    Maximo Scheduler Solution Overview

    Michigan & Chicago Maximo Users Group

    Hosted by Herman Miller

    September 8, 2016

  • Please Note:

    IBMs statements regarding its plans, directions, and intent are subject to change or

    withdrawal without notice at IBMs sole discretion.

    Information regarding potential future products is intended to outline our general product direction and it should not be relied on in making a purchasing decision.

    The information mentioned regarding potential future products is not a commitment, promise, or legal obligation to deliver any material, code or functionality. Information about potential future products may not be incorporated into any contract.

    The development, release, and timing of any future features or functionality described for our products remains at our sole discretion.

    Performance is based on measurements and projections using standard IBM benchmarks in a controlled environment. The actual throughput or performance that any user will experience will vary depending upon many factors, including considerations such as the amount of multiprogramming in the users job stream, the I/O configuration, the storage configuration, and the workload processed. Therefore, no assurance can be given that an individual user will achieve results similar to those stated here.

    1

  • Maximo Scheduler

    7.6.3

    Maximo Asset Mgmt

    7.6.0.5

    Maximo Scheduler

    iLog

    DOC Required only for

    Optimization

    Add-on product to Maximo

    EAM, code embedded in

    core Maximo therefore a

    single install

    Requires a separate

    license purchase

    Includes integration

    adapter and optimization

    engine and models

    Optional: clients may choose

    not to use the optimization

    capability and can skip the

    DOC installation during the

    install process

    DOC Server

    Scheduler embedded in Maximo

    7.6.0.5 fix pack level 2

  • New Graphical Technology!

    3

    No dependency on Java applet / JRE

    Significant usability enhancements

  • 4 Role Based Applications

    1) Graphical Scheduling

    2) Graphical Assignment

    3) Graphical Assignment Repair Facilities

    4) Graphical Crew Management

    Also includes the Everyplace mobile templates to support the Field

    Technicians and the Supervisor

    4

  • 5

    Roles We Accommodate in Managing Work

  • Maximo Scheduler Pedigree

    Work Orders in a Gantt View Labor Load/Avail. Critical Path Methodology PM Forecasts (7.1.1)

    Work Orders in a Gantt View Labor Load/Avail. Critical Path Methodology PM Forecasts Graphical Assignment Dispatching Schedule Compliance Crews Asset, Location, Tools & Item Availability

    Work Orders in a Gantt View Labor Load/Avail. Critical Path Methodology PM Forecasts Asset, Location, Tools & Item

    Avail. Graphical Assignment Dispatching Schedule Compliance Crews Optimization / Automation Scenario Management Compliance Dashboards Graphical Crew Management

    Long Term Planning Manual Long, Mid and

    Short Term Planning Automated Long, Mid and

    Short Term Planning

    6

  • New capabilities built on a new technical foundation Repair Facility Capacity

    Planning Repair Facility Graphical

    Assignment Core Maximo PM costing Includes Nested Job

    Plans Scheduler application name change New name: Graphical

    Scheduling

    Usability enhancements Improved Gantt tools

    and navigation

    New Asset/Location scheduling capabilities built on a new technical foundation Work Orders and PM

    forecasts viewed by asset/location hierarchy

    Multi-tenancy support Usability enhancements Improved Gantt tools and

    navigation

    Port existing applications to the new technical foundation Graphical Scheduling Graphical Assignment

    Dispatch Graphical Crew Management

    Usability enhancements Multi-column sort, search, and

    filtering Multi-craft/skill display Undo / Redo Expand / Collapse Much more.

