STATEMENT OF WORK 

Client  Irvine Ranch Water District 

SI  Infosys Ltd. 

Project   System Integration Services to Implement a Comprehensive Customer Care & 

Billing and Customer Web Portal (OUCSS) Solution 

Date  07‐Jan‐2013 

 

 

 

 

 

 

 

Document No.    Ver. Rev.   0.21 

Authorized by    Signature/ 

Date 

 

 

 

 

 

 

 

 

 

   

EXHIBIT D

Proprietary & Confidential    Statement of Work 

 

 ii

Document Control 

Owner  Infosys Ltd 

Status  Initial Outline 

 

Version  Description of Change  Date  Author 

V0.1  Initial Draft   Jul 26th, 2012  Infosys Ltd 

V0.3  BF Review Draft  Jul 27th, 2012  Infosys Ltd 

V0.4  Numerous   July 30th, 2012  Infosys Ltd 

V0.5  Due Diligence updates  Aug 23rd, 2012  Infosys Ltd 

V0.6  Post Due Diligence updates  Sep 12th, 2012  Infosys Ltd 

V0.7   Sequential go Live updates  Oct 12th, 2012  Infosys Ltd 

V0.8  Reviews  from  Initial  Contract discussions 

Oct 31st, 2012  Infosys Ltd 

V0.9  Changes done after joint Reviews with IRWD and Infosys 

Oct 31st, 2012  Infosys Ltd 

V0.10  Changes made after joint reviews with IRWD and Infosys 

Nov 15th, 2012  Infosys Ltd 

V0.11  Changes  to  the  Payment Milestones 

Nov 19th, 2012  Infosys Ltd 

V0.12  Changes  to  the  deliverable  table and  payment  milestones  after the meeting on Nov 21st, 2012 

Nov 26th, 2012  Infosys Ltd 

V0.13  Changes made  to  the deliverable table  after  the  meeting  on  Nov 27th, 2012 

Nov 28th, 2012  Infosys Ltd 

V0.14  Indentation, formatting changes  Dec 06th, 2012  Infosys Ltd 

V0.15  Miscellaneous  changes  after meeting on Dec 10, 2012 

Dec 12th, 1012  IRWD  and Infosys Ltd 

V0.16  Formatted  reporting  table, keyresource table, others 

Dec 13th, 1012  IRWD  and Infosys Ltd 

Proprietary & Confidential    Statement of Work 

 

 iii

0.17  Incorporated  changes  from  the meeting on Dec 14,2012 

Dec 21st,2012  Infosys Ltd. 

0.18  Changes made by IRWD  Dec 27th, 2012  IRWD 

0.19  Changes/comments by Infosys  January 2nd, 2013  Infosys Ltd. 

0.20  Changes/comments by Infosys  January 3rd, 2013  Infosys Ltd. 

0.21  Adjusted  the milestone values as per  the  revised  deal  price.  Addition of 10.3. 

January 7th, 2013  Infosys Ltd 

Statement of Work     

© 2013 Infosys Limited   

Table of Contents 1.  Overview ................................................................................................................................. 10 

1.1  Project Summary ............................................................................................................................... 10 

1.1.1  Major Project Considerations ..................................................................................................... 10 

1.1.2  Sub‐Contractors .......................................................................................................................... 10 

1.2  Partnership with Oracle Consulting .................................................................................................. 12 

1.3  Business Objectives of the Project .................................................................................................... 12 

1.4  Overall Scope of the Project ............................................................................................................. 12 

1.5  Guiding Principles of the Project ...................................................................................................... 13 

1.6  Acceptance Criteria ........................................................................................................................... 14 

1.6.1  Go Live Criteria ........................................................................................................................... 14 

1.6.2  Post Implementation Acceptance Criteria or Final System Acceptance .................................... 14 

1.7  Software Modules and Version......................................................................................................... 16 

1.8  Project Implementation Software and Tools .................................................................................... 18 

1.9  Project Assumptions ......................................................................................................................... 18 

1.9.1  General ....................................................................................................................................... 18 

1.9.2  Project Structure ........................................................................................................................ 21 

1.9.3  Staffing ....................................................................................................................................... 22 

1.9.4  Project Management .................................................................................................................. 23 

1.9.5  Data Conversion ......................................................................................................................... 24 

1.9.6  Development .............................................................................................................................. 24 

1.9.7  System Testing ............................................................................................................................ 25 

1.9.8  Training ....................................................................................................................................... 25 

1.9.9  Production Readiness and Cutover ............................................................................................ 25 

1.9.10  Post Implementation Support .................................................................................................... 26 

1.9.11  Technology ................................................................................................................................. 26 

1.9.12  Solution Architecture ................................................................................................................. 27 

2.  Definitions ............................................................................................................................... 28 

3.  Performance Criteria ............................................................................................................... 33 

4.  Recommended Hardware and Sizing ...................................................................................... 34 

4.1  CC&B Hardware and Sizing ............................................................................................................... 34 

4.2  OUCSS Hardware and Sizing ............................................................................................................. 35 

Statement of Work     

© 2013 Infosys Limited   

4.3  OBIEE Hardware Sizing ...................................................................................................................... 36 

4.4  DR Infrastructure Setup and Architecture ........................................................................................ 37 

4.5  Desktop Configuration ...................................................................................................................... 38 

5.  Program Scope ........................................................................................................................ 39 

5.1  General Scope Overview ................................................................................................................... 39 

5.2  Program Sctructure ........................................................................................................................... 39 

5.2.1  Project Organization Structure ................................................................................................... 39 

5.2.2  Infosys Staffing ........................................................................................................................... 39 

5.3  Major Scope Components ................................................................................................................ 40 

5.3.1  Client Solution Requirements ..................................................................................................... 40 

5.3.2  Modifications (Extensions) ......................................................................................................... 41 

5.3.3  Interfaces .................................................................................................................................... 41 

5.3.4  Data Conversion ......................................................................................................................... 43 

5.3.5  Reports ....................................................................................................................................... 45 

6.  Implementation Approach ...................................................................................................... 50 

6.1  General Description .......................................................................................................................... 50 

6.2  High Level Schedule .......................................................................................................................... 50 

6.3  Project Phase Definitions .................................................................................................................. 50 

6.4  Project Management & Project Governance .................................................................................... 52 

6.4.1  Activity – Project Activity Management ..................................................................................... 52 

6.4.2  Activity – Status Reporting ......................................................................................................... 53 

6.4.3  Activity – Project Tracking .......................................................................................................... 53 

6.4.4  Activity – Financial and Administration Management ............................................................... 54 

6.5  Pre‐Initiation Phase ........................................................................................................................... 55 

6.5.1  Activity – Contract Completion and Mobilization ...................................................................... 55 

6.6  Initiation Phase ................................................................................................................................. 55 

6.6.1  Activity – Construct Initial Project Documents .......................................................................... 56 

6.6.2  Activity – Develop Detailed Project Work Schedule .................................................................. 57 

6.6.3  Activity – Install & Setup Project Tracking Tools ........................................................................ 58 

6.6.4  Activity – Plan for the Core Team Training Infrastructure ......................................................... 58 

6.6.5  Activity – Plan for the Project Infrastructure ............................................................................. 59 

6.6.6  Activity – Establish Initial Project Infrastructure ........................................................................ 60 

6.6.7  Activity – Install Solution ............................................................................................................ 60 

6.6.8  Activity – Conduct Bootcamp Training Sessions ........................................................................ 61 

Statement of Work     

© 2013 Infosys Limited   

6.7  Business Process Analysis Phase ....................................................................................................... 62 

6.7.1  Activity – Conduct Business Process Analysis Workshops ......................................................... 62 

6.7.2  Activity – Develop Individual To‐Be Business Processes ............................................................ 64 

6.7.3  Activity – Develop Final Business Process Document Catalog ................................................... 64 

6.8  Analysis Phase – FS Documentation ................................................................................................. 65 

6.8.1  Activity – Develop Functional Specifications for Extensions ...................................................... 65 

6.8.2  Activity – Develop Functional Specifications for Interfaces ....................................................... 66 

6.8.3  Activity – Develop Functional Specifications for Reports .......................................................... 66 

6.9  Design Phase – TS Documentation ................................................................................................... 67 

6.9.1  Activity – Develop Solution Configuration Document ............................................................... 67 

6.9.2  Activity – Develop Technical Specifications for Extensions, Interfaces, Reports ....................... 68 

6.10  Configuration & Development .......................................................................................................... 69 

6.10.1  Activity – Develop Solution Configuration ................................................................................. 69 

6.10.2  Activity – Develop Extensions .................................................................................................... 70 

6.10.3  Activity – Develop Interface Programs ....................................................................................... 70 

6.10.4  Activity – Develop Reports ......................................................................................................... 71 

6.11  Data Conversion ................................................................................................................................ 72 

6.11.1  Data Conversion Initiation .......................................................................................................... 72 

6.11.2  Data Conversion Analysis & Design ............................................................................................ 74 

6.11.3  Data Conversion Development .................................................................................................. 75 

6.11.4  Data Conversion Trials & Test Conversions ................................................................................ 76 

6.12  Test Planning ..................................................................................................................................... 77 

6.12.1  Activity – Develop Test Strategy ................................................................................................. 77 

6.12.2  Activity – Develop Functional Testing Scripts ............................................................................ 77 

6.13  Test Execution ................................................................................................................................... 78 

6.13.1  Activity ‐ Execute System Testing ............................................................................................... 78 

6.13.2  Activity – Execute Functional / System Integration Testing ....................................................... 79 

6.13.3  Activity – Execute Performance Testing ..................................................................................... 80 

6.13.4  Activity – Execute User Acceptance Testing (UAT) .................................................................... 81 

6.13.5  Activity – Execute Parallel Testing .............................................................................................. 81 

6.14  Cutover .............................................................................................................................................. 82 

6.14.1  Activity – Prepare Production Environment ............................................................................... 82 

6.14.2  Activity – Preparation for Cutover / Cutover planning .............................................................. 83 

6.14.3  Activity –Cutover to Production Operation ................................................................................ 84 

6.15  Post Implementation Support Phase ................................................................................................ 85 

Statement of Work     

© 2013 Infosys Limited   

6.15.1  Activity – Post Implementation Support .................................................................................... 85 

6.15.2  Activity – Final Acceptance ......................................................................................................... 86 

7.  Organizational Change Management ..................................................................................... 87 

7.1  Organizational Change Management ............................................................................................... 87 

7.1.1  Activity – Develop OCM Plan ...................................................................................................... 87 

7.1.2  Activity – OCM Analysis .............................................................................................................. 88 

7.1.3  Activity – OCM Design ................................................................................................................ 89 

7.1.4  Activity – OCM Plan Execution ................................................................................................... 89 

7.2  Training ............................................................................................................................................. 90 

7.2.1  Activity – Develop Training Plan ................................................................................................. 90 

7.2.2  Activity – Develop Train the Trainer training materials ............................................................. 91 

7.2.3  Activity – Prepare for Training .................................................................................................... 91 

7.2.4  Activity – Deliver User Training (Train the Trainer) .................................................................... 92 

7.2.5  Activity – Deliver End User Training ........................................................................................... 92 

7.2.6  Activity – Stakeholder Analysis ................................................................................................... 93 

8.  Project Management Approach .............................................................................................. 94 

8.1  Program Management Overview ...................................................................................................... 94 

8.2  Project Organization & Reporting Structure ..................................................................................... 94 

8.3  Project Governance & Escalation ...................................................................................................... 94 

8.3.1  Work Assignments & Tracking ................................................................................................... 94 

8.3.2  Weekly PM Meetings ................................................................................................................. 94 

8.3.3  Monthly Steering Committee Meetings ..................................................................................... 95 

8.3.4  Conflict Escalation Process ......................................................................................................... 95 

8.4  Change Order Process ....................................................................................................................... 96 

8.4.1  Process Overview ....................................................................................................................... 96 

8.4.2  Tracking Tool & Process ............................................................................................................. 97 

8.5  Project Controls ................................................................................................................................ 97 

8.6  Project Communications ................................................................................................................... 97 

8.6.1  Project Management Reports .................................................................................................... 97 

8.7  Risk Management ............................................................................................................................. 98 

8.8  Quality Control .................................................................................................................................. 99 

8.8.1  Communication of Deliverable Delivery..................................................................................... 99 

8.8.2  Deliverable Acceptance Process ................................................................................................. 99 

8.8.3  Defect Tracking Tool & Process ................................................................................................ 100 

Statement of Work     

© 2013 Infosys Limited   

8.9  Project Management Tools ............................................................................................................. 100 

8.9.1  Tracking Components ............................................................................................................... 100 

9.  IRWD Assistance ................................................................................................................... 102 

10. Program Pricing ..................................................................................................................... 103 

10.1  Fixed Price for the Project ............................................................................................................... 103 

10.2  Structure for Milestone Payments .................................................................................................. 103 

10.2.1  Milestone Payments ................................................................................................................. 103 

10.3  Intellectual Property ....................................................................................................................... 104 

11. Project Deliverables – Milestones Mapping ......................................................................... 105 

11.1  Table of Deliverables ....................................................................................................................... 105 

12. Travel & Expense Policies ..................................................................................................... 137 

12.1  General Principles ........................................................................................................................... 137 

 

Appendices Appendix 1.  Updated Proposal Document ............................................................................ 139 

A 1.1  Updated Proposal Summary ........................................................................................................... 139 

A 1.2  Functional Checklist ......................................................................................................................... 139 

A 1.3  Price Detail Sheets ........................................................................................................................... 139 

A 1.4  Project Plan ..................................................................................................................................... 139 

Appendix 2.  Clarifying Requirements Document .................................................................. 140 

Appendix 3.  Request for Proposal ......................................................................................... 141 

Appendix 4.  Initial Proposal Document ................................................................................. 142 

    

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 9 of 142 

This Statement of Work (“SOW”), dated as of________ __, 2012 (“Commencement Date”), is entered into by 

and between Irvine Ranch Water District, having a principal place of business at 15600 Sand Canyon Avenue, 

Irvine, CA 92618 (“IRWD”) and Infosys Ltd., having a principal place of business  at 6100 Tennyson Parkway, 

Plano,  Texas  ,  75024  (“Infosys”),  and  is  subject  to  the  terms  and  conditions  of  the  Professional  Services 

Agreement between  IRWD and  Infosys, dated as of ________ __, 2012  (“Agreement”).   The  terms of  the 

Agreement will govern this SOW and are hereby incorporated in this SOW by reference.  Capitalized terms not 

otherwise defined in this SOW will have the meanings set forth in the Agreement.  All references in this SOW 

will be  references  to  sections  set  forth  in  this  SOW, unless  specific  reference  is made  to  a  section  in  the 

Agreement or other Schedules to the Agreement.  The content of this SOW consists of the main body of this 

document plus it’s Exhibits, Schedules and Addendums, including: 

 

  Document Content  Document Location 

Document “A”  Updated  Proposal  and    Price  Sheets,  as  submitted  by  Infosys following due diligence. 

Appendix 1 

Document “B”  Clarifying Requirements Document  Appendix 2 

Document “C”  Request for Proposal Document  Appendix 3 

Document “D”  Initial Proposal Document  Appendix 4 

 

The documents above will be  considered part of  the Agreement.     As  such,  if any discrepancy exists 

between  the  above  referenced  documents,  the  precedence  shall  be  in  the  listed  order.    These 

documents help define  the  scope of  this project and will guide  its execution.     The conclusion of  this 

project is defined by Infosys meeting the requirements for all deliverables as defined this SOW. 

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 10 of 142 

1. Overview 

1.1 Project Summary 

1.1.1 Major Project Considerations 

Irvine  Ranch Water  District  (“IRWD”),  and/or  referenced  as  (“Client”)  has  embarked  on  a  strategic 

initiative  to  replace  its  current  legacy  CIS  (Customer  Information  System) with  a  comprehensive  CIS 

Solution based on Oracle’s Customer Care and Billing (CC&B) software platform. As contemplated, this 

project will ultimately replace IRWD’s current legacy billing system(s) footprint with an integrated suite 

of software applications from Oracle Corporation (Oracle CC&B, OUCSS and OBIEE) and other software 

vendors indicated within this document, including AccuZip, et al.  

Infosys Limited (“Infosys”) will provide the services described herein to IRWD and the project itself will 

be referred to as the “CIS Solution Project.”    Infosys will  install, configure and test the functionality of 

the product(s) listed herein and provide services as described in this Statement of Work (“SOW”).   

The  program  is  planned  to  be  delivered  in  2  phases.    Phase  1  consists  of  the  implementation, 

configuration and customization of all CIS functionality defined within this SOW with using the current 

IRWD  Web  Portal..  Phase  2  will  replace  the  current  IRWD  Web  Portal  with  OUCSS.  This  System 

Replacement Project  is comprised of  the systems described below  in Section 1.7 of  this Statement of 

Work (“SOW”). Infosys will provide program management, organizational change management support, 

and  implementation  services  for  conversion  to  and  installation  of  all  solution  components  defined 

within this SOW. 

 

1.1.2 Sub‐Contractors Infosys, as Prime Contractor for this initiative, will take full ownership of all sub‐contractors (as mutually 

agreed  to  between  Infosys  and  IRWD)  and  their  scope  of  work  as  related  to  the  overall  System 

Replacement Project. It should be noted that throughout our relationship with IRWD, we will endeavor 

to collectively present ourselves as a single, integrated team, and we strongly encourage IRWD to view 

and treat all Infosys sub‐contractors as though they are an extension of the Infosys team. 

Table of  Infosys’ Sub‐Contractors  for  IRWD’s project to  implement a Comprehensive Customer Care & 

Billing Solution: 

Sub‐Contractor Name  Project Role 

Oracle Corp Functional Architect (CCB) 

Technical Architect (CCB) 

Oracle Corp  Migration Consultant 

Oracle Corp  Project Oversight/Project Manager 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 11 of 142 

Sub‐Contractor Name  Project Role 

Oracle Corp Infrastructure  /  Technical 

Consultant 

Oracle Corp  Product Architect  (OUCSS)  

 

   

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 12 of 142 

1.2 Partnership with Oracle Consulting 

Infosys  today  has  an  exclusive  teaming  arrangement  with  Oracle  for  numerous  mid‐market  CIS replacement projects  in North America.   We will utilize Oracle as a subcontractor  to support solution design aspects of the Oracle software in the project roles identified above. Oracle will also assist Infosys in  assessing  the  Client  requirements  and  in  developing  both  configuration  designs  and  the  technical designs  for  all  anticipated modifications,  reports  and  interfaces  that  require  programming  to meet IRWD’s  stated  requirements.  The  objective  of  utilizing  Oracle  in  these  roles  is  to  further enhance/maximize  the  configuration  capacities  in  Oracle’s  software,  and  to minimize  programming changes to the software.   Any changes throughout the project to the configurations and programming designs will be socialized with IRWD and validated by Oracle in support of the Infosys team. 

1.3 Business Objectives of the Project 

IRWD has outlined  several major business drivers and Project  justification  statements  for  this System 

Replacement initiative, including:  

Improve customer service offerings and programs 

Increase knowledge transfer and information sharing between departments  

Improve navigation, data access, and user reporting capabilities 

Improve the ease and support of integration and interfacing to other applications 

Implement  a  system  that  provides  more  flexible  functionality,  and  in  turn,  reduces modifications,  and  allows  IRWD  to more  quickly  and  easily  adapt  to  changing  business  and regulatory requirements 

Support complex and tiered rates 

Improve automated functional processes to reduce manual entries across all applications

Enhance ability to adapt to an  increasingly complex and expanding regulatory and compliance environment  

Increase  and  improve  employee  and  customer  satisfaction  by  improving  the  efficiency  and effectiveness of both employees and business processes. 

1.4 Overall Scope of the Project 

This project includes all activities required to implement a comprehensive CIS Solution based on Oracle’s 

Customer Care and Billing (CC&B) as defined in this SOW and supporting documentation.   The complete 

solution will  include  the  implementation,  configuration  and  delivery  of  the  following  activities  listed 

below. The responsibilities related to the activities below are covered in the subsequent sections. 

Hardware  infrastructure,  including  necessary  server  infrastructure,  printer,  system  software, database and related services.   

 Network  infrastructure and desktop environment,  including necessary hardware and software required to access the CIS Solution.   

 The  base  Oracle  CC&B,  OUCSS  and  other  defined  application  software,  IRWD  specific enhancements and integration with required IRWD and third party application interfaces. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 13 of 142 

The delivery approach will rely on solution configuration rather than solution modifications and will modify its business processes to utilize Oracle CC&B’s best practices where appropriate. 

Infosys  will  provide  installation  services  as  defined  in  this  SOW,  which  include  but  are  not limited  to:  project management,  technology  installation,  application  installation,  application configuration,  data  conversion,  data  archiving,  business  development,  solution  development, data  conversion,  solution  training,  solution  testing,  solution  acceptance,  and  solution installation.  

Infosys  post  installation  services  will  include  stabilization  and  final  acceptance  of  the  CIS Solution 

1.5 Guiding Principles of the Project 

Infosys acknowledges the following overarching principles will underpin the Project: 

The focus behind Infosys’ entire proposed delivery approach has been to ensure the near term and long term success of a mission‐critical IRWD program. Being a services organization, Infosys understands the business criticality of such a program and we are therefore tuned to thinking “Client First.” 

Infosys  shall  conduct  one  or  more  boot  camps  with  the  appropriate  IRWD  project  team members  and  explain  the methodology  described  in  this  and  related  documents  to  ensure everyone  understands  the  frame  of  reference  and  the  relevant  associated  deliverables.  This approach will also help the overall team understand their roles and responsibilities throughout the  lifecycle of  the program. When  there are  tasks or deliverables  that  incrementally build on one another, Infosys will follow the agreed upon sequence as outlined below in Section 6 of this SOW. 

Infosys will not  try  to  force‐fit a reinvention of  the  legacy system environment, but rather we intend to incorporate best practices for the CC&B framework as long as they do not conflict with IRWD’s  regulatory  requirements.  And we  intend  to  accomplish  as much  as  possible  through “configuration”  versus  “programming”  on  this  project.  Infosys will  not  be  granted  access  to IRWD  legacy  systems.   Where  needed,  the  IRWD  team will  provide  data  extracts  or  provide information  from  the  relevant  source  system(s)  in  the mutually  agreed  format  to  facilitate completion of the implementation tasks. 

Infosys  will  focus  on  IRWD’s  business  requirements  defined  in  the  RFP  while  considering potential future requirements of IRWD. 

Infosys will maximize the use of configuration rather than customization 

Infosys  will  apply  a  Governance  model  that  assures  service  delivery  predictability  .    The Governance model will leverage the significant operational experience gained over time working across multiple utility companies.  The model ensures transparency with minimal disruption and will provide IRWD the performance visibility necessary for the current program execution as well as set the stage for future phases.   

Infosys will remain focused on Project goals and on activities that will continue to move the Project forward. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 14 of 142 

Timely Delivery + Quality of Delivery will be key drivers of Infosys as a partner to IRWD throughout the life of our relationship 

1.6 Acceptance Criteria 

The  following  are  the  acceptance  criteria  agreed  between  Infosys  and  IRWD  for  the  successful 

completion of the project. 

1.6.1 Go Live Criteria 

Before  the  new  CIS  solution,  including  converted  IRWD  customer  and  billing  data,  base  software, 

configuration, customization and  interface points can move  to  the  IRWD production environment and 

be implemented in day‐to‐day production processing; the following criteria must be mutually signed off 

between Infosys and IRWD: 

Exit criteria  for Sign off of design, System  integration testing, User acceptance testing, parallel testing  and  performance  testing  are  met.  The  acceptance  criteria  for  individual  stages  are mentioned under individual sections in this document. 

Successful completion of all functional tests, integration tests, performance tests and signed off on all user acceptance tests. 

All requirements in the Client Functional Requirements are delivered as a part of this SOW, with any exceptions and/or deviations from this agreed to by both Infosys and Client via the Change Order process. 

Successful mock Cut‐over dress rehearsals. 

Train  the  trainer deliverables  are  completed by  Infosys  and  End user  training  is delivered by IRWD resources with Infosys support. All end users have also been trained and are confident in their ability to conduct transactions.  

The  Project’s  data  conversion  has  been  reconciled  as  defined within  the  Cut‐over  plan.    All discrepancies are adequately explained, documented and  is signed‐off by  IRWD. The scope of data  conversion  and  the  approach  for  reconciliation  mechanisms  shall  be  discussed  and mutually‐agreed upon during design stages. 

Testing with parallel production samples of all business functions has occurred and will compare the  legacy calculations to the new system calculations. The results are expected to be exact or explained  (deviations)  to  IRWD’s  satisfaction.  The  scope  and  approach  for  parallel  testing  is identified under the Parallel Testing section below.   Parallel Testing is proposed to be done for any  tests  that  have  a  financial  bearing  (such  as  payroll,  bills  and  Invoices  for  a  period  and financial statements at period end). 

1.6.2 Post Implementation Acceptance Criteria or Final System Acceptance 

The  Infosys post  implementation “go‐live” warranty period will cover  three months  for phase 1 and 2 

months for phase 2. The post  implementation support period will be utilized to support IRWD users as 

issues  appear  and  to  resolve  defects  found  and  reported  during  the  post  implementation warranty 

period. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 15 of 142 

Before  the  Project  and  this  Infosys‐IRWD  SOW  scope  can  be  considered  fully  delivered,  the  criteria 

defined within the Final System Acceptance plan must be met.  

Infosys and  IRWD will prepare a Final System Acceptance plan during  the course of  this project.   At a 

minimum  the  Final  System  Acceptance  with  include  the  following  final  acceptance  criteria  unless 

otherwise agreed upon by both IRWD and Infosys. 

1. The execution of the FSA plan will be conducted  window Execution of the FSA plan will be conducted for a period to complete 2 complete billing cycles (estimated at approximately 60 days) and will be begin no later than thirty (30) calendar days following Go‐Live for a total duration of three complete billing cycles. The FSA plan will clearly indicate when Final System Acceptance occurs.   

2. During the two complete billing cycles, the solution within scope must operate without generating any Severity One Errors which are not Testable and repaired within the same period. If any Severity One Errors occur during the warranty  period that are not so tested and repaired, the warranty period will be extended until the solution is tested and repaired. 

3. The solution within scope will be in production and available for use by IRWD’s business users and customers. 

4. Batch processes are completing within 4 hours or other time window as mutually agreed to during the Deploy Phase. 

5. All solution design, configuration, customizations and interface development have been documented and provided to IRWD. 

6. The solution has executed 2 consecutive month close activities successfully. 7. System Deliverables as defined in this SOW have been completed and accepted. 8. Day‐to‐day operations,  including daily and monthly  financial reconciliations, have returned 

to (or are approaching) the documented pre‐project levels of efficiency and accuracy. 9. Deferred  features  and  functionality  that    have  been  mutually  agreed  during  the 

implementation have been provided, tested, implemented and accepted by IRWD. 10. Project Completion criteria met as defined during this project. 11. Client post‐implementation support plan  is  in place with an on‐going support staffing plan.  

Formal  handoff  of  production  support,  including  outstanding  issues,  risks,  and  other concerns, has been made from the Infosys staff to the IRWD staff. 

The FSA plan will  include  interim  reviews of  the criteria  set  forth above during  the warranty window 

where  IRWD will promptly notify  Infosys of any deficiencies or non‐conformity upon discovery of  the 

same.   Within  ten  (10) business days  following completion of  the FSA Review Period  (the  last  two of 

three  complete billing  cycles during warranty) described  above  (including  any  extensions),  IRWD will 

notify Infosys of any remaining deficiencies from or non‐conformity with such criteria. If Infosys does not 

receive this notice within this ten (10) business day period, the FSA test will be deemed satisfactory and 

the solution will be deemed to have met all Acceptance Criteria. 

Upon notice  from  IRWD  (which  shall  include  reasonable documentation  regarding  such  error) of  any 

component  of  the  solution  failing  to meet  the  criteria,  Infosys will  promptly  facilitate  the  repair  or 

replacement of  the non‐performing  component at no additional  cost  to  Infosys  in order  to meet  the 

stated level of effectiveness for the stated period of time, or otherwise satisfy the applicable criterion. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 16 of 142 

 

1.7 Software Modules and Version 

The  following  is  the  list of  software  required  for  the  implementation along with  the  required  license 

count.    IRWD will procure  these  software  components.   Other  software  tools  required by  Infosys  for 

system integration will be procured by Infosys.    These include, but are limited to, the implementation 

tools listed in Section 1.8: Project Implementation Software and Tools. 

