Upload
ngoquynh
View
214
Download
0
Embed Size (px)
Citation preview
1
Martin Carr
From: Fixed Wire Testing [[email protected]]Sent: 24 October 2016 08:52To: [email protected]: EDIT: 304999472232807237 Fixed Wire Testing 160415AS MC
Item Fixed Wire Testing
HS Reference Fixed Wire Testing 160415AS MC
Due Date 31-10-2016
Status Outstanding+
Comments/Notes Martin C to test all fixed wiring in the factory. Estimated cost £7500 for testing, repairs cost as identified. This project is a legal requirement. 16/04/15 Quote requested for alternative company. Note not due until 2016 30/04/15 Awaiting clarification of alternative quote 30/04/15 Alternative quote is approx £4000. Work could start next month. However, due to the budget and planning it will be Q3. 27/07/15 In budget discussion. 07/09/15 Will be looked at again in 2016 17/05/16 Await start date 31/05/16 Start date should be 6th June 02/06/16 Probably start 21st June 21/06/16 Job has started 19/07/16 Ongoing, few weeks should be done. 30/08/16 Estimate mid Sep for finish 22/09/16 Being done at the moment 27/09/16 Done, but maybe a few weeks for paperwork 19/10/16 Chased paperwork 24/10/16 Final report should be here this week
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 304999472232807237
3
Martin Carr
From: Wood LEV [[email protected]]Sent: 21 October 2016 10:50To: [email protected]: 352852612377241707 http://hs.carrs-silver.co.uk/woodlev.pdf
Item Wood LEV
HS Reference http://hs.carrs-silver.co.uk/woodlev.pdf
Due Date 21-10-2016
Status Outstanding+
Comments/Notes 21/10/16 Urgent work required on 4 items. NOTE removed from service until fixed; a/ CNC 4008 Machine b/ Cabinet Makers Shop - Bench extraction c/ De-nibbing Section LHS and RHS Benches when work pieces coated in white primer are sanded. d/ Wadkin Spindle Moulder 13 Refer to report for further details
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 352852612377241707
4
Martin Carr
From: Bunding for Chemicals [[email protected]]Sent: 19 October 2016 18:32To: [email protected]: EDIT: 304999718232785362 Bunding for chemicals MS 1205151226
Item Bunding for Chemicals
HS Reference Bunding for chemicals MS 1205151226
Due Date 20-10-2016
Status Outstanding+
Comments/Notes Martin C to purchase bunding for all chemicals on site.. http://www.tanks-direct.co.uk/ibc_spill_control/covered_ibc_pallet_bund_for_2_ibcs http://www.yellowshield.co.uk/double-covered-ibc-poly-sump-pallet Above links are to suppliers of onsite bunding. Estimated project cost £10000 This project is a legal requirement. 16/04/15 Matt to provide details of which areas require bunding 12/5/15 request partial bunding for oil in Rolling mill area (Hydraulic and slideway) £277 http://www.yellowshield.co.uk/drum-racking- Take the Hydraulic oil out of the Spray shop Garage (it doesent actually fit over the bund) to make space for other unbunded chemicals, and the Rolling mill oils can be ordered in 205L next time to have the storage all in one place 12/05/15 Glynn t advise on cost.. http://www.yellowshield.co.uk/drum-racking-system 01.07.15 Approximate cost for project estimated at £3000. GR to advise when capital available 01/07/15 GR to advise. 30/07/15 Marc you talked about bunding in the toolroom and rolling mill (there is also the IBC,s outside) have you got the links to what you suggest for these two internal projects? 16/09/15 Update from JB 22/09/15 Jason on holiday until Friday 28/09/15 The plan would be to have two of the above. One for the
5
rolling mill chemicals outside the "wendy house" the other being for the toolroom 28/10/2015 GR advised to await until 2016 due finance 15/08/16 There is minimal risk of current none bunded items 19/10/16 Areas to sort are the rolling mill and tool room areas. Suggest https://www.spillcontrolcentre.co.uk/renown-4-drum-spill-pallet In total 3 2 for rolling 1 for maint/toolroom.
Job Type Capex
Notifier [email protected]
Note you can also reply to this e-mail. 304999718232785362
6
Martin Carr
From: Press 2 [[email protected]]Sent: 19 October 2016 15:04To: [email protected]: EDIT: 325058151842767910 http://hs.carrs-silver.co.uk/press2.pdf
Item Press 2
HS Reference http://hs.carrs-silver.co.uk/press2.pdf
Due Date 31-10-2016
Status Completed+
Comments/Notes 25/05/16 Interlocking issues, passed to contractors 26/05/16 Not sure what "scotch" is. 02/06/15 Left message for him to contact me and arrange visit 21/06/16 Had word with Andy to clarify "scotch", had a look and think this is one for Yakub. Can you put it on his list please Martin. 04/07/16 Yacub to check and advise by the end of the week 08/07/16 Chased 12/07/16 Previous comments seem to have disappeared, Guard removed and repaired, replaced and is now safe, setters link pinned, production wanted to use press urgently, so have had to suspend rest of work. 18/07/16 The issue was - Excessive free clearance and travel at scotch with guard open. According to Yakubs last comments, this could be a worn plunger, to verify this will entail some serious stripping of press so will have to co-ordinate with production for down time. 08/08/16 TS reported press was making an unusually loud noise every so many strokes, observed it being used and problem did not happen, however next day Tony said it had made a really loud bang, so I advised him to stop using press and we will investigate when can. 09/08/16 CW asked if we will have a look as next job. 10/08/16 Had a look, scheduled for Monday.. 16/08/16 Stripped flywheel off and clutch mechanism, plunger looks well worn but as to how much will need Yakub to examine. There has been no lubrication on press for some time, some parts missing altogether, looking into remedying this. Will ask CW to contact Yakub for visit to assess and reassemble. Have sent Mohamed a text explaining situation.
7
23/08/16 Charles still to contact 24/08/16 Charles arranged for Mohamed to come Tues/Wed next week. 31/08/16 Breakdown in communication, Mohamed said he was waiting for contact from us and more pictures. These have been sent and on further contact he will arrange visit next week.. 07/09/16 Mohamed came didn't have correct spares, has taken old parts to repair/ refurbish and will come and refit when able. 13/09/16 Have altered scotch ready for Mohamed's visit. 17/10/16 Mohamed fitted new part ,assembled and set up press. Scotch alteration to weld up ready for Allianz check. 19/10/16 Scotch re-fitted etc. Press tried, working ok. A manual lube pump has been fitted which will require periodic operation to lube press.
