GMP Amendment – Exhibit C – Viera Area ES/RFQ#19-422-Q-DR Page 1 of 4
EXHIBIT C
GUARANTEED MAXIMUM PRICE AMENDMENT
TO
AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES
BY AND BETWEEN
WHARTON-SMITH, INC.
AND
SCHOOL BOARD OF BREVARD COUNTY
2700 JUDGE FRAN JAMIESON WAY
VIERA, FL 32940
PHONE: (321) 633-1000
FAX: (321) 633-4646
FOR THE CONSTRUCTION OF:
VIERA AREA ELEMENTARY SCHOOL
RFQ #19-422-Q-DR
May 15, 2019
GMP Amendment – Exhibit C – Viera Area ES/RFQ#19-422-Q-DR Page 2 of 4
ARTICLE 1. GUARANTEED MAXIMUM PRICE (GMP) 1.1 Guaranteed Maximum Price (GMP): Construction Manager guarantees that it shall not
exceed a Guaranteed Maximum Price (GMP) of Twenty-Two Million, Nine Hundred Sixty-Three
Thousand, Two Hundred Forty-Three Dollars ($22,963,243.00) for the identified Project. 1.2 Basis of the GMP:
1.2.1 Construction Documents: The Scope of Work for the GMP shall be as defined in the Contract
Construction Documents, prepared by Architects RZK, Inc. entitled Brevard Public Schools New Viera
Elementary School and dated February 28, 2019 and revised April 17, 22, 24, 25, 26 and 29, 2019.
1.2.2 List of Construction Documents identified in Article 7 of this Guaranteed Maximum Price
Amendment.
1.2.3 Exceptions, Clarifications and Exclusions: The Scope of Work defined in the Construction
Contract Documents shall be modified and/or clarified as identified in Article 8 of this Guaranteed
Maximum Price Amendment.
1.2.4 Credit for Fill: The Construction Manager agrees to execute a deductive change order in an
amount equivalent to Four Dollars and Fifty Cents ($4.50) per cubic yard of fill provided by The Viera
Company and paid directly by the Owner for use on the Project.
ARTICLE 2. PROJECT TIME 2.1 Substantial Completion Date: Substantial Completion of the Work shall be achieved by June
12, 2020.
2.2 Final Completion Date: Final completion of the Work shall be achieved by September 8,
2020.
2.3 Project Schedule: Attached to this Amendment will be a schedule identifying the above
noted completion times and intermediate milestone dates estimated for the Project. The
proposed schedule shall be integrated into the Construction Manager’s Schedule upon
approval of this Guaranteed Maximum Price Amendment.
ARTICLE 3. CONSTRUCTION MANAGER FEE 3.1 Construction Manager Fee: The Construction Manager Fee for the Project shall be a Lump
Sum of Nine Hundred Twenty-Three Thousand, Nine Hundred Twenty-One Dollars
($923,921.00).
ARTICLE 4. REIMBURSABLE GENERAL CONDITIONS COSTS 4.1 General Conditions: General Conditions costs for the Project shall not exceed One Million,
Three Hundred Thirty-Seven Thousand, Three Hundred Seventy-Six Dollars ($1,337,376.00).
General Conditions costs shall be reimbursed at Construction Manager’s actual cost.
General Conditions costs shall be in compliance with the General Conditions to the
Agreement for Construction Management Services (Exhibit A) and are identified in the
attached document prepared by the Construction Manager.
GMP Amendment – Exhibit C – Viera Area ES/RFQ#19-422-Q-DR Page 3 of 4
ARTICLE 5. LIQUIDATED DAMAGES 5.1 Substantial Completion: Construction Manager shall pay Owner One Thousand Dollars
($1,000.00) as liquidated damages for each day that Substantial Completion extends
beyond the Substantial Completion Date.
5.2 Final Completion: Construction Manager shall pay Owner Five Hundred Dollars ($500.00)
as liquidated damages for each day that Final Completion extends beyond the Final
Completion Date.
ARTICLE 6. PROJECT REPRESENTATIVES 6.1 Owner’s Representative: Owner designates the individual listed below as its Owner’s
Project Manager to provide direct interface with Construction Manager with respect to
Owner’s responsibilities.
David Martin Owner’s Project Manager 6.2 Construction Manager’s Representative: Construction Manager designates the individual listed
below as its Construction Manager’s Representative to provide direct interface with Owner with
respect to Construction Manager’s responsibilities.
David Romero Construction Manager’s Project Manager
ARTICLE 7. LIST OF CONSTRUCTION CONTRACT DOCUMENTS 7.1 Drawings: Listed below are the Drawings developed by the Design Firm and their issue
Date which is the basis of this Guaranteed Maximum Price Amendment:
See attached Wharton-Smith, Inc. proposal dated May 13, 2019
7.2 Specifications: Listed below are the Specification Sections developed by the Design Firm
and their issue Date which is the basis of this Guaranteed Maximum Price Amendment:
See attached Wharton-Smith, Inc. proposal dated May 13, 2019
ARTICLE 8. EXCEPTIONS, EXCLUSIONS AND CLARIFICATIONS 8.1 Exceptions and Exclusions: Listed below are specific Exceptions and Exclusions identified
by the Construction Manager during the development of this Project Design and Bidding:
See attached Wharton-Smith, Inc. proposal dated May 13, 2019
8.2 Clarifications: Listed below are specific Clarifications identified by the Construction
Manager during the development of this Guaranteed Maximum Price:
See attached Wharton-Smith, Inc. proposal dated May 13, 2019
GMP Amendment – Exhibit C – Viera Area ES/RFQ#19-422-Q-DR Page 4 of 4
SIGNATURE PAGE: THE SCHOOL BOARD OF CONSTRUCTION MANAGER: BREVARD COUNTY, FLORIDA: WHARTON-SMITH, INC. By:_____________________________ By:___________________________ Tina Descovich, Chairperson Print Name: ___________________ ATTEST (WITNESS): Title: _________________________ By:_____________________________ Date:_________________________ Mark W. Mullins, Ed.D. Superintendent Date:___________________________ ATTEST (WITNESS): By:___________________________ Print Name:____________________ Title:__________________________ Approved as to form: ___________________________ Amy Envall, General Counsel
END OF EXHIBIT C
Darin A. Crafton
Executive Vice President
05/15/19
Kimberly A. Murray
Administrative Manager
750 Monroe Road, Sanford, FL 32771 I Phone: (407) 321-8410 I Fax: (407) 829-4453
Mailing Address: P.O. Box 471028, Lake Monroe, FL 32747-1028
AL – 45684 I FL - CG C032669 I GA – GCCO 001333 I LA – 52227 I MS – 18232MC I NC – 38755 I SC – G97817 I TN – 62419 I VA – 2705121584A
May 13, 2019
Mrs. Susan Hann
School Board of Brevard County
2700 Judge Fran Jamieson Way
Viera, FL 32940-6699
Re: Construction Management Services for the Viera Area Elementary School ‘V’ Project
GMP Proposal
Dear Sue,
We are pleased to provide the attached Sub-Project Guaranteed Maximum Price (GMP) Proposal for the
Viera Area Elementary School ‘V’ Project for your review and approval.
Please contact us with any questions regarding this GMP. We look forward to working with you on this
project.
Sincerely,
Wharton-Smith, Inc.
Johnathan Wilkes
Sr. Project Manager
GUARANTEED MAXIMUM PRICE PROPOSAL FOR
SCHOOL BOARD OF BREVARD COUNTY
Construction Management Services for the Viera Area Elementary School ‘V’ Project
SUBMITTED BY: WHARTON-SMITH, INC.
DATE: May 13, 2019
1
School Board of Brevard County Construction Management Services for the Viera Area Elementary School ‘V’ Project
TABLE OF CONTENTS Exhibit C GMP Summary ......................................................................................... Section 01 Exhibit C-1 List of Contract Documents ................................................................ Section 02 Exhibit C-2 Description of Work ............................................................................. Section 03 Specification Listing ..................................................................................................... 3.1 Qualifications and Assumptions ................................................................................... 3.2 Exclusions .................................................................................................................... 3.3 Value Engineering Recommendations ......................................................................... 3.4 Allowance Schedule ..................................................................................................... 3.5 Add Alternate Schedule ............................................................................................... 3.6 ODP Schedule ............................................................................................................. 3.7 GMP Cost Summary ................................................................................................ Section 04 Master Project Schedule ......................................................................................... Section 05
RFQ #19-422-Q-DR Page 1 of 47 05/13/19
1
SECTION 01
GMP Summary
The Viera Area Elementary School ‘V’ Project to be located on a new campus at 8300 Stadium Parkway in Viera, Florida 32940. The Guaranteed Maximum Price (GMP) encompasses the following scope of services; The project includes site development, utilities and improvements including but not limited to site fill, paved drives, parking area, sidewalks, covered walkway canopies, ramps, curbs, exterior signage, electrical service and utilities to the structure. The new main structure is a single story building of reinforced precast concrete tilt wall system on concrete footings, with a slab on grade. The main frame and roof structure are products of a pre-engineered metal building (PEMB) manufacturer. The exterior material include a standing seam metal roof and the exterior face of the concrete tilt wall system shall have a texture coating. The interior finishes include a suspended acoustical tile ceiling, painted and textured gypsum wallboard on furring or metal stud framing. Floors are specified to be covered with VCT, carpet, porcelain tile or epoxy paint. Interior doors are solid core with some specialty doors. The HVAC system includes water cooled chillers, cooling towers, pumps, AHU’s and VAV’s with ducted supply and return air. The Plumbing System includes toilet fixtures, work sinks and condensate as well as the various piping systems for sanitary sewer and domestic water distribution. The Electrical System includes power for convenience and theatre systems, lighting for ordinary Illumination and theatre production and wiring for various theatre communication systems. The exterior will have a hardscape and landscaping.
