  • 66 HUMAN RESOURCE MANAGEMENT JOURNAL VOL 8 NO 2

    In recent years performance management has come to the fore as organisations seek

    constantly to optimise their human resources in the face of growing competitive

    pressures. The increased interest in performance management has been mirrored by

    the popularity of performance-related pay (PRP) schemes which reward individual

    employees on the basis of their job performance, de ned as `a method of payment where

    an individual employee receives increases in pay based wholly or partly on the regular and

    systematic assessment of job performance (ACAS, 1996: 8). Indeed, definitions of

    performance management (eg Clark, 1995; Storey and Sisson, 1993) often include PRP as

    an intrinsic part of this approach.

    However, the PRP literature indicates that unsuccessful implementation of PRP is often

    associated with ineffective performance management processes (see, for example, Cannell

    and Wood, 1992; Marsden and Richardson, 1992). But, as Dowling and Richardson (1997)

    note, there have been few attempts to explain empirically any observed success or failure of

    PRP, including the extent to which ineffective implementation may explain PRP failure.

    This article seeks to shed light on this debate. It has two aims: the rst is to identify the

    performance management processes which are fundamental to the successful

    implementation of PRP; the second, to establish how effectively these processes were

    conducted in three organisations which were the subject of this research.

    RESEARCH DESIGN

    The focus of the overall study was to arrive at an explanatory theory of the effectiveness of

    PRP schemes. The research design featured three nancial services organisations: Finbank, a

    high street bank, Finsoc, a major building society, and Premierco, a leading insurance

    company. It was anticipated that data collection in three organisations would result in a

    more valid explanatory theory of PRP success than if only one organisation had been used.

    Financial services was chosen because it is in this sector that PRP has been embraced

    with particular enthusiasm, due to the perceived need to generate more commercially

    aware behaviour among employees in an increasingly competitive product market a need

    with which PRP was assumed to be consistent (Snape et al, 1992).

    The focus of the study was on managers at branch (or equivalent) level the recipients of

    PRP. In the three organisations, PRP operated in a similar way for managers at this level,

    and this was the reason for choosing this employee category. Each organisation operated its

    scheme under the umbrella of a performance management system. In all three the corner-

    stone of this system was the setting of objectives by the implementing manager for the

    recipient manager; these were derived from the organisations objectives. These individual

    objectives were assessed at least annually and triggered a performance-based award.

    Assessment in each organisation was on a ve-point scale with any performance award

    being determined by individual performance. Each of the organisations had been running

    its PRP scheme since the late 1980s.

    Managing performance-related pay based on evidence from the nancial services sector

    Philip Lewis, Cheltenham and Gloucester College of Higher Education

  • The main method of data collection was through semi-structured interviews lasting one

    hour or more with 63 recipient managers, together with 23 managers who were either the

    implementers of the scheme (usually area managers) or the designers of the performance

    management scheme (personnel specialists). The semi-structured interview was chosen

    because of its ability to probe beneath the surface of information that otherwise may be

    accepted at face value or, alternatively, not disclosed. For example, in the Finbank pilot study

    the organisations concern to use PRP to reduce labour costs was not revealed in the rst

    instance in senior manager interviews. But it was apparent that this was the perception of

    branch managers; this was con rmed in subsequent senior management interviews. Both

    the general management and personnel management perspectives were thought to be

    important so that a full picture could be obtained.

    Data analysis was consistent with the grounded theory approach (Glaser and Strauss,

    1967). Initially the data were disaggregated into conceptual units which were labelled accord-

    ing to the main themes which arose. Initial de nition of relationships between these themes

    was conducted and then a nal de nition of categories and sub-categories was developed.

    The eldwork was conducted over a period of 18 months between 1993 and 1995. In

    addition to interviews with managers, the author also attended managerial meetings,

    studied organisational documentation and had two three-hour discussions with relevant

    trade union of cials.

    PERFORMANCE MANAGEMENT PROCESSES AND PRP

    Analysis of the data suggested there were several key activities in the implementation of

    PRP. What was clear was these had more to do with what have become known as

    performance management processes than they did with pay per se. This pointed the way to

    an analytical framework derived from the performance management literature.

    Performance management is a term used to describe an integrated set of techniques

    which have had an independent existence under their own names, eg performance

    appraisal. There is no clear agreed de nition of performance management. Storey and Sisson

    (1993) note that, at its broadest, the term can mean any activity which is designed to improve

    the performance of employees. At its narrowest, performance management is used to refer

    to individual PRP. Storey and Sisson (1993) note that performance management has three

    basic activities:

    1. setting clear objectives for individual employees which are derived from the

    organisations strategy and departmental strategies;

    2. formal monitoring and review of progress towards these objectives; and

    3. using the outcomes of the review process to reinforce desired employee behaviour

    through differential rewards and identifying training and development needs.

