Upload
defimediagroup-ldmg
View
220
Download
0
Embed Size (px)
Citation preview
8/20/2019 Mauritius Power Sector RAS Report Part 1
1/155
1
Report No: ACS13923
.
Republic of Mauritius
Mauritius Energy SectorReimbursable Advisory Services
Assessment of electricity demand forecast andgeneration expansion plan with focus
on the 2015–2017 period
.
May, 2015
.
GEE01
AFRICA.
8/20/2019 Mauritius Power Sector RAS Report Part 1
2/155
Standard Disclaimer:
.
This volume is a product of the staff of the International Bank for Reconstruction and Development/ The World Bank. The findings,interpretations, and conclusions expressed in this paper do not necessarily reflect the views of the Executive Directors of The WorldBank or the governments they represent. The World Bank does not guarantee the accuracy of the data included in this work. Theboundaries, colors, denominations, and other information shown on any map in this work do not imply any judgment on the part of TheWorld Bank concerning the legal status of any territory or the endorsement or acceptance of such boundaries.
.
Copyright Statement:
.
The material in this publication is copyrighted. Copying and/or transmitting portions or all of this work without permission may be a
violation of applicable law. The International Bank for Reconstruction and Development/ The World Bank encourages dissemination of
its work and will normally grant permission to reproduce portions of the work promptly.
For permission to photocopy or reprint any part of this work, please send a request with complete information to the Copyright Clearance
Center, Inc., 222 Rosewood Drive, Danvers, MA 01923, USA, telephone 978-750-8400, fax 978-750-4470, http://www.copyright.com/.
All other queries on rights and licenses, including subsidiary rights, should be addressed to the Office of the Publisher, The World Bank,
1818 H Street NW, Washington, DC 20433, USA, fax 202-522-2422, e-mail [email protected].
http://www.copyright.com/http://www.copyright.com/http://www.copyright.com/mailto:[email protected]:[email protected]:[email protected]:[email protected]://www.copyright.com/
8/20/2019 Mauritius Power Sector RAS Report Part 1
3/155
Table of Contents
Part I. BACKGROUND AND OBJECTIVES 1
Part II. EXECUTIVE SUMMARY 3
Part III. ASSESSMENT OF DEMAND FORECASTS 17
1 Initial electricity demand forecasts 18
1.1 Forecasts of electricity sales 18
1.2 Forecasts of energy sent out 22
1.3 Forecasts of peak demand 23
2 Comparison with recent forecasts from CEB 25
3 Sensitized electricity demand forecasts 29
4 Conclusions and recommendations 32
Part IV. ASSESSMENT OF SUPPLY AND DEMAND BALANCE 34
5 Assessment of supply to peak demand 34
5.1 Input data and assumptions 35
5.1.1 Current installed generation capacity 35
5.1.2 Programmed retirements and termination of contracts 39
5.1.3 Programmed capacity additions and redevelopment of generating units 40
5.1.4 Contribution of hydro plants to supply of peak demand 43
5.1.5 Scheduled maintenance of generation fleet 44
5.2 Methodology 46
5.3 Assessment of supply to peak demand under currently programmed additions
and retirements to the generation system 49
5.3.1 Results of the quantitative assessment 49
5.3.2 Summary of recommendations for the short and long terms 51
5.4 Recommendations for the short term (2015 – 2017) 52
5.4.1 Detailed short-term recommendations 53
5.4.2 Simulation of implementation of recommendations for the short term 58
5.5 Recommendations for the long term (2018 – 2022) 61
5.5.1 Detailed long-term recommendations 62
5.5.2 Simulation of implementation of the long-term recommendations 67
6 Conclusions and recommendations 69 6.1 Ensuring the adequacy of the supply to peak power demand in the short term
69
6.2 Firm capacity additions in the long term 71
Part V. RECOMMENDATIONS TO STRENGTHEN CAPACITIES TO
UNDERTAKE POWER SECTOR EXPANSION PLANNING 75
7 Methodologies and procedures for power system planning 75
8 Institutional aspects and planning of the power sector 78
REFERENCES 84 ABBREVIATIONS AND ACRONYMS 86
8/20/2019 Mauritius Power Sector RAS Report Part 1
4/155
Annex I. ASSESSMENT OF GENERATION PLAN DEVELOPED AND
EVALUATED WITH THE WASP PACKAGE BY MAURITIAN
INSTITUTIONS 88
9 Assessment of generation plan DEVELOPED and evaluated with WASP 88
9.1 Factual observations 88 9.2 Conclusions and recommendations 92
Annex II. DETAILED SIMULATIONS OF SUPPLY TO PEAK DEMAND 98
10 Detailed results of simulations of section 5.3.1 98
10.1 Initial set of demand projections 98
10.1.1 Low demand scenario 98
10.1.2 Base demand scenario 101
10.1.3 High demand scenario 104
10.2 Sensitized set of demand projections 107
10.2.1 Low demand scenario 10710.2.2 Base demand scenario 110
10.2.3 High demand scenario 113
11 Detailed results of simulations of section 5.4.1 116
11.1 Initial set of demand projections 116
11.1.1 Low demand scenario 116
11.1.2 Base demand scenario 119
11.1.3 High demand scenario 122
11.2 Sensitized set of demand projections 125
11.2.1 Low demand scenario 125
11.2.2 Base demand scenario 128
11.2.3 High demand scenario 131
12 Detailed results of simulations of section 5.5.1 134
12.1 Initial set of demand projections 134
12.1.1 Low demand scenario 134
12.1.2 Base demand scenario 137
12.1.3 High demand scenario 140
12.2 Sensitized set of demand projections 143
12.2.1 Low demand scenario 143
12.2.2 Base demand scenario 14612.2.3 High demand scenario 149
8/20/2019 Mauritius Power Sector RAS Report Part 1
5/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
1
PART I . BACKGROUND AND OBJECTIVES
The Republic of Mauritius is an island nation in the Indian Ocean. It comprises the main island
of Mauritius and the island of Rodrigues, the outer islands of Agaléga, and the archipelago of
Saint Brandon.
In the Republic of Mauritius, the Ministry of Public Utilities is responsible for the power sector
(as well as the water and wastewater sectors) and for the design and implementation of energy
policy.
The Ministry oversees the power utility, the Central Electricity Board (CEB), which is
statutorily responsible for the control and development of electricity supply. CEB, which is also
a generator and supplier of electricity, currently acts as the electricity regulator. The Electricity
Act of 1939 (amended in 1991), the Electricity Regulations of 1939, and the Central Electricity
Board Act (1964) comprise the legislative framework for the electricity sector and CEB’soperations. According to the 1964 act [1], CEB is empowered to “prepare and carry out
development schemes with the objective of promoting, coordinating and improving the
generation, transmission, distribution and sale of electricity throughout Mauritius as required.”
The governmental policy for the power sector seeks to encourage a greater use of sources other
than oil for the generation of electricity, through the optimization of the use of local and
renewable energy sources. It also seeks to encourage proper management in energy
utilization — the Government of Mauritius (GoM) is joining efforts with private and public
institutions to achieve energy savings and implement energy efficiency practices.
CEB is currently able to meet peak electricity demand in the Republic of Mauritius. However,the increase in demand, coupled with possible delays in the implementation of new projects and
the aging of the existing generation plants, have posed concerns regarding CEB’s ability to
meet electricity demand reliably in the next few years. Depending on the combination of the
load growth and materialization of delays, the security of supply may be at risk already in the
short term. A supply shortage would trigger the need to install new capacity on an emergency
basis.
Taking this into account, the GoM requested technical assistance from the World Bank (WB),
comprising an independent evaluation of electricity demand forecasts and the assessment of the
existing power generation system and the plans for its expansion. For the execution of these
assessments, the period 2015 – 2017 is emphasized, because this mid-term horizon presents
particular challenges to the maintenance of adequate generation supply in Mauritius, as will be
seen further in this document. Yet, the analysis also includes the years until 2022 — a horizon
compatible with CEB’s Integrated Electricity Plan 2013 – 2022 [IEP] [2], though with less detail
on the interval between 2018 and 2022.