RFQ #19-422-Q-DR Page 2 of 47 05/13/19
COV Cover Sheet 2/28/2019
C-101 Overall Site Plan 2/28/2019
C-102 Site and Striping Plan 2/28/2019 4/29/19 (BA4)
C-103 Site and Striping Plan 2/28/2019
C-104 Site and Striping Plan 2/28/2019
C-105 Paving and Drainage Plan 2/28/2019 4/24/2019 (BA 3)
C-106 Paving and Drainage Plan 2/28/2019 4/24/2019 (BA 3)
C-107 Paving and Drainage Plan 2/28/2019
C-108 Paving and Drainage Plan 2/28/2019 4/24/2019 (BA 3)
C-109 Water, Sanitary and Reuse Plan 2/28/2019
C-110 Water, Sanitary and Reuse Plan 2/28/2019
C-111 Water, Sanitary and Reuse Plan 2/28/2019
C-501 Paving and Drainage Details 2/28/2019 4/29/19 (BA4)
C-502 Water Details 2/28/2019
C-503 Water Details 2/28/2019
C-505 Sanitary Details 2/28/2019
C-506 Lift Station Details 2/28/2019
AS-1.0 Architectural Site Plan and SMEP Sheet Index 2/28/2019
LS-0.0 Life Safety Code Compliance Information 2/28/2019
LS-0.1 Life Safety Code Compliance Information 2/28/2019
LS-0.2 Life Safety Code Compliance Information 2/28/2019
LS-1.0 Life Safety Site Plan 2/28/2019
LS-2.0 Life Safety Plan – School 2/28/2019
LS-2.1 Life Safety Plan – Covered Plan 2/28/2019
LS-2.2 Life Safety Plan – Mech. Yard 2/28/2019
L-101 Landscape Plan (BA1) 2/28/2019 4/19/2019 (BA1)
L-102 Landscape Plan (BA1) 2/28/2019 4/19/2019 (BA1)
L-103 Landscape Plan (BA1) 2/28/2019 4/19/2019 (BA1)
L-104 Landscape Plan (BA1) 2/28/2019 4/19/2019 (BA1)
L-105 Landscape Plan (BA1) 2/28/2019 4/19/2019 (BA1)
1A-1.0 School Dimension Floor Plan 2/28/2019
1A-1.1 Enlarged Dim. Floor Plan – Multi-Purpose 2/28/2019
PLANS
EXHIBIT C-1
SECTION 02
CONTRACT DOCUMENTS
Sheet No Sheet TitleDate of
IssueRevised
RFQ #19-422-Q-DR Page 3 of 47 05/13/19
EXHIBIT C-1
SECTION 02
CONTRACT DOCUMENTS
1A-1.2 Enlarged Dim. Floor Plan – Administration 2/28/2019
1A-1.3 Enlarged Dim. Floor plan – Classrooms 2/28/2019
1A-1.4 School Reference Floor Plan 2/28/2019
1A-1.5 Enlarged Ref. Floor Plan – Multi-Purpose 2/28/2019
1A-1.6 Enlarged Kitchen Floor Plan 2/28/2019
1A-1.7 Enlarged Ref. Floor Plan – Administration 2/28/2019
1A-1.8 Enlarged Ref. Floor Plan – Classrooms 2/28/2019
1A-1.9 Enlarged Ref. Floor Plan – Classrooms 2/28/2019
1A-1.10 Enlarged Ref. Floor Plan – Classrooms 2/28/2019
1A-1.11 Enlarged Ref. Floor Plans – Restrooms 2/28/2019
1A-1.12 Mechanical Mezzanine Floor Plan and Details 2/28/2019
1A-1.13 Plan Details 2/28/2019
1A-2.0 School Reflected Ceiling Plan 2/28/2019
1A-2.1 Enlarged RCP – Multi-Purpose 2/28/2019
1A-2.2 Enlarged RCP – Administration 2/28/2019
1A-2.3 Enlarged RCP - Classrooms 2/28/2019
1A-2.4 Enlarged RCP – Classroom 2/28/2019
1A-3.0 School Roof Plan 2/28/2019
1A-4.0 School Exterior Elevations 2/28/2019
1A-5.0 School Building Sections 2/28/2019
1A-5.1 Building Sections 2/28/2019
1A-6.0 School Wall Section 2/28/2019
1A-6.1 School Wall Sections 2/28/2019
1A-7.0 School Interior Elevations 2/28/2019
1A-7.1 School Interior Elevations 2/28/2019
1A-7.2 School Interior Elevations 2/28/2019
2A-1.0 Covered Play Floor Plan 2/28/2019
2A-2.0 Covered Play Reflected Ceiling Plan 2/28/2019
2A-3.0 Covered Play Roof Plan 2/28/2019
2A-4.0 Covered Play Exterior Elevations 2/28/2019
2A-5.0 Covered Play Building Section 2/28/2019
2A-6.0 Covered Play Wall Sections 2/28/2019
2A-7.0 Covered Play Interior Elevations 2/28/2019
3A-1.0 Mech Yard Floor Plan 2/28/2019
3A-2.0 Mech Yard Reflected Ceiling Plan 2/28/2019
RFQ #19-422-Q-DR Page 4 of 47 05/13/19
EXHIBIT C-1
SECTION 02
CONTRACT DOCUMENTS
3A-3.0 Mech Yard Roof Plan 2/28/2019
3A-4.0 Mech Yard Exterior Elevations 2/28/2019
3A-5.0 Mech Yard Building Section 2/28/2019
A-8.0 Door Schedule and Types 2/28/2019
A-8.1 Door Details 2/28/2019
A-8.2 Window Schedule, Types and Details 2/28/2019
A-8.3 Window Details 2/28/2019
A-10.0 Wall Types 2/28/2019
A-10.1 Wall Types 2/28/2019
A-10.2 Wall Types 2/28/2019
A-10.3 Wall Types 2/28/2019
A-10.4 Wall Types 2/28/2019
1S-0.1 Structural Index, Abbreviations, and Symbols 2/28/2019
1S-0.2 Structural Notes 2/28/2019
1S-0.3 Structural Notes 2/28/2019
1S-0.4 Structural Notes 2/28/2019
1S-0.5 Wind Load Diagram 2/28/2019
1S-1.0 Foundation / Slab Plan 2/28/2019
1S-2.0 Roof Framing Plan 2/28/2019
1S-3.0 Enlarged Mezzanine Plans 2/28/2019
2S-1.0 Covered Play Foundation / Slab & Roof Framing Plan 2/28/2019
3S-1.0 Chiller Building Structural Plans 2/28/2019
S-3.0 Structural Sections 2/28/2019
S-4.0 Structural Details 2/28/2019
S.4.1 Structural Details 2/28/2019
S.4.2 Structural Details 2/28/2019
S.4.3 Structural Details 2/28/2019
S.4.4 Structural Details 2/28/2019
S.4.5 Structural Details 2/28/2019
S.4.6 Structural Details 2/28/2019
RFQ #19-422-Q-DR Page 5 of 47 05/13/19
EXHIBIT C-1
SECTION 02
CONTRACT DOCUMENTS
P-0.1 Plumbing Legend & General Notes 2/28/2019
P-1.0 Level 1 – Plumbing Plan –Domestic Water – Overall 2/28/2019
P-1.1 Level 1 – Plumbing Plan – Domestic Water – Area A 2/28/2019
P-1.2 Level 1 – Plumbing Plan – Domestic Water – Area B 2/28/2019
P-1.3 Level 1 – Plumbing Plan – Domestic Water – Area C 2/28/2019
P-1.4 Level 1 – Plumbing Plan – Domestic Water – Area D 2/28/2019
P-1.5 Level 1 – Plumbing Plan – Domestic Water – Area E 2/28/2019
P-1.6 Level 1 – Plumbing Plan – Domestic Water – Area F 2/28/2019
P-1.7 Level 1 – Plumbing Plan – Domestic Water – Chiller Plant 2/28/2019
P-2.0 Level 1 – Plumbing Plan – Sanitary – Overall 2/28/2019
P-2.1 Level 1 – Plumbing Plan – Sanitary – Area A 2/28/2019
P-2.2 Level 1 – Plumbing Plan – Sanitary – Area B 2/28/2019
P-2.3 Level 1 – Plumbing Plan – Sanitary – Area C 2/28/2019
P-2.4 Level 1 – Plumbing Plan – Sanitary – Area D 2/28/2019
P-2.5 Level 1 – Plumbing Plan – Sanitary – Area E 2/28/2019
P-2.6 Level 1 – Plumbing Plan – Sanitary - Area F 2/28/2019
P-2.7 Level 1 – Plumbing Plan – Sanitary – Chiller Plant 2/28/2019
P-2.8 Mezzanine Level – Plumbing Plan – Sanitary 2/28/2019
P-4.0 Plumbing Schedules 2/28/2019
P-5.0 Plumbing Details 2/28/2019
P-5.1 Plumbing Details 2/28/2019
P-5.2 Plumbing Details 2/28/2019
P-5.3 Plumbing Details 2/28/2019
M-0.1 Mechanical Legend and Notes 2/28/2019
M-1.0 Level 1 – Mechanical Overall Plan 2/28/2019
M-1.1 Level 1 – Mechanical Plan – Area A 2/28/2019
M-1.2 Level 1 – Mechanical Plan – Area B 2/28/2019
M-1.3 Level 1 – Mechanical Plan – Area C 2/28/2019
M-1.4 Level 1 – Mechanical Plan – Area D 2/28/2019
M-1.5 Level 1 – Mechanical Plan – Area E 2/28/2019
M-1.6 Level 1 – Mechanical Plan – Area F 2/28/2019
M-1.7 Level 1 – Mechanical Plan – Chiller Plant / PE Building 2/28/2019
M-1.8 Mezzanine Level – Mechanical Plan 2/28/2019
M-2.0 Level 1 – Mechanical Overall Piping Plan 2/28/2019
M-5.0 Mechanical Details 2/28/2019
RFQ #19-422-Q-DR Page 6 of 47 05/13/19
EXHIBIT C-1
SECTION 02
CONTRACT DOCUMENTS
M-5.1 Mechanical Details 2/28/2019
M-5.2 Mechanical Details 2/28/2019
M-6.0 Mechanical Controls 2/28/2019
M-7.0 Mechanical Schedules 2/28/2019
M-7.1 Mechanical Schedules 2/28/2019
E-0.1 Electrical Legend 2/28/2019
E-0.2 Electrical Notes 2/28/2019
E-0.3 Lighting Fixture Schedule 2/28/2019
ES-1.0 Site Lighting Plan 2/28/2019
ES-2.0 Site Power Plan 2/28/2019
ES-5.0 Site Lighting Details 2/28/2019
ES-5.1 Site Power Details 2/28/2019
EL-1.0 Level 1 – Overall Electrical Lighting Plan 2/28/2019
EL-1.1 Level 1 – Lighting Plan – Area A 2/28/2019
EL-1.2 Level 1 – Lighting Plan – Area B 2/28/2019
EL-1.3 Level 1 – Lighting Plan – Area C 2/28/2019
EL-1.4 Level 1 – Lighting Plan – Area D 2/28/2019
EL-1.5 Level 1 – Lighting Plan – Area E 2/28/2019
EL-1.6 Level 1 – Lighting Plan – Area F 2/28/2019
EL-1.7 Lighting Plan Mezzanine 2/28/2019
EL-1.8 Level 1 – Lighting Plan – Chiller Plant & Covered Play 2/28/2019
EL-5.0 Electrical Lighting Details 2/28/2019
EP-1.0 Level 1 – Overall Electrical Power Plan 2/28/2019
EP-1.1 Level 1 – Power Plan – Area A 2/28/2019
EP-1.2 Level 1 – Power Plan – Area B 2/28/2019
EP-1.3 Level 1 – Power Plan – Area C 2/28/2019
EP-1.4 Level 1 – Power Plan – Area D 2/28/2019
EP-1.5 Level 1 – Power Plan – Area E 2/28/2019
EP-1.6 Level 1 – Power Plan – Area F 2/28/2019
EP-1.7 Electrical Plan Mezzanine 2/28/2019
EP-1.8 Level 1 – Power Plan – Chiller Plant & Covered Play 2/28/2019
EP-5.0 Electrical Power Details 2/28/2019
EP-5.1 Electrical Power Details 2/28/2019
EP-5.2 Electrical Power Details 2/28/2019
EP-6.0 Electrical One-Line Diagram 2/28/2019
RFQ #19-422-Q-DR Page 7 of 47 05/13/19
EXHIBIT C-1
SECTION 02
CONTRACT DOCUMENTS
EP-6.1 Feeder Schedule 2/28/2019
E-7.0 Electrical Panel Schedules 2/28/2019
E-7.1 Electrical Panel Schedules 2/28/2019
E-7.2 Electrical Panel Schedules 2/28/2019
E-7.3 Electrical Panel Schedules 2/28/2019
E-7.4 Electrical Panel Schedules 2/28/2019
E-7.5 Electrical Panel Schedules 2/28/2019
E-7.6 Electrical Panel Schedules 2/28/2019
T-0.1 Technology Legend 2/28/2019
T-0.2 Technology Notes 2/28/2019
TA-1.0 Level 1- Overall A/V and Security Plan 2/28/2019
TA-1.1 Level 1 – A/V and Security Plan – Area A 2/28/2019
TA-1.2 Level 1 – A/V and Security Plan – Area B 2/28/2019
TA-1.3 Level 1 – A/V and Security Plan – Area C 2/28/2019
TA-1.4 Level 1 – A/V and Security Plan – Area D 2/28/2019
TA-1.5 Level 1 – A/V and Security Plan – Area E 2/28/2019
TA-1.6 Level 1 – A/V and Security Plan – Area F 2/28/2019
TA-1.7 Level 1 – A/V and Security Plan – Chiller Plant 2/28/2019
TA-5.0 A/V and Security Details 2/28/2019
TA-5.1 A/V and Security Details 2/28/2019
TA-5.2 A/V and Security Details 2/28/2019
TN-1.0 Level 1 – Overall Voice Data Plan 2/28/2019
TN-1.1 Level 1- Voice Data Plan – Area F 2/28/2019
TS-1.0 Site Technology Plan 2/28/2019
TN-1.2 Level 1 – Voice Data Plan – Area B 2/28/2019
