Make-Whole Payments and Distributions Review May 20, 2015 Steve White [email protected] · 501.482.2167

Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. [email protected] · 501.482.2167

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Make-Whole Payments and DistributionsReview

May 20, 2015

Steve [email protected] · 501.482.2167

Page 2: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

1. Day-Ahead Make-Whole-Payment AmountProtocol Reference: 4.5.8.12

2. Day-Ahead Make-Whole-Payment Cost AllocationProtocol Reference: 4.5.8.13

3. RUC Make-Whole-Payment AmountProtocol Reference: 4.5.9.8

4. RUC Make-Whole-Payment Cost AllocationProtocol Reference: 4.5.9.10

Sections

2

Page 3: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Make-Whole-PaymentsThe Basics

• Why do we have MWP?

To ensure eligible Resources cover their operational costs for a Commitment Period

• Who is eligible to receive a MWP?

Any Resource that receives an SPP “Market” Commitment –either for economic or reliability purposes

• Who is responsible to pay for MWP(s)?

Any AO with Market activity at a SL which contributes to the need for MWP(s)

3

Page 4: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

0

10000

20000

30000

40000

50000

60000

70000

80000

cost revenue

Make-Whole-Payment Overview

MWP

Operating Reserve Revenue

Energy Revenue

Operating Reserve Cost

RUC Remainder Start-UpCostIncremental Energy Cost

No Load Cost

Start-Up Cost

4

Page 5: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Common Terms

Commitment Period• The contiguous period of time between a Resource’s Commit

Time and De-Commit Time • By Market – DA Commitment vs RUC Commitment

• Single Commitment can span Operating Days• Multiple Commitments can exist in a single Operating Day

Make-Whole Payment Eligibility Period• Splits a multi-day Commitment Period on day boundaries• Is synonymous to Commitment Period for single day

Commitments

5

Page 6: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

DAY-AHEAD MAKE-WHOLE PAYMENT AMOUNT

Section 1

6

Page 7: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Hourly Revenue

Day-Ahead Make-Whole-Payment Process

Start-UpRUC Remainder (Start-Up)

No-LoadIncremental EnergyOperating Reserves

Make-Whole Payment

EnergyOperating Reserves

Make-Whole Payment Eligibility Period

Hourly Production Costs

7

Page 8: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Day-Ahead Operational CostsStart-Up

• Not Eligible for recovery when:

• Adjacent to the end of a RUC MWP eligibility period

• Includes Self-Commit Hour

• Synchronized more than 1 hour before sync-to-min

• Recovered in the lessor of min-run-time or 24 Hours

• Hot, Warm, or Cold DA Offer

8

Page 9: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Day-Ahead Operational CostsRUC Remainder - Start-Up

• Unrecovered RTBM Start-Up from RUC Commitment adjacent to the beginning of the DA Commitment

• Result of RUC starting a Resource earlier than its DA Commitment

• RUC Commitment may be less than min-run-time due to its adjacency to the DA Commitment

9

Page 10: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Day-Ahead Operational CostsNo Load

• Day-Ahead No Load Offer

Incremental Energy

• Day-Ahead Energy Offer Curve

• Day-Ahead Cleared Energy

10

Page 11: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Day-Ahead Operational CostsOperating Reserve (Reg-Up, Reg-Down, Spin, Supp)

• Day-Ahead Operating Reserve Product Offers

• Day-Ahead Cleared Operating Reserve Products

• Day-Ahead Reg-Up and Reg-Down Unused Mileage

• Day-Ahead Regulation Mileage MCPs

11

Page 12: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Day-Ahead RevenueEnergy

• Day-Ahead Cleared Energy

• Locational Marginal Price at Resource SL

Operating Reserve (Reg-Up, Reg-Down, Spin, Supp)