 

SR#  Oracle Utilities CC&B Elements  Count 

1  Oracle Utilities Customer Care and Billing Base  for Residential Customers – 

100 in Customer Count Perpetual 

850 

2  Oracle  Utilities  Customer  Care  and  Billing  Credit  and  Collections  for 

Residential Customers ‐ 100 in Customer Count Perpetual 

850 

3  Oracle Utilities Customer Care and Billing Rating and Billing for Residential 

Customers ‐ 100 in Customer Count Perpetual 

850 

4  Oracle  Utilities  Customer  Care  and  Billing  Cashiering  for  Residential 

Customers ‐ 100 in Customer Count 

850 

5  Oracle Utilities Customer Care and Billing Task Optimization Tools for 

Residential Customers ‐ 100 in Customer Count Perpetual 

850 

6  Oracle Utilities Customer Care and Billing Archiving for Residential Customers 

‐ 100 in Customer Count Perpetual 

850 

7  Oracle Utilities Customer Care and Billing Base for Commercial & Industrial 

Customers ‐ 100 in Customer Count Perpetual 

150 

8  Oracle Utilities Customer Care and Billing Credit and Collections for 

Commercial & Industrial Customers ‐ 100 in Customer Count Perpetual 

150 

9  Oracle Utilities Customer Care and Billing Rating and Billing for Commercial & 

Industrial Customers ‐ 100 in Customer Count Perpetual 

150 

10  Oracle Utilities Customer Care and Billing Cashiering for Commercial & 

Industrial Customers ‐ 100 in Customer Count Perpetual 

150 

11  Oracle Utilities Customer Care and Billing Task Optimization Tools for 

Commercial & Industrial Customers ‐ 100 in Customer Count Perpetual 

150 

12  Oracle  Utilities  Customer  Care  and  Billing  Archiving  for  Commercial  &  150 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 17 of 142 

Industrial Customers ‐ 100 in Customer Count Perpetual 

13  Oracle Utilities Customer Care and Billing Integration to Oracle E‐Business 

Suite Financials for General Ledger and Accounts Payable – Processor 

Perpetual 

14  Micro Focus Net Express for CC&B (Mfr is Micro Focus International, Third 

Party Program) – Named Developer Perpetual 

15  Oracle Utilities Customer Care and Billing Extractors and Schema ‐ 100 in 

Customer Count Perpetual 

1000 

16  Oracle Utilities Customer Analytics ‐ Application User Perpetual  30 

17  Oracle Utilities Revenue Analytics ‐ Application User Perpetual  30 

18  Oracle Utilities Advanced Spatial Revenue Analytics ‐ Application User 

Perpetual 

30 

19  Oracle Utilities Credit and Collection Analytics ‐ Application User Perpetual  30 

20  Oracle Utilities Advanced Spatial Credit and Collection Analytics ‐ Application 

User Perpetual 

30 

  Technology   

21  Oracle Database Enterprise Edition   

22  WebLogic Suite   

23  Informatica  Power‐Center  and  Power‐Connect  Adapters.  (IRWD  has 

confirmed they have the development license for this software ) 

 

  Oracle – Self Service   

24  Product:  Oracle Utilities Customer Self‐Service v2.x   

 

 

3rd Party Software:   

ACCUZIP  CASS and PAVE software for address validation and Bill Print 

solution 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 18 of 142 

1.8 Project Implementation Software and Tools 

The  following  is  the  list  of  software  that will  be  used  to  support  the  implementation  and  on‐going 

support of the solution.  Both IRWD and Infosys will be responsible for obtaining licenses as needed by 

their respective teams.  

SR#  Implementation and Support Tools  Count 

1  MS Project 2010 for project plan   

2  MS Word, MS Excel, MS Power Point for basic documentation   

3  MS  Visio  (or  other  agreed  upon  tool)  for  business  process  and  workflow 

documentation. 

 

4  Data Integrator Enterprise Edition   

5  Informatica Data Explorer   

6  Informatica Data Quality   

 

1.9 Project Assumptions 

Certain assumptions were taken  into account to determine the  level of effort to perform the scope of 

services included in this Statement of Work. These assumptions fall into the areas described below. 

1.9.1 General  The Project location is in Irvine, CA. 

Scoping  and  estimation  is  based  on  the  requirements  as  specified  in  the  Client  Functional Requirements. 

IRWD with  assistance  from  Infosys will  install  the  backend  database management  system  in each environment as required. Infosys will configure the database as required to support CC&B and OUCSS. 

IRWD  will  install  the  required  hardware  with  configuration  to  meet  Infosys’  specifications defined within this SOW. 

IRWD will provide the environment instances as listed in this SOW. Infosys will provide IRWD ith configuration/setup requirements. 

Infosys will provide support for designing the Disaster Recovery Site for CC&B and OUCSS along with  the  testing of DR site. Based on  the design delivered by  Infosys,  the  IRWD  infrastructure team will implement the DR setup. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 19 of 142 

Infosys will provide 3 months warranty support for Phase 1 and 2 months of warranty support for Phase 2. During  this warranty support period,  it  is assumed  that Level‐1 helpdesk support will be provided by IRWD. IRWD’s Help Desk is the first point of contact for business for issues.  The Help desk team will assess the issue, collect information, validate if it is a warranty issue and pass  it  on  to  the  Infosys  team.  Infosys  team  will  perform  root  cause  analysis  and  provide recommended action/changes to IRWD. 

Responsibility of  running  the  legacy  system during Parallel Run  is  the  responsibility of  IRWD.  Responsibility  of  running  the  new  system  is  shared  with  IRWD  and  Infosys.  Infosys  will  fix defects found during the parallel run. Infosys team will perform root cause analysis and provide recommended action/changes to IRWD. 

Changes to IVR are not included in this statement of work.  However, Infosys is responsible for implementing the interface between the IVR and CC&B. 

Tools for performance testing will not be provided by IRWD.  The project assumption is that all performance testing will be conducted manually.  Infosys is to provide performance benchmark data for reference. Infosys will provide IRWD with a manual performance test scope/plan. 

For  the  Phase  1  integration  of  CC&B  and  Customer  Web  Portal  (IRWEB),  IRWD  will  be responsible  for all changes within  IRWD’s web portal product.    Infosys will be  responsible  for developing  the  interface  to  CC&B.  Infosys  will  assist  with  problem  resolutions  on  interface testing. 

The version of CC&B being proposed in the solution is Oracle Customer Care & Billing V2.3.1, unless agreed to by both parties. Upgrade from 2.3.1 to a higher version is not considered in scope. Upgrade to a major version at any point during the course of the implementation will be considered and governed through the change order process defined in Section 8.4 of this document. 

All prices are quoted in U.S. dollars and include taxes where applicable. 

The Fixed Cost will be  firm  for  the services  identified herein  through  the project duration and post implementation support, as identified in this SOW.  

Prompt  decision‐making  and  problem  resolution will  be  required  to  achieve  an  on‐time,  on‐budget  project  completion.  It  is  expected most  decisions  and/or  problems  will  be  resolved within five business days (or to a mutually agreed to timeframe). 

Infosys and  IRWD are willing  to  implement  inherent “Best Practices”  in order  to minimize  the need  for  software  customizations.   This may not always be possible, but  IRWD will approach each opportunity from this perspective 

IRWD  and  Infosys  understand  the  project  scope  and  project  timelines  and  agree  to communicate and adhere to those objectives, thus setting the proper expectation level. 

All  scope  changes  identified  by  either  the  IRWD  or  Infosys  throughout  this  project  will  be documented and managed through the Change Control process. 

The solution will be developed to support only one language: English. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 20 of 142 

IRWD will provide access to the appropriate internal stakeholders and project team members to participate, provide input, review and sign‐off.  These resources will be backed‐up in the event of vacations, unscheduled lack of availability, etc. 

The workweeks for IRWD Project team members are based on a 9‐80 work schedule.  Daily work hours  are  from  7:00  –  5:00 Monday  –  Friday  except  for  every  other  Friday  as  defined with IRWD’s 9‐80 schedule. 

Out of town project personnel will generally be onsite Monday through Thursday and work from their  home  locations  on  Fridays,  unless  Project  deadlines  or  other  contingencies  require exceptions to this schedule. 

During the User Acceptance test phase, any subsequent changes (fixes, updates, etc) to the test environment will require appropriate regression testing to test for unexpected impacts. 

During  the project,  two  types of data cleansing are expected  to  take place: automated where possible and manual where  required. Automated data cleansing will be employed  in all cases unless  this  is  either  not  possible,  or more  expensive  than manual  data  cleansing  or  IRWD sensitive data requiring special handling.  Infosys’ conversion team will execute the automated data cleansing.  The manual data cleansing will be done by the IRWD business users.  Infosys will provide IRWD with the automated data cleansing documented procedure/process documented. Infosys will provide IRWD business users with documented procedure/process for manual data cleansing. 

Assumes legacy side of Interfaces effort is estimated & delivered by IRWD’s technical team. 

It  is assumed  that 60 months of usage history will be migrated  from  the  legacy CIS system  to CC&B and OBIEE.  

IRWD will go live with the latest version of CC&B, OBIEE, OUCSS and AccuZip as of the end of the Requirements  Analysis  Phase.  No  upgrades  to  newer  versions will  be  applied  until  after  all systems are in production, unless agreed upon by both parties. Service packs and OSS notes will be evaluated  for  inclusion after  the Requirements Analysis Phase only  if  they address  specific issues/requirements that endanger Project success in terms of budget or schedule. 

Infosys will utilize the current versions of Microsoft products, including MS Word, MS Excel, MS Project, MS Visio, MS PowerPoint and MS Access, to produce deliverables according to IRWD’s technical standards.  Should Infosys not operate at the same versions as IRWD, Infosys will make reasonable efforts, within Microsoft product capabilities, to save documents and deliverables to a level that would be accessible by IRWD or vice versa. 

Infosys will install CC&B and OUCSS software and related Third Party Software, as defined in this SOW and/or required to support the solution, on IRWD’s environment – inclusive of MicroFocus, WebLogic, AccuZip, et al. 

During the Project,  IRWD will  implement new rates, which must be built and tested as part of the scope of this project. 

Infosys will assist IRWD in development of documentation of “Best Practices” implemented as a result of the change to the new Oracle‐based Solution. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 21 of 142 

Infosys  and  IRWD  recognizethat  competing  initiatives may  be  a  risk  and  a  challenge  to  the project team and the implementation. IRWD will be responsible to ensure that the appropriate actions are taken to avoid any impact to the Project schedule, staffing, and costs related to any competing  projects.  Infosys  will  develop  and  own  the  Risk  Management  Plan.  Infosys  will monitor and control the risk log and identify action plan to mitigate risks. 

The  project  is  split  into  two  phases.    Based  on  the  schedule  outlined  in  Section  6.2  of  this Statement of Work, Phase 1 will start  in February, 2013 with go‐live scheduled sixteen months after project  start.    Phase  2 will begin  1 month  after  Phase  1  go‐live  and  is  scheduled  for  7 months.   

In  the event  that  IRWD extends  the Project beyond  these dates or  requests work beyond  the defined scope as specified  in this Statement of Work, Infosys may request a Change Order and an amendment to this Statement of Work. 

IRWD should anticipate and plan for organizational adjustments.    IRWD will be responsible for evaluating and managing any business process and  technical environment  changes, managing and executing  the organizational change plan and developing new performance measures  for the organization.  

 

 

Infosys will assist IRWD in in the creation or modification of user procedure documentation. 

1.9.2 Project Structure  IRWD will designate a dedicated Project Manager to oversee all aspects of this Project.  Infosys 

will  also  have  a  dedicated  Project Manager  to manage  all  Infosys  deliverables  and  activities identified within this SOW. 

IRWD will have a dedicated Project Director or sponsoring manager. This person will coach and mentor  the  IRWD Project Management  Team  throughout  the Project  and  ensure  the Project aligns with the enterprise objectives of IRWD. This role will report to the overall Project Sponsor. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 22 of 142 

Infosys  will  have  a  dedicated  Executive  Sponsor.  IRWD  assumes  this  person  is  ultimately responsible for the IRWD project.  Issues will be escalated to this resource. 

IRWD  is responsible for the coordination of the hardware supplier and other 3rd party project vendors under direct contract to IRWD. 

Infosys will be  responsible  for coordinating  third party vendors  for products and services  that have been subcontracted for by Infosys. 

All Infosys staff will report to the Infosys Project Manager. 

IRWD’s Project Manager will have the assistance and support of the IRWD core team throughout the life of the Project. The IRWD core team will have members from all functional areas and will be involved in the decision‐making process for the Project. 

IRWD will  have  a  steering  committee  that will  be  comprised  of  key  executives  and  Project stakeholders.  It  is  assumed  that  the  IRWD  Project  Director,  IRWD  Project Manager  and  the Infosys Project Manager will present  reports  to  the steering committee on at  least a monthly basis regarding the status of the Project. 

Infosys’  executive  sponsor may  participate  in  all monthly  Steering  Committee meetings  via teleconference and will participate in person at least every fourth month 

1.9.3 Staffing 

The IRWD and Infosys project teams will primarily be located in a single facility located at IRWD’s office location in Irvine, CA.  There also may be project activities conducted at other IRWD operations location(s) throughout the Project.  Infosys will perform a significant amount of work offshore.  These offsite project team members will require remote access to the hardware environment in support of this initiative.  Infosys will provide a Pre‐engagement Checklist 2 weeks prior to project start to include accessibility and other requirements. 

Both parties will provide qualified resources to meet the mutually agreed upon project schedule and milestones for implementation of the System.  Potential project delays or missed milestones will be reviewed by the Project Managers and appropriate scope changes or adjustments considered.  

All Project resources (IRWD, Infosys and others) will be available as required and defined in the Project staffing plan.   To  the extent such resources are not available,  Infosys will consult with IRWD about staffing alternative resources, whether such resources turn out to be IRWD, Infosys or  third  party  resources.    To  the  extent  the  staffing  plan  requires  changes  or  updates,  the change order process may apply.  

IRWD  will  staff  the  Project  with  qualified  resources  that  are  familiar  with  IRWD’s  business processes  and  practices.  These  resources  must  possess  the  necessary  competencies, capabilities, and dedication  to complete  the solution on  time.    IRWD’s project  team members will  be  empowered  to make  decisions  related  to  configuration  and  business  processes.    For some key decisions IRWD may be required to escalate the decision process.  IRWD will work to minimize the escalation of decisions to keep the decision process as streamlined as possible. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 23 of 142 

The  Infosys core  team will make decisions  related  to configuration and system enhancements based on the requirements defined by  IRWD team.   Business processes will be developed  in a collaborative manner, while utilizing the inherent best practices within CC&B and OUCSS. 

The  majority  of  business  process  design,  application  configuration  (for  production)  System Integration  testing,  UAT,  Performance  testing,  knowledge  transfer,  cut  over  and  warranty support  will  be  on‐site  at  IRWD’s  location  in  Irvine,  CA.  Development  activities,  application configuration, documentation,  research,  analysis of  issues, preliminary  reconciliation  analysis, data migration runs etc., shall be performed at one or more of Infosys’ off‐site solution centers. Warranty  Support  work  will  include  a  combined  on‐site  and  off‐site  presence  as  deemed appropriate by the Project Management team. IRWD will provide remote access for Infosys staff members working off‐site in support of the Project.  

IRWD shall provide the following facilities to Infosys team. The facilities will be used by Infosys personnel to deliver the scope of work for IRWD.  These facilities requirements will be included in the Pre‐engagement Checklist to be finalized 2 weeks prior to project start. 

o Work space for approximately 10 onsite personnel 

o Access to IRWD’s network using Infosys laptops.  Infosys’ laptops will require scanning and must run approved virus protection software. 

o 5 Virtual machines required to access the onsite servers from offshore resources. SSL VPN connectivity will be provided for rest of the offshore resources for connecting to the onsite servers. 

o Telephone connections for onsite personnel 

o Internet access for onsite personnel, with capability to connect to the Infosys network through VPN 

o Access to conference rooms/meeting spaces (as appropriate) to conduct workshops 

o Access to printer, copier and fax machine(s). 

o Access cards/other  for all  Infosys onsite employees  to  IRWD  facilities during and after office hours and during weekends. Infosys shall comply with the necessary background check needs to facilitate this. 

Infosys will support IRWD’s Quality Assurance activities related to the project.   Those activities will  include but not be  limited  to:  Infosys providing project  information  for Quality Assurance (QA) assessments and Infosys project team members participating in QA interviews. 

All IRWD and Infosys Project Team members are expected to take normal vacation and holiday days  throughout  the  course  of  the  project  except  during  stages  of  the  project where  their presence  is  critical.  The  Project Managers will  review  any  requests  for  time  away  from  the project before approval is granted. 

1.9.4 Project Management 

Infosys will assume responsibility for the successful implementation and completion of this SOW.  Infosys is responsible for managing the Project and ensuring solution delivery.  

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 24 of 142 

Infosys is responsible for maintaining the MS Project schedule (with IRWD input and collaboration) for both Infosys and IRWD resources.  

All Project documents will be maintained in electronic format and supported by supplemental hard copies based on IRWD requirements.  All final version documents will be clearly marked as the “Final” version and turned over to IRWD. 

Infosys is responsible for the initial installation, configuration, and testing of  initial 2 or 3 user PC workstations necessary to support the System’s front‐end environment.  Once IRWD has the knowledge of this process, this will be IRWD’s responsibility. Infosys will provide the required  documentation to enable the IRWD personnel to take up this responsibility.  

Infosys will work with IRWD to establish the electronic project office including: project directories, calendars, work program, status reporting and other items as agreed to. 

1.9.5 Data Conversion  

Infosys will develop a conversion strategy and present to IRWD for review and approval. 

IRWD will assign technical resources to provide Infosys with current system file layouts and data descriptions. 

Infosys will review IRWD file layouts and data descriptions.  The mapping of source data to the target environment will be done in a joint Infosys and IRWD workshop.  Infosys and IRWD will prepare the mapping specifications based on these sessions. 

Infosys will design, develop, create validation processes (for example dollars, meter reads, consumption) and unit test conversion load programs. 

IRWD will design, develop, and unit test the conversion extract programs. 

Infosys will run the data conversion programs and verify the quality of the data. 

Infosys will modify conversion load programs, and IRWD will modify conversion extract programs to address data conversion and data cleanup issues. 

Infosys will execute mock conversions to prepare for Go‐Live cutover as mutually agreed, based upon the results of initial mock conversions. 

IRWD will assign individuals to conduct data preparation and cleansing activities, as required. 

1.9.6 Development  

Infosys will take the lead and be responsible for the development of forms, reports, interfaces, conversions, enhancements, modifications and workflow with the assistance of IRWD resources identified in this SOW. 

Infosys assumes responsibility for managing the interface design, development, testing and roll‐out of interfaces by Infosys as defined in Section 5.3.3. 

IRWD will provide subject matter experts for the legacy system as required to support the design, development and testing of interfaces to other systems. 

Infosys will be responsible for the data import or export portion of all interfaces as they relate to the Solution (reference Section 5.3.3).  IRWD will be responsible for the data import or export portion of all interfaces as they relate to other systems. 

Infosys will be responsible for performing quality assurance of all product enhancements, interfaces, reports, forms, and workflows. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 25 of 142 

For OBIEE reports development the same OBIEE setup and ETL servers currently available by IRWD will be used for development and testing. It is assumed that the current IRWD setup has the development licenses installed for use by Infosys. 

1.9.7 System Testing  

Infosys will provide templates for testing. 

Infosys and IRWD will jointly develop all test plans outlining the testing approach, methods, data, and participants. 

Infosys and IRWD will assume responsibility for conducting a volume test to ensure batch and on‐line performance is within contractual performance levels as described in Section 3.0. 

IRWD will assume responsibility for conducting a business test focusing on how well the business processes flow with the new system. 

IRWD will review and perform testing activities under the direction of Infosys, per the test plan. 

Infosys will provide resources for product fixes resulting from errors identified during the system testing process. 

The System Integration Testing (SIT) testing will cover the components impacted by the implementation scope. IRWD will provide testing support for End to End testing of the components not covered in the Solution. 

1.9.8 Training 

Infosys will provide 2 weeks of operational enhancement training on BI to help the IRWD technical team enhance their knowledge on BI. The schedule of the training will be planned mutually between Infosys and IRWD during the course of the project. 

Infosys will be responsible for “Train the Trainer” deliverables and will develop a detailed training plan/schedule for this.  Infosys will develop an End User Training Plan, based on the Training Needs AssessmentIRWD trainers will be used to deliver training to the end users. Infosys and IRWD will jointly execute end‐user training.  One Infosys trainer will be present for each IRWD‐instructor‐led training session.  

IRWD will provide training classrooms with the appropriate space and technology to execute training. 

IRWD will provide its users with specific times during their workday to conduct a hands‐on user refresher either at their desktop or on a workstation within their work area. 

IRWD has the facilities and will provide the necessary logistics support for all training sessions, including: class schedules, meeting rooms, training rooms, material reproduction, overhead projectors, training workstations, and any other necessary training supplies. 

IRWD will ensure end‐user attendance at training 

 

1.9.9 Production Readiness and Cutover 

Infosys will develop an acceptance test plan.  IRWD will approve the acceptance test plan that will be mutually agreed with Infosys. 

IRWD will be responsible for conducting an acceptance test of the completed system as delivered by Infosys at the completion of system testing activities. 

Infosys with assistance of IRWD will develop a mutually agreed to go‐live plan and schedule. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 26 of 142 

Infosys and IRWD will jointly stage all aspects of the system in preparation for production cutover. 

Infosys and IRWD will jointly conduct production cutover activities. 

IRWD will conduct manual conversion activities as required following production cutover. 

1.9.10 Post Implementation Support 

An IRWD support group will be assembled prior to cutover to stabilize the implementation, and provide production support services, including user authorizations and security support. 

Infosys will provide on‐site support to IRWD during the first three complete monthly billing cycles (for Phase 1 and 2 months for Phase 2) that could require an estimated 14 weeks or more to complete. 

1.9.11 Technology  IRWD will be responsible for the procurement and installation of hardware to support the 

Project, including hardware installation, operating system installation, support, and maintenance.  Infosys will provide laptops, development software and other tools for all Infosys resources. 

IRWD  will  provide  network  setup  and  network  management  support.    Existing  networking infrastructure and adequate housing will be provided for the solution project (i.e. development, test and training environment) and production hardware. 

IRWD will implement a disaster recovery plan for relevant project environments, which will support all locations consistent with the current IRWD policies. IRWD will own the responsibility of Project environments (including Production) as well as the overall system back‐up plan. 

IRWD will provide all instances required for the implementation of the Oracle Solution throughout the Project.  This will include, but is not limited to, separate instances for development, test, quality assurance, training, and production. Additional instances if required during the Project will be procured by IRWD after mutual consent and agreement between Infosys and IRWD. 

The  responsibility  for  code  moves  belongs  to  Infosys  for  Dev,  CRP,  SIT.  However  this  will transition  to  IRWD  staff  as  the  Project progresses  (during  integration  testing),  as part of  the knowledge transfer process.   

Infosys will be  responsible  for  the configuration, packaging, build and deployment of code on different  environments  during  the  course  of  the  project.  Infosys will  define  standard  release management  procedures  for  code  propagation  and  software  configuration  management  to different  environments  using  the  recommended  release  management  procedures  for  the components of the solution.  

The  environment  management  responsibility  will  also  include  the  application  server administration activities required (for Development, Test , Training , Production and Staging) for normal health check procedures  to be conducted on  the Development, Test, Training   Staging and Production environments. This  responsibility will gradually  transition  to  IRWD staff as  the project progresses as part of the knowledge transfer process. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 27 of 142 

IRWD will provide appropriate connectivity for enterprise storage, enterprise backup hardware, software and media for all Project‐related servers. 

IRWD  will  provide  verified  backup  and  recovery  support  for  all  Project  environment infrastructures. 

IRWD  shall  support  the  installed  infrastructure with  support  and  direction  from  the  Infosys technical team members for the duration of the Project. 

IRWD will provide Infosys with access to the hardware and network environments (excluding Production when next explicitly included in scope) necessary for the implementation of the System.  Infosys personnel will adhere to IRWD’s security and data access policies and may be subject to appropriate criminal background checks. 

1.9.12 Solution Architecture The  following  are  the  high  level  guiding  principles  on  which  the  Infosys  solution  architecture  as 

proposed  for  IRWD  is based. The guiding principles are based on  the CC&B support  for  these guiding 

principles and its underlying Oracle Utilities Application framework (OUAF). 

High Availability: Solution components can be highly distributed and are capable of supporting necessary redundancies which promotes reliability, availability, and serviceability. The deployment architecture can be made to support an “always on” processing model.  

Scalability: The proposed solution components and the technology infrastructure are scalable in size, capacity and functionality to meet changing business and technical requirements to maintain ever‐changing service level adherence. 

Flexibility and Extensibility: The entire solution is built on ‘Open Standards’ with a proven architecture style. The application environment can accommodate new business requirements without major changes. 

Modularity and Reusability: Solution can support change and add functionality/services to its portfolio over time. Moreover, the software packages/components used in the overall solution are quite modular (e.g.: some CC&B and OBIEE components can even be implemented on an as‐needed basis.) 

Fault Tolerance: Solution deployment can be achieved to support high‐availability and load balancing techniques. This will ensure continued service in spite of possible failures in some components that constitute the solutions. Infosys will work with IRWD IT to provide guidance on adequate backup and recovery procedures that will meet the needs of point and time recovery. 

Upgradeability and Maintainability: Configuration and customization standard guidelines will be followed to ensure upgradability and maintainability of future releases. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 28 of 142 

2. Definitions Throughout this Statement of Work, the following words and expressions shall have the definitions set 

forth below.   

Acceptance  “Acceptance”  as used within  this  Statement of Work  is meant  as  an  industry 

term and is not a legal conclusion. 

As‐Is Business 

Process Description 

A  document  that  describes  the  steps,  people,  and  resources  involved  in 

completing  specific business  activities.   The  as‐is process documents how  the 

process is executed in the current Project environment. 

Change Order   A written instrument prepared and signed by the appropriate representatives of 

each party pursuant to Section 8.4 of this Statement of Work, memorializing the 

parties’  agreement  and  terms  for  amending  any  completed  or  uncompleted 

Deliverable,  any  additional  Deliverable  not  provided  for  in  this  Statement  of 

Work,  or  otherwise materially  amending    the  provisions  of  this  Statement  of 

Work 

Client   Refers to Irvine Ranch Water District.  

Client Project 

Manager(s) 

References  Client  Project  Manager(s)  and/or  Third‐party  Project  Manager(s) 

working in Client’s behalf. 

Client Solution 

Requirements  

The set of documents that contains IRWD functional and technical requirements 

to be delivered by  Infosys  for this solution  implementation.   These documents 

include:  

1. IRWD’s  RFP  for  Systems  Integration  Services  to  Implement  a Comprehensive Oracle Utilities Customer Care and Billing Solution RFP documents are listed in Appendix 3. 

2. Additional Requirements added to or clarified by  IRWD during the due diligence  phase  and  contract  negotiation  phase  of  this  procurement effort.    These  documents  provide  clarification  and  additional information on  the requirements  to be delivered by  Infosys under  this SOW (see Appendix 2). 

 

3. Additional  Requirements  as  proposed  by  Infosys  within  either  their original  bid  or  within  updated  proposal  documents  during  the  due diligence  and  contract  negotiation  phase.  See Appendix  1  for  Infosys’ updated proposal documents and Appendix 4  for  their  initial proposal documents). 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 29 of 142 

Client Solution 

Requirements Matrix 

Matrix or wookbook created at the closure of Analysis to capture complete  list 

of  requirements  from Client  Solution Requirements.   The  intent  is  to use  this 

matrix for requirements traceability. 

Co‐Responsibility 

 

Both Client and Infosys share the responsibility for the deliverable.  

Cut‐Over   The  Cutover  includes  all  activities  required  to  prepare  the  systems  for  the 

transition  of  testing  the  new  system  to  production  processing with  the  new 

solution.    The  activities  will  include  ensuring  security  is  set,  user  profile 

established,  close‐out  of  pending  data  in  the  legacy  system,  manual  data 

conversions  if  required,  rollout  of  system  access  to  end  users  and  other 

automated or manual activities required. 

Defect Tracking Tool  This is tool/application to be used by the project team to log the defects found 

from the review and validation of the deliverables produced throughout the life 

of  the project. Both  IRWD and  Infosys  (onsite & offshore) will have access  to 

this tool.   The defect tracking tool will be finalized during project initiation. 

Final Acceptance or 

System Acceptance 

The Project  is  complete when  IRWD has accepted all Deliverables and  Infosys 

has  successfully  completed  all Activities described  in  this  Statement of Work.  

IRWD Project Director has reviewed the Project Completion Criteria defined  in 

this Statement of Work and has been accepted by  IRWD.   Formal written sign‐

off will be provided to Infosys. 

Fixed Price  The total cost for implementation services to be paid to the Infosys.  These costs 

cannot  increase  as  long  as  the  scope  corresponds  to  all  of  the  items  in  this 

Statement of Work. 

Go‐Live  The  introduction  of  the  Solution  into  IRWD’s  Production  Environment 

Infrastructure,  fully  operational,  made  available  for  use  to  conduct  IRWD’s 

business operations  and  approved/accepted by  IRWD  as production‐ready  via 

signature.  

Infosys  Infosys Limited, also referred to as System Integrator within this SoW. 

Integration Test   Integration  testing  includes  all  items  delivered  as  part  of  this  Statement  of 

Work.    By  business  process  all  features  and  functions,  configurations, 

modifications,  interfaces,  reports,  custom  code  developed  working  together 

with all associated reports, screens, transactions, and interfaces, and integrated 

with  the  manual  business  processes.    Integration  testing  should  also  test  a 

variety of scenarios covering different  types of customers, accounts,  locations, 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 30 of 142 

user categories, dates, etc.    Integration  testing  is structured  in nature and has 

expected  results.    Integration  Test  is  also  referred  to  as  System  Integration 

Testing (SIT). 

IRWD  Irvine Ranch Water District, also  referred  to as Client or Customer within  this 

SoW. 

IRWEB  IRWD’s existing Customer Web Portal. 

Legacy Systems  References IRWD systems being replaced. 