TN-1.3 Level 1 – Voice Data Plan – Area C 2/28/2019
TN-1.4 Level 1- Voice Data Plan – Area D 2/28/2019
TN-1.5 Level 1 – Voice Data Plan – Area E 2/28/2019
TN-1.6 Level 1 – Voice Data Plan – Area F 2/28/2019
TN-1.7 Level 1 – Voice Data Plan – Chiller Plant 2/28/2019
TN-1.8 Voice Data Plan Mezzanine 2/28/2019
TN-4.0 Voice Data Enlarged Plans 2/28/2019
TN-5.0 Voice Data Details 2/28/2019
TN-5.1 Voice Data Details 2/28/2019
TN-5.2 Voice Data Details 2/28/2019
RFQ #19-422-Q-DR Page 8 of 47 05/13/19
EXHIBIT C-1
SECTION 02
CONTRACT DOCUMENTS
TN-5.3 Voice Data Details 2/28/2019
TN-5.4 Voice Data Details 2/28/2019
TN-5.5 Voice Data Details 2/28/2019
TN-5.6 Voice Data Details 2/28/2019
Type Name
RFI Pre-Bid RFI #1
RFI Pre-Bid RFI #2
Addenda Addendum 1
Addenda Addendum 2
Addenda Addendum 3
Addenda Addendum 4
Addenda Addendum 5
Modification List
Date
4/29/2019
4/29/2019
4/25/2019
4/24/2019
4/22/2019
4/26/2019
4/17/2019
RFQ #19-422-Q-DR Page 9 of 47 05/13/19
Division Description
TITLE PAGE
DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS
00 30 00 AVAILABLE INFORMATION (Universal Engineering Sciences Report)
05 52 33 AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER
00 90 10 PROJECT FORMS
DIVISION 01 GENERAL REQUIREMENTS
36535 SUMMARY OF THE WORK
36547 ALTERNATES
36556 SCHEDULES, REPORTS, PAYMENTS
40209 OWNER DIRECT PURCHASE PROGRAM
01 33 00 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES
01 40 00 QUALITY CONTROL SERVICES
01 41 00 PROJECT COORDINATION
01 42 00 DEFINITIONS AND STANDARDS
01 50 00 TEMPORARY FACILITIES
01 60 00 PRODUCTS AND SUBSTITUTIONS
01 60 01 ZERO TOLERANCE HAZARDOUS MATERIALS STATEMENT
01 74 19 CONSTRUCTION WASTE MANAGEMENT
01 77 00 PROJECT CLOSEOUT
01 77 10 FLOOR CARE
DIVISION 02 EXISTING CONDITIONS – NOT USED
DIVISION 03 CONCRETE
36595 CONCRETE FORMING AND ACCESSORIES
36605 CONCRETE REINFORCING
36615 CAST-IN-PLACE CONCRETE
03 47 13 TILT-UP CONCRETE
DIVISION 04 MASONRY
36638 CONCRETE UNIT MASONRY
DIVISION 05 METALS
36658 STRUCTURAL STEEL FRAMING
36677 STEEL DECKING
05 50 00 METAL FABRICATIONS
05 52 00 GUARDRAILS AND HANDRAILS
DIVISION 06 WOOD, PLASTICS, AND COMPOSITES
06 10 13 WOOD BLOCKING, GROUNDS & FURRING
06 40 23 ARCHITECTURAL LAMINATE CASEWORK
06 65 00 RECYCLED PLASTIC LUMBER
SPECIFICATIONS
SECTION 3.1
SPECIFICATION LISTING
RFQ #19-422-Q-DR Page 10 of 47 05/13/19
SECTION 3.1
SPECIFICATION LISTING
DIVISION 07 THERMAL AND MOISTURE PROTECTION
07 11 13 BITUMINOUS DAMPPROOFING
07 21 00 BATT INSULATION
07 21 13 RIGID WALL INSULATION
07 23 13 FOIL FACED SEMI-RIGID WALL INSULATION
07 27 00 FIRE STOPPING
07 84 00 SPRAY-ON FIREPROOFING
07 84 10 FIRE RATED PENETRATIONS & JOINTS
07 90 00 JOINT SEALERS
DIVISION 08 OPENINGS
08 10 00 HOLLOW METAL FRAMES
08 11 00 HOLLOW METAL DOORS
08 20 00 WOOD DOORS
08 21 00 HARDBOARD FACED DOORS
08 31 00 ACCESS DOORS
08 40 90 ALUMINUM ENTRANCES AND STOREFRONTS (COASTALCOUNTIES)
08 52 10 ALUMINUM WINDOWS
08 71 00 FINISH HARDWARE
08 80 00 GLASS AND GLAZING (INTERIOR)
DIVISION 09 FINISHES
09 12 00 CEILING SUSPENSION SYSTEMS
09 12 50 INTERIOR NON-BEARING METAL FRAMING
09 24 00 LATH AND STUCCO
09 29 00 GYPSUM DRYWALL
09 29 10 INTERIOR TILE BACKER BOARD
09 30 00 CERAMIC TILE
09 40 00 SOLID SURFACE COUNTERTOPS
09 51 13 ACOUSTICAL CEILING PANELS
09 54 10 ACOUSTICAL INSULATION
09 65 00 RESILIENT FLOORING
09 68 13 CARPET TILE
09 77 11 ACOUSTICAL WALL PANELS
09 91 00 PAINTING
DIVISION 10 SPECIALTIES
10 11 00 MARKERBOARDS
10 14 00 IDENTIFYING DEVICES
10 14 10 SITE SIGNAGE
10 21 13 SOLID PLASTIC COMPARTMENTS/PARTITIONS
10 22 26 MANUAL OPERABLE PARTITION
RFQ #19-422-Q-DR Page 11 of 47 05/13/19
SECTION 3.1
SPECIFICATION LISTING
10 26 13 HIGH IMPACT CORNER GUARDS
10 28 00 TOILET AND BATH ACCESSORIES
10 44 00 FIRE EXTINGUISHERS & CABINETS
10 51 13 METAL LOCKERS
10 67 00 SHELVING
10 75 00 FLAGPOLE(S)
DIVISION 11 EQUIPMENT
11 40 30 FOOD SERVICE EQUIPMENT
11 52 13 MANUAL PROJECTION SCREENS
11 52 14 MOTORIZED PROJECTION SCREENS
11 61 43 ACOUSTICAL CURTAINS AND TRACK
DIVISION 12 FURNISHINGS
12 93 13 BICYCLE RACKS
DIVISION 13 SPECIAL CONSTRUCTION
13 34 19 PRE-ENGINEERED METAL BUILDING SYSTEM
DIVISION 14 CONVEYING EQUIPMENT – NOT USED
DIVISION 21 FIRE SUPPRESSION
42876 SLEEVES AND SLEEVE SEALS FOR FIRE-SUPPRESSION PIPING
43241 ESCUTCHEONS FOR FIRE-SUPPRESSION PIPING
45067 GENERAL-DUTY VALVES FOR FIRE PROTECTION PIPING
47259 HANGERS & SUPPORTS FOR FIRE SUPRESSION PIPING & EQUIP.
56025 IDENTIFICATION FOR FIRE-SUPPRESSION PIPING & EQUIPMENT
21 13 13 WET-PIPE SPRINKLER SYSTEMS
DIVISION 22 PLUMBING
22 05 17 SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING
22 05 18 ESCUTCHEONS FOR PLUMBING PIPING
22 05 19 METERS AND GAGES FOR PLUMBING PIPING
22 05 23.12 BALL VALVES FOR PLUMBING PIPING
22 05 29 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIP.
22 05 53 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
22 11 16 DOMESTIC WATER PIPING
22 11 19 DOMESTIC WATER PIPING SPECIALTIES
22 13 16 SANITARY WASTE AND VENT PIPING
22 13 19 SANITARY WASTE PIPING SPECIALTIES
22 33 00 ELECTRIC, DOMESTIC-WATER HEATERS
22 34 00 FUEL-FIRED, DOMESTIC-WATER HEATERS
RFQ #19-422-Q-DR Page 12 of 47 05/13/19
SECTION 3.1
SPECIFICATION LISTING
DIVISION 23 HEATING, VENTILATING & AIR CONDITIONING (HVAC)
23 05 19 METERS AND GAGES FOR HVAC PIPING
23 05 23.12 BALL VALVES FOR HVAC PIPING
23 05 23.13 BUTTERFLY VALVES FOR HVAC PIPING
23 05 23.14 CHECK VALVES FOR HVAC PIPING
23 05 23.15 GATE VALVES FOR HVAC PIPING
23 05 29 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
23 05 48.13 VIBRATION CONTROLS FOR HVAC
23 05 53 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
23 05 93 TESTING, ADJUSTING AND BALANCING FOR HVAC
23 07 13 DUCT INSULATION
23 07 19 HVAC PIPING INSULATION
23 08 00 COMMISSIONING OF HVAC
23 09 23 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 23.11 CONTROL VALVES
23 09 23.12 CONTROL DAMPERS
23 09 23.14 FLOW INSTRUMENTS
23 11 23 FACILITY NATURAL-GAS PIPING
23 21 13 HYDRONIC PIPING
23 21 16 HYDRONIC PIPING SPECIALTIES
23 21 23 HYDRONIC PUMPS
23 23 00 REFRIGERANT PIPING
23 25 13 WATER TREATMENT FOR CLOSED-LOOP HYDRONIC SYSTEMS
23 25 16 WATER TREATMENT FOR OPEN-LOOP HYDRONIC SYSTEMS
23 31 13 METAL DUCTS
23 33 00 AIR DUCT ACCESSORIES
23 33 46 FLEXIBLE DUCTS
23 34 16 CENTRIFUGAL HVAC FANS
23 36 00 AIR TERMINAL UNITS
23 37 13.13 AIR DIFFUSERS
23 37 13.23 REGISTERS AND GRILLES
23 37 23 HVAC GRAVITY VENTILATORS
23 38 13 COMMERCIAL-KITCHEN HOODS
23 64 23.16 WATER-COOLED, SCROLL WATER CHILLERS
23 65 14.13 COOLING TOWERS
23 73 13.13 INDOOR, BASIC AIR-HANDLING UNITS
23 81 26 SPLIT-SYSTEM AIR-CONDITIONERS
23 82 19 FAN COIL UNITS
RFQ #19-422-Q-DR Page 13 of 47 05/13/19
SECTION 3.1
SPECIFICATION LISTING
DIVISION 26 ELECTRICAL
26 00 10 BASIC ELECTRICAL REQUIREMENTS
26 05 19 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
26 05 23 CONTROL-VOLTAGE ELECTRICAL POWER CABLES
26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 05 33 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
26 05 44 SLEEVES&SLEEVESEALSFORELECTRICALRACEWAYS&CABLING
26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS
26 05 73 OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY
26 05 74 OVERCURRENT PROTECTIVE DEVICE ARC-FLASH STUDY
26 08 00 COMMISSIONING OF ELECTRICAL
26 09 23 LIGHTING CONTROL DEVICES
26 22 00 LOW-VOLTAGE TRANSFORMERS
26 24 13 SWITCHBOARDS
26 24 16 PANELBOARDS
26 27 26 WIRING DEVICES
26 28 13 FUSES
26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
26 29 13.03 MANUAL AND MAGNETIC MOTOR CONTROLLERS
26 29 23 VARIABLE-FREQUENCY MOTOR CONTROLLERS
26 32 13 ENGINE GENERATORS
26 36 00 TRANFER SWITCHES
26 41 13 LIGHTNING PROTECTION FOR STRUCTURES
26 43 13 SURGEPROTECTIONFORLOW-VOLTAGEELECTRICALPOWERCIRCUITS
26 51 00 INTERIOR LIGHTING
26 56 13 LIGHTING POLES AND STANDARDS
26 56 19 LED EXTERIOR LIGHTING
DIVISION 27 COMMUNICATIONS
27 05 26 GROUNDING AND BONDING FOR COMMUNICATIONS SYSTEMS
27 05 28 PATHWAYS FOR COMMUNICATIONS SYSTEMS
27 05 29 HANGERS AND SUPPORTS FOR COMMUNICATIONS SYSTEMS
27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
27 05 44 SLEEVES&SLEEVESEALSFORCOMMUNICATIONSPATHWAYS&CABLING
27 05 53 IDENTIFICATION FOR COMMUNICATIONS SYSTEMS
27 11 00 COMMUNICATIONS EQUIPMENT ROOM FITTINGS
27 11 16 COMMUNICATIONS RACKS, FRAMES AND ENCLOSURES
27 13 13 COMMUNICATIONS COPPER BACKBONE CABLING
27 13 23 COMMUNICATIONS OPTICAL FIBER BACKBONE CABLING
RFQ #19-422-Q-DR Page 14 of 47 05/13/19
SECTION 3.1
SPECIFICATION LISTING
27 15 13 COMMUNICATIONS COPPER HORIZONTAL CABLING
27 51 23.50 EDUCATIONAL INTERCOMMUNICATIONS & PROGRAM SYSTEMS
27 53 19 DISTRIBUTED ANTENNA INFRASTRUCTURE
DIVISION 28 ELECTRONIC SAFETY AND SECURITY
28 15 00 ACCESS CONTROL HARDWARE DEVICES
28 20 00 VIDEO SURVEILLANCE
28 46 21.11 ADDRESSABLE FIRE-ALARM SYSTEMS
DIVISION 31 EARTHWORK
36830 SITE CLEARING
31 20 00 EARTH MOVING
31 23 20 DEWATERING
31 25 00 EROSION AND SEDIMENT CONTROL
31 31 16 TERMITE CONTROL
31 63 16 AUGER CAST GROUT PILES
DIVISION 32 EXTERIOR IMPROVEMENTS
48564 ASPHALT PAVING
32 13 13 CONCRETE PAVING
32 31 13 CHAIN LINK FENCES AND GATES
DIVISION 33 UTILITIES
33 10 00 WATER UTILITIES
33 30 00 SANITARY SEWERAGE UTILITIES
33 41 00 STORM UTILITY DRAINAGE PIPING
RFQ #19-422-Q-DR Page 15 of 47 05/13/19
1
SECTION 03
Description of Work
3.2 Qualifications and Assumptions
The following is a summary of Qualifications and Assumptions:
1. The cost of staff identified in the General Conditions not stationed on site, but working exclusively on the project, shall be reimbursed by the SBBC as shown in the attached General Conditions exhibit.
