Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
AECOM 105 Commerce Valley Drive West, Floor 7 905 886 7022 tel Markham, ON, Canada L3T 7W3 905 886 9494 fax www.aecom.com
Memorandum
3. 2014-06-13_BLW Project Modifications Memo_60301207_DRAFT.Docx
To
Ms. Agatha Garcia-Wright, Director, Environmental Approvals Branch, Ministry of the Environment Page 1
CC Rick Chappell, District Manager, MOE Owen Sound District
Subject
Bluewater Wind Energy Centre – Modification to construction disturbance area (CDA) within Centennial Road right-of-way
From AECOM Canada Ltd.
Date June 16, 2014 Project Number 60301207
Varna Wind LP. (Varna), a wholly owned subsidiary of NextEra Energy Canada, ULC (NextEra) is constructing a wind energy project in the Municipalities of Bluewater and Huron East in Huron County, Ontario. The project is referred to as the Bluewater Wind Energy Centre (the “Project”).
This memo has been prepared to document a change to a construction disturbance area and to confirm that the change does not have any significant adverse effects to the environment.
Varna is proposing modifications to the Project that involve changes to a construction disturbance area (CDA) in order to accommodate the movement of transmission line pole 107, as requested by the adjacent landowner and the Municipality of Huron East. The proposed modification consists of extending the CDA within the Centennial Road right-of-way. Figure 1 illustrates the modified Project Site Plan and the extension of the CDA along Centennial Road.
AECOM Canada Ltd. (AECOM), on behalf of Varna, notified the Ministry of Natural Resources (MNR) of the extension of the CDA in a letter dated June 9, 2014. MNR responded with an email dated June 10, 2014 confirming that in review of the information, a NHA re-confirmation from MNR is not required. In addition, the email confirms that the proposed project modification will not affect the Natural Heritage Assessment already confirmed by MNR. Correspondence with the MNR is included in Attachment A of this memo.
AECOM also submitted the Stage 2 Archaeological Assessment Centennial Road and Hensall Road ROW Report (Stage 2 Report) dated June 10, 2014 to the MTCS. In a letter dated June 12, 2014, the MTCS confirmed that it was satisfied with the recommendations of the Stage 2 Report. Both the Stage 2 Report and correspondence from the MTCS is included in Attachment B of this memo.
The Project modification described in this memo does not change the overall conclusion of the Project Description Report (June, 2012) and associated Amendments to the Project Description Report (March, 2013 & September 2013) which state that “this project can be constructed, installed and operated without any significant adverse residual effects to the environment. Post-construction monitoring related to effects on wildlife, including birds and bats, will be undertaken to confirm this conclusion”.
Page 2 Memorandum June 16, 2014
3. 2014-06-13_BLW Project Modifications Memo_60301207_DRAFT.Docx
Figure 1 Project Location
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
! (
!(
Mil l
Rd
Staf
fa R
d
Par r Line
Kipp
enRd
London Rd
HensallRd
Airport Line
Cent
enni
al R
d
Morr ison Line
182 Rd
Brons on Line
Goshen Line
Perth183Rd
Wal
nutR
d
Rom
anRd
Ti le
Rd
19Lin
e
Division Line
Babylon Line
Pavi
llion
Rd
21Lin
e
181Rd
Bel l's Line
Roge
rvill
eRd
Zuric
h-he
nsal
lRd
HannahLine
Bannockburn Line
Ston
e Rd
Fron
t Rd
Danc
elan
dRd
Bl ind Line
Shor
t Hor
n Rd
26Lin
e
Blackbush Line
Fansvi l le Line
Perth
24Lin
e
Chise
lhurs
t Rd
OakRd
Huro
nRd
Stan
ley
Rd
King
St
Ausable Line
Conc 5 Rd
Perth
17 R
d
Gul ley Line
28 L
ine
KinburnLine
Crys
tal S
prin
gs R
d
Wildwood Line
Mai
n St
Birch
St
Harp
urhe
y Rd
MainStS
MainStN
Blue
Blu
f f Rd
Mill
St
James
St
Marke
t St
Quee
nSt
Davi
d St
E
Mctaggar t Line
Goder
ich S
t W
Smirnof f Line
Goder
ichSt
E
Tower Line
Railw
ay S
t
Sills St
WilliamStW
York
St
AlbertSt
WaterSt
William St E
Roxboro Line
Goshen St N
Davi
d St
ChalkSt S
WilliamSt
HighSt
John St S
John St N
JarvisStS
Huro
n St
NorthLine
SparlingSt
Lorne Ave
Brock St
Fron
t St W
Victo
riaSt
El len St N
John St
ChalkStN
OakSt
Goshen St S
East St
Oxfo
rd S
t W
North
St
Walnut St
Mill
StW
Vien
na S
t
Centr
e St
Parkside Ave
Welsh St
GeorgeStS
Alex
ande
r St
Adam St
York
Cres
Briar
hi ll R
d
Cente
nnial
Rd
Huro
nRd
MillRd
Bronson Line
Zuric
h-he
nsal
lRd
Goshen Line
WilliamSt
Fron
t Rd
Pavi
ll ion
Rd
Babylon Line
SparlingSt
So
uth
Hu
ron
So
uth
Hu
ron
5
7
3
1
8 9
6
4
2
32
16
26
37
36
30
11
35
39
24
29
14
34
28
41
33
13
15
25
23
12
40
21
27
22
17
10
38
18
31
19
4460
00
4460
00
4480
00
4480
00
4500
00
4500
00
4520
00
4520
00
4540
00
4540
00
4560
00
4560
00
4580
00
4580
00
4600
00
4600
00
4620
00
4620
00
4640
00
4640
00
4660
00
4660
00
4680
00
4680
00
4700
00
4700
00
4808000
4808000
4810000
4810000
4812000
4812000
4814000
4814000
4816000
4816000
4818000
4818000
4820000
4820000
4822000
4822000
UTM
Zon
e 17
N, N
AD
83
Proj
ect L
ocat
ion Fi
gure
1
June
201
4P
roje
ct 6
0301
207
Blu
ewat
er W
ind
Ene
rgy
Cen
tre
1:30
,000
Base
map
ping
from
Ont
ario
Min
istry
of N
atur
al R
esou
rces
040
080
01,
200
1,60
020
0
Met
res
This
dra
win
g ha
s be
en p
repa
red
for
the
use
of A
EC
OM
's c
lient
an
d m
ay n
ot b
e us
ed,
repr
oduc
ed o
r re
lied
upon
by
third
par
ties,
exce
pt a
s ag
reed
by
AE
CO
M a
nd i
ts c
lient
, as
req
uire
d by
law
or
for
use
by
gove
rnm
enta
l re
view
ing
agen
cies
. A
EC
OM
acc
epts
no
res
pons
ibili
ty,
and
deni
es a
ny l
iabi
lity
wha
tsoe
ver,
to a
ny p
arty
that
mod
ifies
this
dra
win
g w
ithou
t AE
CO
M's
exp
ress
writ
ten
cons
ent.
²Lege
ndW
ind
Ene
rgy
cent
re S
tudy
Are
a
Tran
smis
sion
Lin
e St
udy
Area
!(In
terc
onne
ctio
n Po
int
Mun
icip
al D
ivis
ion
Nat
ural
Fea
ture
sN
atur
al F
eatu
res
(ABC
A)
ABC
A Pr
oper
ties
Prov
inci
al P
ark
Dee
r Win
terin
g A
reas
Wat
erco
urse
Wat
erbo
dy
Car
togr
aphi
c W
etla
nd
! (Tu
rbin
es
Acce
ss R
oads
Col
lect
ion
Line
s
Tlin
e
Subs
tatio
n
Layd
own
Are
a
Dis
turb
ance
Are
a
Proj
ect L
ocat
ion
June
201
4 - 1
20m
Are
a of
In
vest
igat
ion
Path:
I:\GI
S\Ne
xtera
\GIS
Spati
al\M
XDs\R
epor
tMXD
s\NHA
_Map
ping\
Blue
wate
r\601
5503
2_BL
U_Po
le107
_061
3201
4.mxd
Cent
enni
alRd
HensallRd
Adde
d D
istu
rban
ce A
rea
Page 3 Memorandum June 16, 2014
3. 2014-06-13_BLW Project Modifications Memo_60301207_DRAFT.Docx
Attachment A Correspondence with MNR
AECOM 105 Commerce Valley Drive West, Floor 7 905 886 7022 tel Markham, ON, Canada L3T 7W3 905 886 9494 fax www.aecom.com
L_L_2014-06-09_Bluewater T-Line Pole 107_60310723.Docx
June 9, 2014
Mr. Joe Halloran Acting Renewable Energy Program Co-ordinator Ministry of Natural Resources Southern Region Phone: 705-755-5353 [email protected]
Dear Mr. Halloran:
Project No: 60310723 Regarding: Transmission Line Pole 107 – Bluewater Wind Energy Centre
Varna Wind Inc., a wholly owned subsidiary of NextEra Energy Canada, ULC (NextEra) is constructing a wind energy project in the Municipalities of Bluewater and Huron East in Huron County, Ontario. The project is referred to as the Bluewater Wind Energy Centre (the “Project”). AECOM Canada Ltd. (AECOM) was retained by NextEra to prepare a Natural Heritage Assessment and Environmental Impact Study Report for the proposed Project, in accordance with the requirements of the Renewable Energy Approval (REA) process.
The Ministry of Natural Resources (MNR) issued confirmation and re-confirmation letters on March 28, 2012, January 11, 2013 and October 3, 2013 for the Natural Heritage Assessment (NHA) and Environmental Impact Study (EIS) Report (AECOM, 2012), the NHA and EIS Report Amendment (AECOM, 2013a), and the NHA and EIS Report Second Amendment (AECOM, 2013b), respectively, met all requirements in accordance with the REA regulation for this project. The NHA and EIS Report and two Amendments are hereafter collectively referred to as the approved NHA and EIS.
This letter has been prepared to document a change to the Project Location that occurred after MNR confirmation of the approved NHA and EIS. An extension of the construction disturbance area within the Centennial Road right-of-way is required in order to accommodate a change in the location of transmission line pole 107. As shown on the attached map (Figure 1), there are no natural heritage features located within 120 m of the expanded construction disturbance area. This was confirmed during a site visit completed by AECOM’s Environmental Monitor (Jay Cashubec; please refer to attached CV for qualifications) on June 6, 2014, who identified no concerns regarding potential effects to the natural environment resulting from the construction of pole 107.
As such, there are no additional potential effects to significant natural heritage features or mitigation measures required to accommodate this change to the Project Location. Nonetheless, general mitigation measures previously described in the approved NHA and EIS and applied throughout the Project (e.g. erosion and sediment control measures, best management practices related to equipment use, material stockpiling and spills, etc) are considered sufficient to avoid or minimize the potential effects of construction of pole 107 on the natural environment.
Page 2June 9, 2014
L_L_2014-06-09_Bluewater T-Line Pole 107_60310723.Docx
Sincerely, AECOM Canada Ltd.
Jessica MacKay Ward, Ph.D. Ecologist [email protected]
JMW:mm Encl.
References
AECOM, 2012: Bluewater Wind Energy Centre Natural Heritage Assessment and Environmental Impact Study Report. Prepared for Varna Wind, Inc. March 2012.
AECOM, 2013a: Bluewater Wind Energy Centre Natural Heritage Assessment and Environmental Impact Study Report Amendment. Prepared for Varna Wind, Inc. January 2013.
AECOM, 2013b: Bluewater Wind Energy Centre Natural Heritage Assessment and Environmental Impact Study Report Second Amendment. Prepared for Varna Wind, Inc. August 2013.