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 325058151842767910
8
Martin Carr
From: Wall Saw [[email protected]]Sent: 19 October 2016 14:55To: [email protected]: EDIT: 348615913377637297 http://hs.carrs-silver.co.uk/ww001.pdf
Item Wall Saw
HS Reference http://hs.carrs-silver.co.uk/ww001.pdf
Due Date 31-10-2016
Status Outstanding+
Comments/Notes 02/09/16 Work required 19/10/16 Rectified jamming guard etc, DC brake to order and fit.
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 348615913377637297
9
Martin Carr
From: Fixed Wire Testing [[email protected]]Sent: 19 October 2016 08:34To: [email protected]: EDIT: 304999472232807237 Fixed Wire Testing 160415AS MC
Item Fixed Wire Testing
HS Reference Fixed Wire Testing 160415AS MC
Due Date 25-10-2016
Status Outstanding+
Comments/Notes Martin C to test all fixed wiring in the factory. Estimated cost £7500 for testing, repairs cost as identified. This project is a legal requirement. 16/04/15 Quote requested for alternative company. Note not due until 2016 30/04/15 Awaiting clarification of alternative quote 30/04/15 Alternative quote is approx £4000. Work could start next month. However, due to the budget and planning it will be Q3. 27/07/15 In budget discussion. 07/09/15 Will be looked at again in 2016 17/05/16 Await start date 31/05/16 Start date should be 6th June 02/06/16 Probably start 21st June 21/06/16 Job has started 19/07/16 Ongoing, few weeks should be done. 30/08/16 Estimate mid Sep for finish 22/09/16 Being done at the moment 27/09/16 Done, but maybe a few weeks for paperwork 19/10/16 Chased paperwork
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 304999472232807237
10
Martin Carr
From: Replacement Extractor [[email protected]]Sent: 19 October 2016 08:30To: [email protected]: EDIT: 305000253232595418 Replacement Extractor MH 1510151729
Item Replacement Extractor
HS Reference Replacement Extractor MH 1510151729
Due Date 17-10-2016
Status Completed+
Comments/Notes Marc H to investigate replacement for polishing extractor.. Estimated project costs £55000. This project is a priority for business continuity. 16/04/15 Marc and AGH are looking and 2nd hand options 9-5-15 Carter environment have been on-site to survey and advise on alternative new machine 15-6-15 Carter environment advise that current usage requires 25000cfm (current machine is 28000cfm) if usage is projected to stay level or NOT increase then this is a cheaper option - Waiting for quote 17-5-15 - Quote £51000 ex works, £540 Delivery, £3210 intallation (2 day), £475 commissioning Total £55225 - sited (Carrs to connect services) 12-14 weeks leadtime 22/07/15 One for GR 10/09/15 Attached image of current inside damage. 14-9-2015 AAF to visit to provide alternate quote complete - Due to visit 17-9-2015 15-10-2055 Alternative quote from AAF attached (NOTE quote is dependant on euro exchange rate!) £52775 installed identical to current machine 07/01/16 Mark/Dave to get DSS to look at patch work.Dave from dss is coming in on friday 15/01/16 afternoon 12.15pm .
11
13/01/16 Have ordered spare chain and parts 1 week delivery we need to plan work on chain for the next few weeks. 15/01/16 Dave from dss is going to make some bigger outside cover plates so we can make a bigger opening on both sides of fan cover, so we can carry out repair to fan see photo in file then he will make some plates for fan damage will need to speak with martin carr on tuesday 19/01/16 Contact [email protected] 07816 144 433 21/01/16 dss quote inspection covers £135.00 made out requisition order mark parkin 21/01/16 That price is fine, just progress with job.Have placed order ok. 29/01/16 Can we have a meeting with production regarding the work we require to do on the extractor ie:Fit larger covers/repair damage to ducting inside fan/blades/chains links/cleaning extractor out,we have a cherry picker on site from 29/01/16 for one weeks hire.mark parkin 25/01/16 Will be installing larger covers this Friday/Saturday if need be. mark parkin.59977. 29/01/16 Due to weather conditions we will have to plan this job in again regards mark parkin. 02/03/16 Need to plan in to fit covers and chain repairs with production again. 18/03/16 Charles, can you advise on when we can have this from production? 21/03/16 The plan is to do this on a Friday after 10am. Also to do the clean at the same time, weather was the issue last time. 22/03/16 In view of current situation this time frame might need reviewing. 24/03/16 Emergency report issued by Allianz, CW agreed we need to address this quickly, will arrange for cleaning. 1/04/16 TS and team started to clean main duct and branch ducts in polishing shops. 01/04/16 Search e-mail for CEE contact and quote 18/04/16 Charles, when the patch work be done? 20/04/16 CW - Which Thursday are we going to do this? 21/04/16 This will be cleaned out next Thursday 28/04/16 More work next Thursday 04/05/16 Are we still going ahead with the scheduled repairs that were cancelled due to bad weather on 29/01/16. 04/05/16 Yes details to be sorted when CW returns from holiday next week 10/05/16 DW is contacting DSS to arrange for the plates to be made. We will then fit one afternoon 17/05/16 TH contact will be here on Monday to
12
quote for the whole job. 23/05/16 He has been to look at the job and will install the hatches after the spring bank week 08/06/16 Parts will be welded on Friday 13/06/16 Part of the job was done on Friday, more will be done this Friday 20/06/16 Work done Friday final part of work this Friday, weather permitting. 27/06/16 Further work will be done on Friday 01/07/16 More work is being done today, this should be the end for the moment 08/07/16 This has been done.. replacement maybe later 21/07/16 Just the matter of painting left to do. Richard to supply contact he has 10/08/16 Update requested from CW 15/08/16 See if banks have any suggestions 19/08/16 Await price from Banks for paint job. 09/09/16 Chased quote 13/09/16 Will be painted from next Monday 22/09/16 This is being painted at the moment. 05/10/16 There is now the pipe to paint, this will be started tomorrow 11/10/16 Pipe is being primed at the moment
Attachment 20150907_124030.jpg
Attachment QAPS24442 Carrs RCN.pdf
Job Type Maintenence
Notifier [email protected]
Note you can also reply to this e-mail. 305000253232595418
13
Martin Carr
From: Cross Cut Large [[email protected]]Sent: 18 October 2016 16:22To: [email protected]: EDIT: 348615445377295374 http://hs.carrs-silver.co.uk/ww0024.pdf
Item Cross Cut Large
HS Reference http://hs.carrs-silver.co.uk/ww0024.pdf
Due Date 25-10-2016
Status Completed+
Comments/Notes 02/09/16 Work required.. 26/09/16 fitted dc brake working ok 6secs. return mech. still to be sorted
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 348615445377295374
14
Martin Carr
From: Press 2 [[email protected]]Sent: 17 October 2016 09:28To: [email protected]: EDIT: 325058151842767910 http://hs.carrs-silver.co.uk/press2.pdf
Item Press 2
HS Reference http://hs.carrs-silver.co.uk/press2.pdf
Due Date 31-10-2016
Status Outstanding+
Comments/Notes 25/05/16 Interlocking issues, passed to contractors 26/05/16 Not sure what "scotch" is. 02/06/15 Left message for him to contact me and arrange visit 21/06/16 Had word with Andy to clarify "scotch", had a look and think this is one for Yakub. Can you put it on his list please Martin. 04/07/16 Yacub to check and advise by the end of the week 08/07/16 Chased 12/07/16 Previous comments seem to have disappeared, Guard removed and repaired, replaced and is now safe, setters link pinned, production wanted to use press urgently, so have had to suspend rest of work. 18/07/16 The issue was - Excessive free clearance and travel at scotch with guard open. According to Yakubs last comments, this could be a worn plunger, to verify this will entail some serious stripping of press so will have to co-ordinate with production for down time. 08/08/16 TS reported press was making an unusually loud noise every so many strokes, observed it being used and problem did not happen, however next day Tony said it had made a really loud bang, so I advised him to stop using press and we will investigate when can. 09/08/16 CW asked if we will have a look as next job. 10/08/16 Had a look, scheduled for Monday.. 16/08/16 Stripped flywheel off and clutch mechanism, plunger looks well worn but as to how much will need Yakub to examine. There has been no lubrication on press for some time, some parts missing altogether, looking into remedying this. Will ask CW to contact Yakub for visit to assess and reassemble. Have sent Mohamed a text explaining situation.
