Upload
francesco-legname
View
29
Download
0
Tags:
Embed Size (px)
Citation preview
Pearl GTL
Execution Progress: Lower deck Module on Pearl 1
Pearl GTL
Execution Progress: Fabrication & Installation
Pearl GTL
Execution Progress: Fabrication & Installation
20” Spool fabricated /Cladded and
Painted
Pearl GTL
Execution Progress: Fabrication MTA 2/Procurement NON MTA
Pearl 2: 20” spool fabrication completed for Pearl 2 – Shipped to Doha – Still to be painted
Pearl GTL
Execution Progress: MTA Pearl 1 spools
Flare Line – 2” spools -24 No
Pearl GTL
Execution Progress: MTA Pearl 1 spools – Hydrotest
HPU spools 1500#- Hydrotest
Flare /