This document consists of the preliminary report of the activities carried by the WB team, and
is organized as follows:
Following this introduction, the executive summary in Part II presents the main
findings and recommendations arising from the work.
8/20/2019 Mauritius Power Sector RAS Report Part 1
6/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
2
The evaluation of electricity demand forecasts for the island of Mauritius is presented
in Part III, which also contains recommendations for improving the process of demand
forecasting and the use of the demand projections in the planning activity.
Part IV deals with the assessment of the generation system in the island of Mauritius, presenting recommendations on how to proceed with addressing the identified
difficulties in meeting demand with the currently existing and planned generation
systems.
Recommendations for strengthening the capacity of Mauritian institutions to undertake
power sector planning, including methodological and institutional aspects, are
presented in Part V.
Bibliographical references and technical annexes follow Part V.
After the delivery of the initial version of this report, the WB team received and was
requested to analyze the outcomes of planning studies conducted by CEB, in which
generation expansion plans were prepared and evaluated with help of the Wien
Automatic System Planning (WASP) Package. Annex I presents an assessment of the
results and the technical procedures adopted for these planning studies.
Annex II contains detailed results referring to simulations of supply to peak demand.
8/20/2019 Mauritius Power Sector RAS Report Part 1
7/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
3
PART II . EXECUTIVE SUMMARY
The objective of this document is to assess the ability of the generation system in the island of
Mauritius to meet the demand for electricity, and to recommend measures to ensure the
adequacy of supply in this island in the short and long terms. The recommendations refer both
to actions to be taken by Mauritian institutions to improve the security of electricity supply in
the short and long terms, and to actions to strengthen the capacity of these institutions to
undertake power sector planning.
In short, the key recommendations of this report are:
(1) Due to time constraints, ensuring security of supply in the short term (2015-2017)
requires measures not involving capacity additions.
These measures refer to enhancing the operation of the existing system, fast tracking
generation projects already in the pipeline, and extending the operation either of
existing generation assets that are scheduled for decommissioning or of independent
power producers (IPPs) whose contract is scheduled for termination.
The efforts to implement these measures, which are detailed in section 5.4 of the report,
ought to be initiated as soon as possible.
(2) In the long term, new capacity generation additions (i.e., those not referring to projects
already under consideration or implementation) are needed already in 2018.
Given the typical times required to incorporate new capacity, avoiding supply shortages
in 2018 requires actions from Mauritian institutions in the very short term, to becompleted by January 2016. The procurement process for the incorporation of new
generation capacity should be initiated in January 2016 at the latest.
The time available between June 2015 and January 2016 would allow for some
adjustments of the generation capacity expansion alternative for 2018. By
implementing in 2015 the recommendations presented in this report on improvement of
the methodologies and procedures for power system planning, the Mauritian
institutions will be able to optimize the amount of new generation capacity actually
needed and the related timing.
If no improved planning methods and procedures are implemented in Mauritius beforeJanuary 2016, it is recommended to proceed with the procurement of gas turbines (to
run initially on diesel) in the amount the currently applied planning methodology
indicates is needed (2 × 36 megawatts [MW]), since no other formal and consolidated
assessment methodology will be available to support expansion planning decisions.
(3) For the period between 2019 and 2022, the recommended firm capacity additions are
those indicated in Table ES 1.1. The determination of the exact technology
corresponding to those capacity additions should be the result of detailed planning
efforts, which need to be executed under consideration of the recommendations of this
8/20/2019 Mauritius Power Sector RAS Report Part 1
8/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
4
report on how to strengthen the capacity of Mauritian institutions to undertake planning
for power sector expansion.
Table ES 1.1 – Capacity additions recommended for Mauritius in the long term: 2019 – 2022
(4) Strengthening the capacity of Mauritian institutions to plan for power sector expansion
involves institutional and methodological aspects.
From an institutional point of view, the most critical recommendation is to embrace
public consultation mechanisms as part of decision-making processes for the expansion
of the power sector. The WB team believes formal public consultation is the right
approach to address, in a realistic and transparent manner, environmental and socially
sensitive issues related to the power sector, as well as concerns about diversificationand security of supply. A proper public consultation process conducted in all stages by
the Government of Mauritius will make it possible to define the options for expansion
of the power sector actually available for the country in terms of primary resources
(imported fossil fuels, renewables) for power generation, environmental, and other
conditions to be met for their effective use.
It is of utmost importance that policies on the mix of domestic and imported energy
resources and the diversification and security of supply, as well as environmental
constraints and other requirements deriving from social acceptability, are considered
for the definition of scenarios for expansion at the planning stage, and that the costs of
meeting those policies, constraints, and requirements for each scenario are realistically
assessed by planners. Public consultation processes on those scenarios will make it
possible to define those actually viable for Mauritius, as well as to inform the society
on the related implementation costs for the country. For this reason, the WB team
believes starting this process should be seen as an immediate priority in Mauritius.
(5) From a methodological standpoint, it is recommended that Mauritian institutions
conclude as soon as possible — ideally before the end of 2015 — the implementation of
a program to consolidate the modernization of methodologies, procedures, and
computational tools used for power system planning in the country. This modernization
process has already been initiated, and there is an ongoing initiative with theInternational Atomic Energy Agency (IAEA). This report contains specific
recommendations on how to strengthen and consolidate the modernization program.
The current planning methodologies seem to point toward significant capacity
additions in coming years. Thus, assessing these requirements with the help of modern
methodologies and procedures can significantly impact the costs and reliability of
supply in Mauritius.
2019 2020 2021 202290.0 - 45.0 45.0
90.0 90.0 135.0 180.0
YearCapacity additions [MW]
Accumulated capacity additions [MW]
8/20/2019 Mauritius Power Sector RAS Report Part 1
9/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
5
In the context set by the preceding key recommendations on the way forward, a more detailed
description of the main findings and recommendations of this report is presented in the
following sections of this executive summary.
Generating electri city demand forecasts for the island of M aur iti us
Forecasts of the demand for electricity (energy consumption and peak load) are an essential
input for the assessment of the adequacy of a generation system. For this reason, the WB team
generated such forecasts for the island of Mauritius for the period 2015 – 2022. For this task, the
team adopted a top-down econometric approach, projecting demand for the island as a function
of the expected growth in gross domestic product (GDP) in the Republic of Mauritius. Demand
projections were generated:
For three scenarios of GDP growth: low growth, the base case, and high growth.
For two sets of assumptions on how energy efficiency and energy savings programs,as well as structural changes in the Mauritian economy and energy consumption habits,
may impact the demand for electricity in the long term. This resulted in two sets of
projections: the initial set (not taking into consideration any relevant effects of these
phenomena), and the sensitized set (in which these phenomena result in lower growth
of demand for electricity in the long term, after 2018).
The peak power demands determined for these two sets of projections and three growth
scenarios are indicated in Figure ES 1.1. The procedure utilized for generating the sensitized
set of projections was based on the reproduction of the behavior of recent demand projections
made available by CEB [6], in which it is considered that energy efficiency and energy savings
programs, as well as structural changes in the Mauritian economy and energy consumption
habits, affect the demand for electricity significantly in the long term.
Figure ES 1.1 – Peak power demand projections for the island of Mauritius: 2004 – 2022
300
350
400
450
500
550
600
650
700
750
2 0 0 9
2 0 1 0
2 0 1 1
2 0 1 2
2 0 1 3
2 0 1 4
2 0 1 5
2 0 1 6
2 0 1 7
2 0 1 8
2 0 1 9
2 0 2 0
2 0 2 1
2 0 2 2
P e a k p o w e r d e m a n d [ M W ]
Historical peak demand [MW]
Projected peak power demand [MW] Low scenario
Projected peak power demand [MW] Base case
Pro ected eak ower demand MW Hi h scenario
300
350
400
450
500
550
600
650
700
750
2 0 0 9
2 0 1 0
2 0 1 1
2 0 1 2
2 0 1 3
2 0 1 4
2 0 1 5
2 0 1 6
2 0 1 7
2 0 1 8
2 0 1 9
2 0 2 0
2 0 2 1
2 0 2 2
P e a k p o w e r d e m a n d [ M W ]
Historical peak demand [MW]
Projected peak power demand [MW] Low scenario
Projected peak power demand [MW] B ase case
Pro ected eak ower demand MW Hi h scenario
Initial projections Sensitizedprojections
8/20/2019 Mauritius Power Sector RAS Report Part 1
10/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
6
The process of constructing these electricity demand projections, as well as comparing the
projections with those generated by CEB, led to the following conclusions and
recommendations:
The bottom-up, end-use procedure adopted by CEB resulted in projections for the basecase scenario that are consistent with the projections developed by the WB team for
the short term (2015-2017). The procedure adopted by CEB for generating the base
case projections for this horizon — in which the effects of energy efficiency and energy
savings programs, as well as of structural changes in the economy and the electricity
consumption habits of Mauritius, are not expected to strongly affect demand
forecasts — is deemed as adequate by the WB team.
