MERIT installation: Controls for the 5MW power-supply. A.Fabich CERN AB-ATB http://cern.ch/merit September 2006. People. AB/PO Gilles Le Godec AB/CO Marc Vanden Eynden Pablo Alvarez Sanchez (Javier Serrano) MERIT Adrian Fabich (Ilias Efthymiopoulos). Outline. Purpose of this meeting - PowerPoint PPT Presentation
Citation preview
Power controls, Sept. 2006
A.Fabich 1
MERIT installation:Controls for the 5MW power-supply
A.FabichCERN AB-ATB
http://cern.ch/merit
September 2006
Power controls, Sept. 2006
A.Fabich 2
People
AB/PO Gilles Le Godec
AB/CO Marc Vanden Eynden Pablo Alvarez Sanchez (Javier Serrano)
MERIT Adrian Fabich (Ilias Efthymiopoulos)
Power controls, Sept. 2006
A.Fabich 3
Outline
Purpose of this meeting Evaluation of possible layout and work effort
The 5MW power supply in building 193
Controls layout
Estimate of installation work
Power controls, Sept. 2006
A.Fabich 4
Reminder
MERIT Single pulse experiment (limited cycles ~500) Runtime very limited (a few weeks)
Installation is temporary Jan-July 2007 (Run including a commissioning phase) Solutions and implementation of controls layout could be
based on rental.
Budget (T273180) available
Power controls, Sept. 2006
A.Fabich 5
Location
ISR
Westarea
MERIT control room
Power converter
MERIT experiment and local controls
(underground)
Power controls, Sept. 2006
A.Fabich 6
Building 193A
D c
on
tro
l ro
om
AD ring
Power controls, Sept. 2006
A.Fabich 7
Controls layout (Javier)Version 1 (notation Gilles): without GFAS
Console MERITcontrol room
(MERIT, AB/CO)
G64 (AB/PO)
VME (AB/CO)CPU + timing + BC
Ethernet
Timing(start, stop, ...)
MIL1553
BC = bus controller
Version 1 (notation Gilles): with GFAS
CP
U
Ethernet
Tim
ing
GF
AS
BC
VME crate (from above)
MIL1553
Analogue signal
Power controls, Sept. 2006
A.Fabich 8
Additional information
MERIT control room: room 272 S-002 Independent from CCC
Information transmitted to PowerControls Reference current Timing, trigger
Information read (displayed in MERIT control room): Current reading Status of power supply (Off, ready, interlock, error)
Power controls, Sept. 2006
A.Fabich 9
Questions With or without GFAS?
Which parts are already available in building 193? VME crate? Cables (MIL1553, timing ...)? Ethernet? ...
Software in the MERIT control room
Where are the interlocks coming into the game?
Power controls, Sept. 2006
A.Fabich 10
Schedule & runtime
Spring/Summer 2006: Installation Power supply (converter + transformer) DC cabling (building 193 to TT2A)
Autumn 2006: Power converter fully refurbished
Winter 2007: AC cabling Controls Commissioning of the power supply
February 2007: MERIT hardware installation March-April 2007: MERIT commissioning
May 2007: ready for MERIT physics run