15
23/08/16 Charles still to contact 24/08/16 Charles arranged for Mohamed to come Tues/Wed next week. 31/08/16 Breakdown in communication, Mohamed said he was waiting for contact from us and more pictures. These have been sent and on further contact he will arrange visit next week.. 07/09/16 Mohamed came didn't have correct spares, has taken old parts to repair/ refurbish and will come and refit when able. 13/09/16 Have altered scotch ready for Mohamed's visit. 17/10/16 Mohamed fitted new part ,assembled and set up press. Scotch alteration to weld up ready for Allianz check.
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 325058151842767910
16
Martin Carr
From: mop spindle [[email protected]]Sent: 17 October 2016 08:47To: [email protected]: EDIT: 349675320377184347 auto polisher
Item mop spindle
HS Reference auto polisher
Due Date 31-10-2016
Status Outstanding+
Comments/Notes 14/09/16 Spindle requires modifying to accept smaller brg. carrier. JKP doing work 21/09/16 At operators request have asked JKP to modify both spindle ends. 17 10 16 need to contact JKP to see if ready for collection. Not ready yet!
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 349675320377184347
17
Martin Carr
From: Replacement Extractor [[email protected]]Sent: 11 October 2016 10:09To: [email protected]: EDIT: 305000253232595418 Replacement Extractor MH 1510151729
Item Replacement Extractor
HS Reference Replacement Extractor MH 1510151729
Due Date 17-10-2016
Status Outstanding+
Comments/Notes Marc H to investigate replacement for polishing extractor.. Estimated project costs £55000. This project is a priority for business continuity. 16/04/15 Marc and AGH are looking and 2nd hand options 9-5-15 Carter environment have been on-site to survey and advise on alternative new machine 15-6-15 Carter environment advise that current usage requires 25000cfm (current machine is 28000cfm) if usage is projected to stay level or NOT increase then this is a cheaper option - Waiting for quote 17-5-15 - Quote £51000 ex works, £540 Delivery, £3210 intallation (2 day), £475 commissioning Total £55225 - sited (Carrs to connect services) 12-14 weeks leadtime 22/07/15 One for GR 10/09/15 Attached image of current inside damage. 14-9-2015 AAF to visit to provide alternate quote complete - Due to visit 17-9-2015 15-10-2055 Alternative quote from AAF attached (NOTE quote is dependant on euro exchange rate!) £52775 installed identical to current machine 07/01/16 Mark/Dave to get DSS to look at patch work.Dave from dss is coming in on friday 15/01/16 afternoon 12.15pm .
18
13/01/16 Have ordered spare chain and parts 1 week delivery we need to plan work on chain for the next few weeks. 15/01/16 Dave from dss is going to make some bigger outside cover plates so we can make a bigger opening on both sides of fan cover, so we can carry out repair to fan see photo in file then he will make some plates for fan damage will need to speak with martin carr on tuesday 19/01/16 Contact [email protected] 07816 144 433 21/01/16 dss quote inspection covers £135.00 made out requisition order mark parkin 21/01/16 That price is fine, just progress with job.Have placed order ok. 29/01/16 Can we have a meeting with production regarding the work we require to do on the extractor ie:Fit larger covers/repair damage to ducting inside fan/blades/chains links/cleaning extractor out,we have a cherry picker on site from 29/01/16 for one weeks hire.mark parkin 25/01/16 Will be installing larger covers this Friday/Saturday if need be. mark parkin.59977. 29/01/16 Due to weather conditions we will have to plan this job in again regards mark parkin. 02/03/16 Need to plan in to fit covers and chain repairs with production again. 18/03/16 Charles, can you advise on when we can have this from production? 21/03/16 The plan is to do this on a Friday after 10am. Also to do the clean at the same time, weather was the issue last time. 22/03/16 In view of current situation this time frame might need reviewing. 24/03/16 Emergency report issued by Allianz, CW agreed we need to address this quickly, will arrange for cleaning. 1/04/16 TS and team started to clean main duct and branch ducts in polishing shops. 01/04/16 Search e-mail for CEE contact and quote 18/04/16 Charles, when the patch work be done? 20/04/16 CW - Which Thursday are we going to do this? 21/04/16 This will be cleaned out next Thursday 28/04/16 More work next Thursday 04/05/16 Are we still going ahead with the scheduled repairs that were cancelled due to bad weather on 29/01/16. 04/05/16 Yes details to be sorted when CW returns from holiday next week 10/05/16 DW is contacting DSS to arrange for the plates to be made. We will then fit one afternoon 17/05/16 TH contact will be here on Monday to
19
quote for the whole job. 23/05/16 He has been to look at the job and will install the hatches after the spring bank week 08/06/16 Parts will be welded on Friday 13/06/16 Part of the job was done on Friday, more will be done this Friday 20/06/16 Work done Friday final part of work this Friday, weather permitting. 27/06/16 Further work will be done on Friday 01/07/16 More work is being done today, this should be the end for the moment 08/07/16 This has been done.. replacement maybe later 21/07/16 Just the matter of painting left to do. Richard to supply contact he has 10/08/16 Update requested from CW 15/08/16 See if banks have any suggestions 19/08/16 Await price from Banks for paint job. 09/09/16 Chased quote 13/09/16 Will be painted from next Monday 22/09/16 This is being painted at the moment. 05/10/16 There is now the pipe to paint, this will be started tomorrow 11/10/16 Pipe is being primed at the moment
Attachment 20150907_124030.jpg
Attachment QAPS24442 Carrs RCN.pdf
Job Type Maintenence
Notifier [email protected]
Note you can also reply to this e-mail. 305000253232595418
20
Martin Carr
From: degreasing tank [[email protected]]Sent: 11 October 2016 10:09To: [email protected]: EDIT: 330473926377745521 plating shop
Item degreasing tank
HS Reference plating shop
Due Date 15-11-2016
Status Outstanding+
