144
1 Management Control Systems of Large Infrastructure Project: A Case Study of Delhi Metro Anil Kr Gupta , General Manager/PPP anil.gupta @ircon.org IRICEN, Pune, 11, April 2016

Management Control System- Delhi Metro_10042016

Embed Size (px)

Citation preview

Page 1: Management Control System- Delhi Metro_10042016

1

Management Control Systems of Large Infrastructure Project:

A Case Study of Delhi Metro

Anil Kr Gupta,

General Manager/PPP

[email protected]

IRICEN, Pune, 11, April 2016

Page 2: Management Control System- Delhi Metro_10042016

2

Project Management

Many look at it as a tool for planning there work

Everyone of us have to plan his day, week or the year ahead

However as the complexity of a Project increases so does the challenge

It applies to every day business such as Contractors, Consultants, New Development, Made to order

But the complex projects like Space missions, Troop Mobilization, Organizing Commonwealth Games, Building Metros, Bridging and Tunneling in Himalayas are the really challenging ones

Page 3: Management Control System- Delhi Metro_10042016

3

• Frequent Changes in the Chief Executive

• No committed fund

• Commencement without proper investigation and planning

• Faulty contract packaging and poor selection process

• Poor decision making process

• Casual and Indifferent Project Management

Key Reasons for Project Overruns

Page 4: Management Control System- Delhi Metro_10042016

4

Delhi Metro Project presents a Project Management System

that overcomes all these problems?

Page 5: Management Control System- Delhi Metro_10042016

5

Basis of the Case

The Case is based on the Phase I of the Delhi Metro Project in general

and MC1A Contract (Vishwavidyalaya to

Kashmere Gate u/g coridor) in particular

Page 6: Management Control System- Delhi Metro_10042016

6

Background

Detailed Project Report in 1995, Phase I by 2005

DMRC created on 03/05/95 as 50:50 equity from GOI and GOD

Phase I Cost Rs.10,500 crore (62.5% funding from Japan) and field work commenced in Oct’ 98

A General Consultant (GC), of PBI (USA), PCI, JARTS, Tonichi (Japan) and RITES (India) provided the project consultancy

The Project implementation period compressed from 10 years to 7 years and was successfully achieved

Page 7: Management Control System- Delhi Metro_10042016

7

Record Sheet of DMRC

Section Length(km)

Target Dateas in 2002

CommissionDate

Shahdara-Tis Hazari 8.0 Dec 2002 Dec 2002

Tis Hazari-Tri Nagar 4.7 Sept 2003 Sep 2003

Tri Nagar-Rithala 8.8 Mar 2004 Mar 2004

Vishwa Vidyalaya-Kashmere Gate* 4.0 Dec 2004 Dec 2004

Kashmere Gate-Central Secretariate 5.5 Sep 2005 Sep 2005

Barakhamba Road-Kirti Nagar 6.0 June 2005 Dec 2005

Kirti Nagar-Dwarka 16.4 Sep 2005 Dec 2005

*The Case study is based specifically on this MC1A Contract

Page 8: Management Control System- Delhi Metro_10042016

8

Salient Features of Contract MC1A

Section : Vishwavidyalaya – Kashmere Gate

Nature of Contract : Design & Construct Contract LS

Contractor : KSHI - JV

Value Of Contract : Rs 900 Cr + Provisional Sum

Length : 4.105 KM & Depot 434 M

No. Of Stations : 4

Start Date (NTP) : 22nd MAY 2001

Completion Date : 25th JULY 2005 (218 WEEKS)

Line Commissioned in Dec 2004, 7 months prior to the scheduled date

Page 9: Management Control System- Delhi Metro_10042016

MC1A Corridor

9

Work started in May,2001

Expected completion of civil works Dec,2004

2,31,000 Cum of structural concrete

12,00,000 Cum of excavation

Page 10: Management Control System- Delhi Metro_10042016

10

Salient Strategies that Paid off

Page 11: Management Control System- Delhi Metro_10042016

11

Technology Risk Management

• First set of u/g Civil, E&M, System, Rolling Stock contract packaging to attract international firms

• Condition: Indian partner and technology transfer to them

• Even GC Contract required Indian partner (RITES)

• Foreign experts of GC helped in transfer of technology to DMRC

• DMRC Engineers deputed to GC and Contractors

How it paid: All subsequent contracts and consultancy became indigenous

Page 12: Management Control System- Delhi Metro_10042016

Managing Knowledge in GC

GC came in Sept 1998 and during first six months till march 1999 all foreign experts worked

Every Expat was with one Indian counterpart from RITES

All Technical and complex documentation draft done during this period

Subsequently Indian experts with foreign project managers and some key experts managed the show

During the lull periods of delay in tender award expats took series of training sessions for DMRC/GC (Indian) staff

How it paid: Expertise for dealing with foreign contractors and consultants obtained at minimal cost

12

Page 13: Management Control System- Delhi Metro_10042016

Advance Preparation by DMRC

Road widening, boundary wall on sites, land acquisition

Understandings with local authorities on utilities, traffic, tree cutting/re-plantation, ground water

Surveys and alignments by GC came in handy

All the above gave a head start to the contractor

13

Page 14: Management Control System- Delhi Metro_10042016

Mobilization and Build Up Strategy

First six months in mobilization and build up of site organization

Contractor’s and GC’s best brains were deployed during this period

Before the foundation laying all Procedures including Safety, Quality and Environmental systems were in place

Too harsh during first six months of construction in all spheres

14

Page 15: Management Control System- Delhi Metro_10042016

15

Worker/ Engineer Training

• Projects are temporary organizations with large number of fresh hires

• DMRC was a new organization with inexperienced but intelligent and motivated engineers

• All top and middle level engineers/ managers (GC/DMRC) sent to metros around the world

• They became trainers for their junior staff

• Compulsory training in construction methodology, quality and safety systems at site to all recruits of contractor

How it paid: Pride and motivation among staff while working on project, safe and quality work