• Day-Ahead Cleared Operating Reserve Products

• MCPs for Operating Reserve Products in Resource Reserve Zone

• Day-Ahead Reg-Up and Reg-Down Unused Mileage MWPs

12

Page 13: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Hourly Revenue

Day-Ahead Make-Whole-Payment Process

Start-UpRUC Remainder (Start-Up)

No-LoadIncremental EnergyOperating Reserves

Make-Whole Payment

EnergyOperating Reserves

Make-Whole Payment Eligibility Period

Hourly Production Costs

13

Page 14: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

DAY-AHEAD MAKE-WHOLE-PAYMENT COST ALLOCATION

Section 2

14

Page 15: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Hourly Allocation Qty

Day-Ahead Make-Whole-Payment Cost Allocation Process

SPP Wide MWP Costs_________________

SPP Wide Withdrawal MWh

Make-Whole Payment Distribution

Cleared Load MWhCleared Export MWh

Cleared Virtual Bid MWh

Hourly

Daily Allocation Rate

15

Page 16: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Day-Ahead MWP Allocation RateSPP Wide MWP Costs for the Operating Day

• Sum of all Day-Ahead MWP for the Operating Day

SPP Wide Withdrawal MWh for the Operating Day

• Sum of all Day-Ahead Cleared Withdrawal MWh for the Operating Day

• Day-Ahead Cleared Energy Withdrawal MWh

• Day-Ahead Cleared Export MWh

• Day-Ahead Cleared Virtual Energy Bid MWh

16

Page 17: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Day-Ahead MWP Allocation QuantityAO/SL Withdrawal MWh by Hour

• Day-Ahead Cleared Energy Withdrawal MWh

• Day-Ahead Cleared Export MWh

• Day-Ahead Cleared Virtual Energy Bid MWh

17

Page 18: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Hourly Allocation Qty

Day-Ahead Make-Whole-Payment Cost Allocation Process

SPP Wide MWP Costs_________________

SPP Wide Withdrawal MWh

Make-Whole Payment Distribution

Cleared Load MWhCleared Export MWh

Cleared Virtual Bid MWh

Hourly

Daily Allocation Rate

18

Page 19: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

RUC MAKE-WHOLE-PAYMENT AMOUNT

Section 3

19

Page 20: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Revenue

RUC Make-Whole Payment Process

Cancelled Start-Up Start-UpNo-Load

Minimum EnergyIncremental EnergyOperating Reserve

Make-Whole Payment

Incremental EnergyIncremental OR

Out Of Merit Regulation Adjustment

Operational Cost

URD AdjustmentManual Status AdjustmentMinimum Limit Adjustment

Cost Adjustments

Make-Whole Payment Eligibility Period

20

Page 21: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Operational CostsCancelled Start-Up

• Pro-rata share of the as Committed RTBM Start-Up Offer

• Applies to Resources that receive a start-up cancellation while in their start-up window

• Start time defined in the as Committed RTBM Start-Up Offer

• Hot, Warm, or Cold RTBM as Committed Offer

21

Page 22: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Operational CostsStart-Up

• Not Eligible for recovery when:

• Adjacent to the end of a Day-Ahead MWP eligibility period

• Includes Self-Commit Hour

• Synchronized more than 1 hour before sync-to-min

• Recovered in the lessor of min-run-time or 24 Hours

• Must be synchronized at least one Dispatch Interval

• Hot, Warm, or Cold as Committed RTBM Offer

22

Page 23: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Operational CostsNo Load

• As Committed RTBM No Load Offer

• Incremental Cost above Day-Ahead No Load Offer

• Breaker must be closed

(Effective) Minimum Energy

• As Committed RTBM Energy Offer Curve

• Zero if Day-Ahead Cleared MWh >= Real-Time Effective Min MWh

• Area under the curve from zero to Effective Minimum

23

Page 24: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Operational Costs

Incremental Energy

• As Dispatched RTBM Energy Offer Curve

• Area under the curve for Incremental Energy

• From DA Cleared or Effective Minimum to Billable Meter

24

Page 25: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Operational CostsOperating Reserve (Reg-Up, Reg-Down, Spin, Supp)

