DURING DEMOLITION WORK, ALL MECHANICAL SYSTEMS AND BUILDING SERVICES SERVING OCCUPIED AREAS. SHALL BE MAINTAINED OPERATIONAL. WHERE SYSTEM OR SERVICE INTERRUPTIONS ARE REQUIRED, COORDINATE AFTER HOUR ACCESS REQUIREMENTS AND SECURITY EXECUTE WORK WITH CONSTRUCTION MANAGER. INSULATE NEW DUCT AND PIPE CAPS. SUPPLY AIR DUCTWORK AND PIPING NOT SHOWN HATCHED IS TO BE RETAINED, ANY DAMAGE TO EXISTING INSULATION AND DUCTS TO BE REPAIRED TO MATCH EXISTING. DEMOLITION OF EXTERIOR AND INTERIOR WALLS, ROOF CEILING AND FLOORS TO BE SEQUENCED WITH THE OWNER. IN AREAS WHERE ADJACENT OCCUPANCIES ARE NOT IN THE DEMOLITION AREA BUT AFFECTED BY NOISE OF DEMOLITION, OR WHERE TRADE REQUIRES ACCESS TO EXISTING OCCUPIED SPACES, CONTRACTOR SHALL COORDINATE TIMES OF WORK THROUGH THE OWNER. DEMOLISHED WORK SHALL INCLUDE FOR TEMPORARY AND PERMANENT WORK (I.E. SERVICE DIMENSIONS) REQUIRED TO KEEP ACTIVE PREMISES IN OPERATION. COORDINATE TIMES, ACCESS, TEMPORARY HOARDING, TEMPORARY SCAFFOLDING, TOOL/LIGHT POWER REQUIREMENTS AND OTHER MISCELLANEOUS ITEMS NEEDED TO COMPLETE WORK WITH GENERAL CONTRACTOR IN OCCUPIED AREA AT NIGHT OR IN ACCORDANCE WITH THE OWNER APPROVED SCHEDULE. INCLUDE FOR DISPOSAL (FROM SITE) OF ALL REMOVED EQUIPMENT AND SERVICES, DUCTWORK, PIPING, PLUMBING, ETC. INCLUDING INSULATION AND HANGERS. MECHANICAL TRADES BIDDING DEMOLITION WORK SHALL ALLOW FOR A FULL DAY ON SITE TO REVIEW EXISTING MECHANICAL SERVICES AND EQUIPMENT IN DEMOLITION AND RENOVATED PATCH AND MAKE GOOD (TO BASE BUILDING STANDARDS) MECHANICAL COMPONENTS AND FINISHES DAMAGED DURING THE RENOVATION. PROVIDE INSULATED CAPPED CURBS EQUAL TO OR BETTER THAN ROOF R-VALUE FOR FANS, GOOSE NECK OPENINGS AND VENTS BEING ADDED AND REMOVED. GENERAL DEMOLITION NOTES: 6. 4. 5. 3. 2. 1. AREAS. ACCESS WILL BE GIVEN TO ROOF AND EXISTING MECHANICAL AND ELECTRICAL ROOMS AS REQUIRED. SEE TENDER FORM FOR DATE OF MANDATORY SITE MEETING. 7. 8. MECHANICAL LEGEND LIST OF ABBREVIATIONS AND CONTROLS COMPLETE WITH EXHAUST AIR E/A C/W NOT TO SCALE NTS OUTSIDE AIR O/A RETURN AIR R/A RAIN WATER LEADER RWL SUPPLY AIR S/A TOP OF DUCT T.O.D. TOP OF PIPE T.O.P. UNDERSIDE OF DUCT U.O.D. UNDERSIDE OF PIPE U.O.P. UNDERSIDE U/S ABOVE FINISHED FLOOR AFF FROM ABOVE, TO ABOVE F/A, T/A FROM BELOW, TO BELOW F/B, T/B DOWN DN FIRE RESISTANCE RATED FRR UNLESS NOTED OTHERWISE U.N.O. CONNECT TO EXISTING CTE PLUMBING FIXTURE TAG SANITARY DRAIN STORM DRAIN VENT PIPE DOMESTIC COLD WATER DOMESTIC HOT WATER DOMESTIC HOT WATER RECIRC FLOOR/ ROOF/ HUB/ AREA DRAIN CLEAN OUT CO ? ? RETURN LINE EXISTING SERVICE SUPPLY LINE REMOVED SERVICE RELOCATED ITEM LIST OF SYMBOLS AND SERVICES REMOVE ITEM XXXS STW SAN V XXXR P & T RELIEF VALVE SHUT OFF VALVE CHECK VALVE UNION OR FLANGE STRAINER -Y OR BASKET AUTOMATIC AIR VENT PIPE ELBOW RISER / DROP CAP OR PLUG BALANCING VALVE PLUG VALVE 3-WAY CONTROL VALVE PRESSURE REDUCING VALVE AUTOFLOW CONTROL VALVE PRESSURE GAUGE THERMOMETER FLEXIBLE CONNECTION REDUCED PRESSURE BACKFLOW ASSEMBLY PUMP PIPE ANCHOR PIPE GUIDE GLOBE VALVE SUPERVISED VALVE 2-WAY CONTROL VALVE M S DOUBLE CHECK VALVE ASSEMBLY M STACK UP/ DOWN PIPE TEE DOWN AAV RPBA DCVA EQUIPMENT TAG BALANCING DAMPER SUPPLY OUTLET RETURN OR EXHAUST INLET STANDARD BRANCH - DUCTWORK S/A OR O/A DUCT TO OR FROM ABOVE S/A OR O/A DUCT TO OR FROM BELOW R/A OR E/A DUCT TO OR FROM ABOVE R/A OR E/A DUCT TO OR FROM BELOW BD ROUND DUCT DROP ROUND DUCT RISER SINGLE LINE BRANCH HEATING/COOLING COIL +/- T 604.687.1800 www.integralgroup.com Vancouver BC Canada V6C 1S4 Suite 180 - 200 Granville Street Project Reference No: 151366.002 DWG. NO. TITLE SCALE M-01 TITLE SHEET NTS M-02 PLANT ROOM PLAN - DEMO 1/4"=1'-0" M-03 PLANT ROOM PLAN - NEW 1/4"=1'-0" M-04 HYDRONIC SCHEMATIC - DEMO NTS M-05 HYDRONIC SCHEMATIC - NEW NTS M-06 SCHEDULES NTS M-07 DETAILS NTS

