HISTORIC PRESERVATIONR EVIEW BOARDCONCEPT SUBMISSION
BUILDINGS 1B:GROCERY/ MULTIFAMILY BUILDING + PARK & COMMUNITY CENTER
M AY 24, 2013
O WNER DISTRICT OF COLUMBIA
DEVELOPMENTTEAMEYA JAIR LYNCH DEVELOPMENT PARTNERSTRAMMELL CROW COMPANY
PROJECT DIRECTOR ANNE L. CORBETT
M ASTER PLAN A RCHITECTEE&K A PERKINS EASTMAN COMPANY
L ANDSCAPE A RCHITECT
NELSON BYRD WOLTZ
HISTORIC PRESERVATIONCONSULTANTEHT TRACERIES, INC.
CIVILENGINEER BOWMAN CONSULTING
STRUCTURALENGINEER ROBERT SILMAN ASSOCIATES
TRAFFICCONSULTANTGOROVE / SLADE
L AND USE COUNSELHOLLAND & KNIGHT
BUILDING A RCHITECTSEE&K A PERKINS EASTMAN COMPANYLESSARD DESIGN
MV+A / DAVID JAMESONSHALOM BARANES ASSOCIATES
drens osp a
McMillaneservoir
Glenwoodemetery
e er a rs
ransr
eM dical Center
Evarts Street NE
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
2/31
VISION MCMILLAN PARTNERS
Date: May 24, 2013
To: Historic Preservation Review Board
Subject:McMillan Sand Filtration Site | JLDP Grocery &Multifamily + Public Park & Community Center Concept Applications
From: Vision McMillan Partners
The following information is being provided by Vision McMillan Partners (V MP ) to illustrate the design intentionsfor the second set of new buildings proposed for the McMillan Sand Filtration Site. We respectfully request apresentation before the Historic Preservation Review Board (H PRB ) on June 28, 2013.
Please find the enclosed images depicting the proposed architectural concepts for JAIR LYNCH Development PartnersGrocery & Multifamily building and the Public Park and Community Center components of VMPs plans to redevelop
the McMillan Sand Filtration Site. These concepts accompany the concept applications submitted on April 26, 2013for EYAs Row Houses and TCCs Medical Office Buildings.
We presented all four building concepts at a widely publicized community open house on April 27, 2013 from 12noon to 2 pm at St. Georges Episcopal Church, 160 U Street NW a date, time and location chosen by thecommissioners of 5E, in whose ANC the Sand Filtration Site is located.
We have distributed the building illustrations to ANCs 5E, 5A and 1B requesting the opportunity to present at their June meetings.
Please let us know if we may present all four concept applications at the hearing on June 28, 2013 with anyadjustments we may make following community input.
We appreciate your thoughtful consideration.Respectfully,
Anne L. CorbettProject Director
Vision McMillan Partners
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
3/31
P ARK & C OMMUNITY C ENTE
O WNERDISTRICT OF COLUMBIA
V ISION MCMILLAN P ARTNERS DEVELOPMENT TEAMEYA JAIR LYNCH DEVELOPMENT PARTNERSTRAMMELL CROW COMPANY
PROJECT DIRECTOR ANNE L. CORBETT
L ANDSCAPE A RCHITECTNELSON BYRD WOLTZ
A RCHITECTEE&K A PERKINS EASTMAN COMPANY
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
4/31
THIS PAGE IS INTENTIONALLY LEFT BLANK.