Comments/Notes 05/02/16 .Breakdown on heaters sage 2 have placed order with jason urgent, Guyson int p3ht0021 1200w 4off,p3ht0022 2 off heater details. Have repaired damaged copper plate made new one repaired burnt up wire again!!!!!!! will test again on 08/02/16 first thing..Has been ok today will leave this outstanding till we have delivery of heaters. 09/02/16 Heaters now in stock and in our stores mark parkin. 10/02/16 stage 3 no htg. 3 wires off elements. this is a recurring problem as reported earlier, is it the atmosphere? M Parkin contacting Guyson for advice. 22/02/16 Spoken to guyson to get service engineer out we would have to book him in and pay for service engineer do we want to do this ? 22/02/16 Please advise on costs MC. 22/02/16 Martin the cost of a engineer is £825.00 a day .contact details mick banks tel: 01756 799911, machine details serial 59266-3-99 type uor1500/3r+r/t we will have to book a visit, do you want me to book visit ? regards mark 25/02/16 This machine tripped out again this morning waiting to see if wire or heaters gone again !! 7/03/16 Machine tripped out first thing in morning, reset mcb for stage two heater, machine powered up and stayed on, checked all other heaters and found auxillary bank on stage three not working and one main heater on stage three u/s (which was already known about). Left machine coming up to temp. on all stages. will need further investigation and repair. We really need a solution to this ever recurring problem. 24/03/16 Testing required to see if the aquious can
21
do more cleaning 30/03/16 STAGE 2 + 3 CIRCULATING PUMPS NOT WORKING, SIEZED UP WITH NOT BEING USED FOR PROLONGED PERIOD, SUSPECT WILL NEED AT LEAST A REWIND. WILL SEND TO ALL PUMPS FOR QUOTE. 06/0/16 CW okayed pump repair and pump replacement, ordered new pump on order no.60336. 11/04/16 pumps arrived will fit when can 17/04/16 Pumps fitted and tested. traced fault on air valves and repaired faulty valve. 18/04/16 Charles, when can testing of cutlery cleaning start? 19/04/16 Update requested from Charles 25/04/16 Charles, when is this testing happening? 03/05/16 We are awaiting oily cutlery blanks then will test, but suspect we will need different chemicals 10/05/16 Tests happening today, but looks like heaters and Ultrasonic require work 16/05/16 3 out of 4 htrs. on stage 1 u/s. stage 2 ok, 1 out of 3 htrs. u/s on stage 4. 6 out of 8 ultrasonic units not functioning, so called spare units are those that were u/s from trich cleaner, maybe could salvage 1 unit. Will try to get estimate for repairs. 24/05/16 CW has prices for spares, have ordered replacement immersion htrs. Will fit these which should improve cleaning as Ist stage will be able to reach a higher temp. Will check over U/Sonic pulse drivers later. 08/06/16 Sorted and returned back to production. Note that now we do not plate, just clean. 20/06/16 No 2 Ultrasonics not working, fault with driver unit.Do we get Guyson engineer or send unit to them? left with CW. 21/06/16 CW has arranged for engineer's visit next week. 29/06/16 Report in search 01/07/16 There is a new solvent which we will trail in the next few weeks. If all goes well the idea is to try and put this in a smaller cleaner 19/07/16 New solvents will be tested after Daz holidays. The plan would then be to have trade in the two existing cleaners and replace with a smaller one 05/08/16 CW to arrange a trip to supplier next week 15/08/16 Meeting planned for 24th Aug 25/08/16 Trials ongoing, visit but further samples to be sent down. 01/09/16 Further samples to be sent, but will be a few weeks 22/09/16 More samples sent - few weeks before
22
feedback 07/10/16 Update requested from Daz 11/10/16 We currently have no reliable alternative to the one we have at the moment. The current system is working, but we do need to call the engineer from time to time. We are still investigating alternative options
Job Type Maintenence
Notifier [email protected]
Note you can also reply to this e-mail. 330473926377745521
23
Martin Carr
From: degreasing tank [[email protected]]Sent: 07 October 2016 14:25To: [email protected]: EDIT: 330473926377745521 plating shop
Item degreasing tank
HS Reference plating shop
Due Date 11-10-2016
Status Outstanding+
Comments/Notes 05/02/16 .Breakdown on heaters sage 2 have placed order with jason urgent, Guyson int p3ht0021 1200w 4off,p3ht0022 2 off heater details. Have repaired damaged copper plate made new one repaired burnt up wire again!!!!!!! will test again on 08/02/16 first thing..Has been ok today will leave this outstanding till we have delivery of heaters. 09/02/16 Heaters now in stock and in our stores mark parkin. 10/02/16 stage 3 no htg. 3 wires off elements. this is a recurring problem as reported earlier, is it the atmosphere? M Parkin contacting Guyson for advice. 22/02/16 Spoken to guyson to get service engineer out we would have to book him in and pay for service engineer do we want to do this ? 22/02/16 Please advise on costs MC. 22/02/16 Martin the cost of a engineer is £825.00 a day .contact details mick banks tel: 01756 799911, machine details serial 59266-3-99 type uor1500/3r+r/t we will have to book a visit, do you want me to book visit ? regards mark 25/02/16 This machine tripped out again this morning waiting to see if wire or heaters gone again !! 7/03/16 Machine tripped out first thing in morning, reset mcb for stage two heater, machine powered up and stayed on, checked all other heaters and found auxillary bank on stage three not working and one main heater on stage three u/s (which was already known about). Left machine coming up to temp. on all stages. will need further investigation and repair. We really need a solution to this ever recurring problem. 24/03/16 Testing required to see if the aquious can
24
do more cleaning 30/03/16 STAGE 2 + 3 CIRCULATING PUMPS NOT WORKING, SIEZED UP WITH NOT BEING USED FOR PROLONGED PERIOD, SUSPECT WILL NEED AT LEAST A REWIND. WILL SEND TO ALL PUMPS FOR QUOTE. 06/0/16 CW okayed pump repair and pump replacement, ordered new pump on order no.60336. 11/04/16 pumps arrived will fit when can 17/04/16 Pumps fitted and tested. traced fault on air valves and repaired faulty valve. 18/04/16 Charles, when can testing of cutlery cleaning start? 19/04/16 Update requested from Charles 25/04/16 Charles, when is this testing happening? 03/05/16 We are awaiting oily cutlery blanks then will test, but suspect we will need different chemicals 10/05/16 Tests happening today, but looks like heaters and Ultrasonic require work 16/05/16 3 out of 4 htrs. on stage 1 u/s. stage 2 ok, 1 out of 3 htrs. u/s on stage 4. 6 out of 8 ultrasonic units not functioning, so called spare units are those that were u/s from trich cleaner, maybe could salvage 1 unit. Will try to get estimate for repairs. 24/05/16 CW has prices for spares, have ordered replacement immersion htrs. Will fit these which should improve cleaning as Ist stage will be able to reach a higher temp. Will check over U/Sonic pulse drivers later. 08/06/16 Sorted and returned back to production. Note that now we do not plate, just clean. 20/06/16 No 2 Ultrasonics not working, fault with driver unit.Do we get Guyson engineer or send unit to them? left with CW. 21/06/16 CW has arranged for engineer's visit next week. 29/06/16 Report in search 01/07/16 There is a new solvent which we will trail in the next few weeks. If all goes well the idea is to try and put this in a smaller cleaner 19/07/16 New solvents will be tested after Daz holidays. The plan would then be to have trade in the two existing cleaners and replace with a smaller one 05/08/16 CW to arrange a trip to supplier next week 15/08/16 Meeting planned for 24th Aug 25/08/16 Trials ongoing, visit but further samples to be sent down. 01/09/16 Further samples to be sent, but will be a few weeks 22/09/16 More samples sent - few weeks before