MECHANICAL LEGEND LIST OF ABBREVIATIONS AND ......Vancouver BC Canada V6C 1S4 Suite 180 - 200 Granville Street Project Reference No: 151366.002 DWG. NO. TITLE SCALE M-01 TITLE SHEET

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • DURING DEMOLITION WORK, ALL MECHANICAL SYSTEMS AND BUILDING SERVICES SERVING

    OCCUPIED AREAS. SHALL BE MAINTAINED OPERATIONAL. WHERE SYSTEM OR SERVICE

    INTERRUPTIONS ARE REQUIRED, COORDINATE AFTER HOUR ACCESS REQUIREMENTS AND

    SECURITY EXECUTE WORK WITH CONSTRUCTION MANAGER.

    INSULATE NEW DUCT AND PIPE CAPS.

    SUPPLY AIR DUCTWORK AND PIPING NOT SHOWN HATCHED IS TO BE RETAINED, ANY DAMAGE

    TO EXISTING INSULATION AND DUCTS TO BE REPAIRED TO MATCH EXISTING.

    DEMOLITION OF EXTERIOR AND INTERIOR WALLS, ROOF CEILING AND FLOORS TO BE

    SEQUENCED WITH THE OWNER. IN AREAS WHERE ADJACENT OCCUPANCIES ARE

    NOT IN THE DEMOLITION AREA BUT AFFECTED BY NOISE OF DEMOLITION, OR WHERE TRADE REQUIRES ACCESS TO EXISTING OCCUPIED SPACES, CONTRACTOR SHALL COORDINATE TIMES OF

    WORK THROUGH THE OWNER.

    DEMOLISHED WORK SHALL INCLUDE FOR TEMPORARY AND PERMANENT WORK (I.E. SERVICE DIMENSIONS) REQUIRED TO KEEP ACTIVE PREMISES IN OPERATION. COORDINATE TIMES,

    ACCESS, TEMPORARY HOARDING, TEMPORARY SCAFFOLDING, TOOL/LIGHT POWER REQUIREMENTS AND

    OTHER MISCELLANEOUS ITEMS NEEDED TO COMPLETE WORK WITH GENERAL CONTRACTOR

    IN OCCUPIED AREA AT NIGHT OR IN ACCORDANCE WITH THE OWNER APPROVED SCHEDULE.

    INCLUDE FOR DISPOSAL (FROM SITE) OF ALL REMOVED EQUIPMENT AND SERVICES,

    DUCTWORK, PIPING, PLUMBING, ETC. INCLUDING INSULATION AND HANGERS.

    MECHANICAL TRADES BIDDING DEMOLITION WORK SHALL ALLOW FOR A FULL DAY ON SITE TO REVIEW EXISTING MECHANICAL SERVICES AND EQUIPMENT IN DEMOLITION AND RENOVATED

    PATCH AND MAKE GOOD (TO BASE BUILDING STANDARDS) MECHANICAL COMPONENTS AND

    FINISHES DAMAGED DURING THE RENOVATION. PROVIDE INSULATED CAPPED CURBS EQUAL

    TO OR BETTER THAN ROOF R-VALUE FOR FANS, GOOSE NECK OPENINGS AND VENTS BEING

    ADDED AND REMOVED.

    GENERAL DEMOLITION NOTES:

    6.

    4.

    5.

    3.

    2.

    1.

    AREAS. ACCESS WILL BE GIVEN TO ROOF AND EXISTING MECHANICAL AND ELECTRICAL ROOMS

    AS REQUIRED. SEE TENDER FORM FOR DATE OF MANDATORY SITE MEETING.

    7.

    8.