Mock Cut‐over   A mock cut‐over will consist of a test of all activities (automated and manual) to 

be completed as part of cut‐over  to production process.   The mock Go Live  is 

staged in the similar manner as the pre‐cut‐over steps and procedures including 

full data conversions and validation.   The purpose of this test  is to ensure that 

all cut‐over activities have been defined and estimates  identified  for  the  time 

and resources required implementing them. 

Modification   Modification is defined as the extension done to CC&B, OUCSS or OBIEE through 

custom code. 

Organizational 

Change Management 

The activities, events, processes and procedures that are employed for handling 

transformation from one system environment to another.  This relates primarily 

to  the  preparation  of  people  and  the  design  of  business  processes  to work 

within to the new business environment. 

Phase  There are 2 terms for Phase within this SOW.  1) the project will be delivered in 

2  parts.    #1  CC&B/OBIEE  and  #2  OUCSS.    2)  the  project  delivery  tasks  are 

grouped into Phases: Initiation, Req Analysis, Design, etc. 

 

Process Design   The process design is conducted during business process modeling activities and 

focuses  on  conducting  business  process  design  work  in  the  context  of  the 

system  environment.    This  design  work  will  address  operational  and 

organizational changes required to implement the proposed solution. 

Project Management 

Team 

The  Infosys Project Manager(s), Third‐Party Project Manager( as applicable  to 

this project) and  IRWD Project Manager(s) comprise  the Project Management 

Team. 

Quality Assurance  The process of verifying  that  the proper processes and procedures have been 

adhered to on the Project from a methodology as well as Project management 

perspective  and  that  the  deliverables  included  the  appropriate  content  and 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 31 of 142 

meet expectations. 

Release Management   Release  Management  Process  is  the  process  which  will  define  how  the 

code/configuration/algorithm  changes  will  be moved  from  the  development 

environment to the next stages i.e to ST, SIT, UAT or production environments. 

This document will  also  identify how  versioning will be done  for  each of  the 

changes and how  the changes will be applied on each of  these environments 

and the persons responsible for the activities.  

RFP  IRWD’s Request for Proposal: SYSTEMS INTEGRATION SERVICES TO IMPLEMENT 

A COMPREHENSIVE ORACLE UTILITIES CUSTOMER CARE AND BILLING SOLUTION 

released May 15, 2012. 

Severity 1  This  classification  designates  a  programmatic  or  configuration  defect  that 

renders a component of the system unusable or inoperable.  This error is a loss 

of  the  capability  to  perform  a  function.    A workaround  does  not  exist,  and 

testing  that  function  cannot  be  performed  until  the  problem  has  been 

corrected.  Errors that impact the utilities ability to perform financial reporting, 

customer billings and customer facing errors that  impact the ability to present 

accurate  information  to  their  customers or any other  core business  functions 

are automatically classified as a Severity 1. 

Severity 2  This  classification  designates  a  programmatic  or  configuration  defect  that 

renders a key component of the system unusable or inoperable.  This error is a 

loss of the capability to perform an important business function.  A workaround 

does  not  exist  or  the  workaround  is  so  difficult  that  if  the  system  were  in 

production, this defect would result in a serious impact to the business.  

Severity 3  This  classification designates a programmatic or  configuration defect  that has 

significant  limitation to conform to the documented capabilities to  include but 

not  limited  to  the  application,  the  application modules,  the  system  and  its 

features. This  limitation stops the user from performing the normal use of the 

application; however,  a mutually  agreed workaround does  exist.    Testing  can 

continue to be performed on the module with a workaround. These program or 

configuration errors  limit  the capability of  the application or  function, but are 

cosmetic or minor in nature.  There is a practical workaround or the defect does 

not impact IRWD’s operation of the application in any significant respect. 

Solution  The  combination  of  all  Oracle  software  modules,  all  Third  Party  Software 

modules and all Infosys associated services that must meet the requirements of 

this Statement of Work and IRWD Solution Requirements.  

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 32 of 142 

Mock Conversion   A Mock Conversion  is an execution of  the conversion processes and programs 

for the entire data set “To Be” converted.  All conversion validation is executed 

as well as part of the Mock conversion. 

Test Plan  Document that outlines a strategy or approach for testing.   A Project Test Plan 

would  describe  the  schedule,  platforms,  staffing,  requirements,  tools,  testing 

stages, and defect  tracking  for all Project  testing.   Test plans  for specific  tests 

states  detail  groups  of  test  scripts  to  be  used  and  include  key  set‐up  issues, 

dependencies, schedules, platforms, data requirements, etc. 

Test Script  Document  that  describes  what  steps  and  actions  are  required  to  test  a 

particular  feature  or  function.    The  document  also  describes  the  specified 

expected results.  

Third Party Software  Third  Party  Software  includes  all modules  offered  by  Infosys  as  part  of  the 

Solution.  Infosys shall be required to contract with and manage the Third Party 

Software providers. 

“To Be” Business 

Process Description 

A  document  that  describes  the  steps,  people,  and  resources  involved  in 

completing specific business activities.  The “To Be” process documents how the 

process will be executed in the future Solution environment. 

User Acceptance Test  A  final  testing  step  that  is  the  final  tests  prior  to  Cut‐over.    This  test  is  all 

inclusive of  the Project scope and all scope  items must be completed prior  to 

the beginning of this test. 

Warranty(aka Post go 

live support) 

Process  where  production  defects  pertaining  to  the  Solution  are  addressed 

fixed and migrated to production. Infosys warrants to IRWD that it will provide 

the  Services  and Deliverables  in  accordance with  generally  accepted  industry 

standards  and  practices.  This  representation  and warranty  shall  survive  for  a 

period of three (3) months following the “go live” of the Solution, as described 

in the SOW.  

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 33 of 142 

3. Performance Criteria 

Infosys will conduct performance  testing  to ensure  that  the Solution will conform  to  the performance 

standards outlined in Section 3.0 of this Statement of Work. During the Performance Testing portion of 

the Project the required performance levels will be measured using manual testing and Infosys will tune 

the system to get the optimum response time.  

The  System  will  support  120,000  IRWD  customers  receiving  water,  wastewater,  and  other  utility 

services.  The System will support all Client users with no degradation in system performance. 

The proposed system will provide an average response time of 1.0* second during business hours.  The 

nightly batch processing  (all needed modules), must execute within  an  automated  scheduler, will be 

completed within a four (4) hour window. 

If these Performance Criteria are not achieved during the Performance Test a defect will be  logged for 

Infosys to correct as part of the defect resolution process in Section 8.8.3. Since a performance testing 

tool  is not being used for the performance testing,  it  is possible that the average response time of 1.0 

second  is not met  immediately before or  after Go  Live. By  the  end of  the  90 Day warranty  support 

period  Infosys  is  expected  to  correct  this  to  ensure  the  performance  level  are met  consistently  as 

defined in the performance testing plan. 

 

*The  response  times mentioned above are  for  the database and application server performance. Any 

delays due  to  the network  latency  and bandwidth will be excluded  from  the performance  criteria.  If 

problems  with  network  latency  and/or  bandwidth  keep  Infosys  from  being  able  to  meet  the 

performance criteria, Infosys will provide advice and assistance to IRWD on the possible resolutions for 

the network/bandwidth  issue. The actual resolution  for the network  issue will have to be provided by 

IRWD to resolve network and bandwidth issues.  

The above performance criteria agreed is for CC&B as a standalone application. For OUCSS performance 

Infosys and IRWD will mutually develop performance metrics consistent with industry practices together 

and take the best available performance metrics as the base for OUCSS. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 34 of 142 

4. Recommended Hardware and Sizing 

It  is  IRWD’s  responsibility  to purchase  the  recommended  configuration  (or a  configuration of greater 

performance  capacity)  that  IRWD,  Infosys  and  hardware manufacturers  have  agreed  upon.    Prior  to 

ordering the servers, IRWD will review server specifications with Infosys to confirm server specifications. 

Figures  1,  2  &  3  below  show  the  server  configurations  recommended  for  the  performance  criteria 

defined above in section 3.0.* 

*It  is noted  that hardware  technology and performance  capabilities are  constantly  improving.    IRWD 

intends to procure the  latest technologies available.   Therefore, the hardware sizing and configuration 

could be different than that stated below.   However, substituted hardware configurations will provide 

the same or greater performance capabilities.  Mapping of acceptable substitutions can be identified via 

the xRef: IBM x86 Sever Reference. 

4.1 CC&B Hardware and Sizing 

CC&B  Dev  Environment  :    The  6  Cores  36  GB  RAM  servers  available  in  the  current  IRWD  Dev 

Environment can be used as CC&B Dev Box. Upgrade the RAM to 64 GB 

Existing OBIEE Dev Environment:  The existing IRWD OBIEE Dev environment can be used. Upgrade the 

server from 2 to 4 Cores for better performance 

The DR Setup  is recommended as replica of Production. This environment can also be used for testing 

(ST, SIT ) 

Existing OBIEE PROD Environment: The current IRWD PROD environment can be used by upgrading the 

Cores to 4 Cores, RAM : 36 GB 

Tier  Physical Server  Servers  CPU RAM/  

Server(GB) 

High 

Availability

Environment : Production (CC&B) 

App  CCB APP  2  2*6 core cpu (2.66 ghz)  48 Weblogic 

Cluster 

DB  CCB DB  2  2*4 core cpu (2.66 ghz)  64  Oracle RAC 

Batch  CCB Batch  1  2*4 core cpu (2.66 ghz)  32  NA 

Environment: DR / Test (CC&B)  ‐ The DR environment will also be used for Testing purposes 

App  CCB APP  2  2*6 core cpu (2.66 ghz)  48 Weblogic 

Cluster 

DB  CCB DB  2  2*4 core cpu (2.66 ghz)  64  Oracle RAC 

Environment: Pre‐Production / Staging (CC&B) 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 35 of 142 

App  CCB APP  2  2*6 core cpu (2.66 ghz)  48 Weblogic 

Cluster 

DB  CCB DB  2  2*4 core cpu (2.66 ghz)  64  Oracle RAC 

Environment: Development/Demo 

IRWD has confirmed the availability of the 6 Cores 36 GB RAM servers available in the current 

IRWD Dev Environment.  These can be used as CC&B Dev/Demo environments. The RAM has 

to be upgraded to 64 GB. 

Figure 1: CC&B Hardware Sizing (preliminary estimated specifications)

 

4.2 OUCSS Hardware and Sizing 

The OUCSS Production Database will reside on the CC&B production server. The OUCSS DR database will 

reside on the CC&B DR server. The staging environment for OUCSS is optimized to have only 1 physical 

server  each  for  APP  and DB  servers.  The  physical  hardware  recommended  is  IBM  Blade  server  X86 

series. 

Environment  Tier  Physical Server 

Servers OS  CPU  RAM  Per Server (GB) 

High Availability 

Production  Web/App  OUCSS APP 2  Red Hat Linux 

2*4  Core  CPU (2.93 ghz) 

64  Web  logic Cluster 

Production  DB  OUCSS DB  NA  Red Hat Linux 

2*4  Core  CPU (3.06 ghz) 

  CC&B  Oracle RAC 

Staging  Web/App  OUCSS APP 1  Red Hat Linux 

2*4  Core  CPU (2.93 ghz) 

64  Web  logic Cluster 

Staging  DB  OUCSS DB  1  Red Hat Linux 

2*4  Core  CPU (3.06 ghz) 

64  Oracle RAC 

DR/Test  Web/App  OUCSS APP 2  Red Hat Linux 

2*4  Core  CPU (2.93 ghz) 

64  Web  logic Cluster 

DR/Test  DB  OUCSS DB    Red Hat Linux 

2*4  Core  CPU (3.0 ghz) 

64  Oracle RAC 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 36 of 142 

Development  ALL  OUCSS APP/DB 

1  Red Hat Linux 

2*4  core CPU(2.66 ghz) 

48  NA 

 

 

Tier  Physical Server  Servers  CPU RAM/  

Server(GB) 

High 

Availability

Environment: Production (OUCSS). The Database server for OUCSS will reside on the CC&B 

production server. 

Web/App  OUCSS APP  2  2*4 core cpu(2.93 ghz)  64 Web logic 

Cluster 

DB  OUCSS DB  NA Will  reside  on  CC&B 

PROD server   Oracle RAC 

Environment:  DR  /  Test  (OUCSS)    ‐  The  DR  environment  will  also  be  used  for  Testing 

purposes. The Database server for OUCSS will reside on the CC&B production server. 

Web/App  OUCSS APP  1  2*4 core cpu(2.93 ghz)  64 Web logic 

Cluster 

DB  OUCSS DB  NA Will reside on CC&B DR 

server   Oracle RAC 

Environment: Pre‐Production / Staging (OUCSS) 

Web/App  OUCSS APP  1  2*4 core cpu(2.93 ghz)  64 Web logic 

Cluster 

DB  OUCSS DB  1  2*4 core cpu(3.06 ghz)  64  Oracle RAC 

Environment: Development/Demo (OUCSS) 

ALL  OUCSS APP / DB  1  2*4 core cpu(2.66 ghz)  48  NA 

Figure 2: OUCSS Hardware Sizing (preliminary estimated specifications) 

 

4.3 OBIEE Hardware Sizing 

 

Tier  Physical Server  Servers  CPU RAM/  

Server(GB) 

High 

Availability

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 37 of 142 

Environment : Production (OBIEE) 

The  current  IRWD PROD environment  for OBIEE  can be used. The number of  cores on  this 

server needs to be upgraded to 4 Cores and 36 GB RAM for better performance. 

Environment: DR / Test (OBIEE)  ‐  

The  DR  environment  created  earlier  by  IRWD  OBIEE  instance  will  also  host  the  DR 

environment  for  OBIEE‐CC&B  solution.  For  the  purpose  of  OBIEE  testing,  the  CC&B  DR 

environment will be used for installing OBIEE test instance. 

Environment: Pre‐Production / Staging (OUCSS) 

The Pre‐Production / Staging service of CC&B will also host the OBIEE instance. 

Environment: Development/Demo (OUCSS) 

The current  IRWD Dev environment can be used. Upgrade  the server  from 2  to 4 Cores  for 

better performance. 

Figure 3: OBIEE Hardware Sizing (estimated specifications) 

 

4.4 DR Infrastructure Setup and Architecture 

 

The operating system proposed for the CC&B and OUCSS environments is Red Hat Linux. The total SAN 

requirement for the entire stack consisting of CC&B, OUCSS and OBIEE is 22 TB.  

 

Environment/Component  CC&B  OUCSS  OBIEE  Total SAN 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 38 of 142 

Development  1.5 TB  500 GB  2 TB  4 TB 

Testing  NA  NA  NA  NA 

Pre‐Staging  2.5 TB  500 GB  2 TB  5 TB 

Production  3 TB  1 TB  5 TB  9 TB 

DR  3 TB  1 TB  NA  4 TB 

Total  22 TB 

 

The above specifications provided by  Infosys are preliminary sizing numbers based on the  information 

received during the proposal and due diligence phase. Infosys would conduct a detailed sizing exercise 

during the execution phase and recommend a firmed up hardware sizing deployment architecture and 

the hardware availability recommendations based on the server requirements during various phases of 

the project. 

4.5 Desktop Configuration 

IRWD will procure desktops for the endusers of the solution.  Infosys recommends the enduser desktop 

configuration meet or exceed the following. 

Configuration  Processor  Memory  Monitor  

Minimum  Pentium IV–2.0 GHz  1024 

MB 

1024X768**

16‐Bit color 

Recommended  Pentium IV 3.0+ GHz;  any Core2 Duo; or any Athlon X2  2048 

MB 

1280X1024* 

32‐Bit Color 

* The Recommended configuration will support better performance of the client. 

**  To  reduce  the  amount  of  scrolling  required  for  pages  that  are  longer  than  768  or  1024  pixels, 

consider placing a monitor into vertical position (with narrow side on the bottom). 

 

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 39 of 142 

5. Program Scope 

5.1 General Scope Overview 

The  scope of  the Project will  include  implementation of  comprehensive CIS  Solution  consisting of an 

integrated suite of software applications from Oracle Corporation (Oracle CC&B, OUCSS and OBIEE) and 

other  software  vendors  indicated  within  this  document,  including  AccuZip,  et  al.  The  standard 

functionality of these products will be implemented as well as any functionality specifically addressed as 

part of the scope identified in this Statement of Work. 

The  Oracle  Solution  will  assist  IRWD  in  reducing  operating  costs,  optimizing  performance,  and 

streamlining  processes.  The  Oracle  Solution  flexibility  empowers  IRWD  to modify  and maintain  the 

functionality of the system at a reasonable cost as business requirements change. 

Data‐driven  decision making  through  timely,  accurate  information  and  ad‐hoc  reporting  capabilities, 

provide the tools to manage Client’s business effectively. 

The  proposed  Solution  focuses  on  configuration  rather  than  customization. As  IRWD  business  needs 

change and organization expands,  the  inherent  flexibility of  the system supports  these changes. Most 

configuration  changes  can  be made  by  the  IRWD  staff,  eliminating  the  need  for  external  technical 

experts and expensive customizations. 

 

5.2 Program Sctructure 

 

5.2.1 Project Organization Structure 

The management  structure of  the Project will  consist of  team members  from  IRWD,  Infosys and any 

third‐party  hired  by  IRWD.    The  Infosys  Project  Team  members  will  report  to  the  Infosys  Project 

Manager (regarding task assignments). 

5.2.2 Infosys Staffing 

Figure 4 highlights the proposed Infosys and Oracle staffing and reporting structure. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 40 of 142 

Infosys Program Manager

Colin Harrison

Infosys Data Conversion Lead

Infosys Functional Consultants

IRWD CIS SMEs

IRWD Business Analysts

Oracle Functional Consultants

Infosys Technical Lead (CCB, OBIEE)

Infosys Technical Architect (CC&B)

Oracle Infra /Tech Consultant

IRWD Technical Analysts

IRWD DBAs

Functional Team Technical Team

IRWD IT Lead Infosys Test LeadIsabel Fang

Infosys Test Analysts

IRWD Test Lead

Testing Team Change Management Team

IRWD Org Change Manager

IRWD Change Agents

Infosys OCM Lead

Oracle Project Manager

Infosys Project Manager

Stan Tunney

Infosys Relationship Manager

Bill Fenstermaker

Infosys Executive Sponsor

Ashiss Kumar Dash

IRWD Project Sponsor

IRWD Project Manager

Infosys CC&B Functional Team

Infosys Data Conversion 

TeamInfosys Project Management 

Group

Infosys Senior Project ManagerAyyoob Hussain

Infosys Training Developers

Infosys CC&B Technical Team

Infosys DBA

Infosys OBIEE/DWH Technical 

Team

Infosys Offshore Team

IRWD Team

Infosys Onsite Team

Infosys Offshore Team

Oracle Team

Infosys Reporting Team

Oracle Conversion Architect

IRWD Test Analysts

 

Figure 4 : Infosys and Oracle staffing 

 

Project Role  Key Resource 

Executive Sponsor  Ashiss Kumar Dash 

Program Manager   Colin Harrison 

Project Manager   Stan Tunney 

Offshore Sr. Project Manager  Ayyoob Hussain 

 

The final names of resources will be mutually discussed with IRWD and finalized prior to the start of the 

program. 

 

5.3 Major Scope Components 

 

5.3.1 Client Solution Requirements 

The Client Solution Requirements, in conjunction with this Statement of Work will be used as the basis 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 41 of 142 

to guide  the design, configuration, development,  testing and  training activities  for  the solution. Client 

Solution Requirement documents will be  the key  input  to  the analysis activities. A  tracking document 

will  be  generated  listing  all  the  requirements  defined  within  the  Client  Solution  Requirements 

document.   The  format will be  similar  to  structure of  the Functionality Checklist  located  in Appendix 

A1.2  of  the RFP.   Requirements  listed  in  the  RFP  text  (and  not  represented within  the  Functionality 

Checklist) can be added to the Functionality Checklist for tracking purposes.  New columns will be added 

to  the  Functionality  Checklist  to  identify  if  the  item was  covered  during  the  To‐Be  Business  Process 

Analysis session and which To‐Be Business Process Analysis document  it was covered  in. The scope of 

the requirements covered in the Functionality Checklist is categorized into: 

1) Part of Current Base Solution 2) Configuration Required 3) Component Customization ‐ Extensions/Modifications ( includes Interfaces and Reports ) 4) Not provided / Not Needed 5) Manual Workaround 

The requirements categorized as ‘Not Provided’/ Not Needed are not priced as part of the scope and are 

discussed and agreed with IRWD as part of the Due Diligence sessions. The Client Solution Requirements 

are attached in Appendices 1‐4. 

5.3.2 Modifications (Extensions) 

All  modifications  have  been  identified  by  Infosys  and  are  referenced  in  Appendices  1‐4    of  this 

Statement of Work. 

5.3.3 Interfaces 

Infosys will design, build and  test  the  interfaces described  in  the  table below.   This  list  identifies  the 

interfaces requiring additional development that will be delivered as part of the project plan.   The  lists 

of standard  interfaces are  incorporated  into the Client Functionality Requirements which  is  included  in 

Appendices  1‐4 of  this  SOW.    The direction  and  content of  the  interface will be  finalized during  the 

Requirements Analysis phase of the project and documented  in the Requirements Traceability Matrix ; 

this  list  is  intended  to  identify all of  the  known  touch points  identified by  IRWD.   The Requirements 

Traceability Matrix will detail the specific expected data exchange to be agreed to by IRWD. 

 

Interface Name  From   To  Direction  Mechanism 

ACH  Direct  Debit 

Payments 

CC&B  Bank of America  Out Bound  Secured File Based 

ACH  EFT 

Consumer/Business 

Payments 

Bank of America  CC&B  In Bound  Secured File Based 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 42 of 142 

Backflow Assembly  CC&B  Backflow  Test 

Tracking System 

Out Bound  File Based 

Bill Images Archive  CC&B/ OBIEE  Web Docs  Out Bound  Secured File Based 

Bill Print ebill  CC&B  Check Free  Out Bound  Secured File Based 

Bill Printing  CC&B  Printer  Out Bound  Secured File Based 

CASS (AccuZip)  CC&B  CASS Software  Two Way  File Based/ Point to Point 

Conservation/Rebates 

Processing 

Source  CC&B  In Bound  File Based 

Customer  Customized 

Payments (CCP) 

Source  CC&B  Two Way  File Based 

Customer Web  Portal 

(Phase 1) 

CC&B  IRWEB  Two Way  File  Based  +  Point  to 

Point 

ebill  Registration  / 

registration 

Check Free  CC&B  In Bound  Point to Point 

Evapotranspiration 

Rates Upload 

ET Website  CC&B  In Bound  File Based 

GIS Interface  CC&B  GIS  Two Way  Point to Point 

IVR Balance Enquiry  IVR  CC&B  Two Way  Point to Point 

Online Payments  Check Free  CC&B  In Bound  Point to Point 

Oracle AR  CC&B  EBS  Out Bound  Secured File Based 

OUCSS (Phase 2)  OUCSS  CC&B  Two Way  Point to Point  

OUCSS‐Fiserv  OUCSS  Fiserv  Two Way  Point to Point 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 43 of 142 

Remittance 

Processing  –  Credit 

Card 

Bill Matrix  CC&B  In Bound  Secured File Based 

Remittance 

Processing – Lockbox 

US Bank  CC&B  In Bound  Secured File Based 

Reporting  CC&B  BI 

Publisher/OBIEE 

Out Bound  Point to Point 

Single Sign On/CC&B  Online Portal   CC&B/OBIEE  Two Way  Point to Point 

Single Sign On/OUCSS 

 (This  is  for  internal 

customers  or  IRWD 

personnel ) 

Online Portal  OUCSS  Two Way  Point to Point 

Usage Interface  ACS  CC&B  Two Way  Secured File Based 

Work Orders  CC&B  EAMS  Two Way  Point to Point 

 

5.3.4 Data Conversion 

Infosys will work with IRWD to design, build, and test the data conversions from the legacy applications 

to  the  CIS  Solution.    The  content  of  the  data  conversions will  be  finalized  during  the  Requirements 

Analysis phase of the project and documented in the Requirements Traceability Matrix .   

Reconciliation  reports  will  be  created  to monitor  accurate  conversion  of  objects  such  as  accounts, 

meters,  customers,  service  points,  active  balances,  and  other  objects.    Reports will  also  need  to  be 

created  to  identify  records  that must  be  corrected  in  the  legacy  system  prior  to  conversion  (Data 

Cleansing).   The  specific  reports and validation processes will be determined by  the Conversion  team 

during the Requirements Analysis, Design and Build phase, and will be documented  in the Conversion 

Plan. 

The  following  table  summarizes  the most  important deliverables  and  responsibilities  for  a  successful 

conversion: 

Data Conversion Responsibility Matrix: 

P – Primary responsibility 

S – Supporting role 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 44 of 142 

Task  Infosys  Client 

Initiate     

Lead data conversion effort  P   

Create data conversion plan  P  S 

Provide  list of data  that needs  to be  converted along with major 

Oracle  application  suites  tables  that  will  be  populated  and 

applicable valid codes/ranges. 

P  S 

Create legacy data definitions  P  S 

Create and perform standard data extractions from legacy systems   P  S 

Unit test extracted data for validity  P  S 

Automated cleanup of data in legacy systems  P  S 

Manual cleansing of legacy data  S  P 

Extract structure and definition of legacy data, including flat files  S  P 

 

Clean Data from Legacy Systems 

Infosys will be responsible for the data profiling and cleansing activities and will provide clean data to 

the  Infosys Data Conversion  team  for migration.  If  there  is  any data  set  requiring manual  cleansing, 

IRWD will be  responsible  for manual  cleansing on  legacy  systems before  the  automated  cleansing  is 

done by Infosys. 

IRWD will produce financial reports needed from the legacy system prior to the cut‐over and included as 

predecessor tasks in the master project plan.  IRWD will provide: 

 a) Report of total A/R for each customer 

 b) Standard legacy system trial balance report for each data cut.   

The  reason  for  this  is  to  ensure  legacy  system  trial balance  report  totals match  the A/R provided  to 

Infosys in the data cut. 

Infosys Responsibilities 

Infosys will provide a Data Conversion Plan that will: 

List tasks that will require manual entry (automated conversions may depend on completion of manual conversion).  

Establish the number of pre‐install conversions and dates to ensure conversion success. 

List  supporting  documentation  needed  from  IRWD  to  proof  post  conversion  data,  including cutoff dates in conjunction with data cutoff if applicable. 

Create a list of data elements to be balanced with each conversion. 

Detail the data validation plan. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 45 of 142 

Expected completion date for development of conversion programs. 

Assign responsibility and expected start and end date of testing process. 

Within  the  data  conversion  plan,  Infosys will  develop  a  list  of  data  elements  to  balance with  each 

conversion. Infosys and IRWD will work together to build a mutually agreed upon  list based on what  is 

reasonable and possible in the legacy data and with the conversion process. 

 

5.3.5 Reports 

Infosys will deliver the reporting requirements defined within the section 3.1.6 of RFP  

The scope of the Reports considered for the solution is provided below: 

1. OOTB  dashboards  and  reports  from  the  following modules  as  given below  are  considered  in 

scope .   

Oracle Utilities Advanced Spatial Credit & Collection Analytics 

Oracle Utilities Advanced Spatial Revenue Analytics 

Oracle Utilities Credit & Collection Analytics 

Oracle Utilities Revenue Analytics 

Oracle Utilities Customer Analytics 

2. Approximately  62  Reports  from  section  3.1.6  of  the  RFP  are  considered  in  scope.  The 

assumption taken for these 62 reports is 50% of these reports can be met using out of the box 

reports/dashboards  and  50%  of  these will  require  new  reports  to  be  developed.    However, 

IRWD will not be charged  for  these 62  reports, whether out of  the box or new  reports  to be 

developed. We  have  also  assumed  that  the  data  for  these  reports  can  be  created  using  the 

available metadata within OBIEE  for  the  5 modules  (listed  above)  being  implemented.    The 

reports are listed below: 

Accounts Receivable Reports 

UB015 ‐ UB closed account list 

UB015 ‐ UB delinquent bills 

UB038 ‐ Cash Receipts Edit 

UB039 – Cash Receipts Update 

UB051‐ Write off audit list 

UB063 – Month end G/L detail list 

UB064 –Month end GL summary list 

UB067‐ Write off audit update 

UB070 – Month end trust deposits billed/refunded 

UB072 ‐ UB number of units and sewer rate code listing 

UB072 – Number of Units and sewer rate code list 

UB084 ‐ UB Water consumption report by type summary 

UB088 – Month end trust deposit amounts 

UB123 – Account A/R Balance all books (Auditors request) 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 46 of 142 

UB143 – Account usage analysis  

UB168 – Meter book bill generation log 

UB170 ‐ Books to be selected & Misc bills not yet printed 

UB191 – Billing Schedule 

UB202R01_Accounts  by  type  (includes  number  of  active  inactive  and  occupant 

accounts) 

UB202 – Monthly meter listing by type 

UB254 – Revenue Summary by G/L 

UB257 – Customer count statistics 

UB371R01_Pumping surcharge report detail 

UB371 – Pumping surcharge report summary 

 

Newport North tax assessment Reports 

OC001‐ Sewer charges collected through property taxes 

OC003 – Newport Account list – address sequence 

OC005 – Orange County special assessment report 

OC007 ‐ Orange County special assessment reportUB015 ‐ UB closed account list 

 

The Water Resources Reports listed below have been provided by IRWD to provide Infosys additional 

detail for the reports in scope including: required data elements, format, query/sort requirements, etc. 