Pat
h: I
:\GIS
\Nex
tera
\GIS
Sp
atia
l\MX
Ds\
Re
port
MX
Ds\
Ch
ange
_re
port
\BLU
_Cha
ngeR
epor
t_O
utpu
ts\6
0155
032_
BLW
_La
you
tCh
ange
sOve
rvie
wE
LC
Zoo
m_2
0140
606
.mxd
561
565
561
564
562
563
FOD
FOD
MA
S
FOD
MA
M2
FOD
5
FOD
SW
T
SW
D
SW
D
FOD
7-2
CU
M
SW
D
SW
D
MA
M2
CU
M
SW
T
FOD
MA
M
MA
M2
SW
D
SW
D3-
3
CU
P3
FOD
7-2
SW
D4-
1FO
D7-
2
FOD
Tile
Rd
Hensall Rd
Kippen Rd
Cent
enni
al Rd
Perth183Rd
28Li
ne
4660
00
4660
00
4680
00
4680
00
4816000
4816000
4818000
4818000
UT
M Z
one
17N
, NA
D 8
3
Proj
ect L
ocat
ion
Figu
re 1
June
201
4Pr
ojec
t 601
5503
2
Blue
wat
er W
ind
Ene
rgy
Cen
tre
This
dra
win
g ha
s be
en p
repa
red
for
the
use
of A
EC
OM
's c
lient
an
d m
ay n
ot b
e us
ed,
repr
oduc
ed o
r re
lied
upon
by
third
par
ties,
exce
pt a
s ag
reed
by
AE
CO
M a
nd i
ts c
lient
, as
req
uire
d by
law
or
for
use
by
gove
rnm
enta
l re
view
ing
agen
cies
. A
EC
OM
acc
epts
no
res
pons
ibili
ty,
and
deni
es a
ny l
iabi
lity
wha
tsoe
ver,
to a
ny p
arty
that
mod
ifies
this
dra
win
g w
ithou
t AE
CO
M's
exp
ress
writ
ten
cons
ent.
1:13
,000
Pro
duc
ed b
y A
EC
OM
un
der
licen
ce fr
om O
ntar
io M
inis
try o
f N
atu
ral R
esou
rces
, Co
pyrig
ht ©
Que
ens
Pri
nte
r 20
13
²
Lege
ndVe
geta
tion
Type
sC
UM
- C
ultu
ral M
eado
w
CU
P - C
ultu
ral P
lant
atio
n
CU
S -
Cul
tura
l Sav
anna
h
CU
T - C
ultu
ral T
hick
et
CU
W -
Cul
tura
l Woo
dlan
d
FOC
- C
onife
rous
For
est
FOD
- D
ecid
uous
For
est
FOM
- M
ixed
For
est
HE
D -
Hed
gero
w
MA
M -
Mea
dow
Mar
sh
MA
S -
Sha
llow
Mar
sh
OA
O -
Ope
n A
quat
ic
SAF
- Fl
oatin
g-le
aved
Sha
llow
Aqu
atic
SAS
- S
ubm
erge
d S
hallo
w A
quat
ic
SDT
- Tre
ed S
and
Dun
e
SWD
- D
ecid
uous
Sw
amp
SWT
- Thi
cket
Sw
amp
TPO
- O
pen
Tallg
rass
Pra
irie
TPS
- Ta
llgra
ss S
avan
nah
Lege
ndTr
ansm
issi
on L
ine
Stud
y A
rea
Win
d E
nerg
y C
entre
Stu
dy A
rea
Prop
ertie
s
Turb
ines
an
d P
erm
anen
t M
eter
olog
ical
Tow
er!(
Adde
d!(
Rem
oved
!(N
o C
hang
e
Layo
ut M
odifi
catio
n (T
ype,
Sta
tus)
Col
lect
ion
Line
, Add
ed
Col
lect
ion
Line
, Rem
oved
Col
lect
ion
Line
, No
Cha
nge
Acce
ss R
oad,
No
Cha
nge
Tran
smis
sion
Lin
e, N
o C
hang
e
Mod
ifica
tion
to D
istu
rban
ce A
reas
Stat
us Adde
dR
emov
edN
o C
hang
e
Layo
ut M
odifi
catio
n Lo
catio
nsA
1 (Au
gust
201
3 - 1
20m
Are
a of
Inve
stig
atio
n
Acce
ss R
oad,
Add
ed
Acce
ss R
oad,
Rem
oved
Nat
ural
Are
as
June
201
4 - 1
20m
Are
a of
Inve
stig
atio
n
Jay CashubecEnvironmental Technologist
EducationDiploma, Environmental Sciences/Environmental Technician, Sir Sandford Fleming College, 2008Environmental Site Assessment Course, Sheridan College, Brampton, Ontario, Canada, 2010
Years of Experience
With AECOM: 1With Other Firms: 5
Professional AssociationsCanadian Environmental Certification Approvals Board
Training and CertificationsEPt Environmental Practitioner in Training CertificationFirst Aid/CPR Training, Level CSmall Non-pleasure Vessel Basic Safety MED A3Drinking Water Operator Level 1Outdoor Wilderness Survival CertificationPleasure Craft Operator CardQuality Assurance Program for Environmental Investigations in Ontario2 Day Environmental Site Assessment Field Camp40-hour HAZWOPER Training, 8-hour Re-certificationWHMIS TrainingTechnical Writing 3 Day Bioscience Field Camp (Aquatic)Certificate in Ichthyology (ROM)Natural Biological Hazards TrainingATV Training Hazardous Material and Transportation of Dangerous Goods Shipping Awareness (CAN)Module 1 & 2 Behavior Based Safety Awareness (AECOM)Cold and Heat Stress Prevention TrainingElectrical Hazards Awareness (CCOHS)Heavy Equipment Hazard AwarenessIncident Investigation Awareness Canadian Due Diligence – OH&S TrainingRailroad General Worker Protection
Mr. Cashubec is an environmental technologist with over 6 years of experience with Phase II environmental site assessments (ESAs), Phase III ESA site remediation activities, and Phase 1 ESA components. He is proficient in a multitude of ground and surface water sampling techniques; as well as various means of soil sampling, well development procedures, low flow sampling methods, elevation surveys, and landfill and quarry monitoring. In addition, he is practiced in the writing of factual reports, and associated figures and tables for presenting data and well versed in working in remote environments, including use of helicopters and all terrain vehicles.
Mr. Cashubec has played an integral part in many projects that required the quality control measures of site specific risk assessments, Ontario Regulation 347, and Soil, Ground Water and Sediment Standard for Use under Part XV.1 of the Environmental Protection Act (EPA). He has also facilitated courses that teach sampling procedures in conjunction with the EPA Ontario Regulation 153/04, as amended.
In addition, Mr. Cashubec is experienced in soil vapour and gas monitoring and sampling. He is also experienced with ecological work including fish and benthic invertebrate identification and associated methods of capture. Work has included the drafting of in and near water works proposals, as well as endangered species mitigation plans. Mr. Cashubec has conducted creel surveys, water body and stream characterization, stream flow measurements, electrofishing, bathymetry, and amphibian surveys. He is also regularly responsible for equipment management and transportation, development of health and safety plans, program coordination, sample bottle orders, and service locates.
Project ExperienceSurface Water/Hydro Geology Lafarge, Aggregate Quarry Monitoring, Bath, Ontario; and Brantford, Ontario. Conducted stream flow measurements at various creeks and rivers surrounding quarry to assess water usage. Retrieved data loggers and downloaded information at multiple monitoring locations to assess groundwater levels. Ecology/BioscienceBruce Power, Power Facility – Entrainment Sampling, Kincardine, Ontario. Sampled for larval fish and eggs using a plankton net in conjunction with a swift water rescue system for lowering and raising the net in the water, as well as trolling a plankton net behind a boat on Lake Huron. Bruce Power, Power Facility - Creel Survey, Kincardine, Ontario. Conducted creel surveys at various boat launches. Work included fish identification, measurement, and scale samples. Lafarge, Proposed Quarry - Electrofishing, Mansfield, Ontario. Electrofished a cold water stream, including fish identification and measurement for baseline study, as well as habitat mapping. OPG, Baseline Fishery Studies, Darlington, Ontario. Assisted with setting and removal of gill nets for baseline study in Lake Ontario. This included the measuring, counting, and identification of different species within the great lakes system. OPG, Hydro-Electric Operating Facility - Fish Salvage, Niagara, Ontario. Participated with the salvaging of fish during the dewatering of the power facility. Salvaged and transported fish through various means of gill netting, trap netting, and electrofishing. This included the identification, measurement, and transportation of a variety of species. Managed sediment sampling program concerning environmental impacts. Mining Client, Proposed Lithium Mine, Chibougamou, Quebec. Responsible for organizing water sampling gear and protocols, as well as sample bottle requirements for a large scale surface water sampling program, including depth controlled water sampling, and sediment and benthic sampling. Work was conducted in a remote environment using helicopters, all-terrain vehicles, and 4-wheel drive trucks. Also responsible for retrieving samples for baseline fishery study. Gill netting, minnow traps, and electro-fishing were used; as well as water
Awareness Traffic Safety and Control Awareness Trench and Excavation Safety Awareness Working Around Water Safety Awareness
body and stream characterizing implemented. Mining Client, Proposed Iron Ore Mine, Iqualuit, Quebec. Crew lead on two different occasions in extremely remote environment in northern Quebec. Helicopters were used daily to travel to various locations for baseline fishery work, that involved gill netting, electro-fishing, stream and water body mapping and characterization (both from the ground and the air), bathymetry, and stream flow measurements. Meticulous care was needed for planning the work and the safe return of staff for the duration of the stay at the mining camp, in a predominately French speaking environment. Contaminated SitesConfidential Client, Phase II and III Assessment and Remedial Efforts, Oakville, Ontario. Managed drillers with the sampling and installation of monitoring wells. Sampled wells using low flow procedures. Observed appropriate quality control measures in accordance with Reg.153/04 and possible site specific risk assessment. AKZO/ICI, Phase II and III Testing and Remedial Efforts, Parry Sound, Ontario. Environmental technician involved with hand augering, soil delineation, sediment sampling, and surface and groundwater sampling to assess nitro-aromatic impact. Work also involved sediment sampling through lake ice and accompanying safety measures. Shawcor, Phase II and III Soil Delineation, Hamilton, Ontario. Managed the excavation of test pits to assess delineation of coal tar impact. FSM Management, Oil Water Separator and Groundwater Investigation, Mississauga, Ontario. Monitored oil water separators in accordance with TSSA regulations, and sampled effluent for petroleum hydrocarbon exceedances. Monitored and sampled groundwater wells within fuel storage tank farm area for petroleum hydrocarbon impact. Drafted multiple factual reports for client based on analytical data and information gathered on site. TransCanada Pipeline, Soil and Ground and Surface Water Investigation, Hearst, Ontario. Hand augured boreholes in and surrounding run-off ditch to assess hydrocarbon and metals impact in sediment. Sampled groundwater wells stretching from Ramore to 90 kilometres west of Hearst. IBM, Soil Vapour and Ambient Air Sampling, Toronto, Ontario. Conducted a soil vapour sampling program in an industrial building. Duties included installing sub-slab soil vapour probes; vacuum leak testing with helium; screening for various gases, including O2, CO2, CH4, He, and Isobutylene; and sampling via summa canisters and flow controllers. Ambient and background air samples were taken using summa canister’s and flow controllers for quality assurance. John Deere, Contaminate Mitigation between Adjacent Properties, Woodstock, Ontario. Responsible for retrieving defendable soil vapour samples, including vacuum leak tests using helium, collecting samples via flow controllers and summa canisters. Also responsible for low-flow groundwater sampling using peristaltic pump and flow- through cell to document geochemical parameters to ensure that stabilization had occurred and water was being sampled from the representative formation. All in accordance with Ministry of Environment/Environmental Protection Agency protocols. Hydro One, Phase II Proposed Hydro-Generating Station, Holland Landing, Ontario. Managed the installation of boreholes and monitoring wells. Conducted surface and groundwater sampling to assess the condition of the site and potential impacts. As well, collected soil samples to assess geotechnical soil integrity and composition for building purposes. Conducted GPS and shot elevation survey to ensure well location and flow of groundwater. Public Works and Government Services Canada, Phase I and II Site Investigation, Parry Sound, Ontario. Assisted with Phase I site visit for federal client. Managed drillers in conducting Phase II soil sampling and well installation regarding impact from former gas station. Public Works and Government Services Canada, Phase II Investigation, Multiple Sites, Toronto, Ontario. Working for a federal client, managed drillers in conducting soil sampling and well installations to assess subsurface impacts from armoury buildings on multiple sites across Toronto. Sampled water and shot elevation surveys to help determine groundwater flow direction. Federal Government Client, Phase II Investigation of Subsurface Impact, Thunder Bay, Ontario. Responsible for overseeing drillers while conducting soil sampling and well installation surrounding fire fighter training facility inside airport in-field. Organized and shipped soil and groundwater samples.
