, epilepsy etc.)

5) Anyone who has not read and fully understood all aspects of the MET-TRACK® instruction manual

6) Anyone who has not been formally instructed in the operation of MET-TRACK® systems

BRIDGE TRAVEL Before moving the bridge, the operator must check to ensure that the hook is positioned high enough to clear any local obstructions. Before attempting to lift a load, the bridge must be positioned such that it is directly over the load to be lifted. When moving the bridge start the movement slowly and increase the bridge speed gradually. When approaching the target position, slow the bridge down gradually before coming to a complete stop at the target position.

HOIST TROLLEY TRAVEL There is a serious risk to health caused by loads swinging at the start of a lift. For this reason it is vital that when attempting to lift any kind of load that the hoist trolley is positioned directly over the load to be lifted. The hoist hook can then be raised very slowly in order to remove slack from the hoist slings or chain. Once the slack has been removed check again that the hoist is in the correct position before proceeding to lift the load. As with all aspects of MET-TRACK® movement, the hoist trolley must be started at a slow speed before increasing. Speed must then be reduced when approaching the target position before finally stopping at the required point. HOIST MOTION Refer to hoist supplier’s specific operating instructions. GENERAL SUGGESTIONS FOR SAFE AND EFFICIENT MET-TRACK® OPERATION KNOW YOUR MET-TRACK® SYSTEM All MET-TRACK® operators and maintenance personnel should be aware of the key components of the MET-TRACK® system as well as having a thorough understanding and knowledge of the key movements and lifting functions of the system. Both personnel should be aware of both the location and operation of emergency stop systems as well as safe disconnecting procedure for power to the MET-TRACK®

and any associated systems. OPERATOR RESPONSIBILITY Any MET-TRACK® operator should be made aware that they are directly responsible for the safe operation of the system. If the operator has cause to suspect any aspect of the system not being in a suitable condition for safe operation then the operator MUST NOT OPERATE THE SYSTEM! Operation should only resume once safety has been assured or an operator is instructed to proceed by a supervisor. In the latter situation the supervisor them assumes ALL responsibility for the safety of operation. SYSTEM MIS-USE The MET-TRACK® system is a proven design for the safe lifting and movement of loads. Operators or other personnel should be made aware of injuries or loss of life that may result in using the system either incorrectly or for other uses that it is intended. Personnel should not be permitted to ‘ride’ on any part of the system such as the load, hoist or cross bridge at any time. Such mis-use can easily result in serious injury or death.

Page 24: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 24 of 29

GENERAL OPERATING PROCEDURE In addition to operator training and skill, the following guidelines should be followed to achieve safe and efficient handling of the MET-TRACK® system. 1) All crane movements including cross bridge, hoist

trolley and hoist should all be done with a smooth action and should move from a stopped position through a gradual ramp up in speed before normal operating speed is achieved. When coming to a stop, speed should be reduced gradually before bringing any item to a complete stop. When lifting any load ensure that any slack is removed from the slings or chains prior to lifting.

2) Any load being lifted must have the hoist positioned

DIRECTLY above it prior to starting the lift. Failure to observe this could result in the load swinging out when lifted which could result in damage to plant, injury to personnel or overloading the MET-TRACK® NEVER attempt to lift loads outside the standard lift footprint of the MET-TRACK® system.

3) The MET-TRACK® system should only be used to lift

a load in a vertical direction only. Loads should not be pulled or dragged under any circumstances.

4) Loads should not be lifted over any personnel. Any personnel in the immediate are of lift should be made aware of the impending lift and moved clear.

5) The load being lifted should not exceed the safe

working load limit clearly specified on the MET-TRACK® system.

6) Before lifting any load ensure that the hook latch is in

the closed position (if fitted) and that all slings or chains are correctly seated.

7) Ensure that any load is lifted sufficiently high that it

can be moved without fouling any floor obstructions when moved.

8) Under no circumstances should a load be left

suspended from the MET-TRACK® system. Loads should always be lifted, moved and put down and not left suspended. The load operator should be present whenever the load is in the lifted condition.

9) Ensure that any sling hooks not required for lifting a

load are either removed or properly stowed prior to the start of the lift as otherwise they present a hazard.

10) Do not leave slings or chains hanging from the crane

unless they are being used for a specific lift at that time. Hanging equipment can easily damage plant or personnel when the MET-TRACK® is moving.

11) Ensure extra safety precautions are taken if the type of load being lifted demands it (eg. Molten metal, chemicals etc.)

12) Ensure that the following procedure is followed whenever an operator leaves the MET-TRACK®

system: a) All hooks should be raised so as not to cause an

obstruction. b) The MET-TRACK® system be parked at a pre-

determined park position and the load removed. c) Switch all controls to the ‘off’ position. d) Switch the main crane isolator to the ‘off’

position. e) Perform a visual check before leaving the MET-

TRACK® system 13) Whenever maintenance or inspection work is being

performed on the MET-TRACK® system, the main isolator should be set to the ‘off’ position and locked. Warning signs should be positioned to make it clear the MET-TRACK® is to remain isolated.