    MECHANICAL LEGEND

    LIST OF ABBREVIATIONS AND CONTROLS

    COMPLETE WITH

    EXHAUST AIRE/A

    C/W

    NOT TO SCALENTS

    OUTSIDE AIRO/A

    RETURN AIRR/A

    RAIN WATER LEADERRWL

    SUPPLY AIRS/A

    TOP OF DUCTT.O.D.

    TOP OF PIPET.O.P.

    UNDERSIDE OF DUCTU.O.D.

    UNDERSIDE OF PIPEU.O.P.

    UNDERSIDEU/S

    ABOVE FINISHED FLOORAFF

    FROM ABOVE, TO ABOVEF/A, T/A

    FROM BELOW, TO BELOWF/B, T/B

    DOWNDN

    FIRE RESISTANCE RATEDFRR

    UNLESS NOTED OTHERWISEU.N.O.

    CONNECT TO EXISTINGCTE

    PLUMBING FIXTURE TAG

    SANITARY DRAIN

    STORM DRAIN

    VENT PIPE

    DOMESTIC COLD WATER

    DOMESTIC HOT WATER

    DOMESTIC HOT WATER RECIRC

    FLOOR/ ROOF/ HUB/ AREA DRAIN

    CLEAN OUT CO

    ?

    ?

    RETURN LINE

    EXISTING SERVICE

    SUPPLY LINE

    REMOVED SERVICE

    RELOCATED ITEM

    LIST OF SYMBOLS AND SERVICES

    REMOVE ITEM

    XXXS

    STW

    SAN

    V

    XXXR

    P & T RELIEF VALVE

    SHUT OFF VALVE

    CHECK VALVE

    UNION OR FLANGE

    STRAINER -Y OR BASKET

    AUTOMATIC AIR VENT

    PIPE ELBOW RISER / DROP

    CAP OR PLUG

    BALANCING VALVE

    PLUG VALVE

    3-WAY CONTROL VALVE PRESSURE REDUCING VALVE

    AUTOFLOW CONTROL VALVE

    PRESSURE GAUGE

    THERMOMETER

    FLEXIBLE CONNECTION

    REDUCED PRESSURE BACKFLOWASSEMBLY

    PUMP

    PIPE ANCHOR

    PIPE GUIDE

    GLOBE VALVE

    SUPERVISED VALVE

    2-WAY CONTROL VALVEM

    S

    DOUBLE CHECK VALVE ASSEMBLY

    M

    STACK UP/ DOWN

    PIPE TEE DOWN

    AAV

    RPBADCVA

    EQUIPMENT TAG

    BALANCING DAMPER

    SUPPLY OUTLET

    RETURN OR EXHAUST INLET

    STANDARD BRANCH

    -

    DUCTWORK

    S/A OR O/A DUCTTO OR FROM ABOVE

    S/A OR O/A DUCTTO OR FROM BELOW

    R/A OR E/A DUCTTO OR FROM ABOVE

    R/A OR E/A DUCTTO OR FROM BELOW

    BD

    ROUND DUCT DROP

    ROUND DUCT RISERSINGLE LINE BRANCH

    HEATING/COOLING COIL +/-

    T 604.687.1800www.integralgroup.com

    Vancouver BC Canada V6C 1S4Suite 180 - 200 Granville Street

    Project Reference No: 151366.002

    DWG. NO. TITLE SCALE

    M-01 TITLE SHEET NTS

    M-02 PLANT ROOM PLAN - DEMO 1/4"=1'-0"

    M-03 PLANT ROOM PLAN - NEW 1/4"=1'-0"

    M-04 HYDRONIC SCHEMATIC - DEMO NTS

    M-05 HYDRONIC SCHEMATIC - NEW NTS

    M-06 SCHEDULES NTS

    M-07 DETAILS NTS

  • XDHWT-1

    XP1-3

    XP1-4

    52"x20" S/A DUCT

    XP2-2

    XP2-1

    XP1-2

    XB1-1

    XB1-3

    RPBP

    XDHWT-1

    LADDER TO

    MEZZANINE

    52"x20" S/A DUCT

    XF-1

    XAHU-1

    1

    2

    3

    4

    XET2-3

    XET2-4

    5

    6

    56

    7

    56

    8

    10

    9

    11

    EXISTING 25" x 14"

    COMBUSTION AIR

    DUCT TO REMAIN

    EXISTING R/A

    DUCT TO REMAIN

    EXISTING E/A

    DUCT TO REMAIN

    EXISTING 25" x 14"

    COMBUSTION AIR

    DUCT TO REMAIN

    EXISTING R/A

    DUCT TO REMAIN

    EXISTING E/A

    DUCT TO REMAIN

    M

    8

    8

    1

    DEMOLITION NOTES:

    REMOVE EXISTING GAS FIRED BOILER XB1-1 AND ASSOCIATED HEATING

    SUPPLY AND RETURN PIPING, PUMPS AND VALVES AS SHOWN. CAP AND

    MAKE GOOD FOR RECONNECTION.

    2

    3 REMOVE EXISTING GAS PIPING GAS SHOWN. CAP AND MAKE GOOD

    FOR RECONNECTION.