Page 16: Management Control System- Delhi Metro_10042016

16

Managing Utilities

• Utility Diversion through provisional sum

• Local authority’s retired chief engineers hired

• Local authority’s working contractors hired

• Local authority’s engineers supervised

• Innovations passed on to authorities

How it Paid: Work done in 25% of the cost quoted initially by bidders (this is 50% of the cost demanded by utility authorities)

Page 17: Management Control System- Delhi Metro_10042016

17

Traffic Management

• Scientific Diversion plan

• Improvements to branch roads (temporary bridges)

• Comprehensive Traffic Signage

• Own staff for regulating traffic

• Unidirectional traffic flow with lighted hoarding

• Real time congestion monitoring

How it paid: Better access to site, free movement of construction vehicles, public image

Page 18: Management Control System- Delhi Metro_10042016

18

Winning Public Support

• Proper property access through steel decked roads to individual houses

• Improving police station buildings and clubs

• Constructing boundary walls for IP College for women

• Instrumenting buildings for monitoring vibration induced impacts

• Prompt attention to public’s utility disruptions

• Rescheduling works for Five Star Hotel

Page 19: Management Control System- Delhi Metro_10042016

19

Managing Health and Safety

• No entry without helmet and safety boot, not even MD!

• Substandard safety condition reporting (SSPCR)

• 24hrs medical attendant doctor - tie up with nearby hospital

• Safety drill and job training at site

• All incidents, howsoever minor, reported (IR)

• A Safety Compendium was maintained for incidents and learning

How it paid: Minimum disruption, higher motivation, higher work output

Page 20: Management Control System- Delhi Metro_10042016

20

Environmental Management

• Tyre Washing System

• Water sprinkler system for dust control

• Silent Generators

• Neat and tidy work sites

• Conservation of Ground Water

• ISO 14001 certification

How it paid: Better mobility of worker, higher output, public image, fame to contractor

Page 21: Management Control System- Delhi Metro_10042016

21

Quality Management

• Stigma free reporting and documentation of violations

• SIs – for smaller violations (about 250)

• NCNs – for serious violations (about 65)

• Contractor’s corrective and preventive action

• Follow up with changes in MS/ WP

• Contractor’s own similar system

How it paid: Created a Reliable system and work culture which was later used to jack up progress like batting in slog overs of one day match

Page 22: Management Control System- Delhi Metro_10042016

22

Quality Inspections

• Section Engineers all day and Resident Engineer’s morning inspection

• Construction Manager’s weekly inspection

• CPM’s fortnightly inspection

• Director’s Monthly inspection

• MD’s quarterly inspection

• Weekly safety inspection, and surprise night inspections

• Weekly Environmental inspection

• Designer’s weekly site inspection

How it paid: Everyone remain charged up, no blame game, prompt solutions

Page 23: Management Control System- Delhi Metro_10042016

23

Motivating People• Group Awards by Contractor:

– Best Section Award, Best House Keeping Award,

• Group Awards by DMRC:

– Safety Shield for the Best Contract on Safety Day

• Individual Awards:

– Best Section Manager’s Award, Best Safety Manager’s Award, Best worker award

• Functions and Celebrations:

– Foundation Day for DMRC, Foundation Day for Contractor, Safety Day, Celebration for achieving important Key Dates

• Team Spirit Encouraged in joint participation of DMRC, GC, Contractor and Design Consultant staff in celebration

• Colorful MC1A Monthly bulletin for highlighting achievements

Page 24: Management Control System- Delhi Metro_10042016

24

Managing Design and Decisions

• Major decisions in meetings

• Concept approvals by MD in the presentation

• ‘Deemed acceptance if no comments by cut off date’

• Work must not suffer for want of design decisions

• On site consent or even on phone of design changes

• Online monitoring of design progress for scheduled works

How it paid: The biggest reason for delaying a project is gone

Page 25: Management Control System- Delhi Metro_10042016

IIMB, January 6, 2010 25

Managing Informations

Web Based Project Management Information System (PMIS)

