48
Bombay High Court .. 1 ..  ARA-6/07                             IN THE HIGH COURT OF JUDICATURE AT BOMBAY.                           CIVIL APPELLATE  JURISDICTION                  ARBITRATION APPEAL NO.6 OF 2007                            STATE OF MAHARASHTRA  (at the instance of Irrigation Department, Executive Engineer, Koyna Division No.2)           ...  Appellant. V/s. 1. HINDUSTAN CONSTRUCTION COMPANY     (LTD. (“HCC”). 2. ARBITRAL TRIBUNAL OF :     a) S.N.Jha, b) V.M.Ranade, c) B.S.Panchmukhi  ... Respondents. Mr A.A. Kumbhakoni,  learned counsel a/w Mrs S.V.Sonawane learned A.G.P., Mr Shardul Singh and Mr Abhay Anturkar for Appellant.   Mr Aspi Chinoy, senior Counsel a/w Mr Arif Doctor i/b M/s Haresh Joshi & Co. for Respondents.               CORAM :  R.D.DHANUKA  J.              RESERVED ON       : JANUARY 09, 2013.              PRONOUNCED ON : FEBRUARY 01,2013. JUDGMENT  :   By this appeal filed under Section 37 of the Arbitration And Conciliation Act 1996 ( for short herein after referred as 'the Act'), the Government  seeks to challenge an order and judgment dated 29 th  June 2006 passed by the learned District Judge, Ratnagiri rejecting arbitration application Asmita   1/48 ::: Downloaded on - 05/02/2013 13:37:34 :::

Maharashtra Vs HCC Ltd

Embed Size (px)

DESCRIPTION

This Bombay High Court Judgement lays down law of limitation applicable to Arbitration Proceedings.

Citation preview

  • Bom

    bay

    High

    Cou

    rt..1.. ARA6/07

    INTHEHIGHCOURTOFJUDICATUREATBOMBAY.

    CIVILAPPELLATEJURISDICTION ARBITRATIONAPPEALNO.6OF2007STATEOFMAHARASHTRA(attheinstanceofIrrigationDepartment,ExecutiveEngineer,KoynaDivisionNo.2) ...Appellant.

    V/s.

    1.HINDUSTANCONSTRUCTIONCOMPANY(LTD.(HCC).

    2.ARBITRALTRIBUNALOF:a)S.N.Jha,b)V.M.Ranade,c)B.S.Panchmukhi ...Respondents.

    MrA.A.Kumbhakoni,learnedcounsela/wMrsS.V.SonawanelearnedA.G.P.,MrShardulSinghandMrAbhayAnturkarforAppellant.

    MrAspiChinoy,seniorCounsela/wMrArifDoctori/bM/sHareshJoshi&Co.forRespondents.

    CORAM:R.D.DHANUKAJ.RESERVEDON:JANUARY09,2013.PRONOUNCEDON:FEBRUARY01,2013.

    JUDGMENT:

    By this appeal filed under Section 37 of the Arbitration And

    Conciliation Act 1996 ( for short herein after referred as 'the Act'), the

    Government seekstochallengeanorderandjudgmentdated29th June2006

    passedbythelearnedDistrictJudge,Ratnagirirejectingarbitrationapplication

    Asmita 1/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..2.. ARA6/07

    No.44of2003filedbytheGovernmentunderSection34oftheAct.

    2. TheGovernment hadchallengedanawarddeliveredbytheArbitral

    Tribunalallowingsomeoftheclaimsmadebytherespondent (forshortthe

    Government isreferredas'Government'andtherespondentisreferredas'the

    contractor'). Someoftherelevantfactsforthepurposeofdecidingthisappeal

    areasunder:

    Pursuant to the invitation of tender on 1st April 1991 by the

    Government andsubmissionofbidbythecontractoron17th June1991,the

    Government awardedtheworkof constructionof civil workof pressureand

    powerhouseinICTcontractNo.2tothecontractor.Theamountofthecontract

    awardedwasatRs.6825lakh.Boththepartiesenteredintoanagreementon20th

    March1992. Stipulateddateof commencementof theworkwas20th March

    1992.Thestipulateddateofcompletionwas19thMarch1997.TheGovernment

    grantedextensionoftimetocompletetheworktothecontractortill31stMarch

    2000.Theworkwascompletedbythecontractoron31stMarch2000.Thedate

    ofcompletionofmaintenanceperiodwas3rdOctober2000.