    Clark (1995) stresses one important additional facet of performance management activity:

    that of feeding back to the employee the results of the formal monitoring.

    It can be seen from the above definition that PRP is usually an intrinsic part of

    performance management. The IPM survey on performance management (Institute of

    Personnel Management, 1992) reported that two-thirds of the respondent organisations

    which operated PRP without other performance management policies thought that PRP had

    contributed to improved organisational performance. This contrasted with 94 per cent of the

    sample which operated PRP with other performance management policies, who thought

    PRP had contributed to improved organisational performance. This suggests the importance

    Philip Lewis, Cheltenham and Gloucester College of Higher Education

    67HUMAN RESOURCE MANAGEMENT JOURNAL VOL 8 NO 2

  • Managing performance-related pay based on evidence from the nancial services sector

    68 HUMAN RESOURCE MANAGEMENT JOURNAL VOL 8 NO 2

    of PRP being located within the context of performance management activities, ie activities

    which set objectives, measure performance and give feedback against objectives.

    The IPM survey claims several advantages for performance management, including:

    l more effective employees able to meet increased product market competition;

    l the pushing of key decisions down the organisational structure to line managers, together

    with a greater acceptance of accountability by such managers; and

    l reward structures which reward performance.

    Among the bene ts of performance management claimed by Clark (1995: 186) is that it

    `provides a means of inspecting the functioning of the process links which deliver

    performance against objectives . It is this last bene t of performance management which

    makes it particularly attractive as a tool to analyse the implementation of PRP. In the case

    study organisations PRP was concerned with delivering performance against objectives and

    examining the process links between the various aspects of the implementation of PRP

    offered a thorough way of analysing the data.

    Storey and Sisson (1993) and Clark (1995) represent performance management as a cycle of

    activities. Analysis of the PRP data in this study was conducted using a cycle derived from this

    work. Figure 1 illustrates the PRP process cycle, shown here as an interactive cycle as opposed

    to a series of discrete activities; that is, the processes are presented in a logical order and there

    is a relationship between each of the processes in the cycle in that each one affects the others.

    The interactive nature of the model, indicated by the arrows, requires explanation.

    Clearly, the performance objectives set in stage 1 of the cycle are those which it is intended to

    measure in stage 2. But the arrow pointing back to stage 1 indicates that the measurement

    process may involve a redefinition of the objectives. Underperformance may lead to a

    decrease in targets and overachievement an increase.

    The performance measurement process will provide feedback to recipient managers on

    their performance level in stage 3 of the cycle. The arrow returning to stage 2 indicates that a

    consequence of this process may be modi cation of the measures being used and of the way

    in which the feedback is given, eg too infrequently or too critically.

    Feedback on performance eventually leads to the performance rating derived being tran-

    slated into a pay award in stage 4. Here, the arrow points back to stage 1 because it is possible

    that recipient managers may appeal, either informally or formally, against the rating and the

    amount awarded. This may lead to a modi cation of the rating, award and future objectives.

    As Lawler (1995) asserts, communication is a key aspect of the cycle. Communication of

    relevant performance management information from implementing managers to PRP

    recipients is placed at the centre of the model and it is seen to be essential that this ows

    around the complete process cycle. This involves the setting objectives stage. For example,

    what are the origins of the objectives? What are the objectives of colleagues, of other

    divisions and regions? Performance measurement calls into question the extent to which

    information about other recipients is communicated. Communication is obviously at the

    heart of the feedback giving process. For example, how much justi cation is given for the

    assessments made? Translation of performance rating into award implies the need for

    communication of information about the expected level of the `pot size and the implications

    of this for the respective levels of rating. Knowledge of this allows the potential recipient to

    be clear about the award he or she can expect.

    Clearly, the PRP process cycle represents an idealised approach to the implementation of

    PRP. But it is used here principally as a `means of inspecting the functioning of the process

    links which deliver performance against objectives (Clark, 1995: 186) at Finbank, Finsoc and

    Premierco. The data are presented below in the order of each stage of the cycle.

  • Philip Lewis, Cheltenham and Gloucester College of Higher Education

    69HUMAN RESOURCE MANAGEMENT JOURNAL VOL 8 NO 2

    Effectiveness of PRP process cycle in the three case study organisations

    Stage 1: setting objectives Fundamental to performance management are measures of

    performance. Lawler (1990) argues that these should be credible and comprehensive;

    without these ingredients a successful scheme is impossible. Pre-determined objectives are

    one of the most popular forms of measuring performance (ACAS, 1996) and were used in

    each of the three case study organisations.

