Upload
evelyn-lang
View
213
Download
1
Embed Size (px)
Citation preview
MARCHMARCH
1
Risk Management
Why carry out Risk Assessment?
Is the project too risky? Threat intensity?
Improve decision making Clarification of terms
Targets Expected values Commitments
Documentation
RISK
RISK
COST
COST
MARCHMARCH
2
Risk Management
The Risk Management Process - RMP
OWNERSHIP risks
responsibilities and contractors
DEFINE the project
DEFINE the risk
management process
IDENTIFY risks and response
ORGANISE prioritise risks and responses
ESTIMATE size the risks
EVALUATE
PLAN plans and strategies
MANAGE
INITIATION
MARCHMARCH
3
Risk Management
Simple estimating of risk – more detail
0.1
0.3
0.2
4 6 8 10 12 14 16
A=0.15
A=0.35
A=0.2
A = area
Pro
bab
ilit
y d
ensi
ty
Delay
A=0.05 A=0.05A=0.1A=0.1
2
MARCHMARCH
4
Risk Management
Cumulative probability graph
0.2
0.4
0.6
10 12 14 16
Cu
mu
lati
ve P
rob
abil
ity
Delay
0.8
1.0
18 20 22 24
A and B, with B conditional on A
0.12
0.12 + 0.33
0.12 + 0.33 + 0.25
0.12 + 0.33 + 0.25 + 0.24
MARCHMARCH
5
Risk Management
Types of plans Initial plan Reference plan Base plan Contingency plan Horizon plan Action plan
MARCHMARCH
6
Risk Management
Cost model
With uncertainty Use of a range 3 - point estimate
Task CostMin Likely Max Distribution
A 2 4 5 3.7
B 1 3 6 3.3
C 2 3 4 3.0
D 5 7 9 7.0
E 3 6 7 5.3
F 1 6 11 6.0
G 3 4 5 4.0
H 8 10 12 10.0Total 25 43 59 41.3
MARCHMARCH
7
Risk Management
Monte Carlo risk distribution
1.0
0.8
0.6
0.4
0.2
0.0
TOTAL COST
RIS
K O
F E
XC
EE
DIN
G T
AR
GE
T C
OS
T
VALUE EXCEEDED BY 20% OF SAMPLE
TARGET WITH 20% RISK OF BEING EXCEEDED
Because of the values put into the model there will be zero risk of exceeding total cost ‘x’.
All sample total costs will fall below value ‘x’. Hence, the risk is 1.0.
Easy to see what target cost will have a 20% risk of being exceeded.
Trying to set a target near the middle is sensitive to larger changes in the risk.
X
MARCHMARCH
8
Risk Management
PROJECT
USING RISK ASSESSMENT
TASK
TRADITIONAL APPROACH
COST = £5000
DURATION= 3 WEEKS
3 POINT
ESTIMATE
LIKELIHOOD AND IMPACT OF
+VE AND –VE EVENTS
MODEL COSTS
MARCHMARCH
9
Risk Management
Human relations Benefits
Can make all aware of the risks involved, relieving the pressure on individuals
If you wait for more data it may be too late to act Early assessment enhances bid and budget control The plan can run during risk assessment Can focus resources in high risk areas Risk assessment can bolster confidence in the plan One needs confidence that any costs will not exceed the bid price May be client driven May be stakeholder driven