Medilinic Weekly Progress Report No 01

Embed Size (px)

Citation preview

Table of Content

KELE Contracting LLCMediclinic City Hospital North Wing Health Care CityWeekly Progress Report

Doc. No.MCH/KELE/WR/001

Report Date: 09.09.14

MEDICLINIC CITY HOSPITAL NORTH WING

WEEKLY PROGRESS REPORT NO.

Report Period 02.09.14 to 08.09.14

EMPLOYERPROJECT MANAGERCONSULTANTMAIN CONTRACTOR

CONTENTS

SECTION 1.0

SECTION 2.0

SECTION 3.0 EXECUTIVE SUMMARY

CONSTRUCTION PROGRESS

2 WEEKS LOOKAHEAD PROGRAMME

SECTION 4.0 PROGRESS S-CURVE

SECTION 5.0AREA OF CONCERN

SECTION 6.0HSE REPORT

SECTION 7.0 PROGRESS PHOTOGRAPHS

SECTION 1.0 EXECUTIVE SUMMARY

Project DetailsProject Name: Mediclinic City Hospital-North wing Project Location: Dubai Healthcare City.Configuration: (3B+G+6+RF)Employer: Mediclinic City HospitalProject Manager: Turner & TownsendConsultant: Hyder Consulting (ME) Ltd...Main Contractor: Kele Contracting L.L.C.

FinancialOriginal Contract Value: AED 135,980,000.Cumulative Claimed to Date: AED 5,815,969.82Cumulative Certified to Date: AED 3,814,676.74Cumulative Paid to Date: AED 1,161,076.92Applied Variations Value: AED 449,807.25Confirmed Variations Value: TBCRevised Contract Value: TBC

ProgrammeCommencement Date: 27-May-14Original Completion Date: 27-Sep-14 Original Duration: 489 DaysPlanned progress %: 8.09%Actual progress %: 1.03%Variance %: 7.06%Time Elapsed: 105 DaysTime Remaining: 384 Days EOT (Applied): 62 DaysEOT (Granted & approved): TBCRevised Completion Date: TBC

SECTION 2 CONSTRUCTION PROGRESSS.NoActivity DescriptionPlanned % completeActual % Complete

LIFTPIT AND SUMPPIT WORKS

1Excavation for lift pits and sump pits100%100%

2Anti-termite treatment & PCC for lift pits and sump pits100%50%

3Blockwork for footings100%50%

4Waterproofing for lift pits and sump pits100%0%

5Protection screed above waterproofing100%0%

6Reinforcement for lift pit foundation100%0%

7Concreting of lift pit and sump pits100%0%

MAIN RAFT

1Excavation for raft and carting away100%80%

2Pile cutting and removing100%90%

3Compaction for raft foundation100%50%

4Anti-termite treatment and PCC for raft100%50%

5Blockwork around pile caps100%50%

6Water proofing for raft100%0%

7Protection screed above waterproofing100%0%

8Rebar for footing and raft100%0%

SECTION 32 WEEKS LOOK AHEAD PROGRAM

SECTION 4PROGRESS S-CURVE

SECTION 5AREA OF CONCERNSS.NoDescriptionActionCommentsTime Delay

Critical Concern

Potential Concern

1

SECTION 7.0 HSE REPORT WEEKLY SAFETY SUMMARY REPORT

PROJECT NAME:MEDICLINIC CITY HOSPITAL NORTH WINGDATE:03 SEP 2014

REPORTING PERIOD:FROM: 31 AUG 2014 TO: 07 SEPT 2014

(1) MAN HOURS WORKED

MAN HOURS FOR THE PERIODYEAR TO DATEMAN HOURS FROM STARTOf PROJECT

Kele Employees334565598955959

Subcontractors81001328813288

Total415566924769247

(2) ACCIDENTS

S No.TYPE OF ACCIDENTFOR THE PERIODYEAR TO DATEFROM STARTOf PROJECT

1FIRST AID CASE (FAC)010303

2MEDICAL TREATMENT INJURY (MTI)000000

3LOST TIME INJURY (LTI)000000

4NEAR MISS010202

5MAJOR INJURIES000000

6FATALITIES000000

7ENVIRONMENTAL INCIDENTS000000

(3) MAN DAYS LOST

FOR THE PERIODYEAR TO DATEFROM STARTOf PROJECT

000000

(4A) SEVERITY RATE

FORMULA YEAR TO DATEFROM START OF PROJECT

TOTAL MAN DAYS LOST * 1000000TOTAL No. OF MAN HOURS WORKED0000

(4B) LOST TIME INCIDENT FREQUENCY RATE

FORMULA YEAR TO DATEFROM START OF PROJECT

NO OF LOST TIME INCIDENT* 1000000TOTAL No. OF MAN HOURS WORKED0000

(4C) TOTAL RECORDABLE INJURY FREQUENCY RATE

FORMULA YEAR TO DATEFROM START OF PROJECT

NO OF LTI + No. of MTI * 1000000TOTAL No. OF MAN HOURS WORKED0000

(5) OTHER ACTIVITIES

S No. ACTIVITYFOR THE MONTHYEAR TO DATEFROM STARTOf PROJECT

1SAFETY CORRECTIVE ACTION REPORTS (SCAR)053535

2SAFETY AWARDS010101

3SAFETY VIOLATION050606

4SAFETY AUDITS/ INSPECTIONS

A INTERNAL 000303

B - EXTERNAL030303

5TRAININGS:

A SAFETY INDUCTION25245245

B - TOOLBOX TALK051111

C - OTHERS000101

Prepared by : JULIUS SANORJO Approved by: LESLIE FAIRCHILD SAFETY OFFICER PROJECT MANAGER

SIGNATURE: SIGNATURE:

Photographic Documentation

Tool Box Talks:

Safety Performance award for the month of August:

Lifting Equipments:

1. Mobile Crane (off hired) 100 ton Mobile Crane see attached Certificate2. Wolffkran Tower Crane Commissioned 23rd of August 2014 see attached inpection receipt and time sheet

Lifting gears and Accessories

1. Two 5-ton lifting belts (Claymore Certified)2. Two 3-ton lifting belts (new) no 3rd party certificate3. K 370 & K 369 see attached Certificates Tower Crane commissioned 23/08/2014

Main Site Access & Egress

SECTION 7.0 PROGRESS PHOTOGRAPHS