    3. Thedisputearosebetweenthepartiesduringexecutionof workin

    respectofhiddenexpenses. Thecontractorinvokedarbitrationclause. On27th

    Asmita 2/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..3.. ARA6/07

    April1998,firstarbitrationproceedingsstarted.Byanawarddated4thDecember

    1998,theclaimofthecontractorwaspartlyacceptedbythelearnedarbitrator.

    Pursuant to said award, the Government paid sum of Rs.10.2 crore to the

    contractor.TheGovernmentdidnotchallengethesaidaward.

    4. On3rdOctober2000,defectliabilityperiodended.Thedisputearose

    betweentheparties. Thematterwasreferredtoarbitration. ArbitralTribunal

    wasconstitutedbyappointmentofonearbitratorbyeachparty. Thepresiding

    arbitratorwasappointedbytheCentralWaterCommission,NewDelhi.

    5. On26thJune2003,thelearnedarbitratormadeanawardinfavourof

    thecontractorawardingasumofRs.17,81,25,152/. Beingaggrievedbythe

    saidaward,theGovernmentfiledarbitrationapplicationNo.44of2003on22nd

    March2003intheCourtofDistrictJudge,Ratnagirichallengingthesaidaward

    underSection34oftheAct.Byanorderandjudgmentdated29thJune2006,the

    learnedDistrictJudgedealtwithfiveobjectionsraisedbytheGovernment by

    wayof preliminaryobjectionsonlyandnegativedeachof suchobjectionand

    rejectedthesaidarbitrationapplication. TheGovernmenthasfiledthisappeal

    underSection37oftheActforimpugningtheorderandjudgmentdated29th

    June2006passedbythelearnedDistrictJudge.

    Asmita 3/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..4.. ARA6/07

    6. Though Mr Kumbhakoni, the learned counsel appearing for the

    Government wantedtoadvancearguments inrespect of variousother issues

    touching the merits of the claims, however, as the learned senior counsel

    appearingforthecontractorobjectedtosuchadditionalsubmissionswhichwere

    notmadebeforethelearnedDistrictJudge,MrKumbhakonithelearnedcounsel

    wasnotallowedtoagitatethoseadditionalissues.MrKumbhakoni,thelearned

    counsel,thereforedidnotaddressthisCourtonadditionalissuesraisedbythe

    GovernmentandaddressedthisCourtonlyonfivepreliminaryobjectionsraised

    bytheGovernmentbeforetheDistrictJudgeinthisproceedingsalso.

    7. MrKumbhakoni,thelearnedcounselsubmitsthatthecontractorhad

    accepted payment under final bill without making any protest and thus the

    contractitself ceasetoexist. Thelearnedcounselsubmitsthattheclaimsthus

    made by the contractor were not arbitrable in view of such accord and

    satisfactionduetoacceptanceoffinalbillwithoutprotest. Thelearnedcounsel

    submitsthatthecontractorhadacceptedandsigned164thandfinalbilland165th

    andfinalbillwithoutprotest.Itissubmittedthatboththesebillsweresignedby

    theauthorisedrepresentativeofthecontractorandchequesforfinalbillhadbeen

    acceptedandcreditedinthebankaccountofthecontractor.

    Asmita 4/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..5.. ARA6/07

    8. Mr Chinoy, the learned senior counsel appearing on behalf of the

    contractor,ontheotherhandsubmitsthatthesignatoryto164thand165thbills

    wasnotauthorisedtosignanysuchbillsbuthewasauthorisedtosign/acceptRA

    bills. The learnedcounsel submits that under clause60.8of theGCC, the

    contractorhadsubmittedthedraftfinalbillon30thDecember2000containing3

    parts(i) BOQitems,(ii)Extraitemsand(iii)Claims. Itissubmittedthatthe

    Governmentsdidnotpreparetherequisitedraftfinalaccountwithin2monthsas

    requiredunderClause60.8andalsodidnotpreparefinalcertificateunderthe

    saidclause.ItissubmittedthatpaymentofBOQitemsandExtraitemswasmade

    bytheGovernmentaspartof164thandfinalbillandpaymentforpricevariation

    wasmadeaspartof165thandfinalbill.Itissubmittedthathowever,inrespect

    of5claims,nofinalbillwasissuedeitheracceptingorrejectingtheclaimsmade

    bythecontractor.Itissubmittedthateventheamountsascertifiedunder164th

    and165thbillswerepaidbytheGovernmentin34instalments.Itissubmitted

    that164thand165thandfinalbillswerenotfinalbillsascontemplatedbyclause

    60.8.Thecontractordidnotissuenoclaimcertificate.Itissubmittedthatthus,

    therewasnoaccordorsatisfactiononthepartofthecontractorandthusclaims

    werearbitrable.