The recent projections by CEB [6] obtained for the low growth and the high growth
scenarios for the period 2015 – 2017 were respectively above and below those generated
by the WB team for the low growth and the high growth scenarios. The difference was
significant for the low growth scenario, and less so for the high growth one.
The WB team had access to a document developed by CEB [9], which served as the
support material for a presentation before National Energy Commission (NEC), in
which the peak supply simulations and analyses are conducted exclusively for the base
case demand forecast scenario. This alone cannot be considered as evidence that the
low growth and high growth scenarios developed in the IEP 2013 – 2022 have not been
used for the planning activity. However, the WB team stresses the need to define
credible demand projection scenarios that are actually used by decision makers to
develop robust expansion plans.
As for the demand projections for the period 2018 – 2022, the intrinsic income-
consumption elasticities embedded in the recent projections by CEB [6] are rather low
(hovering around 0.7). While the WB team understands that this may be the result of
energy efficiency and energy savings programs that are expected to be developed in
the future, as well as of expected structural changes to the economy and the electricity
consumption habits in the Republic of Mauritius, these low values deserve particular
attention. Establishing the socioeconomic conditions that allow attaining such low
elasticities in a country with a developing economy, even when the growth of this
economy is heavily based on the services sector, is a challenging task.
Therefore, the WB team recommends that the evolution of the structural changes andthe energy efficiency and energy savings programs that are expected to allow attaining
such low elasticity values be continuously monitored, and that demand forecasts be
periodically adjusted based on the results of this monitoring. Furthermore, the WB team
recommends that long-term strategies for expanding the supply side of the power
system (generation, transmission, and distribution systems) be flexible enough to allow
for rapid response to any failure in achieving the expected effects of future structural
changes in the economy and energy consumption habits.
8/20/2019 Mauritius Power Sector RAS Report Part 1
11/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
7
In light of the previous recommendations, the assessment of the ability of the generation system
in the island of Mauritius to meet the demand for electricity was conducted both for the initial
and for the sensitized demand projections developed by the WB team and shown above.
Ensur ing the securi ty of electricity supply in the short term (2015 – 2017)
The results of simulations of the energy supply to peak demand in the island of Mauritius
carried out by the WB team1 revealed significant capacity gaps for the period 2015 – 2017. The
term capacity gap is used in reference to a situation in which the existing or planned installed
generation capacity is insufficient for meeting peak demand under the supply reliability criteria
currently adopted in Mauritius.
If the current expansion plan for the generation system of the island of Mauritius — i.e., the
currently programmed additions, redevelopments, and retirements of generators, as well as the
currently programmed termination of contracts — is considered for the assessment of supply to
peak power demand, the capacity gaps indicated in Table ES 1.2 are identified. Results of
analyses for the low growth scenario are not presented in this summary for the sake of
conciseness, but are available in following sections of the report.
Table ES 1.2 – Capacity gap to meet target reserve margin in 2015 – 2022, per demand
scenario, under the current generation expansion plan
In the short term, time constraints would very likely prevent any additions to the generation
installed capacity in the island of Mauritius that are not already planned and under development.
Therefore, the measures recommended by the WB team to eliminate the capacity gaps in this
horizon refer to enhancing the operation of the existing system, fast tracking generation projects
already in the pipeline, and extending the operation either of existing generation assets that are
scheduled for decommissioning or of IPPs whose contract is scheduled for termination.
Specifically, the recommended measures are:
1 The data available for the execution of the quantitative analyses by the WB team constrained the choice of
the methods and procedures used for the assessment of peak demand supply. Basically, the analysis approach
refers to a scenario-based evaluation of adequacy of supply to peak demand, employing procedures
analogous to those used in Mauritius for the development of the Integrated Electricity Plan 2013-2022. As
will be seen further in this document, after the delivery of the initial version of this report the WB team
received the results of planning studies conducted by CEB, in which generation expansion plans were
prepared and evaluated with help of the Wien Automatic System Planning (WASP) Package and using
probabilistic methods. A critical appraisal of the analysis with WASP is found in Annex I of this report.
2015 2016 2017 2018 2019 2020 2021 2022
Sensitiz. Base 35.3 51.2 65.2 79.4 93.8
Initial Base 42.9 67.1 90.1 114.1 139.0
Sensitiz. High 64.1 88.8 111.3 134.4 158.1
Initial High 72.2 106.1 138.9 173.4 209.7
Capacity gap to meet target reserve capacity margin [MW] in yearDem. projection
scenario
0 50.7 71.8
4.8 63.7 92.6
8/20/2019 Mauritius Power Sector RAS Report Part 1
12/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
8
(1) Optimizing the maintenance schedules of CEB’s plants and IPPs, with the main goal
of reducing the volume of generation capacity under maintenance during the off-crop
summer season.
(2) Negotiating a new power purchase agreement (PPA) with IPP CEL Beau Champ, toensure that it contributes to the supply of peak power demand until 2018, since the
plant’s original PPA is expiring in the second semester of 2015. Mauritian institutions
recently advised the WB team that negotiations for the extension of this PPA are
already under way, and that these negotiations refer to a “bridge” PPA, whose duration
would be three years.
(3) Fast tracking the addition of new heavy fuel oil (HFO) units of the Saint Louis power
station, to enable the commissioning of four new generating units, each with 15 MW
of injectable capacity, until the second semester of 2017.
(4) Implementing emergency voltage reduction in 2016 and 2017, to reduce peak powerdemand at times of low reserve capacity margins, by reducing the operating voltages
in the electricity grid. Detailed studies should be carried out as soon as possible to
determine a realistic value for the maximum reduction in demand attainable as a result
of emergency voltage reduction in the island of Mauritius,2 since the possibility of
achieving reductions higher than those corresponding to the conservative assumption
adopted in this report may eliminate3 the necessity of implementing recommendation
(1), above.
(5) Extending the operation of the Pielstick engines of the Saint Louis power station
through 2016, such that these units are retired only in the second semester of 2017.
Mauritian institutions should consider the measures recommended above as priorities to
ensure the security of electricity supply in the island of Mauritius in the short term.
The equivalent increments in the injectable generation capacity of the island of Mauritius
corresponding to the implementation of the above-mentioned measures are summarized in
Table ES 1.3. The effects of implementing these measurements are detailed in Part IV and
Annex II of this report.
2 Mauritian institutions recently advised the WB team that, according to estimates of their technicians, the
maximum reduction in demand attainable as a result of emergency voltage reduction in the island of
Mauritius would be of MW [12]. The WB team understands that this may be a very conservative assumption.
The team also understands that the potential for demand reduction attainable as a result of emergency voltage
reduction is more properly expressed as a percentage of demand, rather than as an absolute value in
megawatts.
3 The WB team understands that Mauritian institutions are currently concerned about the availability of spare
parts for the Pielstick engines and the physical integrity of the equipment, due to its advanced age. This
justifies the perception that Mauritian institutions may seek to avoid implementing recommended measure
(1).