• Daily Site wise Progress

• Cumulative Progress

• Site Photographs

• Drawing Management

• Controlled Documents

• Reports

• Schedules

•Online Instrumentation

• Milestone Status

Home Page

Page 26: Management Control System- Delhi Metro_10042016

Some Site Photographs

26

Page 27: Management Control System- Delhi Metro_10042016

27

A view of Concrete Batching Plant

Page 28: Management Control System- Delhi Metro_10042016

28

A view of Rebar Fabrication Yard

Page 29: Management Control System- Delhi Metro_10042016

29

Formwork fixing in Progress on Tunnel Roof

Page 30: Management Control System- Delhi Metro_10042016

30

Concreting in Progress on Tunnel Roof

Page 31: Management Control System- Delhi Metro_10042016

31

Work in Progress from Steel Deck inside the Hoarding

Page 32: Management Control System- Delhi Metro_10042016

32

Work in Progress at Vishwavidyalaya Station

Page 33: Management Control System- Delhi Metro_10042016

33

Excavation under Steel Struts Supporting Sheet Piles

Page 34: Management Control System- Delhi Metro_10042016

34

Inside the partially roof casted tunnel

Page 35: Management Control System- Delhi Metro_10042016

35

Dedicated Footpath on both sides on the Shamnath Marg

Page 36: Management Control System- Delhi Metro_10042016

36

6.00 Hrs in the morning, traffic stopped for blast

Page 37: Management Control System- Delhi Metro_10042016

37

Rebar Fixing at floor slab at Vishwavidyalaya Station

Page 38: Management Control System- Delhi Metro_10042016

38

An aerial view of road and work sites

Page 39: Management Control System- Delhi Metro_10042016

39

Tunnel Taking Shape- Top Down Construction

Page 40: Management Control System- Delhi Metro_10042016

40

Steel Deck Access to a Residence in Civil Lines area

Page 41: Management Control System- Delhi Metro_10042016

41

Vibro Sheet Piler at work

Page 42: Management Control System- Delhi Metro_10042016

42

Silent Sheet Piler at work

Page 43: Management Control System- Delhi Metro_10042016

43

Tyre Washing System

Page 44: Management Control System- Delhi Metro_10042016

44

A safety training in Class

Page 45: Management Control System- Delhi Metro_10042016

45

Crack Meter on the wall of a building

Page 46: Management Control System- Delhi Metro_10042016

46

Best Section Manager Award by MD to A-1 Section Manager

Page 47: Management Control System- Delhi Metro_10042016

47

Safety Talk to Workers on Safe Working at Height in A-2 Section

Page 48: Management Control System- Delhi Metro_10042016

48

Safety Award to the Project Leader of the KSHI JV by MD

Page 49: Management Control System- Delhi Metro_10042016

49

Hand Written Note by MD

Page 50: Management Control System- Delhi Metro_10042016

50

Recognition to the Safety Manager of the MC1A

Page 51: Management Control System- Delhi Metro_10042016

ISO 14001 Certification

Page 52: Management Control System- Delhi Metro_10042016

Citation From MD for ISO 14001 Certification

Page 53: Management Control System- Delhi Metro_10042016

My Last Working Day on 25th November 2003 (Kashmere Gate Station in the Background)

Page 54: Management Control System- Delhi Metro_10042016

Founding Principles of Delhi Metro Construction Management

No hoardings reading

– “Inconvenience is regretted”,

– “Work in Progress”,

– “Please bear with us”

These hoardings indicate poor planning and callous approach

They are indicators to future accidents, time overruns and cost overruns

Page 55: Management Control System- Delhi Metro_10042016

Founding Principles....

A new project brings new investment

Agency developing the infrastructure is in a better position to manage civic services at site

Hoardings at work sites on street should

– be a welcome sign

– public should expect better roads, smoother traffic and safer environment

– be a brand building for agency, contractor and consultant

Page 56: Management Control System- Delhi Metro_10042016

56

Contract Planning

Page 57: Management Control System- Delhi Metro_10042016

Framework of Works Contract

Item Rate

Contract

Build to

Design

Contract

Design and

Build

Contract

Design, Build

and Finance

Contract

Design,

Build,

Finance and

Maintain

Contract

Increasing Degree of Risk Allocation to Contractor

BOT

EPC BOLT

Page 58: Management Control System- Delhi Metro_10042016

Objectives of Contracting

Faster Construction

Smaller no. of Interfaces

Less Intensive Supervision

Project Financing (for part funding of project)

Lower Life Cycle Cost

Superior Asset Reliability - near zero failure

Less Frequent Maintenance

Lower Maintenance Duration

Page 59: Management Control System- Delhi Metro_10042016

Contract Selection by DMRC

Item Rate (Zonal Based) Contract for site preparation

Construct Only Contracts for Elevated

Design and Construct for first two u/g contracts, MC1A and MC1B

Subsequent u/g contracts for phase I on Construct Only

U/g contracts in second phase on Design and Construct

Private Concessioning-(Airport Line)

– Tunnel on EPC model

– System, Rolling Stock and operation on BOT model

Page 60: Management Control System- Delhi Metro_10042016

Review of DPR

Page 61: Management Control System- Delhi Metro_10042016

Why Review of DPR

DPR generally prepared by a team not directly responsible for implementation

Many DPRs do not get implemented

Project team and its Leader must own the DPR on which project is implemented

To avoid any blame game later on

61

Page 62: Management Control System- Delhi Metro_10042016

Reviewing DPR by DMRC Corridors revised to align them to the busiest roads

Contract Packaging changed for better quality and control e.g. Metro Corridor:

Contract Package

• Two Contract MC1A & 1B.

• Design & Construct -EPC

• The Packaging is done based on proposed method of construction i.e.(cut & Cover vs Tunnel Boring)

• Civil Engg. Electrical & Mechanical, Lighting(AC & Ventilation) all combined.

DPR

• 10 Civil Structure Contracts.

• Construct Only.

• Tender Documents are prepared on the basis of traditional multi-contract implementation Strategy

• Several E&M Contracts

• Several Ventilation/AC Contracts

Page 63: Management Control System- Delhi Metro_10042016

Project Management Consultant(PMC)

Page 64: Management Control System- Delhi Metro_10042016

64

Why PMC ?

A new SPV is neither experienced nor adequately equipped to handle the project management on its own.

To keep organization lean

Professional Management

Bridging the Knowledge Gaps

Better Relationship with Contractor

Managing New Contract types

Page 65: Management Control System- Delhi Metro_10042016

65

Project Consultancy Practices

Contract Specific

– NHAI, RVNL, BOT Projects

Project Specific

– General Consultant in DMRC

Organization Specific

– Irrespective of Contract or Project; being considered for CAO’s organization on IR

Page 66: Management Control System- Delhi Metro_10042016

66

Defining the Role

Project Management involve:

– Planning, Procurement and Tendering

– Measurement and Billing

– Progress Reporting

– Quality and Safety Monitoring

What should be the best way of allocation of above works?

Page 67: Management Control System- Delhi Metro_10042016

67

Role Allocation

Authority

Design Consultants

Contractor

CAO RVNL DMRC

Authority Authority

PMCPMC

Contractor Contractor

Page 68: Management Control System- Delhi Metro_10042016

68

How to Balance the role?

Client • Payment, Variations, and other contract management issues

• Planning, procurement and tendering

• Overall responsibility

Contractor • Contractor’s own Safety and Quality monitoring

• Monthly Progress Reporting

• Measurement and Billing

PMC • Safety and Quality monitoring

• Parallel Progress Reporting

• Checking of measurement and bills

• Assist client in planning, procurement and tendering

Page 69: Management Control System- Delhi Metro_10042016

69

Risk of Misjudgment

LeaderCAO

Individual

System

Exhibit-9

Leader

Individual

System Leader

Individual

System

CAO RVNL DMRC

Page 70: Management Control System- Delhi Metro_10042016

70

General Consultant to DMRC

Acted as Employer’s Representative on specific corridors and contracts

Did for Employer

– review of DPR

– tender management

– monitoring of execution

– NOC to Contractor’s drawings

– Testing and Commissioning different systems

DMRC kept payment, changes in contract, approval to

key drawings only

Page 71: Management Control System- Delhi Metro_10042016

71

EPC Contract Design

Page 72: Management Control System- Delhi Metro_10042016

72

Description Amount

a. Additional Testings

b. Furniture, Cabinets & Shelves

c. Artwork & Landscaping

d. Architectural finishes including false ceiling

e. Diversion & Support of utilities

Rs. 50 Lacs

Rs. 50 Lacs

Rs. 1.5 lacs

Rs. 15.5 (crores)

