10
ROBUST CAPACITY PLANNING IN A MAKE-TO-ORDER JOB-SHOP Prof. Dr. José Antonio Heredia Álvaro Industrial System Engineering and Design Department Universitat Jaume I Castellón - Spain

Make to Order

Embed Size (px)

DESCRIPTION

a new approach to assess process behaviour

Citation preview

Page 1: Make to Order

ROBUST CAPACITY PLANNING IN A MAKE-TO-ORDER JOB-SHOP

Prof. Dr. José Antonio Heredia Álvaro

Industrial System Engineering and Design Department

Universitat Jaume I

Castellón - Spain

Page 2: Make to Order

MAKE-TO-ORDER PLANNING

• It is fundamentally a capacity planning problem

• A trade-off between cost and quality of service:

+capacity +manufacturing cost

+capacity -WIP

+capacity quality of service

Lead-time

Reliability

Page 3: Make to Order

Case example

Product family: Sprinkler clampWorkstation: Press 160 and Press 200Customer : HiltiDemand 2013: 2,5 million units

Stock level: 220.000 unitsService level: 96%Lead time: 5 days

Page 4: Make to Order

Cycle time distribution

• A very complex problem using traditional approaches

• With traditional queuing theory researchers doesn´t find the solution ->

approximations for the mean (and variance in some cases)

• Embedded Markov chains at departure epochs allows to obtain the exact

density function in some simple cases (Neuts, Bertsimas)

• The approach that I´m developing solve this problem with a different paradigm

Page 5: Make to Order

Example of PH-distribution

l l

p0

1-p0

phase-type distribution as a network of exponential processes among which with certain probability transitions may occur

Page 6: Make to Order

Example: workstation with 2 machines

l

m1

m2

0,0 1,0 2,0

0,1 1,1 2,1

l

m1

m2

m1

m2

l

l

2,b

l

m1 +m2

m1

m1

m2l l

Cycle time distribution

Page 7: Make to Order

PH-distribution modelling

1TH

TH

Page 8: Make to Order

PH-characterization

=( ,0, 1- )a D D

p1=1-p0

Page 9: Make to Order

Function relating Lead-Time and Capacity

1

2

3

4

5

6

7

8

9

0,5 0,6 0,7 0,8 0,9 1 1,1 1,2 1,3 1,4 1,5

Lead Time

Capacity

service level95%

90 %

85 %

1

1,5

2

2,5

3

3,5

4

4,5

5

5,5

6

1 3 5 7 9 11

Lead Time

Buffer size

95%

90%

85%

Page 10: Make to Order

Conclusions

•The new approach allows modeling more realistic cases that previous

•For simple cases the approach is accurate

•Provides valuable insights to understand the system behavior

•It is a pedagogical tool to master the art of simulation modeling