    REHABILITATION AND UPGRADING OF EXISTING PASSENGER TERMINAL BUILDING , ROAD CAR PARK AND PARKING APRON AT DAMASCUS INSYRIAN ARAB REPUBLICDated: 09/12/09M&E Testing & Commissioning

    Item Sub Con Description of Testing & Commissioning Schedule

    1

    KEMJ

    Electrical Boards (MSBs, SSBs, DBs) 10/26/2009 1

    2 Public Address 10/27/2009

    3 Generator Set 11/2/2009

    4 Uninteruptable Power Supply, UPS 11/5/2009

    5 Telephone System 11/25/2009

    6 Palmac Construction Plumbing Services 10/28/2009 1

    7 Meridian Engineering Fire Protection Services 11/3/2009

  • 8/14/2019 M&E Outstanding Work

    2/10

    8 Baggage Handling System, BHS 11/4/2009

    9 Airconditioning & Mechanical Ventilation System 11/9/2009

    10

    K L I A I N F O R M A T I K

    Networking System 11/9/2009

    11 Flight Information Display System, FIDS 11/12/2009

    12 Close Circuit Television, CCTV 10 - 14/01/10

    13 Network Training 10 11/01/1014 FIDS Training 13 14/01/1015 CCTV Training 17 18/01/10

  • 8/14/2019 M&E Outstanding Work

    3/10

    M&E Outstanding Work

    Item Sub Con Services Description of Outstanding WorksDail

    Previous

    1 Local supplier Electrical Cabling work for mobile genset 0%

    2

    KEMJ

    Electrical Termination of essential supply to EMSB. 0%

    3 Electrical Electrical Panel MSB, SSB, DB type tested. 0%

    4 Electrical Alternator issue 0%

    5 Electrical Fitting installation for Keluar Sign fitting 65%6 Plumbing 0%

    Fire Protection Beam detector. 0%

    7

    KLIA InfoCUPS CUPS software 0%

    8 CCTV Image focusing and joystick at control room mulfunction. 0%

    9 CCTV Additional 3 nos CCTV camera / DVR / Monitor 0%

    10 Rectification work for all existing AHU as requested by SCAA :

    11

    ACMV AHU G3-1

    a) Hot Water Pipes Insulation for existing pipes 0%

    12 b) Duct insulation for existing ductworks 0%

    13 c) Motor changed/fan inspected 90%14

    ACMV AHU G3-2

    a) Hot & Chilled Water Pipes Insulation for existing pipes 0%

    15 b) Duct insulation for existing ductworks 0%

    16 c) Motor changed/fan inspected 90%

    17

    ACMV AHU GT-1

    a) Hot Water Pipes Insulation for existing pipes 0%

    18 b) Duct insulation for existing ductworks 100%

    19

    Pathfinder

    c) Motor changed/fan inspected 90%

    20

    ACMV AHU GT-2

    a) Hot Water Pipes Insulation for existing pipes 0%

    21 b) Duct insulation for existing ductworks 100%

    22 c) Motor changed/fan inspected 90%

    23

    ACMV AHU C1W

    a) Hot Water Pipes Insulation for existing pipes 0%

    24 b) Duct insulation for existing ductworks 100%

    25 c) Motor changed/fan inspected 90%

    26

    ACMV AHU C4E

    a) Hot Water Pipes Insulation for existing pipes 0%

    27 b) Duct insulation for existing ductworks 100%

    28 c) Motor changed/fan inspected 100%

    29

    ACMV AHU K6W

    a) Hot Water Pipes Insulation for existing pipes 0%

    30 b) Duct insulation for existing ductworks 100%

    31 c) Motor changed/fan inspected 100%

    32

    ACMV AHU I6E

    a) Hot Water Pipes Insulation for existing pipes 0%

    33 b) Duct insulation for existing ductworks 0%

    34 c) Motor changed/fan inspected 90%

    35

    ACMV AHU K7W

    a) Hot Water Pipes Insulation for existing pipes 0%

    36 b) Duct insulation for existing ductworks 100%

    37 c) Motor changed/fan inspected 90%

    38

    ACMV AHU I6W

    a) Hot Water Pipes Insulation for existing pipes 0%

    39 b) Duct insulation for existing ductworks 100%

    40 c) Motor changed/fan inspected 90%

    41

    ACMV AHU I5E

    a) Hot Water Pipes Insulation for existing pipes 0%

    42 b) Duct insulation for existing ductworks 100%

    43 c) Motor changed/fan inspected 90%

    ea age o ot water tan at ew rr va u c to et to et nosleaked as-off todate .