    4

    REMOVE EXISTING GAS FIRED BOILER XB1-3 AND ASSOCIATED HEATING

    SUPPLY AND RETURN PIPING, PUMPS AND VALVES AS SHOWN. CAP AND

    MAKE GOOD FOR RECONNECTION.

    5 COMPLETELY REMOVE EXISTING XB1-1 FLUE UP THROUGH ROOF.

    CONTRACTOR TO PATCH AND MAKE GOOD ALL EXISTING BASE

    BUILDING WALLS AND ROOF TO MATCH BASE BUILDING AS REQUIRED

    FOR DEMOLITION OF DUCTWORK.

    6 COMPLETELY REMOVE EXISTING XB1-3 AND DHWT-1 & 2 FLUE UP

    THROUGH ROOF. CONTRACTOR TO PATCH AND MAKE GOOD ALL

    EXISTING BASE BUILDING WALLS AND ROOF TO MATCH BASE

    BUILDING AS REQUIRED FOR DEMOLITION OF DUCTWORK.

    7 RELOCATE EXISTING AIR COMPRESSOR AND ALL ASSOCIATED

    PIPING/ELECTRICAL AS NEEDED TO FIT NEW BOILER LAYOUT.

    8 REMOVE AND REPLACE EXISTING RPBP WITH NEW.

    9 COMPLETELY REMOVE EXISTING AHU-1. CAP AND MAKE GOOD EXISTING

    DUCTWORK CONNECTIONS AND MAKE GOOD FOR RE-CONNECTION.

    CONTRACTOR TO COORDINATE DOWN TIME OF AHU WITH CLIENT ON

    SITE AND PROVIDE TEMPORARY VENTILATION AS REQUIRED.

    CONTRACTOR TO REVISE ELECTRICAL DISCONNECT CONNECTION TO

    AHU-1 AS REQUIRED.

    10 CUT AND CAP EXISTING HEATING WATER SUPPLY AND RETURN PIPING

    AND MAKE GOOD FOR RECONNECTION.

    COMPLETELY REMOVE EXISTING 3-WAY VALVE AND REPLACE WITH

    NEW. 3-WAY VALVE TO BE WIRED TO EXISTING DDC. UPDATE ALL BMS

    GRAPHICS AND CONTROLS AS REQUIRED FOR CONTROL VALVES.

    COMPLETELY REMOVE EXISTING XF-1. CAP AND MAKE GOOD EXISTING

    DUCTWORK CONNECTIONS AND MAKE GOOD FOR RE-CONNECTION.

    CONTRACTOR TO COORDINATE DOWN TIME OF AHU WITH CLIENT ON

    SITE AND PROVIDE TEMPORARY VENTILATION AS REQUIRED.

    CONTRACTOR TO REVISE ELECTRICAL DISCONNECT CONNECTION TO F-1

    AS REQUIRED.

    11

    T 604.687.1800www.integralgroup.com

    Vancouver BC Canada V6C 1S4Suite 180 - 200 Granville Street

    Project Reference No: 151366.002

    21 80 4

    SCALE: 14" = 1'-0"

    PLANT ROOM GROUND FLOOR - DEMO21 80 4

    SCALE: 14" = 1'-0"

    PLANT ROOM MEZZANINE - DEMO

  • XDHWT-2

    XDHWT-1

    LADDER TOMEZZANINE

    AHU-1

    P1-3

    P1-4

    M

    M

    S

    P1-2

    B-1

    BP-1

    B-2

    BP-2

    B-5 BP-5

    P2-1

    P2-2

    2

    5

    5

    5

    5

    B-4 BP-4 5

    B-3 BP-3 5

    55

    5

    5

    VERTICAL LOW

    LOSS HEADER

    4

    ET2-3

    1

    1

    1

    1

    1

    6

    6

    6

    66

    HWS T/B

    TYP.

    2

    TYP.

    2

    TYP.

    5 7

    EXISTING R/A

    DUCT

    EXISTING E/A

    DUCT

    EXISTING 25" x 14"

    COMBUSTION AIR

    DUCT

    3

    8

    XDHWT-2

    52"x20" S/A DUCT

    XDHWT-1

    LADDER TO

    MEZZANINE

    52"x20" S/A DUCT

    F-1

    AHU-1

    2@ NEW 8"ø DHWT FLUE UP THROUGH ROOF.

    ENSURE TERMINATIONS AND MINIMUM DISTANCES

    FROM FLUE EXHAUST ARE INSTALLED AS PER CSA

    AND MANUFACTURERS REQUIREMENTS

    2@ NEW 8"ø BOILER FLUES UP THROUGH ROOF.

    ENSURE TERMINATIONS AND MINIMUM DISTANCES

    FROM FLUE EXHAUST ARE INSTALLED AS PER CSA

    AND MANUFACTURERS REQUIREMENTS

    8

    8

    5

    2@ NEW 8"ø DHWT FLUE UP THROUGH ROOF.

    ENSURE TERMINATIONS AND MINIMUM DISTANCES

    FROM FLUE EXHAUST ARE INSTALLED AS PER CSA

    AND MANUFACTURERS REQUIREMENTS

    2@ NEW 8"ø BOILER FLUES UP THROUGH ROOF.

