- 1 -
Maynard Jackson High School Weekly Photo Report
This Week’s Activities – Classroom Building
October 21 – October 27
• Upper level and Main level Science room sink installation is ongoing.
• Kitchen equipment installation has begun.
• Upper Level Corridor VCT installation is ongoing.
• Main Level corridor painting is ongoing.
• Main Level Science Room casework installation is ongoing.
• Theater ceiling painting is complete and lighting is ongoing.
• Lower Level ceiling and wall framing is ongoing.
• Stair 5 wall installation is ongoing.
• Theater entry curtain wall installation is ongoing.
• Roof grading is complete.
Upper Level Corridor
Upper Level Ceiling Tile
Date: October 25, 2013
Client: Atlanta Public Schools
Project Name: Maynard Jackson High School Renovation
Project #: #12-034
Prepared By: Coralys Rodriguez
Distribution: APS Project Team, TWCC Project Team, Perkins & Will, Spurlock & Associates,
Uzun & Case
Comments: October 21st
to October 27th
, 2013 Photo Report
- 2 -
Maynard Jackson High School Weekly Photo Report
Main Level Corridors
Theater Curtain Wall
Kitchen
Theater Entry
- 3 -
Maynard Jackson High School Weekly Photo Report
Stair 5
Roof
This Week’s Activities – Gymnasium
October 21 – October 27
• Main Level C wall framing and drywall installation is ongoing.
• Stair 9 installation is ongoing.
• Joist erection has begun.
• CMU wall installation has begun.
Gym Addition Steel Gym Exterior Walls
- 4 -
Maynard Jackson High School Weekly Photo Report
This Week’s Activities - Sitework
October 21 – October 27
• Glenwood Ave tree planting is complete.
• Service drive tree planting has begun.
• East campus paving is ongoing.
• East campus sidewalks are ongoing.
• Softball field bleacher slabs and flumes are being placed.
East Campus and Softball Field Glenwood Ave Streetscape
Next Week’s Activities
October 28 – November 3
• Joist erection at Gym to continue.
• Roof railings to be complete.
• Upper Level VCT installation to continue.
• Main Level VCT installation to resume.
• Lower Level topping slabs to resume.
• Main Level ceiling installation and painting to continue.
• Lower Level ceiling framing to continue.
• Upper Level Science rooms sink installation to be complete.
Schedule Status • Classroom Building TCO December 1, 2013
• FF&E Deliveries to Start December 2, 2013
• Relocation on Weekends to Start December 7, 2013
• Full Time Relocation to Start December 20, 2013
• Band/Orchestra Corridor TCO December 31, 2013
• Classroom Building Classes Begin January 7, 2014
• Gym CO March 7, 2014
� Project is on schedule to date