25
feedback 07/10/16 Update requested from Daz
Job Type Maintenence
Notifier [email protected]
Note you can also reply to this e-mail. 330473926377745521
26
Martin Carr
From: Press Shop Heating [[email protected]]Sent: 07 October 2016 14:25To: [email protected]: EDIT: 328418129377734786 Press Shop Heating
Item Press Shop Heating
HS Reference Press Shop Heating
Due Date 07-10-2016
Status Completed+
Comments/Notes 12/01/16 Look at replace Electric heating. 18/01/16 The plumbers will need to look at this when they are in doing the silversmiths heater 25/01/16 This would need to be floor standing 11/02/16 Jason to seek quote 15/02/16 Updated requested - From: Jason Bee [mailto:[email protected]] Sent: 15 February 2016 08:33 To: 'Martin Carr' Subject: RE: EDIT: Outstanding+ HS Job 15-02-2016 Had a quick chat with Chaz, I think I will get a price for the 90uf Model that’s next to the toilet block opposite tubing department, maybe the next model down too.. 22/02/16 Quote attached 18/03/16 By the time this is delivered and then fitted it will not be needed until next winter. Given that heaters are cheaper to buy in summer, job post dated 31/05/16 Jason to investigate 21/06/16 Quote request also to [email protected] 20/07/16 Quote on file 21/07/16 Looking at ones that are floor mounted. 15/08/16 Quote received 16/08/16 Installation date requested 17/08/16 They will come to do final survey 23rd Sep, Install 29th. Need Maint to sort control before 07/09/16 New Stat will be here today 08/09/16 Just waiting for heater now. 05/10/16 Will be finished off tomorrow, was awaiting flu guard 07/10/16 Now fully installed
Attachment WJD_11037.pdf
27
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 328418129377734786
28
Martin Carr
From: Gas Heater Service [[email protected]]Sent: 07 October 2016 14:24To: [email protected]: EDIT: 331637770768483725 Gas Heater Service
Item Gas Heater Service
HS Reference Gas Heater Service
Due Date 11-10-2016
Status Outstanding+
Comments/Notes 18/02/16 Plan for the warmer months 22/03/16 [email protected] e-mailed plan to have service in June 30/03/16 Chased via e-mail 06/04/16 Service booked for June 21st search e-mail for further details MC. 19/04/16 Advised them to clean 2 x heaters in woodshop 20/06/16 Confirmed on site tomorrow 08/07/16 Quote received for heaters to replace polishing shop 19/07/16 Await service reports 21/07/16 Requested mid August installation date 30th Aug 06/09/16 Watson to install electrics. Also await service report for heaters. 22/09/16 They are in next Thursday so will check service reports 07/10/16 We just now need the reports
Attachment Gas Quote.pdf
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 331637770768483725
29
Martin Carr
From: Press Shop Heating [[email protected]]Sent: 05 October 2016 16:27To: [email protected]: EDIT: 328418129377734786 Press Shop Heating
Item Press Shop Heating
HS Reference Press Shop Heating
Due Date 07-10-2016
Status Outstanding+
Comments/Notes 12/01/16 Look at replace Electric heating. 18/01/16 The plumbers will need to look at this when they are in doing the silversmiths heater 25/01/16 This would need to be floor standing 11/02/16 Jason to seek quote 15/02/16 Updated requested - From: Jason Bee [mailto:[email protected]] Sent: 15 February 2016 08:33 To: 'Martin Carr' Subject: RE: EDIT: Outstanding+ HS Job 15-02-2016 Had a quick chat with Chaz, I think I will get a price for the 90uf Model that’s next to the toilet block opposite tubing department, maybe the next model down too.. 22/02/16 Quote attached 18/03/16 By the time this is delivered and then fitted it will not be needed until next winter. Given that heaters are cheaper to buy in summer, job post dated 31/05/16 Jason to investigate 21/06/16 Quote request also to [email protected] 20/07/16 Quote on file 21/07/16 Looking at ones that are floor mounted. 15/08/16 Quote received 16/08/16 Installation date requested 17/08/16 They will come to do final survey 23rd Sep, Install 29th. Need Maint to sort control before 07/09/16 New Stat will be here today 08/09/16 Just waiting for heater now. 05/10/16 Will be finished off tomorrow, was awaiting flu guard
Attachment WJD_11037.pdf
Job Type HS Job
31
Martin Carr
From: Replacement Extractor [[email protected]]Sent: 05 October 2016 13:28To: [email protected]: EDIT: 305000253232595418 Replacement Extractor MH 1510151729
Item Replacement Extractor
HS Reference Replacement Extractor MH 1510151729
Due Date 11-10-2016
Status Outstanding+
Comments/Notes Marc H to investigate replacement for polishing extractor.. Estimated project costs £55000. This project is a priority for business continuity. 16/04/15 Marc and AGH are looking and 2nd hand options 9-5-15 Carter environment have been on-site to survey and advise on alternative new machine 15-6-15 Carter environment advise that current usage requires 25000cfm (current machine is 28000cfm) if usage is projected to stay level or NOT increase then this is a cheaper option - Waiting for quote 17-5-15 - Quote £51000 ex works, £540 Delivery, £3210 intallation (2 day), £475 commissioning Total £55225 - sited (Carrs to connect services) 12-14 weeks leadtime 22/07/15 One for GR 10/09/15 Attached image of current inside damage. 14-9-2015 AAF to visit to provide alternate quote complete - Due to visit 17-9-2015 15-10-2055 Alternative quote from AAF attached (NOTE quote is dependant on euro exchange rate!) £52775 installed identical to current machine 07/01/16 Mark/Dave to get DSS to look at patch work.Dave from dss is coming in on friday 15/01/16 afternoon 12.15pm .