2. The cost of suitable import fill dirt material available on the adjacent property and calculated into this GMP proposal is $4.50 per cubic yard.
3. If any additional fill dirt materials are required and not immediately available at the cost of $4.50 per cubic yard, then additional costs per cubic yard will be required and paid by the Owner.
4. The GMP Proposal includes $46,730 for independent material testing and inspections.
5. The GMP Proposal includes $26,250 for Engineer’s threshold inspections & testing.
6. The GMP Proposal only includes provisions for independent material testing and threshold Inspections. Any other testing or inspections are not included within the GMP Budget.
RFQ #19-422-Q-DR Page 16 of 47 05/13/19
1
SECTION 03
Description of Work
3.3 Exclusions
The following is a listing of Exclusions;
1. The GMP excludes any FF&E, including but not limited to, Furniture, Kiln, Technology, Flat Panel Teaching Displays, Televisions, Phones, Computers, and DVD/VCR Players.
2. The GMP excludes any emergency generator, automatic transfer switches and fuel tanks.
3. The GMP excludes any and all liquid propane tanks and Stage 1 gas regulators.
4. The GMP excludes any temporary utilities or infrastructure if TVC has not completed their work on time and provide availability when required to service project requirements.
5. The GMP excludes removal of unsuitable soils or other unknown hazardous conditions.
6. Removal of “casual water” (normal rainwater) is included in the GMP, however, mass site dewatering, well pointing, mud pumping and subterranean drilling of any type is not included.
7. The GMP excludes 3rd Party Commissioning of any type (note: the GMP does include Threshold Inspections).
8. The GMP excludes any provisions for wall covering or wall paper.
9. The GMP excludes any provisions for an irrigation system.
10. The GMP excludes the cost of Permitting, Permit Expediting and Impact fees.
11. The GMP excludes the cost of any start-up chemicals.
12. The GMP excludes the cost of any start-up electric consumption charges.
RFQ #19-422-Q-DR Page 17 of 47 05/13/19
1
SECTION 03
Description of Work
3.4 Value Engineering Recommendations
Final Design Documents include value management ideas discussed by the project team and School Board of Brevard County during the design development process. These value management items have been incorporated into the Guaranteed Maximum Price Proposal through the inclusion of the current contract documents as listed in the Exhibit C-1 Section 02 List of Contract Documents and Section 3.1 Specifications Listing.
RFQ #19-422-Q-DR Page 18 of 47 05/13/19
1
SECTION 03
Description of Work
3.5 Allowance Schedule
1. Evacuation Gate Entrance Allowance ........................................................... $10,000.
2. Play Court Surfacing Allowance ...................................................................... $4,872.
3. Monument Sign Allowance ($25,000 Signage/$25,000 Electrical/Data) ........ $50,000.
4. Flagpole Allowance…………………………………………………………………..$4,412.
5. Audio Visual Equipment Allowance ................................................................. $6,000.
6. Athletic Equipment Allowance………………………………………………………$3,600.
7. Playground Surfacing & Equipment Allowance ............................................. $87,574.
8. Primary Electric Power Allowance ................................................................. $25,000.
9. Lightning Protection Allowance……………………………………………………$15,000.
10. Access Control Systems Allowance .............................................................. $50,000.
RFQ #19-422-Q-DR Page 19 of 47 05/13/19
1
SECTION 03
Description of Work
3.6 Add Alternates Schedule
The following is a summary of Add Alternates which have been incorporated into the GMP Estimate:
1. Provide add alternate for the Covered Play canopy and the restrooms, office, storage and electrical rooms. 2. Provide add alternate for black vinyl coated fencing in lieu of the aluminized coated fencing. 3. Provide deduct for VCT with vinyl base in all locations that are indicated to be porcelain tile floor with porcelain tile base. 4. Provide add alternate for acoustical wall treatments (AWT) within Multi-Purpose / Dining – 200 and Hall – 205. 5. Provide add alternate for the water cooled chillers to have low delivery water temperature option. 6. Provide a ground rod based lightning protection system for the entire facility. See Section 3.5 Allowance Schedule, Item 9. 7. Provide electronic controlled LED school marquis sign with message board. See Section 3.5 Allowance Schedule, Item 3. 8. Provide add for conduits for future connections associated with covered play building.
RFQ #19-422-Q-DR Page 20 of 47 05/13/19
1
SECTION 03
Description of Work
3.7 ODP Schedule
The Owner Direct Purchase (ODP) Values for this project will be determined ASAP and submitted following the GMP approval. Please see below for the estimated amounts; Estimated Owner Direct Purchases (ODP) $3,800,000.00 Estimated Sales & Sur Tax $228,750.00 Total Estimated Owner Direct Purchases (ODP) with Taxes $4,028,750.00
RFQ #19-422-Q-DR Page 21 of 47 05/13/19
1
SECTION 04
GMP Cost Summary
SEE ATTACHED
RFQ #19-422-Q-DR Page 22 of 47 05/13/19
WHARTON-SMITH CONSTRUCTION GROUP
GMP Estimate
New Viera ES
DIVISION
LINE DESCRIPTION TOTAL
1 Site Earthwork, Utilities & Paving 3,170,493
2 Landscaping 202,247
3 Fencing & gates 78,053
4 Concrete & Masonry 1,711,986
5 Architectural Laminate Casework 451,437
6 Damproofing & Sealants 54,200
7 Spray Applied Fireproofing 13,500
8 Doors, Frames & Hardware 550,178
9 Glass & Glazing 729,821
10 Drywall & Stucco 1,919,086
11 Acoustical Ceilings & Wall Panels 439,977
12 Resilient tile & carpet 383,815
13 Painting 264,570
14 Visual Display & Marker Boards 71,583
15 Identifying Devices 68,832
16 Toilet Partitions & Accessories 115,520
17 Fire Extinguishers & Cabinets 6,870
18 Lockers & Metal Storage Shelving 2,390
19 Flagpoles (Allowance) 4,412
20 Food Service Equipment 281,721
21 Audio Visual Equipment (Allowance) 6,000
22 Stage Curtains 6,858
23 Athletic Equipment (Allowance) 3,600
24 Pre-Engineered Metal Building 2,983,806
25 Horizontal Louver Blinds 10,202
26 Bicycle Storage Racks 8,860
27 Playground Surfacing & Equipment (Allowance) 87,574
28 Fire Protection 206,345
29 Plumbing 1,160,760
30 HVAC 2,424,870
31 Test & Balance 29,780
32 Electrical 2,952,600
33 Total Direct Cost 20,401,946
34 General Conditions 1,116,527
35 General Liability Insurance 68,890
36 Builders Risk 22,734
37 Bond 129,225
38 Total Adjusted Cost 21,739,322
39 CM Fee 923,921
40 Contingency 300,000
41 Total Construction Cost 22,963,243
RFQ #19-422-Q-DR Page 23 of 47 05/13/19
WHARTON-SMITH CONSTRUCTION GROUP
GMP Estimate
New Viera ES
LINE DESCRIPTION QTY UNIT TOTALS
42 Site Earthwork, Utilities & Paving
43
44
45
46 Survey & control
47 Layout 802,383 sf 80,238
48 Certified as-builts 802,383 sf 24,553
49 Erosion Control
50 Type III silt fence 4,946 lf 4,946
51 Inlet protection 40 ea 8,800
52 Maintain thru duration of project 11 mo 2,200
53 Soil Track Prev device @ 2 locations 68 sy 812
54 Dust control for 2/3 time 26 wk 9,152
55 Earthwork & Grading
56 Strip site 6" 20,060 cy 50,149
57 Reuse stripping @ 80% 16,048 cy 36,107
58 Export excess stripping 4,012 cy 32,095
59 Cut 2,134 cy 5,335
60 Fill 63,202 cy 158,005
61 Import fill (Fill provided by TVC @ 4.5/CY and left near site) 49,867 cy 224,403
62 Compact building pad 14,480 cy 21,720
63 Compact sidewalk & walkways 3,171 sy 4,757
64 Rough grade 89,154 sy 66,865
65 Fine grade 66,865 sy 100,298
66 Storm system
67 6" Downspout Stub and Cap 40 ea 4,400
68 WYE 6" FOR DOWNSPOUT 1,265 lf 18,089
69 4" PERFORATED 402 lf 10,062
70 12" PVC 922 lf 23,969
71 15" PVC 366 lf 10,253
72 6" RCP 143 lf 2,868
73 8" RCP 500 lf 12,093
74 12" RCP 213 lf 5,851
75 15" RCP 140 lf 4,912
76 18" RCP 885 lf 43,811
77 24" RCP 996 lf 65,731
78 30" RCP 373 lf 30,773
79 36" RCP 80 lf 8,184
80 12" x 15" INCREASER 1 ea 550
81 CO's 14 ea 9,240
82 Connect to existing pipe 2 ea 2,000
83 FES (flared end section) 6 ea 18,000
84 TYPE D INLET 6 ea 22,800
85 TYPE C INLET 10 ea 35,000
86 CURB INLET GRATE 9 ea 49,500
87 MANHOLE 3 ea 22,500
88 CONTROL STRUCTURE CS-1-D (MODIFIED TYPE D CATCH BASIN) 1 ea 3,500
89 18" X 18" YARD DRAIN 10 ea 32,000
RFQ #19-422-Q-DR Page 24 of 47 05/13/19
90 Trench Drain @ play courts 121 lf 11,495
91 Testing 5,734 lf 11,468
92 Dewatering - Installation 5,734 lf 29,535
93 Dewatering - Fuel & Maintain 57 dy 8,601
94 Potable Water
95 Water main 12" 1,260 lf 27,721
96 Water main 10" 385 lf 7,622
97 Water main 6" 361 lf 4,765
98 Water main 4" 163 lf 1,613
99 16" X 12" TAPPING SADDLE W/ GV 1 ea 3,500
100 2" METER 1 ea 1,000
101 2" RPBFP 1 ea 2,500
102 6" X 4" REDUCER 1 ea 500
103 8" GV 1 ea 1,500
104 8" STUB W/ BLIND FLANGE 1 ea 2,500
105 10" X 4" TEE 1 ea 500
106 12" 45° BEND 1 ea 750
107 12" GV 1 ea 2,000
108 12" X 8" TEE 1 ea 1,000
109 4" 90° BEND 1 ea 500
110 Testing 1,328 lf 2,656
111 Dewatering - Installation 2,169 lf 13,013
112 Dewatering - Fuel & Maintain 22 dy 3,470
113 Fire
114 PVC fire line 8" 352 lf 6,977
115 PVC fire line 6" 111 lf 1,827
116 FDC 1 ea 2,800
117 FH assembly 3 ea 10,800
118 6" 45° BEND 2 ea 1,000
119 6" 90° BEND 2 ea 1,000
120 6" DDCA 1 ea 10,000
121 6" GV 5 ea 7,500
122 6" PLUG 1 ea 2,500
123 6" TEE 2 ea 1,500
124 8" 45° BEND 1 ea 600
125 8" X 6" REDUCER 1 ea 750
126 8" X 6" TEE 2 ea 1,500
127 12" X 6" TEE 1 ea 1,000
128 12" X 10" REDUCER 1 ea 1,000
129 Testing 463 lf 926
130 Dewatering - Installation 463 lf 2,779
131 Dewatering - Fuel & Maintain 5 dy 741
132 Gravity Sewer Main
133 8" PVC C-900 227 lf 16,996
134 8" PVC 737 lf 35,390
135 6" PVC 310 lf 9,299
136 4" PVC 109 lf 2,727
137 Sanitary Manhole 4 ea 20,000
138 Cleanout 6" 1 ea 600
139 8" Cap for future use 1 ea 1,500
140 Testing 1,022 lf 2,045
141 Dewatering - Installation 914 lf 5,482
142 Dewatering - Fuel & Maintain 9 dy 1,462
143 Force Sewer Main
144 FORCE MAIN 6" 740 lf 37,000
RFQ #19-422-Q-DR Page 25 of 47 05/13/19
145 PUMP STATION 1 1 ea 240,000
146 12" X 6" TAPPING SADDLE W/ GV 1 ea 3,000
147 Testing 740 lf 1,480
148 Dewatering - Installation 740 lf 4,440
149 Dewatering - Fuel & Maintain 7 dy 1,184
150 Temporary Stabilized roadways for construction
151 6" crushed concrete for crane road 16,644 sy 149,800
152 Maintain 8 mo 6,400
153 Paving
154 HD Pavement @ Bus loop & asocc. parking 13,832 sy 525,614
155 LD Pavement @ Parent loop & service yard 12,745 sy 407,855
156 Pavement Markings
157 4" solid white stripe 6,800 lf 2,720
158 6" solid white stripe 1,056 lf 422
159 B06 18" chevrons 0 lf 0
160 24" stop bar - thermoplastic 77 lf 1,538
161 B08 directional arrow 31 ea 2,945
162 12" crosswalk, painted onsite - thermoplastic 302 lf 4,530
163 ADA parking symbol & sign 9 ea 2,205
164 Letters - No parking fire lane 17 ea 1,615
165 Traffic signage 17 ea 1,785
166 12" crosswalk, painted off-site - thermoplastic 75 lf 1,125
167 Site concrete
168 Modified Type F Curb 12,387 lf 222,957
169 Type A curb 258 lf 4,127
170 Wheel stops 6 ea 210
171 Bike Rack (Moved to Division 10) 8 ea
172 Approved Alternates ea
173 Alt #4. PEMB Covered Play Area Civil Work 1 ls 28,300
174 ea
175 ea
176 0
177 Bond 3,206,685 $ 64,134
178 Adjusted total 1 LS (100,326)
179 0
180 0
181 0
182 Subtotal - Site Earthwork, Utilities & Paving 3,170,493
RFQ #19-422-Q-DR Page 26 of 47 05/13/19
183 Landscaping
184
185
186 Trees 98 ea 58,800
187 Shrubs 1,042 ea 17,714
188 Groundcover 347 sf 2,429
189 Bahia sod 421,673 sf 126,502
190 Mulch 4" deep 170 cy 6,800
191 Soils Testing for Fertilizer 1 ls 1,500
192 Soil amendments 347,057 sf 3,471
193 Irrigation 0 0
194 Irrigated area 0 sf 0
195 Sleeves 0 lf 0
196 Maintenance 8 trips 8,000
197 0
198 0
199 Bond 225,215 $ 4,504
200 Adjusted total 1 LS (27,473)
201 0
202 0
203 0
204 Subtotal - Landscaping 202,247
205 Fencing & gates
206
207
208 6' high galv chain link fence (TVC to pay upcharge) 2,342 lf 42,156
209 6' high galv chain link fence @ propane tank 60 ea 1,080
210 6' high galv chain link fence @ chiller yard 20 ea 360
211 4' high galv chain link fence @ playground 250 ea 3,750
212 20' wide, dble swing, CL gate 1 ea 2,000
213 12' wide, dble swing, CL gate 1 ea 1,200
214 6' wide, dble swing, CL gate 3 ea 1,800
215 4' wide, dble swing, CL gate 1 ea 400
216#1 Typical Security Gate Allowance - (2) 48" wide x 6' tall.