    Performance management ineffectiveness may not only be a product of inappropriate

    objectives but lack of management skill in their application (Lawler, 1990). In their study

    Cannell and Wood (1992) conclude that, while managers found the setting of objectives easy,

    the assessment of their impact and effectiveness was less so. These potential problems are

    re ected in the data from the case studies in this research, where the main weaknesses were

    the imposition, narrowness and number of objectives.

    At Finbank the way in which the objectives were set was the cause of unease. The of cial

    line was that objectives were negotiated by the branch manager with the area manager. Yet

    most branch managers insisted the reality was that they were imposed by the bank on area

    managers and by area managers on branch managers:

    There was the opportunity last year to have some say in this but the bank just went ahead and

    imposed what they wanted to impose anyway. Branch manager

    ... branch managers complained there was no such thing as negotiation, that they [objectives]

    were imposed. So the employee relations manager at the time said, `OK, lets make it clear

    they are imposed. Union national of cer

    In addition, the scope of performance objectives for Finbank managers was narrow. They

    seemed only to dwell on the achievement of nancial business targets. This encouraged

    managers to concentrate on the short term rather than build long-term developmental

    relationships with staff and customers.

    FIGURE 1 PRP process cycle

    COMMUNICATION

    Stage 1: setting objectives

    Stage 2: measuring performance

    Stage 3: giving performance feedback

    Source: developed from Clark (1995) and Storey and Sisson (1993)

    NB Bold arrows represent forward progression throughout the cycle. The lighter arrows indicate the possibilityof each stage being revisited as a consequence of what happens at that stage. See text for full explanation.

    Stage 4: translating performance into award

  • At Finsoc the performance objectives fell into two categories business/ nancial and

    personal development. The latter category covered speci c areas related to the development

    of the branch (eg branch appearance) as well as the development of the manager. The former

    category consisted of hard, quantitative measures; the latter soft and qualitative. There

    seemed little doubt from interview evidence that the business/ nancial objectives were

    imposed and the personal development objectives were negotiated. According to one area

    manager, this was inevitable:

    In reality, there is little opportunity for managers to in uence me in the targets I set for them.

    In the same way I cant really in uence my boss. The society hands down the goals and we

    have to work to them. Area manager

    All Finsoc area managers interviewed pointed out that at least they were likely to give

    branch managers the opportunity to disagree with their objectives. But branch managers all

    echoed the point that, although there was the opportunity to disagree, there was little point

    in doing so.

    There was also evidence at Finsoc that managers thought there were too many objectives:

    There are too many key performance areas about 20. This is far too many because managers

    lose sight of the ones they really should be aiming for... Area manager

    This may be the reason why, as many branch managers confessed, they did not refer to

    the performance agreement frequently, seeing it as little more than bureaucracy.

    Managers at Premierco were less critical of the objective setting process. The hub of the

    PRP system was the performance contract. Future objectives for managers were derived

    from the companys strategic objectives and the previous annual appraisal round. These

    were written into a performance contract giving the manager explicit standards which

    re ected the need for improved performance. Premierco managers had a high achievement

    orientation: set them a target and they would strive to achieve it.

    Overall, there appeared to be more evidence of ineffective than effective implementation

    of stage 1 of the PRP process cycle. This had the effect of disenfranchising the recipient

    managers, of creating the impression that the PRP process cycle was something that was

    `done to them rather than something in which they played an active part.

    Stage 2: measuring performance A consistent theme in the PRP literature is that employees

    agree in principle with the concept but disagree with the way in which schemes are operated

    (see, for example, Kessler, 1994). This calls into question the processes in the performance

    management cycle. Two main issues dominate the empirical literature (eg Procter et al, 1993;

    Marsden and Richardson, 1992): the extent to which employees feel favouritism is being

    practised and the tendency for ratings to cluster at the mid-point in the distribution. Such

    clustering has the effect of not discriminating between individuals, which they feel is unfair.

    Finbank managers expressed concern about the subjectivity of the measurement process.

    Some managers were worried about the lack of congruence between their views on the

    variables affecting achievement and those of the rating manager. The general view seemed

    to be: i`ts okay as long as he thinks in the same way as you. A fear of a small group of

    corporate lending managers was that their implementing manager may not understand all

    the complexities of the job, thereby exacerbating the worst effects of rating subjectivity.