1
Cus
hing
, Jul
ia
From
:H
allo
ran,
Joe
(MN
R) <
Joe.
Hal
lora
n@on
tario
.ca>
Sent
:Tu
esda
y, J
une
10, 2
014
9:55
AM
To:
Mac
Kay
War
d, J
essi
caC
c:R
ose,
Mar
c; G
arci
a, A
ndre
a; T
ang,
Jon
atha
n; M
urra
y, J
ake;
Val
liant
, Em
ma
(MN
R);
Keyv
ani,
Moh
sen
(EN
E)
Subj
ect:
RE:
Blu
ewat
er W
EC -
Proj
ect L
ocat
ion
Cha
nge
for T
-line
Pol
e 10
7
Hi Je
ssic
a,
Than
k yo
u fo
r the
doc
umen
tatio
n de
taili
ng th
e pr
opos
ed p
roje
ct m
odifi
catio
n at
the
Blue
wat
er W
ind
Ener
gy C
entr
e.
In re
view
of t
he in
form
atio
n, a
NHA
re-c
onfir
mat
ion
from
MN
R is
not r
equi
red.
The
pro
pose
d pr
ojec
t mod
ifica
tion
will
not
affe
ct th
e N
atur
al H
erita
geAs
sess
men
t alre
ady
conf
irmed
by
MN
R.
Chee
rs,
Joe
Hal
lora
nSo
uthe
rn R
egio
nPh
: 705
-755
-535
3jo
e.ha
llora
n@on
tario
.ca
From
: M
acKa
y W
ard,
Jes
sica
[m
ailto
:Jes
sica
.Mac
KayW
ard@
aeco
m.c
om]
Sen
t: J
une
9, 2
014
6:52
PM
To:
Hal
lora
n, J
oe (
MN
R)C
c: R
ose,
Mar
c; G
arci
a, A
ndre
a; T
ang,
Jon
atha
n; M
urra
y, J
ake
Sub
ject
: Bl
uew
ater
WEC
- P
roje
ct L
ocat
ion
Chan
ge fo
r T-
line
Pole
107
Hi Jo
e,
Plea
se fi
nd a
ttac
hed
a le
tter
we
have
pre
pare
d re
gard
ing
a ch
ange
to th
e Bl
uew
ater
Win
d En
ergy
Cen
tre
Proj
ect L
ocat
ion.
An
exte
nsio
n of
the
tran
smiss
ion
line
cons
truc
tion
dist
urba
nce
area
with
in th
e Ce
nten
nial
Roa
d rig
ht-o
f-way
is re
quire
d in
ord
er to
acc
omm
odat
e a
chan
ge in
the
loca
tion
of p
ole
107.
We
kind
ly re
ques
t con
firm
atio
n th
at th
is ch
ange
is a
ccep
tabl
e to
MN
R.
Best
rega
rds,
Jess
ica
2
Jess
ica
Mac
Kay
War
d, P
h.D.
Ecol
ogis
t, En
viro
nmen
tD:
905
-747
-751
4 C
: 416
-333
-527
4Je
ssic
a.M
acKa
yWar
d@ae
com
.com
AECO
M10
5 Co
mm
erce
Val
ley
Driv
e W
est,
7th
Floo
rM
arkh
am, O
N
L3T
7W3
T: 9
05-8
86-7
022
F: 9
05-8
86-9
494
ww
w.a
ecom
.com
Page 4 Memorandum June 16, 2014
3. 2014-06-13_BLW Project Modifications Memo_60301207_DRAFT.Docx
Attachment B Stage 2 Report and Correspondence from MTCS
Environment
Varna Wind, Inc.
Stage 2 Archaeological Assessment Centennial Road and Hensall Road ROWTransmission Line Study for Bluewater Wind Energy CentreGeographic Township of TuckersmithMunicipality of Huron East, Huron County, Ontario
Licensee: Erik PhaneufLicense: P393PIF Number: P393-0027-2013
Prepared by:AECOM410 – 250 York Street, Citi Plaza 519 673 0510 telLondon, ON, Canada N6A 6K2 519 673 5975 faxwww.aecom.com
Project Number: 60301207FIT Number: FIT-FJI7S7X
Date:June 10, 2013REVISED REPORT
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
Distribution List
Hard Copy # PDF Association / Company Name
0 yes Varna Wind, Inc.
0 yes Ontario Ministry of Tourism, Culture and Sport
1 yes AECOM
Revision Log
Revision # Revised By Date Issue / Revision Description
1 A. Grant 10 June 2014 Revised to show all areas subject to assessment
AECOM Signatures
Report Prepared By:Adria Grant, BA, CAHPArchaeology Practice Lead
Report Reviewed By:Marc Rose, MES, MCIP, RPPSenior Environmental Planner
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
Executive Summary
AECOM Canada Ltd. (AECOM) was contracted by Varna Wind, Inc., a wholly owned subsidiary of NextEra Energy Canada, ULC, to conduct a Stage 2 archaeological assessment of additional land to be impacted by the proposed transmission line route to the Bluewater Wind Energy Centre (WEC) in the Municipality of Huron East, Huron County, Ontario. The land subject to assessment consists of 75 m of the road right-of-way (ROW) of Centennial Road south of Hensall Road, and Hensall Road south of Centennial Road which will be impacted by the placement of transmission poles, located within the Geographic Township of Tuckersmith, now the Municipality of Huron East, Huron County, Ontario. This report documents the background research, fieldwork methods and results and presents conclusions and recommendations pertaining to archaeological concerns in these areas.
This Stage 2 archaeological assessment was conducted to meet the requirements for an application for a Renewable Energy Approval (FIT-FJI7S7X), as outlined in Ontario Regulation 359/09 section 22(3) of the Environmental Protection Act (Ontario Government 2009a). According to section 22(1) of O. Reg 359/09, an archaeological assessment must be conducted if it is deemed that archaeological materials will be impacted during the renewable energy project. In 2012 Golder Associates Ltd. (Golder) deemed the Bluewater WEC to have a moderate to high archaeological potential for pre-contact Aboriginal archaeological material and a moderate to high potential for Euro-Canadian archaeological material (Golder 2012a). This project is also subject to the Ontario Heritage Act (Government of Ontario 1990b) and the Standards and Guidelines for Consultant Archaeologists(Government of Ontario 2011).
The Stage 2 archaeological assessment for the 75 m section of Centennial Road ROW south of Hensall Road, and the 75 m section of Hensall Road ROW south of Centennial Road did not result in the identification of any archaeological sites or material. The entire subject property was found to be extensively previously disturbed and did not retain archaeological integrity. Archaeological concerns in this area may be considered addressed and no further archaeological work is required.
The Ministry of Tourism, Culture and Sport is asked to accept this report into the Ontario Public Register of Archaeological Reports and issue a letter of concurrence with the recommendation that archaeological concerns under land use planning and development processes are considered addressed and no further archaeological assessment is required.
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
Project Personnel
Project Director Marc Rose, M.E.S., MCIP, RPP
Project Manager Adria Grant, BA, (R131), Archaeology Practice Lead
Licensed Archaeologist Erik Phaneuf, (P393), Professional Archaeologist
Report Production Jennifer Morgan, MA
Field Supervisor Adria Grant, BA, CAHP (R131), Nancy Van Sas, BA (R323)
Field/Lab Technicians Adria Grant, BA, CAHP (R131)
Project Support Stephanie Patzer, Environmental Engineer
GIS Analyst Paul Adams
Acknowledgements
Proponent Contact Andrea Garcia, NextEra Energy Canada, ULC
Municipality of Huron East Barry Mills, Public Works
Ministry of Tourism, Culture Archaeological Data Coordinatorand Sport Archaeological Review Coordinator
Jim Sherratt, Archaeology Team Lead
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
Table of Contents
Distribution ListExecutive SummaryProject Personnel
page
1. Project Context ............................................................................................................................11.1 Development Context .......................................................................................................................... 1
1.1.1 Objectives ............................................................................................................................... 21.2 Historical Context................................................................................................................................. 2
1.2.1 Pre-Contact Aboriginal Settlement ......................................................................................... 21.2.2 Post-Contact Aboriginal Settlement........................................................................................ 41.2.3 Euro-Canadian Settlement ..................................................................................................... 51.2.4 Reports with Relevant Background Information ..................................................................... 6
1.3 Archaeological Context........................................................................................................................ 81.3.1 Natural Environment ............................................................................................................... 81.3.2 Known Archaeological Sites and Surveys .............................................................................. 81.3.3 Determination of Archaeological Potential ............................................................................. 91.3.4 Existing Conditions ............................................................................................................... 10
2. Field Methods............................................................................................................................. 11
3. Record of Finds.......................................................................................................................... 12
4. Analysis and Conclusions......................................................................................................... 13
5. Recommendations..................................................................................................................... 14
6. Bibliography and Sources......................................................................................................... 15
7. Images ........................................................................................................................................ 197.1 Photographs ...................................................................................................................................... 19
8. Maps ........................................................................................................................................... 22
9. Advice on Compliance with Legislation................................................................................... 27
List of Figures
Figure 1: Location of Study Area............................................................................................................................. 23Figure 2: Study Area in Detail ................................................................................................................................. 24Figure 3: A Portion of the 1879 Map of the Geographic Township of Tuckersmith ................................................ 25Figure 4: Methods and Results of the Stage 2 Field Investigation.......................................................................... 26
List of Tables
Table 1: Cultural Chronology for Huron County ............................................................................................................ 2Table 2: Archaeological Assessment Reports for Bluewater Wind Energy Centre....................................................... 6Table 3: Registered Archaeological Sites within the Bluewater WEC Study Area....................................................... 8Table 4: Inventory of Documentary Record................................................................................................................. 12
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
1. Project Context1.1 Development Context
AECOM Canada Ltd. (AECOM) was contracted by Varna Wind, Inc., a wholly owned subsidiary of NextEra Energy Canada, ULC, to conduct a Stage 2 archaeological assessment of additional land to be impacted by the proposed transmission line route to the Bluewater Wind Energy Centre (WEC) in the Municipality of Huron East, Huron County, Ontario. The land subject to assessment consists of 75 meters (m) of the road right-of-way (ROW) of Centennial Road south of Hensall Road, and Hensall Road south of Centennial Road which will be impacted by the placement of transmission poles, located within the Geographic Township of Tuckersmith, now the Municipality of Huron East, Huron County, Ontario. This report documents the background research, fieldwork methods and results and presents conclusions and recommendations pertaining to archaeological concerns in these areas.