(Allowance) 1 ls 10,000
217 Chiller Yard 10' Dbl Gate 2 ea 2,400
218 Dumpster Gates 12'-4" Dbl 2 ea 4,800
219 Approved Alternates ea
220 Alt # C-1. Black Coating Added to aluminized fencing 1 ls 17,260
221 ea
222 ea
223 0
224 0
225 0
226 Bond 87,206 $ 1,744
227 Adjusted total 1 LS (10,897)
228 0
229 0
230 0
231 Subtotal - Fencing & gates 78,053
RFQ #19-422-Q-DR Page 27 of 47 05/13/19
232 Concrete & Masonry
233
234 Concrete
235 MAIN BUILDING 0
236 Building Foundation Pads 0
237 F3 - 3'-0" x 3'-0" x 1'-0" 7 ea 1,982
238 F4 - 4'-0" x 4'-0" x 1'-4" 12 ea 5,943
239 F4.5 - 4'-6" x 4'-6" x 1'-6" 12 ea 8,108
240 F5 - 5'-0" x 5'-0" x 1'-6" 36 ea 29,210
241 F6 - 6'-0" x 6'-0" x 1'-6" 12 ea 14,534
242 F7 - 6'-0" x 6'-0" x 1'-8" 2 ea 3,321
243 F8.4 - 8'-0" x 4'-0" x 1'-6" 2 ea 2,127
244 F9 - 9'-0" x 9'-0" x 2'-0" 4 ea 11,917
245 F10 - 10'-0" x 10'-0" x 2'-0" 22 ea 78,974
246 F11 - 11'-0" x 11'-0" x 2'-0" 4 ea 17,489
247 F12 - 12'-0" x 12'-0" x 2'-0" 2 ea 10,191
248 Continuous Footers
249 WFST 1'-6"x Cont. 1'-0" at Stage 208 lf 9,035
250 Slabs
251 4" Slab On grade on 15mil VB W/6x6-W2.9 x w2.9 wwf 113,606 sf 550,048
252 4" Elevated Stage Slab 1,480 sf 10,279
253 Courtyard and Entry Slabs 9,268 sf 46,340
254 Second floor, 3 1/2", normal weight, reinforced Mezzanine 4,841 sf 33,781
255 Covered Play Area (Add Alternate)
256 MFX.X - 8'-0" x 8'-0" x 3'-3" @ covered play canopy Pads 10 ea 0
257 Chiller Plant Building
258 WF2.0 - 2'-0" x Cont x 1'-0" 84 lf 4,343
259 WF3 - 3'-0" x Cont x 1'-0" 144 lf 15,690
260 WF4 - 4'-0" x Cont x 1'-0" 73 lf 9,840
261 Tie beams x 16" (Rake, room separation and tie-beams ) 367 lf 20,837
262 5" Slab On grade on 15mil VB W/6x6-W2.9 x w2.9 wwf 3,028 lf 15,140
263 TS1.33 Interior Mono Ftg. 64 lf 4,025
264 Dumpster & Compactor Enclosure
265 WF6 - 6'-0" x Cont x 1'-4" 208 lf 208
266 5" Slab On grade on 15mil VB W/6x6-W2.9 x w2.9 wwf 620 sf 3,100
267 Miscellaneous Concrete
268 Stage/ramp/stairs 178 sf 24,823
269 Mechanical pads 8" 180 sf 1,620
270 Mechanical pads 4" 806 sf 7,250
271 Termite treatment 122,538 sf 24,508
272 Slab thickened edge @ stage 210 lf 8,564
273 Stair nosing install (furnished by others) 146 lf 491
274 Concrete pan filled stairs 146 sf 1,095
275 Concrete Filled Landings 2 sf 650
276 Site Concrete Paving
277 4" Sidewalks 21,494 sf 112,844
278 Off-site 4" Sidewalks 7,045 sf 36,986
279 ADA ramps 377 sf 1,979
280 Bicycle enclosure SOG 2,582 sf 12,910
281 School Sign Footing 10 lf 50
282 Lift Pump Concrete Cap & Driveway 925 sf 6,475
283 Basketball goal installation 2 ea 300
284 Bollard installation 9 ea 4,500
285 Propane Tank Slab 1 ea 1,500
RFQ #19-422-Q-DR Page 28 of 47 05/13/19
286 Building Tilt-Wall Panels, Including Embeds, Erection, Bracing, etc.
287 Casting slabs and removal sf 0
288 Panels, 5 1/2" (Net Area Measured) 30,871 sf 432,187
289 Embeds (panel-panel, panel-foundation) 30,871 sf 3,087
290 Grout @ panel base 71 cf 3,557
291 Grout @ panel side 233 cf 11,650
292 Layout 0
293 Fine grading 0
294 Excavate & Backfill 0
295 Install H/M frames in tiltwalls (supply by others) 0
296 Masonry
297 Main Campus
298 Stage Stemwall 2 block height 279 sf 3,910
299 Interior Doorways to 10'-8" height 650 sf 9,100
300 Column Wrap w/Downspouts 373 sf 5,221
301 Central Energy Plant 0 0
302 14' CMU With 1'-4" TB finishing height @ 15'-4" 1,013 sf 14,177
303 11'-4" AVG with 1'-4" Rake Beam 1,405 sf 19,669
304 10'-0" CMU plus 1'-4" TB 263 sf 3,682
305 9'-0" CMU with BB at Dumpster 915 sf 12,814
306 9'-0" CMU with BB at Cooling Tower 605 sf 8,467
307 8'-8" CMU with 1'-4" TB finishing height 10'-0" 1,254 sf 17,558
308 Approved Alternates ea
309 Alt #4. PEMB Covered Play Area Concrete Work 1 ls 56,170
310 Alt #4. PEMB Covered Play Area Masonry Work 1 ls 24,375
311 ea
312 0
313 Bond 1,778,631 $ 35,573
314 Adjusted total 1 LS (102,217)
315
316
317
318 Subtotal - Concrete & Masonry 1,711,986
319 Architectural Laminate Casework
320
321
322 Base Cabinets 2,366 lf 473,200
323 Wall Cabinets 1,340 lf 234,500
324 Cubie Cabinet 336 lf 84,000
325 Counter Tops 2,693 sf 201,975
326 Upper level Counter12" Wide 43 lf 5,375
327 Tall storage cabinet (36x24x72) Solid Door 112 ea 61,600
328 Tall storage cabinet (36x24x72) Open 1/2 56 ea 25,200
329 Tall storage cabinet (36x24x72) Open 1/2 @ Music 1 ea 450
330 Tall storage cabinet (60x24x72) Solid Door @ Resource 3 ea 2,250
331 0 0
332 Bond 1,088,550 $ 0
333 Adjusted total 1 LS (637,113)
334 0
335 0
336 0
337 Subtotal - Architectural Laminate Casework 451,437
RFQ #19-422-Q-DR Page 29 of 47 05/13/19
338 Damproofing & Sealants
339
340
341
342 Ext wall joint Backer Rod and Caulking
343 CMU 15 ft 165 sf 371
344 SOG control joints 9,932 lf 19,865
345 Floor expansion joints 3,135 lf 6,270
346 Tilt Wall & CMU Bituminous Coating 1 ls 28,000
347 Sidewalk to building 741 lf 1,112
348 Sidewalk expansion joints 250 lf 375
349
350 Bond 55,993 $ 0
351 Adjusted total 1 LS (1,793)
352 0
353 0
354 0
355 Subtotal - Damproofing & Sealants 54,200
356 Spray Applied Fireproofing
357
358 Spray Applied Fireproofing
359 Columns/beams/joists at Mezzanine 3,028 sf 13,626
360 Protect vented deck/clean floors 4,000 sf 3,000
362
363 Bond 16,626 $ 333
364 Adjusted total 1 LS (3,459)
366 0
367 0
368 Subtotal - Spray Applied Fireproofing 13,500
369 Doors, Frames & Hardware
370
371 EXTERIOR
372 Hollow Metal
373 4070 G90 Type H1 1 ea 300
374 3070 G90 Type H4 1 pr 600
375 3070 G90 Type H5 60 Minute Fire Rated 1 pr 325
376 3070 G90 Type 6 6 pr 2,100
377 4070 G90 HM Frame 1 ea 150
378 6070 G90 HM Frame 7 ea 2,100
379 6070 G90 HM Frame 60 minute Fire Rated 1 ea 300
380 INTERIOR
381 3070 A60 Type H1 HM 12 ea 3,600
382 3070 A60 Type H5 7 pr 2,100
383 3070 A60 HM Frames 12 ea 1,800
384 6070 A60 HM Frames 7 ea 2,100
385 3070 A60 HM Frames 140 ea 21,000
386 3070 60 Minute Fire Rated HM Frames 56 ea 8,400
387 3070 20 Minute Fire Rated HM Frames 58 ea 8,700
388 6070 60 Minute Fire Rated HM Frames 10 ea 3,000
389 6870 60 Minute Fire Rated HM Frames 5 ea 1,625
390 6070 20 Minute Fire Rated HM Frames 1 ea 325
391 WOOD DOORS
392 3070 Flush Type M1- Paint Grade Hardboard 131 ea 45,850
393 3070 Flush with UL 60 Minute 6 ea 2,100
394 3070 flush with DLO Type M2 1 ea 350
RFQ #19-422-Q-DR Page 30 of 47 05/13/19
395 ROTARY CUT BIRCH TRANSPARENT
396 3070 Flush Type W1 60 Minute 11 ea 4,400
397 3070 Flush Type 20 Minute 6 ea 2,400
398 3070 Flush 6 ea 2,400
399 3070 flush with DLO Type W2 2 ea 800
400 3070 flush with DLO UL 20 Minute 52 ea 20,800
401 3070 flush with DLO UL 60 Minute 39 ea 15,600
402 3070/3070 UL 60 Minute Type W5 1 pr 400
403 3070/3070 UL 60 Minute Type W6 9 pr 3,600
404 3470/3470 UL 60 Minute 5 pr 2,000
405 3070/3070 UL 20 Minute 1 pr 400
406 Door Covers and Protection 1 ls 4,500
407 Hollow Metal Interior Windows 56 ea 28,000
408 Hardware 298 ea 149,000
409 Installation Doors and Hardware 1 ls 95,000
410 Approved Alternates ea
411 Alt #4. PEMB Covered Play Area Doors & Hardware 1 ls 9,000
412 0
413 Bond 445,125 $ 8,903
414 Adjusted total 1 LS 96,150
416 0
417 Subtotal - Doors, Frames & Hardware 550,178
418 Glass & Glazing
419
420
421 Door Glazing 0 0
422 View Lite (2'8" x 0'3") - based on 80% 138 sf 8,280
423 Glazing @ Exterior HM Storefront 0 0
424 Window Type A 12'-0 x 5'-6" 3,168 sf 269,280
425 Window Type C 5'-0 x 3'-6" 35 sf 2,975
426 Window Type F Punch 9'-0" x 4'-8" w/Sliding Panes 42 sf 3,573
427 Window Type G Punch 4'-4" x 2'-8" 12 sf 985
428 Window Type H Punch 3'-0" x 3'-6" 21 sf 1,785
429 Aluminum Storefront 0 0
430 Alum - Exterior storefront 14.0 x 12.0 115 sf 10,898
431 Alum - Exterior storefront 26.5 x 12.0 234 sf 22,230
432 Alum - Exterior storefront 27.0 x 12.0 0 sf 0
433 Alum Storefront doors - single 4 ea 10,400
434 Alum Storefront doors - double 0 ea 0
435 0 0
436 0 0
437 Bond 330,406 $ 6,608
438 Adjusted total 1 LS 392,807
439 0
440 0
441 0
442 Subtotal - Glass & Glazing 729,821
RFQ #19-422-Q-DR Page 31 of 47 05/13/19
443 Drywall & Stucco
444
445
446 Drywall 0 0
447 GWB on tilt 21,000 sf 115,500
448 Stucco on 20 CMU Columns 1,400 sf 35,000
449 GWB partition to 12 ft 50,148 sf 413,721
450 GWB partition Smoke Partition Wall 12ft 18,084 sf 159,139
451 GWB partition Smoke Partition Wall 20ft 11,500 sf 103,500
452 GWB partition Fire Wall 20ft 22,640 sf 215,080
453 GWB partition Fire Wall 25ft 11,125 sf 110,138
454 GWB Smoke Envelop Ceiling Lid 1A-5.-0 12,605 sf 63,025
455 GWB bulkheads 10,135 sf 50,675
456 GWB ceilings 6,672 sf 40,032
457 GWB soffits 4,450 sf 26,700
458 Antimicrobial Wall Panels 1,599 sf 13,989
459 Approved Alternates ea
460 Alt #4. PEMB Covered Play Area Drywall 1 ls 11,900
461 0
462 0 0
463 0 0
464 Bond 1,358,398 $ 27,168