 

Regulation: Water Resources Reports 

53_AgFY0809.xls 

AccountCOUNTER.dbq 

ACFT_0607_rev.xls 

ACFT_0708.xls 

ACRE0001.xls 

Ag_All.xls 

All CII Water.xls 

Area9Rec_2010QryResults_2.xls 

BMP5_Acct#.dbq 

BMP5_Acct#.xls 

BMP5‐AllocVUsage.xls 

BMP9_CII_Use.dbq 

BMP9_CII_Use.xls 

BMP9_CII_Use(90‐96).dbq 

BMP9_CII_Use(90‐96).xls 

Copy of IRWD_Historical_water_usage by system and Type_1.xls 

Count_FY CSR06‐07.xls 

GLR084_20090722.PDF 

LandscapeAcreFeetperAcre.dbq 

LSAllocVsUsage.DBQ 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 47 of 142 

NAICS_irwd_commercial_industrial.xlsx 

RatesRevenue0809.xls 

Reclaim Water.dbq 

Reclaimed Use.GWI 

RecycledWaterAccountsWbackflow.dbq 

RW_Usage0506.xls 

SAC_AgFY9900.xls 

Total_Rec_Water_Per_Month.dbq 

UB084R‐1  0809.PDF 

UB084R‐1 0809.xlsx 

WATER020.xls 

WaterVarianceReport.pdf 

WTRFL89thru04.pdf 

WTRFLCONSOL10.xls 

 

5.3.5.1 Reports Required by Regulation:  Water Resources 

1. Urban Water Management Plan and SBx7‐7 Reporting 

Data output requirements from BI (Business Intelligence) include: 

Water supplies (own supplies and imports) into the system by water type/source on a monthly and fiscal year basis 

Water exports by water type on a monthly and fiscal year basis 

Annual deliveries by customer type and water type – fiscal year basis 

Ability to identify urban from ag customers and any associated usage 

# of accounts by customer type by fiscal year 

All of above data on historical basis back to at least 1990 

Ability to maintain/identify data by areas IRWD consolidated with (LAWD, SAH, Santiago, OPA)  

2. California Urban Water Conservation Council BMP Reporting Requirements 

Capability to provide the following information from BI.  All data is by fiscal year: 

Number of metered accounts 

Number of multi‐family units served (may have multiple units on one account) 

Number of metered accounts read 

Number of metered accounts billed by volume of use 

Number of unbilled accounts by customer type and volume of use 

Number of estimated reads by type of customer versus actual reads 

Number of commercial, industrial and institutional accounts with mixed use meters (indoor and outdoor use on the same meter).  Note – we don’t have this capability with the current system, and have to estimate, but hope to address it in CC&B. 

Number of mixed use accounts retrofitted with dedicated irrigation meters during the reporting period (fiscal year) 

Annual revenue from volumetric charges by customer class 

Annual revenue from fixed charges (meter service fees) by customer class 

Annual revenue for sewer service by customer class  

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 48 of 142 

Annual revenue for sewer service for commodity charges 

Number of on‐site customer assistance for leak detection (i.e. survey, water efficiency suggestions and/or inspections 

Number of showerheads and faucet aerators provided 

Number of dedicated irrigation accounts with water budgets (allocation‐based billing) 

Acreage with assigned water budgets 

Average ET for dedicated irrigation budgets 

Number and type of devices rebated/financial incentives provided (from the conservation rebate database) 

3. Recycled Water  ‐ Regional Board Annual Reporting 

Ability to query through BI to produce annual reporting with the following data for accounts 

served with recycled water on a fiscal year basis: 

Report by Pressure Zone 

Account number 

Customer name on account 

Customer Type/ Water Type Served 

Service Address 

Service Village 

Pressure Zone (ability to specify). Would like capability to link this to GIS. 

Monthly usage  

Report of On‐Site Contact 

Account number 

Name on account 

Customer contact name 

Service address 

Phone number 

Emergency contact name 

Emergency contact phone number 

Fax number 

Property Management company name 

Property Management contact name 

Property Management contact phone number 

Site annual usage (fiscal year basis)  

5.3.5.2 Reports for processing Newport North tax assessment data: 

Sewer charges collected through property taxes 

Newport Account list – address sequence 

Orange County special assessment report 

5.3.5.3 Accounts Receivable Reports 

Cash Receipts Edit 

Cash Receipts Update 

Billing Schedule 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 49 of 142 

Books to be selected & Misc bills not yet printed 

Meter book bill generation log 

UB Water consumption report by type summary 

UB number of units and sewer rate code listing 

UB delinquent bills 

UB closed account list 

Write off audit list 

Write off audit update 

Month end GL summary list 

Account A/R Balance all books (Auditors request) 

Pumping surcharge report summary 

Account usage analysis  

Revenue Summary by G/L 

Month end G/L detail list 

Monthly meter listing by type 

Customer count statistics 

Month end trust deposits billed/refunded 

Month end trust deposit amounts 

Number of Units and sewer rate code list 

5.3.5.4 Conservation Program Reports 

ET weekly allocation information.  

Average daily use and at least 5‐ year historical use. This is used for individual customer trend analyses, as well as pulling data for broader research studies.  

Customers sorted by over‐allocation use, by account type and month (user defined).  

Access/view CII base index, with ability to have different monthly values  

Quarterly and historical views of over‐allocation use by account  

Irrigation accounts also include info for property manager and landscape contractor  

Customer history with graph (3‐year report, excel) 

Property Manager Report.  Includes contact information and landscape contractor information. 

Landscape measurements report. Historical usage reports. 

 

Additional  new  Reports  required  other  than  these  62  reports  will  be  considered  as  a  new 

requirement and will follow the formal change order process mutually agreed between Infosys 

and IRWD. 

Requirements classified as reports in Client Solution Requirements (Appendices 1‐4 of this SOW)  

are included in scope 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 50 of 142 

6. Implementation Approach 

6.1 General Description 

The Project will use  Infosys’s general  implementation methodology. This Statement of Work explains 

key items that are considered critical to a successful implementation. 

It is understood and agreed by both parties that all services shall be performed in accordance with the 

terms of the Professional Services Agreement and this SOW. Deliverables shall be subject to inspection 

and approval by IRWD according to the Acceptance Criteria and Procedures described herein. 

6.2 High Level Schedule 

This chart represents the major activities and the planned timeline for those activities. As shown from 

the plan below, the program is being delivered in 2 Phases over approximately 26 months. 

Phase 1: CC&B and Reporting using OBIEE along with the current IRWD  Customer web portal integrated 

with CC&B 

Phase 2: OUCSS implementation along with integration with CC&B 

Month 1 - 1 M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 M27 M28

Build

Warranty Support

Contract Sign Off

Phase 1 Go Live

ST+ SIT

UAT

Design

TrainingTraining  Doc Prep

CRP1 CRP2

Delivery of Functional

Design

SIT Test Case Prep

ST Env available SIT Env Dev + Demo Env Available

Req Analysis

Scope 

MigratedDatafor SIT Testing

UAT Env available

Parallel 

UAT

OUCSS ST+ 

OUCSS Build

Requirements + Design

Phase 2 Go Live

Warranty 

ST Test Case Prep

 

 

6.3 Project Phase Definitions 

1. Project Management and Project Governance 

Project Management activities are ongoing throughout the Project.  These activities are related 

to all Project delivery phases described below. The process of updating  the Project Schedule, 

creating  status  reports, participating  in  steering  committee meetings  and  providing  generally 

accepted Project Management services throughout the Project. 

2. Initiation 

The Initiation phase is the first Project phase, includes Project start up activities, and defines the 

process  of  formulation  and  articulation  of  business  and  technology  strategies  for  each work 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 51 of 142 

stream. This phase also defines the detailed schedule for the business process workshops and 

conducts the bootcamp trainings for the IRWD key stakeholders participating in the workshops. 

3. Business Process Analysis  

This phase defines  the detailed  requirements  for  the  solution  to be  implemented. Functional 

workshops  are  conducted  with  the  business  users  for  each  business  process  and  a  To‐Be 

business  process  document  is  created  using  the  Industry  best  practices  and  the  Utility 

Reference Model applicable for the business process. 

4. Analysis – Functional Specification development 

The  phase  of  the  Project  in  which  Functional  Specifications  are  created  for  each  business 

process and test plans and customize test scenarios are developed  for  functional,  integration, 

and user acceptance testing. 

5. Design – Technical Specifications Documentation 

The phase of  the project  in which  the  technical  specifications are created  for  the Extensions, 

Interfaces  and  Reports.  This  phase  also  creates  the  configuration  documents  for  the  final 

configurations to be done on the end product. 

6. Configuration and Development 

The phase of  the project  in which  the configuration and development  (extensions,  interfaces, 

reports) activities are completed. 

7. Data Conversion 

All aspects of conversion design, development and execution. 

8. Test Planning  

The phase of the project where the validation and testing activities to be conducted throughout 

the project are planned and strategies defined and agreed with IRWD for the execution of the 

test plans. This phase delivers  the  test plan,  test  strategy documents and  the  functional  test 

scripts. 

9. Test Execution 

This  phase  includes  the  execution  of  functional,  integration  ,user  acceptance  testing, 

Performance testing and Parallel Testing. 

10. Deployment (also known as Cut Over and Go Live) 

Deployment migrates  the organization  to  the  defined business  solution.  It  includes  activities 

used  to  transition  business  process,  and  technology  solution  elements  to meet  the  defined 

enterprise value. 

11. Post Implementation Support(also known as Warranty Support) 

Maintains and operates the Oracle Solution as developed in earlier phases. The key objective is 

to provide effective operations of both business and  technical solutions within clearly defined 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 52 of 142 

parameters. The Operate phase addresses Project activities that are performed after the Oracle 

Solution has been implemented, specifically post implementation support. 

6.4 Project Management & Project Governance 

These are recurring activities and deliverables that occur weekly and monthly throughout the phases of 

the Project.  The Infosys and IRWD Project Managers shall be responsible for the planning and execution 

of  the  project.    The  Project Managers will  jointly  be  responsible  for  project management  activities 

throughout the project, and the delivery of change management as well as project communications. The 

Project Managers overall management objective will be  to quickly establish an effective project office 

leveraging established Infosys methods, templates and tools. 

The  Project  Team  includes  staff  from  IRWD’s  Project  Sponsors,  Organization’s  Project  Owners, 

Organization’s Project Manager, and  Infosys’s Project Manager.    See  section 8.0  for more on Project 

Management. 

6.4.1 Activity – Project Activity Management   

SR#  Parameter  Activities 

1  Overview  Infosys  is  responsible  for  the  overall  project  schedule  and  the 

management of  the  Infosys  team members and sub‐contractors. The 

Infosys Project Manager directs  activities  and deliverables  for which 

Infosys is responsible under this SOW. 

The  IRWD  Project  Manager  is  responsible  for  the  management  of 

IRWD’s project activities. The IRWD Project Manager is responsible for 

working with the Infosys Project Manager to coordinate activities and 

deliverables that are the responsibility of IRWD.  In addition, the IRWD 

Project Manager is responsible for ensuring the quality and timeliness 

of activities and deliverables of IRWD staff and sub‐contractors.   

2  Entry Criteria  NA 

3  Deliverables  Team and Project managed to the following items.  These items must 

be updated frequently. 

Project Plan/Schedule  

Deliverables Plan 

Resource Plan 

Quality Plan 

Risk Plan 

Issue Resolution Plan 

Change Request Management Process  

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 53 of 142 

Project Documentation Management Plan 

Communication Plan  

4  Exit Criteria  NA 

     

6.4.2 Activity – Status Reporting  

SR#  Parameter  Activities 

1  Overview  Infosys,  with  assistance  from  IRWD,  is  responsible  for  the 

development of  the  status  reporting process  for  the Project.    There 

are multiple  reports  required as defined  in  the Section 8.6.1 Project 

Management Reports   of this document.   There are weekly activities, 

reports  and monthly  activities  and  reports  required  for  this  activity 

and deliverable. 

2  Entry Criteria  NA 

3  Deliverables  Project  Management  Reporting  (Starting  from  project  start  and 

Continuing Through the Last Month of Post Implementation Support) 

Weekly Status Reports 

Monthly Status Reports 

Weekly Project Team Meetings 

Steering Committee Meetings 

4  Exit Criteria  NA 

 

6.4.3 Activity – Project Tracking  

SR#  Parameter  Activities 

1  Overview  Infosys  and  IRWD will  document  all  tracking  components,  based  on 

the Project  schedule,  in  the Project  tracking  tool  to  facilitate Project 

tracking.    Infosys will  use  its  internal  project management/tracking 

tools to ensure the project  is on schedule. Project status reports can 

be provided to  IRWD regularly as agreed  in the SOW.    Infosys will be 

able  to provide  the necessary  information/data  required by  IRWD  to 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 54 of 142 

manage  IRWD  contribution.  Infosys  and  IRWD  resources will  gather 

data, update lists, configure tool settings and deliverable metrics, load 

resources, and other activities to set‐up the project tracking tools. 

2  Entry Criteria  NA 

3  Deliverables  Weekly Project Status Reports 

4  Completion 

Criteria 

NA 

  

6.4.4 Activity – Financial and Administration Management  

SR#  Parameter  Activities 

1  Overview  The  IRWD  Project  Manager  and  Infosys  Project  Manager  are 

responsible  for managing  the  financial  aspects  of  the  project.    The 

items or activities  listed below, as appropriate  to  their organizations 

and team members.   

• Invoices & Payment Authorizations 

• Time reporting  

• Vacation planning  

• Absence planning 

• Payment Schedule 

• Scope/change control 

2  Entry Criteria  NA 

3  Deliverables  NA 

4  Completion 

Criteria 

NA 

       

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 55 of 142 

6.5 Pre‐Initiation Phase 

The Pre‐Initiation phase is the period when the some of the pre‐requisite activities required to start the 

project are completed for the project to kick off. As part of this phase, the IRWD and Infosys contract is 

completed,  the  Infosys  and  Oracle  contract  is  completed  and  the  project  teams  identified  for  the 

initiation phase are mobilized.   

6.5.1 Activity – Contract Completion and Mobilization 

 

SR#  Parameter  Activities 

1  Overview  Infosys  and  IRWD  have  completed  and  signed  contracts  services  as 

required  to  support  the  work  defined  in  this  SOW.  Infosys  will 

complete the contract completion activitities with Oracle for them to 

onboard  the  resources. As part of  this activity  Infosys will also have 

mobilized  initial project  team and would begun project preparations 

onsite. 

2  Entry Criteria   

3  Deliverables Executed Infosys contract, executed Oracle contract, mobilized team on‐site, Pre‐Initiation Engagement Checklist, workshop preparations complete 

4  Completion 

Criteria 

Infosys and Oracle onsite Resources mobilized and have begun project 

preparations onsite. 

  

6.6 Initiation Phase 

The Initiation phase is the initial period when the project organization is setup and information gathered 

to allow for the finalization of the Project Plan that clearly defines the timeline of the project.   During 

the initial project plan preparation, IRWD and Infosys teams are formed and the resources scheduled to 

ensure that there are no resource conflicts. 

The Project Governance model will be defined during the project initiation phase as described below in 

Section 6.6.1.  Project‐guiding documents are created during the Initiation Phase.  These will include: 

Develop the Project Charter; 

Establish a Project Team; 

Establish the Project Team and reporting relationships; 

Define the Quality and Risk Management Plans; 

Establish the Business Process Change Process; 

Establish and Adopt the Change Control Process; 

Establish Readiness Criteria for Cutover; 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 56 of 142 

Define the Communication Plan; 

Finalize the Project Plan; 

Develop Initial System Infrastructure Plan. 

System Overview  training  (Bootcamp) will be  conducted  for  IRWD Team  in order  to  familiarize  them with  the System’s  functionality as a basis  for  the Discovery  sessions which will  take place  in  the next phase. 

 

6.6.1 Activity – Construct Initial Project Documents 

 

SR#  Parameter  Activities 

1  Overview  Infosys  will  develop  the  Project  Charter  with  IRWD.    The  Project 

Charter  will  define  mission,  scope,  major  deliverables,  high  level 

Project  schedule, metrics  (calculation and definitions),  issue and  risk 

management  procedure,  high‐level  landscape  (environments),  and 

organizational  chart,  roles  and  responsibilities  and  Project 

management.  The  Project  team  will  conduct  Kick  Off Meetings  for 

both  onshore  and  offshore  project  teams.  Following  agenda will  be 

covered: 

The Organization of the Joint Project Team  

The Reporting Structure 

Project Timeline, Plan overview 

Resources, roles and responsibilities for Infosys and IRWD 

Key Project Milestones 

Critical Success Factors 

Project Charter 

2  Entry Criteria  Contract has been signed. 

3  Deliverables  Project Management Plan (Covering the above agenda items) 

Finalized Project Plan (baseline plan) 

Project Charter 

Established Project Team; 

Project Team reporting relationships (i.e. project Organization Chart); 

Quality and Risk Management Plans 

Business Process Change Process 

Change Request Control Process 

Readiness Criteria for Cutover 

Communication Plan 

Initial System Infrastructure Plan (Demo, Development environment ) 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 57 of 142 

IPM+ Plan (Infosys Offshore Project Management Tool for Project tracking) 

Configuration Management (CM) Plan 

Knowledge Management (KM) Plan 

Defect Prevention Plan (Infosys Internal Deliverable) 

Analysis Workshop Plan 

4  Completion 

Criteria 

Kick  Off  Meeting  conducted  including  both  onsite  and  offshore 

(including participation by IRWD and on‐site project team leadership). 

All deliverables reviewed and signed off by IRWD. 

 

6.6.2 Activity – Develop Detailed Project Work Schedule 

Infosys, with IRWD’s assistance, will develop a detailed Project Schedule in Microsoft Project.  Infosys is 

responsible for this deliverable, with IRWD’s assistance. This is the Project Schedule that is revised and 

approved by IRWD, and represents the starting point for the Project. 

SR#  Parameter  Activities 

1  Overview  This schedule will outline all tasks to complete the overall Project and 

have  resources  from  Infosys  and  IRWD  assigned  and  properly 

allocated based on the resources availability. Future deliverables, such 

as  functional  specifications,  technical  specifications,  code 

developments,  system  test  and  training  execution  will  be  further 

detailed  as  the  Project  progresses  since  information  needed  is  not 

completely  available  at  this  point.   Work  activities  planned  for  the 

next (rolling) ninety days will be detailed as accurately as possible.   

2  Entry Criteria  NA 

3  Deliverables  Detailed Project Schedule (MPP) 

4  Completion 

Criteria 

The  Project  schedule  will  be  updated  throughout  the  Project  with 

additional details and completion information. If there is an approved 

scope  change,  the  Project  Schedule will  be  updated  to  reflect  that 

change.  The  project  plan  can  be  re‐base‐lined  upon  approval  from 

IRWD. 

 

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 58 of 142 

6.6.3 Activity – Install & Setup Project Tracking Tools 

This activity is the set‐up of the Project Tracking Tools. 

SR#  Parameter  Activities 

1  Overview  Infosys  and  IRWD will  document  all  tracking  components,  based  on 

the Project  schedule,  in  the Project  tracking  tool  to  facilitate Project 

tracking.    Infosys will  use  its  internal  project management/tracking 

tools to ensure the project  is on schedule. Project status reports can 

be provided to  IRWD regularly as agreed  in the SOW.    Infosys will be 

able  to provide  the necessary  information/data  required by  IRWD  to 

manage  IRWD  contribution.  Infosys  and  IRWD  resources will  gather 

data, update lists, configure tool settings and deliverable metrics, load 

resources, and other activities to set‐up the project tracking tools. 

2  Entry Criteria  NA 

3  Deliverables  Installed Project Tracking Tools 

Following tools will be used for the project tracking: 

Issue Tracker – xls template ‐ TBD 

Risk Management Tool ‐ TBD 

Defect Tracker ‐ TBD 

MS Project 

IPM+ (Infosys Internal tool for Integrated Project Management) 

4  Completion 

Criteria 

IRWD and  Infosys Provided Project Tracking Tool  is usable by Project 

team members and training has been provided 

 

 

 

6.6.4 Activity – Plan for the Core Team Training Infrastructure 

 

SR#  Parameter  Activities 

1  Overview  The  purpose  of  this  activity  is  to  allow  IRWD  infrastructure  staff  to 

plan the  installation of Project and system deployment  infrastructure 

specific  to  the needs  for  the Core Team  training.  IRWD will plan  the 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 59 of 142 

deployment of  server hardware  and  related  infrastructure based on 

infrastructure  requirements  provided  by  Infosys,  sized  to meet  the 

needs  for  Core  team  training.    This  includes  operating  system, 

databases, application servers, and settings. 

2  Entry Criteria  NA 

3  Deliverables  System Infrastructure Plan for Core Team training 

4  Completion 

Criteria 

Approval  of  plan  by  Project  Managers  and  IRWD  IT  Infrastructure 

Manager. 

 

6.6.5 Activity – Plan for the Project Infrastructure 

The purpose of this activity  is to allow  IRWD  infrastructure staff to plan the  installation of Project and 

system deployment infrastructure in accordance with the preliminary Project Plan. 

SR#  Parameter  Activities 

1  Overview  IRWD  will  plan  the  deployment  of  server  hardware  and  related 

infrastructure based on revised hardware configuration requirements 

provided  by  Infosys,  sized  to  meet  Performance  Criteria  stated  in 

Section  3.0.The  Project  Plan  will  specify  timing  of  various  servers 

(project  multi‐instance  vs.  production  use)  and  provision  of  data 

center resources (space, power, UPS, cooling, etc.). 

Except for hardware configuration changes identified by Infosys at the 

completion of  the Testing Execution and Training phases,  IRWD and 

Infosys  will  agree  to  restrict  changes  to  the  infrastructure  used  to 

support the Project and planned for production deployment. The basis 

for  the  infrastructure  will  be  the  description  given  by  Infosys  and 

detailed in Section 4.0 of this Statement of Work.  Any changes to this 

configuration will  use  the  Change Order  process when  changes  are 

unavoidable (or as recommended by Infosys to meet the Performance 

Criteria), and have to be agreed upon by both Infosys and IRWD. 

2  Entry Criteria  NA 

3  Deliverables  Project and Deployment Infrastructure Plan 

4  Completion 

Criteria 

Approval  of  plan  by  Project  Managers  and  Client  IT  Infrastructure 

Manager. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 60 of 142 

 

6.6.6 Activity – Establish Initial Project Infrastructure 

The purpose of this activity is to install the technology infrastructure required to support the Project. 

SR#  Activity  Activities 

1  Overview  IRWD will acquire, install and configure IRWD, networking, server and 

peripheral  technology  required  to  support  the  project  Scope, 

Requirements  Analysis,  Design  and  Build  Phases.    Additional 

technology will be acquired, installed and configured as defined within 

the Project Infrastructure Plan. 

This  includes, but  is not  limited  to,  the Project multi‐instance  server 

hardware, database, reporting and operating system software. 

2  Entry Criteria  Completion of the Project Infrastructure Plan 

3  Deliverables  Project Infrastructure, acquired, installed and configured 

4  Completion 

Criteria 

IRWD  shall notify  Infosys when  the Project  Infrastructure  is  in place 

and verified. 

 

6.6.7 Activity – Install Solution 

The purpose of this activity is to install the technology infrastructure required to support the Project. 

SR#  Activity  Activities 

1  Overview  Infosys  shall  install  all  products  (out  of  the  box  installation)  of  the 

Solution (as described in Section 1.7 of this Statement of Work) and all 

tools  required  for  all project  activities:  i.e.  training,  analysis, design, 

build, etc. at IRWD site. Infosys will conduct the appropriate testing to 

demonstrate  that  the  software  and  associated  databases  were 

properly  installed,  configured,  set  up,  operational  and  ready  for 

Project use.  IRWD technical staff will shadow the  installation process 

for  the    development    and  demo  environment.    Further  training 

requirements for IRWD resources will be reviewed and recommended 

with  IRWD.    For  Phase  1,  Infosys  shall  install  the  instances  for 

development,  training,  Testing  phases  (i.e.  Development/Demo  and 

DR/Test  environments).    However  the  Pre‐prod/Staging  and 

Production  instances shall be built by the IRWD IT team with support 

from  Infosys.  For  Phase  2,  Infosys  shall  install  the  instances  for 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 61 of 142 

Development/Demo  and  DR/Test.  IRWD  will  install  Pre‐

production/Staging  and Production  environments with  support  from 

Infosys. 

Infosys  will  provide  an  installation  checklist,  which  is  a  list  of  all 

software installation and activities that demonstrate and confirm that 

the software components are installed correctly. 

Infosys  will  document  the  deployment  process  so  that  IRWD  can 

prepare  the  instances  for  Pre‐prod/Staging  and  Production 

environments. 

2  Entry Criteria  Completion of installation of server hardware and system software to 

operate the initial installation of the Solution. 

3  Deliverables  Installation Checklist 

Installed Solution Environments (Development/Demo and DR/Test environments) 

o CC&B, OBIEE o AccuZip o DBs 

Installed Project Tools 

Other Project Tracking Tool listed above.   

Completed Testing of installed environments. 

4  Completion 

Criteria 

Infosys has demonstrated, to Client’s satisfaction that the Solution can 

perform  basic  functions  using  test  or  sample  data,  excluding  any 

function requiring an interface or additional configuration beyond that 

provided by the standard install. 

 

6.6.8 Activity – Conduct Bootcamp Training Sessions 

The purpose of this activity is to install the technology infrastructure required to support the Project. 

SR#  Activity  Activities 

1  Overview  This  activity  is  the  system  overview  training  (Bootcamp)  to  be 

conducted for IRWD Team in order to familiarize them with the CC&B 

System’s functionality as a basis for the Functional Workshop sessions 

which  will  take  place  in  the  next  phase.  Infosys  will  develop  and 

conduct bootcamp training for IRWD’s core project team. 

2  Entry Criteria  Installation of Demo environment  

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 62 of 142 

Bootcamp training plan and materials available 

3  Deliverables  Bootcamp training 

Training material for project team. 

4  Completion 

Criteria 

IRWD project team has received bootcamp training. 

 

6.7 Business Process Analysis Phase 

The  purpose  of  the Analysis  Phase  is  to  clarify  detailed  requirements  for  the  various  aspects  of  the 

solution  implementation.    Workshops  and  meetings  are  conducted  to  define  the  functional 

specifications  as  they  relate  to  the  solution    The  following  activities will  be  undertaken  during  the 

analysis phase of the project: 

6.7.1 Activity – Conduct Business Process Analysis Workshops 

The  purpose  of  this  activity  is  the matching  of  IRWD’s  business  requirements  in  the  Client  Solution 

Requirements  to  capabilities of  Solution by  conducting  facilitated workshops.    The duration of  these 

sessions will be decided based on the detailed planning exercise to be done in the initiation phase of the 

project. 

SR#  Activity  Activities 

1  Overview  In these workshops, IRWD and Infosys will: 

Confirm all the assumptions made by both IRWD and Infosys 

Demonstrate  alternative ways  of meeting  the  requirements, particularly  taking  advantage  of  the  system's  flexibility  via application configuration 

Identify  details  needed  to  finalize  the  functional  design  of interfaces, modification,  letters,  reports  and  any  other  code changes required 

Confirm how the Solution will address each requirement from the  IRWD  Functional  Matrix  and  any  new  requirement identified 

Document all decisions and validations 

Formalize the concurrence and approval by IRWD 

2  Entry Criteria  Analysis Workshop Plan 

Client Solution Requirements available  

Change Control Plan available 

Demo Environment Available for use 

Boot Camp training sessions completed 

3  Deliverables  To‐Be Process Document Per Process/Module   

Functional Requirements Mapping Document 

Modification Requirements Document 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 63 of 142 

Interface Requirements Document 

4  Completion 

Criteria 

Signed Off Functional Requirements Mapping Document by IRWD 

Signed off Modification requirements by IRWD 

Signed off Interface requirements by IRWD 

Signed off To‐Be Process Documents By IRWD 

Infosys will  lead Analysis Workshop  sessions  involving  appropriate  IRWD  business  process  experts  in 

order  to  create documentation  that will be used  to provide  input  to  the  configuration design of  the 

System.   

IRWD will provide  functionally knowledgeable Leads, with sufficient expertise  to complete  their  tasks. 

These  Functional  Leads will be available as needed  throughout workshop and  configuration activities 

and will be given the authority to make decisions related to their area of expertise.  IRWD will provide 

business  process  documentation  (if  available),  samples  of  screens,  reports,  letters,  bills,  etc.  to  help 

support the workshops as appropriate.  

During the workshops, Infosys will offer suggested process alternatives, intended to maximize the use of 

the functionality of the standard Solution while addressing the objectives of IRWD, but avoiding custom 

development wherever  reasonable.    IRWD will  review  the  suggestions  and  decide  at  its  reasonable 

discretion whether the changes are acceptable. 