8/20/2019 Mauritius Power Sector RAS Report Part 1
13/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
9
Table ES 1.3 – Equivalent increments in the injectable generation capacity corresponding
to the implementation of previously described measures
(a) Reported values correspond to the incremental effect of the measure. Incremental effect is calculated by assuming all
other measures (2) – (5) were implemented, and simulating the subsequent implementation of measure (1). Effects vary with
time, due to the assumption of proportionality of the capacity under maintenance with respect to the injectable capacity of the
system, with different proportionality factors for the crop and off-crop seasons. A decrease in the capacity out due tomaintenance in the off-crop season is assumed to lead to an increase in the capacity out due to maintenance during the crop
season, which explains the negative values in the table. Refer to section 5.4.1 for further clarification on this topic.(b) The original PPA with IPP CEL Beau Champ is assumed to be active until the first
semester of 2015 in the reference scenario. Therefore, the effect of entering the new "bridge"
PPA will be felt start ing in the second semester of 2015. The "bridge" PPA would expire only
at the second semester of 2018.
(c) The results of fast tracking these units are the following: the first set of new units of the St. Louis power
plant (30 MW of injectable capacity) would be operational at the second semester of 2017, instead of just atthe very end of this year (2017); the second set of new units of the St. Louis power plant (30 MW) would be
operational at the second semester of 2017, instead of the beginning of 2018. Refer to section 5.4.1 for further
clarification.
(d) Values reported are reductions in peak demand multiplied by 110%, since a reduction of δ% in demand would result in a
demand of (1+10%)∙δ% in generation requisites due to the 10% spinning reserve criterion. A reduction in demand is not
rigorously equivalent to an increase in the available capacity for the purposes of the calculation of the reserve capacity
margin (RCM), as the RCM is defined as the quotient of the available capacity by 110% of the demand, as detailed further in
this report. However, the simplification of reporting the reduction of demand as an increase in generation capacity is made
here to simplify the presentation of results. For simulations of the full effect of the emergency demand reduction, refer to thetables of Annex I. The results of the tables of this report that indicate the aggregate effect of all measures do not consider any
simplification of the results and were taken directly from the full simulations of Annex II.
(e) Though the units would be kept operable through 2016, there are concerns about the physical integrity
of the equipment, due to the advanced the age of the engines.
As indicated in Table ES 1.4, implementing these recommendations in the short term is
expected to significantly relieve the capacity gaps identified in the island of Mauritius for the
base case projections of demand growth. The capacity gaps verified for the base case demand
projections are sensibly reduced, but still result in violations to the – 5 percent reserve capacity
margin that are of 2.5 percentage points in 2016 and 2.1 percentage points in 2017, as detailed
in Chapter 5. These correspond to a capacity gap of 13.5 MW and 11.5 MW in 2017, as shownin Table ES 1.4. This means that the remaining capacity gaps can be eliminated by running the
system under stricter operating conditions — i.e., slightly violating the existing supply reliability
criterion. Alternatively, the technicians in Mauritius might seek to obtain a demand decrease
via emergency voltage reduction that is above the very conservative estimates of 5 MW recently
made available to the WB team. The implementation of higher levels of voltage reductions,
aiming to reduce a larger portion of the load and therefore avoid even these violations of up to
2.5 percentage points for the base case demand, is an emergency measure that can be adopted
if its feasibility is confirmed.
Summer Winter Winter Winter Summer
Off-crop Off-crop Off-crop
(1) Optimizingmantenance
11.4 -12.0 -10.7 16.9 -12.4 -12.4 (a)
(2) "Bridge" PPA with
IPP CEL Beau Champ
Not yet
implem. 12 12 22 12 12 22 12 12 (b)
(3) Fast tracking of new
units of St. Louis plant 60 30 (c)
(4) Emergency
voltage reduction 5.5 5.5 5.5 5.5 5.5 5.5 (d)
(5) Extending operation
of Pielstick units of St.L. 25 25 25 25 (e)
2015 2016 2017
Summer Summer
Crop Crop Crop
Equivalent
increase in
injectable
capacity due to
implementaion
of measurement
[MW]
C o m m e n
t
Not yet implemented
Not yet implemented
Not yet implemented
Year
Calendar season
Crop/off-crop season
Not yet implemented
Measure no
longer active
8/20/2019 Mauritius Power Sector RAS Report Part 1
14/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
10
Table ES 1.4 – Capacity gap to meet the target reserve margin in 2015 – 2017, per demand scenario (with
recommendations for period implemented)
From Table ES 1.4, it is clear that the island of Mauritius may face capacity shortages in the
short term if the demand grows as indicated in the high growth scenario, even if all of the above-
mentioned measures are implemented.
Ensur ing the securi ty of electri city supply in the long term (2018 – 2022)
Values in Table ES 1.4 indicate that capacity additions are required to ensure the adequacy of
electricity supply for the island of Mauritius during 2018 – 2022.
In the long term, new capacity additions (i.e., those not referring to projects already under
consideration or implementation) to the electricity generation system of the island of Mauritius
are needed from 2018. Given the time typically required for the installation and commissioning
of new generating units, meeting capacity gaps expected to occur in 2018 requires actions from
Mauritian institutions in the very short term. In particular, the procurement process for the
incorporation of new generation capacity should be initiated at the latest in January 2016.
Planning for subsequent years of the horizon is important to devise long-term strategies for the
power system in the island of Mauritius, but these indicative plans should be adjusted in
accordance with any future updates of demand projections.
The WB team recommends the following measures to ensure the adequacy of supply to peak
demand in the island of Mauritius in the long term:
(1) Implementing in 2015 the recommendations presented in this report on improvement
of the methodologies and procedures for power system planning. By doing this , the
Mauritian institutions will be able to optimize the amount of new generation capacity
actually needed and the related timing.
(2) Procuring additional firm generation capacity to be commissioned at the beginning of
2018. The island of Mauritius is expected to experience capacity gaps in 2018, partly
as a result of the cancelation of the CT Power project. Installation of new generationcapacity is needed to prevent these capacity gaps from materializing.
Given the time frame required for the implementation of generation projects, two
technological alternatives for the capacity additions were analyzed in this document
(both with 70 MW of injectable capacity): (a) a 2 × 36 MW gas turbine thermal plant
running initially on diesel; (b) a 3 × 24 MW HFO-fired internal combustion engine
plant.
These alternatives were compared based on their performance regarding the annual
capacity utilization costs (in United States dollars (USD) per MW installed per year).
2015 2016 2017 2018 2019 2020 2021 2022
Sensitiz. Base 32.5 48.4 62.4 76.6 91.0
Initial Base 40.1 64.3 87.3 111.3 136.2
Sensitiz. High 61.3 86.0 108.5 131.7 155.4
Initial High 69.4 103.3 136.1 170.6 206.90 26.5 32.2
Dem. projection
scenario
Capacity gap to meet target reserve capacity margin [MW] in year
0 13.5 11.5
8/20/2019 Mauritius Power Sector RAS Report Part 1
15/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
11
Considering the results of this analysis and on other considerations detailed in section
5.5, the alternative recommended for the additional firm generation capacity to be
commissioned at the beginning of 2018 is the 2 × 36 MW gas turbine thermal plant
running initially on diesel.
Although gas turbines are by design dual-fuel (natural gas and diesel) machines, it is
recommended that the detailed specifications of the generating units of the new plant
be prepared to ensure the quick conversion of the gas turbines for operation on natural
gas at a later point in time, such that these units can be considered as the gas-turbine
phase of a combined-cycle, gas-fired thermal plant in the future.
Given the typical times required to incorporate new capacity, the procurement process
of the new power plants needs to be initiated at the latest in January 2016. If no
improved planning methods and procedures are implemented in Mauritius until January
2016, it is recommended to proceed with the procurement of gas turbines (to run
initially on diesel) in an amount (2 x 36 MW) that the currently applied planning
methodology indicates is needed, since no other formal and consolidated assessment
methodology will be available to support expansion planning decisions.
(3) Continuously monitoring structural determinants for electricity demand, and updating
demand forecasts for the long term. Insight on the importance of this measure may be
gained by verifying the significant difference in the capacity gaps reported in Table ES
1.4 for the initial and the sensitized demand projections. As explained in detail in
Chapter 3, these sets of projections differ in that the effects of energy efficiency and
energy savings programs, as well as the effects of structural changes in the economy
and the energy consumption habits, result in significantly lower demand growth in theisland of Mauritius in the sensitized demand projections. In fact, the analyses of Chapter
3 indicate that the current assumptions of Mauritian institutions about the effects of
these phenomena are very ambitious, with a significant decrease in the implied
elasticity of electricity consumption with respect to GDP growth starting in 2018.