465 Adjusted total 1 LS 533,520
466 0
467 0
468 0
469 Subtotal - Drywall & Stucco 1,919,086
470 Acoustical Ceilings & Wall Panels
471
472 24" x 24" Lay-In Acoustical Panel w/ Suspended Grid 91,856 sf 321,496
473 24" x 24" Lay-In Acoustical Panel w/ Suspended Grid - 1hr Fire Rated 15,205 sf 76,025
474 24" x 48" Lay-In Acoustical Panel w/ Suspended Grid - Moisture Resistant 2,415 sf 9,056
475 Acoustical Sound Panels @ Multipurpose (See Alternates) 0 sf 0
476 Acoustical Sound Panels @ Music 2,052 sf 28,728
477 Acoustical Sound Panels @ Classroom AWT 600 sf 8,400
478 Acoustical Sound Panels @ classrooms AWT-3 0 sf 0
479 Acoustical Sound Panels @ classrooms AWT-4 0 sf 0
480 Approved Alternates ea
481 Alt #10. Acoustical Sound Panels @ Multipurpose 1 ls 25,850
482 0
484 Bond 469,555 $ 9,391
485 Adjusted total 0 LS (38,969)
486
487
489 Subtotal - Acoustical Ceilings & Wall Panels 439,977
RFQ #19-422-Q-DR Page 32 of 47 05/13/19
490 Resilient tile & carpet
491
492
493 Flooring
494 Carpet tile 11,699 sf 49,720
495 Vinyl Treads and Risers 299 sf 10,465
496 Stage risers 184 sf 6,440
497 Porcelain Tile 95,156 sf 880,193
498 Quarry Tile 2,375 sf 21,371
499 Vinyl Comp. Tile @ stage 1,042 sf 2,605
500 Wall Tile 0 0
501 Porcelain tile - wainscot height at wet walls 2,693 sf 28,277
502 Porcelain tile - full height - wet walls - group RR 0 sf 0
503 Porcelain tile - full height - dry walls - group RR 0 sf 0
504 Porcelain tile - wainscot at wet walls - small RR 0 sf 0
505 Porcelain tile - wainscot at wet walls - classroom RR 0 sf 0
506 Porcelain tile - full height at wet walls - classroom RR 0 sf 0
507 Base 0 0
508 VB - Vinyl Base 13,452 lf 24,214
509 Quarry Tile Base 1,500 lf 13,500
510 VB - Vinyl Base 1,130 lf 2,034
511 0 0
512 Window Sills -Marble 0 0
513 Window Sills 0 lf 0
514 Window Type A 12'-0 x 5'-6" 576 lf 10,368
515 Window Type C 5'-0 x 3'-6" 10 lf 180
516 Window Type F Punch 9'-0" x 4'-8" w/Sliding Panes 9 lf 162
517 Window Type G Punch 4'-4" x 2'-8" 5 lf 96
518 Window Type H Punch 3'-0" x 3'-6" 6 lf 108
519 0 0
520 Floor Prep 110,754 sf 33,226
521 Floor Protection 110,754 sf 27,689
522 Approved Alternates ea
523 Alt #4. PEMB Covered Play Flooring 1 ls 13,730
524 Alt # A-8 Deduct to use VCT ILO porcelain flooring (Exclude Restrooms) 1 ls (720,130)
525 0
526 0 0
527 0 0
528 Bond 404,246 $ 8,085
529 Adjusted total 1 LS (28,517)
530 0
531 0
532 0
533 Subtotal - Resilient tile & carpet 383,815
RFQ #19-422-Q-DR Page 33 of 47 05/13/19
534 Painting
535
536 Interior Paint
537 GWB on tilt 18,900 sf 12,285
538 GWB partition to 12 ft 66,865 sf 43,462
539 GWB partition to 20 ft 23,915 sf 15,545
540 GWB partition 25 ft 29,814 sf 19,379
541 GWB bulkheads 10,135 sf 6,588
542 GWB ceilings 7,194 sf 5,396
543 GWB soffits 4,450 sf 3,338
544 Panels, 5 1/2" @ main bldg 30,871 sf 38,588
545 Panels, 6 1/4" @ CEP 1,578 sf 1,973
546 Panels, 6 1/4" @ CEP Yard & Dumpster screen walls 1,719 sf 2,149
547 Exposed structure 6,123 sf 6,123
548 Play Court Sidelines and Markings (Allowance) 1 ls 4,872
549 Hollow Metal Frames 314 ea 12,560
550 HM Doors 88 ea 6,600
551 Bollard Safety Yellow 9 ea 360
552 Seal block 6,884 sf 2,065
553 Seal concrete 10,562 sf 3,697
554 Approved Alternates ea
555 Alt #4. PEMB Covered Play Area Painting Work 1 ls 11,300
556 ea
557 ea
558 0 0
559 0 0
560 Bond 196,279 $ 3,926
561 Adjusted total 1 LS 64,365
562 0
563 0
564 0
565 Subtotal - Subtotal - Resilient tile & carpet 264,570
566 Visual Display & Marker Boards
567
568
569 Tack board (4'x4') 56 ea 8,120
570 Tack strip (1.5") 56 ea 6,720
571 MB-6 Marker board (4'x6') 126 ea 63,000
572 0 0
573 0 0
574 Bond 77,840 $ 0
575 Adjusted total 1 LS (6,257)
576 0
577 0
578 0
579 Subtotal - Visual Display & Marker Boards 71,583
RFQ #19-422-Q-DR Page 34 of 47 05/13/19
580 Identifying Devices
581
582
583 Signage 0 0
584 Room name/number 314 ea 29,830
585 S-2 Evac map 10 ea 500
586 RR 6 ea 300
587 No storage 2 ea 100
588 In case of fire - stair sign 2 ea 100
589 Stair sign 4 ea 200
590 Roof access 1 ea 50
591 Max capacity 10 ea 500
592 Secured access 2 ea 100
593 FAAP 1 ea 50
594 Monument sign LED Controlled (Allowance) 1 ls 25,000
595 16" Alum letters "School Name" 30 ea 2,466
596 16" Alum letters numeric street address 4 ea 329
597 16" Alum letters building number 3 ea 247
598 0 0
599 Plaque 1 ea 1,980
600
601 Bond 61,751 $ 0
602 Adjusted total 1 LS 7,081
603 0
604 0
605 0
606 Subtotal - Identifying Devices 68,832
607 Toilet Partitions & Accessories
608
609
610 Toilet Partitions
611 ADA Compartment 4 ea 3,600
612 Standard compartment 9 ea 6,300
613 Urinal Screen 1 ea 250
614 Toilet Accessories
615 A-4 42" Horizontal grab bar 152 ea 11,400
616 A-6 Waste receptacle 30 ea 2,700
617 A-7 Surface mounted hand towel dispenser w/ attachable receptacle 147 ea 40,425
618 A-8 Mop racks 8 ea 240
619 A-12 18"x30" L-shaped horiz grab bar 3 ea 225
620 A-14 Toilet paper dispenser 88 ea 13,200
621 A-15 Surface mounted san napkin disposal 22 ea 3,850
622 A-16 Soap dispenser 154 ea 23,100
623 A-17 Folding shower seat 3 ea 675
624 A-20 Mirror 16"x24" 92 ea 13,800
625 A-21 Shower Curtain & Rod 3 ea 300
626 A-23 Robe hook 88 ea 3,080
627 Poster frame installation 2 400
628 Hufcor Partition Wall -Price from Hufcor (W/O Closet Door) 1 ea 19,050
629 Corner guard (Vinyl 96" w/2" leg @ corridor, high traffic areas, cafeteria) 223 ea 7,805
630 0 0
631 Bond 150,400 $ 0
632 Adjusted total 1 LS (34,880)
634 0
635 0
RFQ #19-422-Q-DR Page 35 of 47 05/13/19
636 Subtotal - Toilet Partitions & Accessories 115,520
637 Fire Extinguishers & Cabinets
638
639
640 Fire extinguisher - bracket mounted 19 ea 1,206
641 Fire extinguisher - wall mounted Type K 1 ea 165
642 Fire extinguisher & cabinet - recess mounted 14 ea 2,450
643 Defibrillator 3 3,750
644 Knoxbox 1 400
646 0 0
647 Bond 7,971 $ 0
648 Adjusted total 1 LS (1,101)
650 0
651 0
652 Subtotal - Fire Extinguishers & Cabinets 6,870
653 Lockers & Metal Storage Shelving
654
655
656 Lockers and benches 0 0
657 Employee lockers (12x15x72) 5 ea 1,200
658 A4 - "heavy duty" shelving units 0 ea 0
659 0 0
660 0 0
661 Bond 1,200 $ 0
662 Adjusted total 1 LS 1,190
663 0
664 0
665 0
666 Subtotal - Lockers & Metal Storage Shelving 2,390
667 Flagpoles (Allowance)
668
669 0
670 Flagpole - 30' 1 ea 2,500
671 Flagpole setup, alignment, & installation 1 ls 1,912
672 0 0
673 0 0
674 Bond 4,412 $ 0
675 Adjusted total 0 LS 0
676 0
677 0
678 0
679 Subtotal - Flagpoles (Allowance) 4,412
680 Food Service Equipment
681
682
683 Serving Line Cashier 1 ea 2,200
684 Serving Line Frost Top 1 ea 10,600
685 Serving Line Countertop 1 ea 7,200
686 Serving Line Four Well Hot Top 1 ea 10,500
687 Mixer 1 ea 7,900
688 Mixer 1 ea 16,000
689 Slicer 1 ea 4,600
690 Food Cutter 1 ea 5,400
691 Range 1 ea 3,100
692 Reach In Refrigerator 1 ea 9,700
RFQ #19-422-Q-DR Page 36 of 47 05/13/19
693 Proofer/Hot Box 3 ea 11,100
694 Platform Scale 1 ea 1,250
695 Power Wash Sink 1 ea 13,200
696 Bun Pan Rack 2 ea 950
697 Bun Pan Rack 3 ea 1,500
698 Work Table 7 ea 3,955
699 Produce Sink 1 ea 2,500
700 Faucet 1 ea 300
701 Pot Rack Table 1 ea 1,870
702 Steamer 1 ea 16,500
703 Kettle 1 ea 15,200
704 Faucet 1 ea 150
705 Convection Oven 4 ea 58,000
706 Ice/Machine Bin 1 ea 3,200
707 Walk-in Cooler & Freezer 1 ea 25,000
708 Dunnage Rack 1 ea 165
709 Shelving 1 ea 260
710 Washer 1 ea 780
711 Dryer 1 ea 700
712 Reach-in Freezer 1 ea 10,500
713 Salad Bar 1 ea 5,000
714 Milk Cooler 1 ea 0
715 Soda Cooler 1 ea 0
716 Ice Cream Freezer 1 ea 0
717 Gas Hoses 1 ea 1,650
718 Installation 1 ea 20,000
719 0 0
720 0 0
721 Bond 270,930 $ 5,419
722 Adjusted total 1 LS 5,372
723 0
724 0
725 Subtotal - Food Service Equipment 281,721
726 Audio Visual Equipment (Allowance)
727
728 Recess mounted projection screens 12x9 2 ea 5,000
729 Projector Mounting Plate 2 ea 1,000
730 Flat panel monitors 0 0
731 0 0
732 Bond 6,000 $ 0
733 Adjusted total 0 LS 0
734 0
735 0
736 0
737 Subtotal - Audio Visual Equipment (Allowance) 6,000
738 Stage Curtains
739
740 Theatrical curtain & track package 1 ls 12,000
741 0 0
742 0 0
743 Bond 12,000 $ 0
744 Adjusted total 1 LS (5,142)
745 0
746 0
747 Subtotal - Stage Curtains 6,858
RFQ #19-422-Q-DR Page 37 of 47 05/13/19
748 Athletic Equipment (Allowance)
749 See Addendum #1
750
751
752 Basketball backboards & posts 2 ea 3,600
753 0 0
754 0 0
755 0 0
756 Bond 3,600 $ 0
757 Adjusted total 1 LS 0
758 0
759 0
760 0
761 Subtotal - Athletic Equipment (Allowance) 3,600
762 Pre-Engineered Metal Building
763
764
765
766 Pre-engineered metal building
767 Main frames 124,399 sf 497,596
768 Purlins 131,571 sf 394,713
769 Girts 4,104 lf 49,248
770 Girt subframe behind fascia panels @ tilt wall 9,101 sf 27,304