Infosys will develop  complete documentation around all decisions.   Workshops will be  conducted  for 

each of the following process areas as an example: 

Account,  Customer  &  Location Management  (Establish  Person/Account,  Start/Stop  premise, 

Manage deposit, Manage Budget, Manage Loan, True Up Budget, Review Deposits etc ) 

Usage Management, 

Billing Management 

Financial Management 

Credit & Collections Management etc 

Infosys will conduct the workshops on the following guidelines: 

Defining solutions for the desired state of the business rather than directly mapping to current 

needs and current practices 

Address  critical  business  processes  identified  before  seeking  resolution  on  minor  business 

processes 

Optimize efficiency by reducing process cycle time 

Use standard (baseline) system features, functions, and reports whenever possible 

Identify  and  propose  work‐arounds  employing  baseline  functionality  before  designing  and 

building  a  custom  solution  requiring  an  extension.    IRWD  approval  of  all  work‐arounds  is 

required. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 64 of 142 

When multiple options are available, IRWD will choose the option that supports company goals 

or broad business areas rather than the option, which satisfies the needs of a single department 

or user 

6.7.2 Activity – Develop Individual To‐Be Business Processes 

This  activity will  produce  the  To‐Be  Business  Process    document  based  on  the  Individual  Functional 

Workshop  conducted during the Analysis phase. 

SR#  Activity  Activities 

1  Overview  Following will be the output in the to‐be business process document: 

1) To‐Be Business Process Flow Diagram 2) Detail of  the workings of 

the  business  process,  including manual  and  automated  activities  3) 

Business process name, activities, responsible team, responsible role, 

activity  dependencies,  constraints,  software  module  required,  key 

decision points, high  level software configurations required to set‐up 

the activity/process, highlight major differences with the existing As‐Is 

process,  impacted reports, modifications,  interfaces, and relationship 

to the Statement of Work, and Client Functional Requirements list. 

IRWD will support Infosys mapping effort to the software modules and 

IRWD  Functional  Requirements  List  and  Business  Process  Analysis 

document. 

2  Entry Criteria  Boot Camp Trainings Completed 

Completion of applicable Business Process Analysis workshops 

3  Deliverables  To‐Be Business Process Flow Diagrams 

To Be Business Process Analysis Documents, Final Listing Of RICE elements for the individual To‐Be Process 

4  Completion 

Criteria 

Detailed To‐Be Business Process documents  to be  signed off by IRWD  

 

6.7.3 Activity – Develop Final Business Process Document Catalog 

Following  the  completion  of  all  the  Business  Process  Analysis workshops,  Infosys will  document  all 

mutually agreed to decisions made during the sessions in the Business Process document. The purpose 

of  this  activity  is  to  define  how  IRWD’s  original  functional  requirements  in  IRWD  Client  Solution 

Requirements,  in Appendices 1‐4, are being met  in the new Solution and how IRWD’s current business 

processes will be transitioned with the new Solution. 

SR#  Activity  Activities 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 65 of 142 

1  Overview  Creation of the Business Process Analysis document containing results 

of all workshops. The Business Process Analysis documents will outline 

all components that will be included in the Project going forward, and 

is a summary of  the decisions made  in  the Business Process Analysis 

workshops.  All  requirements  reviewed  in  Business  Process  Analysis 

workshops  will  be  documented  (by  area)  for  IRWD.  During  IRWD's 

review of the draft Business Process Analysis documents, responsible 

persons for each area from IRWD will have opportunity to review each 

requirement and evaluate how  Infosys  recommends addressing each 

requirement.   End  result  for each  requirement will be an "accepted" 

by IRWD or removal as "deferred".  IRWD is responsible for obtaining 

internal  approvals  of  the  Business  Process  Analysis  document  in 

accordance  with  the  Deliverable  Acceptance  Process  (see  Table, 

Section 8.8.2).    If additional  time  is needed,  the parties will address 

changes  to  the  services  performed  or  additional  time  through  the 

Change Order  process  set  forth  in  Section  8.4  of  this  Statement  of 

Work. 

2  Entry Criteria  Completion of Business Process Analysis Workshops 

3  Deliverables  TOC document listing all the To‐Be Business Process documents ( with Hyperlinks to the Individual documents) 

Creation and completion of Client Solution Requirements Matrix 

4  Completion 

Criteria 

Detailed  To‐Be  Business  Process  documents  to  be  signed  off  by IRWD 

 

6.8 Analysis Phase – FS Documentation 

The purpose of the Analysis Phase  is to further clarify detailed requirements for the various aspects of 

the  solution  implementation.    Additional  workshops  and  meetings  are  conducted  to  define  the 

functional specifications as they relate to the solution  The following activities will be undertaken during 

the analysis phase of the project: 

 

6.8.1 Activity – Develop Functional Specifications for Extensions 

 

SR#  Activity  Description 

1  Overview  During  this  activity,  Infosys  will  develop  Functional  Specifications 

Document for the Extensions as defined in the To‐Be Business Process 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 66 of 142 

Analysis  document.    These  specifications  will  be  based  upon  the 

information obtained during the Business Process Analysis workshops 

and  supplemented with  information  provided  by  IRWD  staff  during 

this activity. 

2  Entry Criteria  Completion of Business Process Analysis workshops 

Acceptance of To‐Be Business Process Analysis document 

3  Deliverables  Functional Specifications Document for each Process Area 

4  Completion 

Criteria 

Functional Specifications Document approved by Client in accordance with Acceptance Criteria established in this Statement of Work. 

 

6.8.2 Activity – Develop Functional Specifications for Interfaces 

 

SR#  Activity  Description 

1  Overview  During  this  activity,  Infosys  will  develop  Functional  Specifications 

Document  for  the  Interfaces  as  identified  in  the  Business  Process 

Analysis  document.    These  specifications  will  be  based  upon  the 

information obtained during the Business Process Analysis workshops 

and  supplemented with  information  provided  by  IRWD  staff  during 

this activity. 

2  Entry Criteria  Completion of Business Process Analysis workshops 

Acceptance of Business Process Analysis document 

3  Deliverables  Interface Specifications Document for each Interface 

4  Completion 

Criteria 

Interface  Specifications Document  approved by Client  in  accordance with Acceptance Criteria established in this Statement of Work. 

 

6.8.3 Activity – Develop Functional Specifications for Reports 

This  activity  will  focus  on  developing  the  functional  specification  for  the  reports  in  scope  for  this 

Statement of Work.  IRWD will provide a catalog of all the reports specified  in the RFP document with 

the  format  and  sample  report  from  existing  system which will be  called  as  the  Initial Master Report 

Catalog. 

SR#  Activity  Description 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 67 of 142 

1  Overview  During this phase, Infosys will develop a report functional specification 

for  each  of  the  reports,  portals  and  letters  for  which  they  are 

responsible. These  specifications will be based upon  the  information 

obtained  during  the  Business  Process  Analysis  workshops  and 

supplemented with  information  provided  by  IRWD  staff  during  this 

activity. 

Infosys and IRWD will develop Report Specifications for each Modified 

Report  Output  Object  (Printed  Forms  such  as  Bill  Print  Formats 

Business Reports, System Generated Letters and Query Portals).  Each 

developed  report  will  contain  a  Report  Specification.    The  Report 

Specification will have two primary sections 1) Functional Design and 

2)  Technical  Design.    The  Report  Specifications will,  at  a minimum, 

contain:  Report  Name,  General  Description,  Description  of  the 

Departments  that  use  the  report,  Report  Owner,  Data  Fields  and 

Definitions needed  for the Report, Mathematical Calculations  for the 

Report  when  applicable,  Sorting,  Filtering  and  any  other  items 

deemed necessary by  IRWD.   Test Case(s) will be developed for each 

Report as part of the report functional specification. 

2  Entry Criteria  Completion of Business Process Analysis workshops 

Initial Master Report Catalog (Report Analysis Spreadsheet) 

3  Deliverables  Report Specifications Document 

4  Completion 

Criteria 

Report  Specifications  approved  by  IRWD  in  accordance with Acceptance Criteria established in this Statement of Work. 

 

 

 

 

6.9 Design Phase – TS Documentation 

The purpose of the Design Phase  is to develop technical specifications for the functional requirements 

identified in the functional design.  

6.9.1 Activity – Develop Solution Configuration Document 

This activity will focus on developing the Solution Configuration Document 

SR#  Activity  Description 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 68 of 142 

1  Overview  The purpose of this activity is to design the  configuration settings for 

CC&B  according  to  the  solution  agreed  during  the  functional 

workshops.  ,   Configuration will be driven by decisions documented 

during the Business Process Analysis workshops. 

Infosys will deliver a Configuration Document  that  includes  the most 

updated  configuration  information  related  to  the  Solution.  The 

Solution  Configuration  Document  will  be  a  consolidated  xls  with 

separate  worksheets  for  all  modules  like  Account,  Customer  and 

Location  management,  Usage,  Rates,  Billing,  Credit  &  Collections, 

Conservation  &  Rebates  etc.  The  Solution  Configuration  Document 

developed at this stage will be a living document and will get updated 

till the end of configuration and build phase of the project. 

2  Entry Criteria  Completion of the Business Process Analysis workshops 

Completion of the Analysis Phase of the project 

3  Deliverables  First Version of Solution Configuration Document 

4  Completion 

Criteria 

The  Solution  Configuration Document  is  delivered  to  IRWD  and  the 

Document  is  approved  in  accordance  with  Acceptance  Criteria 

established in this Statement of Work. 

 

6.9.2 Activity – Develop Technical Specifications for Extensions, Interfaces, Reports 

This  activity  will  focus  on  developing  the  Technical  specification  for  the  Extensions,  interfaces  and 

reports in scope for this Statement of Work.  

SR#  Activity  Description 

1  Overview  Infosys  will  document  Technical  Specifications  for  each  Extension, 

Interface & Report. The  Interface Technical Specifications will define 

the  behavior  of  the  Interfaces  involved  in  the  Solution.  For  the 

Interfacing  systems,  IRWD  will  assist  Infosys  by  providing  available 

information about the external systems and the integration approach. 

IRWD will  be  responsible  for  coordination  of  Third  Party  (Interface 

Firms,  etc.)  resource  activities,  if necessary,  for  the development of 

interfaces. 

Infosys  and  IRWD  will mutually  agree  to  the  usage  of  the  IRWD’s 

internal  standards  for  using  the  Web  Services  and  the  associated 

technologies and methodologies for these tools  (naming conventions 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 69 of 142 

etc.) during the Project initiation phase. 

2  Entry Criteria  As each Functional Specification is approved and signed off, it is assigned  to an  Infosys developer, who begins work on  the corresponding  Technical  Specifications,  or  to  a  IRWD developer, in the case of interface processing for which IRWD has agreed to be responsible. 

3  Deliverables  Individual  Technical  Specifications  developed  for  for Extensions, Interfaces and Reports 

4  Completion 

Criteria 

Delivery of  the  Infosys and  IRWD Technical Specifications  for each Extension, Interfaces and Reports 

 

6.10 Configuration & Development  

The purpose of the Configuration and Development Phase is to build the configurations, development of 

extensions ,  interfaces and Reports. 

6.10.1 Activity – Develop Solution Configuration This activity will  focus on configuring  the Oracle Solution as per  the  solution configuration document 

signed off by IRWD. 

SR#  Activity  Description 

1  Overview  The purpose of this activity is to enter configuration settings into, and 

perform initial configuration test of, the Solution. Configuration will be 

driven by decisions documented during the Business Process Analysis 

workshops. 

Infosys  will  lead  and  manage  the  configuration  activities,  with 

participation and support by the IRWD functional and technical teams.   

Infosys  will  work  on  the  configurations  as  agreed  in  the  Business 

Process Analysis workshops. The Knowledge transfer to  IRWD on the 

configurations will be done during the transition process, to minimize 

the impact on the project schedule.  

2  Entry Criteria  Completion of the Solution Configuration Document 

Solution Configuration Document Signed off by IRWD 

3  Deliverables  Base Product Configuration completed on CC&B 

Updated Solution Configuration Document 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 70 of 142 

4  Completion 

Criteria 

Solution Configuration is completed on the development instance and 

Unit testing completed for the delivered configuration. 

 

6.10.2 Activity – Develop Extensions  

SR#  Activity  Description 

1  Overview  The  purpose  of  this  activity  is  to  develop  and  unit  test  all 

modifications/extensions  to  the  Solution  to  satisfy  the  functions 

specified  in  the  final  approved  Business  Process  Analysis  document 

and Functional Specifications.  

Infosys will develop the extensions to the Solution.   These extensions 

will be built  as defined  and  Signed off  in  IRWD  approved  functional 

and technical specifications. 

2  Entry Criteria  Client approval of individual Functional Specifications 

Completion of Infosys Developed Technical Specification 

3  Deliverables  Completed code for each extension 

4  Completion 

Criteria 

All  components  defined  in  the  Functional  Specifications  are delivered  to  IRWD.    Each modification/extension must  have been successfully  tested by  IRWD  to ensure compliance with the Functional Specifications. 

 

6.10.3 Activity – Develop Interface Programs 

 

SR#  Activity  Description 

1  Overview  The  purpose  of  this  activity  is  to  Code  and  Unit  Test  interface 

programs.   The  interface programs will be based upon  the  interface 

specifications:   

The deliverable will be  the completed code  for each  Interface object 

(programs  that  require  send/receive  data  interchanges  with  third 

party  applications  and  the  Solution),  including  documentation  that 

program/executable  code  for  each  development  object  has  been 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 71 of 142 

developed,  successfully  unit  tested  and  delivered  based  on  the 

functional and  technical specifications.   This deliverable will  function 

in accordance with associated specification documentation.  

Infosys  will  address  and  resolve  all  of  the  Unit  Test  incidents  that 

pertain to Solution interfaces or Solution components. 

IRWD will address and  resolve all  test  Incidents  that pertain  to  third 

party applications that are not part of the Solution. 

Infosys will  deliver  the  interface  files  to  IRWD’s  specified  interfaces 

identified  in this Statement of Work.    Infosys and  IRWD will mutually 

agree  to  the  usage  of  IRWD’s  internal  standards  for  using  Web 

Services and the associated technologies and methodologies for these 

tools (naming conventions etc.). 

2  Entry Criteria  Completion of Functional Specifications for Interfaces 

Completion of Technical Specifications for interfaces 

3  Deliverables  Completed code for each Interface object. 

4  Completion 

Criteria 

Development completion for the interfaces 

 

6.10.4 Activity – Develop Reports  

SR#  Activity  Description 

1  Overview  The  purpose of  this  activity  is  to  develop  and  unit  test  the  reports, 

letters,  query  portals,  bill  formats,  etc.    The  deliverable  is  the 

completed  code  for  each Modified  Report Object  (Printed  Business 

Reports,  letters  or  query  portals),  including  documentation  for  the 

program/executable  code  for  each  development  object,  successfully 

unit  tested  and  delivered  based  on  the  report  specifications.    This 

deliverable will  function  in  accordance with  associated  Specification 

Documentation.   

Infosys  will  develop  and  unit  test  the  reports  for  which  Infosys  is 

responsible.  Infosys will  provide  updated  Report  Specifications with 

technical  information  to  support  the maintenance  of  reports  in  the 

future for the reports for which Infosys is responsible. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 72 of 142 

2  Entry Criteria  Completion of functional Report Specifications 

Completion of Technical specification for Reports 

3  Deliverables  Completed Code for each modified Report 

4  Completion 

Criteria 

All  reports  defined  in  Report  Specifications  and  delivered  and 

accepted by IRWD 

     

6.11   Data Conversion The  scope  of work  Infosys will  perform  as  part  of  the  Data  cleansing  and  Data  conversion work  is 

detailed out in the sections below. 

6.11.1 Data Conversion Initiation 

6.11.1.1 Activity ‐ Data Conversion Plan 

 

SR#  Activity  Description 

1  Overview  Infosys will develop a data conversion plan consisting of the following details: 

Dependencies for data conversion 

Dates  for  completion of  all  critical  tasks  and milestones  like completion  of  data  conversion  strategy,  completion  of conversion mapping document,  conversion programs, partial and full conversion execution and testing plans, 

Environments required for data cleansing and data conversion  

List  tasks  that  will  require  manual  entry  (automated conversions  may  depend  on  completion  of  manual conversion).  

Establish  the number of pre‐install  conversions and dates  to ensure conversion success. 

List  supporting  documentation  needed  from  IRWD  to  proof post  conversion  data,  including  cutoff  dates  in  conjunction with data cutoff if applicable. 

Detail the data validation plan. 

Assign  responsibility  and  expected  start  and  end  date  of testing process. 

Within  the  data  conversion  plan,  Infosys will  develop  a  list  of  data 

elements to balance with each conversion. Infosys and IRWD will work 

together  to  build  a  mutually  agreed  upon  list  based  on  what  is 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 73 of 142 

reasonable  and possible  in  the  legacy data  and with  the  conversion 

process. 

2  Entry Criteria  NA 

3  Deliverables  Data Conversion Plan (MPP) 

4  Completion 

Criteria 

Approved  Conversion  Plan  in  accordance  with  Acceptance  Criteria 

established in this Statement of Work. 

 

6.11.1.2 Activity – Develop Data Conversion Strategy 

 

SR#  Activity  Description 

1  Overview  Conduct Data Migraion Workshops.  This activity will define and create 

the Data Conversion Plan  that will be used  for  the Project. The plan 

will address the following details: 

what data will be converted systematically 

what data will be converted manually 

how much and what type of historical data will be converted, 

currently planned for a minimum of five years of history 

proposed timeline for test conversions 

define the proposed storage and access method for data that 

is not converted 

how  conversion  related  issues will  be  tracked  and  resolved once they have been identified 

The Data  Conversion  Plan  defines  detailed  processes  and  tools  that 

will govern  the conversion process  for data mapping, data cleansing, 

technical design, development and testing. 

2  Entry Criteria  Identification of data sources 

3  Deliverables  Data Conversion Plan/Strategy Document 

4  Completion 

Criteria 

Approved  Conversion  Plan  in  accordance  with  Acceptance  Criteria 

established in this Statement of Work. 

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 74 of 142 

6.11.2 Data Conversion Analysis & Design 

6.11.2.1 Activity – Document Data Conversion Specifications 

 

SR#  Activity  Description 

1  Overview  As part of this activity, Infosys with assistance from IRWD will develop 

initial and detailed technical specifications for data conversion.  IRWD 

will  assist  Infosys  by  providing  sufficient  information  about  the 

content and meaning of Legacy System files and data elements.  

The  initial  data  mapping  specifications  document  defines  the  data 

mappings  between  the  legacy  and  the  target  system  as well  as  the 

data  that  are missing  from  a  legacy  perspective  and  target  system 

perspective and  the method  for  resolving  the data  gaps.   The  initial 

data‐mapping  document will  include  a  high  level  description  of  any 

custom data manipulation needed.  Each field for all applicable legacy 

system tables will be mapped to the target systems tables and fields. 

The Conversion Design Specifications/Detailed Data Mapping  (Target 

System)  to be developed by  Infosys defines  the program  logic, data 

elements  and  file  formats,  and  report  formats  for:  the  "Upload" 

Conversion  Program, Audit  Control  Reports  and  Financial  Balancing, 

and Error Reports. 

2  Entry Criteria  Completion of the Data Mapping workshop/meetings 

Data Conversion Plan Available 

Approved Data Conversion Strategy  

3  Deliverables  Initial Data Mapping Specifications 

Conversion  Design  Specifications  /  Detailed  Data  Mapping 

Document 

4  Completion 

Criteria 

Initial  Data  Mapping  Specifications  and  Conversion  Design Specifications  have  been  approved  by  Client  in  accordance with  Acceptance  Criteria  established  in  this  Statement  of Work. 

Detailed  Data  Mapping  Specifications  will  continue  to  be amended  due  to  the  development  of  configuration  and  the results  from  various  testing  phases.  Detailed  Data Mapping Specifications will not be finalized until Cut‐over. 

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 75 of 142 

6.11.3 Data Conversion Development 

6.11.3.1 Activity – Develop Automated Conversion Processing 

 

SR#  Activity  Description 

1  Overview  The  purpose  of  this  activity  is  to  code  and  unit  test  the  necessary 

extract,  transform, and  load processing and  to  conduct Conversions.  

Programs will  be  developed  and  tested.   Mock  Conversions will  be 

planned  and  conducted  and  the  results  evaluated  for  accuracy  and 

timing according to the specification. 

2  Entry Criteria  Approval of Initial Data Mapping  

3  Deliverables  Data Conversion Programs  

4  Completion 

Criteria 

The partial conversion  is completed and results approved by Client  in 

accordance with Acceptance Criteria established  in  this Statement of 

Work 

 

IRWD will provide  resources  as  required  to  verify  the  accuracy of  converted data  against  the  legacy 

system. 

6.11.3.2 Activity – Data Extraction/Cleansing from Legacy Applications  

 

SR#  Activity  Description 

1  Overview  The  scope  of  this  activity  is  to  conduct  the  automated  and manual 

data  cleansing before  the data  is provided  to CC&B  system  for data 

conversion. Infosys will perform the automated data cleansing and the 

manual data cleansing (if required) will be performed by IRWD staff.  

2  Entry Criteria  Identification of Legacy data sources involved in the data conversion 

Approved Data Conversion Plan / Strategy Document 

3  Deliverables  Data Cleansing Programs 

Completed automated and manual data cleansing 

4  Completion  The  Data  cleansing  development  is  completed  along  with  the  unit 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 76 of 142 

Criteria  testing. 

 

6.11.4 Data Conversion Trials & Test Conversions Infosys will  perform  various  Trials  and  Test  Conversions  as  part  of  this  activity  to  ensure  the  data 

cleansing and data conversion activity  is developed and tested  iteratively after each test conversion  is 

completed. Test conversions will be performed with subset of legacy data on Development environment 

and  results verified with  the validation and  reconcilitation  scripts developed during  the development 

phase.  Full conversions will be performed during SIT, UAT, parallel testing and go‐live phases. 

SR#  Activity  Description 

1  Overview  As  described  in  the  Data  Conversion  Plan,  Infosys  will  test  the 

conversion  processing  along with  assistance  from  IRWD  Conversion 

Analysts. 

Once the conversion processing is unit tested, Infosys will execute test 

conversions  of  all  data  to  be  converted.  Full  conversions  will  be 

performed  regularly  throughout  the Project, according  to a schedule 

mutually agreed between Infosys and IRWD. 

IRWD  staff assigned  to  review  converted data will  review  converted 

data, comparing the data converted into the Solution with the data in 

the source system, using the data mapping documents as a roadmap 

for data verification by IRWD. 

Following Test conversions will be performed by the Data conversion 

team multiple times during the phase of the project: 

Data  conversion  execution  for  development  environment  – 

Partial conversion 

Data  conversion  execution  for  SIT  environment  –  Full 

Conversion 

Data  conversion  execution  for  UAT  environment  –  Full 

Conversion 

Data  conversion  execution  for  parallel  testing  –  Full 

Conversion 

The SIT, UAT and Parallel testing phases will use the data provided by 

the data conversion teams for the functional testing. 

2  Entry Criteria  Development  completed  for  Automated  Conversion Processing 

Environments available for Trial/Test Conversions 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 77 of 142 

3  Deliverables  Updated Conversion Data Mapping Document 

Updated Reconciliation & Testing Specification 

Reconciliation Results 

Test Report with the Results published for each Test Run 

4  Completion 

Criteria 

Data Conversion and  testing completed  for each of  the  test/trial  run completed  on  the  environments  listed  above  .  Test Results  for UAT and Parellel testing signed off by IRWD. 

 

 

 

6.12 Test Planning  

6.12.1 Activity – Develop Test Strategy   

SR#  Activity  Description 

1  Overview  This activity is the process of defining the overall testing approach for 

this  Project,  which  will  be  documented  in  the  Testing  Strategy 

deliverable. This document will  identify, at a high  level, all phases of 

testing,  along  with  goals,  timeframes,  proposed  resources,  and 

materials  for  each  phase.    Infosys  will  create  a  Testing  Strategy 

Document to show the roadmap for planned testing phases  including 

relationship to other Project activities. The test strategy document will 

cover  the  approach  for  System  Integration  Testing,  UAT,  Parallel 

Testing and Performance Testing. 

2  Entry Criteria  Completion  of  Business  Process  Analysis  workshops  (All  the 

workshops) 

3  Deliverables Testing Strategy / Plan Document 

4  Completion 

Criteria 

Approved Testing Strategy Document  in accordance with Acceptance 

Criteria established in this Statement of Work. 

6.12.2 Activity – Develop Functional Testing Scripts   

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 78 of 142 

SR#  Activity  Description 

1  Overview  The  purpose  of  this  activity  is  to  define  the  details  to  be  used  in 

Functional Testing,  as defined  in  the  approved  Functional  Test Plan. 

Infosys will  lead  the  development  of  the  Functional  Testing  Scripts 

with the support from IRWD. 

2  Entry Criteria  Completion of the Design Phase 

The Functional Specifications are signed off by IRWD 

3  Deliverables Functional Test Scripts and Expected Results Development 

4  Completion 

Criteria 

Test  scenarios  are  developed  for  each  Functional  Requirement 

identified in the ‘Functional Requirements Mapping Document’ 

 

6.13 Test Execution 

6.13.1 Activity ‐ Execute System Testing 

 

SR#  Activity  Description 

1  Overview  Infosys will  lead  the execution of  the  System  testing.   This phase of 

testing will  test  the  product  configuration,  integration  testing  using 

test data  in  xml  format as defined below. The  Infosys Test Manager 

will  lead  the  testing  effort with  a  defect  status  report  shared with 

IRWD at the end of the Testing. 

The  testing  team will  prepare  subset  of  test  cases  in  the  following 

areas which will be used for system testing: 

Modifications/Extensions, Interfaces and Reports approved  in the Business Process Analysis document 

All Configurations  approved  in  the Business Process Analysis document 

All Scope Items defined in this Statement of Work 

For the testing of interfaces in system testing Infosys will create mock 

XML  data  in  the  format  required  by  the  interfaces  to  simulate  the 

scenarios. 

2  Entry Criteria  Test Strategy Document available and signed off by IRWD 

Development completed for all scope items defined in this 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 79 of 142 

statement of work 

3  Deliverables  ST Status Report 

4  Completion 

Criteria 

All System Testing scripts executed 

 

6.13.2 Activity – Execute Functional / System Integration Testing 

 

SR#  Activity  Description 

1  Overview  Infosys will  lead the execution of the Functional Testing Scripts.   The 

Infosys Test Manager will  lead  the  testing effort with a defect status 

report shared with IRWD at the end of the Functional Testing. 

The following items will be tested during Integration testing: 

All Modifications/Extensions, Interfaces and Reports approved in the Business Process Analysis document 

All Configurations  approved  in  the Business Process Analysis document 

All Scope Items defined in this Statement of Work 

For  the  testing of  interfaces,  IRWD  is  responsible  for providing data 

from  interfacing  third  party  applications  in  a  format  required  for 

testing 

2  Entry Criteria  Test Strategy Document available and signed off by IRWD 

Acceptance of the Functional Test Scripts and the expected results 

3  Deliverables  SIT Status Report 

4  Completion 

Criteria 

All Functional Testing scripts executed. 

All Client Solution Requirements Items have been tested. 

Source and Object Code for Extensions, interfaces, and reports have been delivered and approved by  IRWD, and  Integration Testing is complete. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 80 of 142 

 

6.13.3 Activity – Execute Performance Testing 

 

SR#  Activity  Description 

1  Overview  This  activity  tests  the  performance  of  the  Solution  including  the 

proposed  production  environment  (operating  system,  network, 

database and disk array distribution) and system parameters. 

Infosys will develop the Performance Test Plan that will be approved 

in accordance with the Deliverable Acceptance Process. The plan will 

detail the elements to be tested and the methodology for execution to 

meet the Performance Criteria defined in Section 3.0 of this Statement 

of Work. The Plan contains: 

A roadmap for performance testing, roles and responsibilities 

Test  plan  and  expected  results  for  exercising  the  Solution system  based  on  the  loads  described  in  Section  3.0  of  this Statement of Work 

Detailed  specifications  for  the  work  station  used  for Performance Testing 

Detailed  responsibilities  for support and maintenance of  the performance test environment to be performed by the IRWD DBA and System Administrator 

Hardware,  database  and  application  parameters  for  the performance test environment  

IRWD will provide a performance‐testing tool to be determined after 

Project kickoff or a mutually agreed to manual process. Hardware and 

software will  be  tuned  prior  to  the  start  of  performance  testing  by 

IRWD to the best of their ability with Infosys support.   The batch and 

the online modules used  in the performance test will be  functionally 

tested and approved by IRWD Core Team before the execution of the 

first performance test. 

Infosys will execute  the Performance Test Plan.   A document will be 

developed  that will  include  the  results  of  each  test  (batch  program 

and online panel), an analysis of those results, and recommendations 

to  improve  the  results  if  applicable.  Infosys will  be  responsible  for 

performance defects of  Infosys‐delivered components. Following  the 

completion  of  the  testing,  Infosys will  deliver  the  Performance  Test 

Results  Report which will  document  the  results  of  the  Performance 

Testing and the changes that were made to tune the application to be 

in compliance with Section 3.0 of this Statement of Work. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 81 of 142 

2  Entry Criteria  Completion of all development Work 

Completion of Integration Testing Phase 

Completion of Staging Environment preparation 

3  Deliverables  Performance Test Results Report. 

4  Completion 

Criteria 

Performance Testing Complete and  in  conformance with Section 3.0 

of this Statement of Work. 

 

6.13.4 Activity – Execute User Acceptance Testing (UAT) This activity  addresses  the planning and execution of  testing processes  combined  in an emulation of 

business days in production. 

