MDOT- Michigan Department of TransportationChallenges for TodayPartnerships for Tomorrow
I-96/US-23 Interchange
Located in: Brighton Township Livingston County
I-96/US-23 Interchange HistoryOriginal Construction early 1960’sConcept was visualized using cardboard models-
I-96/US-23 design today3D modeling utilizing computer design software-
ADD 3D Model I-96/US-23 Interchange
Traffic then- Traffic now
Ramp J (EB I-96 to SB US-23) DHV anticipated in 1960’s 420 vph
Today’s peak hour volume 1375 vph 20 Projected volume 1700 vph
I-96/US-23 Interchange - Existing
I-96/US-23 Interchange - Project
I-96/US-23 Customer Impact
Downtown Brighton Area
Lee Road Mall Residential
Communities Commercial Areas Rush hour through
traffic
Downtown Brighton
Area
Lee Road Mall
Residential Communities
I-96/US-23 Project Challenges
Old US-23 (accommodations)Existing two lane road with 8’ shoulders
Future Opening on Old US-23Accommodations for a five lane section with room for pedestrian walkways
I-96/US-23 Context Sensitive SolutionsStakeholder engagement resulted in the selection of the bridge aesthetics-
I-96/US-23 How are we going to build it?Four major Stages
Prestage Summer 2014Stage 1 2014- Spring 2015Stage 2 May- July 2015Stage 3 Aug- Nov 2015
Pre-StageSpencer Bridge, Temp paving & Spencer Ramp workThree lanes of traffic maintained during peak hours.
Stage 1Three lanes of traffic maintained on existing I-96 during construction of new mainline roadway in the middle.
Stage 2Part width construction of existing roadway two lanes maintained on new mainline one lane maintained on existing roadways.
Stage 3Part width construction of existing roadway two lanes maintained on new mainline one lane maintained on existing roadways.
Detours
2014Spencer Road (Closure)
~45 days this summer2014 & 2015
US-23 SB (Spencer Road)US-23 NB (Kensington Road)
Nightly for Bridge Beams
Spencer Rd Local DetourSpencer through movement closed- detour via Old US-23
EB I-96 On-Ramp Detour
EB I-96 On-Ramp Detour
Detours using Spencer RdSB US-23 night closures for beam placementFreeway to freeway ramp reconstructions
Spencer Rd at I-96 Interchange during Detours
Detours using Kensington RdSB US-23 night closures for beam placementFreeway to freeway ramp reconstructions
What happens next?
Finish the design early 2014 Demolition Work spring 2014 Utility Relocations spring 2014 Begin construction summer 2014 Fully open to traffic fall 2015 Cleanup & Planting spring of 2016
I-96 / US-23 Needs & Concerns Acres of clearing: 24.8 (approximately 7,000 trees)
Replanting Trees: (Deciduous, Shrubs and Conifer) Deciduous 1,930 $97,175 Shrubs 800 $12,200 Conifer 7,000 $49,000 Water/Cultivating $50,000 Site Preparation $100,225
○ Subtotal $308,600
Restoration Areas: Short-Grass Understory Seeding $248,000 Detention Seeding $ 66,815 Standard Freeway Restoration $261,000
○ Subtotal $575,815
Total Landscaping/Restoration Estimate $884,415
How much will this cost?
Estimated Bid $53 million Construction Eng $ 5 million Design $ 5 million Real Estate $ 3 million Total Project Estimate $66 million
I-96/US-23 InterchangeAerial 5 – 10 Year Growth
I-96 / US-23 – Project Information
Design: Road MDOT, University Region Design
Bridge ○ New Mainline/Spencer Road: MDOT, Bridge Design○ Existing Bridge Redesign: Alfred Benesch & Co., and URS
Context Sensitive Solutions (CSS): Parsons Transportation Group
Construction Team: Brighton TSC Field Staff
Letting Date: June 2014
Construction: 2014 / 2015
QUESTIONS