Marti Technik AGConveyor belt system Koralm tunnel (A)

Services provided by Marti Technik AGConstruction, manufacture, transportation, assembly

and commissioning of the entire conveyor belt system

including electrical equipment and control system.

Plant descriptionThe conveyor belt system consists of

2 vertical conveyors (Elevator 130, Elevator 230)

2 drift conveyor belts (Belt 150 and Belt 250)

Technical dataElevator 130

Belt width 1 600 mm

Extraction drift 60 m

Mass flow 1 000 t/h

Capacity 315 kW

Elevator 230

Belt width 1 600 mm

Extraction drift 60 m

Mass flow 1 000 t/h

Capacity 315 kW

Band 150

Belt width 1 000 mm

Extraction drift 77 m

Mass flow 1 000 t/h

Capacity 75 kW

Band 250

Belt width 1 000 mm

Extraction drift 80 m

Mass flow 1 000 t/h

Capacity 75 kW

Koralm tunnel (A)Conveyor belt system

Client ÖBB Infrastruktur AG

Main contractor ARGE Koralmtunnel KAT2

(Strabag & Jäger Bau GmbH)

Sub-contractor Marti Technik AG

Order value CHF 2.1 mn

Drawn up 2011 / 2012