- 1 - Maynard Jackson High School Weekly Photo Report This Week’s Activities – Classroom Building October 21 – October 27 Upper level and Main level Science room sink installation is ongoing. Kitchen equipment installation has begun. Upper Level Corridor VCT installation is ongoing. Main Level corridor painting is ongoing. Main Level Science Room casework installation is ongoing. Theater ceiling painting is complete and lighting is ongoing. Lower Level ceiling and wall framing is ongoing. Stair 5 wall installation is ongoing. Theater entry curtain wall installation is ongoing. Roof grading is complete. Upper Level Corridor Upper Level Ceiling Tile Date: October 25, 2013 Client: Atlanta Public Schools Project Name: Maynard Jackson High School Renovation Project #: #12-034 Prepared By: Coralys Rodriguez Distribution: APS Project Team, TWCC Project Team, Perkins & Will, Spurlock & Associates, Uzun & Case Comments: October 21 st to October 27 th , 2013 Photo Report

Maynard Jackson High School - Atlanta Public Schools · • Lower Level topping slabs to resume. • Main Level ceiling installation and painting to continue. • Lower Level ceiling

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Maynard Jackson High School - Atlanta Public Schools · • Lower Level topping slabs to resume. • Main Level ceiling installation and painting to continue. • Lower Level ceiling

- 1 -

Maynard Jackson High School Weekly Photo Report

This Week’s Activities – Classroom Building

October 21 – October 27

• Upper level and Main level Science room sink installation is ongoing.

• Kitchen equipment installation has begun.

• Upper Level Corridor VCT installation is ongoing.

• Main Level corridor painting is ongoing.

• Main Level Science Room casework installation is ongoing.

• Theater ceiling painting is complete and lighting is ongoing.

• Lower Level ceiling and wall framing is ongoing.

• Stair 5 wall installation is ongoing.

• Theater entry curtain wall installation is ongoing.

• Roof grading is complete.

Upper Level Corridor

Upper Level Ceiling Tile

Date: October 25, 2013

Client: Atlanta Public Schools

Project Name: Maynard Jackson High School Renovation

Project #: #12-034

Prepared By: Coralys Rodriguez

Distribution: APS Project Team, TWCC Project Team, Perkins & Will, Spurlock & Associates,

Uzun & Case

Comments: October 21st

to October 27th

, 2013 Photo Report

Page 2: Maynard Jackson High School - Atlanta Public Schools · • Lower Level topping slabs to resume. • Main Level ceiling installation and painting to continue. • Lower Level ceiling

- 2 -

Maynard Jackson High School Weekly Photo Report

Main Level Corridors

Theater Curtain Wall

Kitchen

Theater Entry

Page 3: Maynard Jackson High School - Atlanta Public Schools · • Lower Level topping slabs to resume. • Main Level ceiling installation and painting to continue. • Lower Level ceiling

- 3 -

Maynard Jackson High School Weekly Photo Report

Stair 5

Roof

This Week’s Activities – Gymnasium

October 21 – October 27

• Main Level C wall framing and drywall installation is ongoing.

• Stair 9 installation is ongoing.

• Joist erection has begun.

• CMU wall installation has begun.

Gym Addition Steel Gym Exterior Walls

Page 4: Maynard Jackson High School - Atlanta Public Schools · • Lower Level topping slabs to resume. • Main Level ceiling installation and painting to continue. • Lower Level ceiling

- 4 -

Maynard Jackson High School Weekly Photo Report

This Week’s Activities - Sitework

October 21 – October 27

• Glenwood Ave tree planting is complete.

• Service drive tree planting has begun.

• East campus paving is ongoing.

• East campus sidewalks are ongoing.

• Softball field bleacher slabs and flumes are being placed.

East Campus and Softball Field Glenwood Ave Streetscape

Next Week’s Activities

October 28 – November 3

• Joist erection at Gym to continue.

• Roof railings to be complete.

• Upper Level VCT installation to continue.

• Main Level VCT installation to resume.

• Lower Level topping slabs to resume.

• Main Level ceiling installation and painting to continue.

• Lower Level ceiling framing to continue.

• Upper Level Science rooms sink installation to be complete.

Schedule Status • Classroom Building TCO December 1, 2013

• FF&E Deliveries to Start December 2, 2013

• Relocation on Weekends to Start December 7, 2013

• Full Time Relocation to Start December 20, 2013

• Band/Orchestra Corridor TCO December 31, 2013

• Classroom Building Classes Begin January 7, 2014

• Gym CO March 7, 2014

� Project is on schedule to date