KELE Contracting LLCMediclinic City Hospital North Wing Health Care CityWeekly Progress Report
Doc. No.MCH/KELE/WR/001
Report Date: 09.09.14
MEDICLINIC CITY HOSPITAL NORTH WING
WEEKLY PROGRESS REPORT NO.
Report Period 02.09.14 to 08.09.14
EMPLOYERPROJECT MANAGERCONSULTANTMAIN CONTRACTOR
CONTENTS
SECTION 1.0
SECTION 2.0
SECTION 3.0 EXECUTIVE SUMMARY
CONSTRUCTION PROGRESS
2 WEEKS LOOKAHEAD PROGRAMME
SECTION 4.0 PROGRESS S-CURVE
SECTION 5.0AREA OF CONCERN
SECTION 6.0HSE REPORT
SECTION 7.0 PROGRESS PHOTOGRAPHS
SECTION 1.0 EXECUTIVE SUMMARY
Project DetailsProject Name: Mediclinic City Hospital-North wing Project Location: Dubai Healthcare City.Configuration: (3B+G+6+RF)Employer: Mediclinic City HospitalProject Manager: Turner & TownsendConsultant: Hyder Consulting (ME) Ltd...Main Contractor: Kele Contracting L.L.C.
FinancialOriginal Contract Value: AED 135,980,000.Cumulative Claimed to Date: AED 5,815,969.82Cumulative Certified to Date: AED 3,814,676.74Cumulative Paid to Date: AED 1,161,076.92Applied Variations Value: AED 449,807.25Confirmed Variations Value: TBCRevised Contract Value: TBC
ProgrammeCommencement Date: 27-May-14Original Completion Date: 27-Sep-14 Original Duration: 489 DaysPlanned progress %: 8.09%Actual progress %: 1.03%Variance %: 7.06%Time Elapsed: 105 DaysTime Remaining: 384 Days EOT (Applied): 62 DaysEOT (Granted & approved): TBCRevised Completion Date: TBC
SECTION 2 CONSTRUCTION PROGRESSS.NoActivity DescriptionPlanned % completeActual % Complete
LIFTPIT AND SUMPPIT WORKS
1Excavation for lift pits and sump pits100%100%
2Anti-termite treatment & PCC for lift pits and sump pits100%50%
3Blockwork for footings100%50%
4Waterproofing for lift pits and sump pits100%0%
5Protection screed above waterproofing100%0%
6Reinforcement for lift pit foundation100%0%
7Concreting of lift pit and sump pits100%0%
MAIN RAFT
1Excavation for raft and carting away100%80%
2Pile cutting and removing100%90%
3Compaction for raft foundation100%50%
4Anti-termite treatment and PCC for raft100%50%
5Blockwork around pile caps100%50%
6Water proofing for raft100%0%
7Protection screed above waterproofing100%0%
8Rebar for footing and raft100%0%
SECTION 32 WEEKS LOOK AHEAD PROGRAM
SECTION 4PROGRESS S-CURVE
SECTION 5AREA OF CONCERNSS.NoDescriptionActionCommentsTime Delay
Critical Concern
Potential Concern
1
SECTION 7.0 HSE REPORT WEEKLY SAFETY SUMMARY REPORT
PROJECT NAME:MEDICLINIC CITY HOSPITAL NORTH WINGDATE:03 SEP 2014
REPORTING PERIOD:FROM: 31 AUG 2014 TO: 07 SEPT 2014
(1) MAN HOURS WORKED
MAN HOURS FOR THE PERIODYEAR TO DATEMAN HOURS FROM STARTOf PROJECT
Kele Employees334565598955959
Subcontractors81001328813288
Total415566924769247
(2) ACCIDENTS
S No.TYPE OF ACCIDENTFOR THE PERIODYEAR TO DATEFROM STARTOf PROJECT
1FIRST AID CASE (FAC)010303
2MEDICAL TREATMENT INJURY (MTI)000000
3LOST TIME INJURY (LTI)000000
4NEAR MISS010202
5MAJOR INJURIES000000
6FATALITIES000000
7ENVIRONMENTAL INCIDENTS000000
(3) MAN DAYS LOST
FOR THE PERIODYEAR TO DATEFROM STARTOf PROJECT
000000
(4A) SEVERITY RATE
FORMULA YEAR TO DATEFROM START OF PROJECT
TOTAL MAN DAYS LOST * 1000000TOTAL No. OF MAN HOURS WORKED0000
(4B) LOST TIME INCIDENT FREQUENCY RATE
FORMULA YEAR TO DATEFROM START OF PROJECT
NO OF LOST TIME INCIDENT* 1000000TOTAL No. OF MAN HOURS WORKED0000
(4C) TOTAL RECORDABLE INJURY FREQUENCY RATE
FORMULA YEAR TO DATEFROM START OF PROJECT
NO OF LTI + No. of MTI * 1000000TOTAL No. OF MAN HOURS WORKED0000
(5) OTHER ACTIVITIES
S No. ACTIVITYFOR THE MONTHYEAR TO DATEFROM STARTOf PROJECT
1SAFETY CORRECTIVE ACTION REPORTS (SCAR)053535
2SAFETY AWARDS010101
3SAFETY VIOLATION050606
4SAFETY AUDITS/ INSPECTIONS
A INTERNAL 000303
B - EXTERNAL030303
5TRAININGS:
A SAFETY INDUCTION25245245
B - TOOLBOX TALK051111
C - OTHERS000101
Prepared by : JULIUS SANORJO Approved by: LESLIE FAIRCHILD SAFETY OFFICER PROJECT MANAGER
SIGNATURE: SIGNATURE:
Photographic Documentation
Tool Box Talks:
Safety Performance award for the month of August:
Lifting Equipments:
1. Mobile Crane (off hired) 100 ton Mobile Crane see attached Certificate2. Wolffkran Tower Crane Commissioned 23rd of August 2014 see attached inpection receipt and time sheet
Lifting gears and Accessories
1. Two 5-ton lifting belts (Claymore Certified)2. Two 3-ton lifting belts (new) no 3rd party certificate3. K 370 & K 369 see attached Certificates Tower Crane commissioned 23/08/2014
Main Site Access & Egress