David Saenz FAC CF Overview [email protected] .edu April 20, 06 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities D. Saenz / SLAC

Meeting of the LCLS Facilities Advisory Committee

Embed Size (px)

DESCRIPTION

Meeting of the LCLS Facilities Advisory Committee. LCLS Conventional Facilities D. Saenz / SLAC. Conventional Facilities Overview. Systems Description Construction Projects to Date Status of Design and Construction SLAC/Turner Plans for Construction Construction Schedule - PowerPoint PPT Presentation

Citation preview

Page 1: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

Meeting of the LCLS Facilities Advisory Committee

LCLS Conventional Facilities

D. Saenz / SLAC

Page 2: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

Conventional Facilities Overview•Systems Description•Construction Projects to Date•Status of Design and Construction•SLAC/Turner Plans for Construction •Construction Schedule•CF Organization Chart•Summary

Page 3: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

SLAC Site PlanSLAC Main Gate

Bldg #081 - MMF

Research Yard

Pep Ring Road

LCLS General Work Boundary

Sector 25

Sector 20 Upstream

Research Office Building

Page 4: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

Systems Description

• Sector 20 Injector Facility

• Magnetic Measurement Facility

• Linac Improvements

• Beam Transport Hall

• Undulator Hall

• Front End Enclosure

Page 5: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

Systems Description – cont’d

•Electron Beam Dump

•Near Experimental Hall

•X-Ray Transport & Diagnostics Tunnel

•Far Experimental Hall

•Central Lab Office Complex

Page 6: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

Beam Transport Hall – 227m long above grade facility to transport the electron beam through the existing RSY

Undulator Hall – 170m long underground tunnel housing undulators and ancillary equipment

Central Lab Office Complex – office facility to house ~ 275 LCLS researchers, engineers, technicians, administrative staff and visiting experimentalists

Far Experimental Hall – underground single 46’ cavern to house 3 experimental hutches and prep space

Electron Beam Dump – 40m long underground facility used to separate the electron and x-ray beams

Front End Enclosure – 40m long underground facility to house various diagnostic equipment in support of the photon beam

Near Experimental Hall – underground facility whose primary function is to house 3 experimental hutches, prep and shops

X-Ray Transport & Diagnostics Tunnel – 200m long underground tunnel used to transport photon beams from NEH to FEH

Page 7: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

Plan At GradeBeam Transport Hall

UH Service

Bldg

CUP

CLOC

Existing CEH

RSY (E) Pep Ring Rd

Page 8: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

Below Grade Plan

Undulator Hall

XRT

FEHNEH

EBD

FEE

Page 9: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

CLOC Exterior Elevations

Page 10: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

LCLS Site PlanSpear Pep Ring Road

SLC

SLC Tunnel

Research Yard

Pep Tunnel

Survey Tower

Beam Transport Hall

FutureBeam Lines

NEH

X-Ray Transport

Beam DumpFront EndEnclosure

Office ComplexUndulator Hall

FutureOffice Space

Page 11: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

Construction Projects to Date

Sector 24 Equipment Enclosure (Complete) FFTB Wall (Complete)Magnetic Measurement Facility (Complete) Sector 20 Injector Facility (Punch-List in Process)MMF Electrical Feed (In Progress)FFTB Removal (Commenced)Research Yard Demolition (Award is Imminent)Beam Dump Spoils (July 06)Turner Mobilization (June-July 06)

Page 12: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

Present and Upcoming Activities•SLAC Managed Projects

•Demolition of Building #113, #102 A/B and SLC Gas Pad (Pep Ring Road)

•Project has been out to bid and award is eminent

•Beam Dump Spoils Analysis

•Pending award

•FFTB Removal

•Project awarded and on schedule

•ALL SLAC MANAGED ACTIVITIES MUST BE COMPLETED PRIOR TO JULY 21, 06 TO AVOID DELAY TO TCCO CONTRACT!

Page 13: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

Status of Title II

RSY - CLOC performed by Jacobs Engineering Design Progress

100% design submittal received as scheduled on Jan 30, 06LCLS design review completed Feb 3, 06

LCLS submitted 100% comments to JE Feb 6, 06

Final submittal (“Issue For Bid”) submitted Feb 17, 2006 including 100% construction cost estimate

Addendum #1 submitted Mar 27, 06

Addendum #2 submitted Apr 10, 06

Issue For Construction set submitted Apr 14, 06

Page 14: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

Status of CMGCTC is engaged in Phase 1 stage performing pre-construction and pre-planning activities

Pre-con on site staff (2 PM’s and 1 PE), other staff on-site throughout the week include superintendent, safety coordinator, scheduler, etc

Enhance understanding of site conditions and lab activitiesDevelopment of bid packages (Groups 1-4)Conducted bidders pre-conferenceManage and direct potholing activities for verification of underground utilities

Commenced weekly Owner/Architect/Contractor (OAC) meetings

Page 15: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

SLAC Plans for ConstructionUse of Alpine Gate for all subcontractorsGate 17 will remain open 24/7Implement an approved Tunnel Rescue Team prior to start of any tunneling by July 25, 06Resolve recommendations from an acoustical consulting engineer for noise levels resulting from construction activities July 25, 06

Develop noise abatement plan for equipment Continue to engage with Turner in developing a strong bidders listContinue coordinating with lab liaison (Steve Williams) for LCLS and SLAC interface issues

Page 16: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

Turner Plans for ConstructionSubmit packages out for bid

Page 17: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

Turner Plans for Construction – cont’d

Receive Authorization to Proceed May 10, 06Complete potholing and underground surveying by May 24, 06Mobilization and Site Work commences on May 24, 06Tunneling operations commence July 25, 06

GC staff peaks at 19 personnel on-site

Work the approved processes in place for Change Orders, Request For Information (RFI) and SubmittalsTurner schedule meets or exceeds LCLS needs

Page 18: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

TCCO Logistics Plan

Overall, Plan Offers Many Benefits

•Maintains spoils adjacent to project

•Sufficient lay-down areas for subs

•Area is generally isolated from the lab main arteries (CEH and RSY exception)

•All contractors access project through Alpine Gate

Page 19: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

LCLS CF Construction Schedule

•RSY-CLOC activities reflect 1 month float→L3 milestone

•Construction phase commences June 06→Oct 08

Page 20: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

CF Construction Organization

Brad * Youngman

Const Mgr

*SLAC UTR

Additional support from lab CEF Engineering and UTR support

Page 21: Meeting of the  LCLS Facilities Advisory Committee

David Saenz

FAC CF Overview [email protected]

April 20, 06

SummaryWorked >30,000 construction man-hours to date with zero injuries Title II 100% design submittal received with returned comments from SLAC on Feb 06, 06Construction documents “Issue for Bid” on Feb 17Turner Construction is 60% complete thru Phase 1CF staff has been strengthened to ensure adequate experience is integrated in all requirementsGC staff will have adequate level of support for all construction activitiesTeam (LCLS CF/JE/TC) is ready to commence construction!