1 Mermaid Sweaters Ltd Feroza Apparels Ltd Ltd 177/1, 178, South Bishil Mirpur-1 Dhaka - 1216 (23.795529N, 90.350728E) 4 th March 2015

Mermaid Sweaters Ltd Feroza Apparels Ltd

Embed Size (px)

Citation preview

Page 1: Mermaid Sweaters Ltd Feroza Apparels Ltd

1

Mermaid Sweaters LtdFeroza Apparels Ltd

Ltd

177/1, 178, South Bishil Mirpur-1 Dhaka - 1216(23.795529N, 90.350728E)

4th March 2015

Page 2: Mermaid Sweaters Ltd Feroza Apparels Ltd

2

Observations

Page 3: Mermaid Sweaters Ltd Feroza Apparels Ltd

3

ObservationsBuilding 1

Page 4: Mermaid Sweaters Ltd Feroza Apparels Ltd

4Observations Building 1

High Stress Levels in ColumnsAnd Loadbearing Brickwork

Page 5: Mermaid Sweaters Ltd Feroza Apparels Ltd

5 Observations Building 1

Outline calculations indicate that concrete columns and loadbearing brickwork walls and pillars at the Ground Floor and 1st Floor are highly stressed under their current loading condition

Page 6: Mermaid Sweaters Ltd Feroza Apparels Ltd

6Observations Building 1

Absence of structural drawings

Page 7: Mermaid Sweaters Ltd Feroza Apparels Ltd

7

Only as built drawings for Building 1 available (shown with red) but no structural information was presented

Observations Building 1

Page 8: Mermaid Sweaters Ltd Feroza Apparels Ltd

8

Apparently non-engineered roof structure at top floor

Observations Building 1

Page 9: Mermaid Sweaters Ltd Feroza Apparels Ltd

9

Roof structure over the prayer room and knitting room at top floor appears non-engineered

Observations Building 1

Page 10: Mermaid Sweaters Ltd Feroza Apparels Ltd

10

ObservationsBuilding 2

Page 11: Mermaid Sweaters Ltd Feroza Apparels Ltd

11Observations Building 2

High Stress Levels in Columns

Page 12: Mermaid Sweaters Ltd Feroza Apparels Ltd

12 Observations Building 2

Outline calculations indicate that a number of columns at the Ground Floor are highly stressed under their current loading condition and require to be reviewed urgently.

High stress level in the columns shown with red circle

Page 13: Mermaid Sweaters Ltd Feroza Apparels Ltd

13

Discrepancies between site observation and information on drawing

Observations Building 2

Page 14: Mermaid Sweaters Ltd Feroza Apparels Ltd

14 Observations Building 2

Additional grid shown in the as built drawing (marked with red rectangle) not present in the structural drawings and also not been observed on site

As built drawing

Structural drawing

Page 15: Mermaid Sweaters Ltd Feroza Apparels Ltd

15 Observations Building 2

Building Permit Drawings for4-storied residential building

Additional floor not shown in buildingpermit drawings. Also building is used as factory but permit is for residential use.

Page 16: Mermaid Sweaters Ltd Feroza Apparels Ltd

16

Possible lack of bracing in roof structure

Observations

Page 17: Mermaid Sweaters Ltd Feroza Apparels Ltd

17 Observations

Possible lack of bracing in the roof of warehouse. Bracing may be required(marked with red lines)

Possible lack of bracing in the roof of passage between Building 1 & 2. Bracing may be required (marked with red lines)

Page 18: Mermaid Sweaters Ltd Feroza Apparels Ltd

18

Priority Actions

Page 19: Mermaid Sweaters Ltd Feroza Apparels Ltd

19

Problems ObservedBuilding 1ITEM 1: High Stress Levels in Columns and Loadbearing BrickworkITEM 2 : Absence of structural drawingsITEM 3 : Apparently non-engineered roof structure at top floor

Building 2ITEM 1: High Stress Levels in ColumnsITEM 2: Discrepancy between site observation and information on drawingITEM 3: Possible lack of bracing in roof structure

Page 20: Mermaid Sweaters Ltd Feroza Apparels Ltd

20

Building 1

Page 21: Mermaid Sweaters Ltd Feroza Apparels Ltd

21

Item No. Observation Recommended Action Plan Recommended Timeline

1Building 1: High Stress Levels in Columns and Loadbearing

Brickwork

Factory Engineer to review design, loads and column stresses in all columns. Factory Engineer to review design, loads and stresses in all brickwork walls and pillars.

Immediate - Now

2Building 1: High Stress Levels in Columns and Loadbearing

Brickwork

Verify insitu concrete strength by taking 100mm diameter cores from 4 columns at ground Floor. Verify grade and amount of steel reinforcement used.

Immediate - Now

3Building 1: High Stress Levels in Columns and Loadbearing

BrickworkVerify brickwork strength and mortar strength. Immediate - Now

4Building 1: High Stress Levels in Columns and Loadbearing

Brickwork

A Detail Engineering Assessment to be commenced on Building 1, see attached Scope.

Immediate - Now

5Building 1: High Stress Levels in Columns and Loadbearing

Brickwork

Detail Engineering Assessment to be completed on Building 1.

6-weeks

6Building 1: High Stress Levels in Columns and Loadbearing

Brickwork

Produce and actively manage a loading plan for all floor plates within the factory giving consideration to floor capacity and column capacity.

6-weeks

7Building 1: High Stress Levels in Columns and Loadbearing

BrickworkContinue to implement load plan 6-months

8Building 1: Absence of

structural drawings

As part of the Detail Engineering Assessment (see Item 1), Factory Engineer to prepare accurate as built structural drawings.