32
13/01/16 Have ordered spare chain and parts 1 week delivery we need to plan work on chain for the next few weeks. 15/01/16 Dave from dss is going to make some bigger outside cover plates so we can make a bigger opening on both sides of fan cover, so we can carry out repair to fan see photo in file then he will make some plates for fan damage will need to speak with martin carr on tuesday 19/01/16 Contact [email protected] 07816 144 433 21/01/16 dss quote inspection covers £135.00 made out requisition order mark parkin 21/01/16 That price is fine, just progress with job.Have placed order ok. 29/01/16 Can we have a meeting with production regarding the work we require to do on the extractor ie:Fit larger covers/repair damage to ducting inside fan/blades/chains links/cleaning extractor out,we have a cherry picker on site from 29/01/16 for one weeks hire.mark parkin 25/01/16 Will be installing larger covers this Friday/Saturday if need be. mark parkin.59977. 29/01/16 Due to weather conditions we will have to plan this job in again regards mark parkin. 02/03/16 Need to plan in to fit covers and chain repairs with production again. 18/03/16 Charles, can you advise on when we can have this from production? 21/03/16 The plan is to do this on a Friday after 10am. Also to do the clean at the same time, weather was the issue last time. 22/03/16 In view of current situation this time frame might need reviewing. 24/03/16 Emergency report issued by Allianz, CW agreed we need to address this quickly, will arrange for cleaning. 1/04/16 TS and team started to clean main duct and branch ducts in polishing shops. 01/04/16 Search e-mail for CEE contact and quote 18/04/16 Charles, when the patch work be done? 20/04/16 CW - Which Thursday are we going to do this? 21/04/16 This will be cleaned out next Thursday 28/04/16 More work next Thursday 04/05/16 Are we still going ahead with the scheduled repairs that were cancelled due to bad weather on 29/01/16. 04/05/16 Yes details to be sorted when CW returns from holiday next week 10/05/16 DW is contacting DSS to arrange for the plates to be made. We will then fit one afternoon 17/05/16 TH contact will be here on Monday to
33
quote for the whole job. 23/05/16 He has been to look at the job and will install the hatches after the spring bank week 08/06/16 Parts will be welded on Friday 13/06/16 Part of the job was done on Friday, more will be done this Friday 20/06/16 Work done Friday final part of work this Friday, weather permitting. 27/06/16 Further work will be done on Friday 01/07/16 More work is being done today, this should be the end for the moment 08/07/16 This has been done.. replacement maybe later 21/07/16 Just the matter of painting left to do. Richard to supply contact he has 10/08/16 Update requested from CW 15/08/16 See if banks have any suggestions 19/08/16 Await price from Banks for paint job. 09/09/16 Chased quote 13/09/16 Will be painted from next Monday 22/09/16 This is being painted at the moment. 05/10/16 There is now the pipe to paint, this will be started tomorrow
Attachment 20150907_124030.jpg
Attachment QAPS24442 Carrs RCN.pdf
Job Type Maintenence
Notifier [email protected]
Note you can also reply to this e-mail. 305000253232595418
34
Martin Carr
From: Fixed Wire Testing [[email protected]]Sent: 27 September 2016 13:45To: [email protected]: EDIT: 304999472232807237 Fixed Wire Testing 160415AS MC
Item Fixed Wire Testing
HS Reference Fixed Wire Testing 160415AS MC
Due Date 18-10-2016
Status Outstanding+
Comments/Notes Martin C to test all fixed wiring in the factory. Estimated cost £7500 for testing, repairs cost as identified. This project is a legal requirement. 16/04/15 Quote requested for alternative company. Note not due until 2016 30/04/15 Awaiting clarification of alternative quote 30/04/15 Alternative quote is approx £4000. Work could start next month. However, due to the budget and planning it will be Q3. 27/07/15 In budget discussion. 07/09/15 Will be looked at again in 2016 17/05/16 Await start date 31/05/16 Start date should be 6th June 02/06/16 Probably start 21st June 21/06/16 Job has started 19/07/16 Ongoing, few weeks should be done. 30/08/16 Estimate mid Sep for finish 22/09/16 Being done at the moment 27/09/16 Done, but maybe a few weeks for paperwork
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 304999472232807237
35
Martin Carr
From: Cross Cut [[email protected]]Sent: 26 September 2016 16:21To: [email protected]: EDIT: 348615293377173293 http://hs.carrs-silver.co.uk/ww021.pdf
Item Cross Cut
HS Reference http://hs.carrs-silver.co.uk/ww021.pdf
Due Date 26-09-2016
Status Completed+
Comments/Notes 02/09/16 Work required.. 26/09/16 DC brake fitted working ok 6secs
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 348615293377173293
36
Martin Carr
From: Cross Cut Large [[email protected]]Sent: 26 September 2016 16:20To: [email protected]: EDIT: 348615445377295374 http://hs.carrs-silver.co.uk/ww0024.pdf
Item Cross Cut Large
HS Reference http://hs.carrs-silver.co.uk/ww0024.pdf
Due Date 14-09-2016
Status Outstanding+
Comments/Notes 02/09/16 Work required.. 26/09/16 fitted dc brake working ok 6secs. return mech. still to be sorted
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 348615445377295374
37
Martin Carr
