Upload
vuthu
View
217
Download
0
Embed Size (px)
Citation preview
IAEA International Atomic Energy Agency
Management of Financial Risks
in Nuclear Power
Presentation to TM on Topical Issues of Infrastructure Development
Nuclear Power Project Development in Emerging Nuclear Power States
Paul Warren
Planning & Economic Studies Section
Vienna, 12th February 2013
IAEA
Risks over the nuclear project lifecycle
Construction Operation Decommissioning
Design
performance
not achieved
Inadequate
demand
Inadequate
financial
provision
2
Exchange
rate risk
Interest rate
risk
Schedule
delay
Construction
cost overrun
Regulatory
delays
Design
capacity not
achieved
All these risks will potentially impact the return received by funders
All these risks are financial risks!
IAEA
Contracting: stakeholders and agreements
3
Commercial
banks
Shareholders Host
government
Electricity
Utility
Fuel supplier
EPC
contractor
Export credit
agencies
Multilateral
agencies
Owner/
Operator
Shareholder
agreement Fuel
supply
agreement
EPC
contract
PPA
Loan
agreement
Loan
guarantee
Political
risk
insurance
Political
risk
insurance
IAEA
Risk sharing via contract language
“The contractor undertakes to construct a
power plant with a (net) capacity of 900MWe
for the sum of 4 billion USD.
The contractor will pay for replacement
power for each day in excess of 10 in any
year in which unplanned outages exceed 10
days.
The contractor will also pay for replacement
power for every day on which the plant is not
synchronized to the grid after January 1,
2018, except for delays caused by
unreasonable regulatory performance.”
Schedule
delays
Design
performance
not achieved
Regulatory
delay
Design capacity
not achieved
Construction
cost overrun
Inadequate
demand
Exchange rate
risk
4
Owner/Operator
EPC contractor
IAEA
Shifting risk away risk premia
5
Commercial
banks
Shareholders Host government
Electricity Utility
Fuel supplier
EPC contractor
Export credit
agencies
Multilateral
agencies
Owner/
Operator
Shareholder
agreement
Fuel supply
agreement
EPC
contract
PPA
Loan
agreement
Loan
guarantee
Political risk
insurance
Political risk
insurance
• As you put together your project as an Owner/Operator you can
offload risk – but there’ll be a cost of doing so: a risk premium
IAEA
Risk allocation financing cost
6
Owner/
Operator
Electricity
Utility
Fuel supplier
EPC
contractor
Fuel
supply
agreement
EPC
contract
PPA
Commercial
banks
Shareholders
Shareholder
agreement
Loan
agreement
Residual
financial
risk
IAEA
Intuitions on risk premiums
• Premium paid by OO to a ‘Party’ will depend on:
1. Size of the risk
• Volatility
• Monetary value
2. Party’s financial capacity relative to the size of
the risk
• A small party, with limited financial capacity might be
willing to bear a large volatile risk, but….
• …it will demand a large risk premium for doing so
3. Party’s risk appetite
4. Party’s ability to control the risk
7
NB!
IAEA
Allowing contractors a ‘menu’ approach
8
Fee
Site
pre
p
Equipment
Construction
materials
Construction
labour
Alternate pricing
options
Nu
cle
ar
Isla
nd
BO
P
AS
Nu
cle
ar
Isla
nd
BO
P
AS
Nu
cle
ar
Isla
nd
BO
P
AS
Fixed Price (1)
Firm Price (2)
Target with 10% collar
(3)
Target with a fee at risk
(at signing) (5)
Target with a fee at risk
(after signing) (6)
Reimbursable with a
fixed fee (8)
Cost plus (9) Pre
fere
nti
al
treatm
en
t o
f b
id
IAEA
Intuitions on risk premiums
• Premium paid by OO to a ‘Party’ will depend on:
1. Size of the risk
• Volatility
• Monetary value
2. Party’s financial capacity relative to the size of
the risk
• A small party, with limited financial capacity might be
willing to bear a large volatile risk, but….