• As Dispatched RTBM Operating Reserve Product Offers

• Incremental RTBM Cleared Operating Reserve Products

• Reg-Up and Reg-Down Excess Mileage

• Incremental Reg-Up and Reg-Down Unused Mileage

• RTBM Regulation Mileage MCPs

25

Page 26: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time RevenueIncremental Energy

• From DA Cleared to Billable Meter

• Locational Marginal Price at Resource SL

Operating Reserve (Reg-Up, Reg-Down, Spin, Supp)

• RTBM Incremental Cleared Operating Reserve Products

• MCPs for Operating Reserve Products in Resource Reserve Zone

• RT Reg-Up and Reg-Down Unused Mileage MWPs

26

Page 27: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time RevenueOut of Merit

• Cost above LMP for OOME Dispatch above economics

• As Dispatched RTBM Energy Offer Curve

• RTBM LMP above DA LMP for OOME Dispatch below DA Cleared

• RTBM MCP above DA MCP for OOME OR below DA Cleared

27

Page 28: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Revenue AdjustmentRegulation Adjustment

• Cost above LMP for Regulation-Up Deployment

• Recover losses from Regulation-Up Deployment

• LMP above Cost for Regulation-Up Deployment

• Claw back profit from Regulation-Up Deployment

• Cost below LMP for Regulation-Down Deployment

• Recover lost profit from Regulation-Down Deployment

• LMP below Cost for Regulation-Down Deployment

• Claw back cost savings from Regulation-Down Deployment

28

Page 29: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Operational Cost AdjustmentsUninstructed Resource Deviation

• Resource operates outside its Operating Tolerance

• Resource has no exemption

• Disallows Incremental Energy costs above Desired Energy Costs

• As Dispatched RTBM Energy Offer Curve

29

Page 30: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Operational Cost AdjustmentsManual Status Adjustment

• Resource changes its Control Status to “Manual”

• Resource is not operating Uninstructed

• Disallows Incremental Energy costs above Desired Energy Costs

• As Dispatched RTBM Energy Offer Curve

30

Page 31: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Operational Cost AdjustmentsMinimum Limit Adjustment

• Resource increases its Effective Minimum Limit above the limit used to commit the Resource

• And above the Resource’s Operating Tolerance

• Disallows Incremental Energy costs above Desired Energy Costs

• As Dispatched RTBM Energy Offer Curve

31

Page 32: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Revenue

RUC Make-Whole Payment Process

Cancelled Start-Up Start-UpNo-Load

Minimum EnergyIncremental EnergyOperating Reserve

Make-Whole Payment

Incremental EnergyIncremental OR

Out Of Merit Regulation Adjustment

Operational Cost

URD AdjustmentManual Status AdjustmentMinimum Limit Adjustment

Cost Adjustments

Make-Whole Payment Eligibility Period

32

Page 33: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

REAL-TIME MAKE-WHOLE-PAYMENT COST ALLOCATION

Section 4

33

Page 34: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Hourly Deviation Qty

Real-Time Make-Whole-Payment Cost Allocation Process

SPP Wide MWP Costs_________________

SPP Wide Deviation MWh

Make-Whole Payment Distribution

Deviation MWh

Hourly

Daily Allocation Rate

34

Page 35: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time MWP Allocation RateSPP Wide MWP Costs for the Operating Day

• Sum of all RUC MWP for the Operating Day

SPP Wide Deviation MWh for the Operating Day

• Sum of all Real-Time Deviation MWh for the Operating Day

35

Page 36: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time MWP Deviation QuantityAO/SL Deviation MWh by Hour

• Real-Time Net Settlement Location Deviation MWh

• Real-Time Minimum Limit Deviation MWh

• Real-Time Maximum Limit Deviation MWh

• Real-Time Outage Deviation MWh

• Real-Time (Manual) Control Status Deviation MWh

• Real-Time RUC Self-Commit Deviation MWh

• Real-Time RUC Commit Deviation MWh

• Real-Time URD Deviation MWh36

Page 37: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Deviation QuantityReal-Time Net Settlement Location Deviation MWh