14) The hoist trolley should not contact the bridge stop

bolts and buffers under normal operating conditions. Likewise the bridge end trucks should not contact the runway stop bolts and buffers during normal operation. The stop bolts are there as a safety feature and are not designed to be contacted by the hoist or bridge during normal operation.

15) The Metreel MET-TRACK® system includes a number

of built in safety features which are required for safe operation of the system. Under no circumstances should any safety features, or any standard MET-TRACK® components be removed, disabled or impaired as this will provide a serious safety risk.

Any removal, disabling or impairment of any aspect of the MET-TRACK® system will automatically and immediately make void all Metreel expressed and implied warranties.

Page 25: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 25 of 29

INSPECTION AND MAINTENANCE SCHEDULE

The information below covers suggested inspection procedure of a MET-TRACK® system in order to guarantee trouble free operation and running.

It is strongly recommended to check all of the criteria listed below one month after the initial installation of the system to ensure that all fixings are correctly tightened after the system has settled following installations.

Following this initial inspection the frequency can revert to the frequency listed below.

Note that the frequencies specified are suggested; however federal, state or local codes may stipulate a tighter frequency rate. Please refer to federal, state and local codes in your location territory.

Note that any concerns highlighted during any inspection or highlighted at any other time on the system MUST be addressed immediately and corrected and the MET-TRACK® system not used until the corrective work has been carried out. Failure to do this will pose a serious safety risk.

COLUMN TO FLOOR FIXING HARDWARE Frequency: Every 12 Months

Maintenance Procedure:

Check for full compression of lock washer if fitted. Ensure bolts are tightened to manufacturers specified torque value. Perform visual check for any signs of damage.

COLUMN TO HEADER FIXING HARDWARE

Frequency: Every 12 Months Maintenance Procedure:

Check for full compression of lock washer if fitted. Ensure bolts are tightened to manufacturers specified torque value. (refer to installation manual for details) Perform visual check for any signs of damage.

HEADER TO RUNWAY FIXING HARDWARE

Frequency: Every 12 Months Maintenance Procedure:

Check for full compression of lock washer if fitted. Ensure bolts are tightened to manufacturers specified torque value. (refer to installation manual for details) Perform visual check for any signs of damage.

Page 26: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 26 of 29

FESTOON STORAGE EXTENSION TO RUNWAY TRACK HARDWARE (if fitted)

Frequency: Every 12 Months Maintenance Procedure:

Ensure bolts are tightened to manufacturers specified torque value. (refer to installation manual for details) Ensure that the two screw on the top of extension are correctly adjusted to provide a flush rolling surface from the runway to storage extension. Perform visual check for any signs of damage.

FESTOON STORAGE EXTENSION STOP BOLTS (if fitted)

Frequency: Every 12 Months Maintenance Procedure:

Ensure bolts are tightened to manufacturers specified torque value. (refer to installation manual for details) Perform visual check for any signs of damage.

RUNWAY TO RUNWAY SPLICE JOINT KIT (if fitted)

Frequency: Every 12 Months Maintenance Procedure:

Ensure bolts are tightened to manufacturers specified torque value. (refer to installation manual for details) Ensure that all screws on the splice joint are adjusted to provide a flush rolling surface from one runway to another (refer to the installation manual for details). Perform visual check for any signs of damage.

FESTOON STORAGE EXTENSION TO RUNWAY TRACK HARDWARE (if fitted)

Frequency: Every 12 Months Maintenance Procedure:

Ensure bolts are tightened to manufacturers specified torque value. (refer to installation manual for details) Ensure that all screws on the splice joint are adjusted to provide a flush rolling surface from one runway to another (refer to the installation manual for details). Perform visual check for any signs of damage.

Page 27: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 27 of 29

HOIST TROLLEY

Frequency: Every 12 Months Maintenance Procedure:

Ensure that the cotter pin is wrapped securely around the load pin. Perform visual check for any signs of damage to cotter pin. Perform visual check for any signs of damage to load pin.

ALL RUNNING WHEELS

Frequency: Every 12 Months Maintenance Procedure:

Perform visual check for any signs of damage such as cracks or signs of excessive wear. Note that wheels are supplied as a sealed unit and so will not require lubrication of wheel bearings.