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
5/31McMillan Buildings 1b may 24, 20
P ARK & COMMUNITY CENTER INTRODUCTION
lrongholdl
Bloomingdale
M ic h iga n A v e n u e N W
E
South Park
South Service Court
Elevated Olmsted Walk
Informal Play Area
Community Center
Stormwater Wetland
Preserved Cell 28
Park SouthSouth Service Court = 1.8 Acres
South Park = 6.2 AcresTotal Public Space = 8 Acres
Park program includes:
- Convenient pedestrian and vehicle access, bike parking, and car parking viaSouth Service Court
- Service access to DC Water access hatch integrated into park design
- Large informal play areas
- Elevated Olmsted Walk recreates historic condition
- Significant preserved portion of below-grade Filter Bed Cell 28 andabove-grade manholes / skylights
- Spray water jets play area
- Public community center integrated into park
- Terraced seating
- Stormwater wetland
- Pedestrian access from all surrounding streets- ADA accessibility throughout
Community Center17,500 gross sf
Community center program includes:
- Circulation & gallery spaces with exhibits on the history of the McMillan site
- 25-yard swimming pool- Multipurpose community meeting room with catering kitchen
- Outdoor gathering space connected to multipurpose community meeting room
- Multipurpose fitness studio
- Locker & shower facilties
- Reception/security & office
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
6/31
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
7/31
McMillan Buildings 1b may 24, 20
P ARK CONCEPT PERSPECTIV
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
8/31
8 McMillan Bumay 24, 2013
P a r k &
C o m m u n i t y
C e n t e r P ARK CONCEPT PERSPECTIVE
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
9/31
McMillan Buildings 1b may 24, 20
P ARK CONCEPT PERSPECTIV
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
10/31
10 McMillan Bumay 24, 2013
0 16
+155
+155
+155
+155
+155
POOL
LOCKERS
MULTIPURPOSEFITNESS
M E C H
LOWER LE
HALL
PRESERVED CELL 28
UP
UP
P a r k &
C o m m u n i t y
C e n t e r COMMUNITY CENTER FLOOR PLAN LOWER LEVEL
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
11/31
McMillan Buildings 1b may 24, 20
0 16 32
MULTI-PURPOSE
COMMUNITYROOM
G A L L E R Y
GALLERY
W C
W C
RECEPTION
CATERINGKITCHEN
OUTDOOR TERRACE
+165 +165
UP
DN
+165
+155
+170
+170
+170
+170
MAINENTRANCE
PARK ENTRANCE
OPEN TO BELOW
UPPER LEVEL
UP
COMMUNITY CENTER FLOOR PLAN UPPER LEVE
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
12/31
THIS PAGE IS INTENTIONALLY LEFT BLANK.
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
13/31
McMillan Buildings 1b may 24, 20
GREEN ROOF
MECHANICALPENTHOUSE
TRELLIS
MAINENTRANCE
0 16 32
ROOF LEVEL
COMMUNITY CENTER R OOF PLAN
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
14/31
14 McMillan Bumay 24, 2013
P a r k &
C o m m u n i t y
C e n t e r
165.00
155.00
170.00
Copper sheathing on entrance vestibule,skylights, and mechanical enclosurereferences historic turquoise elements
High-performace glazingadmits ample daylight to pooland other public spaces
Lightweight metal exterior trellis shading systemconditions exterior space andshades building
Slender steel columns supportexterior shading system anddefine public arcade
Reinforced concrete groin vaults recreate experience of historic below-grade filter beds
NOTE: Material annotations typical for all elevations
COMMUNITY CENTER ELEVATION E AST
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
15/31
McMillan Buildings 1b may 24, 20
165.00 170.00
COMMUNITY CENTER ELEVATION W EST
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
16/31
16 McMillan Bumay 24, 2013
P a r k &
C o m m u n i t y
C e n t e r
165.00 170.00
COMMUNITY CENTER ELEVATION N ORTH
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
17/31
McMillan Buildings 1b may 24, 20
155.00
170.00
COMMUNITY CENTER ELEVATION SOUTH
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
18/31
18 McMillan Bumay 24, 2013
155.00
165.00
170.00