This Stage 2 archaeological assessment was conducted to meet the requirements for an application for a Renewable Energy Approval (FIT-FJI7S7X), as outlined in Ontario Regulation 359/09 section 22(3) of the Environmental Protection Act (Ontario Government 2009a). According to section 22(1) of O. Reg 359/09, an archaeological assessment must be conducted if it is deemed that archaeological materials will be impacted during the renewable energy project. In 2012 Golder Associates Ltd. (Golder) deemed the Bluewater WEC to have a moderate to high archaeological potential for pre-contact Aboriginal archaeological material and a moderate to high potential for Euro-Canadian archaeological material (Golder 2012a). This project is also subject to the OntarioHeritage Act (Government of Ontario 1990b) and the Standards and Guidelines for Consultant Archaeologists(Government of Ontario 2011).
The project is referred to as the Bluewater WEC and is located in the Municipalities of Bluewater and Huron East, Huron County, Ontario. The Bluewater WEC project involves the site preparation, construction, operation, and decommissioning of a Class 4 wind generating facility. The major components of the project include:
40 GE 1.6 MW Wind Turbine generator locations with pad mounted step-up transformers (a maximum of 37 turbines will ultimately be constructed)
Turbine access roads (approximately 40 km)
Temporary and permanent laydown and storage areas
Approximately 52 km of 34.5 kV underground electrical collection lines
Approximately 24 km of 115 kV transmission line proposed along Centennial Road and Hensall Road from the proposed transformer substation to the existing Hydro One Seaforth Transformer Station
Operations and maintenance building
A Stage 1 archaeological assessment was conducted by Golder (2012a) and following the Stage 1 archaeological assessment, a Stage 2 field investigation was carried out on the majority of the lands to be impacted during the proposed development of the Bluewater WEC by Golder (2012b, 2013a) and Archaeological Research Associates Ltd. (ARA) (2013a, 2013b). The following report pertains to two sections of ROW that were not previously assessed during the Stage 2 archaeological assessments for the Bluewater WEC and will be impacted by the Transmission Line.
1
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
Permission to access the study area to conduct all required archaeological fieldwork activities was provided by Andrea Garcia of NextEra Energy Canada, ULC and Barry Mills of the Municipality of Huron East. There were no limits placed on access.
The MTCS is asked to review the results and recommendations presented in this report and provide a Letter of Review and Acceptance into the Ontario Public Register of Archaeological Reports.
1.1.1 Objectives
The objective of the Stage 2 property assessment is to determine if any archaeological resources are present on the ROW land and to make a determination on whether any of the resources might be artifacts or archaeological sites with cultural heritage value or interest requiring further assessment, and to recommend appropriate Stage 3 assessment strategies for any archaeological sites identified.
1.2 Historical Context
The study area consists entirely of the ROW land, extending 75 m south of the intersection of Centennial Road and Hensall Road along both roadways. The study area consists of Lot 5, Concession 6 north of Centennial Road andeast of Hensall Road; Lot 5, Concession 7 south of Centennial Road, east of Hensall Road; and, Lot 6, Concession 7 south of Centennial Road, west of Hensall Road, in the Geographic Township of Tuckersmith, now the Municipality of Huron East, Huron County, Ontario.
1.2.1 Pre-Contact Aboriginal Settlement
It has been demonstrated that Huron County has been extensively utilized by pre-contact Aboriginal people who began occupying southwestern Ontario as the glaciers receded from the land, as early as 11,000 B.C. Table 1provides a breakdown of the cultural and temporal history of past occupations in the Huron County, drawn from Ellis and Ferris (1990).
Table 1: Cultural Chronology for Huron County
Archaeological Period Characteristics Time Period Comments
Early Paleo-Indian Fluted Points 9000-8400 BC Arctic tundra and spruce parkland, caribou hunters
Late Paleo-Indian Holcombe, Hi-Lo and Lanceolate Points 8400-8000 BC Slight reduction in territory size
Early Archaic Notched and Bifurcate base Points 8000-6000 BC Growing populations
Middle Archaic Stemmed and Brewerton Points, Laurentian Development 6000-2500 BC Increasing regionalization
Late ArchaicNarrow Point 2000-1800 BC Environment similar to presentBroad Point 1800-1500 BC Large lithic toolsSmall Point 1500-1100 BC Introduction of bow
Terminal Archaic Hind Points, Glacial Kame Complex 1100-950 BC Earliest true cemeteriesEarly Woodland Meadowood Points 950-400 BC Introduction of pottery
Middle Woodland Dentate/Pseudo-scallop Ceramics 400 BC – AD 500 Increased sedentism
Late Woodland
Riviere au Vase Phase AD 500-800 Seasonal hunting and gathering
Younge Phase AD 800-1200 Agriculture combined with seasonal rounds
Springwells Phase AD 1200-1400 Agricultural villagesWolf Phase AD 1400-1500 Earthworked villages, warfare
Contact Aboriginal Various Algonkian and Iroquoian Groups AD 1600-1875 Early written records and
treatiesEuro-Canadian French and English Euro-Canadian AD 1749-present European settlement
Note: taken from Ellis and Ferris, 1990
2
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
As Chapman and Putnam (1984) illustrate, the modern physiography of southern Ontario is largely a product of events of the last major glacial stage and the landscape is a complex mosaic of features and deposits produced during the last series of glacial retreats and advances prior to the withdrawal of the continental glaciers from the area. Southwestern Ontario was finally ice free by 12,500 years ago. With continuing ice retreat and lake regressions the land area of southern Ontario progressively increased while barriers to the influx of plants and animals steadily diminished (Karrow and Warner 1990).
The first human settlement can be traced back 11,000 years; these earliest well-documented groups are referred to as Paleo-Indians which literally means old or ancient Indians. Paleo-Indian people were non-agriculturalists who depended on hunting and gathering of wild food stuffs; they would have moved their encampments on a regular basis to be in the locations where these resources naturally became available and the size of the groups occupying any particular location would vary depending on the nature and size of the available food resources (Ellis and Deller 1990). The picture that has emerged for early and late Paleo-Indian people is of groups at low population densities who were residentially mobile and made use of large territories during annual cycles of resource exploitation (Ellis and Deller 1990).
The next major cultural period following the Paleo-Indian is termed the Archaic, which is broken temporally into the Early, Middle and Late. There is much debate on how the term Archaic is employed; general practice bases the designation off assemblage content as there are marked differences in artifact suites from the preceding Paleo-Indian and subsequent Woodland periods. As Ellis et al (1990) note, from an artifact and site characteristic perspective the Archaic is simply used to refer to non-Paleo-Indian manifestations that pre-date the introduction of ceramics. Throughout the Archaic period the natural environment warmed and vegetation changed from closed conifer-dominated vegetation cover, to mixed coniferous and deciduous forest to the mixed coniferous and deciduous forest in the north and deciduous vegetation in the south we see in Ontario today (Ellis et al 1990). During the Archaic period there are indications of increasing populations and decreasing size of territories exploited during annual rounds: fewer moves of residential camps throughout the year and longer occupations at seasonal campsites; continuous use of certain locations on a seasonal basis over many years; increasing attention to ritual associated with the deceased; and, long range exchange and trade systems for the purpose of obtaining valued and geographically localized resources (Ellis et al 1990).
In the 17th century two major language families, Algonquian and Iroquoian, were represented by the diverse people of North America. Iroquoian speaking people were found in southern Ontario and New York State, with related dialects spoken in the mid-Atlantic and interior North Carolina, while Algonquian speaking peoples were locatedalong the mid-Atlantic coast into the Maritimes, throughout the Canadian Shield of Ontario and Quebec and much of the central Great Lakes region (Ellis et al 1990). Linguists and anthropologists have attempted to trace the origin and development of these two language groups and usually place their genesis during the Archaic (Ellis et al 1990).
The Early Woodland period is distinguished from the Late Archaic period primarily by the addition of ceramic technology, which provides a useful demarcation point for archaeologists but is expected to have made less difference in the lives of the Early Woodland peoples. The settlement and subsistence patterns of Early Woodland people shows much continuity with the earlier Archaic with seasonal camps occupied to exploit specific natural resources (Spence et al 1990). During the Middle Woodland well-defined territories containing several key environmental zones were exploited over the yearly subsistence cycle. Large sites with structures and substantial middens appear in the Middle Woodland associated with spring macro-band occupations focussed on utilizing fish resources and created by consistent returns to the same site (Spence et al 1990). Groups would come together into large macro-bands during the spring-summer at lakeshore or marshland areas to take advantage of spawning fish; in the fall inland sand plains and river valleys were occupied for deer and nut harvesting and groups split into small
3
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
micro-bands for winter survival (Spence et al 1990). This is a departure from earlier Woodland times when macro-band aggregation is thought to have taken place in the winter (Ellis et al 1988; Granger 1978).
The period between the Middle and Late Woodland period was both technically and socially transitional for the ethnically diverse populations of southern Ontario and these developments laid the basis for the emergence of settled villages and agriculturally based lifestyles (Fox 1990). The Late Woodland period began with a shift in settlement and subsistence patterns involving an increasing reliance on maize horticulture. Corn may have been introduced into southwestern Ontario from the American Midwest as early as 600 A.D.; however, it did not become a dietary staple until at least three to four hundred years later. A more sedentary lifestyle was adopted by the Ontario Iroquoians and villages with longhouses and palisades were occupied by large numbers of people. Increased warfare is inferred from the defensive placement of village walls and recorded changes over time in village organization are taken to indicate the initial development of the clans which were a characteristic of the historically known Iroquoians.
A distinct cultural occupation was present in the Late Woodland in the western-most corner of southern Ontario in the modern counties of Kent, Essex and Lambton as well as portions of west Middlesex and west Elgin. This emerging cultural manifestation is generally classified as Western Basin Tradition and has been observed in south-eastern Michigan and north-western Ohio. The inhabitants of these communities are considered distinct from Iroquoian groups to the east and Mississipian to the south. In recent years research has indicated that there was more variability in settlement-subsistence patterns within Western Basin Tradition groups than previously thought, the most surprising being evidence of significant maize consumption (Watts et al 2011). Western Basin Tradition people had previously been thought to maintain seasonal hunting and gathering cycles and non-sedentary lifestyles and much evidence has been recorded from seasonal occupation sites (Murphy and Ferris 1990); however, recent research in the Arkona area of Lambton County has uncovered large agriculturally based villages (Golder 2012). We now understand the Western Basin Tradition as Late Woodland people who combined seasonal hunting and gathering along with maize horticulture and lived in short-term camps, large palisaded villages and everything in between. The radical changes that agricultural practice brought to the Early Ontario Iroquoian people living to the east did not have the same impact on settlement-subsistence patterns in the Western Basin Tradition.
Archaeologists are able to trace archaeologically known groups from this time period to the historically documented people identified when French fur traders first arrived (Wright 1994). The Ontario Iroquois from southern Ontario gave rise to the Huron, Petun, Neutral and Erie; the St. Lawrence Iroquois, a distinct population encountered by Jaques Cartier in 1535 that had disappeared by the time Samuel de Champlain returned to the same area in 1603; and from Northern Ontario the groups that gave rise to the Algonquian speaking Cree, Ojibwa and Algonquin people (Wright 1994).