    Favouritism was an issue with some Finbank managers. This had four strands. The rst

    was the straightforward `if you dont get on with your manager its not so good for your

    PRP. The second strand was that `managers have their pet issues, and the third related to

    the extent to which the manager was visible in the performance of the job. But the fourth

    Managing performance-related pay based on evidence from the nancial services sector

    70 HUMAN RESOURCE MANAGEMENT JOURNAL VOL 8 NO 2

  • Philip Lewis, Cheltenham and Gloucester College of Higher Education

    71HUMAN RESOURCE MANAGEMENT JOURNAL VOL 8 NO 2

    strand of favouritism was the most insidious the `old boy network. There were distinct soc-

    ial groupings in the bank, which meant promotions were often seen to be based on this rather

    than on performance. Many interviewees thought there was still too much of this in the bank:

    After all, a lot of managers have put in a lot of service together and grown up together in the

    bank. This meant there tended to be great insularity. Managers are reluctant to lose people

    theyve groomed. Business banking manager

    Perceived favouritism manifested itself in a different way at Finsoc. Branch managers felt

    staff in head of ce received systematically higher ratings than retail staff. This was part of a

    wider issue of perceived unfairness in that retail staff thought head of ce staff at Finsoc had

    an `easy life in comparison with them.

    I... spent a year in the head of ce and I couldnt believe the lack of pressure those people there

    were experiencing. I think a lot of them ought to have a spell in the branches and see what life

    is really like. Branch manager

    Managers choosing the `safe rating was a significant problem at Finsoc. This was

    recognised by branch and area managers and the retail HR manager; the latter thought this

    may have been due to the availability of so many options (nine) for the rating manager.

    In 1993-4, 84 per cent of Finsoc staff received ratings which used just three (mid-point) of

    the nine rating options. The most signi cant consequence of this was that genuine good or

    poor performance was not recognised or rewarded:

    One of the problems with the last award was the difference between a 3 and a 3.5 rating. It

    translated to 0.1 per cent of the increase last time which is ridiculous. People will rightly ask,

    why did I bother? The difference in effort required surely warrants more than that!

    Branch manager

    The low level of funds in the PRP `pot in recent years may explain the lack of different-

    iation. However, some argued that this was an example of managers t`aking the easy way

    out and not being prepared to be accountable for their actions.

    For Premierco managers the measures were precise and demanding. Managers were

    measured on keeping within budget, meeting service quality standards, meeting nancial

    controls, relationships with other departments and relationships with staff.

    The implementing manager was not the sole arbiter of performance. Feedback was

    obtained from all parties who were relevant to job performance, including, importantly,

    immediate colleague managers and other managers able to contribute. It also involved the

    completion of a questionnaire by the manager s staff on her performance as a people

    manager. The consequence of using such a wide range was that recipient managers saw the

    feedback process as far more complete and the eventual PRP award much more accurate.

    PRP at Premierco depended upon improved performance. Managers were continually set

    fresh challenges in one form or another. This may not have been promotion but perhaps a

    new project or extra functional responsibility, thus ensuring intrinsic motivation. Few

    managers interviewed had been doing their jobs for more than two years.

    Another facet of the performance measurement stage of the PRP process cycle which was

    effective at Premierco was the meeting of implementing managers on a quarterly basis to

    review the ratings given to recipient managers. This was pursued to achieve greater

    conformity across the division and had the effect of ensuring that implementing managers

    justi ed their decisions to peers.

    Stage 3: giving performance feedback Feedback on performance is seen as part of the wider

    issue of communication in the prescriptive performance management literature (see, for

    example, McAdams, 1988; Hoevemeyer, 1989) and deemed to be a process of key signi cance.

  • There was no impression that Finbank managers were receiving qualitative feedback on

    their job performance. This could have been provided by the area manager or other senior

    managers. Indeed, there was no evidence that managers were encouraged to learn from the

    experiences of others. Advancement was something which was seen in terms of salary or

    promotion. But for many managers salary had effectively been capped and promotion

    opportunities had been reduced by initiatives which had seen layers of management

    removed.

    There was also evidence at Finsoc that the performance management process was not

    conducted thoroughly. One area manager readily admitted that he only did three reviews a

    year rather than the prescribed four. It was not dif cult to have some sympathy with his

    reasons:

    There is a far too big a span of control on my part and the managers managing me. If you take

    my manager as an example. He has 23 direct reports and he has to do four appraisals a year

    thats 23 times four times 20 key performance indicators!