  • 8/14/2019 M&E Outstanding Work

    4/10

    44

    Pathfinder

    ACMV AHU K6E

    a) Hot Water Pipes Insulation for existing pipes 0%

    45 b) Duct insulation for existing ductworks 100%

    46 c) Motor changed/fan inspected 90%

    47

    ACMV AHU E4E1

    a) Hot Water Pipes Insulation for existing pipes 0%

    48 b) Duct insulation for existing ductworks 0%

    49 c) Motor changed/fan inspected 90%

    50

    ACMV AHU D7E

    a) Hot Water Pipes Insulation for existing pipes 0%

    51 b) Duct insulation for existing ductworks 0%

    52 c) Motor changed/fan inspected 90%

    53

    ACMV AHU C5W

    a) Hot Water Pipes Insulation for existing pipes 0%

    54 b) Duct insulation for existing ductworks 0%

    55 c) Motor changed/fan inspected 0%

    56

    ACMV

    a) Hot Water Pipes Insulation for existing pipes 0%

    57 b) Duct insulation for existing ductworks 0%

    58 c) Motor changed/fan inspected 0%

    59

    ACMV

    a) Hot Water Pipes Insulation for existing pipes 0%

    60 b) Duct insulation for existing ductworks 0%

    61 c) Motor changed/fan inspected 50%

    62

    ACMV AHU E6E

    a) Hot Water Pipes Insulation for existing pipes 0%

    63 b) Duct insulation for existing ductworks 0%

    64 c) Motor changed/fan inspected 90%

    65

    ACMV AHU E2E

    a) Hot Water Pipes Insulation for existing pipes 0%

    66 b) Duct insulation for existing ductworks 0%

    67 c) Motor changed/fan inspected 90%

    68

    Pathfinder

    ACMV

    a) Hot Water Pipes Insulation for existing pipes 0%

    69 b) Duct insulation for existing ductworks 0%

    70 c) Motor changed/fan inspected 0%

    71

    ACMV

    a) Hot Water Pipes Insulation for existing pipes 0%

    72 b) Duct insulation for existing ductworks 0%

    73 c) Motor changed/fan inspected 90%

    74

    ACMV AHU ZE-1

    a) Hot Water Pipes Insulation for existing pipes 0%

    75 b) Duct insulation for existing ductworks 0%76 c) Motor changed/fan inspected 10%

    77

    ACMV AHU ZE-2

    a) Hot Water Pipes Insulation for existing pipes 0%

    78 b) Duct insulation for existing ductworks 0%

    79 c) Motor changed/fan inspected 10%

    80

    ACMV AHU G4-1

    a) Hot Water Pipes Insulation for existing pipes 0%

    81 b) Duct insulation for existing ductworks 0%

    82 c) Motor changed/fan inspected 90%

    83

    ACMV AHU G4-2

    a) Hot Water Pipes Insulation for existing pipes 0%

    84 b) Duct insulation for existing ductworks 0%

    85 c) Motor changed/fan inspected 90%

    86

    Pathfinder

    ACMV

    Existing FCU unit at 1st floor transit area (4 nos):87 b)Rectify all duct work due to poor air distribution. 0%88 c)To install grille/diffuser/flexible duct at Departure Gates 0%

    89 ACMV To add splitter/damper at sick bay duct branch out. 0%

    90 ACMV 100%

    91 ACMV Pressure test for chilled water and hot water system. 50%

    92 ACMV Softener test result to achieved correct water hardness. To add softener tank. 0% 0%

    AHU E7E-1

    AHU E7E-2

    AHUG4W-1

    AHUG4W-2

    To extend condensing pipes to the nearest gutter/floor trap for PC 1, PC 2, PC 3and PC 6.