1.2.2 Post-Contact Aboriginal Settlement
The post-contact Aboriginal occupation of southern Ontario was heavily influenced by the dispersal of Iroquoian speaking peoples, such as the Huron, Petun and Neutral by the New York State Confederacy of Iroquois, followed by the arrival of Algonkian speaking groups from northern Ontario. The Ojibwa of southern Ontario date from about 1701 and occupied the territory between Lakes Huron, Erie and Ontario (Schmalz 1991). This is also the period in which the Mississaugas are known to have moved into southern Ontario and the Great Lakes watersheds (Konrad 1981) while at the same time the members of the Three Fires Confederacy, the Chippewa, Ottawa and Potawatomi were immigrating from Ohio and Michigan (Feest and Feest 1978). As European settlers encroached on their territory the nature of Aboriginal population distribution, settlement size and material culture changed. Despite these changes it is possible to correlate historically recorded villages with archaeological manifestations and the similarity of those sites to more ancient sites reveals an antiquity to documented cultural expressions that confirms a long historical continuity to Iroquoian systems of ideology and thought (Ferris 2009). First Nations people of southern
4
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
Ontario have left behind archaeological resources throughout the Great Lakes region that show continuity with past peoples even if this was not recorded in Euro-Canadian documentation.
The study area within Huron County was most likely occupied by Algonkian-speaking groups who also exhibitedcultural influence from Iroquoian-speaking groups, both before and after European contact. Generally, the pre-contact Aboriginal presence in much of southern Ontario reflects occupation by Northern Iroquoian speakers.During and following the Iroquois Wars of the mid-17th century and the dispersal of the Iroquoian-speaking Huron-Petun and Neutral, a considerable reduction in the extent of territory occupied by Iroquoian speakers occurred in southern Ontario. Beginning about 1690 Algonkian speakers from northern Ontario began to move southwards (Ferris 2009; Rogers 1978:761; Schmalz 1991). It has been presumed that occupation of Huron County before about 1690 would have been by Iroquoians, but the Middle Woodland Saugeen Complex, known best from locations just north of Huron County in the Saugeen River valley such as the Donaldson site, is most often interpreted as Algonkian (Fiedel 1999), arguing for an occupation of Huron County by Algonkian speakers for millennia. Dating somewhat later than the Donaldson site, Wright (1974:303; Fox 1990:461) believed that the isolated occurrence of a palisaded village in neighbouring Bruce County at the Middle Ontario Iroquoian-like (Middleport substage) Nodwell site established a case for immigration by the Iroquoian-speaking Huron. More recently, however, Rankin (2000) has argued that the Nodwell village represents a short-lived sedentary farming experiment by hunter-gatherers, probably indigenous Algonkian speakers, who may have been ancestral to the Odawa (see also Warrick 2008:159). French missionaries indicated relatively close ties between the Odawa and the Huron-Petun (Fox 1990; cf. Feest and Feest 1978:773).
Ferris (1999:119-120) has also pointed out the potential misuse in the literature of the designation “Huron” todescribe sites in Huron and Bruce County. As Koenig (2005:61-61) indicates, there are some who argue that the ancestors of those Algonkian speaking First Nations now occupying the shores of Lake Huron and Bruce Peninsula only arrived in the mid-1800s, relating to known relocations from the U.S. and the establishment of reserves (Surtees 1971:48). In southwestern Ontario, however, members of the Three Fires Confederacy (Chippewa, Ottawa and Potawatomi) were immigrating from Ohio and Michigan in the late 1700s (Feest and Feest 1978:778-779). Still, archaeological sites in Huron County point to much earlier settlement, probably by at least some of their ancestors. So, during the Late Woodland period, there is evidence that the study area could have been inhabited by Algonkianor Iroquoian speaking groups, or a combination of groups.
While it is difficult to trace ethnic affiliation during the period of initial contact between Aboriginal and Europeangroups, Koenig states that “there is no doubt that some native groups regularly occupied sites on the [Bruce]peninsula at the end of [the early historic] period” (2005:62). Feest and Feest (1978:772-773) imply that the Bruce Peninsula was Odawa territory from 1616 and early 17th century French glass trade beads at the Glen and Cripps sites on the northern tip of the Bruce Peninsula appear to attest to this (Fox 1990:465-466). Fox not only points to Odawa (or Ottawa) settlement on the Bruce Peninsula during the mid-1600s at Hunter’s Point, but also to sites in the southern Bruce County littoral such as the Hunter site on the Saugeen Reserve, dating about 1600 (1990:462, 472), as well as the Inverhuron-Lucas site (1990:463). Abandonment of this area by the Odawa seems to have occurred, at least briefly, in the mid-1600s due to the Iroquois Wars (Fox 1990:472). By 1690, Algonkian speakers from the north appear to have begun to repopulate Huron and Bruce Counties (Rogers 1978:761). This is the period in which the Mississaugas are known to have moved into southern Ontario and the Lower Great Lakes watersheds (Konrad 1981).
1.2.3 Euro-Canadian Settlement
This area first enters Euro-Canadian documentation as part of Treaty 27½ made between the Chippewa First Nations and James Givens, representative of the Crown on the 26th of April 1825 and is described as:
5
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
… an agreement made at Amherstburg in the Western District of the Province of Upper Canada on the 26th of April, 1825, between James Givens, Esquire, Superintendent of Indian Affairs, on behalf of His Majesty King George the Fourth and the Chiefs and Principal Men of the part of the Chippewa Nation of Indians, inhabiting and claiming the tract of land … . Wawanosh Township in the County of Huron was named after Way-way-nosh the principal Chief of the Band making this Treaty.
Morris 1943: 26-27
Treaty Number 27½ was subsequently confirmed on July 10th, 1827 as Treaty Number 29 with only a minor change in the legal description of the boundaries of the land surrender (Morris 1943:27).
The Euro-Canadian creation and settlement of Huron County was largely due to the Canada Company, itself formed in 1824, purchasing a large parcel of land known as the Huron Tract and preparing it for settlement by British settlers. The Huron Tract was mostly surveyed by Deputy Provincial Surveyor John McDonald on behalf of the Canada Company.
By the late 1800’s Huron County and the Township of Tuckersmith had been subject to years of settlement and development by Euro-Canadian pioneers. According to the 1879 Illustrated Historical Atlas of Huron County Ontario, Township of Tuckersmith G. Laidlaw was the owner of Lot 5, Concession 6, A. Sproat was the owner of the western quarter of Lot 5, Concession 7, and M. O’Keefe was the owner of Lot 6, Concession 7 (Belden & Co. 1879).Structures associates with these owners are shown to be some distance from the current study areas. The 19th
century map indicates the dense settlement of Euro-Canadian people in this area. The community of Egmondville is located north to the north and Brucefield is west of the current study area. The current road grid is in place and recognizable as the transportation system still in use today. Figure 3 provides a portion of the 1879 map with the study areas illustrated.
Additional detailed information on the Euro-Canadian settlement of this area, and specifically the Geographic Township of Tuckersmith, may be found in the Stage 1 archaeological assessment report for the Bluewater WEC (Golder 2012a).
1.2.4 Reports with Relevant Background Information
The project area has been the subject of a series of archaeological assessments conducted as part of the Bluewater WEC and Transmission Line Study. A list of these archaeological assessments is provided in Table 2. The report with relevant background information for the current study area is the Stage 1 report; however other reports provide information on archaeological resources and additional areas subject to archaeological assessment in the vicinity.
Table 2: Archaeological Assessment Reports for Bluewater Wind Energy Centre
Year Title Author PIF Number(s)2012a Stage 1 Archaeological Assessment, NextEra Energy Canada, ULC, Bluewater
Wind Energy Centre, Huron County, Ontario.Golder P001-609-2010
2012b Stage 2 Archaeological Assessment, NextEra Energy Canada, ULC, Bluewater Wind Energy Centre, Huron County, Ontario (Final Report).
Golder P218-040-2011, P319-017-2012
2013a Stage 2 Archaeological Assessment, Bluewater Wind Energy Centre, Location 26 through 35, Various Lots and Concessions, Geographic Township of Stanley, Hay and Tuckersmith, now Municipalities of Bluewater and Huron East, Huron County, Ontario (Revised Report)
Golder P218-275-2012
2013b Stage 3 Archaeological Assessment, Bluewater Wind Energy Centre, Locations Golder P218-279, 280,
6
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
13, 14, 24 and 25, Various Lots and Concessions, Geographic Township of Hay and Stanley, Huron County, Ontario.
281, 282-2012
2013a Stage 2 Property Assessment, Additional Lands and ROWs, Bluewater Wind Energy Centre, FIT-FJI7S7X, Multiple Lots and Concessions, Municipalities of Bluewater and Huron East, Geographic Townships of Hay, Stanley and Tuckersmith, Huron County, Ontario.
ARA P007-522-2013
2013b Stage 2 Property Assessment, Heavy Haul Route Turns, Bluewater Wind EnergyCentre, FIT-FJI7S7X, Municipality of Bluewater Multiple Lots and Concessions,Geographic Townships of Hay and Stanley Huron County, Ontario.
ARA P089-0032-2013
2013c Stage 3 Site-Specific Assessment, Location 13 (AiHj-6), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 10, Concession 11, Geographic Township of Stanley, Huron County, Ontario.
ARA P089-025-2013
2013d Stage 3 Site-Specific Assessment, Location 14 (AiHk-1), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 9, Concession 8, Geographic Township of Stanley, Huron County, Ontario.
ARA.P089-026-2013
2013e Stage 3 Site-Specific Assessment, Location 24 (AiHj-9), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 24, North Boundary, Geographic Township of Hay, Huron County, Ontario.
ARAP089-027-2013
2013f Stage 3 Site-Specific Assessment, Location 25 (AjHj-14), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 17, Concession 9, Geographic Township of Stanley, Huron County, Ontario.
ARAP089-028-2013
2013g Stage 3 Site-Specific Assessment, Location 25 (AjHj-14), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 17, Concession 9, Geographic Township of Stanley, Huron County, Ontario.
ARAP089-031-2013
2013h Stage 3 Site-Specific Assessment, Location 30 (AjHi-12), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Huron East, Part of Lot 23, Concession 4 ELR, Geographic Township of Tuckersmith, Huron County, Ontario.
ARAP007-544-2013
2013i Stage 4 Mitigation of Development Impacts, Location 14 (AiHk-1), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 9, Concession 8, Geographic Township of Stanley, Huron County, Ontario.
ARAP007-506-2013
2013j Stage 4 Mitigation of Development Impacts, Location 13 (AiHj-6), Bluewater Wind Energy Centre, FIT-FJI7S7X, Part of Lot 10, Concession 11, Municipality of Bluewater, Geographic Township of Stanley, Huron County, Ontario.
ARAP007-557-2013
2013k Stage 4 Mitigation of Development Impacts, Location 24 (AiHj-9), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 24, North Boundary, Geographic Township of Hay, Huron County, Ontario.
ARAP007-558-2013
2013l Stage 4 Mitigation of Development Impacts, Location 25 (AjHj-14), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 17, Concession 9, Geographic Township of Stanley, Huron County, Ontario.
ARAP007-559-2013
7
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
1.3 Archaeological Context
1.3.1 Natural Environment
The study area falls within the Horseshoe Moraines physiographic region as described by Chapman and Putnam (1966). The Horseshoe Moraines physiographic region:
…forms the core of a horseshoe-shaped region flaking the upland that lies to the west…The southwestern limb of the region, typically seen as the southern part of Huron County, has a fairly simple landscape. Structurally it consists of two, and in some places three moranic ridges composed of pale, brown, hard, calcareous fine-textured till, with a moderate degree of stoniness. Huron clay loam is the most representative soil type of themoranic ridges and it occurs quiet widely in other well drained areas as well. The average depth of the Huron profile is from 18 to 20 inches and even though the slopes are generally moderate, the top soil is susceptible to erosion.