From: Fixed Wire Testing [[email protected]]Sent: 22 September 2016 16:06To: [email protected]: EDIT: 304999472232807237 Fixed Wire Testing 160415AS MC
Item Fixed Wire Testing
HS Reference Fixed Wire Testing 160415AS MC
Due Date 28-09-2016
Status Outstanding+
Comments/Notes Martin C to test all fixed wiring in the factory. Estimated cost £7500 for testing, repairs cost as identified. This project is a legal requirement. 16/04/15 Quote requested for alternative company. Note not due until 2016 30/04/15 Awaiting clarification of alternative quote 30/04/15 Alternative quote is approx £4000. Work could start next month. However, due to the budget and planning it will be Q3. 27/07/15 In budget discussion. 07/09/15 Will be looked at again in 2016 17/05/16 Await start date 31/05/16 Start date should be 6th June 02/06/16 Probably start 21st June 21/06/16 Job has started 19/07/16 Ongoing, few weeks should be done. 30/08/16 Estimate mid Sep for finish 22/09/16 Being done at the moment
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 304999472232807237
38
Martin Carr
From: Replacement Extractor [[email protected]]Sent: 22 September 2016 16:05To: [email protected]: EDIT: 305000253232595418 Replacement Extractor MH 1510151729
Item Replacement Extractor
HS Reference Replacement Extractor MH 1510151729
Due Date 30-09-2016
Status Outstanding+
Comments/Notes Marc H to investigate replacement for polishing extractor.. Estimated project costs £55000. This project is a priority for business continuity. 16/04/15 Marc and AGH are looking and 2nd hand options 9-5-15 Carter environment have been on-site to survey and advise on alternative new machine 15-6-15 Carter environment advise that current usage requires 25000cfm (current machine is 28000cfm) if usage is projected to stay level or NOT increase then this is a cheaper option - Waiting for quote 17-5-15 - Quote £51000 ex works, £540 Delivery, £3210 intallation (2 day), £475 commissioning Total £55225 - sited (Carrs to connect services) 12-14 weeks leadtime 22/07/15 One for GR 10/09/15 Attached image of current inside damage. 14-9-2015 AAF to visit to provide alternate quote complete - Due to visit 17-9-2015 15-10-2055 Alternative quote from AAF attached (NOTE quote is dependant on euro exchange rate!) £52775 installed identical to current machine 07/01/16 Mark/Dave to get DSS to look at patch work.Dave from dss is coming in on friday 15/01/16 afternoon 12.15pm .
39
13/01/16 Have ordered spare chain and parts 1 week delivery we need to plan work on chain for the next few weeks. 15/01/16 Dave from dss is going to make some bigger outside cover plates so we can make a bigger opening on both sides of fan cover, so we can carry out repair to fan see photo in file then he will make some plates for fan damage will need to speak with martin carr on tuesday 19/01/16 Contact [email protected] 07816 144 433 21/01/16 dss quote inspection covers £135.00 made out requisition order mark parkin 21/01/16 That price is fine, just progress with job.Have placed order ok. 29/01/16 Can we have a meeting with production regarding the work we require to do on the extractor ie:Fit larger covers/repair damage to ducting inside fan/blades/chains links/cleaning extractor out,we have a cherry picker on site from 29/01/16 for one weeks hire.mark parkin 25/01/16 Will be installing larger covers this Friday/Saturday if need be. mark parkin.59977. 29/01/16 Due to weather conditions we will have to plan this job in again regards mark parkin. 02/03/16 Need to plan in to fit covers and chain repairs with production again. 18/03/16 Charles, can you advise on when we can have this from production? 21/03/16 The plan is to do this on a Friday after 10am. Also to do the clean at the same time, weather was the issue last time. 22/03/16 In view of current situation this time frame might need reviewing. 24/03/16 Emergency report issued by Allianz, CW agreed we need to address this quickly, will arrange for cleaning. 1/04/16 TS and team started to clean main duct and branch ducts in polishing shops. 01/04/16 Search e-mail for CEE contact and quote 18/04/16 Charles, when the patch work be done? 20/04/16 CW - Which Thursday are we going to do this? 21/04/16 This will be cleaned out next Thursday 28/04/16 More work next Thursday 04/05/16 Are we still going ahead with the scheduled repairs that were cancelled due to bad weather on 29/01/16. 04/05/16 Yes details to be sorted when CW returns from holiday next week 10/05/16 DW is contacting DSS to arrange for the plates to be made. We will then fit one afternoon 17/05/16 TH contact will be here on Monday to
40
quote for the whole job. 23/05/16 He has been to look at the job and will install the hatches after the spring bank week 08/06/16 Parts will be welded on Friday 13/06/16 Part of the job was done on Friday, more will be done this Friday 20/06/16 Work done Friday final part of work this Friday, weather permitting. 27/06/16 Further work will be done on Friday 01/07/16 More work is being done today, this should be the end for the moment 08/07/16 This has been done.. replacement maybe later 21/07/16 Just the matter of painting left to do. Richard to supply contact he has 10/08/16 Update requested from CW 15/08/16 See if banks have any suggestions 19/08/16 Await price from Banks for paint job. 09/09/16 Chased quote 13/09/16 Will be painted from next Monday 22/09/16 This is being painted at the moment.