    Addressing RFEs during these releases

    7

    Scheduler 7.6.x Delivery Timeline

  • Advanced use cases being requested by clients

    Ability to schedule customer appointments Match customer's location and requirements with technician's skills and availability to schedule a service

    appointment

    Model a complex project plan using real world interdependencies of tasks A plant turnaround requires many dependent actions to shutdown the location, perform project work, and re-

    start the location to bring it back to an operational stage

    Ensure resources with the right qualifications are assigned to work with special requirements Supervisors need to ensure that technicians have valid certifications to do the work

    How do the current traffic conditions effect work in progress? Incorporate real-time traffic conditions to better route technicians to their work locations

    Handle larger volumes of data Many Maximo clients require the ability to manage a heavy volume of work orders be it for shutdowns,

    turnarounds, outages, or for dispatching field technicians

  • Appointment scheduling

    Make customer appointments within a schedule window

    Customer notifications cancel / reschedule

    Managing large projects

    Dependencies across work orders and tasks

    Highlight critical path, backward pass, % complete

    Weather integration

    Incorporate weather data into planning/scheduling and dispatching

    Weather alerts / notifications

    Dynamic dispatching

    Auto refresh, re-optimization based on real-time progress

    Incorporate real-time traffic conditions

    Introducing Scheduler Plus!

    Advanced work management solution, built on top of Maximo Scheduler

    The information on the new product is intended to outline our general product direction and it should not be relied on in making a purchasing decision. The information on the new product is for informational purposes only and may not be incorporated into any contract. The information on the new product is not a commitment, promise, or legal obligation to deliver any material, code or

    functionality. The development, release, and timing of any features or functionality described for our products remains at our sole discretion. . 9

  • Scheduler Plus also embedded in Maximo

    Maximo Asset Mgmt

    Maximo Scheduler

    iLog

    DOC

    Required for

    Optimization

    Maximo Scheduler

    Maximo Scheduler

    Plus

    Advanced scheduling

    solution

    Add-on product to

    Maximo Scheduler,

    code embedded in

    core Maximo therefore

    still a single install

    On-prem and via SaaS

    Requires a separate

    license purchase

    Includes the

    optimization models

    10

  • Maximo Scheduler and Scheduler Plus Roadmap

    Notice: IBMs statements regarding its plans, directions, and intent are subject to change or withdrawal at IBMs sole discretion. Information regarding potential future products is intended to outline our general product direction and it should not be relied on in making a purchasing decision. The information mentioned regarding potential

    future products is not a commitment, promise, or legal obligation to deliver any material, code or functionality. Information about potential future products may not be

    incorporated into any contract. The development, release, and timing of any future features or functionality described for our products remains at our sole discretion.

    Weather Configurable weather views Enabled in Graphical Scheduling and

    Graphical Assignment Appointment Scheduling

    - Make customer appointments within a schedule window, see tech availability, incorporate weather

    - Cancel, reschedule appointments Network dependencies (Phase 1)

    - Link across WOs and tasks

    Weather impact on Assets Weather overlay on maintenance/operational

    windows Weather impact on Job Plans

    Adding weather requirements to conditional job plans

    Variable length condition (ex: weather impacted) Go or No Go criteria Applying conditional job plan tasks to existing

    WOs Network dependencies (Phase 2)

    - Backward pass - Highlight critical path - Introduce % complete

    Excel Export Enhance status color to include synonyms

    Qualifications at WO & Task Level - Manual and Optimization

    Weekly and Monthly planning buckets

    Performance

    Dynamic Dispatching Auto refresh for improved tracking of

    progress Re-optimization based on real-time

    progress, including emergent work Real-time road conditions and traffic Continuous weather updates and

    weather event notifications Everyplace template updates - weather

    Weather based assignments

    Manual clearing of decks Optimization reschedule planned

    and emergency

    Enhanced resource availability WO outside schedule, shifts/breaks

    PM display Constraint window Compare PM scenarios Emergency template (ex. Weather

    event activity) Performance

    Scheduler Scheduler Plus

  • Maximo Scheduler Wiki -

    https://www.ibm.com/developerworks/community/wikis/home?lang=en#!/wik

    i/IBM%20Maximo%20Asset%20Management/page/Maximo%20Scheduler

    If unable to access, you may need to create a developerWorks account here:

    http://www.ibm.com/developerworks/

Search related