Chapman and Putnam 1966:198
The topography of the study area was found to be relatively level. The closest source of potable water is the Broadfoot Drain which is situated approximately 450 m west of the intersection of Centennial Road and Hensall Road. Lake Huron is located approximately 25 km to the west of this location.
1.3.2 Known Archaeological Sites and Surveys
Previous assessments have indicated that Huron County was intensively occupied by pre-contact Aboriginal people and early Euro-Canadian pioneers. During the Stage 1 background study Golder consulted the Archaeological Sites Database (ASDB) and reported 12 archaeological sites within the limits of the Bluewater WEC study area, including ten pre-contact Aboriginal sites and two multi-component sites. Table 3 provides a breakdown of the archaeological sites within the study area, according to the Stage 1 archaeological assessment by Golder (2012a).
Table 3: Registered Archaeological Sites within the Bluewater WEC Study Area
Cultural Affiliation Site Type Number of Sites
Pre-Contact Aboriginal Campsite 5
Pre-Contact Aboriginal Findspot 3
Pre-Contact Aboriginal/Historic Euro-Canadian
Campsite 1
Archaic/Historic Euro-Canadian
Campsite/House 1
Middle Woodland Campsite 1
Woodland Campsite 1
Two phases of Stage 2 archaeological assessments were subsequently completed by Golder (2012b, 2013a). Thefirst phase was carried out between May 5, 2011 and March 22, 2012 under the PIF numbers P218-040-2011 and P319-017-2012 (Golder 2012b). The second phase was conducted between April 4, 2012 and August 7, 2012 under PIF P218-275-2012(Golder 2013a). ARA also carried out Stage 2 assessments of additional lands and ROWsbetween May and August 2013 under PIF P007-522-2013, as well as an assessment of lands with the potential to be impacted by the proposed turbine delivery route to the Bluewater WEC in July, August, and October 2013 under PIF P089-0032-2013 (ARA 2013a, 2013b).
8
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
A total of 39 archaeological sites (Locations 1–35, Locations 36–37) were identified during the Stage 2 archaeological assessments and included 21 pre-contact Aboriginal sites and 16 Euro-Canadian sites. Twelve of these sites (Locations 13–14, 24–26, 28–33 and 36) were recommended for Stage 3 archaeological assessment (Golder 2012b: Table 52; 2013a: Table 41, ARA 2013a: 46–47). An additional two Euro-Canadian sites (Locations 38 and 39) were identified during the assessment of lands with the potential to be impacted by the proposed turbine delivery route (ARA 2013b). These sites were found to be of no further cultural heritage value or interest and were not recommended for Stage 3 assessment (ARA 2013b: 50). Golder and ARA subsequently conducted Stage 3 site-specific assessments and Stage 4 mitigations of development impacts at those sites within the project location that could not be avoided through project redesign (Golder 2013b; ARA 2013c–2013l). None of these sites are in close proximity to the study area.
The provincial archaeological sites database (ASDB) was referred to on November 29, 2013 to determine if there were any registered archaeological sites in close proximity to the study area. The database search indicated that there are no archaeological sites within a 1 km radius of the current ROW study area land.
1.3.3 Determination of Archaeological Potential
Archaeological potential is established by determining the likelihood that archaeological resources may be present on a subject property. Criteria commonly used by the Ontario MTCS (Ontario Government 2011) to determine areas of archaeological potential include:
Proximity to previously identified archaeological sites; Distance to various types of water sources;Soil texture and drainage;Glacial geomorphology, elevated topography and the general topographic variability of the area;Resource areas including food or medicinal plants, scarce raw materials and early Euro-Canadian industry;Areas of early Euro- Canadian settlement and early transportation routes;Properties listed on municipal register of properties designated under the Ontario Heritage Act (Government of Ontario 1990b);Properties that local histories or informants have identified with possible archaeological sites, historical events, activities or occupants; and Historic landmarks or sites.
Distance to modern or ancient water sources is generally accepted as the most important element for past humansettlement patterns and when considered alone may result in a determination of archaeological potential. In addition any combination of two or more of the criteria listed above, such as well drained soils or topographic variability, may indicate archaeological potential.
Certain features indicate that archaeological potential has been removed, such as land that has been subject to extensive and intensive deep land alterations that have severely damaged the integrity of any archaeological resources. This includes landscaping that involves grading below the topsoil level, building footprints, quarrying and sewage and infrastructure development (Ontario Government 2011).
The potential for pre-contact and contact period Aboriginal archaeological resources is judged to be moderate to high, based on the proximity to potable water and previously known archaeological sites (Golder 2012a:32). The potential for Euro-Canadian archaeological resources is judged to be moderate to high based on the proximity to thehistoric communities within or just outside of the study area, the early 19th century settlement of Tuckersmith
9
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
Township as agriculturally based, and the historical evidence of First Nations residing within the study area (Golder2012a:34).
1.3.4 Existing Conditions
The Stage 2 archaeological assessment for the proposed transmission line development of the segments of the Centennial Road ROW, east of Hensall Road and the Hensall Road ROW, south of Centennial Road, was conducted on December 6, 2013 under Professional license P393 issued by the MTCS to Erik Phaneuf, Professional Archaeologist at AECOM, under PIF number P393-0027-2013. The Stage 2 archaeological assessment was attempted on December 4, 2013; however upon arrival at the site it was found to have over 5 centimetres (cm) of snow cover and the assessment was delayed until conditions for archaeological assessment improved.
The land subject to assessment consists of 75 m of the ROW of Centennial Road south of Hensall Road, and Hensall Road south of Centennial Road which will be impacted by the placement of transmission poles, located within the Geographic Township of Tuckersmith, now the Municipality of Huron East, Huron County, Ontario. The study areas consist primarily of gravel road with grassy shoulders and are made up of two sections approximately 0.16 ha in size, for a total of 0.32 ha of land subject to assessment.
10
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
2. Field MethodsThe Stage 2 field investigation involved the physical survey of a 75 m section of Centennial Road ROW south of Hensall Road, and a 75 m section of Hensall Road ROW south of Centennial Road, as shown in Figures 2 and 4.Although the proposed location for transmission poles will impact only the north ROW sections of Centennial and Hensall roads, both the north and south sections of ROW were assessed to provide flexibility for transmission pole placement.
The study area land consists of 60% gravel road surface and 40% grassy shoulder within which a gas main and existing hydro poles are situated. As the area could not be ploughed the Stage 2 field investigation was conductedby the standard shovel test pit survey method and where previous disturbance could be visually determined the area was photo-documented. The limits of the ROW were staked prior to the archaeological assessment. Although the entire ROW appeared previously disturbed a line of test pits were excavated at the limit of the ROW closest to the agricultural fields to determine if any land retaining archaeological potential was present. Test pits were excavated at a 10 m interval due to evidence of previous disturbance, and each test pit was approximately 30 cm in diameter, was excavated at least 5 cm into sterile subsoil and was examined for stratigraphy, cultural features or evidence of fill. All soil was screened though hardware mesh with an aperture of 6 millimetres (mm) to facilitate the recovery of cultural material and was then used to backfill the pit. The determination of previous disturbance was verified by the test pit excavation and the high level of road grade gravel and other non-native fill within the soil excavated. No cultural material was identified during the test pit survey which would have caused the survey intervals to be decreased according to Section 2.1.3 of the Standards and Guidelines for Consultant Archaeologists (Ontario Government 2011).
As per the Standards and Guidelines for Consultant Archaeologists (Section 7.8.6, Standard 1a, Ontario Government 2011), Photos 1 to 10 document the study area to confirm conditions met the requirements for Stage 2 archaeological assessment. Photograph locations and directions are provided on Figure 4 along with an illustrationof the methods and results of the Stage 2 field investigation.
The weather during the Stage 2 assessment was cold and overcast, with a high of 4 degrees Celsius. Visibility and lighting conditions were excellent and there were no conditions that were detrimental to the identification and recovery of archaeological material.
11
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
3. Record of FindsThe Stage 2 archaeological assessment for the 75 m section of Centennial Road ROW south of Hensall Road, and the 75 m section of Hensall Road ROW south of Centennial Road, as shown in Figures 2 and 4, was conducted by employing the methods outlined in Section 2 of this report. The Stage 1 background research conducted by Golder indicated that the study area had a moderate to high potential to contain archaeological resources (Golder 2012a:32-34); however, the Stage 2 field investigation did not result in the identification of any archaeological sites or material.
The entire subject property was found to be extensively previously disturbed and did not retain archaeological integrity. In addition no archaeological sites or material were identified during the course of the Stage 2 archaeological assessment. Table 4 provides a listing of the documentary record generated by the Stage 2 fieldwork and indicates the location of each document type.
Table 4: Inventory of Documentary Record
Document Type Quantity Location Additional CommentsField Notes 2 pgs AECOM London Office In original field book and photocopied in project fileHand Drawn Maps 1 pg AECOM London Office In original field book and photocopied in project fileProponent Maps 1 pg AECOM London Office Hard copy and digital copy in project fileDigital Photographs 28 AECOM London Office Stored digitally in project file
12
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
4. Analysis and ConclusionsThe Stage 2 archaeological assessment for the 75 m section of Centennial Road ROW south of Hensall Road, and the 75 m section of Hensall Road ROW south of Centennial Road did not result in the identification of any archaeological sites or material. The entire subject property was found to be extensively previously disturbed and did not retain archaeological integrity. Archaeological concerns in this area may be considered addressed and no further archaeological work is required.
13
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
5. RecommendationsThe Stage 2 archaeological assessment for the 75 m section of Centennial Road ROW south of Hensall Road, and the 75 m section of Hensall Road ROW south of Centennial Road did not result in the identification of any archaeological sites or material. The entire subject property was found to be extensively previously disturbed and did not retain archaeological integrity. Archaeological concerns in this area may be considered addressed and no further archaeological work is required.
The Ministry of Tourism, Culture and Sport is asked to accept this report into the Ontario Public Register of Archaeological Reports and issue a letter of concurrence with the recommendation that archaeological concerns under land use planning and development processes are considered addressed and no further archaeological assessment is required.
14
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
6. Bibliography and SourcesArchaeological Research Associates Ltd. (ARA) 2013a Stage 2 Property Assessment, Additional Lands and ROWs, Bluewater Wind Energy Centre, FIT-FJI7S7X,
Multiple Lots and Concessions, Municipalities of Bluewater and Huron East, Geographic Townships of Hay, Stanley and Tuckersmith, Huron County, Ontario. PIF #P007-522-2013. Archaeological Research Associates Ltd.
2013b Stage 2 Property Assessment, Heavy Haul Route Turns, Bluewater Wind Energy Centre FIT-FJI7S7X,Municipality of Bluewater, Multiple Lots and Concessions, Geographic Townships of Hay and Stanley, Huron County, Ontario. PIF #P089-0032-2013. Archaeological Research Associates Ltd.
2013c Stage 3 Site-Specific Assessment, Location 13 (AiHj-6), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 10, Concession 11, Geographic Township of Stanley, Huron County, Ontario. PIF #P089-025-2013. Archaeological Research Associates Ltd.
2013d Stage 3 Site-Specific Assessment, Location 14 (AiHk-1), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 9, Concession 8, Geographic Township of Stanley, Huron County, Ontario. PIF #P089-026-2013. Archaeological Research Associates Ltd.