BRIDGE END TRUCKS - EXTENDED

Frequency: Every 12 Months Maintenance Procedure:

Check that the bridge has the correct 12” cantilever from the end of the bridge to the centre line of the end truck. Check that fixings are fastened correctly on one of the bridges only and that the other end truck has had all of its fixings removed (refer to the installation manual for details). Check wheels for as detailed previously. Perform visual check for any signs of damage paying particular attention to the following:

• Overall condition of the square tubes, checking for excessive bow

• Check all welds visually looking for any damaged sections or cracks

• Ensure all bolts are tightened to specified torque

Page 28: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 28 of 29

BRIDGE END TRUCKS - STANDARD

Frequency: Every 12 Months Maintenance Procedure:

Check that the bridge has the correct 12” cantilever from the end of the bridge to the centre line of the end truck. Check that fixings are fastened correctly on one of the bridges only and that the other end truck has had all of its fixings removed (refer to the installation manual for details). Check wheels for as detailed previously. Perform visual check for any signs of damage paying particular attention to the following:

• Overall condition of the square tubes, checking for excessive bow

• Check all welds visually looking for any damaged sections or cracks

• Ensure all bolts are tightened to specified torque

BRIDGE, RUNWAY & FESTOON EXTENSION STOP BOLTS

Frequency: Every 12 Months Maintenance Procedure:

Ensure bolts are tightened to manufacturers specified torque value (refer to the installation manual for details). Perform visual check for any signs of damage paying particular attention to the rubber buffer around the inboard bolt.

FESTOON SYSTEM CABLE CLAMPS or VACUUM HOIST CLAMP (if fitted) Frequency: Every 12 Months Maintenance Procedure:

Ensure bolts are tightened to manufacturers specified torque value (refer to the installation manual for details). Perform visual check for any signs of damage.

Page 29: MET-TRACK Workstation Bridge Cranes FLOOR MOUNTED

Floor Mounted Workstation Bridge Crane

Installation & Maintenance Instructions

Document No. TD002-0618 Last Updated: 14 June 2018

Page 29 of 29

WARRANTY STATEMENT

Metreel Inc. warrants that the Goods that it manufactures shall at the time of delivery be free from defects in workmanship and materials and/or the Services will be carried out with reasonable care and skill. If any Goods or Services do not conform to this warranty Metreel Inc. will at its option:

• Replace the Goods or repeat the Services found not to confirm to the warranty • Take such steps as Metreel Inc. thinks necessary to bring the Goods into the state where they are free from

such defects; or • Take back the Goods found not to conform to the warranty and refund the appropriate part of the purchase price;

or • Refund the appropriate part of the charge for the Services • Or any combination of the above which, in the opinion of Metreel Inc. shall be reasonable

Provided that Metreel Inc.’s liability shall in no event exceed the price of the Goods or Services and performance of any of the above options shall constitute an entire discharge of Metreel Inc.’s liability under this warranty.

The above warranty is subject to the following conditions:

• The Buyer must give written notice to Metreel Inc. of the alleged defect in the goods or Services within seven days of the time when the Buyer discovers or ought to have discovered the defect, and in any event within twelve months of delivery or supply of the goods and Services; and

• The Buyer must give Metreel Inc. a reasonable opportunity to inspect the Goods and, if requested by M Metreel Inc., return the allegedly defective Goods to Metreel Inc.’s works, carriage pre-paid, for inspection to take place there; and

• The Goods have not been altered or modified in any way whatsoever, other than by Metreel Inc. or on its instruction and have not been subjected to misuse or unauthorized repair; and

• The Goods have been properly installed and connected to such systems as advised by Metreel Inc.; • And the Buyer has complied with its obligations under this or any other contract made with Metreel Inc.

It is agreed that the equipment detailed in paragraphs below is subject to the following LIMITED warranty and no other.

• Metreel Inc. warrants the manual MET-TRACK® Workstation Crane and Workstation Jib products to be free from defects in material and workmanship for a period of 10 years or 20,000 hours of use, from the date of shipment by Metreel Inc.

• Metreel Inc. warrants the motorized MET-TRACK® Workstation Crane and Workstation Jib products to be free from defects in material and workmanship for a period of 2 years or 4,000 hours use, from the date of shipment by Metreel Inc.

Any such actions shall void this extended warranty.

Metreel Inc. shall not under any circumstances be liable in contract, tort, stature or otherwise for any direct, indirect or consequential loss or for increased costs or expenses or loss of profit, business, contracts, revenues or savings howsoever arising which may be suffered by the Buyer (except in respect of death or personal injury cause by Metreel Inc.’s negligence).

If, notwithstanding the above provisions of this Condition, Metreel Inc. is found liable for any loss or damage suffered by the Buyer, that liability shall in no event exceed the unit price of the goods or Services so affected.

Metreel Inc. reserves the right to make any changes to the Specification of the Goods or to the components within the goods provided that these do not materially affect the quality or performance of the goods other than to the extent that Metreel Inc. advises of such an affect.

Where the completion of the contact requires the cooperation of the Buyer and/or the timely submission of information, data or agreement to proposals by the Buyer, Metreel Inc. shall not be liable for the consequences of the Buyer’s failure to so act or respond on time, in full or in part.