    One of the key performance monitoring aspects was the clear communication to recipient

    managers of what precisely it was they needed to do to turn this year s rating into a higher

    rating in the following year. In general, Finsoc managers could not do this.

    The situation at Premierco was quite different. There were often weekly, monthly or

    quarterly progress meetings and reviews. There was also the annual appraisal at which all

    employees completed a self-appraisal. This was shared with the reviewing manager who

    had completed an appraisal of the individual. The object was to reach a consensus; the

    output of the process was the setting of future objectives and planning training and

    development needs. Many managers talked of the major bene t of the system being `no

    surprises at the end of the year when the nal performance rating was announced.

    It seemed performance management was taken very seriously by managers at Premierco,

    where senior managers were convinced of its bene ts. The performance feedback process

    was the best example of the `new style managerialism which was evident at Premierco and

    was summarised by an enthusiastic operations manager:

    I dont know anything at all about the technical side of the jobs my people do. I think its my

    job to manage them. I do that through talking to them about what they do and making sure

    everything is right for them to do their jobs. If you treat them correctly youll get that back 20

    times over from them. They will want to do it for you.

    Stage 4: translating performance into reward In none of the organisations did managers

    know what the nal PRP award was going to be until shortly before it was actually paid. In

    addition, they did not rate it as attractive when it was nally paid.

    A typical comment was from a Finbank business banking manager:What would be nice is if you could say what your level of remuneration was going to be once

    you had achieved a certain level of performance. But the way that the system is now, you

    cant make that connection.

    The situation was similar at Finsoc. For all managers this operated at two levels: they did

    not know what they would get and they were not sure what rating to give their staff. The

    amounts in recent years had been so small that managers generally were keen to push

    ratings as high as possible. The retail HR manager acknowledged this was a problem, but

    public declaration of the pot size, and therefore the payments associated with different

    ratings, would have been revealing managements negotiating hand to the trade union.

    The lack of money available to drive the performance management system at Finsoc

    exacerbated the major focus of managers dissatisfaction the lack of differentiation in the

    Managing performance-related pay based on evidence from the nancial services sector

    72 HUMAN RESOURCE MANAGEMENT JOURNAL VOL 8 NO 2

  • amount of award between the different levels of performance rating. There was a negligible

    difference between the cash amounts generated by different ratings.

    At Premierco, too, managers did not know what the award for a particular rating would

    be. This situation was brought about, partly, by the system which operated whereby awards

    were linked not only to performance but position on pay scale. Therefore a manager who

    was high on the scale received less PRP award for the same rating. It was also due to the fact

    the pay award was not declared until the latter part of the review year.

    Secondly, in recent years the size of awards had been small. This was due to the limited

    amount of money available for increases. There was some interview evidence which

    suggested this has led to some managers saying i`f there is so little to give out, then why

    bother? Cascio (1989) and Lawler (1990) suggest that anything less than 10 per cent of salary

    is too little to be of consequence to employees. During the period of the eldwork, in all

    three organisations the maximum amount payable even to the outstanding performer was

    less than this amount.

    Communication

    Part of the PRP process entails communicating information to participants. Although not a

    major focus of the interview data, several points arose. One was the failure to communicate

    information about the awards which had been given, and a Finbank business manager

    explained this very clearly:

    I... think those who achieve 2s and 1s [the top two ratings] ought to be publicised. This is so

    others could go to them and say: `What is it you did to make you a 1? I have asked this

    question of my manager, and frankly he doesnt know the answer. It is essential that managers

    are open and can say what it is that made the difference between the outstanding performer

    achieving all his targets and doing that something extra... This would enable the person to

    emulate the outstanding achiever. The more you open up the system to scrutiny the more

    accountable you make managers, and they should be accountable.

    A good example of the mystique created by this lack of openness was related by a

    manager who did receive a 1 rating in 1994. When questioned about what he had to do to

    repeat the rating in the next year he replied:

    I wouldnt get the same rating next year... nobody gets a 1 in two successive years. I dont

    know why they just dont.

    There was no information conveyed to recipient managers about the general level of PRP

    awards at any level, either in the team, division, region or bank. As a consequence suspicion

    was evident.

    There was little evidence at Finsoc that there was any more communication about PRP

    than in Finbank. But there were two noteworthy perspectives which derive from the

    communication component of the PRP process cycle at Finsoc. First, the communication of

    society strategy to staff gave branch managers an impression of the broad frame of reference

    informing the performance feedback of the area manager. Secondly, a less positive point

    concerned the failure to communicate information regarding the general performance of

    other branch managers in the team and beyond in the wider organisation. This failed to

    provide managers with any benchmark of their own performance, a benchmark from which

    they may have derived self-esteem, solace or just satis ed curiosity.