2013e Stage 3 Site-Specific Assessment, Location 24 (AiHj-9), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 24, North Boundary, Geographic Township of Hay, Huron County, Ontario. PIF #P089-027-2013. Archaeological Research Associates Ltd.
2013f Stage 3 Site-Specific Assessment, Location 25 (AjHj-14), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 17, Concession 9, Geographic Township of Stanley, Huron County, Ontario. PIF #P089-028-2013. Archaeological Research Associates Ltd.
2013g Stage 3 Site-Specific Assessment, Location 29 (AjHj-16), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 15, Concession 9, Geographic Township of Stanley, Huron County, Ontario. PIF #P089-031-2013. Archaeological Research Associates Ltd.
2013h Stage 3 Site-Specific Assessment, Location 30 (AjHi-12), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Huron East, Part of Lot 23, Concession 4 ELR, Geographic Township of Tuckersmith, Huron County, Ontario. PIF #P007-544-2013. Archaeological Research Associates Ltd.
2013i Stage 4 Mitigation of Development Impacts, Location 14 (AiHk-1), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 9, Concession 8, Geographic Township of Stanley, Huron County, Ontario. PIF #P007-506-2013. Archaeological Research Associates Ltd.
2013j Stage 4 Mitigation of Development Impacts, Location 13 (AiHj-6), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 10, Concession 11, Geographic Township of Stanley, Huron County, Ontario. PIF #P007-557-2013. Archaeological Research Associates Ltd.
2013k Stage 4 Mitigation of Development Impacts, Location 24 (AiHj-9), Bluewater Wind Energy Centre, FIT-FJI7S7X, Municipality of Bluewater, Part of Lot 24, North Boundary, Geographic Township of Hay, Huron County, Ontario. PIF #P007-558-2013. Archaeological Research Associates Ltd.
2013l Stage 4 Mitigation of Development Impacts, Location 25 (AjHj-14), Bluewater Wind Energy Centre, FIT-
15
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
FJI7S7X, Municipality of Bluewater, Part of Lot 17, Concession 9, Geographic Township of Stanley, Huron County, Ontario. PIF #P007-559-2013. Archaeological Research Associates Ltd.
Belden, H. & Co.1879 Illustrated Historical Atlas of the County of Huron, Ontario. Toronto: H. Belden & Co.
Chapman, L. J. and D. F. Putnam1966 The Physiography of Southern Ontario. Second edition. Ontario Research Foundation, University of Toronto
Press.
Ellis, C.J., J.A. Fisher and D.B. Deller1988 Four Meadowood Phase Lithic Artifact Assemblages from Caradoc and Delaware Townships, Southwestern
Ontario. Kewa 88(8):3-20.
Ellis, Chris J., Ian T. Kenyon and Michael W. Spence1990 The Archaic. In The Archaeology of Southern Ontario to A.D. 1650, eds. Chris J. Ellis and Neal Ferris.
Occasional Publication of the London Chapter, OAS Number 5.
Ellis, Chris J. and D. Brian Deller1990 Paleo-Indians. In The Archaeology of Southern Ontario to A.D. 1650, eds. Chris J. Ellis and Neal Ferris.
Occasional Publication of the London Chapter, OAS Number 5.
Ellis, Christopher J. and Neal Ferris (editors)1990 The Archaeology of Southern Ontario to AD 1650, Eds. Christopher Ellis and Neal Ferris, Occasional
Publication of the London Chapter, Ontario Archaeological Society, Number 5.
Ferris, Neal1999 What’s in a Name? The Implications of Archaeological terminology Used in Nonarchaeological Context. In
Taming the Taxonomy: Toward a New Understanding of Great Lake Archaeology, edited by Ronald Williamson and Christopher Watts.
2009 The Archaeology of Native-lived Colonialism: Challenging History in the Great Lakes. University of Arizona Press, Tucson.
Feidel, Stuart1999 Algonquians and Iroquoians: Taxonomy, Chronology and Archaeological Implications. In Taming the
Taxonomy: Toward a New Understanding of Great Lake Archaeology, edited by Ronald Williamson and Christopher Watts.
Feest, Johanna E. and Christian F. Feest1978 In Handbook of North American Indians. Vol.15 Northeast, pp.772-786. B.G. Trigger, Ed. Washington:
Smithsonian Institute.
Fox, William A.1990 The Middle to Late Woodland Transition. In The Archaeology of Southern Ontario to A.D. 1650, eds. Chris
J. Ellis and Neal Ferris. Occasional Publication of the London Chapter, Ontario Archaeological Society, Number 5.
Golder Associates Ltd. (Golder)2012a Stage 1 Archaeological Assessment, NextEra Energy Canada, ULC, Bluewater Wind Energy Centre, Huron
County, Ontario. PIF #P001-609-2010. Golder Associates Ltd.
16
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
2012b Stage 2 Archaeological Assessment, NextEra Energy Canada, ULC, Bluewater Wind Energy Centre, Huron County, Ontario (Final Report). PIF #P218-040-2011, P319-017-2012. Golder Associates Ltd.
2013a Stage 2 Archaeological Assessment, Bluewater Wind Energy Centre, Location 26 through 35, Various Lots and Concessions, Geographic Township of Stanley, Hay and Tuckersmith, now Municipalities of Bluewater and Huron East, Huron County, Ontario (Revised Report). PIF #P218-275-2012. Golder Associates Ltd.
2013b Stage 3 Archaeological Assessment, Bluewater Wind Energy Centre, Locations 13, 14, 24 and 25, Various Lots and Concessions, Geographic Township of Hay and Stanley, Huron County, Ontario. PIFs #P218-279, 280, 281, 282-2012. Golder Associates Ltd.
Karrow, P.F. and B.G Warner1990 The Geological and Biological Environment for Human Occupation in Southern Ontario. In The Archaeology
of Southern Ontario to A.D. 1650, eds. Chris J. Ellis and Neal Ferris. Occasional Publication of the London Chapter, OAS Number 5.
Koenig, Edwin2005 Cultures and Ecologies A Native Fishing Conflict on the Saugeen-Bruce Peninsula. University of Toronto
Press, Toronto.
Konrad, Victor 1981 An Iroquois Frontier: the North Shore of Lake Ontario during the Late Seventeenth Century. Journal of
Historical Geography 7(2).
Murphy, Carl and Neal Ferris1990 The Late Woodland Western Basin Tradition of Southwestern Ontario. In The Archaeology of Southern
Ontario to A.D. 1650, eds. Chris J. Ellis and Neal Ferris. Occasional Publication of the London Chapter, OAS Number 5.
Ontario Government1990a Environmental Protection Act. R.S.O. 1990, CHAPTER E.19. Last amendment: 2010, c. 16, Sched. 7, s.2.
Retrieved August 21, 2013 from: http://www.e-laws.gov.on.ca/html/statutes/english/elaws_statutes_90e19_e.htm
1990b Ontario Heritage Act. R.S.O. 1990, CHAPTER O.18, Last amendment: 2009, c. 33, Sched. 11, s. 6. Electronic document: http://www.e-laws.gov.on.ca/html/statutes/english/elaws_statutes_90o18_e.htm. Last assessed April 2013.
2011 Standards and Guidelines for Consultant Archaeologists. Ministry of Tourism, Culture and Sport.
n.d Archaeological Sites Database (ASDB). Ministry of Tourism, Culture and Sport.
Rogers, E.S1978 Southeast Ojibwa. In Handbook of North American Indians. Volume 15, Northeast, edited by Bruce Trigger,
pp.760-771.
Schmalz, Peter S.1991 The Ojibwa of Southern Ontario. University of Toronto Press.
Surtees, Robert1971 The Original People. Holt, Rinehart and Winston, Toronto.
17
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
Spence, Michael W., Robert H. Pihl and Carl R. Murphy1990 Cultural Complexes of the Early and Middle Woodland Periods. In The Archaeology of Southern Ontario to
A.D. 1650, eds. Chris J. Ellis and Neal Ferris. Occasional Publication of the London Chapter, OAS Number 5.
Warrick, Gary2008 A Population History of the Huron-Petun, A.D. 500-1650. Cambridge University Press, Cambridge.
Wright, James V.1994 Before European Contact. In Aboriginal Ontario: Historic Perspectives on the First Nations. Eds. Edward S.
Rogers and Donald B. Smith. Ontario Historical Studies Series, Dundurn Press, Toronto.
18
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
7. Images7.1 Photographs
Photo 1: North ROW of Centennial Road, facing southeast, note sloping road grade
Photo 2: North ROW of Centennial Road, example of test pit with evidence of disturbance, note gravel
Photo 3: North ROW of Centennial Road, facing northwest towards intersection with Hensall Road, note road grade
Photo 4: South ROW of Centennial Road, facing southeast, note sloping road grade
19
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
Photo 5: South ROW of Centennial Road, example of test pit note disturbance
Photo 6: South ROW of Hensall Road, facing southwest, note sloping road grade
Photo 7: South ROW of Hensall Road, example of test pit, note gravel
Photo 8: North ROW of Hensall Road, facing northeast towards intersection with Centennial Road, note road grade
20
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
Photo 9: North ROW of Hensall Road, example of test pit, note gravel
Photo 10: North ROW of Hensall Road, facing southwest
21
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
8. MapsMaps documenting the methods and results of the Stage 2 archaeological assessment of the 75 m section of Centennial Road ROW south of Hensall Road, and the 75 m section of Hensall Road ROW south of Centennial Road are provided on the following pages.
22
k
MIL
L
KIPPEN
PARR
STA
FFA
21
19
LONDON
HENSALL
AIRPORT
GOSHEN
MORRISON
CEN
TEN
NIA
L
ROAD183
FRON
T
28
17
ROAD182
BRONSON
DIVISION
BLUEWATER
TILE
WA
LNU
T
RO
MA
N
BELLS
ROAD18132
BABYLON
8
RO
GER
VILL
E
HURO
N
LINE
26
HANNAH
BANNOCKBURN
BLIND
DA
NC
ELA
ND
STON
E
FANSVILLE
ZUR
ICH
HEN
SALL
HYDR
OLI
NE
VAN
AST
RA
SHO
RT
HO
RN
OAK
COUN
TYRD
24
BLACKBUSH
NORTH
AUSABLE
BAYF
IELD
RIV
ER
COUNTYRD180
PAVI
LLIO
N
CHIS
ELHU
RST
MAPLE
BRID
GE
MAIN
KINBURN
WILDWOOD
GULLEY
TUYLL
CRY
STA
L SP
RIN
GS
ROXBORO
DAV
ID
KIN
G
WEB
B
BLU
E B
LUFF
JER
RY
CR
EST
GODE
RICH
MCTAGGART
SANCTUARY
STIRLINGS
JAN
E
FRY
HARP
URHE
Y
SUN
SET
LAPO
RTE
WO
OD
LAN
D
3
CH
UR
CH
JOHN
BLU
EHAV
EN
SMIRNOFF
SHA
NG
RIL
ACO
LIN
A
MARK
ET
KEIT
H
TOWER
ELMSLIE
OLD RIVER
EGER
TON
BEA
CH
LIDDERDALE
YOR
K
WILLIAM
RAILW
AY
MO
OR
E
BIRC
H
BED
AR
D
ELLIOT
LORNE
ALBERT
BAULCH
MA
RY
ELM
RAVI
NELINDYDEL
EVA
N
DRIFTWOOD
GEORGE
JOWETT
CENT
REDU
KE
PAVI
LLIO
N
MA
IN
MIL
LM
ILL
FRON
T
WOODLAND
RO
GER
VILL
EKINBURN
BRONSON
BABYLON
HURO
N
CENT
ENNI
AL
ZUR
ICH
HEN
SALL
BLU
E B
LUFF
BRONSON
4440
00
4440
00
4460
00
4460
00
4480
00
4480
00
4500
00
4500
00
4520
00
4520
00
4540
00
4540
00
4560
00
4560
00
4580
00
4580
00
4600
00
4600
00
4620
00
4620
00
4640
00
4640
00
4660
00
4660
00
4680
00
4680
00
4700
00
4700
00
4720
00
4720
00
4808000
4808000
4810000
4810000
4812000
4812000
4814000
4814000
4816000
4816000
4818000
4818000
4820000
4820000
4822000
4822000
4824000
4824000
UTM
Zon
e 17
N, N
AD
83
Loca
tion
of P
roje
ct
Are
a
Figu
re 1
June
201
460
3012
07
Blu
ewat
er W
EC
Tra
nsm
issi
on L
ine
Stu
dyS
tage
2 A
rcha
eolo
gica
l Ass
essm
ent
1:75
,000
Bas
emap
ping
from
Ont
ario
Min
istry
of N
atur
al R
esou
rces
This
dra
win
g ha
s be
en p
repa
red
for
the
use
of A
EC
OM
's c
lient
an
d m
ay n
ot b
e us
ed,
repr
oduc
ed o
r re
lied
upon
by
third
par
ties,
exce
pt a
s ag
reed
by
AE
CO
M a
nd i
ts c
lient
, as
req
uire
d by
law
or
for
use
by
gove
rnm
enta
l re
view
ing
agen
cies
. A
EC
OM
acc
epts
no
res
pons
ibili
ty,
and
deni
es a
ny l
iabi
lity
wha
tsoe
ver,
to a
ny p
arty
that
mod
ifies
this
dra
win
g w
ithou
t AEC
OM
's e
xpre
ss w
ritte
n co
nsen
t.