Therefore, it is recommended that the evolution of the Mauritian economy and
consumption habits, as well as of the effects of energy efficiency and energy savings
programs, be continuously monitored, and that the projections of demand growth be
periodically updated to account for reasonable and quantifiable effects of these
variables over demand growth.
(4) Considering the ambitious nature of the assumptions regarding energy conservation
and structural changes that underlie the sensitized set of demand projections, as well as
the significant drop in the implied elasticities of demand to GDP for the demand
projected in the long term, the WB team considers the initial set of demand projections
as the reference scenario for determination of the new firm capacity additions required
from 2019 onward. The resulting recommended schedule of new capacity additions is
indicated in Table ES 1.5.
8/20/2019 Mauritius Power Sector RAS Report Part 1
16/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
12
Table ES 1.5 – Capacity additions (projects not currently under consideration or
under development) recommended for Mauritius in the long term: 2019 – 2022
The determination of the exact technology needed to correspond to these capacity
additions should be the result of detailed planning efforts that take into account the
recommendations of Part V of this report.
If the schedule of firm capacity additions indicated in Table ES 1.5 is implemented, the
capacity gaps in the long term are practically eliminated, as indicated in Table ES 1.6.
Table ES 1.6 – Capacity gap to meet the target reserve margin in 2015 – 2022, per demand scenario (with
recommendations for the period implemented)
It is worth emphasizing that the choice of methods and procedures for the assessment of supply
to peak demand adopted in this report was constrained by the data made available to the WB
team. With the information at hand, the team opted to adopt a deterministic planning procedure,
analogous to that currently used by Mauritian institutions. Nevertheless, the team identified
important recommendations about the improvement of the methodologies and procedures used
for generation system expansion planning in Mauritius, which are presented at the end of thisexecutive summary.
Another specific aspect of the planning criteria used for the development of the Integrated
Electricity Plan 2013-2022 in Mauritius deserves some comments. Under the methods and
procedures adopted for generation system expansion planning in Mauritius in the context of the
elaboration of the IEP 2013-2022, the contribution of renewable power plants with intermittent
output to the supply of peak power demand is considered to be strictly nil. Continuing to use
this practice may lead to an underevaluation of the attractiveness of this class of generators as
alternatives for generation system expansion planning, with the possible consequence of
limiting the future participation of renewable generators, such as wind and solar power plants,
in the country’s electricity matrix to suboptimal levels.
Probabilistic analyses carried out by Mauritian institutions were made available to the WB team
after the delivery of the initial version of the report. Yet, the modeling of renewable power
plants and of system operation for the purposes of these analyses also requires improvements,
as indicated in Annex I of this report.
These findings support the recommendations on the necessity to consolidate the modernization
of planning methods and procedures in Mauritius, in order to properly account for the
contribution of renewable generation technologies to the supply of peak power, without
2019 2020 2021 2022
90.0 - 45.0 45.0
90.0 90.0 135.0 180.0
Year
Capacity additions [MW]
Accumulated capacity additions [MW]
2015 2016 2017 2018 2019 2020 2021 2022
Sensitiz. Base 0 0 0 0 0
Ini ti al Base 0 0 0 0 0
Sensitiz. High 0 0 0 0 0
Initial High 6.2 0 0 0 00 26.5 32.2
Dem. projection
scenario
Capacity gap to meet target reserve capacity margin [MW] in year
0 13.5 11.5
8/20/2019 Mauritius Power Sector RAS Report Part 1
17/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
13
disregarding the uncertainty and variability of their output. These topics are analyzed in the
following section of this executive summary.
Improving the methodologies and tools for power sector planni ng in Maur iti us
As the power system of Mauritius grows in scale and complexity, ensuring the security of
electricity supply requires that planners have access to adequate methodologies and
computational tools, and that the planning procedures are adapted to support the increased
complexity of the decision-making process.
The WB team has identified several items of the generation planning methodology currently
adopted in Mauritius that require improvement. These are particular instances of the broader
phenomenon of constraints to power system operation and expansion planning that arise as a
consequence of the set of methodologies, procedures, and computational tools currently
adopted in the country.
The WB team specifically recommends that the institutions of Mauritius consolidate the
modernization of the methodologies, procedures, and computational tools used for power
system planning in the country.
This modernization program can have the following steps:
(1) Identification of minimum requisites for methodologies, procedures, and computer
tools used for power system operation and expansion planning in the Republic of
Mauritius, given the current state of the system and the alternatives for its future
evolution.
(2) Incorporation of the following products and services:
a. Computational tools that allow the implementation of the methodologies and
procedures identified in item (1), above; and
b. Training of the CEB staff in the use of these methodologies and computational
tools, in the context of updated planning procedures.
(3) Construction of thorough databases to allow the use of the methodologies, procedures,
and computational tools indicated above.
Guidelines for identifying the requisites for the methodologies and tools to be adopted in the
island of Mauritius are presented in detail in Chapter 7. These guidelines are summarized
below:
(1) Methodologies and tools that support decision making under uncertainty should be
adopted. Given the uncertainty in factors that range from consumer behavior to the
variability of energy resources for renewable generators, engineers must have the right
instruments at their disposal to ensure that power system expansion is planned to
minimize risks — e.g., risks of extreme costs, of severe blackouts, of sustained capacity
shortages, of very poor performance related to emissions, etc.
8/20/2019 Mauritius Power Sector RAS Report Part 1
18/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
14
(2) The stochastic behavior of all variables in the system should be adequately modeled,
with particular attention to spatial and temporal correlations among them.
(3) Finally, methodologies and tools should be adopted that support integrated decision
making, considering all links of the chain of power system expansion and operationactivities. Assessing the impacts of decisions on the entire chain of expansion and
operation activities, including unit commitment, allows planners to balance the
structural reinforcements and operational flexibility and ensure the expansion plans
result in flexibility levels that allow maintaining reliability of supply cost-effectively.
Improving i nstitu tional aspects of the Mauri tian power sector
In the WB team’s view, the improvement of certain institutional aspects of the power system
planning activity — particularly of expansion planning — is of utmost importance to meet the
expectations of Mauritian society regarding electricity supply.
The recommendations of the WB team presented in this section refer to three main topics: (1)
the introduction of public consultation mechanisms as part of decision-making processes in the
electricity sector; (2) during the planning activities, the thorough and realistic consideration of
resource diversification, security of supply, and the environmental and other socially sensitive
dimensions of power system expansion and operations; and (3) the creation of proper
institutional conditions for the consideration of energy policy guidelines during the execution
of power system planning activities by CEB, and for achieving these policy goals as a result of
these planning activities.
Ensuring that the stakeholders of other sectors of society — electricity consumers, generation
project developers, communities in the vicinity of planned projects, etc. — are heard and have
their points of view considered both in the process of setting energy policy goals and in the
development of power system expansion planning activities based on those goals is also key to
ensuring that the development of the power sector meets the expectations of Mauritian society.
In fact, the numerous submissions of different stakeholders to the NEC, in the context of the
process of elaboration of its report Making the Right Choice for a Sustainable Energy Future
[15] , indicate the eagerness of different segments of Mauritian society (as well as of
international institutions) to contribute to the decisions on the development of the country’s
electricity sector.
The WB team recommends that formal public consultation processes be organized and held byMauritian institutions to define the energy policy goals, as well as during the process of
elaboration of power sector development plans (IEP) or development of documents stating the
country’s energy policy, and that the contributions of different stakeholders presented in the
context of these public consultations be duly evaluated by the competent entities. The obligation
to hold these consultations should be formally included in legal or regulatory instruments
defining the mandate and attributions of CEB and of the governmental bodies responsible for
the definition of Mauritian energy policy. From an organizational point of view, it is important
that public consultation processes are given adequate publicity, that they are executed within a
time window that allows the participation of all stakeholders interested in the energy planning
8/20/2019 Mauritius Power Sector RAS Report Part 1
19/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
15
activities, and that the procedures for the submission of contributions from these stakeholders
are simple and effective, to encourage participation.