    ENSURE TERMINATIONS AND MINIMUM DISTANCES

    FROM FLUE EXHAUST ARE INSTALLED AS PER CSA

    AND MANUFACTURERS REQUIREMENTS

    87

    EXISTING R/A

    DUCT

    EXISTING E/A

    DUCT

    EXISTING 25" x 14"

    COMBUSTION AIR

    DUCT

    EXISTING R/A

    DUCT

    EXISTING E/A

    DUCT

    EXISTING 25" x 14"

    COMBUSTION AIR

    DUCT

    10

    M

    11

    9

    1

    CONSTRUCTION NOTES:

    CONNECT NEW PUMP AND ASSOCIATED PIPING/VALVES TO EXISTING

    PIPING. ENSURE ALL NEW PUMP TRIM AND VALVES ARE INSTALLED AS

    SHOWN ON MECHANICAL DRAWINGS. RE-BALANCE NEW PUMP

    2 CONNECT NEW PIPING TO EXISTING.

    3 CONNECT GAS TO EXISTING. PIPE NEW 12"ø GAS PIPE TO EACH BOILERCOMPLETE WITH SHUTOFF VALVE AND REGULATOR.

    4 PROVIDE NEW GAS SOLENOID WIRED TO EMERGENCY GAS SHUTOFF

    BUTTON TO DE-ACTIVATE BOILERS AND GAS SUPPLY TO BOILERS.

    5 ALL NEW ELECTRICAL WORK IS THE RESPONSIBILITY OF THE

    CONTRACTOR TO DESIGN AND APPLY FOR THE REQUIRED PERMITS.

    6 MODIFY EXISTING BOILER HOUSE KEEPING PADS AS REQUIRED TO FIT

    NEW BOILERS.

    7 INSTALL NEW AHU-1 AS PER MECHANICAL SCHEDULE AND

    SPECIFICATION. ADJUST EXISTING DUCTWORK AND HYDRONIC PIPING

    TO SUIT NEW AHU-1 CONFIGURATION. CONTRACTOR TO REVISE WORKS

    RELATED TO ELECTRICAL CONNECTION TO AHU-2 AS REQUIERD

    INCLUDING PERMITS, COORDINATION AND INSTALLATION.

    8 CONNECT NEW DUCTWORK TO MATCH EXISTING.

    9 MODIFY EXISTING CONCRETE HOUSEKEEPING PAD TO SUIT NEW

    CONFIGURATION OF AHU-1.

    10 INSTALL NEW F-1 AS PER MECHANICAL SCHEDULE AND SPECIFICATION.

    ADJUST EXISTING DUCTWORK TO SUIT NEW F-1 CONFIGURATION.

    CONTRACTOR TO REVISE WORKS RELATED TO ELECTRICAL

    CONNECTION TO F-1 AS REQUIRED INCLUDING PERMITS, COORDINATION

    AND INSTALLATION.

    11 PROVIDE NEW ACTUATORS FOR OUTDOOR AIR, EXHAUST AIR AND

    MIXING AIR DAMPERS.

    T 604.687.1800www.integralgroup.com

    Vancouver BC Canada V6C 1S4Suite 180 - 200 Granville Street

    Project Reference No: 151366.002

    21 80 4

    SCALE: 14" = 1'-0"

    HYDRONIC PLANT ROOM GROUND FLOOR - NEW21 80 4

    SCALE: 14" = 1'-0"

    HYDRONIC PLANT ROOM MEZZANINE - NEW

    21 80 4

    SCALE: 14" = 1'-0"

    HVAC PLANT ROOM GROUND FLOOR - NEW21 80 4

    SCALE: 14" = 1'-0"

    HVAC PLANT ROOM MEZZANINE - NEW

  • LWCO

    XB1-1

    XP1-3

    XP1-4

    CHEMICAL POT

    FEEDER

    4"ø HWS

    4"ø HWR

    XP1-2

    LWCO

    XB1-3

    CHEMICAL POT

    FEEDER

    XP2-2

    XP2-12"ø NG

    3"ø HWS

    3"ø HWR

    2-12"ø NG 2"ø NG TO

    DHWT-1 & 2

    HWS/R

    TO WHIRLPOOL

    RPBP

    HWS/R

    DOWN

    HWS/R

    DOWN

    HWS/R

    UP

    HWS/R

    DOWN

    HWS/R

    UP

    12 3

    DEMOLITION NOTES:

    2 REMOVE EXISTING GAS FIRED BOILER XB1-3 AND ALL ASSOCIATED

    HEATING PIPING, PUMP, AND VALVES SERVING EXISTING DOMESTIC

    HOT WATER TANK. CAP AND MAKE GOOD FOR RECONNECTION.

    3

    1 REMOVE EXISTING GAS FIRED BOILER XB1-1 AND ALL ASSOCIATED

    HEATING PIPING, PUMP, AND VALVES SERVING EXISTING DOMESTIC

    HOT WATER TANK. CAP AND MAKE GOOD FOR RECONNECTION.

    INSTALL NEW CIRCUIT BALANCING VALVE AND HAVE BALANCING

    CONTRACTOR CONFIRM FLOWRATE PRIOR TO DEMOLITION OF

    MECHANICAL ROOM.

