Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Our visionTo deliver energy security for all Australians, and meet the changing needs of the market by involving multiple jurisdictions, participants, and communities.
We operate Australia's National Electricity Market and power grid in Australia’s eastern and south-eastern seaboard, and the Wholesale Electricity Market and power grid in south-west WA.
We also operate retail and wholesale gas markets across south-eastern Australia and Victoria’s gas pipeline grid.We are a company with three control centres and multiple offices across five States. Our costs are recovered through fees.
Ownership
Marketparticipants
40%Governments of Australia
60%The image part with relationship ID rId3 was not found in the file.
The Australian energy industry changed on 28 September 2016
Black system event - with a state losing power, impacting 1.7 million Australians
• Loss of three transmission lines (tornado wind speeds 190-260km/h)
• Six system faults, protective settings activated, disconnection of wind farms, 465 MW loss
• Heywood Interconnector compensated, safety protection measures activated, 900 MW from Victoria to SA lost.
The Australian energy industry changed on 28 September 2016
Black system event - with a state losing power, impacting 1.7 million Australians
• Restart proceeded with the use of a System Restart Ancilliary Service generating unit
• 40% of load that could be restored had been restored by 9pm local time and after midnight, 80-90% of the load capable of being restored had been restored.
• All load was restored by 11 October.
The Australian energy industry changed on 28 September 2016
Black system event - with a state losing power, impacting 1.7 million Australians
AEMO’s key finding • The technical challenges of the changing
generation mix need to be managed with the support of efficient and effective regulatory and market mechanisms that work together for the least cost and long-term interest of consumers.
AEMO’s final report into the event19 recommendations for power system improvement, split into the following categories:1. Enhanced preparation (short term operation and
weather forecasting, and greater access to data)2. During the event (including stakeholder
engagement)3. Post event (System restart and managing market
suspension).
18 recommendations to be completed by end of 2017, with the final to be implemented by early 2018.
Plant connecting to the Grid need to meet higher technical standards
Actions taken • The windfarms inability to ride through a sequence of
faults in close succession has been dealt with.• AEMO has completed more detailed studies of the
dynamic performance of the South Australian system, much of it using new, more detailed power system modelling
• Revised technical standards have been proposed from this work.
Implementation of Rule changes• Following consultation with stakeholders, ESCOSA
introduced new licence conditions for generators seeking to connect in South Australia
• The new licence conditions have applied to all new connections since August 2017
• Proposed changes to the National Electricity Rules were then lodged with the AEMC and are being assessed
• This process is consistent with recommendations in the
A range of essential services are required to ensure the security of the Power Grid • Maintaining system security and resilience requires a
number of essential services from connected plant• These services have often been given little attention in the
past as they are provided by conventional plant. As the generation mix changes, the power system behaviour changes and the need for these services become evident
• System strength has been identified as the most critical currently in South Australia.
Analysis highlights system needs
Levels of system strength is required to operate a secure power system
South Australia• In November 2016 AEMO set a minimum
requirement of two large synchronous machines online in SA to manage system strength related issues.
• In July 2017, following further work AEMO introduced enhanced arrangements.o For wind generation up to 1200 MW a more
complex arrangement of synchronous plant is required to be online at all times
o A constraint limits wind output to 1,200 MW unless there is more than the minimum synchronous generation online at the time.
• AEMO intervenes in the market and directs to ensure sufficient system strength to meet lower levels of wind generation. It does not intervene to allow higher levels of wind generation.
Management of power system and supply of essential services
South Australia and NEM• The AEMC have now issued Rules to deal with
system strength and provided transitional arrangements
• AEMO is working with Electranet to determine the way forward
• A better structured approach and investment in synchronous condensers can bring down pool prices
• Providing an orderly transition can deliver a better informed market, reduce risk and reduce costs.
The electricity industry in Australia is undergoing change and disruption on an unprecedented scale • Increased customer choice and changing
customer behaviour• New technologies, new business models • Costs of renewables now below conventional
generation in some cases• Less conventional synchronous plant• More distributed energy• New role for storage
• Finkel review commissioned along with advice from AEMO and now advice from the ESB
Australia’s changing load profile
600
800
1,000
1,200
1,400
1,600
1,800
2,000
00:00 01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00
Aver
age
Annu
al S
A1 O
pera
tiona
l Dem
and
as G
ener
ated
(MW
)
Time (hrs)
South Australia daily demand for grid electricity
2009 2011 2014 2016 2020 Forecast 2030 Forecast
Two-waypower gridevolutionHuge growth in customers providing energy back to the grid.
2017 2030
6.5GWh
20.0GWh
2015 2016
500
6,750
Rooftop PVs(GWh)
BatteryInstallations
Source: AEMO Source: Sunwiz
By 2050customer-ownedgenerators will supply Australia’s electricity needs
30-45%
Source: CSIRO
Managing security and reliability in a transforming system
Adequacy
Reliability and Security
Resources required (not just conventional generators but other solutions)
AEMO's actions to support the transformation
Frequency and inertia requirements
Operational changes and advanced forecasting tools
Proof of concepts
Advice on reserves and need for flexibility
Storage
AEMO is playing an active role in managing the transformation
Australian market has changed rapidly- with government policy, consumer attitudes and technology all contributing
Reaching a tipping point- where renewables are becoming cheaper than traditional resources and can be deployed more rapidly
Markets need to value and price supply reliability and security - inertia, system strength, and dispatchability all need to be considered.