Rs.15 crores

MC1A Contract- Uncertain and Risky Items in Provisional Sum

Page 73: Management Control System- Delhi Metro_10042016

73

Activity Milestones Based Payment Cost Center Based Planning:

– 01 Preliminaries and General Requirements

– 02 Design (A-Civil, B-E&M, C-Tunnel Vent)

– 03 Tunnel Construction (A to D Sections, E-Depot Access)

– 04 Station Construction (A to D Stations)

– 05 Electrical (A to D Stations)

– 06 Water, Plumbing, Drainage (A to D Stations)

– 07 Fire Detection and Suppression (A to D Stations)

– 08 ECS (A to D Stations)

– 09 Tunnel Vent (A to D Stations)

– 10 Testing & Commissioning (A to D Stations)

– 11 Product Support (A to D Stations)

Page 74: Management Control System- Delhi Metro_10042016

74

Milestones Submission by Tenderers

Cost Center Outline describing activities included in it and typical activities and their ID numbers provided in tender

Tenderer to prepare its own Milestone Schedule matching its Program for entire project quoting $ and Re components of payment demanded together with Week of completion

Typical Milestone Numbers and what it implies

– 3B.20B implies Sheet Plie 50% complete by plan length at Ch 11+002 m to 11+627 m of Tunnel from V V Stn. to OS Stn.

– 4D.10A implies V V Station Base Slab 50% complete

Monthly cash flow to be submitted by tenderer and that should generally match with the physical progress of work proposed e.g.‘S’ Curves for Concrete

Lowest tenderer based on cumulative present value of milestone payment schedule of the tenderer

Page 75: Management Control System- Delhi Metro_10042016

75

Sub-Contracting Provisions

Tenderer prequalified with Design Consultant and T&C of proposed contract with it to be submitted with tender

Sub-contracting for works other than design limited to 50% of LS Price

Each sub-contract exceeding Rs. 1 million to be prior approved

Each sub-contract for provisional sum works, irrespective of value, to be prior approved

Page 76: Management Control System- Delhi Metro_10042016

76

MC1A Contracting EnvironmentDMRC

KSHI JV

GC

Sub Contractors

(upto 50% of the LS cost)

NOC for > Rs.1 million

Labour Contractors

PS Sub Contractor

Design Consultant

(MSEA)

Sub Consultants

Approval for each PS Sub Contract

Page 77: Management Control System- Delhi Metro_10042016

77

Interfacing with Other Contracts

Page 78: Management Control System- Delhi Metro_10042016

78

Metro Corridor System Wide Contracts

MC1A Civil Structures VW Station to ISBT (4Km)

MC1B Civil Structures ISBT to Central Secretariat (6.5 KM)

SYS 01 Signalling and Communication

SYS 02 Traction & Power Supply

SYS 03 Track work

SYS 04 Automatic Fare Collection

SYS 05 Lifts and Escalators

MC2 Khyber Pass Depot

RS1 Rolling Stock

Page 79: Management Control System- Delhi Metro_10042016

79

Key Dates for MC1A Connecting System Wide Contracts

KeyDate

Description of Key Date

KD1

KD5

KD8A

KD8B

KD8C

KD9

KD10

KD11

KD12

Preliminary Design 14 Weeks

Definitive Design 39 Weeks

Hand Equipment Rooms to SYS01 & SYS02-113 Weeks

Hand Concourse to SYS04 –155 Weeks, station complete

Handover Basic Structure to SYS 05-120 Week

Hand Track way to SYS 03 – 120 Weeks, tunnel complete

Power on to Station/Tunnels – 186 Weeks

Handover for Integrated Testing-193 Weeks

Completion of Works – 218 Weeks

Page 80: Management Control System- Delhi Metro_10042016

Key Dates vs Milestones

Both have a date specified in number of weeks from NTP for each

Key Dates are constraints for Project Network but Milestones are not

Non adherence to a Key Date invites penalty while that of a Milestone only delays the respective payment

Achievement of subsequent Key Date gets refund of penalty on earlier Key Dates while achievement of any milestone is independent of any other milestone

Key Dates were renegotiated for early commissioning while Milestones were allowed to be split for improving cash flow to contractor

80

Page 81: Management Control System- Delhi Metro_10042016

81

Project Scheduling

Page 82: Management Control System- Delhi Metro_10042016

82

Scheduling Strategy of DMRC

Chief Program Expert in GC was responsible for developing Primavera schedule

Stage wise commissioning dates identified in top level schedule

Cut off dates for all policy, technical, and contractual decisions in the planning phase

While fixing key dates for contracts, strategic buffer was kept at the end

Two level project management

– Corporate level: Key Dates for interfacing and buffer management

– Contract level: Milestones and Network Technique for monitoring

Page 83: Management Control System- Delhi Metro_10042016

83

Key Dates and Buffers

Buffer

Critical Chain = L Buffer = L/2 Commissioning

KD 1 KD 2 KD 3

KD 4

KD 5 KD 6

A Typical Project Schedule

Page 84: Management Control System- Delhi Metro_10042016

84

Scheduling Strategy of Contractor

Cumulative Payments ‘S’ curve matched with the Earthwork and Concrete ‘S’ curve derived from Schedule

Estimation of cost, payment flows and Programme logic followed each other

Some key resources centralized for reducing uncertainties- Lab, Batching Plant, Rebar Fabrication yard, Plant Maintenance, stone crushing plant