771 Fascia panels 9,101 sf 45,506
772 Standing seam roof 131,571 sf 1,598,588
773 Roof insulation 131,571 sf 460,499
774 Wall insulation 9,101 sf 25,028
775 Gutters 1,852 lf 33,336
776 Downspouts 13'-6" 405 lf 7,290
777 Downspouts 10'-6" 63 lf 1,134
778 Mezzanine Columns, Base Plates & Beams 0 0
779 Connection Angles and Bracing 3 tons 9,873
780 Metal decking, corrugated, 1-1/2" 20 Ga G60 VL (floor) 4,769 sf 10,730
781 Embeds, panel to steel frame 1 ls 25,000
782 118A Stair, steel pan with handrail 1 fl 9,000
783 118B Stair, steel pan with handrail 1 fl 9,000
784 Miscellaneous steel 1 ls 29,263
785 Pad Anchor Bolts ( 20"x3/4" Galvanized) 640 ea 7,680
786 Tiebeam Anchor Bolts (12"x5/8"Galv.) 80 ea 640
787 Approved Alternates ea
788 Alt #4. PEMB Covered Play Area PEMB Work 1 ls 135,000
789 ea
790 ea
791 0
792 0 0
793 Bond 3,376,428 $ 67,529
794 Adjusted total 1 LS (460,151)
795 0
796 0
797 0
798 Subtotal - Pre-Engineered Metal Building 2,983,806
RFQ #19-422-Q-DR Page 38 of 47 05/13/19
799 Horizontal Louver Blinds
800
801
802
803 Window Blinds
804 Window Type A 12'-0 x 5'-6" 48 sf 240
805 Window Type C 5'-0 x 3'-6" 2 sf 10
806 Window Type G Punch 4'-4" x 2'-8" 2 sf 10
807 Window Type H Punch 3'-0" x 3'-6" 2 sf 10
808 0 0
809 0 0
810 Bond 270 $ 0
811 Adjusted total 1 LS 9,932
812 0
813 0
814 0
815 Subtotal - Horizontal Louver Blinds 10,202
816 Bicycle Storage Racks
817
818 Bicycle storage rack 16 ea 12,000
819 Installation 16 ea 1,600
820 0 0
821 0 0
822 Bond 13,600 $ 0
823 Adjusted total 1 LS (4,740)
824 0
825 0
826 0
827 Subtotal - Bicycle Storage Racks 8,860
828 Playground Surfacing & Equipment (Allowance)
829
830
831 Tot Lot Surfacing - artificial mulch 3,090 sf 9,270
832 Gravel base 0 tn 0
833 Concrete border curb 238 lf 3,332
834 Youth Play lot - artificial mulch 6,084 sf 18,252
835 Gravel base 0 tn 0
836 Concrete ribbon curb 330 lf 4,620
837 Play structure @ tot lot 1 ls 20,000
838 Play structure @ youth play 1 ls 32,000
839 Shade structure @ tot lot 0 ls 0
840 Shade structure @ youth play 0 ls 0
841 0 0
842 0 0
843 Bond 87,474 $ 1,749
844 Adjusted total 1 LS (1,649)
845 0
846 0
847 0
848 Subtotal - Playground Surfacing & Equipment (Allowance) 87,574
RFQ #19-422-Q-DR Page 39 of 47 05/13/19
849 Fire Protection
850
851
852 Fire Protection 124,399 sf 261,238
853 Provide Sprinkler System to meet or exceed NFPA-13. 0 0
854 Shop Drawings and Permits as required 0 0
855 2 risers with control valves, tamper switches, main drains etc. 0 0
856 78 brass standard coverage upright sprinklers on exposed pipe. 0 0
857 116 white semi-recessed pendants 0 0
858 4 white semi-recessed dry pendant fire sprinklers 0 0
859 Underground Piping 0 0
860 0 0
861 Bond 261,238 $ 5,225
862 Adjusted total 1 LS (60,118)
863 0
864 0
865 0
866 Subtotal - Fire Protection 206,345
867 Plumbing
868
869
870 Drinking Fountain Outdoor 2 ea 3,000
871 Elec Water Cooler Bi Level w/Bottle Fill 4 ea 18,000
872 L - Lavatory Wall Hung 96 ea 336,000
873 WC - Water Closet Flr Mtd 91 ea 318,500
874 UR - Urinal Wall Hung 6 ea 21,000
875 CS - Drop-in Counter Sink 71 ea 177,500
876 Bubbler fountain @ drop in sink 64 ea 22,400
877 Shower 2 ea 7,000
878 MS - Mop Sink 6 ea 24,000
879 RCP - Water Heater Circ system 7 ea 42,000
880 EWH - Electric Water Heater @ custodial closets - 20 gal 7 ea 24,500
881 GWH - Electric Water Heater Kitchen 120 Gal 1 ea 7,500
882 WMB - Washing machine box 1 ea 500
883 IMB - Ice Maker Box 3 ea 1,500
884 Carriers 108 ea 64,800
885 CO 87 ea 39,150
886 HB 55 ea 35,750
887 Valves 154 ea 69,300
888 Mixing Valves 35 ea 26,250
889 FD - Floor, hub drains 32 ea 56,000
890 VTR - Vent Thru Roof 18 ea 9,000
891 PT - Plaster Trap 1 ea 1,500
892 Grease trap 1250 gal 3 ea 21,000
893 SI - Solids interceptor 1 ea 3,500
894 HS - Hand sink - Furnished by food service equip) 4 ea 3,200
895 TD - Floor Trough (furnished by food service equipment) 2 ea 1,200
RFQ #19-422-Q-DR Page 40 of 47 05/13/19
896 3 compartment sink (furnished by food service equipment) 1 ea 600
897 2 compartment sink (furnished by food service equipment) 1 ea 600
898 Gas Piping Distribution - Kitchen & WH 0 ls 0
899 Approved Alternates ea
900 Alt #4. PEMB Covered Play Area Plumbing Work 1 ls 47,000
901 ea
902 ea
903 0 0
904 Bond 1,382,250 $ 27,645
905 Adjusted total 1 LS (249,135)
906 0
907 0
908 0
909 Subtotal - Plumbing 1,160,760
910 HVAC
911
912
913 HVAC 0
914 Carrier Chillers - (2) 173 = 346 tons water cooled Models - 30HXC186 346 tons 207,600
915 (2) B&G 20 HP Primary CHW Pumps 40 hp 24,000
916 (3) 10 HP B&G Condenser Water Pumps 30 hp 18,000
917 1-B&G Model B-200 53 Gal Expansion tank 1 ea 4,000
918 Air Separator B&G R-6F. 1 ea 5,000
919 Chemical Shot Feeders & Treatment 1 ea 5,000
920 Refrigerant Monitoring System 1 ea 8,000
921 Evapco USS 29-4118 C. Tower Dual Cell SS -346 Tons, cell size 520 GPM 346 tons 86,500
922 Chilled water supply & return AG CEP 0 0
923 6" Insulated pipe OH 380 lf 60,800
924 8" Insulated pipe OH 166 lf 35,690
925 Fittings, valves, strainers, operators, instrumentation 75 ea 86,250
926 Chilled water supply & return AG Main Bldg 0 0
927 6" Insulated pipe OH 120 lf 19,200
928 8" Insulated pipe OH 120 lf 31,800
929 Chilled water supply & return UG 0 0
930 8" Insulated pipe UG 462 lf 92,400
931 Isolation valves 8" 2 ea 7,000
932 Valve vault 1 ea 2,500
933 (7) Air handlers 91,215 cfm 296,449
934 Bipolar ionization 91,215 cfm 18,243
935 Exhaust 6,510 cfm 14,972
936 VAV's Terminal Units 88 ea 81,400
937 Captive Air Kitchen Hoods (KEF 1 & 2) Roof Exhausts Included 2 30,000
938 Carrier DX Split Unit (AHU/CU-5) 1 30,000
939 Mini-Splits 8 12,800
940 In-Line Ceiling Exhaust Fans 9 4,500
941 Exterior Wall Mount Louvers 5 1,000
942 Ductwork 242,658 lbs 727,974
943 Insulation 66,154 sf 165,385
944 Exhaust grille 99 ea 5,487
945 Supply register 426 ea 50,673
946 Return register 200 ea 12,920
947 Balancing Damper 101 ea 2,904
948 Fire/Smoke damper 59 ea 27,553
949 MVD - Motorized volume damper 7 ea 8,932
950 OAL - Outside air louver 10 ea 10,750
RFQ #19-422-Q-DR Page 41 of 47 05/13/19
951 EL - Exhaust louver 8 ea 8,600
952 GRV - Gravity vent 8 ea 8,600
953 Gravel Bed for Chiller Yard (20 CUYDS) 1 ls 3,000
954 Control System 124,399 sf 205,258
955 T & B (Removed to Separate Division Below) 1 ls 40,000
956 Copper Condensate Lines 1 ls 15,000
957 Motor Starters 1 ls 4,000
958 Commissioning Assistance 1 ls 5,000
959 Approved Alternates ea
960 Alt #4. PEMB Covered Play Area Painting Work 1 ls 24,000
961 Alt #M-4 Install Low delivery temperature water cooled chillers. 1 ls 2,244
962 ea
963 ea
964 0 0
965 Bond 2,421,140 $ 48,423
966 Adjusted total 1 LS (134,937)
967 0
968 0
969 0
970 Subtotal - HVAC 2,424,870
971 Test & Balance
972
973
974 Test & Balance 124,399 sf 37,320
975 0 0
976 Bond 37,320 $ 0
977 Adjusted total 1 LS (7,540)
978 0
979 0
980 0
981 Subtotal - Test & Balance 29,780
982 Electrical
983
984 Site Electrical
985 Primary power & conduit (Allowance) 1 ls 25,000
986 Secondary conduit w/conc encasement to MDP1 290 lf 43,500
987 Conduit U/G 3'' w/3 #300 1,890 lf 84,748
988 Conduit U/G 3'' w/4 #500 168 lf 13,154
989 Trenching 357 lf 2,678
990 Concrete Encasement Premium 95 lf 1,425
991 Structured Cable Backbone
992 UG 1.5" to 4" conduit 5,251 lf 38,282
993 Handhole/pullbox 4 ea 6,000
994 Trenching 1,889 lf 14,168
995 Building Power & Lighting
996 New Building Power & Lighting 124,399 sf 995,192
997 Light Fixture Type A 2 x 4 Lay In H 1,331 ea 465,850
998 Light Fixture Type B 2 x 4 Lay In H 159 ea 55,650
999 Light Fixture Type C 4' 2 Tube Strip H 109 ea 38,150
1000 Light Fixture Type CL Wall Pack 11 ea 10,450
1001 Light Fixture Type D Downlight 6" Dia 7 ea 2,450
1002 Light Fixture Type F 4' 2 Tube Recessed H 94 ea 25,850
1003 Light Fixture Type G 2 x 4 Lay In H 68 ea 23,800
1004 Light Fixture Type H 2 x 4 Lay In H 19 ea 6,650
1005 Light Fixture Type K 2 x 4 Lay In H 18 ea 7,200
RFQ #19-422-Q-DR Page 42 of 47 05/13/19
1006 Light Fixture Type M Wall Pack 51 ea 56,100
1007 Light Fixture Type X1 Exit Sign Recessed Mtd 26 ea 4,550
1008 Light Fixture Type X2 Exit Sign Wall Mtd 18 ea 2,880
1009 Light Fixture Type Y2 Emergency Light 2 Head w/Battery Pack 357 ea 190,995
1010 Dimming Package 1 ls 50,000
1011 Daylight/Energy Conserve Wiring Class Rooms 56 ea 84,000
1012 Occ Sensors 183 ea 41,175
1013 Light Fixture SLB Sgl Head 30' Pole Mtd 22 ea 77,000
1014 Light Fixture SLB Sgl Head 20' Pole Mtd 17 ea 51,000
1015 Standard systems
1016 Data 0 sf 0
1017 Monument Sign Data Allowance 1 ls 25,000
1018 Fire Alarm 124,399 sf 186,599
1019 Intercom 121,329 sf 181,994
1020 Lightning Protection Grounding Allowance 1 ls 15,000
