Upload
hoangque
View
216
Download
2
Embed Size (px)
Citation preview
MCE Deepwater Development 2015Modularity of PLET and ILT design
for easy offshore installation and pipelay
March 24th 2015
Emmanuel Fontaine
2Page 2-Mar-15
1- PLET and ILT functionalities2- Offshore installation methods3- Installation constraintsand impact on design4- Mudmat modularity5- Conclusions
Agenda
3Page 2-Mar-15
1 - PLET AND ILT FUNCTIONALITIES• A PLET or ILT makes connection between the pipeline and a well or
manifold
• Contains special features:
- A piping bend with one connector or
more + valves and secondary featings
- A piping frame to hold the piping elements
and protect from dropped object
- A mudmat foundation to sustain:
Gravity load
Environmental loads
Equipment loads
Pipeline, Jumper loads
Mudmat can be sliding on seabed or allow the pipeline expansion (rails)
4Page 2-Mar-15
2 - OFFSHORE INSTALLATION METHODS
• Requires to accomodate a range of installation methods
• Needs to cope with installation constraints
• Subsea Structure needs thus to be modular: Piping module; Mudmatmodule; Special double joint module
• Some part are standardized with specific dimensions for flexibility and variety in use (S-J-Reel)
Installation Vessels3 Installation
modesS-Reel-J lay
3 Types of structurePLET – First End
PLET - Second EndInline Tee (ILT)
Thus 9 Groups of design to cope with
vessels and structure types
FUNCTION
CLIENT NEEDS
PLET-ILT
DESIGN
VESSELTO
INSTALL
5Page 2-Mar-15
2 - OFFSHORE INSTALLATION METHODS
Assemblyin S-lay
firing line
Double joint module
Piping module
Foundation module
StingerPLET in
Catenary(S-type)
Buoyancy module
S-LAY
J-laytower/weldingstation
PLET in Catenary(J-Type)
Buoyancy module
PLET handling system
Pipingmodule + double joint module + foundation J-LAY
PLET handling system
Pipingmodule + double joint module + foundation
Reel laywork
station/weldingstation
PLET in Catenary(J-type)
Buoyancy module
REELLAY
6Page 2-Mar-15
2 - OFFSHORE INSTALLATION METHODS REEL-LAY INSTALLATION SEQUENCE
• PLET installed in Reel-lay • A PLET handling system (PHS) skids the structure aft and
transversally into the workstation for welding up to pipeline
Aligner Wheel
Pipe Storage drum
Lay rampat vessel Stern
PLET Handling SystemSeven Oceans
PLET in the workstation
7Page 2-Mar-15
2 - OFFSHORE INSTALLATION METHODS REEL-LAY INSTALLATION SEQUENCE – Laydown case
Final landing of complete PLET or simple piping module on a Pre-installed foundation. Foundation could also be post-installed.
PLET
8Page 2-Mar-15
2 - OFFSHORE INSTALLATION METHODS J-LAY INSTALLATION SEQUENCE – Laydown case
• PLET installed in J-lay
• Pipeline and structure are deployed along vessel side with a J-lay tower
J-lay tower
Seven Borealis
PLET
Pipeline catenary
J-lay tower structure
PLET handling frame
9Page 2-Mar-15
2 - OFFSHORE INSTALLATION METHODSJ-LAY INSTALLATION SEQUENCE - Laydown
Last stage: Final Landing of the all integrated PLET or single pipingmodule on a Pre-installed foundation. The foundation can also be post-installed.
PLET up-righted
Buoys
Pipeline catenary
10Page 2-Mar-15
2 - OFFSHORE INSTALLATION METHODS S-LAY INSTALLATION SEQUENCE – ILT CASE
For S-lay, the challenge is having the Piping module pass along the firing line: may be installed before/after tensioners
Joints are welded, Field joint coated Tensioners are opened to their maximum range
allowing the double joint module to transit
DOUBLE JOINTMODULE
PIPINGMODULE
11Page 2-Mar-15
2 - OFFSHORE INSTALLATION METHODS S-LAY S-LAY INSTALLATION SEQUENCE – ILT CASE
• Then the structure exits the firing line and enter the stinger
• Cross of the overbend region• Buoyancy is connected• Exit the stinger and last
rollers• Last stage: Final Landing of
the complete ILT or single piping module on Pre-installed foundation. Mudmatcan also be Post-installed.