Objective: Latest Start and Highest economy

Proposed: 3 phase construction, for reusing temporary structural steel

Page 85: Management Control System- Delhi Metro_10042016

85

Concrete Consumption

0

5000

10000

15000

20000

25000

1-Apr-02

1-May

-02

1-Ju

n-02

1-Ju

l-02

1-Aug

-02

1-Sep

-02

1-Oct-02

1-Nov

-02

1-Dec

-02

1-Ja

n-03

1-Fe

b-03

1-Mar-03

1-Apr-03

1-May

-03

1-Ju

n-03

1-Ju

l-03

1-Aug

-03

1-Sep

-03

1-Oct-03

1-Nov

-03

1-Dec

-03

1-Ja

n-04

1-Fe

b-04

1-Mar-04

Time Period

Co

nc

re

te Q

ty

0

50000

100000

150000

200000

250000

300000

Monthly Concrete Qty

Actual Monthly Qty

Cumulative Concrete Qty

Cumulative Concrete Qty

S-Curve for Concrete Pouring S- Curve for Milestone Payment

Payment S-Curve

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

Jun-

01

Aug

-01

Oct-0

1

Dec

-01

Feb-

02

Apr

-02

Jun-

02

Aug

-02

Oct-0

2

Dec

-02

Feb-

03

Apr

-03

Jun-

03

Aug

-03

Oct-0

3

Dec

-03

Feb-

04

Apr

-04

Jun-

04

Aug

-04

Oct-0

4

Dec

-04

Feb-

05

Apr

-05

Jun-

05

Millio

ns

Months

Cu

mu

lati

ve

IN

R. Eq

uiv

ale

nt

Cumm.

INR Equi.

Use of S- Curve for Project Scheduling

Page 86: Management Control System- Delhi Metro_10042016

86

EPC Bidding Process

Page 87: Management Control System- Delhi Metro_10042016

87

Project Feasibility by the Contractor

It is inherent in the process that a contractor follows in responding to the request for proposal

Tender System should be designed to ensure proper feasibility study by the contractor for complex projects (EPC)

Pre Qualification and Technical Proposal plays an important role in this

Page 88: Management Control System- Delhi Metro_10042016

88

Request for Qualification (RFQ)

Page 89: Management Control System- Delhi Metro_10042016

89

Why need Pre Qualification?

Preparation of High Value EPC Bid: a time consuming and costly affair

Good parties do not invest in bidding unless they have a 20% chance of winning

Pre-qualified bidders provide a structured and meaningful feedback on the bid process and documents

They become stakeholders in the faster completion of the bid process

Necessary for bigger and complex projects

Page 90: Management Control System- Delhi Metro_10042016

90

Technical Proposals

Page 91: Management Control System- Delhi Metro_10042016

9191

Technical Proposals Essential for Complex Tenders

Drawings speak much more than Specifications

To avoid interpretation problems later

Authority is paying for the works and shall have to maintain the assets

To bring the understandings of different bidders at a level playing field before opening financial bids

Example of Vishwavidyalaya metro station technical evaluation

Page 92: Management Control System- Delhi Metro_10042016

92

Contents of Tender Documents

Works Program including Key Dates and Milestones

Employer’s requirements- Functional, Design, Construction, Manufacturing, Installation and Testing

Outline Design Specifications

Outline Construction Specifications

GCC & SCC

Safety, Quality and Environmental Manual

Tender Drawings and Tender Forms

Page 93: Management Control System- Delhi Metro_10042016

93

Evaluation of Tender Proposal

GC teams of experts in each field including programming constituted

Based on pre-bid queries and meetings with pre-qualified Tenderer's eight amendments issued

211 clarification questions covering every aspect of the proposal raised- many repeated to get clear confirmation

Answers/ confirmations sought in unambiguous terms together with revised proposals in many cases

NPV computation for the financial proposal

Page 94: Management Control System- Delhi Metro_10042016

94

Sample Clarification Question & Answer

Page 95: Management Control System- Delhi Metro_10042016

95

Value Addition During Tendering

Page 96: Management Control System- Delhi Metro_10042016

96

Alternatives and Options in Tender

Alternatives for deviations from Employer's Requirements and Outline Specifications in separate ‘Technical’ and ‘Financial’ packets

Options for change in basic nature of project

– Option A- Tunneling from Ch11+025m to 12+000m (Rocky area) instead of Cut & Cover

– Option B- Entire stretch with Tunneling instead of Cut & Cover

Alternatives are deviations in the Base offer itself while Options are complete set of optional tender

Page 97: Management Control System- Delhi Metro_10042016

97

Value Addition in Tender Process

Interactions with tenderers lead to understanding of break up of offer and risks that were priced

A reduction of more than Rs. 60 crore was achieved in LS Price

– By including Utility Diversion in Provisional Sum and increasing it by Rs.15 crore

A reduction of more than Rs. 200 crore was achieved in LS price due to following changes

– Min soil cover over tunnel/station box roof relaxed from 2m to 1m at localized places like subways

– Road allowed to be raised and regraded at localized places to meet min soil cover without raising tunnel alignment

Page 98: Management Control System- Delhi Metro_10042016

Execution of the Project

98

Page 99: Management Control System- Delhi Metro_10042016

99

Flow Chart of Design and Drawings

Tender Proposal

Preliminary Design

Definitive Design

Construction Reference Drawing

Working Drawings

Final design

As-Built Drawings

Page 100: Management Control System- Delhi Metro_10042016

Project Management

100

Page 101: Management Control System- Delhi Metro_10042016

101

Project vs OperationProject Operation

One time or a few times activities

Repetitive Activities

Temporary Organization Permanent Organization

Decisions Based on situations

Decisions Based on set rules

Higher technological and knowledge input

Mechanized or systematized set up

Managing constraints through unknown routes

Hardly any unknown situation

First time execution a Project

When execution isrepeated, becomes Operation

Page 102: Management Control System- Delhi Metro_10042016

102

Project Management

It has three dimensions

– Budget, Time and Quality Standards

An efficient organic way of achieving the Project Goal with necessary tradeoffs among the three

But be careful against treating it as hard quantitative CPM/PERT application software