6-weeks

9Building 1: Apparently non-engineered roof structure at

top floor

Building engineer to check the capacity of the lightweight roofs and stairs and make any necessary alterations.

6-months

Page 22: Mermaid Sweaters Ltd Feroza Apparels Ltd

22

This Schedule develops a minimum level of information, Analysis and testing expected as part of a Detail Engineering Assessment.The Building(s) have been visually assessed and it is deemed necessary that a detailed engineering assessment be carried out by a competent Engineering Team employed by the factory Owner. This Request should be read in conjunction with the BUET developed Tripartite Guideline document for Assessment of Structural Integrity of Existing RMG Factory Buildings in Bangladesh (Tripartite Document), the latest version of this document should be referenced. T his document also gives guidance on required competency of Engineering Team.

We expect that the following will be carried out:1. Development of Full Engineering As-Built Drawings showing Structure, loading, elements, dimensions , levels, foundations and framing on Plan,

Section and Elevational drawings .2. The Engineering team are to carry out supporting calculations with a model based design check to assess the safety and serviceability of the building

against loading as set out in BNBC-2006, Lower rate provisions can be applied in accordance with the Tripartite Guidelines following international engineering practice, justification for these lower rate provisions must be made.

3. A geotechnical Report describing ground conditions and commenting on foundation systems used/proposed.4. A report on Engineering tests carried out to justify material strengths and reinforcement content in all key elements studied.5. Detailed load plans shall be prepared for each level showing current and potential future loading with all key equipment items shown with associated

loads.6. The Engineering team will prepare an assessment report that covers the following:

• As-Built drawings including• Plans at each level calling up and dimensioning all structural components • Cross sectional drawings showing structural beams, slabs, floor to floor heights, roof build-ups and Basic design information of the

structure• Highlight any variation between As-built compared to the designed structure• Results of testing for strength and materials• Results of geotechnical assessment and testing/investigation• Details of loading, inputs and results of computer modelling• Commentary on adequacy/inadequacy of elements of the structure• Schedule of any required retrofitting required for safety or performance of Structure

Any proposals for Retrofitting to follow guidance developed in the Tripartite Document

Detail Engineering Assessment

Page 23: Mermaid Sweaters Ltd Feroza Apparels Ltd

23

Building 2

Page 24: Mermaid Sweaters Ltd Feroza Apparels Ltd

24

Item No. Observation Recommended Action Plan Recommended Timeline

10Building 2: High Stress Levels

in ColumnsFactory Engineer to review design, loads and column stresses in all columns.

Immediate - Now

11Building 2: High Stress Levels

in Columns

Verify insitu concrete strength by taking 100mm diameter cores from 4 columns at ground Floor. Verify grade and amount of steel reinforcement used.

Immediate - Now

12Building 2: High Stress Levels

in ColumnsA Detail Engineering Assessment to be commenced on Building 2, see attached Scope.

Immediate - Now

13Building 2: High Stress Levels

in ColumnsDetail Engineering Assessment to be completed on Building 2.

6-weeks

14Building 2: High Stress Levels

in Columns

Produce and actively manage a loading plan for all floor plates within the factory giving consideration to floor capacity and column capacity.

6-weeks

15Building 2: High Stress Levels

in ColumnsContinue to implement load plan 6-months

16Building 2: Discrepancy

between site observation and information on drawing

As part of the Detail Engineering Assessment (see Item 1), Factory Engineer to update the as-built drawings to reflect actual site measurements.

6-weeks

17Building 2: Possible lack of bracing in roof structure

Building engineer to check the capacity of the lightweight roofs and make any necessary alterations.

6-months

Page 25: Mermaid Sweaters Ltd Feroza Apparels Ltd

25

This Schedule develops a minimum level of information, Analysis and testing expected as part of a Detail Engineering Assessment.The Building(s) have been visually assessed and it is deemed necessary that a detailed engineering assessment be carried out by a competent Engineering Team employed by the factory Owner. This Request should be read in conjunction with the BUET developed Tripartite Guideline document for Assessment of Structural Integrity of Existing RMG Factory Buildings in Bangladesh (Tripartite Document), the latest version of this document should be referenced. T his document also gives guidance on required competency of Engineering Team.

We expect that the following will be carried out:1. Development of Full Engineering As-Built Drawings showing Structure, loading, elements, dimensions , levels, foundations and framing on Plan,

Section and Elevational drawings .2. The Engineering team are to carry out supporting calculations with a model based design check to assess the safety and serviceability of the building

against loading as set out in BNBC-2006, Lower rate provisions can be applied in accordance with the Tripartite Guidelines following international engineering practice, justification for these lower rate provisions must be made.

3. A geotechnical Report describing ground conditions and commenting on foundation systems used/proposed.4. A report on Engineering tests carried out to justify material strengths and reinforcement content in all key elements studied.5. Detailed load plans shall be prepared for each level showing current and potential future loading with all key equipment items shown with associated

loads.6. The Engineering team will prepare an assessment report that covers the following:

• As-Built drawings including• Plans at each level calling up and dimensioning all structural components • Cross sectional drawings showing structural beams, slabs, floor to floor heights, roof build-ups and Basic design information of the

structure• Highlight any variation between As-built compared to the designed structure• Results of testing for strength and materials• Results of geotechnical assessment and testing/investigation• Details of loading, inputs and results of computer modelling• Commentary on adequacy/inadequacy of elements of the structure• Schedule of any required retrofitting required for safety or performance of Structure

Any proposals for Retrofitting to follow guidance developed in the Tripartite Document

Detail Engineering Assessment