    At Premierco the low level of awards which threatened PRPs productivity goals was a

    problem of which the company was very aware. Therefore much time was spent in

    managing the expectations of employees through employee communication. The economic

    position in which the company was placed was explained to all employees with the result

    Philip Lewis, Cheltenham and Gloucester College of Higher Education

    73HUMAN RESOURCE MANAGEMENT JOURNAL VOL 8 NO 2

  • that those who had an increase in 1993 were pleasantly surprised. Like the other two

    organisations, the distribution of ratings at Premierco was not communicated to recipients.

    DISCUSSION

    The evidence outlined above indicates that the PRP process cycle was implemented

    ineffectively in Finbank and Finsoc, and only effectively in Premierco. But this raises the

    question: what do the data presented in this study add to existing insights on PRP theory

    and practice? This final section argues the case for the value of the process cycle as an

    analytical framework, questions the concern of writers with motivation theory, con rms the

    pre-eminence of the line manager in the management of PRP and reasons that the inclusion

    of pay in the performance management process may be unnecessary.

    Value of PRP process cycle

    Often the literature is clear in drawing the conclusion that PRP is unsuccessful, usually as

    measured by surveys which show employee discontent (eg Marsden and Richardson, 1992),

    but less clear about the reasons for this discontent. In adopting a processual analysis, this

    study has attempted to gain a clearer understanding of these reasons. In this respect the PRP

    process cycle has been helpful because of its ability to examine the functioning of the process

    links which deliver performance against objectives. As Guest (1997) asserts, with regard to

    recent attempts in the literature to establish the effect of wider HRM practices on

    organisational performance (see Dyer and Reeves, 1995), without making explicit the

    possible linkages between cause and effect the understanding of the reasons for success or

    failure will not be understood. Guest (1997: 267) explains: `without some linkages... we have

    no theory. The PRP process cycle constitutes a theory; if the four stages are conducted

    effectively and information ows around the cycle, then PRP is more likely to be accepted by

    individuals and the objectives of the organisation in its introduction are more likely to be

    achieved. It is a highly deterministic theory and one, moreover, that takes no account of

    contingency theory, rightly a traditional concern of the pay literature (eg Lupton and Gowler,

    1969). But it makes some advance in our thinking of why PRP may succeed or fail.

    This raises another question: what is meant by success or failure of PRP? This study

    follows the lead of Lawler (1984) in using the criterion of employee acceptance to determine

    the level of its success. Thus, the possible criteria of organisational objectives set for PRP

    in all three organisations these were unclear and impact on overall organisational

    performance because of the dif culty of isolating one HR component (Kessler and Purcell,

    1995; Kinnie and Lowe, 1990) were rejected. In essence, the argument here is that if

    employees are generally in agreement with both the principle and practice of PRP, then they

    will be motivated to better job performance and bene cial organisational outcomes will

    follow. Conversely, if they are not in agreement with either the principle or the practice of

    PRP, then they will not be motivated to perform more effectively in their jobs and such

    organisational outcomes will not follow. Rather than improved job performance, the emp-

    loyee will feel at best apathetic, leading to PRP being largely ignored or alienated from both

    the PRP process and those responsible for its implementation (Gabris and Mitchell, 1988).

    Over three-quarters of the recipient managers interviewed at Finbank were extremely

    unhappy with both the principle and practice of PRP, so much so that the issue was the

    subject of a strike ballot soon after its introduction. Finsoc managers were less strident in

    their rejection; however, although generally accepting the principle of PRP, over two-thirds

    were unhappy with the way in which PRP was implemented. But at Premierco managers

    Managing performance-related pay based on evidence from the nancial services sector

    74 HUMAN RESOURCE MANAGEMENT JOURNAL VOL 8 NO 2

  • were overwhelmingly positive about PRP. They saw it as conducted fairly and perceived its

    congruence with the meritocratic values which the company had traditionally preached and

    they had absorbed. Therefore, using Lawler s (1984) criterion of employee acceptance, PRP

    could be said to be a success in Premierco but not in Finbank or Finsoc. In addition, only in

    Premierco was the PRP process cycle implemented effectively, giving some credence to the

    theory articulated above.