  • 8/14/2019 M&E Outstanding Work

    5/10

    93

    INTERROLLER

    Carousal 0%

    94 Carousal To check and rectify the damaged of conveyor belt at departure area. 0%

    95 Carousal Review of departure carousal congestion problem at T-junction. 0%

    96 Carousal To clarify thermal load protection breaker rating too high. 0%

    97

    By Others

    0%

    98 Civil work 0%

    99 Civil work Apron concreting area B, C, D, E and F. 36%

    100 Civil work Apply silicon for area B,C,D,E and F 0%

    101 Civil work High mast, edge light and airfield signage installation. 0%

    102 Civil work GSC road construction for area B, C, and D. 0%

    103 Civil work Folding door modification / replacement. 0%

    104 Civil work Car park road cutting. 100%

    105 Civil work Car park road painting (repainting). 94%

    106 Civil work Car park water ponding rectification work. 100%

    107 Civil work To review drainage system comment by Halcrow. 0%

    108 Civil work Proposal to extent conveyor and guardrail 0%

    109 Civil work To rectify wearing course at departure area. 100%

    110 Civil work To provide clading surrounding external VIP facial. 0%

    111 Civil work Manhole at arrival carousal to be air tight type. 100%

    112 Civil work Painting at arrival rentaining wall and external void. 87%

    113 Civil work Painting at external departure area. 100%

    114 Civil work Replacement of "Terminal 1" signage. 0%

    Completed work.Work in progress (WIP)

    Notes:1. Zink sheet for hot & chilled water pipe delivered to site not enough.

    Installation of replacement body skirting accessories for Carousel OB-1 atDeparture area.(Previously damaged by SCAA)

    PresidentialPavillion

    To submit construction drawing for M&E and architectural. To fabricateelectrical board IP44 from Malaysia. Site to clarify design drawing.

    Terminal building existing VIP roof leaking repair work. To provide proposal toGCEC-Halcrow for approval.

  • 8/14/2019 M&E Outstanding Work

    6/10

    ERNATIONAL AIRPORT

    ual Remark Action

    1st Inspection2nd Inspection

    HR & Pyrogen

    FA 1st T&C

    FA 2nd T&C

    FA 3rd T&C

    FA 4th T&C

    GCEC emphasize on the type tested panel requirement (including DBand SSB)

    Mobilazation of kitlite expectedon 23/12/09 in anticipation thatbalance material like conduit(including additional light to

    arrive / clear by 22/12/09)

    GCEC advise not to terminate the new essential supply new EMSB untilthe type tested issue resolve to avoid inconvenient to airport operation

    Meb had notified GCEC that MSB shall be VO to the contract. Meb isawaiting acknowledgement from GCEC

    T&C completed with comment on echo phenomenon in concourse area.GCEC advised Meb to treat the echo problem.T&C completed but final approval subject to documents submissionconforming to the specification.

    T&C completed but final approval subject to the documents submissionconforming to the specification.

    MEB had written to Airport Director request for fix line for testing.MEB to coordinate with airport maintenance team for this line. Letter sent

    T&C completed with comment on damages and defective fittings due to public rough handling.

    T&C of Hose reel & Pyrogen system completed. T&C of Fire AlarmSystem in progress

    GCEC require original catalogue submission for all fire protectiondevices installed at site especially for FA panel. Catalogue under compilation & target to submit 12/12/09. HQ to assist getting JVK to

    justify:

  • 8/14/2019 M&E Outstanding Work

    7/10

    1) PC based graphic central control system

    2) Fault isolator

    SCAA has run boiler for heating system. Temperature 24

    1st T&C

    2nd T&C

    1st T&C2nd T&C

    3) Panel for 4 loops used against 10 loops in final installation (whether to change the panel to 10 loops or not).

    GCEC agreed to proceed the training as per Meb/Petris submission.Require SCAA to confirm training date.

    First inspection at server room has been carried out. Second inspection ataccess point in the ground area pending due to inspector do not haveworkpass. Target to carry out on 6 January 2010.

    T&C completed with general comment on cleanliness of the monitorsand replacement of some burn mark monitors.

    Target physical inspection on Mid Dec 2009 and official inspectionaround Mid Jan 2009.

  • 8/14/2019 M&E Outstanding Work

    8/10

    As-Off:12/8/2009

    RemarksCompleted

    0% No confirmation from SCAA. Please advice.