• Load SL that Deviate from their DA Cleared MWh

• Export Transaction that Deviate from their DA Cleared MWh

• Import Transactions that Deviate from their DA Cleared MWh

• Through Transactions that Deviate from their DA Cleared MWh

• Sink Transaction only

• Absolute Value - DA Cleared Virtual Energy Offers MWh

37

Page 38: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Deviation QuantityReal-Time Minimum Limit Deviation MWh

• Resource Clears in the DA Market

• Resource increases its Effective Minimum Limit in RTBM Offer

• More than Operating Tolerance

• Above its DA Cleared MWh

• Resource is Dispatched to its RTBM Minimum Dispatch MW

• For at least one Dispatch Interval in the Hour

• Deviation MWh equals the difference between the Resources RTBM Effective Minimum Limit and the lesser of the (DA Cleared MWh or the DA Effective Minimum Limit)

38

Page 39: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Deviation QuantityReal-Time Maximum Limit Deviation MWh

• Resource Clears in the DA Market

• Resource decreases its Effective Maximum Limit in RTBM Offer

• More than Operating Tolerance

• Below its DA Cleared MWh

• Resource is Dispatched to its RTBM Maximum Dispatch MWh

• For at least one Dispatch Interval in the Hour

• Deviation MWh equals the difference between the greater of (DA Cleared MWh and the DA Effective Maximum Limit) and the Resources RTBM Effective Maximum Limit

39

Page 40: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Deviation QuantityReal-Time Outage Deviation MWh

• Resource Clears in the DA Market

• Resource is Off-Line in the RTBM

• Resource does not have an SPP De-Commit Instruction

• Deviation MWh equals the DA Cleared MWh

40

Page 41: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Deviation QuantityReal-Time (Manual) Control Status Deviation MWh

• Resource Clears in the DA Market

• Resource is in “Manual” Control Status in RTBM

• Deviation MWh equals the difference between Resource’s Desired Energy and Billable Meter

41

Page 42: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Deviation QuantityReal-Time RUC Self-Commit Deviation MWh

• Resource does not Clears in the DA Market

• Resource Self-Commits following the DA Market

• Resource is Dispatched to its RTBM Minimum Dispatch MWh

• For at least one Dispatch Interval in the Hour

• Resource is Exempt from this Deviation if:

• Resource Offered into the DA Market but did not Clear

• Resource Self-Committed prior to DA RUC

• Deviation MWh equals the Resources actual output MWh42

Page 43: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Deviation QuantityReal-Time RUC Commit Deviation MWh

• Resource does not Clears in the DA Market

• Resource either Self-Commits or is Committed by SPP following the DA Market

• Resource is Off-Line in the RTBM

• Resource does not have an SPP De-Commit Instruction

• Deviation MWh equals the greater of the Resource’s Economic Minimum Limit and its Desired Energy at the beginning of the Commitment

43

Page 44: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Real-Time Deviation QuantityReal-Time URD Deviation MWh

• Resource operates outside its Operating Tolerance in the RTBM

• Resource does not have an Exemption

• Deviation MWh equals the Resource’s Uninstructed Deviation MWh

44

Page 45: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Hourly Deviation Qty

Real-Time Make-Whole-Payment Cost Allocation Process

SPP Wide MWP Costs_________________

SPP Wide Deviation MWh

Make-Whole Payment Distribution

Deviation MWh

Hourly

Daily Allocation Rate

45

Page 46: Make-Whole Payments and Distributions Review review - may 2015.pdfMake-Whole Payments and Distributions Review May 20, 2015 Steve White. swhite@spp.org · 501.482.2167

Questions?

Meeting materials available online at:

www.spp.org

Org Groups > Market Working Group > Settlement User Group

For further information contact:

[email protected]

46