    Concern with motivation theory

    There is clear empirical evidence which suggests employee motivation is high on the list of

    organisations reasons for the introduction of PRP (Thompson, 1992; Cannell and Wood,

    1992). Therefore it is only to be expected that the central concern of both researchers and

    practitioners is with the degree to which PRP has motivated employees to work in different

    ways in order to achieve a PRP award. This prompts questions about the extent to which

    PRP has provided an incentive for individuals to work harder, show more initiative, get

    work priorities right, increase the quality and quantity of work and whether the amount of

    award is suf cient to act as an incentive (Marsden and Richardson, 1992). These are perfectly

    valid concerns, but they have the effect of steering attention towards the `harder aspects of

    the cycle. The data from this study suggest that it is the `softer processes those which

    involve employees in the cycle rather than exclude them which are likely to be associated

    with greater acceptance of PRP. In Premierco this was the skilful giving of performance

    feedback, coaching to improve performance, gathering of performance data from a wide

    range of sources, negotiation of objectives and the management of expectations about the

    nal award.

    This suggests that, even if the pay element of the cycle (stage 4) is not accepted by

    employees, the processes which concern the determination of the award, if conducted

    effectively, may mitigate the unacceptable impact of the pay element. This was largely the

    case at Premierco. However, it must be said that existence of `new style managers at

    Premierco operating in a highly meritocratic culture played a signi cant part in promoting

    the effectiveness of the soft processes. This reinforces the earlier point about the importance

    of considering contingency theory in addition to the PRP process cycle theory. The

    Premierco context in which PRP took place was of considerable signi cance. Therefore, a

    virtuous circle was operating where effective PRP processes were reinforcing the

    meritocratic culture, thus further strengthening them.

    Pre-eminence of line managers

    It follows from the above that the effective implementation of the softer processes turns on

    the skills and attitudes of the line manager. This study has con rmed the conclusion of

    Storey (1992) that line managers have an important part to play in the HRM model of

    managing the employment relationship, of which PRP is often a signi cant component.

    They have a particularly important role in the implementation of PRP. As noted above, this

    role has a hard and a soft side. The hard side is detailed by ACAS (1996). It is line managers

    who must de ne the required standards of performance and behaviour, explain these to

    their subordinates, take tough decisions about assessments, communicate these decisions to

    subordinates and defend their judgements if asked. The soft side, exempli ed in this study

    by the new style managerialism evident at Premierco, is thought to be consistent with

    Guests (1987) HRM goal of employee commitment.

    It may be that there is an inherent contradiction between PRP and the soft goals of HRM.

    Driving employees to perform better by carrot and stick when they are excluded from the

    Philip Lewis, Cheltenham and Gloucester College of Higher Education

    75HUMAN RESOURCE MANAGEMENT JOURNAL VOL 8 NO 2

  • process by dint of managers monopolising information setting objectives and standards

    and making assessments and awards (Marsden and Richardson, 1992) can hardly be

    thought of as a commitment seeking strategy.

    What this study has indicated is that, in two of the organisations, neither the hard nor soft

    aspects of the PRP process cycle were conducted effectively. This calls into question the

    attitudes and skill of the managers. The evidence suggested that short-term concerns, Storey

    and Sissons (1993: 76) `quick-fix agreements, fire-fighting solutions and Tayloristic job

    design methods which are built on command and control rather than the more time-

    consuming consensus-seeking methods, governed the thinking and behaviour of these

    managers. The evidence from this study suggests that, if the softer elements of the PRP

    process cycle are to be promoted, then line managers need a longer term investment

    perspective on their management of employees, which will lead to the involvement of

    individuals in the process cycle rather than exclusion from it.

    CONCLUSION: `MUCH ADO ABOUT NOTHING

    The thrust of this discussion has been that the soft aspects of the PRP process cycle are

    those which have been given less attention in the literature, a shortcoming this article has

    sought to rectify. The argument has been that agreeing clear objectives, defining

    performance standards which emphasise how the job is done as well as the results of the

    job, monitoring progress towards objectives and feeding back to the employee the results

    of the monitoring in a developmental way are necessary pre-conditions for the acceptance

    of PRP by employees. But these activities could be part of a performance management

    process without the presence of pay. Indeed, these activities are consistent with what Bevan

    and Thompson (1991: 39) call `development driven integration, where the outcome of the

    performance management process is the identi cation of training and development needs.

    So is pay a necessary part of performance management? Certainly the recipient managers

    at both Finbank and Finsoc thought it doubtful. Even if all the hard and soft aspects of the

    PRP process cycle had been conducted effectively, the feeling still remained that an increase

    of 2 per cent was `much ado about nothing . But this study has shown that, when the PRP

    process cycle is conducted effectively as at Premierco, PRP is more likely to be accepted by

    employees than when it is conducted ineffectively, whatever the level of award.