• …it will demand a large risk premium for doing so
3. Party’s risk appetite
4. Party’s ability to control the risk
9
NB!
IAEA
‘Controllable’ versus ‘uncontrollable’ risks
10
Change in
taxation
regime
Inadequate
wind (wind
power)
Inadequate
rainfall
(hydro)
Project
becomes
uneconomic
Fossil fuel
price
escalation
Equipment
failure during
operation
Fuel supply
interruption
Pollution
limits not met
Inadequate
demand
Design
performance
not achieved
Construction
cost overrun
Schedule
delay
Commodity
price
escalation
Interest rate
volatility
Exchange
rate volatility
Design
capacity not
achieved
Regulatory
delay
Exchange
convertibility
risk
Controllable Uncontrollable
IAEA
Allocating ‘uncontrollable’ risks
• The larger and more ‘uncontrollable’ the risk
(e.g. prices set in global markets) the more
likely that only parties with very high financial
capacity will be willing to bear it at a price which
allows the project to remain economic
• Host governments (i.e. tax base!)
• Customer base (via regulated utilities)
• Multi-lateral agencies, regional development
banks
• Financial markets (via hedging instruments)
11
IAEA
Three ‘uncontrollable’ risks
• When risks depend on prices determined in
global markets (e.g. exchange rates), it is difficult
to identify any stakeholder “able to control them”
• Exchange rate risk
• Interest rate risk
• Commodity price escalation risk
• Risk of construction material price increases during
construction
• Risk of fuel price escalation during operation
• These risks can be allocated to financial markets
via swaps, options and futures
12
IAEA
An uncontrollable risk
• A risk which is similar to these three
‘uncontrollable’ risks is default risk
• The risk that the owner of the project will be unable
to repay some part (or any) of the principal or
interest on the loan
• Default risk associated with a project will be a
concern for lenders
• This makes it a concern for the project owner as well
• The higher the default risk that lenders perceive in a
project, the more they will charge to lend
13
IAEA
Default risk: sovereign guarantees
• A common way of mitigating default risk is
the sovereign guarantee • When a host national government guarantees to a
lender that if the project fails, it will repay all lending
• Providing a sovereign guarantee will almost
always reduce the cost of financing • Because governments are able to tax, their ability to
raise revenue is highly trusted by lenders
• A sovereign guarantee shifts significant
risk onto domestic taxpayers
14
NB!
IAEA
Takeaways
• All risk maps into financial risk
• As you put together your project as an
Owner/Operator you can offload risk – but there’ll
be a cost of doing so: a risk premium
• Costs of financing – including risk premiums – are
not necessarily always identified separately - but
they will be present nonetheless
• Sovereign guarantees will usually lower financing
costs – but they will also increase risk exposure
15
IAEA
Coordinated Research Project
• Financing Nuclear Investments will bring together
Member States, supported by IAEA activities.
• Objectives will include:
• Identifying the lessons which can be drawn with regard to
sources of financing for nuclear projects
• Exploring the nature of the financing process (including the
role of Financial Advisors)
• Identifying the barriers to financing nuclear projects.
• Designed for Member States with limited (or non-
existent) experience of financing nuclear power
projects
• Contact: [email protected]
16
IAEA
Financing TECDOC
• Document is currently being prepared
• Authors (5) are investment banking professionals
• Extensive financing experience in energy and nuclear ‘space’
• Framework, contents and topics set out by IAEA
• Document will constitute a “textbook” (a comprehensive set
supporting material) for future Expert Missions on financing
• Intended audience: mid-level Ministry of Finance or Ministry of Energy
officials (likely on secondment to a NEPIO) or mid-level executive in a
sponsoring utility
• An Executive Summary will be aimed at policy makers - explaining the
main options and choices that they will face when looking at financing.
• Contact: [email protected]
17
IAEA 18
Thank you!