The WB teams believes that formal public consultation is the right approach to address
realistically and transparently environmental and all other socially sensitive issues with directimpact on the options for expanding the power sector in Mauritius. The GoM should promote
and conduct a formal public consultation process to discuss key energy policy issues, such as
(1) mix of primary energy resources (firm and nonfirm, domestic resources and imported fossil
fuels, etc.) providing adequate levels of security of supply for the country; (2) policies and rules
to be met for the use of lands and location of facilities for power generation, transmission, and
distribution; and (3) standards to be met for all types of emissions produced by electricity
infrastructure in all segments (generation plants of all technologies, transmission and
distribution networks, etc.).
The definition of those issues is a fully sovereign decision of any country, involving all
segments of its society. There are no right or wrong options in those matters, and any
organization external to the country has no say on them. What really matters is to have an open
and transparent public discussion on those topics. The GoM should promote and conduct that
public consultation process, starting with the preparation of a draft document identifying and
describing the options (scenarios) available for the country, and an assessment of the costs
related to the eventual adoption of each of them.
It is of utmost importance that all constraints to the expansion of the power system are
considered for the definition of energy policy goals and at the expansion planning stage, as well
that the costs for the country of addressing those constraints are realistically assessed and
presented at that stage, to allow the proper comparison of different power system expansionalternatives and avoid cost overruns and delays during the implementation stage of power
system expansion.
Clear and preferably standardized protocols should support decision makers in the tasks of
comparing alternatives for power system expansion. These protocols should establish clear
criteria for the assessment of the costs and benefits of a project, considering all potential
environmental and socioeconomic impacts. The assessment should cover all stages of a
project’s lifecycle: conception, implementation, operation, and dismantlement. Guidelines
prepared by multilateral institutions, offering countries the possibility of customization to their
particular requirements, are available to assist in the creation of such protocols.From an institutional point of view, this task may require close cooperation — e.g., for the
exchange of information and the understanding of environmental constraints to power system
expansion — between the planning authorities and the governmental bodies responsible for
environmental licensing. Nonetheless, particular attention should be directed to avoiding that
the consideration of environmental dimension within the power system expansion planning
activity is reduced to obtaining environmental licenses as just another planning task. That is to
say, the main goal should not be merely obtaining the environmental licenses and permits for
projects already at the planning stage. Rather, the main goal is to ensure (1) that power system
expansion plans adhere to social expectations regarding the environment, and (2) that the costs
8/20/2019 Mauritius Power Sector RAS Report Part 1
20/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
16
of compliance with these expectations are properly assessed, in order to allow meaningful
comparisons of expansion alternatives under consideration of all of the relevant costs —
including, but not limited to, the costs of mitigation of environmental impacts.
Regarding the third topic, the recommendations of the WB team to the GoM are the following:
Implement mechanisms to allow governmental bodies (including the Ministry of Public
Utilities) to regularly monitor the compliance of the power system expansion process
with energy policy goals.
Increase the frequency of update and publication of energy policy goals, taking into
account not only the status of compliance of current plants with long-term goals, but
also any conjuncture constraints that may delay the achievement of these goals.
Enhance the preparedness of CEB to carry out actions required to meet policy goals,
through workforce capacity building.
Establish clear differentiation between the attributions of setting the energy policy (by
governmental bodies directly reporting to the central government) and of executing
power system expansion and operation under the guidelines of this policy (by CEB).
Make sure that other governmental policies (fiscal, industrial, environmental,
infrastructure development, etc.) are consistent with the objectives of the energy policy
and enable the achievement of its goals.
8/20/2019 Mauritius Power Sector RAS Report Part 1
21/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
17
PART II I . ASSESSMENT OF DEMAND FORECASTS
Electricity demand forecasts are a key input for the process of power system expansion
planning. For this reason, the technical analyses of this report begin with this topic.
This third part of the report is organized as follows:
In Chapter 1, the WB team presents its independent electricity demand forecasts. These
forecasts are termed initial forecasts, as they do not take into account the effects of
energy efficiency and energy savings programs expected to be carried out in Mauritius
in the longer term, nor do they take into account structural changes in the economy or
energy consumption habits that are relevant for demand forecasts.
In Chapter 2, these initial forecasts are compared with the most recent demand
forecasts indicated by CEB in [6]. This comparison reveals a possible strategy to
incorporate the effects of energy efficiency and energy savings programs in the initial
forecasts.
In Chapter 3, the WB team presents an approximate approach to factor the effects of
energy efficiency and energy savings programs, as well as those of structural changes
in the economy and energy consumption habits, on the initial forecasts, in the absence
of primary data that allow a thorough evaluation of the effects of these phenomena. The
forecasts obtained under this approach are termed sensitized forecasts in the remainder
of this document.
Recommendations on the topic of demand forecasting are presented in Chapter 4.
The following quantities are relevant for the forecasts:
(1) Energy sales refers to the amount of electrical energy sold in a given year to end
consumers in the island of Mauritius.
(2) Energy sent out is defined as the energy effectively injected into the electricity grid of
the island of Mauritius by CEB, IPPs, and continuous power producers (CCPs4), and
takes into account technical losses in the electricity grid.5
(3) Peak power demand forecasts, also referred to simply as peak demand or peak load
forecasts, refers to the maximum power demand in the electricity grid, also taking
technical losses into account.
4 According to the following definition of [2]: “In Mauritius, CPPs refers to sugar factories which generate
electricity from ‘bagasse’ during the crop season and export it to the CEB’s grid.”
5 No references to commercial losses are made in [2]. For this reason, the WB’s team assumes that they are
not relevant in the island of Mauritius.
8/20/2019 Mauritius Power Sector RAS Report Part 1
22/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
18
1 INIT IAL ELECTRICITY DEMAND FORECASTS
In this chapter, the WB team presents the initial electricity demand forecasts for 2014 – 2022.
These forecasts are termed initial forecasts, as they do not take into account the effects of
energy efficiency and energy savings programs expected to be carried out in Mauritius in thelonger term.
1.1 Forecasts of electricity sales
The forecasts of the electricity sales in the island of Mauritius will be based on a traditional
econometric model [3], which relates electricity consumption to GDP levels according to the
following equation:
∙
where:
E t = electricity sales (in gigawatt-hours [GWh]) in year t ;
GDP t = gross domestic product (in international dollars6) in year t ;
α = linear coefficient;
γ = exponent of power function.
The model above is a constant elasticity model , which accounts exclusively for the income
elasticity of electricity demand (sales). In the method above, the income elasticity of demand
is constant and given by γ, since the elasticity is given by:
∙
The income elasticity of the electricity sales is the explanatory economic phenomenon
considered in the model above. Also, in this model this elasticity does not change with time,
which is due to the parameters α and γ being obtained by fitting the function to historical data,
and then kept constant for the whole projection horizon.
The use of a top-down aggregate forecast model, such as the one described above, is determined
mainly by constraints on the data available for the forecasting activities, and should not be
interpreted as a recommendation to use this model specifically or this class of models. In fact,
there are many benefits in using bottom-up end-use forecasting models, such as the possibility
to better estimate the effects of changes in the patterns of electricity consumption in time. For
6 GDP figures are presented considering purchasing power parity (PPP), which explains the reference to
international USD. An international dollar has the same purchasing power over GDP as the USD has in the
United States. Therefore, we often refer to international dollars simply as USD in this document, for the
sake of conciseness of notation.
8/20/2019 Mauritius Power Sector RAS Report Part 1
23/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
19
this reason, end-use forecast methods may be preferred over aggregate econometric models,
such as the one described above, whenever reliable data are available to be used as inputs for
them.
To select the historical data on electricity sales and on GDP to be used for the fitting of theabove model, we may consider the information displayed in Table 1.1.
Table 1.1 – Electricity sales in the island of Mauritius and GDP (PPP)
of the Republic of Mauritius7: historical data (2004 – 2014)
Sources: [4], [5], [6]
(a) Total sales for 2014 are provided in [6]. The reference did not contain the composition of sales by sector.