    Note

    The author acknowledges with thanks the helpful comments of an unknown referee which

    guided the preparation of this article.

    REFERENCES

    ACAS. 1996. Appraisal Related Pay, London: ACAS.

    Bevan, S. and Thompson, M. 1991. `Performance management at the cross-roads. Personnel

    Management, November, 36-39.

    Cannell, M. and Wood, S. 1992. Incentive Pay: Impact and Evolution, London: Institute of

    Personnel Management and National Economic Development Of ce.

    Cascio, W. F. 1989. Managing Human Resources 2nd ed, New York: McGraw-Hill.

    Clark, G. 1995. `Performance management in Strategic Human Resource Management. C.

    Mabey and G. Salaman. Oxford: Blackwell.

    Dowling, B and Richardson, R. 1997. `Evaluating performance-related pay for managers in

    Managing performance-related pay based on evidence from the nancial services sector

    76 HUMAN RESOURCE MANAGEMENT JOURNAL VOL 8 NO 2

  • Philip Lewis, Cheltenham and Gloucester College of Higher Education

    77HUMAN RESOURCE MANAGEMENT JOURNAL VOL 8 NO 2

    the National Health Service. International Journal of Human Resource Management. Vol. 8,

    no. 3, 348-366.

    Dyer, L. and Reeves, T. 1995. ` Human resource strategies and rm performance: what do we

    know and where do we need to go? International Journal of Human Resource Management,

    Vol. 63, 657-670.

    Gabris, G. T. and Mitchell, K. 1988. `The impact of merit raise scores on employee attitudes:

    the Matthew effect on performance appraisal. Public Personnel Management, Vol. 17, no. 4,

    369-386.

    Glaser, B. and Strauss, A. 1967. The Discovery of Grounded Theory, Chicago: Aldine.

    Guest, D. 1987. `Human resource management and industrial relations . Journal of

    Management Studies, Vol. 24, no. 5, 503-521.

    Guest, D. 1997. `Human resource management and performance: a review and research

    agenda. International Journal of Human Resource Management, Vol. 8, no. 3, 263-276.

    Hoevemeyer, V. A. 1989. `Performance-based compensation: miracle or waste? Personnel

    Journal, July, 64-68.

    Institute of Personnel Management. 1992. Performance Management in the UK, Wimbledon:

    Institute of Personnel Management.

    Kessler, I. 1994. ` Performance pay in Personnel Management. K. Sisson (ed). Blackwell.

    Kessler, I. and Purcell, J. 1995. `Individualism and collectivism in theory and practice:

    management style and the design of pay systems in Industrial Relations: Theory and

    Practice in Britain. P. Edwards (ed). Oxford: Blackwell.

    Kinnie, N. and Lowe, D. 1990. `Performance related pay on the shop floor. Personnel

    Management, November, 45-49.

    Lawler, E. E. 1984. `The strategic design of reward systems in Strategic Human Resource

    Management. C. Fombrun, N. M. Tichy and M. A. Devanna. New York: John Wiley.

    Lawler, E. E. 1990. Strategic Pay: Aligning Organisational Strategies and Pay Systems, San

    Francisco: Jossey Bass.

    Lawler, E. E. 1995. `The new pay: a strategic approach. Compensation and Bene ts Review,

    July-August: 14-22.

    Lupton, T. and Gowler, D. 1969. `Selecting a wage payment system. Research paper 111.

    London: Engineering Employers Federation.

    Marsden, D. and Richardson, R. 1992. `Motivation and performance-related pay in the

    public sector: a case study of the Inland Revenue. Discussion Paper No. 75. Centre for

    Economic Performance. London School of Economics.

    McAdams, J. 1988. `Performance-based reward systems: towards a common fate

    environment . Personnel Journal, June, 103- 113.

    Procter, S, McArdle, L, Rowlinson, M, Forrester, P. and Hassard, J. 1993. `Performance-

    related pay in operation: a case study from the electronics industry . Human Resource

    Management Journal, Vol. 3, no. 4, 60-74.

    Snape. E, Redman, T. and Wilkinson, A. 1992 `Human resource management in building

    societies: making the transformation? Human Resource Management Journal, Vol. 3, no. 3.

    Storey, J. 1992. Developments in the Management of Human Resources, Oxford: Blackwell.

    Storey, J. and Sisson, K. 1993. Managing Human Resources and Industrial Relations ,

    Buckingham: The Open University Press.

    Thompson, M. 1992. Pay and Performance: the Employer Experience, Falmer, Brighton: Institute

    of Manpower Studies.