    T 604.687.1800www.integralgroup.com

    Vancouver BC Canada V6C 1S4Suite 180 - 200 Granville Street

    Project Reference No: 151366.002

    SCALE: N.T.S.

    HYDRONIC SCHEMATIC - DEMO

  • S R S R S R

    T

    T

    B-3 B-4 B-5

    BP-3 BP-4 BP-5

    T

    T

    T

    AIR/DIRT

    SEPARATOR

    S R

    B-2

    S R

    B-1

    BP-2BP-1

    P2-2

    P1-2

    P2-1

    XHWR

    XHWS

    XHWR

    XHWS

    XHWR

    XHWS

    XHWR

    XHWS

    EX

    PA

    NS

    ION

    TA

    NK

    2-12" HWS/R CAPPED FOR FUTURE DHWTCONNECTION.

    P1-3

    P1-4

    HWR

    HWS

    HWR

    HWS

    HWR

    HWS

    CHEMICAL

    POT FEEDER

    FIL

    TE

    R

    TEST COUPON

    FLOW

    INDICATOR

    CORROSION

    3

    3M

    M

    S

    G

    4

    G G GG

    3 3 3 3 3

    2

    2

    2

    2

    5

    1

    1

    1

    1

    1

    2

    TO EXISTING DHWT-1 & 2

    2

    4"ø HWR HEADER

    4"ø HWS HEADER

    2-12"ø HWS(49.5 GPM)

    4"ø HWS HEADER

    (247.5 GPM)

    4"ø HWR HEADER

    (247.5 GPM)

    6

    RPBP

    2-12"ø HWS(49.5 GPM)

    2-12"ø HWS(49.5 GPM)

    2-12"ø HWS(49.5 GPM)

    2-12"ø HWS(49.5 GPM)

    180°F

    160°F

    1

    CONSTRUCTION NOTES:

    CONNECT NEW PUMP AND ASSOCIATED PIPING/VALVES TO EXISTING

    PIPING. ENSURE ALL NEW PUMP TRIM AND VALVES ARE INSTALLED AS

    SHOWN ON MECHANICAL DRAWINGS. RE-BALANCE EXISTING PUMP TO

    EXISTING FLOW NOTED ON MECHANICAL PUMP SCHEDULE. UPDATE ALL

    BMS GRAPHICS AND CONTROLS AS REQUIRED FOR NEW PUMPS.

    2 CONNECT NEW PIPING TO EXISTING AND MATCH EXISTING PIPE SIZE.

    CONTRACTOR TO CONFIRM EXACT PIPE SIZE ON SITE.

    3 CONNECT GAS TO EXISTING AND MATCH EXISTING PIPE SIZE. PIPE NEW1

    2"ø GAS PIPE TO EACH BOILER COMPLETE WITH SHUTOFF VALVE ANDREGULATOR.

    4 PROVIDE NEW GAS SOLENOID WIRED TO EMERGENCY GAS SHUTOFF

    BUTTON TO DE-ACTIVATE BOILERS AND GAS SUPPLY TO BOILERS.

    5 NEW VIESSMANN LOW LOSS HEADER MODEL 400/200.

    6 PIPE NEW RPBP DRAIN, C/W AIR GAP TO EXISTING FLOOR DRAIN.

    T 604.687.1800www.integralgroup.com

    Vancouver BC Canada V6C 1S4Suite 180 - 200 Granville Street

    Project Reference No: 151366.002

    SCALE: N.T.S.

    HYDRONIC SCHEMATIC - NEW

  • FAN SCHEDULE

    Tag No. Description

    Design Details Electrical Details Motor Details

    NotesDesign

    SupplyVolume

    (cfm)

    Select

    SupplyVolume

    (cfm)

    Resistance

    ("wg)

    SelectExternal AirResistance

    ("wg)

    ElectricalVoltage

    (V)

    Electrical

    SupplyPhase

    (1 or 3)

    Frequency

    (Hz)

    AbsorbedPower

    (BHP)

    MotorRating

    (BHP)

    Motor

    Starting

    Method

    TotalMinimum

    Efficiency

    (%)

    Motor

    Speed

    (RPM)

    FanType

    Manufacturer Model

    F-1 AHU-1 Return Fan 4625 5088 0.40 0.48 230 3 60 0.65 1.50 INV 60 1160 Inline Axial Twin City TD30E8 1, 2, 3

    Notes

    Unit to come complete with:

    1 - Vibration Isolators

    2 - VFD

    3 - Controlled by DDC

    BOILER B-1, B-2, B-3, B-4, B-5

    Boiler Information

    Location Mechanical Room

    Manufacturer Viessmann

    Model Vitodens B2HA 150

    Type Wall Mounted Gas Condensing Boiler

    Design Information

    Input Gas Requirement MBH 530

    Boiler Output Capacity MBH 495

    Thermal Efficiency (%) 93.4

    Water Flow (gpm) 24.8

    Maximum Water Pressure Drop (ft) 8.00

    Maximum Operating Pressure (psig) 80.0

    Operating Weight (lbs) 332

    Burner stages Fully Modulating

    Fuel type Natural Gas

    Boiler Dimensions (WxDxH) (in) 24x28x45

    Boiler Connections

    Boiler Supply Connection (in) 2

    Boiler Return Connection (in) 2

    Safety Valve Connection (in) 3/4

    Boiler Drain (in) 3/4

    Gas connection (in) 1

    Electrical Requirements

    Burner Motor MOCP 15 Amps

    Electrical Requirements 120/1/60

    Notes

    1. CPVC flue gas system installed to manufacturer's recommnedations. Flue material is to be certified together with boiler as a constructed

    unit.