SR#  Activity  Description 

1  Overview  IRWD will develop a  formal UAT Plan.    IRWD will be  responsible  for 

developing  end‐to‐end  test  scenarios  that  will  cross  multiple 

operational  areas  (i.e.  read  to  bill).    IRWD  and  Infosys  will  jointly 

investigate discrepancies in results, documenting all reconciling items.  

Infosys is responsible for correcting defects caused by Infosys. 

2  Entry Criteria  Completion of all Development and Integration Testing 

Completion of Conversion Testing 

Completion of Staging Environment preparation 

3  Deliverables  UAT Status Report Delivered by IRWD 

4  Completion 

Criteria 

UAT Signed Off by IRWD 

 

6.13.5 Activity – Execute Parallel Testing This activity addresses the planning and execution of parallel testing.  

 Infosys will perform one month of parallel testing wherein the output of the new CC&B system will be compared with  the output of  the existing CIS system,  in order  to verify  the new CC&B system operates correctly. The results are expected to be exact or explained to IRWD’s satisfaction.   

Parallel  testing  is proposed  to be done  for any  tests  that has a  financial bearing  (eg., Payroll, Bills and invoices for a billing period, Financial statements at period end etc.) . 

 

SR#  Activity  Description 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 82 of 142 

1  Overview  To  ensure  that  the  processing  of  new  application  is  consistent with 

respect to the processing of previous application version.  Infosys will 

develop  the  plan  and  scenarios  for  Parallel  testing  and  IRWD  will 

review  the  plan/scenarios  to  ensure maximum  coverage.  IRWD  and 

Infosys will jointly investigate discrepancies in results, if there are any.  

Infosys is responsible for correcting defects caused by Infosys. 

2  Entry Criteria  Successful completion of UAT 

3  Deliverables  Test Results report 

4  Completion 

Criteria 

Parallel testing completed and results accepted by IRWD 

 

6.14 Cutover  

6.14.1 Activity – Prepare Production Environment 

 

SR#  Activity  Description 

1  Overview  The  purpose  of  this  activity  is  to  prepare  for  the  production 

environment.  IRWD  Infrastructure  team  will  acquire,  install  and 

configure the production hardware as per the sizing and specifications 

provided  by  Infosys  and  as  per  the  timelines  agreed  in  the  Project 

Infrastructre Plan. The CC&B application installation will be performed 

by  IRWD  technical  team with  support  from  Infosys  Technical  team. 

Based  on  the  results  of  testing  performed  during  UAT  and  Parallel 

Testing the final version of the configuration, the extensions, interface 

code and  the  reports will be deployed on production by  IRWD using 

the  installation  checklist  and document prepared by  Infosys.  Infosys 

will conduct appropriate testing to demonstrate that the software and 

associated  databases  were  properly  installed,  configured,  set  up, 

operational and ready for production use. 

2  Entry Criteria  Completion of UAT by IRWD 

3  Deliverables  Updated Installation Checklist  

Updated Deployment Document 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 83 of 142 

4  Completion 

Criteria 

Production Environment Ready for use 

All sanity test scenarios executed successfully (passed) 

All  the  interfaces  with  internal  IRWD  systems  and  external systems established and tested 

 

6.14.2 Activity – Preparation for Cutover / Cutover planning  

SR#  Activity  Description 

1  Overview  The purpose of this activity is to prepare for cutover. This preparation 

includes planning  for  the cutover and  testing  the documented plans. 

The Cutover Plan defines the detail steps (automated and manual) to 

execute  the  Cut‐over  production, metrics,  timing,  record  balancing, 

financial  balancing  and  items  that  need  to  be  in  place  for  the 

conversion  cutover  to  production.    The  Cutover  Plan  has  two 

components, the Strategy document and the Cutover Checklist. 

Infosys  will  develop  a  Cutover  Strategy  document  with  input  from 

IRWD,  which  will  document  the  approach  to  cutover  testing  and 

cutover planning.  The Strategy will also define the Issue Management 

Process for Warranty support and the Plan for support of End Users.  

Infosys  will  develop  a  Cutover  Checklist  that  contains  all  activities, 

whether  business  or  technical, which will  be  performed  during  the 

mock and real cutovers. 

The Checklist will  include for each task the timing, schedule, and role 

responsible. All Roles and responsibilities and the resources assigned 

to  those  roles  will  be  defined  along  with  individual  contact 

information.   The Cutover Checklist has built  in Go / No Go decision, 

Go / No Go decision points, and the IRWD and Infosys staff members 

who are responsible for participating in each of the decisions. 

2  Entry Criteria  Integration Testing Completed 

Training (Train the trainer) Completed by Infosys 

3  Deliverables  Cutover Strategy 

Cutover Checklist 

4  Completion 

Criteria 

Cutover  Strategy Document  and  Cutover  Checklist  approved by IRWD in accordance with Acceptance Criteria established in this Statement of Work 

Issues identified in the Mock Cutovers must be corrected 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 84 of 142 

Successful execution of mock cutovers 

Holding of Support Phase Kickoff meeting 

The Cutover Strategy document and the Cutover Checklist will, at minimum, address the following: 

Project Management Readiness 

Business Solution Testing Readiness 

Business Readiness 

IT Infrastructure Readiness 

Organization/People Readiness 

Requirements and procedures for "uninstalling" the new system and rolling back to the previous production platform in the event that the Cut‐over is unsuccessful 

Potential points of failure (people, process, technical) in the rollback process 

Internal  Help  Desk  Procedures,  Tools,  Escalation  Process  and  Post  Implementation  Support Strategy and Procedures 

Staffing and areas of responsibilities to be included 

Issue Management Process 

At a minimum, there will be three practice or mock cutovers executed where all activities are performed 

or emulated by the resource that will be responsible for that activity in the real Cut‐over.  These include 

all  conversion  activities,  system  validation,  balancing,  and  any manual  data  entry  planned  for  actual 

cutover.   Timings of each activity are made and the checklist  is reviewed after each mock cutover and 

adjusted to reflect the finding from the practice run.  The first one or two Mock Conversions will actually 

be executed in earlier phases of the Project.  The final Mock Conversion will be completed as part of the 

preparation for cut‐over as specified. 

A kickoff meeting will be held for Post Go Live Support.  Infosys will present cutover planning, schedule, 

roles and responsibilities, timeline, help desk and escalation procedures and other support related items 

in order to prepare Project and other support staff for production support following cut‐over. 

6.14.3 Activity –Cutover to Production Operation The purpose of  this activity  is  to  initiate use of  the Solution  in day‐to‐day operations of  IRWD and  to 

cease use of the current Legacy System. 

SR#  Activity  Description 

1  Overview  The  tasks  included  in  the  Cutover  Checklist  will  be  implemented, 

executed and completed by both, IRWD and Infosys, as assigned in the 

Checklist, including each of the Go / No Go decision points. 

During this activity, all components of the Solution, related third party 

applications, and related application databases will be migrated to the 

Production  Environment  supported  by  the  agreed  upon  tools  and 

procedures.   Other applications with which the Solution  interfaces or 

integrates  to  will  also  be  migrated  to  the  appropriate  Production 

Environment with data extracted from the Legacy System at a point in 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 85 of 142 

time identified in the Checklist. 

The ongoing support and maintenance of the replaced Legacy System 

will  continue  to  be  the  responsibility  of  IRWD  following  conversion 

and cutover.  

2  Entry Criteria  Successful completion of End User Training 

Successful completion of Cutover Planning 

Successful completion of Cutover Testing 

Successful completion of the UAT 

3  Deliverables  Updated Cutover Checklist 

4  Completion 

Criteria 

Decision document, authorizing Cut‐over is reviewed by IRWD Project 

Manager  and  approved  and  signed  by  the  IRWD  Executive  Steering 

Committee 

 

6.15 Post Implementation Support Phase 

6.15.1 Activity – Post Implementation Support  

This activity details the tasks carried out by Infosys and IRWD during the Post Implementation phase of 

the Program. 

SR#  Activity  Description 

1  Overview  Infosys shall provide three (3) months of post‐implementation support 

for Phase 1 and 2 months for Phase 2. Immediately after the Cut‐over 

Infosys may be required to provide on‐site support for extended hours 

for Severity 1 and Severity 2 defects. Infosys resources at offshore will 

be on‐call during non‐business hours ensuring round the clock support 

during warranty period. 

The  ongoing  production  operation  for  the  Solution  will  be  the 

responsibility of IRWD following the Cut‐over date with the support of 

Infosys. Infosys will correct or offer solutions for all defects associated 

with  Infosys  delivered  configuration,  enhancements,  interfaces, 

scripts,  cases  and  portals,  reported  by  IRWD  during  the  warranty 

period of production system  i.e 3 months  for Phase 1 and 2 months 

for Phase 2.  

2  Entry Criteria  GO ahead Given by IRWD after the Cut‐Over Completion 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 86 of 142 

3  Deliverables  Post Implementation Support Status Report 

4  Completion 

Criteria 

Each month of post‐implementation support will be considered a task 

during  which  Infosys  continues  to  address  issues  and  defects  in  a 

timely manner. 

 

6.15.2 Activity – Final Acceptance  This activity details the tasks carried out by Infosys and IRWD during the Post Implementation phase of 

the project. 

SR#  Activity  Description 

1  Overview  The Project is complete when IRWD has accepted all Deliverables and 

Infosys  has  successfully  completed  all  Activities  described  in  this 

Statement of Work.    IRWD Project Director has reviewed  the Project 

Completion Criteria defined  in  this Statement of Work and has been 

accepted.  Formal written sign‐off will be provided to Infosys. 

2  Entry Criteria  The last month of post implementation support has been completed. 

3  Deliverables  Post Implementation Support Status Report 

4  Completion 

Criteria 

The Solution has been in production use for three calendar months for 

Phase 1 and 2 months for Phase 2 following Cut‐over and Infosys has 

provided  post  production  support  during  that  period  in  accordance 

with the requirements of this Statement of Work.  

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 87 of 142 

7. Organizational Change Management 

 

Organizational Change Management (OCM) and Training activities will begin during the initial phases of 

the project and continue throughout the project.  

7.1 Organizational Change Management 

Infosys and IRWD will be responsible for the Change Management activities that will provide the IRWD 

organization  and  staff  an  effective  transition  from  the  current  CIS  system  to  the  new  solution.  This 

includes  the  preparation  of  people  and  the  design  of  business  processes  to  work  within  the  new 

business environment. 

7.1.1 Activity – Develop OCM Plan  

 

SR#  Activity  Description 

1  Overview  Infosys will develop a change management strategy and plan that will 

successfully  integrate  the business  strategy  and new processes with 

the new solution.    Infosys will, with assistance from  IRWD resources, 

review and assess the business environment, determine the scope of 

change management  activities  and develop  the  change plan  for  the 

solution implementation.   

The change management plan will  include at a minimum activities to 

accomplish the following: 

Identifying  and  documenting  change  impacts  (including 

business  process,  knowledge/skill  requirements,  job  design 

impacts, new terminology, new concepts, etc. 

Planning and delivering stakeholder communications 

Preparing  the  organization  for  job  design  and  responsibility 

changes 

Supporting  and  enabling  change  leadership  and  sponsorship 

activities 

Supporting business readiness activities 

Planning and implementing post‐implementation user support 

processes 

 

2  Entry Criteria  Initial Project Plan developed 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 88 of 142 

3  Deliverables  Change Management Strategy and Plan  

Communication Plan 

Stakeholder Engagement Plan 

4  Completion 

Criteria 

IRWD  approved  Change Management  Plan,  Communication 

Plan  and  Stakeholder  Engagement  Plan  in  accordance  with 

Acceptance Criteria established in this Statement of Work 

7.1.2 Activity – OCM Analysis 

 

SR#  Activity  Description 

1  Overview Infosys  will  be  responsible  for  assessing  the  change  management 

needs of IRWD required to transition to the new solution.  Infosys will 

identify  stakeholder  groups  and  analyze business  change  impacts  to 

those stakeholder groups. This analysis will  indentify  the  full context 

and impact of the change.  

The Analysis Report  should  include  the  assessment  of  the  following 

areas and how they will be impacted: 

Workflows:  Assess  changes  to  the  way  work  is  currently 

completed at  IRWD and descriptions of  the  impacts of  these 

changes. 

Organization  Structure:  Identify  possible  changes  to  work 

group responsibilities and relationships. 

Job Design/Responsibilities:  Identify changes to job roles and 

responsibilities. 

Skill/Knowledge  Requirements:  Identifiy  the  skills  and 

knowledge  required by users  to perform  tasks with  the new 

processes and systems. 

Company Policy: Identify possible changes to company policy. 

Key Performance Indicators: Define how process performance 

is measured. 

Issues and Resolutions: Document outstanding issues that are 

related to the process and organizational changes. 

Other as needed. 

2  Entry Criteria  OCM Strategy and Plan 

3  Deliverables  Stakeholder Analysis Report 

Impact Analysis Report  

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 89 of 142 

4  Completion 

Criteria 

IRWD  approved  Stakeholder  Analysis  Report  and  Impact 

Analysis  Report  in  accordance  with  Acceptance  Criteria 

established in this Statement of Work 

7.1.3 Activity – OCM Design 

 

SR#  Activity  Description 

1  Overview Infosys  will  work  with  IRWD’s  management  and  impacted 

stakeholders  to  determine  the  most  effective  way  to  handle  job 

changes, organizational  responsibility  changes  and  impacts  to  short‐ 

and  long‐term  staffing  levels.    Infosys  will  provide  assistance  and 

guidance regarding potential changes and implications of the changes.  

Infosys will document the following: 

Job impacts and changes 

Revised job descriptions 

Potential staffing impacts  

Recommending approaches to adjust staffing levels  

Transition plans for implementing changes 

2  Entry Criteria  Stakeholder Analysis Report 

Impact Analysis Report 

3  Deliverables  Job Change Plan 

Organization Structure Plan 

Job and Organization Transition Plans 

4  Completion 

Criteria 

IRWD  approved  Job  Change  Plan,  Organization  Structure  Plan,  Job 

and  Organization  Transition  Plans  in  accordance  with  Acceptance 

Criteria established in this Statement of Work 

7.1.4 Activity – OCM Plan Execution 

 

SR#  Activity  Description 

1  Overview Infosys will present  IRWD stakeholders with detailed business  impact 

reports  and  work  with  the  IRWD  personnel  to  implement 

recommended  changes.    Infosys  will  provide  guidance  during  the 

transition.    Infosys  will  develop  readiness  checklists  and  assess 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 90 of 142 

whether IRWD is prepared for go‐live. 

2  Entry Criteria  Job Change Plan 

Organization Structure Plan 

Job and Organization Transition Plans 

3  Deliverables  Leadership during transition 

Readiness Checklist and Criteria 

Kickoff Readiness Network presentation  

Readiness Assessment 

4  Completion 

Criteria 

IRWD  approved  Readiness  Checklist  and  Criteria,  Kickoff  Readiness 

Network presentation and Readiness Assessment in accordance with 

Acceptance Criteria established in this Statement of Work 

 

 

7.2 Training 

7.2.1 Activity – Develop Training Plan  

 

SR#  Activity  Description 

1  Overview  This activity develops a training approach that outlines  learning goals 

and  objectives  for major  target  audiences.    Infosys  OCM Manager 

along with  assistance  from  IRWD will  develop  the  Training  Plan  for 

Train  the  Trainer  Program  and  the  end  user  training,  based  on  the 

Training Needs Assessment for both the programs.  

The  Training  Plan  develops  a  learning  program  for  implementation, 

which includes: 

Train the Trainer training & End User training 

Proposed proficiency metrics 

Proposed high level schedule 

Training materials 

Roles and responsibilities 

Facility requirements 

2  Entry Criteria  Approval of the Training Needs Assessment 

Trainers to be identified by IRWD 

3  Deliverables  

Approved Training Plan  (consisting of  train  the  trainer and end user 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 91 of 142 

training) 

4  Completion 

Criteria 

IRWD approved Training Plan  in accordance with Acceptance Criteria established in this Statement of Work 

7.2.2 Activity – Develop Train the Trainer training materials 

 

SR#  Activity  Description 

1  Overview  Infosys  will  provide  a  complete  set  of  Train  the  trainer  Training 

materials for the Solution. 

2  Entry Criteria  Approval of the Training Needs Assessment 

Trainers to be identified by IRWD 

3  Deliverables Training Material for Training 

4  Completion 

Criteria 

Completed Training Materials for Each Business Process 

7.2.3 Activity – Prepare for Training 

 

SR#  Activity  Description 

1  Overview  This activity addresses the tasks that are necessary before the training 

can  begin,  as  defined  in  the  approved  Training  plan.  Two weeks  of 

training will be provided by  Infosys as part of the “Train the Trainer” 

activity. The first week will focus on business practices and processes 

within the application and the second week will discuss training best 

practices in addition on how to best educate the end users specific to 

the  software  topic  training  issues,  such  as  recommended  labs,  data 

preparation, expected issues and concerns from the end users. Infosys 

will  provide  the  base  training  materials  for  the  Solution  prepared 

according to Train the Trainer plan. 

2  Entry Criteria  Approval of the Training Needs Assessment 

Trainers to be identified by IRWD 

Approval of the Training Plan  

Creation of the End User Training Materials 

3  Deliverables  Training Schedule 

Training Material 

End User Assessment questionnaire 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 92 of 142 

4  Completion 

Criteria 

Training  environments  ready  for  End  User  training,  with training data 

Training Invitations issued to End User attendees 

 

7.2.4 Activity – Deliver User Training (Train the Trainer) 

 

SR#  Activity  Description 

1  Overview  This activity addresses the execution of the User training activities as 

defined in the approved Training Plan. 

2  Entry Criteria  Approval of the Training Needs Assessment 

Trainers to be identified by IRWD 

Training Invitations issued to End User attendees  

3  Deliverables  Training Schedule 

Training Material 

End User Assessment questionnaire 

4  Completion 

Criteria 

All  scheduled End Users have either been  trained or did not attend scheduled session(s) 

7.2.5 Activity – Deliver End User Training  

 

SR#  Activity  Description 

1  Overview  This activity addresses the execution of the End User training activities 

as defined  in the approved Training Plan.  IRWD will conduct the end 

user  training.  Infosys  will  support  IRWD  in  resolving  the  training 

environment  issues  if  any.  Infosys  will  also  provide  the  training 

material used  in  the  train  the  trainer approach  to  the  IRWD  trainers 

which  can  be  extended  or  further  developed  for  end  user  training.  

One or two  Infosys trainers will be present for each  IRWD‐instructor‐

led training session 

2  Entry Criteria  Approval of the Training Needs Assessment 

Trainers to be identified by IRWD 

Training Invitations issued to End User attendees  

3  Deliverables  Training Schedule 

Training Material 

End User Assessment questionnaire 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 93 of 142 

4  Completion 

Criteria 

All  scheduled End Users have either been  trained or did not attend scheduled session(s) 

 

7.2.6 Activity – Stakeholder Analysis  

 

SR#  Activity  Description 

1  Overview  This activity focuses on the indentification of key internal and external 

stakeholders  for  the  program.    Stakeholders would  typically  include 

IRWD executive leadership, IT and business leads, users and impacted 

user  groups  within  IRWD,  and  board  interests.    Program  success 

criteria,  initial  risks  and  issues,  and  communication  plan  links  are 

identified and captured in the Stakeholder Engagement Plan. 

2  Entry Criteria  Stakeholder analysis completed 

3  Deliverables  Stakeholder Engagement Plan 

4  Completion 

Criteria 

Stakeholder  Engagement  Plan  reviewed  and  Signed  off  by IRWD 

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 94 of 142 

8. Project Management Approach 

8.1 Program Management Overview 

Infosys will provide leadership in executing the Project based on their experience and best practices for 

successfully implementing Oracle solutions in the utilities industry.  The Infosys Project Manager will be 

proactive  in  their management  style  and  in working with  IRWD  Project Manager.  The  IRWD  Project 

Manager(s) and  Infosys Project Managers will make  the Project management decisions  together, with 

the IRWD Project Manager being the final decision maker regarding these processes 

8.2 Project Organization & Reporting Structure 

 The Infosys Project Manager will be responsible for all Project activities, schedules and staffing of those 

activities.  The  IRWD  PM will  be  responsible  to  ensure  that  the  IRWD  core  team  is  available  for  the 

needed assignments.   The  IRWD PM will also manage all Project administrative duties associated with 

the IRWD core team. The IRWD and Infosys Project Managers are jointly responsible for the day‐to‐day 

planning of the Project activities.    

The purpose of this reporting structure is to centralize and streamline all Project related decision‐making 

activities.  If a conflict occurs and the  IRWD and  Infosys Project Managers cannot resolve the  issue the 

Conflict escalation Process can be initiated. 

8.3 Project Governance & Escalation 

8.3.1 Work Assignments & Tracking  

The  Infosys Project Manager will develop a detailed Microsoft Project schedule that will drive all work 

assignments  for  Client  and  Vendor  tasks  for  to  the  program/Project.    The work  assignments will  be 

printed or provided electronically to the individual team members by the Infosys Project Manager.  The 

work performed by the team will directly correlate to the current Project schedule jointly produced by 

the Project management teams.  

Weekly, the Infosys Project Manager will conduct group and/or individual meetings with team members 

to review their assigned Project tasks.  The purpose of these meetings is to gather information regarding 

the overall Project status, to identify obstacles to successful completion of tasks, and to provide needed 

assistance and coaching.   Assignments will be distributed via the Microsoft Project schedule to ensure 

the team members are using the same task list as the Project management team.  Assigned tasks, risks, 

issues and any other Project issues will be reviewed during these meetings. 

8.3.2 Weekly PM Meetings  

The  Project management  team,  along with  other  lead  Project  team members  if  needed, will meet 

weekly.  The purpose of these meetings will be to discuss the Project work items and the current status, 

using  the Microsoft Project Schedule data as a driving  tool of  the meeting.   Examples of  topics  to be 

covered in this meeting are listed below, but not limited to: 

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 95 of 142 

Prior week accomplishments 

Project metrics (deliverable status, percent complete, etc.) 

Status of major Project tasks 

Review of open Project Issues 

Review of the risk log 

Review organization readiness 

Review of the Project calendar for scheduling purposes (resource availability, On‐site Time, etc.) 

Project concerns 

Action items from this meeting 

8.3.3 Monthly Steering Committee Meetings  

 The IRWD’s members of the Steering Committee will  include the Project Sponsor, and other members 

to be defined and documented in the Project Charter. 

On  a monthly  basis  the  IRWD  steering  committee will  host  a  status  review meeting.      The  Project 

management  teams will develop a  series of Power Point  slides  that communicate  the current Project 

status and a forecast. These slides will communicate a detailed view of the current Project metrics and a 

brief  status  of  each major phase  and  component  of  the  Project  as  appropriate.    The  Infosys  Project 

management  team will have  responsibility  to develop  slides  for  the meeting as well as  integrate key 

slides from the IRWD into the overall presentation. 

Approximately three days prior to the meeting, a review of all the slides will be conducted in person or 

via online meeting technology with the Project management team.   No  later than the day prior to the 

steering committee,  the presentation slides will be  reviewed with  the  IRWD Project sponsor. Steering 

committee meetings will be conducted no less than once per month. 

8.3.4 Conflict Escalation Process  

8.3.4.1 Initial Conflict Identification and resolution process 

As conflicts arise  in  the Project,  it  is expected  that most  issues will be addressed at  the Project  team 

level.   If the  individual team members are unable to resolve the conflict the team members will report 

the issue to their respective Project team lead.  The Project team lead will then attempt to resolve the 

issue with their counterpart from the IRWD/Infosys.  If the issue is still not resolved, the team lead will 

report the issue to the Project Managers. 

An  issue / action can be raised from any area of the Program. The  issue will be  logged  in  issue tracker 

with  each  issue  /  action  with  a  priority  number,  category  and  code.  The  respective  owner  team 

investigates  the  issue  and  recommends  resolution  for  review  and  approval  by  the  IRWD  &  Infosys 

Project managers 

8.3.4.2 Escalated Conflict Resolution Process 

The  Escalated  Conflict  Resolution  Process  shall  consist  of  a  three‐step  approach  to  resolve  disputes 

related  to  this agreement.   Once a dispute has been  formally escalated  from  the Project Managers of 

the IRWD and Infosys the formal process begins, starting with Step 1 below: 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 96 of 142 

Step1 – The  initiating party’s assigned Project Manager will  inform  the other party’s Project Manager 

that a dispute exists.  The two Project Managers will work together to resolve the issue.  If after five (5) 

business days, or a mutually agreeable timeframe, the matter has not been resolved, the  issue will be 

escalated to the Step 2 process. 

Step 2 – The Project Managers will inform their Project Sponsor/Steering Committee Chairperson that a 

dispute exists.  The Project Director of Infosys will represent Infosys for this role.  IRWD will escalate the 

dispute to the Project Director.  The party that initiated the dispute will clearly document their concern 

in writing to the other party and outline what their expectations are related to the desired resolution for 

the outstanding  issue.     The party required to resolve the problem will have ten (10) business days, or 

mutually agreeable  timeframe,  to  resolve  the matter.    If  the matter has not been  resolved after  this 

phase, the issue will be escalated to Step 3. 

Step 3 – During  this  step,  the  information documented  from Step 2 and any other clarifications  from 

Step 2 will be provided via certified mail to the party that  is required to resolve the  issue. The Project 

Director empowered to resolve Project  issues will represent the IRWD. The party that has  initiated the 

Dispute  Resolution  Process will  allow  the  other  party  ten  (10)  business  days,  or mutually  agreeable 

timeframe, to resolve the matter.  If at the end of this phase  the matter  is not resolved the aggrieved 

party  may  seek  resolution  through  arbitration  pursuant  with  the  parties’  Professional  Services 

Agreement. 

8.4 Change Order Process 

8.4.1 Process Overview  

Either party may request a Change Order.   Such a request must be  in writing and  identify the business 

and other reasons for the requested change and the impacts if the change is agreed upon.  No Change 

Order shall become effective unless mutually agreed to by the parties. 

After  any  request  for  a  Change  Order  is made,  the  parties will  have  five  (5)  business  days  or  any 

additional, mutually  agreed  upon  period  of  time  to  consider  the  request  (the  “CO  Review  Period”).  

During  that period,  Infosys will provide Client with  all  information material  to  the  requested Change 

Order, regardless of which party requested it, including but not limited to any additional fees that would 

be  incurred,  the  impacts on  the  relevant Deliverables, and any alteration of  the Schedule  that would 

result if the Change Order is agreed to.  Infosys will also during the CO Review Period create an order of 

magnitude cost estimate at its expense regarding any requested Change Order.   

During the CO Review Period, Client will provide Infosys with any information reasonably requested for 

Infosys to evaluate any Change Order requested by Client. 

Infosys will agree to any Change Order requested by Client, provided the parties are able to agree upon 

the any  changed  terms, additional  fees and modification  to  the  Schedule  that would  result  from  the 

Change Order. 

If both parties agree  to  the change, all relevant  terms shall be documented  in  the Change Order. Any 

charges  not  already  specified  in  the  Statement  of Work  or  which  are  different  than  those  in  this 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 97 of 142 

Statement of Work will be noted in the Change Order.  Any additional services performed by Infosys as a 

result of a Change Order will require the payment to Infosys of additional fees as agreed.    

If agreement on a requested Change Order does not occur by the end of the CO Review Period, either 

party may  initiate  the conflict  resolution process  set  forth  in Section 8.3.4 of  this Statement of Work 

regarding the requested Change Order. 

Any  Deliverables  that  have  already  been  completed  and  accepted  by  Client  that  are  subsequently 

altered as a result of a Change Order must be appropriately revised, pursuant to the Change Order, with 

the change number and date noted.   An updated version of such a Deliverable will then be signed and 

stored with the project documentation. 

8.4.2 Tracking Tool & Process  

All change orders will be documented in the change control log with the current status reflected in each 

request. 

8.5 Project Controls 

Infosys will provide the Project baselines and controls outlined in this section to support the monitoring 

and controlling of the Project progress and identify and prioritize issues arising during the Project. 

If IRWD does not accept any of the Deliverables as described in the acceptance process in the sections 

above, IRWD will provide details that outline the items that need to be resolved. 

Infosys will provide metrics  for  controlling  the Project  including  schedule metrics defect metrics, and 

metrics  related  to  the  completion  of  Project  deliverables,  such  as  counts  of  business  processes 

documented, test cases written, and requirements tested etc.   

8.6 Project Communications 

Infosys  will  be  responsible  to  support  the  IRWD’s  communication  management  process  per  the 

Communication and Stakeholder Plans developed by Infosys.   IRWD will need Infosys to, at a minimum, 

provide key  information  that will be disseminated  to  the various stakeholders of  the Project.     At key 

stages  of  the  Project,  Infosys  will  be  required  to  support  the  review  of  key  functionality  to  the 

stakeholders of the Project.   For example, Infosys will present to the stakeholders how key functionality 

will work based on IRWD’s unique configurations.  The Infosys functional lead for that specific topic will 

be responsible for the development of Power Point slides to illustrate the new capability and to present 

the software in a demonstration manner. 