(b) GDP PPP data for 2014 were not available in [4] as the time of the elaboration of this report.
Not surprisingly, Table 1.1 reveals that the growth of the participation of the services sector in
the composition of the GDP has been accompanied by a growth of the share of the commercial
consumption segment in the total electricity sales in the island of Mauritius. The data reveal
that the economy (and the electricity consumption) of Mauritius is dynamically changing,
suggesting that the income elasticity of electricity consumption will also be changing
continuously. Since the econometric model used for the demand forecasts of this section does
not account for changes in the income elasticity of demand, we opt to adjust the model with
basis solely in the data for the last three years of the historical series for which data are available
on both total sales and GDP (2011 – 2013), to at least capture the trend corresponding to a more
recent stance of the economic and physical data.
Fitting the model to the data of this period results in the following values for the parameters: α
= 87.83 and γ = 1.070.8 Therefore, the resulting electricity sales forecast model is:
7 The GDP for the Republic of Mauritius is used as a proxy for that of the island of Mauritius (for which the
projections of electricity sales are executed), as no separate data of the GDP of the island of Mauritius are
available.
8 The reader will notice that the income elasticity implicit in this model is 1.070. Developing countries tend
to have slightly higher income elasticities of electricity demand; however, the lower value for Mauritius is
generally compatible with the preponderance of the services sector in the structure of the country’s economy.
Res Com Ind Other Agriculture Industry Services
2004 1,682.0 33% 30% 33% 4% 15.47 6% 29% 64%
2005 1,752.2 34% 31% 31% 4% 15.66 6% 28% 66%
2006 1,855.1 33% 31% 33% 4% 16.28 5% 26% 69%
2007 1,950.5 32% 31% 33% 4% 17.24 4% 26% 69%
2008 2,028.4 31% 33% 32% 3% 18.19 4% 27% 69%2009 2,043.2 33% 34% 30% 3% 18.73 4% 27% 69%
2010 2,147.5 32% 34% 30% 3% 19.50 4% 26% 70%
2011 2,201.4 32% 36% 30% 3% 20.26 4% 25% 71%
2012 2,266.8 33% 36% 29% 3% 20.91 3% 25% 72%
2013 2,354.9 32% 36% 29% 3% 21.58 3% 24% 72%
2014 2,422.0 N/A(a)
N/A(b)
Composition by sector of origin [%]
GDP, PPP
GDP, PPP [Billion
USD@2011]
Year
Electricity sales
Total sales
[GWh]
Composition by sector [%]
8/20/2019 Mauritius Power Sector RAS Report Part 1
24/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
20
87.83 ∙ .00
Using this model to obtain forecasts of electricity sales for 2015 – 2022 requires projections of
the GDP of the Republic of Mauritius for the same time horizon. We adopt the projections of
the International Monetary Fund (IMF), which are available for the period 2014 – 20199 [7]. The
corresponding projections of the annual GDP growth of the Republic of Mauritius, and the GDP
in constant 2011 international dollars corresponding to these projections for 2014 – 2019, are
indicated in Table 1.2.10 The growth rate used to obtain GDP estimates for 2020 – 2022
corresponds simply to the average growth during 2014 – 2019.
Table 1.2 – Projected GDP and GDP growth rates (base scenario): 2014 – 2022
For the analyses of this report, we are interested in obtaining electricity demand projections for
three scenarios: base case (or simply base projection), and high growth and low growth
scenarios (or simply high and low projections). The data in Table 1.2 will be used to obtain the
base projections. To obtain the high and low projections, we refer to [8], in which the IMF
presents projections of long-term economic growth for Mauritius for three scenarios: baseline,
optimistic, and pessimistic. The projected growth rates presented in [8] are sensitized with
respect to several items, but for each sensitivity analysis, projections are presented for the
baseline, optimistic, and pessimistic scenarios. Also, the difference in projected growth rates
between the pessimistic and the baseline scenarios, and between the optimistic and the baseline
scenarios, is approximately 30 – 33 percent for all sensitivity analyses. Therefore, to construct
the projections of GDP to be used in our electricity demand projections, we adopt the
assumption that the growth rates in the low growth scenario will be one-third lower than those
of the base case, and that those of the high growth scenario will be one-third higher than those
9 A consultation of traditional sources, such as the WB, the IMF, and The Economist Intelligence Unit,
revealed that no projections are available for the period until 2022.
10 The quantity originally projected by the IMF was the GDP based on PPP valuation in current international
dollars. Projections of the U.S. inflation, from the same source, were used to convert the original data from
current to constant international dollars. The growth rates reported in Table 1.2 are those implicit in these
projections converted to constant international dollars. The GDP values in constant 2011 international dollars
indicated in the table were obtained by applying the projected growth rates to the value of GDP (PPP) verified
in 2013, according to the WB database [4].
2014-2013 3.02% 2014 22.23
2015-2014 3.66% 2015 23.05
2016-2015 3.88% 2016 23.94
2017-2016 3.92% 2017 24.88
2018-2017 3.96% 2018 25.86
2019-2018 4.12% 2019 26.93
2020-2019 3.76% 2020 27.94
2021-2020 3.76% 2021 28.99
2022-2021 3.76% 2022 30.08
Biennium Year
Projected GDP (PPP)
growth rate
[%/year]
Projected GDP, PPP
[Billion USD@2011]
8/20/2019 Mauritius Power Sector RAS Report Part 1
25/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
21
of the base case. The resulting GDP and GDP growth rates for 2014 – 2022 are indicated in
Table 1.3. It is worth emphasizing that we do not assume any modification in the mathematical
model relating GDP and electricity sales across the scenarios.
Table 1.3 – Projected GDP and GDP growth rates (low and high growth scenarios): 2014 – 2022
The effects of applying the previously presented model results in the low, base, and high
projections of the electricity sales in the island of Mauritius are indicated in Table 1.4 and
Figure 1.1.
Table 1.4 – Projected electricity sales in the island of Mauritius
(low , base, and high projection scenarios): 2015 – 2022
Low scenario High scenario Low scenario High scenario
2014-2013 2.02% 4.02% 2014 22.02 22.45
2015-2014 2.45% 4.87% 2015 22.56 23.54
2016-2015 2.60% 5.16% 2016 23.14 24.76
2017-2016 2.62% 5.21% 2017 23.75 26.04
2018-2017 2.65% 5.27% 2018 24.38 27.42
2019-2018 2.76% 5.48% 2019 25.05 28.92
2020-2019 2.52% 5.00% 2020 25.69 30.36
2021-2020 2.52% 5.00% 2021 26.33 31.88
2022-2021 2.52% 5.00% 2022 27.00 33.48
Biennium Year
Projected GDP (PPP)
growth rate [%/year]
Projected GDP, PPP
[Billion USD@2011]
Low scenario Base case High scenario
2015 2,485.64 2,517.03 2,548.44
2016 2,554.85 2,621.68 2,689.42
2017 2,626.63 2,731.66 2,839.54
2018 2,701.31 2,847.63 2,999.95
2019 2,781.15 2,973.31 3,176.13
2020 2,856.17 3,093.06 3,346.33
2021 2,933.21 3,217.64 3,525.66
2022 3,012.33 3,347.23 3,714.59
Year Projected electricity sales [GWh]
1,500
2,000
2,500
3,000
3,500
4,000
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
E l e c t r i c e n e r g y s a l e s [ G W
h ]
Histor ical sales [GWh] Pro jected electrici ty sales [kWh] Low scenario
Projected electricity sales [kWh] Base case Projected electricity sales [kWh] High scenario
8/20/2019 Mauritius Power Sector RAS Report Part 1
26/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
22
Figure 1.1 – Historical and projected electricity sales in the island of Mauritius (low , base, and high
projection scenarios)
1.2 Forecasts of energy sent out
With the projections of electricity sales at hand, we proceed to the projections of energy sent
out . As previously mentioned, the energy sent out is energy effectively injected into the
electricity grid of the island of Mauritius by CEB, IPPs, and CCPs. Therefore, this quantity
differs from the electricity sales due to the technical losses in the electricity grid. As there are
no references to commercial losses in [2], the WB team assumes that these losses are not
relevant in the island of Mauritius.