It is actually a Soft Behavioral and System Approach

Hierarchy of Decisions is key

Page 103: Management Control System- Delhi Metro_10042016

103

Management Hierarchy in Project System

System Environment

Institutional Level

Organizational Level

Technical Core

Power delegation and decision making at each level has to be different for the system to work

Page 104: Management Control System- Delhi Metro_10042016

104

Decision Makers in the Hierarchy

System Hierarchy

Phase-I of Delhi Metro

MC1A Contract

System Environment MoUD, Delhi Government, BoD

(DPR and Funding Variation)

MD and Directors

(Cost and Time Variation)

Institutional Level MD and Directors

(Alignment and Contract Packaging)

PM/CPM

(Specification Variations)

Organizational Level CPM

(Land, Survey and Planning)

RE/ DyCE

(Procedure variation)

Technical Core Dy CE

(Site Development)

Site Engineers

(Inspection and Conformances)

Page 105: Management Control System- Delhi Metro_10042016

105

System Hierarchy for Routine Work

System Environment

Institutional Level

Organizational Level

Technical Core

As the complexity and uncertainty decreases the inner circles expand

Page 106: Management Control System- Delhi Metro_10042016

106

Standardization of Processes

Page 107: Management Control System- Delhi Metro_10042016

107

Procedures and Method Statements

Deputy Production Manager responsible for preparing from Contractor side

Resident Engineer from GC responsible for reviewing and giving comments

Work started only after relevant process approved through issue of NOC from GC

32 MPs, 56 MSs & ITPs and more than 30 WPs were developed in the contract

Page 108: Management Control System- Delhi Metro_10042016

108

Standard Procedures Expanded the Technical Core

System Environment

Institutional Level

Organizational Level

Technical Core

As the standardization and repetitiveness increased the inner circles expanded requiring lesser intervention of higher level decision makers

Page 109: Management Control System- Delhi Metro_10042016

109

Project Life Cycle and Phases

Page 110: Management Control System- Delhi Metro_10042016

110

Activities in Life Cycle of Project

Planning Designs Construction Services Finishing Commissioning

Time

Activities

Page 111: Management Control System- Delhi Metro_10042016

111

Each Phase Requires Different Levels of

Control

Page 112: Management Control System- Delhi Metro_10042016

112

Phases of a Project and its Control

Phase Primary Control

Secondary Control

Tertiary Control

Project Creation

System Environment

Planning Institutional System Environment

Design Organizational Institutional System Environment

Construction, Services and Finishing

Technical Core Organizational Institutional

Testing and Commissioning

Organizational Institutional

Operation Separate Operating Organization

Page 113: Management Control System- Delhi Metro_10042016

113

Flexible Management System

Life Cycle puts resources, costs and schedules in a constant state of change

Management must be flexible to respond and authorize changes

Flexible strategies for tradeoff among time, cost and standards

Page 114: Management Control System- Delhi Metro_10042016

114

One Implementing Agency for All Activities

Page 115: Management Control System- Delhi Metro_10042016

115

No Duplicity of Implementing Agency

Agency developing the infrastructure is in a better position to manage civic services at site

– No dependency on DJB, DVB, MCD, MTNL for utility diversion

This avoids blame game and feelings of helplessness

Compare this with the preparation for the Commonwealth Games 2010

No amount of GOM or Committees can replace the decision making process of one sole agency

Page 116: Management Control System- Delhi Metro_10042016

116

Monitoring System

Page 117: Management Control System- Delhi Metro_10042016

117

Building Site Organization- MC1A Contract

4 Sections, A to D (corresponding to cost center names) comprising one km of tunnel including one station

GC Organization parallel to Contractor’s

– Section Manager (Contractor) vs Section Engineer (GC)

Quality, Safety and Environment Managers reporting directly to the Project Leader

– Respective GC Experts reported to PD whereas SE Spl was the counterpart at site reporting to RE

Traffic and Utility Coordinator appointed by the contractor for coordination with sub contractors and authorities

Page 118: Management Control System- Delhi Metro_10042016

118

SE Section B

MD (DMRC)

Proj Dir (GC)Dir Proj

CPM (MC)

Dy. CE North MC

E. E.-1

PM (MC)

CRE (MC1A)

RE

SE Section A

PM

SM Section A

PL (MC1A)

E. E.-2

SE Section C

SE Section D

SM Section B

SM Section C

SM Section D

SE Spl RMs 1,2,3,4

CPM-Chief Proj Manager; PM-Proj Manager; CRE-Chief Resident Engineer; RE-Resident Engineer; SE-Section Engineer; EE-Executive Engineer; PL-Proj Leader; PM-Production Manager; SM-Section Manager; RMs-Resource Managers

Organizational Structure of MC1A

Line of communication

Line of Command

Page 119: Management Control System- Delhi Metro_10042016

119

Schedule of Meetings

• Chaired By DMRC

– Quarterly Community Interaction Meeting

– Monthly progress meeting by Director

– Field meeting by MD after inspection

• Chaired by GC

– Weekly Progress Meeting

– Weekly Design Coordination meeting

Page 120: Management Control System- Delhi Metro_10042016

120

Schedule of Meetings…contd.

• Chaired by Contractor

– Monthly Safety Meeting

– Site coordination meeting by each Section Manager

– Interface Coordination meeting with other contractors

How it Paid: Complex issues got resolved fast to every one’s satisfaction, Accountability for commitments

Page 121: Management Control System- Delhi Metro_10042016

121

Procedure for Monitoring Programme

Uniform procedure across contracts

Primavera 2.0 or later Software

3 month rolling program every month

4 week rolling program every week

Every program to show how key dates being achieved

Page 122: Management Control System- Delhi Metro_10042016

Primavera Project Plan

An important tool for developing and checking the integrity of Project Plan

But limited use for monitoring and interface at discussion level

Simple Gantt Charts were used for monitoring in addition to Primavera reports

122

Page 123: Management Control System- Delhi Metro_10042016

123

SECTION - A1 ( V V STATION)

TYPESTART

DATESCOPE

FINISH

DATE

S.P. 17-Nov-01 2063 20-Jan-03744 m 1636 m

73872 m3

EXCAVATION(STN) 1-Mar-02 160000 28-Oct-02

R.R. @ m3/day

m3

EXCAVATION(S) 7-Jun-02 74789 3-Oct-02 62172 m3 @ m3/day

EXCAVATION(N) 10015 to 10350

10-Aug-02 103451 11-Mar-03

m2

DECKING 16-Apr-02 10,600 21-Jan-035692m2 R.R.@ 78 m2/day

33 nos.