8.6.1 Project Management Reports   

8.6.1.1 Weekly Status Report 

The  Infosys Project Manager will develop a weekly status  report at  the end of each week. This status 

report will outline  the planned accomplishments  for  the week versus  the actual accomplishments  for 

the week. The report will also summarize the current status of all the deliverables, staffing issues, risks 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 98 of 142 

and open issues.  It will include metrics appropriate to the Project phase (# business cases, # test cases, 

# defects, etc 

 

8.6.1.2 Monthly Steering Committee Report 

No  less than two business days prior to the steering committee meeting, the  Infosys Project Manager 

will develop a series of PowerPoint slides that summarize the current status of the Project.   All Project 

metrics will be  included with  these PowerPoint  slides and no additional  status updates will be made 

after  this  delivery,  to  ensure  the  Project  management  team  has  enough  time  to  review  the 

presentations and prepare for the meeting. 

These slides will discuss the current status, what  items remain  to complete  for the current phase and 

count  key  deliverable  metrics  for  the  phase  and  the  overall  Project.    The  intention  of  these 

presentations  is  to  communicate  to  the  steering  committee  the  current  status  and  for  the  steering 

committee  to  understand  if  the  Project  is  on‐schedule.    In  addition  these  slides  will  discuss 

accomplishments and any potential roadblocks facing the Project. 

 

8.6.1.3 Weekly Project Schedule Updates 

The Microsoft Project schedule will be updated and provided  to  the  IRWD weekly by  the  Infosys PM.  

The schedule should be current prior to the weekly Project management meeting.   These updates will 

consist  of  updating  the  key  items  defined  as  “Microsoft  Project  Schedule  Updates”.    As  needed  a 

detailed joint review of the schedule will be conducted and updates made in real time if the team feels 

this is the most productive means to reach agreement regarding the schedule. 

8.7 Risk Management 

Infosys, assisted by  the  IRWD Project Manager, will develop a Risk Management Plan that will outline 

how  the  team will work  together  to  identify,  classify,  review, and manage  risks.   The purpose of  risk 

management is to take action to reduce threats to the Project.  The focus will be on reducing the threat, 

not just documenting it. 

A  risk  response  plan will  be  developed  and  implemented  for  each  risk.    The  identified  risks will  be 

reviewed and updated,  if needed, no  less than every other week  in the Project management meeting.  

Infosys will  create  and  execute  the  Risk Management  process  and  associated  logs, managed  by  the 

Infosys project manager. 

A risk response plan may generate a Change Order request to this Statement of Work.  If that is the case, 

the Change Order will be managed as outlined in Section 6.4 of this Statement of Work. 

Unforeseen events  that adversely affect  the Project will be documented as  issues, and will prompt a 

review  of  the  identified  risks.      These  issues  will  be  logged  and  available  for  review  by  the  next 

practicable Project management weekly meeting for review. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 99 of 142 

8.8 Quality Control 

The  Project Management  Plan will  provide  additional  detail  regarding  Project  quality.  In  general  the 

Project will leverage multiple quality control points throughout the Project. 

All Project deliverables, including, but not limited to, documents, hardware, and software, will be placed 

under Quality Control as outlined in this Statement of Work. 

8.8.1 Communication of Deliverable Delivery 

The status of Project deliverables will be maintained in the agreed‐upon Project tracking tools.  As each 

deliverable  is completed the status will be updated to note that the deliverable  is ready for the other 

party, typically the IRWD, to review. 

The developer of the deliverable will also be required to contact (email and phone) the other party to 

schedule a walkthrough to review the deliverable.  In the case of document deliverables, the developer 

will ensure that the other party has access to the deliverable and will allow up to 5 days for deliverable 

review prior  to  the walkthrough.  If multiple complex deliverables are delivered at  the same  time,  the 

Project Managers will agree on review priorities. 

There may be several iterations of reviews as a deliverable is being prepared.  For example, Infosys and 

IRWD should review an early draft of a deliverable to ensure both parties agree to the general direction 

taken by the preparer of the deliverable. 

At  the conclusion of  the  formal  final deliverable walkthrough,  the acceptance process and  timeframe 

begins. 

8.8.2 Deliverable Acceptance Process 

The acceptance procedure for all deliverables will be as follows: 

When a deliverable is complete, Infosys will conduct a detailed walkthrough of the key deliverables with 

the IRWD team members that are appropriate to the deliverable length and complexity.   The intent of 

this walkthrough is to confirm that the deliverable is correct and complete.  Walkthroughs can consist of 

document reviews, design reviews, presentation reviews, program demos, or other activities to confirm 

that  the deliverable  is  ready  for  the  IRWD acceptance. The Key deliverables which will need detailed 

walkthough with IRWD will be mutually agreed between Infosys and IRWD during the initiation phase of 

the project. 

After  the walkthrough with  the  IRWD,  the  IRWD will  have  up  to  five  (5)  business  days  or mutually 

agreeable  timeframe  to accept  the deliverable.  IRWD will give email acceptance of  the deliverable so 

that the sign off of the deliverable can be archived with the Project documentation. 

If  IRWD  is not able to approve a deliverable,  IRWD will provide  Infosys with a description of what the 

deficiencies  of  the  deliverable  are,  via  the  defect‐tracking  tool.  The  parties will meet  to  discuss  the 

deficiency of the deliverable in detail.  Infosys will then provide a plan to remedy the deficiencies within 

five business days (5) as per the defect process. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 100 of 142 

If this deliverable is not remedied and or approved within the agreed‐upon time frame then this process 

will start the “Escalated Conflict Resolution Process” as defined Section 8.3.4 of this Statement of Work. 

 

8.8.3 Defect Tracking Tool & Process 

 All deliverable defects will be tracked  in the defect‐tracking tool.   This  includes document deliverables 

(To‐Be Business Process Documents, Functional Specification Documents, etc.) as well as software and 

hardware deliverables. 

8.8.3.1 Classification Categories Defects will be classified by severity, type, status, and  function affected.   See the definition section of 

this document for additional definition.  These tracking categories will be mutually agreed to during the 

start‐up process of the Project. 

Severity 

Please see the definition section of this document for the descriptions of Severity 1, 2,and 3. 

Type 

Defect  When  the  system  or  a  component  of  the  system  does  not  meet  the  stated 

requirements  or  functional  design,  or  does  not  work  in  a  way  that  is  generally 

expected, a defect of type “defect” is recorded. A defect is a mistake, an error, a bug, 

or a flaw in software, documentation or deliverables. Infosys must resolve all Severity 

1, 2, and 3 defects of type “defect”, and must map unresolved Severity 3 defects back 

to  IRWD  Client  Solution  Requirements  sheet  or  the  functional  design  document 

affected. 

8.8.3.2 Defect Tracking Responsibility 

It will be the responsibility of all team members to log defects as they are identified.  The defects will be 

reviewed  on  a weekly  basis  as  part  of  the  Project management weekly meeting.  It will  be  Infosys’s 

responsibility  to provide estimated completion dates  for  identified defects within  three business days 

from being logged into the tracking tool for all Severity 1 and Severity 2 defects. 

8.9 Project Management Tools 

8.9.1 Tracking Components 

 All major work activities will be tracked regarding their key status information.  Key status Information 

includes but is not limited to: IRWD‐responsible, Infosys‐responsible, person currently assigned, person 

to sign‐off, status, percent‐complete and other attributes deemed necessary for accurate reporting. 

At  a minimum  the  following  items will  be  tracked.  Project work  assignments  for  team members,  all 

contract deliverables (at the work breakdown structure level), Change Orders, Modifications/Extensions, 

Interfaces,  Issues,  Risks,  Documents,  Conversion  Items,  To‐Be  Business  Processes  Documents, 

Configurations,  Test  Script Designs,  Test  Script  Execution,  Training Material Designs,  Training  Course 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 101 of 142 

Executions, Knowledge Transfer Progress, Risks and other items deemed necessary by the IRWD Project 

Manager.  

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 102 of 142 

9. IRWD Assistance 

 This Section describes  the assistance  IRWD will  supply  Infosys  to meet defined  services and meet  its 

obligations  under  this  Statement  of  Work.  In  the  event  that  IRWD  cannot  provide  the  required 

assistance, there may be material impact on Infosys’s ability to deliver the components of the program.  

This impact and required remediation will be assessed mutually and may result in a Change Order. 

IRWD will provide: 

The project infrastructure, such as connectivity to the servers, and Oracle RDBMS software 

Secure remote VPN access to network(s) 

Onsite Internet access, printers, and necessary project‐related equipment 

The required software licenses for all project‐related applications as defined in this SOW. 

Other information and assistance such as access to subject matter experts 

The  office  space  at  Client  location(s)  and  furnishings  consistent  with  Client’s  employees  in accordance with  the  requirements  of  this  Statement  of Work  and  Pre‐engagement  checklist expected 2 weeks prior to project start 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 103 of 142 

10. Program Pricing 

10.1 Fixed Price for the Project This is a fixed price deliverable‐based agreement for services and software.  Travel and related expenses 

are included in the fixed price for the Project.  The pricing given below does not include pricing for any 

licenses  for  software  to  be  provided  by  IRWD  as  defined  in  this  SOW.   However,  the  pricing  below 

includes all software that the Infosys team may require to deliver the services defined in this SOW. 

SI Services  Total Fixed Price (USD) 

CC&B Implementation + OBIEE + Migration + OUCSS 

Implementation  $ 5,325,000 

 

10.2 Structure for Milestone Payments 

10.2.1 Milestone Payments 

IRWD  shall  pay  a  portion  of  the  Fixed  Price  on  a Milestone  basis  upon  IRWD’s  Acceptance  of  the Deliverables associated with that Milestone (“Milestone Payments”).  

The payment of the price shall be effected as follows: 

The payment of  the price  for Phase 1( CC&B + OBIEE)  shall be effected as mentioned  in  the  table of 

deliverables. 

The  payment  of  the  price  for  Phase  2  (  OUCSS  )  shall  be  effected  as  mentioned  in  the  table  of 

deliverables. 

Pricing  

All pricing and billing currency is in USD. 

The fees are excluding all taxes like as local, sales, service; value added tax and any other transaction related taxes payable on services received by the Customer from Infosys. These would be extra and is to be borne by customer. 

Credit period will be 30 days from date of receipt of invoice. 

Infosys prices are exclusive of any software/hardware licensing costs. 

The pricing given is for the given scope of work and agreed set of services. Any change that might have an impact on the scope, services, timeline, and any changes in the assumptions will have an impact on prices and would be handled through a contractual change management process. 

Any additional travel and related expense incurred in connection with the provision of services outside the IRWD base location, undertaken at Customers request would be charged back to IRWD at actual cost. 

Connectivity charges if any would be charged to the IRWD. 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 104 of 142 

The Milestone dates provided above are estimated dates assuming the project start date of Feb‐2013.  

In the event that change orders that involve additional costs are agreed to by the parties, each 

such change orders should include its own payment terms and the percentages above will serve 

as the guiding principles to determine the payment schedule. 

10.3 Intellectual Property Infosys will develop, leverage and enhance tools, code components, documentation and accelerators as 

part of this engagement. These tools, code components, documentation and accelerators will be Infosys 

IP  (Intellectual  Property).  Infosys  will  retain  ownership  rights  of  these  tools,  code  components, 

documentation and accelerators with the exclusion of data, technology and business references specific 

to IRWD. Infosys will be able to license these to other utilities as per Infosys standard license agreement. 

IRWD will have  full rights  to use  Infosys  intellectual property as per the    terms and conditions of   the 

IRWD PSA and this SOW.  The fees for use of Infosys intellectual property are included in the submitted 

final price quote. Intellectual Property includes:  

 

Documentation   –  Includes process flows beyond oracle URM, Enhanced Training documentation, Test 

artifacts,  Conversion  templates,  Configuration  templates  prepared  by  Infosys  (exclusive  of  data, 

technology and business references to IRWD). 

Configuration      – CC&B Configuration metadata for water utilities, incremental algorithms and business 

logic plugins developed by Infosys (exclusive of data, technology and business references to IRWD). 

Reporting             – System Balancing Reports, OUBI Dashboards, extraction logic, ETL processing logic, all 

BIP  reports  custom  developed  by  Infosys  (exclusive  of  data,  technology  and  business  references  to 

IRWD). 

Interfaces            –  Framework  developed  for Meter  read  processing,  Payment  uploads  from  external 

agencies, address validation & CASS certification  solution,  interfaces developed  for credit  score check 

(exclusive of data, technology and business references to IRWD). 

Extensions          – Extensions developed by Infosys generic for other water utilities excluding the unique 

requirements for IRWD (exclusive of data, technology and business references to IRWD). 

Conversion         – Data validation framework, Field  level data mapping spreadsheet template, ETL data 

mappings, input table layouts (exclusive of data, technology and business references to IRWD). 

 

 

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 105 of 142 

11. Project Deliverables – Milestones Mapping 

Infosys  Project Manager  shall  be  responsible  for  the  completion  of  the  project  deliverables  and will work with  IRWD  Project Manager  to 

complete those deliverables  listed  in this Statement of Work.    Infosys shall use the  Infosys methodology and apply project management best 

practices throughout the course of Project.  

11.1 Table of Deliverables The following table  identifies major deliverables for each phase.   The party responsible for  leading the effort or providing significant decisions 

are identified under the “Lead” column.  The parties required to assist in the deliverable are identified under the “Assist” column. 

Payment Milestones are contingent upon the IRWD accepting all Deliverables as indicated in table below. 

 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

DELIVERABLES FOR Project Management Activities 

2.1 to 

2.21 

Not 

Applicable PM 

Updated 

Project Plan / 

Schedule  

Project  Plan  updates  are  performed 

throughout  the  month  and  published 

monthly.  

The plan  is updated for refinements to tasks, 

percent complete and milestone completions 

inclusive of  resource updates and  timeframe 

updates.  Both parties will commit to staffing 

and  resources  to  meet  a  rolling  3‐month 

window.  Approximately 21 ‐ one per month. 

Infosys  IRWD 

3.1 to 

3.21 

Not 

Applicable PM 

Issue Logs 

and Issue 

Worksheets 

Report that  lists the  issues  for the project as 

well  as  responsible  resource  and  due  date.   

The  report  is  an  extract  from  the  Issues 

Database.    Issues  are  reviewed on  a  regular 

Infosys  IRWD 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 106 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

basis by the Project Team, led by Infosys.  The 

frequency  of  the  reviews  is  usually  weekly.  

The issue summary is reported in the Monthly 

Status  Report.    Approximately  21  ‐  one  per 

month. 

4.1 to 

4.21 

Not 

Applicable PM 

Monthly 

Status 

Reports 

Status reports will document:

Project Management Assessment 

Project Planning Activities ‐ Plan changes 

By Phase, detail of prior accomplishments and upcoming activities, risks 

Issue Summary 

Risk Register 

Key Milestone table 

Financial status 

Change Request History 

Resource Status 

Communications Status Approximately 25 ‐ one per month. 

Infosys  IRWD 

5.1 to 

5.100 

Not 

Applicable PM 

Weekly 

Status 

Reports 

Status reports will document:

Weekly project team assignments 

Weekly project team accomplishments 

Issues Review 

Project Tasks Status 

Etc. Approximately 100 ‐ one per week. 

Infosys  IRWD 

6.1 to 

6.100 

Not 

Applicable PM 

Weekly 

Project 

Team 

Team meetings will present and discuss: 

Weekly project team assignments 

Weekly project team 

Infosys  IRWD 

   

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 107 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

Meetings  accomplishments 

Issues Review 

Project Tasks Status 

Etc. Approximately 100 ‐ one per week. 

7.1 to 

7.x 

Not 

Applicable PM 

Steering 

Committee 

Meetings 

Steering Committee meetings will be 

conducted monthly (or more frequently 

as needed) to present and discuss: 

 

Monthly key accomplishments 

Projected key activities for month/period ahead 

Review and confirmation of key decisions, issues and risks 

Program performance review 

Etc.  

Infosys  IRWD 

   

DELIVERABLES FOR M0 (Contract Completion and Mobilization) 

0.1  M0  Mobilize 

Oracle 

Contract 

Completed 

Infosys  has  completed  and  signed  contract 

with  Oracle  Professional  Services  for  the 

resources and services as required to support 

this effort and defined in this SOW. 

Infosys   

0.2  M0  Mobilize 

IRWD 

Contract 

Completed 

Infosys and IRWD have completed and signed 

contracts services as required to support this 

effort and defined in this SOW. 

Infosys   

0.3  M0  Mobilize 

 Project & 

Workshop 

Preparation 

 Infosys will develop project & workshop 

preparation.  Infosys    IRWD 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 108 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

0.4  M0  Mobilize  Project Team 

Mobilized 

 Infosys has mobilized initial project team and 

has begun project preparations onsite.  Infosys    IRWD 

Milestone Completion  15‐Feb‐13 $150,000

Retainage $0

Net Payment (USD)  $150,000

DELIVERABLES FOR M1 (Initiation) 

1.1  M1  Initiation  Project Plan 

Defines the tasks, resources and schedule 

required to complete project (including post‐

implementation tasks). For the initiation 

phase of the project Infosys will deliver the 

draft project plan. The first draft of the 

project plan will have minimum next 90 

activities planned in detail. The activities after 

90 Days can be detailed out further in the 

next milestones. 

Infosys  IRWD 

1.2  M1  Initiation Project 

Charter 

Defines the mission, goals/objectives, 

activities, boundaries, metrics and 

governance of the Project. 

IRWD  Infosys 

1.3  M1  Initiation Project Org 

Chart 

Defines participants and reporting 

relationships.  This should be part of the 

Charter. 

Infosys  IRWD 

1.4  M1  Initiation 

Quality 

Management 

Plan 

Defines how the parties will participate in 

Quality Management. Infosys  IRWD 

1.5  M1  Initiation 

Risk 

Management 

Plan 

Defines how the parties will participate in a 

Risk Management plan and how Risks will be 

identified, documented, reported and 

Infosys  IRWD 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 109 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

handled.

1.6  M1  Initiation Communicati

on Plan 

Defines the Project Strategy for 

communicating internally within the Project 

Team and to external users and Stakeholders. 

IRWD  Infosys 

1.7  M1  Initiation 

System 

Infrastructure 

Plan for 

Demo and 

Development 

Environment 

Defines the hardware, network and other 

ancillary software required for the initiation 

phase of the Project.  Detailed Network 

diagrams will be provided in Visio.  

Infosys  IRWD 

1.8  M1  Initiation 

Analysis 

Workshop 

Plan 

Analysis workshop plan is the schedule for 

conducting the functional workshops. This 

plan is made in advance and published to the 

business users to block their calendars 

according to the functional areas to be 

covered in the workshops.  

Infosys  IRWD 

1.9  M1  Initiation 

Installation 

and Setup of 

Project 

Tracking Tool  

Installation and Setup of Project Tracking 

Tools such as Issue Tracker, Risk Management 

Tool, Defect Tracker, etc.   

Infosys and 

IRWD  

1.10  M1  Initiation 

Project Kick‐

off Meeting 

Conducted 

Materials will have been created and the kick‐

off meeting held with the project team. 

Infosys and 

IRWD   

 

1.11  M1  Initiation 

Project 

Tracking Tool 

Installation 

and training. 

Setup and configuration of the Project 

Tracking Tools.  Training for project team has 

been completed. 

IRWD   

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 110 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

1.12  M1  Initiation 

Plan for the 

Core Team 

Training 

Infrastructure 

Plan for the installation of Project and system 

deployment infrastructure specific to the 

needs for the Core Team training 

IRWD  Infosys 

 

1.13  M1  Initiation 

Plan for 

Project 

Infrastructure 

Plan for the deployment of server hardware 

and related infrastructure for the 

environment required for training and 

Development. 

Infosys  IRWD 

 

1.14  M1  Initiation 

Establish 

Initial Project 

Infrastructure 

Install and configure technology for initial 

phases of project as defined in the Project 

Infrastructure Plan. 

IRWD  Infosys 

 

1.15  M1  Initiation Solution 

Installation 

Verified installation of all products (out of the 

box installation) within the Solution and all 

tools required for all project activities: i.e. 

training, analysis, design, build, etc.  Testing 

of installations completed. 

Infosys  IRWD 

 

1.16  M1  Initiation Boot Camp 

Training 

Boot Camp training has been conducted and 

training materials provided to project team. Infosys  IRWD 

 

1.17  M1  Initiation 

Conduct 

Offshore 

Team Kick Off 

Infosys  and  IRWD  will  have  a  meeting  to 

check  the  status  of  the  offshore  team 

readiness. On‐boarding of  the required  team 

members at offshore to start the work, status 

of  the  project  management  activities  at 

offshore for initiation phase. 

Infosys  IRWD 

 

Milestone Completion  28‐Feb‐13 $254,000

Retainage  $25,400

Net Payment (USD)  $228,600

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 111 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

DELIVERABLES FOR M2 (Functional Workshop)  

2.1  M2  Initiation 

Business 

Process 

Change 

Management 

Plan/Strategy 

This defines how IRWD will implement 

business process changes. Infosys  IRWD 

   

2.2  M2  Initiation 

Readiness 

Criteria for 

Cutover 

Defines Readiness Criteria for Cutover.  IRWD  Infosys 

   

2.3  M2  Analysis Analysis 

Workshops 

Business Process Analysis Workshops have 

been conducted. Infosys  IRWD  

 

2.4  M2  Analysis 

To‐Be 

Process 

Document 

Per 

Process/Mod

ule 

To‐Be Processes documentation is 

completed.   Infosys    

 

2.5  M2  Analysis 

Updated 

Client 

Solution 

Requirement

s  

Client Solution Requirements updated for the 

workshops completed. This will consist of the 

extensions, interfaces or Reports. 

Infosys    

 

2.6  M2  Analysis 

Listing of 

RICE 

elements 

Complete documentation of RICE elements.  Infosys    

2.7  M2 Data 

Convers‐

Data 

Conversion 

Conversion Plan developed, documented and 

approved Infosys  IRWD 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 112 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

ion  Plan 

2.8  M2 

Data 

Convers‐

ion 

Data 

Conversion 

Strategy 

Document 

Conversion approach and strategy 

documented and approved Infosys  IRWD 

2.9  M2  Initiation  OCM  Stakeholder Engagement Plan  Infosys  IRWD 

Milestone Completion  16‐May‐2013 $404,000

Retainage $40,400

Net Payment (USD)  $363,600

DELIVERABLES FOR M3 (Functional Specifications) 

3.1  M3  Analysis 

Business 

Process 

Document 

Catalog 

Completed catalog of all the To‐Be Business 

Process documents. Infosys    

3.2  M3  Analysis 

Functional 

Workshop 

Activities 

Sign‐off 

Sign‐off indicates that all Functional 

Workshop work activities and all deliverables 

are complete. 

IRWD  Infosys 

3.3  M3  Analysis 

Extension 

Functional 

Specification  

Completed Functional Specifications for each 

Extension RICE item identified. Infosys   

3.4  M3  Analysis 

Interfaces 

Functional 

Specification  

Completed Functional Specifications for each 

interface RICE Item identified. Infosys   

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 113 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

3.5  M3  Analysis 

Reports 

Functional 

Specification  

Completed Reports Specifications Document 

for each reports RICE Item identified. Infosys   

3.6  M3 

Data 

Convers‐

ion 

Data 

Migration 

Workshops 

Complete data migration workshops.  Infosys  IRWD 

3.7  M3  Analysis 

Analysis 

Phase Sign‐

off 

Phase Sign‐off indicates that all work 

activities and all deliverables for this phase 

and the project management activities have 

been completed.   Signoff may be conditional. 

IRWD   

Milestone Completion  08‐Jul‐2013 $404,000

Retainage $40,400

Net Payment (USD)  $363,600

DELIVERABLES FOR M4 (Design ‐ Technical Specifications) 

4.1  M4  Testing Test Strategy 

Document 

Completed Test Strategy and Test Plan 

Document for ST, SIT and UAT Infosys  IRWD 

4.2  M4  Design 

First Version 

of Solution 

Configuration 

Document 

Configuration information defining the 

Solution. The Solution Configuration 

Document will be the design for all modules 

like Account, Customer and Location 

management, Usage, Rates, Billing, Credit & 

Collections, Conservation & Rebates etc 

Infosys  IRWD 

4.3  M4  Design 

Interfaces 

Technical 

Specifications 

Individual technical specifications for 

interfaces RICE Items Infosys  IRWD 

4.4  M4  Design Reports 

Technical 

Individual technical specifications for reports 

(RICE Items for reports). Infosys  IRWD 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 114 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

Specifications

4.5  M4  Design 

Extensions 

Technical 

Specifications 

Individual technical specifications for RICE 

items pertaining to extensions. Infosys   

4.6  M4  Design Design Phase 

Sign‐off 

Phase Sign‐off indicates that all work 

activities and all deliverables for this phase 

and the project management activities have 

been completed.   Signoff may be conditional 

Infosys   

Milestone Completion  09‐Sept‐13 $404,000

Retainage $40,400

Net Payment (USD)  $363,600

DELIVERABLES FOR M5 (Data Migration Design Completion) 

5.1  M5 

Data 

Convers‐

ion 

Data 

Conversion 

Specifications 

Detailed technical specifications for data 

conversion Infosys  IRWD 

5.2  M5 

Data 

Convers‐

ion 

Data 

Mapping 

Document 

Details data conversion mapping document  Infosys  IRWD 

5.3  M5  Design 

Data 

Conversion 

Design Phase 

Sign‐off 

Phase Sign‐off indicates that all work 

activities and all deliverables for this phase 

and the project management activities have 

been completed.   Signoff may be conditional 

Infosys   

Milestone Completion  4‐Nov‐13 $406,000

Retainage $40,600

Net Payment (USD)  $365,400

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 115 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

DELIVERABLES FOR M6 (Solution Configuration + Build) 

6.1  M6  Build Base Product 

Configuration Initial configuration completed and tested.  Infosys   

6.2  M6  Build 

Updated 

Solution 

Configuration 

Document 

Configuration document updated to reflect 

actual configuration. Infosys   

6.3  M6  Build 

Release 

Management 

Process 

Defines how changes to environments will be 

controlled.  I.e. who and when medications, 

configurations, etc are implemented into an 

environment (instance). 

Infosys  IRWD 

6.4  M6 

Data 

Convers‐

ion 

Data 

Conversion 

Programs 

Completed code and unit test the necessary 

extract, transform, and load processing and 

to conduct Conversions.  Programs will be 

developed and tested. 

Infosys  IRWD 

6.5  M6 

Data 

Convers‐

ion 

Data 

Migration 

Test Plans 

and Schedule 

Final Functional test plan, test schedule and 

walkthrough Infosys  IRWD 

6.6  M6  Testing 

Functional 

Test Scripts 

and Expected 

Results 

Development 

Details to be used in Functional Testing, as 

defined in the approved Functional Test Plan Infosys   

6.7  M6  Build 

Extensions 

Developed, 

coded and 

tested 

Develop and unit test all 

modifications/extensions to the Solution to 

satisfy the functions specified in the final 

approved Business Process Analysis 

Infosys   

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 116 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

document and Functional Specification.

6.8  M6  Build 

Interfaces 

Developed, 

coded and 

tested 

Develop and unit test all interface programs 

to the Solution to satisfy the functions 

specified in the final approved Business 

Process Analysis document and Functional 

Specification. 

Infosys   

6.9  M6  Build 

Reports 

Developed, 

coded and 

tested 

Develop and unit test all reports, letters, 

query portals, bill formats, etc. Infosys  IRWD 

6.10  M6  Build Build Phase 

Sign‐Off 

Phase Sign‐off indicates that all work 

activities and all deliverables for this phase 

and the project management activities have 

been completed.   Signoff may be conditional 

Infosys  IRWD 

Milestone Completion  1‐Jan‐14 $807,500

Retainage $80,750

Net Payment (USD)  $726,750

DELIVERABLES FOR M7 (ST) 

7.1  M7  Testing  Test 

Execution Completion of ST   Infosys   

Milestone Completion  3‐Feb‐14 $580,500

Retainage $58,050

Net Payment (USD)  $522,450

DELIVERABLES FOR M8 (SIT PHASE) 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 117 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

8.1  M8 

Data 

Convers‐

ion 

Data 

Migration for 

SIT 

Completion of conversion for SIT  Infosys  IRWD 

8.2  M8  Testing  SIT Test 

Execution Completion of SIT functional testing  Infosys   

8.3 

 M8  Testing 

 SIT Status 

Report 

A final SIT Status Report will be sent by 

Infosys to IRWD which will show the status of 

the SIT, the open issues/defects not resolved 

in SIT.s 

Infosys   

8.4  M8  Training  Training Plan Training Plan based on the Training Needs 

Assessment for both the programs. Infosys  IRWD 

8.5  M8  Training Training 

Schedule   Infosys  IRWD 

8.6  M8  Training 

End User 

Assessment 

questionnaire 

  Infosys  IRWD 

Milestone Completion  10‐Mar‐14 $656,500

Retainage $65,600

Net Payment (USD)  $590,400

DELIVERABLES FOR M9 (UAT) 

9.1  M9 

Data 

Convers‐

ion 

Data 

Cleansing 

Completed 

Conduct the automated and manual data 

cleansing before the data is provided to CC&B 

system for data conversion. Infosys will 

perform the automated data cleansing and 

the manual data cleansing (if required) will be 

performed by IRWD staff 

Infosys  IRWD 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 118 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

9.2  M9 

Data 

Convers‐

ion 

Data 

Migration for 

UAT 

Completion of conversion for UAT  Infosys  IRWD 

9.3  M9 

Data 

Convers‐

ion 

Data 

Conversion 

Test Reports 

with Results 

for each Test 

Run 

Once the conversion processing is unit tested, 

Infosys will execute test conversions of all 

data to be converted. Full conversions will be 

performed regularly throughout the Project, 

according to a schedule mutually agreed 

between Infosys and IRWD 

Infosys  IRWD 

9.4  M9 

Data 

Convers‐

ion 

Reconciliatio

n Results 

Once the conversion processing is unit tested, 

Infosys will execute test conversions of all 

data to be converted. Full conversions will be 

performed regularly throughout the Project, 

according to a schedule mutually agreed 

between Infosys and IRWD 

Infosys  IRWD 

9.5  M9 

Data 

Convers‐

ion 

Reconciliatio

n and Testing 

Specifications 

Once the conversion processing is unit tested, 

Infosys will execute test conversions of all 

data to be converted. Full conversions will be 

performed regularly throughout the Project, 

according to a schedule mutually agreed 

between Infosys and IRWD. 