The historical figures of levels of energy losses in Figure 1.2 (in percentage of the energy sent
out11) in Mauritius are provided in [2]:
Source: [2]
Figure 1.2 – Historical levels of technical energy losses in the electricity grid: 2001 – 2011
Figure 1.2 is succeeded by the following excerpt in [2]:
“It can be observed that the network losses of the country are continuously improving.
However, there is a limit to which the system losses can be reduced. For the planning
period, CEB has assumed a network loss of around 8%.”
This assumption of the maintenance of the levels of technical losses in the electricity network
at 8 percent is adopted for the analyses of this report. Considering this level of technical losses,
the projections of energy sent out for the three scenarios are indicated in Table 1.5.
11 That is to say, the losses level is defined as:
Losses [%] = [(total energy sent out – total energy sales) / (total energy sent out)] · 100%.
8/20/2019 Mauritius Power Sector RAS Report Part 1
27/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
23
Table 1.5 – Projected energy sent out in the island of Mauritius (low , base, and high projection scenarios):
2015 – 2022
1.3 Forecasts of peak demand
Finally, the forecasts of peak power demand in the island of Mauritius are approached. The data
for the calculation of the load factor of the power system in the island of Mauritius, presented
in Table 1.6, are relevant for these forecasts.
Table 1.6 – Data for calculation of the load factor in the island of Mauritius: 2004 – 2014
(a) Assumed data. Compatible with assumptions of [2].
(b) Assumed data on technical losses required for the calculation of the load factor.
Sources: [2], [5], [6]
It is clear from Table 1.6 that the load factor in the island of Mauritius has grown significantly
since 2004, even though with fluctuations (an increase to levels over 67 percent in 2007 and
2008, followed by a decrease to 65.67 percent and then a subsequent increase). This trend is
consistent with the increasing participation of the commercial segment in the consumption of
electricity, and with the typical load profile of consumers of this segment, with a significant use
of air-conditioning devices during all working hours during the summer season. Therefore, it is
fair to expect that the continuing growth of the participation of the services sector in the
economy of Mauritius, and the associated growth of the participation of the commercial
Low scenario Base case High scenario
2015 2,701.79 2,735.90 2,770.042016 2,777.01 2,849.65 2,923.28
2017 2,855.03 2,969.19 3,086.46
2018 2,936.21 3,095.25 3,260.81
2019 3,022.99 3,231.86 3,452.31
2020 3,104.53 3,362.02 3,637.32
2021 3,188.27 3,497.43 3,832.24
2022 3,274.27 3,638.29 4,037.60
Year Projected energy sent-out [GWh]
Peak demand [MW] Date of occurrence
2004 1,682 10.5% 332.6 23-Nov-2004 1,879 8,784 214.0 64.33%
2005 1,752 11.1% 353.1 27-Dec-2005 1,971 8,760 225.0 63.72%
2006 1,855 9.5% 367.3 20-Dec-2006 2,050 8,760 234.0 63.71%
2007 1,951 9.7% 367.6 29-Nov-2007 2,160 8,760 246.6 67.08%
2008 2,028 9.5% 378.1 20-Mar-2008 2,241 8,784 255.2 67.48%
2009 2,043 8.6% 388.6 18-Feb-2009 2,235 8,760 255.2 65.67%
2010 2,148 8.2% 404.1 2-Mar-2010 2,339 8,760 267.0 66.08%
2011 2,201 7.9% 412.5 20-Dec-2011 2,390 8,760 272.9 66.15%
2012 2,267 8.0%(a)
430.0 Not Available 2,464 8,784 280.5 65.23%(b)
2013 2,355 8.0%(a)
441.1 Not Available 2,560 8,760 292.2 66.24%(b)
2014 2,422 8.0%(a)
446.0 Not Available 2,633 8,760 300.5 67.38%(b)
Number of
hours in
year [h]
Electricity
sent-out
[average MW]
Load factor
[%]
Electricity
sales [GWh]
Technical losses in
electricity network
[%]
Peak power demand and date of
occurrence
Electricity
sent-out
[GWh]
Year
8/20/2019 Mauritius Power Sector RAS Report Part 1
28/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
24
segment in electricity consumption, will continue to increase the load factor in the island of
Mauritius.
For the projection of peak demand, the WB team opts to assume that the load factor of the
Mauritian system will remain constant at the value estimated for 2014 (67.38 percent)throughout the horizon. This is a conservative assumption, since no improvement (increase) of
the load factor within the projection horizon (2015-2022) is assumed. Given a set of projections
of energy sent out, adopting a lower load factor for the projection of peak demand results in a
higher projection of this latter quantity, which is why we characterize the assumption of
maintenance of the load factor verified in 2014 for the whole projection horizon as conservative.
Given the projections of energy sent out indicated in Table 1.5, and considering the fixed load
factor of 66.15 percent for the horizon 2014 – 2022, the resulting forecasts of peak demand for
the three scenarios of interest of this analysis are those shown in Table 1.7 and Figure 1.3.
Table 1.7 – Projected summer peak demand in the island of Mauritius
(low , base , and high projection scenarios): 2015 – 2022
Figure 1.3 – Historical and projected summer peak demand in the island of Mauritius
(low , base, and high projection scenarios)
Low scenario Base case High scenario
2015 457.74 463.52 469.30
2016 470.48 482.79 495.26
2017 483.70 503.04 522.91
2018 497.45 524.40 552.45
2019 512.16 547.54 584.89
2020 525.97 569.59 616.23
2021 540.16 592.54 649.26
2022 554.73 616.40 684.05
Year Projected peak power demand [MW]
0
100
200
300
400
500
600
700
800
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
P e a k p o w e r d e m a n d [ M W ]
Historical peak demand [MW] Projected peak power demand [MW] Low scenario
Projected peak power demand [MW] Base case Projected peak power demand [MW] High scenario
8/20/2019 Mauritius Power Sector RAS Report Part 1
29/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
25
The instant power demands reported above in Table 1.7 and Figure 1.3 correspond to the
summer peak in the island of Mauritius. The winter peak (Table 1.8) is determined by
considering historical data provided in [9], in which a ratio of the winter to the summer peak
demand is reported as being 89 percent. This information seems to refer to the most recent
year — 2012 — for which data were available as of the elaboration of [9].
Table 1.8 – Projected winter peak demand in the island of Mauritius
(low , base , and high projection scenarios): 2015 – 2022
In this document, references to peak demand , without specification of the season in which this
demand occurs, allude to the summer peak demand.
2 COMPARISON WITH RECENT FORECASTS FROM CEB
In this chapter, the initial electricity demand forecasts elaborated by the WB team and presented
in the previous chapter are compared with the most recent demand forecasts indicated by CEB
in [6].
The comparison focuses on the forecasts of electricity sales and peak demand, and will facilitate
a discussion on a possible way of incorporating the effect of energy efficiency and energy
savings programs into the initial forecasts presented in Chapter 1, in order to obtain the
sensitized forecasts.
Figure 2.1 and Figure 2.2 indicate, respectively, the forecasts for electricity sales and peak
demand [6] for 2015 – 2022, as well as the historical values until 2014.
Low scenario Base case High scenario
2015 407.39 412.53 417.68
2016 418.73 429.68 440.78
2017 430.49 447.71 465.39
2018 442.73 466.71 491.68
2019 455.82 487.31 520.55
2020 468.11 506.94 548.452021 480.74 527.36 577.84
2022 493.71 548.60 608.80
Year Projected winter peak power demand [MW]
8/20/2019 Mauritius Power Sector RAS Report Part 1
30/155
T E C H N I C A L A S S I S T A N C E T O G O V E R N M E N T O F M A U R I T I U S I N T H E E N E R G Y S E C T O R
26
Figure 2.1 – Electricity sales in the island of Mauritius projected by CEB and historical data
Figure 2.2 – Peak demand in the island of Mauritius projected by CEB and historical data
Figure 2.3 compares the initial projections of the previous section with the demand forecasts
of the IEP 2013 – 2022.
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
2004 20