11-May-02 78 6-Sep-02

BASE SLABC&C(S) 18-Jul-02 8600 31-Jan-032518m3 delay by 58 days

BASE SLAB VV STN 26-Jun-02 10000 5-Feb-033552m3 delay by 80 days

CD1B EAST 347.6m85m

V.V.STN

CD1A WEST 55.6m

Legend 304.2 m

S.P. : SHEET PILE EXCAVATION DECKING

PROGRESS UPTO DATE TARGETTED BORED PILES

BASE SLAB

R.R. REQUIRED RATE

130909m3

BORED PILES

4306

170

1035

0

1872

TEMPORARY RETAINING STRUCTURES

STATUS AS ON:

PROGRESS BAR

1323.6 m

3524

1070

0

1035

0

738721030

0

1020

0

1010

0

1064

0

Page 124: Management Control System- Delhi Metro_10042016

124

Pictorial Presentation of Progress

Page 125: Management Control System- Delhi Metro_10042016

Monitoring through Cost Center and Milestones

Cost Center bifurcation helped in distinct responsibility and monitoring of works of various disciplines in one composite contract

Every conceivable requirement in contract linked to at least one milestone with coding

– 4A.10A [Vishwa Vidyalaya Station (4A), Station Box external walls (10) 50% complete (A)]

Even Contractor’s monthly supervision (1.12 to 1.61), monthly site running (1.79 to 1.128), Quarterly Audit reports on Quality/Safety/Environment (1.62 to 1.78) had one milestone each

Every submission is linked to a milestone

The coding of milestone and the organizational structure ensures that the responsible person for each milestone is known

125

Page 126: Management Control System- Delhi Metro_10042016

Milestone is the Focal Point

Network Programme is based on Milestone

Certification of completion of Milestone by GC enable payment

GC asks Production wing why certain Milestones that should have been completed in the month were not completed

Accounts wing computes the achievable milestones to get required cash flow and chases Production for completing

126

Page 127: Management Control System- Delhi Metro_10042016

Milestone Focal Point…

GC asks Quality, Safety and Environment wings for closure of NCNs and blocks payment of respective milestones

Accounts chases theses wings for getting blocked Milestones cleared

Quality, Safety and Environment wings chases Production for compliances so that they close the NCNs to release the milestone payment

127

Page 128: Management Control System- Delhi Metro_10042016

128

Assuring Cash Flow to Contractor

Weekly cash disbursal monitored by MD

80% payment within 3 days of submission of contractor prepared bills

Recovery of Advance suspended for certain period

Advances against ‘under consideration claims’

Milestones allowed to be split for faster cash flow

Motto: No Contractor should suffer for want of cash flow

Page 129: Management Control System- Delhi Metro_10042016

129

Monitoring Strategy- DMRC/ GC

• Monitoring changes behavior:

– This rule used to channelize energy

• Separate measurement units for different departments of contractor- Dealt separately to keep them motivated

• Simple measurements to reflect overall progress-e.g. Volume of Earthwork, Volume of Concrete

Page 130: Management Control System- Delhi Metro_10042016

130

Concrete Consumption

0

5000

10000

15000

20000

25000

1-Apr-02

1-May

-02

1-Ju

n-02

1-Ju

l-02

1-Aug

-02

1-Sep

-02

1-Oct-02

1-Nov

-02

1-Dec

-02

1-Ja

n-03

1-Fe

b-03

1-Mar-03

1-Apr-03

1-May

-03

1-Ju

n-03

1-Ju

l-03

1-Aug

-03

1-Sep

-03

1-Oct-03

1-Nov

-03

1-Dec

-03

1-Ja

n-04

1-Fe

b-04

1-Mar-04

Time Period

Co

nc

re

te Q

ty

0

50000

100000

150000

200000

250000

300000

Monthly Concrete Qty

Actual Monthly Qty

Cumulative Concrete Qty

Cumulative Concrete Qty

S-Curve for Concrete Pouring S- Curve for Milestone

Payment

Payment S-Curve

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

Jun-

01

Aug

-01

Oct-0

1

Dec

-01

Feb-

02

Apr

-02

Jun-

02

Aug

-02

Oct-0

2

Dec

-02

Feb-

03

Apr

-03

Jun-

03

Aug

-03

Oct-0

3

Dec

-03

Feb-

04

Apr

-04

Jun-

04

Aug

-04

Oct-0

4

Dec

-04

Feb-

05

Apr

-05

Jun-

05

Millio

ns

Months

Cu

mu

lati

ve

IN

R. Eq

uiv

ale

nt

Cumm.

INR Equi.