    2. Complete with boiler control with cascade and/or DDC interface.

    3. Complete with Viessmann acid neaturalization system.

    4. Multiple boiler installation requires detached boiler native cascade control (Vitotronic 300-K MW2C Cascade Control)

    5. Vitotronic 200 HO1B Controller

    6. Separate 120V/1PH required for boiler and controllers.

    7. Viessmann boiler mounting bracket and frame.

    8. Contractor resopnsible to register boiler with BC Safety Authority prior to substantial completion.

    AHU-1

    Supply Air Fan

    Manufacturer Engineered Air

    Model LM8/C/V

    Design Air Volume (cfm) 8050 Fan Speed * (RPM) 1750

    Ductwork Leakage (%) 10 Absorbed Power * (BHP) 4.6

    Total AHU Volume (cfm) 8855 Motor Rating * (HP) 5.0

    Design External Static ("wg) 1.02 Motor Starting Method INV

    Static Pressure Spare Capacity (%) 21 Full Load Current * (Amps)

    Total External Static ("wg) 1.23 Starting Current * (Amps)

    AHU Internal Static ("wg) 0.90 Electrical Supply

    Total Static ("wg) 2.13

    Inverter Driven (Yes/No) Yes

    Fan Type Centrifugal

    Total Fan Efficiency * (%) 65

    Mixing Section

    Fresh Air Volume (cfm) 3763 Outside Winter Temperature DB (°F) 15.8

    Return Air Volume (cfm) 5092 Room Temperature DB (°F) 71.6

    Percentqage of Air Recirculated (%) 57.5 Room Temperature WB (°F) 60.0

    Mixed Winter Temperature DB (°F) 47.9

    Supply Filtration

    Panel Filter Grade MERV 8

    Heating Coil

    Air On Coil Temperature (°F) 47.9 Flow Water Temperature (°F) 180.0

    Air Off Coil Temperature (°F) 76.0 Return Water Temperature (°F) 160.0

    Duty (Btuh) 268875 Glycol Content (%) 0

    Specific Heat Capacity Solution (BTU/lbF) 1.00

    Water Flow Rate (gpm) 26.9

    Supply Fan Sound Power Levels Total 63Hz 125Hz 250Hz 500Hz 1kHz 2kHz 4kHz 8kHz

    Case Breakout * (dB(A))

    Intake * (dB(A))

    Discharge * (dB(A))

    Notes

    Unit to come complete with:

    1) Unit to be variable frequency drive (VFD) compatible. VFD to be supplied by mechanical contractor.

    2) Filter compartment, Heating Coil and Fan Compartment. Mixing section of existing unit to be reused.

    Expansion Tank Schedule

    Bladder Expansion Tank Information ET2-1

    Location Mechanical Room

    Service Heating Water

    Manufacturer Amtrol

    Model Extrol

    Orientation Horizontal

    Material Steel

    Working Pressure (psi) 30.0

    Maximum Working Pressure (psi) 125.0

    Tank Volume (gal) 132

    Dimensions (øxL) (Inch) 24x79

    Acceptance Volume (gal) 132

    Weight (lbs)

    Note:

    1) All Tanks should be Bladder type, designed and constructed as per ASME Section V111, Division-1

    Standards.

    PUMP SCHEDULE

    TAG No. Description Location

    Electrical Details Motor Details

    NotesDesign

    Capacity

    (gpm)

    Selected

    Capacity

    (gpm)

    Design

    Head

    (ft w.g.)

    Selected

    Head

    (ft w.g.)

    Electrical

    Voltage

    (V)

    Electrical

    Supply

    Phase

    (1 or 3)

    Frequency

    (Hz)

    Motor

    Starting

    Method

    Total

    Minimum

    Efficiency

    (%)

    Absorbed

    Power

    (BHP)

    Motor

    Rating

    (BHP)

    Motor

    Speed

    (RPM)

    Manufacturer Model

    BP-1 B-1 Boiler Pump Mechanical Room 49.5 54.5 23.6 28.6 208 1 60 INV 60 0.7 0.3 1750 Grundfos Magna3 1, 2

    BP-2 B-2 Boiler Pump Mechanical Room 49.5 54.5 23.6 28.6 208 1 60 INV 60 0.7 0.3 1750 Grundfos Magna3 1, 2

    BP-3 B-3 Boiler Pump Mechanical Room 49.5 54.5 23.6 28.6 208 1 60 INV 60 0.7 0.3 1750 Grundfos Magna3 1, 2