1021 CCTV 121,329 sf 60,665
1022 Intrusion Prevention - pathway only 121,329 sf 30,332
1023 Access Control 1 ls 50,000
1024 Security Cameras 36 ea 108,000
1025 TV Production System 1 ea 15,000
1026 Multipurpose Sound System 1 ea 30,000
1027 Special lighting & systems
1028 Theatrical Lighting System 1 ls 50,000
1029 Classroom Sound Enhancement
1030 Generator 80KW w/sound enclosure, fuel & testing 1 75,000
1031 ATS 2 ea 5,000
1032 System Testing if not by owner 1 ea 34,000
1033 Approved Alternates ea
1034 Alt #4. PEMB Covered Play Area Electrical Work 1 ls 36,000
1035 Alt # E-4 Provide UL Listed lightning protection system (See Allowances) 1 ls 0
1036 Alt # T-1 Provide Data for Monument Sign (See Allowances) 1 ls 0
1037 Alt # T-2 Conduit only for low Volt eqpt at Covered Play Bldg w/ buyout 1 ls 0
1038 ea
1039 ea
1040 0 0
1041 0 0
1042 Bond 3,275,485 $ 65,510
1043 Adjusted total 1 LS (433,394)
1044 0
1045 0
1046 0
1047 Subtotal - Electrical 2,952,600
1048 TOTAL 20,401,946
RFQ #19-422-Q-DR Page 43 of 47 05/13/19
RFQ #19-422-Q-DR Page 44 of 47 05/13/19
WHARTON-SMITH CONSTRUCTION GROUP
340 dy
GMP Estimate 49 wk
New Viera ES 11 mo
LINE GENERAL CONDITIONS TOTALS COMMENTSITEM DESCRIPTION QTY UNIT1,105 Water and ice 0 wk 0
1,106 Water - monthly 11 mo 2,943
1,107 Electric - FPL Temporary Transformer 0
1,108 Electric - install/remove temp system 0 ea 0 BY ELECTRICIAN
1,109 Electric - monthly charges (field) 6 mo 9,630
1,110 Generators - 10,000 watts 3 ea 6 Mos 6 mo 28,890
1,111 Generators - fuel (216 hr/mo x 2gal/hr) 7,794 gal 29,189
1,112 Temporary lighting (night lighting) 0
1,113 Field office - WSI - rent (2 wide) 11 mo 25,894
1,114 Field office - BPS - rent 0 mo 0 TBD
1,115 Field office - set up & remove - WSI 1 ea 4,428
1,116 Field office - set up & remove - BPS 0 ea 0 TBD
1,117 Field office furnishings & equipment - purchase 1 ls 5,350
1,118 Copier rental 11 mo 5,002
1,119 Computer, copier & other equip for field office - 4 ea rental 11 mo 10,452 $148 x 6 Computers
1,120 Software licenses (PlanGrid) 11 mo 3,825
1,121 Project FTP site 0
1,122 Storage & tool trailers (1 ea) 11 mo 2,354
1,122 Storage & tool trailers - set up & remove 1 ea 614
1,123 Temporary Fence and Gates 4,950 lf 22,275
1,124 Temporary toilets - 10 ea 11 mo 18,244
1,125 Temporary sewage holding tanks - 2 ea 0 mo 0
1,124 Daily Clean-up 49 wks 15,729
1,125 Final Clean-up 1 ls 44,100
1,126 Dumpsters/Dump Charges 90 ea 36,000
1,127 CONSTRUCTION EQUIPMENT & TOOLS 0
1,128 Small tools 11 mo 5,500
1,129 Extended boom forklift mo 0
1,130 All terrain vehicle 11 mo 7,062
1,131 Equipment fuel 0
1,132 Water Supply Truck 6 mo 22,470
1,133 Broom Truck 0
1,134 Fuel tank 0
1,135 Vehicle, fuel, oil, grease 11 mo 50,545 $919 x 5 Vehicles
1,136 Equipment maintenance 0
1,137 Move in/out equipment 0
1,138 Move in material 0
1,139 SAFETY & HEALTH & HOUSEKEEPING 0
1,140 Safety meetings 0
1,141 Safety devices & equipment 1 ls 1,500
1,142 Preventative medicine 0
1,143 JLA Badging 8 ea 813
1,144 PROJECT START-UP & CLOSEOUT 0
1,145 Start up chemicals 0 BY OWNER
1,146 Start up electric consumption charges 0 BY OWNER
1,147 0
1,148 SUBTOTAL GENERAL CONDITIONS 1,103,6121,149 SALES TAX 12,9151,150 TOTAL GENERAL CONDITIONS 1,116,527
RFQ #19-422-Q-DR Page 45 of 47 05/13/19
1
SECTION 05
Master Project Schedule
Master Project Schedule Narrative: Site Work & Underground Utilities: The project schedule reflects commencement of construction activities on July 8th, 2019 for the new elementary school. Mobilization will begin on 7/8/2019 with immediate erection of temporary fence and SWPPP silt fence. Clearing and grubbing will begin shortly after and the project site will be graded for the building pad. Once the site is graded and the building pad in place the underground utilities will begin. Slab on Grade & Form Panels: The slab will be poured in two stages. The first pour will be around the perimeter of the building so that the panels can be formed on the slab and the MEP trades can continue to work where the slab is not poured. Once the plumbing is finished the interior slab will be poured. Erect Tilt Panels & PEMB: The end of October the precast panels will be tilted into place. Once the panels are in place and finalized the pre-engineered metal building will be erected. The PEMB erection will last about two months including roof placement and dry-in. Interior Finishes: Beginning in early January 2020 once the building is dried in the interior metal framing and drywall will be installed. MEP rough in, interior finishes, and MEP trim out will follow through until May of 2020. Parking Lots and Landscape: The roads, parking lots, sidewalks, and landscaping will be constructed in early March and April of 2020. Final Inspections: Subcontractor inspections will take place in the end of May. Punchlist and Test & Balance activities will continue until June with Building Final Inspections the first week of June and a Substantial Completion date of June 12th of 2020.
RFQ #19-422-Q-DR Page 46 of 47 05/13/19
Activity Name Original Duration Start Finish
19-013 - VES - GMP SCHEDULE19-013 - VES - GMP SCHEDULE19-013 - VES - GMP SCHEDULE19-013 - VES - GMP SCHEDULE
PRECONSTRUCTIONPRECONSTRUCTIONPRECONSTRUCTIONPRECONSTRUCTION
Kick Off Meeting 0 04-Jan-19
Preconstruction Proposal 10 07-Jan-19 18-Jan-19
Board Approval 20 21-Jan-19 15-Feb-19
Budget Estimate / Constructability Review 15 18-Feb-19 08-Mar-19
Budget / Plan Review Meeting 0 11-Mar-19
Update Budget / Plans 20 11-Mar-19 05-Apr-19
GMP Bidding Process 17 08-Apr-19 30-Apr-19
Budget / Plan Review Meeting 0 01-May-19
Bid Evaluation / GMP Preparation 6 01-May-19 08-May-19
GMP Review & Approval 13 09-May-19 28-May-19
Notice to Proceed 0 29-May-19
PRELIMINARY TASKSPRELIMINARY TASKSPRELIMINARY TASKSPRELIMINARY TASKS
Permitting and Procurement 27 29-May-19 05-Jul-19
Procurement of Metal Building 96 29-May-19 11-Oct-19
Commencement of Construction 0 08-Jul-19*
Construction Trailer Setup 5 29-Jul-19 02-Aug-19
SITEWORKSITEWORKSITEWORKSITEWORK
Fence & SWPPP 5 08-Jul-19 12-Jul-19
Clear & Grub 15 08-Jul-19 26-Jul-19
Grading Building Pad & Casting Slabs 20 29-Jul-19 23-Aug-19
Underground Utilities 45 26-Aug-19 28-Oct-19
Tie-In Utilities 15 29-Oct-19 18-Nov-19
Pavilion 20 10-Jan-20 06-Feb-20
Parking Lot 30 06-Mar-20 16-Apr-20
Hardscape 20 20-Mar-20 16-Apr-20
Testing & Inspections 5 17-Apr-20 23-Apr-20
BUILDINGBUILDINGBUILDINGBUILDING
Layout Building 1 26-Aug-19 26-Aug-19
Auger Poles 5 27-Aug-19 03-Sep-19
Form In Place Foundations 15 27-Aug-19 17-Sep-19
Slab on Grade or Casting Slabs 10 18-Sep-19 01-Oct-19
MEP Underground 20 25-Sep-19 22-Oct-19
Tilt Panels Form In Place 15 02-Oct-19 22-Oct-19
Slab on Grade over MEP UG 15 23-Oct-19 12-Nov-19
Erect Tilt Panels 5 23-Oct-19 29-Oct-19
Erect Metal Building 49 30-Oct-19 09-Jan-20
Building Dry In 0 09-Jan-20
Exterior Finishes 40 10-Jan-20 05-Mar-20
Framing / Drywall 60 10-Jan-20 02-Apr-20
MEP Rough In 45 24-Jan-20 26-Mar-20
Interior Finishes 45 13-Mar-20 14-May-20
MEP Trim Out 40 27-Mar-20 21-May-20
Subcontractor Final Inspections 5 22-May-20 29-May-20
WS Punchlist 10 22-May-20 05-Jun-20
Test & Balance 5 22-May-20 29-May-20
Building Final Inspections 10 01-Jun-20 12-Jun-20
Substanital Completion 0 12-Jun-20
Closeout / Commissioning 60 15-Jun-20 08-Sep-20
Final Completion 0 08-Sep-20
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
2019 2020 2021
Kick Off Meeting
Preconstruction Proposal
Board Approval
Budget Estimate / Constructability Review
Budget / Plan Review Meeting
Update Budget / Plans
GMP Bidding Process
Budget / Plan Review Meeting
Bid Evaluation / GMP Preparation
GMP Review & Approval
Notice to Proceed
Permitting and Procurement
Procurement of Metal Building
Commencement of Construction
Construction Trailer Setup
Fence & SWPPP
Clear & Grub
Grading Building Pad & Casting Slabs
Underground Utilities
Tie-In Utilities
Pavilion
Parking Lot
Hardscape
Testing & Inspections
Layout Building
Auger Poles
Form In Place Foundations
Slab on Grade or Casting Slabs
MEP Underground
Tilt Panels Form In Place
Slab on Grade over MEP UG
Erect Tilt Panels
Erect Metal Building
Building Dry In
Exterior Finishes
Framing / Drywall
MEP Rough In
Interior Finishes
MEP Trim Out
Subcontractor Final Inspections
WS Punchlist
Test & Balance
Building Final Inspections
Substanital Completion
Closeout / Commissioning
Final Completion
NEW VIERA ELEMENTARY SCHOOL
GMP MILESTONE SCHEDULE
WHARTON-SMITH, INC.
Project ID:19-013 GMP
Run 10-May-19 at 16:53
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 1 TASK filter: All Activities
RFQ #19-422-Q-DR Page 47 of 47 05/13/19