Progress on S- Curves

Page 131: Management Control System- Delhi Metro_10042016

131

MONTH EXCAVATIONCUMM. EXCAVATION

JULY,02 15570 57280

AUG,02 19420 72850

SEPT,02 15260 92270

OCT,02 18080 107530

NOV,02 22030 125610

DEC,02 27170 147640

JAN,03 30700 174810

FEB,03 20370 205510

MARCH,03 23080 225880

APRIL,03 36700 248960

MAY,03 22440 285660

JUN,03 24170 308100

JULY,03 10130 332270

AUG,03 13240 342400

EXACVATION PROGRESS

0

5000

10000

15000

20000

25000

30000

35000

40000

JU

LY

,02

AU

G,0

2

SE

PT

,02

OC

T,0

2

NO

V,0

2

DE

C,0

2

JA

N,0

3

FE

B,0

3

MA

RC

H,0

3

AP

RIL

,03

MA

Y,0

3

JU

N,0

3

JU

LY

,03

AU

G,0

3

MONTH

MO

NT

HL

Y E

XC

AV

AT

ION

0

50000

100000

150000

200000

250000

300000

350000

400000

CU

MM

UL

AT

IVE

EX

CA

VT

ION

EXCAVATION

CUMM. EXCAVATION

month

monthly

concrete cummulative

NOV,2 1550 1736

DEC,2 2084 3820

JAN,3 1291 5111

FEB,3 2240 7351

MAR,3 2180 9531

APR,3 1991 11522

MAY,3 4171 15693

JUN,3 5036 20729

JUL,3 5325 26054

AUG,3 5283 31337

SEPT,03 5634 36971

CONCRETING PROGRESS

0

500

1000

1500

2000

2500

3000

3500

4000

4500

5000

5500

6000

NO

V,2

DE

C,2

JA

N,3

FE

B,3

MA

R,3

AP

R,3

MA

Y,3

JU

N,3

JU

L,3

AU

G,3

SE

PT

,03

MONTH

MO

NT

HL

YC

ON

CR

ET

ING

0

5000

10000

15000

20000

25000

30000

35000

40000

CU

MM

. C

ON

CR

ET

ING

MONTHLY CONCRETING

CUMM. CONCRETING

Trends of Progress in a Section

Page 132: Management Control System- Delhi Metro_10042016

132

GC/ DMRC’s Hot and Cold Strategy

• Too harsh in the beginning, even at the cost of progress

• Cyclical harshness in the middle, correcting the course

• Lenient toward the end, pushing the progress and making contractor succeed

Page 133: Management Control System- Delhi Metro_10042016

133

Recovering Delays

Visible implication of a day’s delay to the SPV

Visible implication of a day’s delay to each contractor

Above should be known to every engineer and worker on the project

Page 134: Management Control System- Delhi Metro_10042016

134

Visible implication of a day’s delay

• To DMRC

– Each day that the project is delayed, the cost goes up by Rs.1.4cr. due to inflation and DMRC deprived of Rs. 89 lacs of net revenue.

– Each day saved will benefit the city to the extent of Rs. 4.5 cr. in terms of fuel saved & other social benefits.

• To MC1A Contractor

– 0.005% of contract price every day( Rs 5 lakh) if a key date is missed but refundable when subsequent key date is achieved

• Constant reminder: Project Clock ticking number of days left to commissioning

Page 135: Management Control System- Delhi Metro_10042016

135

Buffer Management in Construction Projects

• Delays are rule rather than exceptions

• As soon as a contract is signed it starts slipping

• Key to success lies in Effective Buffer (Slippage) Management:

– Keep Buffer away from the Activity In-charge

– Link Buffer with Reserve Cash

– Slippages cause loss and Acceleration costs money

– Use Buffer Management for galvanizing/ re-energizing the organization

Page 136: Management Control System- Delhi Metro_10042016

136

Key Dates and Buffers

Buffer

Critical Chain = L Buffer = L/2 Commissioning

KD 1 KD 2 KD 3

KD 4

KD 5 KD 6

A Typical Project Schedule

Page 137: Management Control System- Delhi Metro_10042016

137

Key Dates for MC1A Contract

KeyDate

Description of Key Date

KD1

KD5

KD8A

KD8B

KD8C

KD9

KD10

KD11

KD12

Preliminary Design 14 Weeks

Definitive Design 39 Weeks

Hand Equipment Rooms to SYS01 & SYS02-113 Weeks

Hand Concourse to SYS04 –155 Weeks (70%), station complete

Handover Basic Structure to SYS 05-120 Week

Hand Track way to SYS 03 – 120 Weeks (54%), tunnel complete

Power on to Station/Tunnels – 186 Weeks

Handover for Integrated Testing-193 Weeks

Completion of Works – 218 Weeks

Page 138: Management Control System- Delhi Metro_10042016

138

Tradeoff Between Quality and Time

• Initial Stringent norms were relaxed to assist the Contractor in mobilizing additional resources

• Construction methodology was allowed to be revised

• Additional smaller subcontractors and indigenous equipments were allowed

• Temporary works were allowed to be simplified on the experience gained allowing faster work with lesser material

• Non-conformances were closed with acceptable corrections

Page 139: Management Control System- Delhi Metro_10042016

139

Tradeoff Between Cost and Time

• Taking up parallel works by abandoning phasing by mobilizing additional alternative materials

• Introducing Night Shift and allowing extra days of salary to all workers for meeting and exceeding targets

• Deploying additional Indian engineers in place of expats

As S curve became sharper, Project Leader forced to think new solutions to face DMRC/GC

Page 140: Management Control System- Delhi Metro_10042016

Using Key Resources in Speeding

Senior Management monitored batching plant and concreting

Monthly, weekly and daily pour program were prepared

Rate of site preparation didn’t match with the concrete pouring capacity till towards the end of the Month

Last week of every month was concreting week till 6.00 AM in the morning of the 1st of next month

140

Page 141: Management Control System- Delhi Metro_10042016

141

Assuring Cash Flow to Contractor

Weekly cash disbursal monitored by MD

80% payment within 3 days of submission of contractor prepared bills

Recovery of Advance suspended for certain period

Advances against ‘under consideration claims’

Milestones allowed to be split for faster cash flow

Motto: No Contractor should suffer for want of cash flow

Page 142: Management Control System- Delhi Metro_10042016

Arranging Alternatives

Silent Sheet Pile driving equipment imported to avoid excessive vibration to sensitive buildings

Air lifting of equipments in case of delay in shipping

Alternative sources of aggregates when SC banned mining

Obtained Delhi police permission for controlled blasting to speed up rock excavation

142

Page 143: Management Control System- Delhi Metro_10042016

143

Buffer Management by DMRC

• Buffer kept in testing and commissioning helped

• Confidence developed in Rail Corridor led to targeting reduction in time

• Contractors were given incentives for preponing key dates

• Partial opening of stations planned

• Phased handing over to system contractors agreed

Opportunity lies on the upper portion of ‘S’ curve

Page 144: Management Control System- Delhi Metro_10042016

Open for Questions and Discussion

144