Infosys  IRWD 

9.6  M9  Testing 

User 

Acceptance 

Test 

Execution 

Execution of end‐to‐end test scenarios that 

will cross multiple operational areas (i.e. read 

to bill).  IRWD and Infosys will jointly 

investigate discrepancies in results, 

documenting all reconciling items.  Infosys is 

responsible for correcting defects caused by 

Infosys 

IRWD  Infosys 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 119 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

9.7  M9  Cutover Installation 

Checklist 

Checklist defining configuration, the 

extensions, interface code and the reports 

will be deployed on production 

Infosys  IRWD 

9.8  M9  Cutover Deployment 

Document 

Deployment document will have the detailed 

steps to deploy the application on the Staging 

and production environment. 

Infosys  IRWD 

9.9  M9  Cutover 

Cutover 

Strategy 

Document 

Will document the approach to cutover 

testing and cutover planning.  The Strategy 

will also define the Issue Management 

Process for Warranty support and the Plan for 

support of End Users. 

Infosys  IRWD 

9.10  M9  Training Training 

Material 

a complete set of Train the trainer Training 

materials for the IRWD‐specific Solution 

implementation 

Infosys  IRWD 

Milestone Completion  5‐May‐14 $380,000

Retainage $38,000

Net Payment (USD)  $342,000

DELIVERABLES FOR M10 (Parallel Testing + Go Live ) 

10.1  M10 

Data 

Convers‐

ion 

Data 

Migration for 

Parallel 

Testing 

Completion of conversion for Parallel testing  Infosys  IRWD 

10.2  M10 

Data 

Convers‐

ion 

Data 

Migration 

Trials and 

Mock 

Conversions 

Completion of mock conversions  Infosys  IRWD 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 120 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

10.3  M10 

Data 

Convers‐

ion 

Final 

Conversion 

Data 

Mapping 

Document 

Once the conversion processing is unit tested, 

Infosys  will  execute  test  conversions  of  all 

data to be converted. Full conversions will be 

performed  regularly  throughout  the  Project, 

according  to  a  schedule  mutually  agreed 

between Infosys and IRWD 

Infosys  IRWD 

10.4  M10  Testing  Parallel 

Testing 

Infosys  will  develop  the  plan  and  scenarios 

for Parallel  testing and  IRWD will  review  the 

plan/scenarios to ensure maximum coverage. 

IRWD  and  Infosys  will  jointly  investigate 

discrepancies  in  results,  if  there  are  any.  

Infosys  is  responsible  for  correcting  defects 

caused by Infosys 

IRWD, 

Infosys  

10.5  M10  Testing 

Performance 

Test Results 

Report – First 

Draft 

Performance  of  the  Solution  including  the 

proposed production environment (operating 

system,  network,  database  and  disk  array 

distribution)  and  system parameters.   Based 

on  the  manual  testing  done.    The  final 

Performance  test  results  report  will  be 

delivered at  the end of 90 Days of Warranty 

support. 

Infosys   

10.6  M10 Deliver 

Training 

Training 

Sessions 

Completed 

  Infosys  IRWD 

10.7  M10  Cutover Cutover 

Checklist 

Contains  all  activities,  whether  business  or 

technical, which will be performed during the 

mock and real cutovers. 

Infosys  IRWD 

10.8  M10  Cutover Cutover 

Completed   Infosys  IRWD 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 121 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

10.9  M10  Cutover 

Cutover 

Phase Sign‐

Off 

Phase  Sign‐off  indicates  that  all  work 

activities  and  all  deliverables  for  this  phase 

and  the  project management  activities  have 

been  completed.      Sign‐off  may  be 

conditional. 

Infosys  IRWD 

Milestone Completion  09‐Jun‐14 $277,500

Retainage $27,750

Net Payment (USD)  $249,750

DELIVERABLES FOR M11 (Completion of Warranty Support – Month 1) 

11.1  M11  Warranty 

Warranty 

Support 

Report 

Month 1 

  Infosys   

Milestone Completion 04‐Jul‐14

$101,500 

Retainage $10,150

Net Payment (USD)  $91,350

   DELIVERABLES FOR M12 (Completion of Warranty Support Month 2) 

12.1  M12  Warranty 

Warranty 

Support 

Report 

Month 2 

  Infosys   

Milestone Completion  01‐Aug‐14 $75,000

Retainage $7,500

Net Payment (USD)  $67,500

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 122 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

   DELIVERABLES FOR M13 (Completion of Warranty Support ‐ Month 3 ) 

13.1  M13  Warranty 

Warranty 

Support 

Report 

Month 3 

  Infosys   

Milestone Completion  29‐Aug‐14 $75,000

Retainage $7,500

Net Payment (USD)  $67,500

DELIVERABLES FOR M14 (Final Acceptance) 

14.1  M14  Warranty Phase 1 Final 

Acceptance   Infosys   

14.2  M14  Warranty 

Post 

Implementati

on Status 

Report 

  Infosys   

14.3  M14  Warranty 

Final 

Performance 

Test Results 

Report 

This is the follow‐up report for the 

performance results taken as per the 

performance criteria defined in section 3.0 of 

this SOW. 

Infosys   

14.4  M14 

Final 

Accept‐

ance 

Final 

Acceptance 

Sign‐off 

  Infosys   

Milestone Completion 29‐Aug‐14

$482,500 

Retainage $0

Net Payment (USD) 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 123 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

$482,500

PHASE 2 (OUCSS) MILESTONES VS DELIVERABLES MAPPING 

DELIVERABLES FOR M15 (Initiation) 

15.1  M15  Initiation  Project Plan 

Defines the tasks, resources and schedule 

required to complete project (including post‐

implementation tasks). For the initiation 

phase of the project Infosys will deliver the 

draft project plan. The first draft of the 

project plan will have minimum next 90 

activities planned in detail. The activities after 

90 Days can be detailed out further in the 

next milestones. 

Infosys  IRWD 

15.2 

M15 

Initiation 

OUCSS 

Performance 

Baseline 

Gather and report of current OUCSS 

performance metrics to assist in baselining 

Phase 2 performance objectives. 

Infosys   

15.3 

M15 

Initiation Project 

Charter 

Defines the mission, goals/objectives, 

activities, boundaries, metrics and 

governance of the Project. 

IRWD  Infosys 

15.4 

 

M15  Initiation Project Org 

Chart 

Defines participants and reporting 

relationships.  This should be part of the 

Charter. 

Infosys  IRWD 

15.5 

 

M15  Initiation 

Quality 

Management 

Plan 

Defines how the parties will participate in 

Quality Management. Infosys  IRWD 

15.6  

M15  Initiation Risk 

Management 

Defines how the parties will participate in a 

Risk Management plan and how Risks will be Infosys  IRWD 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 124 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

Plan  identified, documented, reported and 

handled. 

15.7 

 

M15  Initiation Communicati

on Plan 

Defines the Project Strategy for 

communicating internally within the Project 

Team and to external users and Stakeholders. 

IRWD  Infosys 

15.8 

 

 

 

M15 Initiation 

System 

Infrastructure 

Plan for 

Demo and 

Development 

Environment 

Defines the hardware, network and other 

ancillary software required for the initiation 

phase of the Project.  Detailed Network 

diagrams will be provided in Visio.  

Infosys  IRWD 

15.9 

 

 

M15 Initiation 

Analysis 

Workshop 

Plan 

Analysis workshop plan is the schedule for 

conducting the functional workshops. This 

plan is made in advance and published to the 

business users to block their calendars 

according to the functional areas to be 

covered in the workshops.  

Infosys  IRWD 

15.10 

 

M15 Initiation 

Installation 

and Setup of 

Project 

Tracking Tool  

Installation and Setup of Project Tracking 

Tools such as Issue Tracker, Risk Management 

Tool, Defect Tracker, etc.   

Infosys and 

IRWD  

15.11 

 

M15  Initiation 

Project Kick‐

off Meeting 

Conducted 

Materials will have been created and the kick‐

off meeting held with the project team. 

Infosys and 

IRWD   

15.12 

 

M15  Initiation 

Project 

Tracking Tool 

Installation 

and training. 

Setup and configuration of the Project 

Tracking Tools.  Training for project team has 

been completed. 

IRWD   

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 125 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

15.13 

 

 

M15 Initiation 

Plan for the 

Core Team 

Training 

Infrastructure 

Plan for the installation of Project and system 

deployment infrastructure specific to the 

needs for the Core Team training 

IRWD  Infosys 

15.14 

M15 

Initiation 

Plan for 

Project 

Infrastructure 

Plan for the deployment of server hardware 

and related infrastructure for the 

environment required for training and 

Development. 

Infosys  IRWD 

15.15 

 

M15  Initiation 

Establish 

Initial Project 

Infrastructure 

Install and configure technology for initial 

phases of project as defined in the Project 

Infrastructure Plan. 

IRWD  Infosys 

15.16 

 

 

M15  Initiation Solution 

Installation 

Verified installation of all products (out of the 

box installation) within the Solution and all 

tools required for all project activities: i.e. 

training, analysis, design, build, etc.  Testing 

of installations completed. 

Infosys  IRWD 

15.17 M15 

Initiation Boot Camp 

Training 

Boot Camp training has been conducted and 

training materials provided to project team. Infosys  IRWD 

15.18 

 

 

M15 Initiation 

Conduct 

Offshore 

Team Kick Off 

Infosys and IRWD will have a meeting to 

check the status of the offshore team 

readiness. On‐boarding of the required team 

members at offshore to start the work, status 

of the project management activities at 

offshore for initiation phase. 

Infosys  IRWD 

Milestone Completion 18‐Jul‐2014 $35,000

Retainage $3500

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 126 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

Net Payment (USD) $31,500

DELIVERABLES FOR M16 (Functional and Technical Specifications) 

16.1  M16  Initiation 

Business 

Process 

Change 

Management 

Plan/Strategy 

This defines how IRWD will implement 

business process changes. Infosys  IRWD 

16.2 

 

M16  Initiation 

Readiness 

Criteria for 

Cutover 

Defines Readiness Criteria for Cutover.  IRWD  Infosys 

16.3  

M16  Analysis Analysis 

Workshops 

Business Process Analysis Workshops have 

been conducted. Infosys  IRWD  

16.4 

 

 

M16 Analysis 

To‐Be 

Process 

Document 

Per 

Process/Mod

ule 

To‐Be Processes documentation is 

completed.   Infosys    

16.5 

 

M16 

Analysis 

Updated 

Client 

Solution 

Requirement

s  

Client Solution Requirements updated for the 

workshops completed. This will consist of the 

extensions, interfaces or Reports. 

Infosys    

16.6 

 

M16  Analysis 

Listing of 

RICE 

elements 

Complete documentation of RICE elements.  Infosys    

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 127 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

16.7  M16  Analysis 

Business 

Process 

Document 

Catalog 

Completed catalog of all the To‐Be Business 

Process documents. Infosys    

16.8  M16  Analysis 

Functional 

Workshop 

Activities 

Sign‐off 

Sign‐off indicates that all Functional 

Workshop work activities and all deliverables 

are complete. 

IRWD  Infosys 

16.9  M16  Analysis 

Extension 

Functional 

Specification  

Completed Functional Specifications for each 

Extension RICE item identified. Infosys   

16.10  M16  Analysis 

Interfaces 

Functional 

Specification  

Completed Functional Specifications for each 

interface RICE Item identified. Infosys   

16.11  M16  Analysis 

Reports 

Functional 

Specification  

Completed Reports Specifications Document 

for each report RICE Item identified. Infosys   

16.12  M16 

Data 

Convers‐

ion 

Data 

Migration 

Workshops 

Complete data migration (profile migration) 

workshops. Infosys  IRWD 

16.13  M16  Analysis 

Analysis 

Phase Sign‐

off 

Phase Sign‐off indicates that all work 

activities and all deliverables for this phase 

and the project management activities have 

been completed.   Signoff may be conditional. 

IRWD   

16.14  M16  Testing Test Strategy 

Document 

Completed Test Strategy and Test Plan 

Document for ST, SIT and UAT Infosys  IRWD 

16.15  M16  Design 

First Version 

of Solution 

Configuration 

Configuration information defining the 

Solution. The Solution Configuration 

Document will be the design for all modules 

Infosys  IRWD 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 128 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

Document like Customer Registration, Bill Viewing, 

Payments, Profile management, Analytics etc   

16.16  M16  Design 

Interfaces 

Technical 

Specifications 

Individual technical specifications for 

interfaces RICE Items Infosys  IRWD 

16.17  M16  Design 

Reports 

Technical 

Specifications 

Individual technical specifications for reports 

(RICE Items for reports). Infosys  IRWD 

16.18  M16  Design 

Extensions 

Technical 

Specifications 

Individual technical specifications for RICE 

items pertaining to extensions. Infosys   

16.19  M16  Design Design Phase 

Sign‐off 

Phase Sign‐off indicates that all work 

activities and all deliverables for this phase 

and the project management activities have 

been completed.   Signoff may be conditional 

Infosys   

Milestone Completion 12‐Sep‐2014 $70,000

Retainage $7,000

Net Payment (USD) $63,000

DELIVERABLES FOR M17 (Solution Configuration + Build) 

17.1  M17  Build Base Product 

Configuration Initial configuration completed and tested.  Infosys   

17.2  M17  Build Updated 

Solution 

Configuration document updated to reflect 

actual configuration. Infosys   

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 129 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

Configuration 

Document 

17.3  M17  Build 

Release 

Management 

Process 

Defines how changes to environments will be 

controlled.  I.e. who and when modifications, 

configurations, etc are implemented into an 

environment (instance). 

Infosys  IRWD 

17.4  M17 

Data 

Convers‐

ion 

Data 

Conversion 

Programs 

Completed code and unit test the necessary 

extract, transform, and load processing and 

to conduct Conversions.  Programs will be 

developed and tested. 

Infosys  IRWD 

17.5  M17 

Data 

Convers‐

ion 

Data 

Migration 

Test Plans 

and Schedule 

Final Functional test plan, test schedule and 

walkthrough Infosys  IRWD 

17.6  M17  Testing 

Functional 

Test Scripts 

and Expected 

Results 

Development 

Details to be used in Functional Testing, as 

defined in the approved Functional Test Plan Infosys   

17.7  M17  Build 

Extensions 

Developed, 

coded and 

tested 

Develop and unit test all 

modifications/extensions to the Solution to 

satisfy the functions specified in the final 

approved Business Process Analysis 

document and Functional Specification. 

Infosys   

17.8  M17  Build 

Interfaces 

Developed, 

coded and 

tested 

Develop and unit test all interface programs 

to the Solution to satisfy the functions 

specified in the final approved Business 

Process Analysis document and Functional 

Specification. 

Infosys   

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 130 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

17.9  M17  Build 

Reports 

Developed, 

coded and 

tested 

Develop and unit test all reports, letters, 

query portals, bill formats, etc. Infosys  IRWD 

17.10  M17  Build Build Phase 

Sign‐Off 

Phase Sign‐off indicates that all work 

activities and all deliverables for this phase 

and the project management activities have 

been completed.   Signoff may be conditional 

Infosys  IRWD 

Milestone Completion 14‐Nov‐2014 $105,000

Retainage $10,500

Net Payment (USD) $94,500

DELIVERABLES FOR M18 (Completion of ST + SIT) 

18.1  M18  Testing  Test 

Execution Completion of ST   Infosys   

18.2  M18 

Data 

Convers‐

ion 

Data 

Migration for 

SIT 

Completion of profile migration  for SIT  Infosys  IRWD 

18.3  M18  Testing  SIT Test 

Execution Completion of SIT functional testing  Infosys   

18.4  M18  Testing  SIT Status 

Report 

A final SIT Status Report will be sent by 

Infosys to IRWD which will show the status of 

the SIT, the open issues/defects not resolved 

in SIT. 

Infosys   

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 131 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

18.5  M18  Training  Training Plan Training Plan based on the Training Needs 

Assessment for both the programs. Infosys  IRWD 

18.6  M18  Training Training 

Schedule   Infosys  IRWD 

18.7  M18  Training 

End User 

Assessment 

questionnaire 

  Infosys  IRWD 

Milestone Completion 19‐Dec‐2014 $70,000

Retainage $7,000

Net Payment (USD) $63,000

19.1  M19 

OUCSS 

UAT + Go 

Live 

 Completion 

of UAT & Go 

Live 

The deliverables listed below will be 

completed for the Milestone M19.    

19.2  M19 

OUCSS 

UAT  

Data 

Migration for 

UAT 

Completion of conversion (profile migration) 

for UAT. IRWD  Infosys 

19.3  M19 

OUCSS 

UAT  

Data 

Conversion 

Test Reports 

with Results 

for each Test 

Run 

Once the conversion processing is unit tested, 

Infosys will execute test conversions of all 

profile data to be converted. Full conversions 

will be performed regularly throughout the 

Project, according to a schedule mutually 

agreed between Infosys and IRWD. 

IRWD  Infosys 

19.4  M19 OUCSS 

UAT  

Reconciliatio

n Results 

Once the conversion processing is unit tested, 

Infosys will execute test conversions of all IRWD  Infosys 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 132 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

data to be converted. Full conversions will be 

performed regularly throughout the Project, 

according to a schedule mutually agreed 

between Infosys and IRWD 

19.5  M19 OUCSS 

UAT  

Reconciliatio

n and Testing 

Specifications 

Once the conversion processing is unit tested, 

Infosys will execute test conversions of all 

data to be converted. Full conversions will be 

performed regularly throughout the Project, 

according to a schedule mutually agreed 

between Infosys and IRWD. 

IRWD  Infosys 

19.6  M19 OUCSS 

UAT  

User 

Acceptance 

Test 

Execution 

Execution of end‐to‐end test scenarios for 

OUCSS.  Infosys is responsible for correcting 

defects caused by Infosys 

IRWD  Infosys 

19.7  M19 OUCSS 

UAT  

Installation 

Checklist 

Checklist defining configuration, the 

extensions, interface code and the reports 

will be deployed on production. 

Infosys  IRWD 

19.8  M19 OUCSS 

UAT  

Deployment 

Document 

Deployment document will have the detailed 

steps to deploy the application on the Staging 

and production environment. 

Infosys  IRWD 

19.9  M19  Cutover 

Cutover 

Strategy 

Document 

Will document the approach to cutover 

testing and cutover planning.  The Strategy 

will also define the Issue Management 

Process for Warranty support and the Plan for 

support of End Users. 

Infosys  IRWD 

19.10  M19  Training Training 

Material 

A complete set of train the trainer Training 

materials for the IRWD‐specific Solution 

implementation 

Infosys  IRWD 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 133 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

19.11  M19 

Perform‐

ance 

Testing 

Performance 

Test Results 

Report – First 

Draft 

Performance of the Solution including the 

proposed production environment (operating 

system, network, database and disk array 

distribution) and system parameters.  Based 

on the manual testing done.  The final 

Performance test results report will be 

delivered at the end of Warranty support. 

Infosys  IRWD 

19.12  M19  Training 

Training 

Sessions 

Completed 

  Infosys  IRWD 

19.13  M19  Cutover Cutover 

Checklist 

Contains all activities, whether business or 

technical, which will be performed during the 

mock and real cutovers. 

Infosys  IRWD 

19.14  M19  Cutover Cutover 

Completed 

Cutover for Phase 2 completed and the 

application up and running on production. Infosys  IRWD 

Milestone Completion 19‐Jan‐2015 $35,000

Retainage $3500

Net Payment (USD) $31,500

20.1  M20  Warranty 

Completion 

of Warranty 

Support ‐ 

Month 1 

  Infosys   

Milestone Completion 13‐Feb‐2015 $35,000

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 134 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

Retainage $3500

Net Payment (USD) $31,500

21.1  M21  Warranty 

Completion 

of Warranty 

Support ‐ 

Month 2 

  Infosys  IRWD  

NA 

22.1  M22 

Final 

Accept‐

ance 

Final 

Acceptance      

22.2  M22 

Final 

Accept‐

ance 

Post 

Implementati

on Status 

Report 

  Infosys   

22.3  M22 

Final 

Accept‐

ance 

Final 

Performance 

Test Results 

Report 

This is the follow‐up report for the 

performance results taken as per the 

performance criteria defined in section 3.0 of 

this SOW. 

Infosys   

22.4  M22 

Final 

Accept‐

ance 

Final 

Acceptance 

Sign‐off 

  Infosys   

Milestone Completion 12‐Mar‐2015 NA

Retainage $0.00

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 135 of 142 

Deliver

able 

No. 

Payment 

Milestone Phase  Name  Deliverable Description/Definition  Lead  Assist  

Estimated 

Completion  

Date 

Payments 

(USD) 

Net Payment (USD) $35,000

 

 

M#  Description Milestone  Date 

Services Amount  Retainage Amount  Net Payment (USD) 

M0  Contract Completion & Mobilization  15‐Feb‐13   $      150,000.00    $                   ‐      $      150,000.00  

M1  Initiation Complete  28‐Feb‐13   $      254,000.00    $    25,400.00    $      228,600.00  

M2  Functional Workshop  16‐May‐13   $      404,000.00    $    40,400.00    $      363,600.00  

M3  Functional Specifications  8‐Jul‐13   $      404,000.00    $    40,400.00    $      363,600.00  

M4  Design ‐ Technical Specifications  9‐Sep‐13   $      404,000.00    $    40,400.00    $      363,600.00  

M5  Data Migration Design Completion  4‐Nov‐13   $      406,000.00    $    40,600.00    $      365,400.00  

M6  Solution Configuration + Build  1‐Jan‐14   $      807,500.00    $    80,750.00    $      726,750.00  

M7  Completion of ST  3‐Feb‐14   $      580,500.00    $    58,050.00    $      522,450.00  

M8  Completion of SIT  10‐Mar‐14   $      656,000.00    $    65,600.00    $      590,400.00  

M9  Completion of UAT  5‐May‐14   $      380,000.00    $    38,000.00    $      342,000.00  

M10  Go Live  9‐Jun‐14   $      277,500.00    $    27,750.00    $      249,750.00  

M11  Completion of Warranty Support ‐ Month 1  4‐Jul‐14   $      101,500.00   $    10,150.00   $      91,350.00 

M12  Completion of Warranty Support ‐ Month 2  1‐Aug‐14   $      75,000.00    $    7,500.00    $        67,500.00  

M13  Completion of Warranty Support ‐ Month 3  29‐Aug‐14   $      75,000.00    $    7,500.00    $        67,500.00  

M14  Final Acceptance  29‐Aug‐14         $      482,500 

TOTALS    $ 4,975,000.00   $482,500.00  $4,975,000.00 

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 136 of 142 

OUCSS Payment Milestones: 

M#  Description  Milestone  Date Services Amount 

Retainage  Amount 

Net Payment (USD) 

M15  Initiation Complete  18‐Jul‐14  $35,000  $3,500  $31,500 

M16  Design ‐ Technical Specifications  12‐Sep‐14  $70,000  $7,000  $63,000 

M17  Solution Configuration + Build  14‐Nov‐14  $105,000  $10,500  $94,500 

M18  Completion of ST + SIT  19‐Dec‐14  $70,000  $7,000  $63,000 

M19  Completion of UAT & Go Live  19‐Jan‐15  $35,000  $3,500  $31,500 

M20 Completion of Warranty Support ‐ Month 1 

13‐Feb‐15  $35,000  $3,500  $31,500 

M21  Final Acceptance ‐ Month 2  12‐Mar‐15  $0  $0  $0 

M22  Final Acceptance   12‐Mar‐15  $0  $35,000 

TOTALS  $350,000  $35,000  $350,000 

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 137 of 142 

12. Travel & Expense Policies 

12.1 General Principles All travel costs are included in the base price for the proposed services. For the duration of the services 

defined in this SOW, IRWD will not be billed for any travel‐related or any other Project‐related expenses. 

However, In the event that change orders that involve additional travel costs are mutually agreed to by 

the parties,  Infosys will bill  the  travel  involved  (as part of  the change order execution) as actual costs 

incurred.  

   

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 138 of 142 

IN  WITNESS  WHEREOF,  the  parties  have  executed  this  Statement  of  Work  by  their  authorized 

representatives as of the date first written above. 

   

 

 

 

 

 

 

 

 

 

 

Infosys Limited  Irvine Ranch Water District, Irvine, CA 

___________________________  ______________________________ 

Authorized Signatory  Authorized Signatory 

___________________________  ______________________________ 

Name  Name 

 

___________________________  ______________________________ 

Title  Title 

 

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 139 of 142 

Appendix 1.  Updated Proposal Document 

The updated proposal consists of the following documents. 

 

A 1.1 Updated Proposal Summary 

This  document  identify  adjustments  that  Infosys  has  made  to  their  initial  proposal.    It  represents 

changes to Infosys’ original proposal that are required to deliver the proposed solution.  These changes 

were identified during the due diligence phase. 

File:  IRWD Post DD Session Response Final.pptx 

 

A 1.2 Functional Checklist 

This document contains a list of requirements that will be delivered by Infosys.  The document identifies 

the effort required to deliver these requirements (i.e. whether configuration, modification, etc.).   Note 

that this is not a complete list of requirements to be delivered, but only a subset.  All requirements are 

represented by the complete set of documents comprising the Client Solution Requirements as defined 

in this SOW. 

File: IRWD STAR Requirements Final.xlsx 

 

A 1.3 Price Detail Sheets 

This document contains the detailed breakdown of all costs associated with the services to be delivered 

by Infosys.  Payment for these services is subject to the payment rules and acceptance critieria defined 

within the SOW and the Agreement. 

File: IRWD_Attachment_B_Price Sheet IRWD update 12‐10.xlsx 

 

A 1.4 Project Plan 

This document contains the initial project plan for Phase 1 and Phase 2 of the project.   

File: IRWD_CCB‐Project Plan_Final 2012‐12‐10.mpp 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 140 of 142 

Appendix 2. Clarifying Requirements Document 

These documents were provided to  Infosys during the due diligence phase to provide clarification and 

additional information on the requirements to be delivered by Infosys under this SOW. 

File 1: Interface ‐ Hosted Backflow Assembly Test Tracking System.pdf 

File 2: IRWD CCP Interface Process_ Document v1.0_IRWD.docx 

File 3: Batch jobs that communicate data between IRWD and Fiserv.docx 

File 4: IRWD Customer Web Portal_1.docx 

File 5: IRWD WEB Portal Flows for Phase 1.xlsx 

 

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 141 of 142 

Appendix 3. Request for Proposal 

These documents  contain  the  intial RFP distributed by  IRWD.    Some of  the  requirements within  the 

orginal RFP were adjusted as reflected  in the “Clariying Requirements Document”  (see Appendix 1) or 

the “Updated Proposal Document” (see Appendix 2). 

 

File 1: IRWD  RFP for SI ‐ Oracle CCB Implementation.pdf 

File 2: IRWD Attachment A1 ‐ Professional Services Agreement ‐ Sample.pdf 

File 3: IRWD  Attachment  A2  ‐  Professional  Services  Agreement  ‐  Sample  Exhibit  B  Compensation 

Schedule.pdf 

File 4: RWD  Attachment  A3  ‐  Professional  Services  Agreement  ‐  Sample  Exhibit  C  Variance  Form 

Sample.pdf 

File 5: IRWD Attachment B ‐ Proposal Section 13 Price Sheets.xlsx 

File 6: IRWD Attachment C ‐ Proposal Section 11 Instructions for the Use of STAR.pdf 

File 7: IRWD Attachment D ‐ Enterprise Network.pdf 

File 8: IRWD Attachment E ‐ Proposal Response Format.docx 

File 9: IRWD Attachment F ‐ Schedule of Rates and Charges.pdf 

 

Statement of Work    

© 2012 Infosys Limited                                                                                                                     Page 142 of 142 

Appendix 4. Initial Proposal Document 

These documents were submitted by Infosys in response to IRWD’s RFP.  Infosys’ proposal was adjusted 

are reflected in the “Updated Proposal Document” (see Appendix 1). 

 

File 1: IRWD RFP Response‐Infosys.docx 

File 2: IRWD_Requirements_Response_Infosys.pdf 

File 3: IRWD_Appendix_1_Implementation Schedule‐Project Plan‐Infosys.pdf 

File 4: IRWD ‐ Appendix_3_Infosys Case Studies‐Infosys.docx 

File 5: IRWD ‐Appendix_4 Infosys Key Profiles‐Infosys.docx 

File 6: IRWD_Attachment_B_‐_Proposal_Section_13_Price_Sheets‐Infosys.xlsx 

File 7: Infosys Case Studies.docx 

File 8: Resumes.docx 

File 9: IRWD_RFP_Managed_Services_Response‐Infosys.docx