    0%

    0% Please advise.

    0%

    65% Awaiting material from supplier Wassem.0% HQ to order 4 nos hot water tanks.

    0%

    0%

    0% KLIA Infomatic informed material ETA by end of Dec 09.

    0% KLIA Infomatic informed material ETA by end of Dec 09.

    0%

    0%

    100%

    0%

    0%

    100%

    0%

    100%

    100%

    0%

    100%

    100%

    0% Fabrication of hot water jacket completed.

    100%

    100%

    10%

    100%

    100%

    0% Dismantle of existing jacket completed.

    100%

    100%

    0% Dismantle of existing jacket completed.

    20% Dismantle of existing insulation completed.

    100%

    0% Dismantle of existing jacket completed.

    100%

    100%

    0% Dismantle of existing jacket completed.

    100%

    100%

    0% Dismantle of existing jacket completed.

    100%

    100%

    KEMJ workers demob on 2/12. HQis arranging for Kitlite to mob

    tentative on 23/12/09 subject to thefull delivery of conduit and l ight

    fittings / accessories.

    GCEC advised no to connect main electrical system to the new essentialsupply until the "type tested" issue resolved.

    T&C completed but final approval subject to documents submissionconforming to the specification.

    Beam detector arrived on 8/12/09. Worker went back without permissionon 6/12/09.

    TKH to assist getting next fromMeridian.

    Awaiting confirmation from SCAA to proceed with the IATAcompliancy audit to our system. SCAA to give official confirmation andcommitment.

    Sourcing zink sheet from local in progress. Current stock 600 out of

    2000 meter

  • 8/14/2019 M&E Outstanding Work

    9/10

    0% Dismantle of existing jacket completed.

    100%

    100%

    0% Dismantle of existing jacket completed.

    0% Dismantle of existing insulation completed.

    100%

    0% Dismantle of existing jacket completed.

    0% Dismantle of existing insulation completed.

    100%

    0% Dismantle of existing jacket completed.

    0% Dismantle of existing insulation completed.

    90% Test run in progress.

    0% Dismantle of existing jacket completed.

    0% Dismantle of existing insulation completed.

    90% Test run of airflow in progress.

    0% Dismantle of existing jacket completed.

    0% Dismantle of existing insulation completed.

    90% Test run in progress.

    0% Fabrication of hot water jacket completed.

    0% Dismantle of existing insulation completed.

    100%

    0% Fabrication of hot water jacket completed.

    0% Dismantle of existing insulation completed.

    100%

    0% Fabrication of hot water jacket completed.

    0% Dismantle of existing insulation completed.

    0% Motor on site.

    0% Fabrication of hot water jacket completed.

    0% Dismantle of existing insulation completed.

    100%

    0%

    0%100% Test run in progress.

    0%

    0%

    100% Test run in progress.

    0%

    0%

    100%

    0%

    0%

    100%

    0%

    0%

    0%

    100%

    50%

    0% HQ to assist finalize the order of softener with Pathfinder.

    Sourcing zink sheet from local in progress. Current stock 600 out of

    2000 meter

    Pressure test on hot water pipe completed. Pressure test for chilled water system in progress.

  • 8/14/2019 M&E Outstanding Work

    10/10

    0% Material on site.

    0%

    0%

    0%

    0% 8/25/2009

    0% SCAA's contractor already commence repair work on 26/11/09. 8/25/2009

    37% Apron F- 2 panels casted TBA TBA

    0% TBA TBA

    0% TBA TBA

    0% TBA TBA

    0% TBA TBA

    100% completed

    95% 12/15/2009

    100% completed

    0% TBA TBA

    0% TBA TBA

    100% TBA completed

    0% Material under importation. TBA TBA

    100% TBA completed

    87% 12/15/2009

    100% completed

    0% TBA TBA

    Interoller claimed has sent the letter regarding this issue to MEB HQ.Ahmad please advise. TQ

    Internal completed. External texture paint approved 26/11/09.Appoinment of subcontractor in progress.

    Quotation received on 6-12-09, submited to GCEC on 22-11-09 for approval. Appoinment of subcontractor in progress.