    BP-4 B-4 Boiler Pump Mechanical Room 49.5 54.5 23.6 28.6 208 1 60 INV 60 0.7 0.3 1750 Grundfos Magna3 1, 2

    BP-5 B-5 Boiler Pump Mechanical Room 49.5 54.5 23.6 28.6 208 1 60 INV 60 0.7 0.3 1750 Grundfos Magna3 1, 2

    P1-2 Secondary Heating Pump Mechanical Room 49.5 54.5 28.5 34.5 208 1 60 INV 60 0.8 0.5 1750 Grundfos Magna3 1, 2, 4

    P1-3 Secondary Heating Pump Mechanical Room 91.0 100.1 60.0 72.6 208 1 60 INV 60 3.1 3.0 1750 Grundfos Magna3 1, 2

    P1-4 Secondary Heating Pump Mechanical Room 91.0 100.1 60.0 72.6 208 1 60 INV 60 3.1 3.0 1750 Grundfos Magna3 1, 2

    P2-1 Secondary Heating Pump Mechanical Room 8.0 8.8 29.5 35.7 208 1 60 INV 60 0.1 0.3 1750 Grundfos Magna3 1, 2, 3

    P2-2 Secondary Heating Pump Mechanical Room 80.0 88.0 20.0 24.2 208 1 60 INV 60 0.9 1.0 1750 Grundfos Magna3 1, 2

    Notes

    1) Constant speed pumping control c/w BACNET output/input.

    2) Complete with Magna Integrated Variable Speed Drive (VFD)

    3) Existing flow rate not available. Contractor install circuit balancing valve in system and have balancing contractor confirm flow and pressures of existing pump prior to demolition. Contractor to carry costs for supply and installation of a new Grundfos Magna Pump as specified.

    4) Existing flow rate not available. Contractor engage balancing contractor prior to demolition to confirm flows and pressures of existing pump. Existing Pump model is B&G Series 60 1.25 x 5.25. Contractor to carry costs for that supply and installation of a new Grundfos Magna pump that is equipavelent to the existing pump.

    T 604.687.1800www.integralgroup.com

    Vancouver BC Canada V6C 1S4Suite 180 - 200 Granville Street

    Project Reference No: 151366.002

  • T 604.687.1800www.integralgroup.com

    Vancouver BC Canada V6C 1S4Suite 180 - 200 Granville Street

    Project Reference No: 151366.002

    NOTES:

    P

    VERTICAL IN LINE PUMP INSTALLATION

    SUPPORT FOOT BOLTED

    TO PUMP FLANGE

    SUPPORT FOOT

    CONSTRUCTED FROM 10mm

    [3/8"] THICK STEEL PLATE.

    VIBRATION ISOLATORS

    AS SPECIFIED.

    SEISMIC SPRING

    ISOLATORS

    PIPE SIZE AS

    SHOWN ON PLAN

    GATE VALVE

    COMBINATION BALANCING/

    CHECK VALVE OR LONG

    SWEEP ELBOW &

    INDIVIDUAL CHECK W/

    BALANCE VALVES.

    MAX. 250mm [10"]

    100mm [4"]CONC. PAD

    VIBRATION ISOLATORS

    (SEE SPECIFICATION)

    SUCTION GUIDE

    STRAINER

    GATE VALVE

    SUPPORT FOOT TO BE BOLTED TO THE FLOOR SLAB, THROUGH THE

    CONC. PAD USING NEOPRENE WASHERS AND BUSHINGS ON THE BOLTS

    (MIN. 2 BOLTS).

    NOTES:

    FRONT VIEW

    SCALE NTS

    END VIEW

    PUMP

    CHEMICAL

    POT FEEDER

    CHEMICAL POT FEEDER

    DRAIN VALVE

    ISOLATION BALL

    VALVEUNION

    ISOLATION

    BALL VALVE

    BALANCE LINE

    UNION

    ISOLATION

    BALL VALVE

    300 Min.

    SCALE NTS

    HANGER ROD

    CLEVIS HANGER

    REFER TO SPEC.

    VAPOUR SEAL

    PREFORMED PIPE

    INSULATION. REFER TO

    SPEC.

    CLEVIS HANGER

    REFER TO SPEC.

    PREFORMED PIPE

    INSULATION IF

    REQ''D. REFER TO

    SPEC.

    HANGER DETAIL FOR PIPING WITH VAPOUR SEALED INSULATION

    (FOR COLD PIPING 10°C [50°F] OR LESS)

    HANGER DETAIL FOR INSULATED HOT PIPING UP TO NPS

    3 (75mm) OR ALL SIZES OF BARE PIPE

    PIPE HANGERS

    FOR NPS 2-1/2 PIPE AND

    LARGER. REFER TO SPEC.

    FOR INSERTS OR HIGH

    DENSITY INSULATION AT

    INSULATION PROTECTION

    SHIELDS.LOCKING NUT

    SUPPORT NUT

    PIPE

    INSULATION

    PROTECTION SHIELD AT

    HANGER. REFER TO

    SPEC.

    HANGER ROD

    LOCKING NUT

    SUPPORT NUT

    PIPE

    SCALE NTS

    M-01M-02M-03M-04M-05M-06M-07