Attachment 20150907_124030.jpg
Attachment QAPS24442 Carrs RCN.pdf
Job Type Maintenence
Notifier [email protected]
Note you can also reply to this e-mail. 305000253232595418
41
Martin Carr
From: degreasing tank [[email protected]]Sent: 22 September 2016 16:04To: [email protected]: EDIT: 330473926377745521 plating shop
Item degreasing tank
HS Reference plating shop
Due Date 05-10-2016
Status Outstanding+
Comments/Notes 05/02/16 .Breakdown on heaters sage 2 have placed order with jason urgent, Guyson int p3ht0021 1200w 4off,p3ht0022 2 off heater details. Have repaired damaged copper plate made new one repaired burnt up wire again!!!!!!! will test again on 08/02/16 first thing..Has been ok today will leave this outstanding till we have delivery of heaters. 09/02/16 Heaters now in stock and in our stores mark parkin. 10/02/16 stage 3 no htg. 3 wires off elements. this is a recurring problem as reported earlier, is it the atmosphere? M Parkin contacting Guyson for advice. 22/02/16 Spoken to guyson to get service engineer out we would have to book him in and pay for service engineer do we want to do this ? 22/02/16 Please advise on costs MC. 22/02/16 Martin the cost of a engineer is £825.00 a day .contact details mick banks tel: 01756 799911, machine details serial 59266-3-99 type uor1500/3r+r/t we will have to book a visit, do you want me to book visit ? regards mark 25/02/16 This machine tripped out again this morning waiting to see if wire or heaters gone again !! 7/03/16 Machine tripped out first thing in morning, reset mcb for stage two heater, machine powered up and stayed on, checked all other heaters and found auxillary bank on stage three not working and one main heater on stage three u/s (which was already known about). Left machine coming up to temp. on all stages. will need further investigation and repair. We really need a solution to this ever recurring problem. 24/03/16 Testing required to see if the aquious can
42
do more cleaning 30/03/16 STAGE 2 + 3 CIRCULATING PUMPS NOT WORKING, SIEZED UP WITH NOT BEING USED FOR PROLONGED PERIOD, SUSPECT WILL NEED AT LEAST A REWIND. WILL SEND TO ALL PUMPS FOR QUOTE. 06/0/16 CW okayed pump repair and pump replacement, ordered new pump on order no.60336. 11/04/16 pumps arrived will fit when can 17/04/16 Pumps fitted and tested. traced fault on air valves and repaired faulty valve. 18/04/16 Charles, when can testing of cutlery cleaning start? 19/04/16 Update requested from Charles 25/04/16 Charles, when is this testing happening? 03/05/16 We are awaiting oily cutlery blanks then will test, but suspect we will need different chemicals 10/05/16 Tests happening today, but looks like heaters and Ultrasonic require work 16/05/16 3 out of 4 htrs. on stage 1 u/s. stage 2 ok, 1 out of 3 htrs. u/s on stage 4. 6 out of 8 ultrasonic units not functioning, so called spare units are those that were u/s from trich cleaner, maybe could salvage 1 unit. Will try to get estimate for repairs. 24/05/16 CW has prices for spares, have ordered replacement immersion htrs. Will fit these which should improve cleaning as Ist stage will be able to reach a higher temp. Will check over U/Sonic pulse drivers later. 08/06/16 Sorted and returned back to production. Note that now we do not plate, just clean. 20/06/16 No 2 Ultrasonics not working, fault with driver unit.Do we get Guyson engineer or send unit to them? left with CW. 21/06/16 CW has arranged for engineer's visit next week. 29/06/16 Report in search 01/07/16 There is a new solvent which we will trail in the next few weeks. If all goes well the idea is to try and put this in a smaller cleaner 19/07/16 New solvents will be tested after Daz holidays. The plan would then be to have trade in the two existing cleaners and replace with a smaller one 05/08/16 CW to arrange a trip to supplier next week 15/08/16 Meeting planned for 24th Aug 25/08/16 Trials ongoing, visit but further samples to be sent down. 01/09/16 Further samples to be sent, but will be a few weeks 22/09/16 More samples sent - few weeks before
43
feedback
Job Type Maintenence
Notifier [email protected]
Note you can also reply to this e-mail. 330473926377745521
44
Martin Carr
From: Gas Heater Service [[email protected]]Sent: 22 September 2016 16:03To: [email protected]: EDIT: 331637770768483725 Gas Heater Service
Item Gas Heater Service
HS Reference Gas Heater Service
Due Date 28-09-2016
Status Outstanding+
Comments/Notes 18/02/16 Plan for the warmer months 22/03/16 [email protected] e-mailed plan to have service in June 30/03/16 Chased via e-mail 06/04/16 Service booked for June 21st search e-mail for further details MC. 19/04/16 Advised them to clean 2 x heaters in woodshop 20/06/16 Confirmed on site tomorrow 08/07/16 Quote received for heaters to replace polishing shop 19/07/16 Await service reports 21/07/16 Requested mid August installation date 30th Aug 06/09/16 Watson to install electrics. Also await service report for heaters. 22/09/16 They are in next Thursday so will check service reports
Attachment Gas Quote.pdf
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 331637770768483725
45
Martin Carr
From: Wadkin Router [[email protected]]Sent: 21 September 2016 16:08To: [email protected]: EDIT: 348974540377801939 http://hs.carrs-silver.co.uk/ww005.pdf
Item Wadkin Router
HS Reference http://hs.carrs-silver.co.uk/ww005.pdf
Due Date 27-09-2016
Status Outstanding+
Comments/Notes 06/09/16 21/09/16 Top casting cracked, having it brazed up.
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 348974540377801939
46
Martin Carr
From: Edge Sander [[email protected]]Sent: 21 September 2016 15:54To: [email protected]: EDIT: 348973651377192998 http://hs.carrs-silver.co.uk/ww014.pdf
Item Edge Sander
HS Reference http://hs.carrs-silver.co.uk/ww014.pdf
Due Date 03-10-2016
Status Completed+
Comments/Notes 06/09/16 Work required on tension cover guard. 21/09/16 Made guard extension and fitted. This job finished however hinge broken on main guard which we will be repairing.
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 348973651377192998
47
Martin Carr
From: Profile Sander [[email protected]]Sent: 21 September 2016 15:49To: [email protected]: EDIT: 348973345377839423 http://hs.carrs-silver.co.uk/ww011.pdf
Item Profile Sander
HS Reference http://hs.carrs-silver.co.uk/ww011.pdf
Due Date 21-09-2016
Status Completed+
Comments/Notes 06/09/16 Work required to guard. 21/09/16 Adapted guard
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 348973345377839423
48
Martin Carr
From: mop spindle [[email protected]]Sent: 21 September 2016 08:10To: [email protected]: EDIT: 349675320377184347 auto polisher
Item mop spindle
HS Reference auto polisher
Due Date 28-09-2016
Status Outstanding+
Comments/Notes 14/09/16 Spindle requires modifying to accept smaller brg. carrier. JKP doing work 21/09/16 At operators request have asked JKP to modify both spindle ends.
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 349675320377184347
49
Martin Carr
From: Mitre Saw [[email protected]]Sent: 20 September 2016 14:53To: [email protected]: EDIT: 348613106377126056 http://hs.carrs-silver.co.uk/ww004.pdf
Item Mitre Saw
HS Reference http://hs.carrs-silver.co.uk/ww004.pdf
Due Date 20-09-2016
Status Completed+
Comments/Notes 02/09/16 Guarding and stop button issues..
Job Type HS Job
Notifier [email protected]
Note you can also reply to this e-mail. 348613106377126056