SOUTH SERVICE COURT CIRCULATION AND GALLERY SPACE
P a r k &
C o m m u n i t y
C e n t e r COMMUNITY CENTER SECTION N ORTH-SOUTH
0 16 32
MULTI-PURPOSE
COMMUNITYROOM
G A L L E R Y
GALLERY
W C
W C
RECEPTION
CATERINGKITCHEN
OUTDOOR TERRACE
+165 +165
UP
DN
+165
+155
+170
+170
+170
+170
MAINENTRANCE
PARK ENTRANCE
OPEN TO BELOW
UPPER LEVEL
UP
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
19/31
McMillan Buildings 1b may 24, 20
155.00
170.00
165.00
PARK SOUTHCOMMUNITY MEETING ROOM - UPPER LEVELPOOL AND FITNESS ROOM - LOWER LEVEL
COMMUNITY CENTER SECTION E AST-W EST
0 16 32
MULTI-PURPOSE
COMMUNITYROOM
G A L L E R Y
GALLERY
W C
W C
RECEPTION
CATERINGKITCHEN
OUTDOOR TERRACE
+165 +165
UP
DN
+165
+155
+170
+170
+170
+170
MAINENTRANCE
PARK ENTRANCE
OPEN TO BELOW
UPPER LEVE
UP
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
20/31
20 McMillan Bumay 24, 2013
P a r k &
C o m m u n i t y
C e n t e r O VERALLA ERIALV IEW FROM SOUTHEAST
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
21/31
McMillan Buildings 1b may 24, 20
GROUND-LEVELV IEW FROM SOUTH SERVICECOURT F ACING M AIN ENTRANCE
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
22/31
22
N a m e o f
S e c t i o n
McMillan Bumay 24, 2013
GROUND-LEVELV IEW FROM TERRACEDSEATING A REA F ACING NORTH
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
23/31
M ULTIFAMILY /G ROCERY BUILDIN
DEVELOPERJAIR LYNCH DEVELOPMENT PARTNERS
PROJECT DIRECTOR ANNE L. CORBETT
A RCHITECTSMV+A ARCHITECTS / DAVID JAMESON ARCHITECT
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
24/31
McMillan Buildings 1b may 24, 20
O r e re e the p th tr ter t te ove the North Serv e Co rt. T
e t re ow the e e o the to re thepr r te to re o the North Serv e Co rt.
G o w o t the o rete re o theor f tr t o e e e ew o t ro er ret e v ro e t. A ove the ro er , the exter or
w o the t ho w re the orp rpo e o the M M te: f tr t o w ter.
M t ho h ee o e ve other tor the ro er te w th r e ope o rt. We e eve
r h te t re t t root q e t t o e thetor e the pre re o p e. C re o er t o
o the e o e h or row ho e o NorthC p to Street ew M M row ho e o t ,o w th the e re to r t r ht to the
North Serv e Co rt, t v te o r e r h or ettere o t o .
Te r o the M M p th o tr x prov e o r th t j xt po e to the
e r q t o the North So th Serv e Co rt .Te p th or o tr te w o t o e
to o o pe ve e . Te p th othero tr t o r p rpo e o t the M Mte: , re tor ho e , f tr t o e ;
e e the DNA o o r e ve t t o .
O r e o e ve to e e tor tto ether the v r o e exp
j e t to the M M te. Row htow ho e to the e t o th o o r te
th the ro er p th o o r propo . Te re the o t r h te t r e e e t North Serv e Co rt.
Te t pe t o o r e or e thew r pre re o the e h or row ho e
the t te w th the North Serv e Co rt.Te re t t p t o th t prov e
re th p e ope terr e o the ro er p th. For , the ho retre t ro the wo the p th, the e e to the k re e e the
ver e o the ope per pe t ve o the top .
INSPIRATION & PROCESS
M C
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
25/31
McMillan Buildings 1b may 24, 20
M ATERIALSCONCEPT
S P
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
26/31
McMillan Buildings 1b may 24, 20
0 100 200
SITE PLAN
GROCERY / RETAILPLAN
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
27/31
McMillan Buildings 1b may 24, 20
0 50 100
GROCERY / R ETAILPLAN
TYPICALRESIDENTIALPLAN
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
28/31
McMillan Buildings 1b may 24, 20
0 50 100
TYPICALR ESIDENTIALPLAN
VIEW LOOKING SOUTH INTO THE NORTH SERVICECOURT
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
29/31
McMillan Buildings 1b may 24, 20
V IEW LOOKING SOUTH INTO THE NORTH SERVICECOURT
LONGITUDINAL BUILDING SECTION
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
30/31
McMillan Buildings 1b may 24, 200 25 50
LONGITUDINAL BUILDING SECTION
VIEW LOOKING NORTH UP NORTH CAPITOL STREE
7/28/2019 McMillan HPRB Buildings 1B Submission Final_Email 2013-05-24
31/31
McMillan Buildings 1b may 24, 20
V IEW LOOKING NORTH UP NORTH C APITOL STREE