²0
460
920
1,38
01,
840
230
Met
res
Lege
nd Blu
ewat
er W
ind
Ene
rgy
Cen
tre
Stu
dy A
rea
Blu
ewat
er T
rans
mis
sion
Lin
eS
tudy
Are
a
Lot L
ines
Wat
erbo
dy
Wat
erco
urse
Woo
dlot
Stud
y A
rea
Stu
dy A
rea
Loca
tion
k
Hensall Rd
Cent
enni
al R
d
305
310
4816000
4816000
UTM
Zon
e 17
N, N
AD
83
Stud
y A
rea
in D
etai
l Figu
re 2
June
201
460
3012
07
Blu
ewat
er W
EC
Tra
nsm
issi
on L
ine
Stu
dyS
tage
2 A
rcha
eolo
gica
l Ass
essm
ent
1:1,
000
Bas
emap
ping
from
Ont
ario
Min
istry
of N
atur
al R
esou
rces
This
dra
win
g ha
s be
en p
repa
red
for
the
use
of A
EC
OM
's c
lient
an
d m
ay n
ot b
e us
ed,
repr
oduc
ed o
r re
lied
upon
by
third
par
ties,
exce
pt a
s ag
reed
by
AE
CO
M a
nd i
ts c
lient
, as
req
uire
d by
law
or
for
use
by
gove
rnm
enta
l re
view
ing
agen
cies
. A
EC
OM
acc
epts
no
res
pons
ibili
ty,
and
deni
es a
ny l
iabi
lity
wha
tsoe
ver,
to a
ny p
arty
that
mod
ifies
this
dra
win
g w
ithou
t AEC
OM
's e
xpre
ss w
ritte
n co
nsen
t.
²0
612
1824
3
Met
res
Lege
nd Con
tour
s
Pre
viou
sly
Ass
esse
d
Stu
dy A
rea
Lot L
ines
2000
2000
Not
to S
cale
A Po
rtio
n of
the
1878
Map
of
The
Tow
nshi
p of
Tuc
kers
mith
Figu
re 3
June
201
460
3012
07
Blu
ewat
er W
EC
Tra
nsm
issi
on L
ine
Stu
dyS
tage
2 A
rcha
eolo
gica
l Ass
essm
ent
Bas
emap
ping
from
Ont
ario
Min
istry
of N
atur
al R
esou
rces
This
dra
win
g ha
s be
en p
repa
red
for
the
use
of A
EC
OM
's c
lient
an
d m
ay n
ot b
e us
ed,
repr
oduc
ed o
r re
lied
upon
by
third
par
ties,
exce
pt a
s ag
reed
by
AE
CO
M a
nd i
ts c
lient
, as
req
uire
d by
law
or
for
use
by
gove
rnm
enta
l re
view
ing
agen
cies
. A
EC
OM
acc
epts
no
res
pons
ibili
ty,
and
deni
es a
ny l
iabi
lity
wha
tsoe
ver,
to a
ny p
arty
that
mod
ifies
this
dra
win
g w
ithou
t AEC
OM
's e
xpre
ss w
ritte
n co
nsen
t.
²
Lege
nd
Stud
y A
rea
¹
Hensall Rd
Cent
enni
al R
d
305
310
4816000
4816000
UTM
Zon
e 17
N, N
AD
83
Met
hods
and
Res
ults Fi
gure
4
June
201
460
3012
07
Blu
ewat
er W
EC
Tra
nsm
issi
on L
ine
Stu
dyS
tage
2 A
rcha
eolo
gica
l Ass
essm
ent
1:1,
000
Bas
emap
ping
from
Ont
ario
Min
istry
of N
atur
al R
esou
rces
This
dra
win
g ha
s be
en p
repa
red
for
the
use
of A
EC
OM
's c
lient
an
d m
ay n
ot b
e us
ed,
repr
oduc
ed o
r re
lied
upon
by
third
par
ties,
exce
pt a
s ag
reed
by
AE
CO
M a
nd i
ts c
lient
, as
req
uire
d by
law
or
for
use
by
gove
rnm
enta
l re
view
ing
agen
cies
. A
EC
OM
acc
epts
no
res
pons
ibili
ty,
and
deni
es a
ny l
iabi
lity
wha
tsoe
ver,
to a
ny p
arty
that
mod
ifies
this
dra
win
g w
ithou
t AEC
OM
's e
xpre
ss w
ritte
n co
nsen
t.
²0
612
1824
3
Met
res
Lege
nd Con
tour
s
Lot L
ines
Pre
viou
sly
Dis
turb
ed -
V
isua
lly A
sses
sed
Test
Pit
at 1
0m In
terv
als
-P
revi
ousl
y D
istu
rbed
= !
!1P
hoto
Loc
atio
n an
d D
irect
ion
=!!
1
! (2
=!!3
=!!
4
! (5
=!
!
6
! (7
=!
!8
! (9
=!
!
10
Pre
viou
sly
Ass
esse
d
AECOM Varna Wind, Inc Stage 2 Archaeological AssessmentROW Centennial Road and Hensall Road South for Transmission Poles
9. Advice on Compliance with LegislationThis report is submitted to the Ontario Minister of Tourism, Culture and Sport as a condition of licensing in accordance with Part VI of the Ontario Heritage Act, R.S.O. 1990, c 0.18. The report is reviewed to ensure that it complies with the standards and guidelines that are issued by the Minister, and that the archaeological fieldwork and report recommendations ensure the conservation, protection and preservation of the cultural heritage of Ontario. When all matters relating to archaeological sites within the project area of a development proposal have been addressed to the satisfaction of the Ministry of Tourism, Culture and Sport, a letter will be issued by the Ministry stating that there are no further concerns with regard to alterations to archaeological sites by the proposed development.
It is an offence under Sections 48 and 69 of the Ontario Heritage Act for any party other than a licensed archaeologist to make any alteration to a known archaeological site or to remove any artifact or other physical evidence of past human use or activity from the site, until such time as a licensed archaeologist has completed fieldwork on the site, submitted a report to the Minister stating that the site has no further cultural heritage value or interest, and the report has been filed in the Ontario Public Register of Archaeology Reports referred to in Section 65.1 of the Ontario Heritage Act.
Should previously undocumented archaeological resources be discovered, they may be a new archaeological site and therefore subject to Section 48(1) of the Ontario Heritage Act. The proponent or person discovering the archaeological resources must cease alteration of the site immediately and engage a licensed consultant archaeologist to carry out archaeological fieldwork, in compliance with Section 48(1) of the Ontario Heritage Act.
The Cemeteries Act, R.S.O. 1990 c. C.4 and the Funeral, Burial and Cremation Services Act, 2002, S.O. 2002, c.33 (when proclaimed in force) require that any person discovering human remains must notify the police or coroner and the Registrar of Cemeteries at the Ontario Ministry of Consumer Services.
27
Ministry of Tourism, Culture and Sport
Archaeology Program Unit Programs and Services Branch 401 Bay Street, Suite 1700 Toronto, ON M7A 0A7 Telephone: (416) 212-5107 Email : wai.hadlari@ontario,ca
Ministère du Tourisme, de la Culture et du Sport
Unité des programmes d’archéologie Direction des programmes et des services 401 Rue Bay, Bureau 1700 Toronto, ON M7A 0A7 Téléphone: (416) 212-5107 Email: wai.hadlari@ontario,ca
June 12, 2014
Andrea Garcia NextEra Energy Canada, ULC 390 Bay Street,Toronto, ON M5H 2Y2
RE: Stage 2 Archaeological Assessment Centennial Road and Hensall Road ROW Transmission Line Study for Bluewater Wind Energy Centre Geographic Township of Tuckersmith, Municipality of Huron East, Huron County, Ontario MTCS File Number: HD00689 FIT Number: FIT-FJI7S7X PIF: P393-0027-2013
Dear Ms. Garcia:
This letter constitutes the Ministry of Tourism and Culture’s written comments as required by s. 22(3)(a) of O. Reg. 359/09 under the Environmental Protection Act regarding archaeological assessments undertaken for the above project.
Based on the information contained in the report you have submitted for this project, the Ministry believes the archaeological assessment complies with the Ontario Heritage Act's licensing requirements, including the licence terms and conditions and the Ministry's 2011 Standards and Guidelines for Consultant Archaeologists. Please note that the Ministry makes no representation or warranty as to the completeness, accuracy or quality of the report.*
The report recommends the following:
The Stage 2 archaeological assessment for the 75 m section of Centennial Road ROW south of Hensall Road, and the 75 m section of Hensall Road ROW south of Centennial Road did not result in the identification of any archaeological sites or material. The entire subject property was found to be extensively previously disturbed and did not retain archaeological integrity. Archaeological concerns in this area may be considered addressed and no further archaeological work is required.
The Ministry of Tourism, Culture and Sport is asked to accept this report into the Ontario Public Register of Archaeological Reports and issue a letter of concurrence with the recommendation that archaeological concerns under land use planning and
* In no way will the Ministry be liable for any harm, damages, costs, expenses, losses, claims or actions that may result: (a) if the Report(s) or its recommendations are discovered to be inaccurate, incomplete, misleading or fraudulent; or (b) from the issuance of this letter. Further measures may need to be taken in the event that additional artifacts or archaeological sites are identified or the Report(s) is otherwise found to be inaccurate, incomplete, misleading or fraudulent.
development processes are considered addressed and no further archaeological assessment is required.
The Ministry is satisfied with these recommendations.
This letter does not waive any requirements which you may have under the Ontario Heritage Act. A separate letter addressing archaeological licensing obligations under the Act will be sent to the archaeologist who completed the assessment and will be copied to you.
This letter does not constitute approval of the renewable energy project. Approvals of the project may be required under other statutes and regulations. It is your responsibility to obtain any necessary approvals or licences.
Please feel free to contact me if you have questions or require additional information.
Sincerely,
Wai Hadlari Archaeology Review Officer
cc. Erik Phaneuf