12Page 2-Mar-15
2 - OFFSHORE INSTALLATION METHODS ALTERNATE DEPLOYMENT TABLE
• Use a deployment table (after pipeline recovery after a Reel J-S lay)
• Can be used for very large/heavy structure
• Not applicable for ILT• Requires recovery of the line
and installation of PLET in a second stage
• Can be done with a second vessel (without J/S or Reel capacity)
Hang-off table
Pipeline catenary
Abandonment cable
PLET
13Page 2-Mar-15
3 - INSTALLATION CONSTRAINTS AND IMPACT ON DESIGN
• We have a wide range of installation constraints and Contractorneeds to integrate them in the PLET/ILT design.
• Need to specialize/adapt the design for each vessel tool.
• For foundation the greatest flexibiltity is coming with the Pre and Post-installed mudmat.
Pipi
ngm
odul
e •Similar for all 3 modes S, Reel, J
•But Requiresspecialinterfaces : the PLET handling toolsof Reel and J-lay towers Pi
pelin
e s
peci
aljo
int •Integrated to
piping module for Reel and J-lay
•Separated for S-lay
Foun
datio
nm
odul
e •Generallyintegrated (Reel/J)
•Can be separatedfor S-lay
•Can be Pre or Post installed for all 3 modes
•Can be fixed to piping module or allow it to slide ( with rails)
14Page 2-Mar-15
3 - INSTALLATION CONSTRAINTS AND IMPACT ON DESIGN
With interface for J-lay handling With interface for Reel-lay handling
With separated pipingframe for S-lay handling
With special double joint (S-lay firing line)
PLET/ILT MODULE TYPES
15Page 2-Mar-15
3 - INSTALLATION CONSTRAINTS AND IMPACT ON DESIGN
Mudmat integrated to PLET/ILT(w/o foldable wings)
Pre-installed mudmat
Suction Pile for stab and hinge over system Post-installed mudmat
PLET/ILT FOUNDATION
MODULE TYPES
16Page 2-Mar-15
4 - MUDMAT MODULARITY• The structure overall size is a constraint for the offshore
deployment.• The mudmat can be quite large and heavy.• The weight of the PLET is increased due to the mudmat (+ 10-
20 MT).• Additional buoyancy is required for the mudmat.• The mudmat is adding a hydrodynamic mass (limit sea states).• The installation time is increased as well as risks to deploy
heavy and large structure.• Solutions :Post-install the foundation on a pre-installed piping module
(patent pending)Pre-install the foundation and land the piping module inside
(patent pending)
17Page 2-Mar-15
4 - MUDMAT MODULARITYPOST-INSTALLED MUDMAT SOLUTION
• Video of installation stages: the piping module exits the stinger, goes in the sagbend transit and lands on seabed, Mudmat is then connected by the top (patent pending)
18Page 2-Mar-15
4- MUDMAT MODULARITYPRE-INSTALLED MUDMAT SOLUTION
Piping module and frame
Mudmat
Piping module and frame
Mudmat module
19Page 2-Mar-15
4- MUDMAT MODULARITYGAINS WITH A MODULAR MUDMAT APPROACH
Geotechnic Pipeline Structure InstallationPost-installed:Mudmat is connected by the top Final settlement of the assembly is enabledby load transfer of piping module on the mudmat
Pre-installed:Mudmat is pre-installed on seabedMudmat settlementoccurs with selfweightof foundation, and further after pipingmodule landing
Both: No size limit to cope with very soft soil
Both:Can be used withS/Reel/J lay modes
Residual plastic strain (S & Reel lay) may induce a pipeline axial rotationBuoys counter the rotation and residual torsion to remain small for mudmatconnection (post-installed case) or piping module tilt (pre-installed case)
Less buoyancyrequired in catenary
Both:There is no size limitation for the mudmat
The piping frame can be sliding on mudmatand accommodate large thermal expansion
Installation is reversible: recovery is possible without overstressing the piping frame
Conception ismodular and can bestandardized
Post-installed:No need to oversize the mudmat for installation tolerances
Pre-installed:Mudmat size needs to account for installation tolerances +/-5m
Both: installedseparately and can bewith a smaller vessel
Lighter and safer to handle with vesselcranes
20Page 2-Mar-15
5 - CONCLUSIONS
• S-Reel-J methods require specific interfaces on PLET/ILT modules for installation.
• Design must take into account these constraints (in pipingand mudmat module) by having common part related to installation method.
• Thinking modular ease the design and installation• The Pre or Post-Installed mudmat modules offers great
flexibility for installation • The Pre and Post-Installed mudmat design are applicable to
S, J or Reel-lay• A separate foundation module allow lighter structure in the
firing line (the structure is easier to handle)
21Page 2-Mar-15
• Thank you for your attention
• Any Questions ?
This presentation only reflects the opinion of its author and does not imply endorsement by the company to which acknowledgements are made.