    9. The learned senior counsel placed reliance upon the judgment of

    Asmita 5/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..6.. ARA6/07

    Supreme Court in case of Bharat Coking Coal Ltd. Vs. Annapurna

    Construction1andmoreparticularlypara9whichreadsthus:

    9.Onlybecausetherespondenthasacceptedthefinalbill,thesamewouldnotmean that it was not entitled to raise any claim. It is not the case of theGovernmentthatwhileacceptingthefinalbill,therespondenthadunequivocallystatedthathewouldnotraiseanyfurtherclaim....

    10. Relyinguponthesaidjudgment,thelearnedcounselsubmitsthat,as

    thecontractorhadnotunequivocallystatedthathewouldnotraiseanyfurther

    claim,contractorwouldbeentitledtoraiseanyclaimandwouldnotbeestopped

    orprecludedfromraisinganyclaim.

    11. The arbitral tribunal has considered this issue in paragraph 10 to

    10.13of the impugnedaward. It was observed that procedure statedunder

    clause60.8(b)and(c)wasnotobservedbytheGovernment. Contractoralso

    didnotsubmitthe'draftstatementofFinalAccounts'asperClause60.8(a)and

    didnotpursueitwiththeGovernment forissuanceofsuchcertificateofFinal

    AccountasperClause60.8(c).TheArbitralTribunalobservedthatneitherthe

    contractornortheGovernmenthereinadheredtotheprovisionsofClause60.8.

    Ithasbeenheldthatitwouldhavebeenreasonableonthepartofthecontractor

    to expect that the five claims would be considered by the Government

    1 2004(5)ALLMR(SC)

    Asmita 6/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..7.. ARA6/07

    independentlyandaccepted,partiallyacceptedorrejectedontheirmeritsasthe

    casemaybeandifthatdecisionoftheGovernment wasnotacceptabletothe

    contractor,thedisputecouldthenbereferredtothePanelofArbitratorsasper

    Clause66SettlementofDispute.TheArbitralTribunalrenderedafindingthat

    thecontractordidnotwaiveitsrighttoreferitsclaimforadjudicationbythe

    Arbitral panel merely because they had not lodged the protest against the

    paymentbytheGovernmentoneither164thandfinalor165thorfinalbill.

    12. TheDistrictJudgehasconsideredthisissueinparagraphs33and34

    oftheimpugnedOrderandhasrejectedthecontentionraisedbytheGovernment

    afterrecordingreasons.

    13. Onperusaloftherecordsproducedbyboththepartiesandonperusal

    of theawardmadebytheArbitral Tribunal andorder passedbythe learned

    DistrictJudge,itisclearthattheprocedureunderClause60.8wasnotfollowed

    byeither party. Thus RAbills 164and165and final bills were rightly not

    consideredbytheArbitralTribunalasfinalbills.Itisnotindisputethatthere

    wasanyseparatebillpreparedinrespectoffiveclaimsmadebythecontractor.

    Inmyview,afterconsideringthefactsandthedocumentsandoninterpretation

    ofClause60.8,ArbitralTribunalhasrenderedafindingthattherewasnoaccord

    Asmita 7/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..8.. ARA6/07

    andsatisfactionandthecontractorhadnotwaiveditsrighttomakeanyclaims.

    SuchfindingsrenderedbytheArbitralTribunalandconfirmedbythelearned

    DistrictJudgearenotperverse. Inmyview,nointerferenceisthuswarranted

    withsuchfindingsrenderedbytheArbitralTribunalandupheldbytheDistrict

    Judge.

    14. The next submission of Mr Kumbhakoni, the learned counsel

    appearingfortheGovernmentisthatClaimNo.1madebythecontractorbefore

    thelearnedarbitratorwasbarredby resjudicata. Thelearnedcounselsubmits

    thatClaimNo.1oughttohavebeenreferredtoearlierArbitralPanelintheyear

    1998.Itissubmittedthatthoughtheworkinrespectofthisclaimwascompleted

    duringthependencyof earlier arbitrationproceedings, thecontractordidnot

    raisethisclaimintheearlierarbitration.

    15. Mr Chinoy, the learned senior counsel appearing on behalf of the

    contractorontheotherhandsubmitsthattherewere3Claimsreferredtoearlier

    arbitraltribunaland2Claimswereaddedlateron.Itissubmittedthatpresent

    ClaimNo.1wasnotmaturedat that timeandcouldnotbe included in that

    arbitration. ItissubmittedthatmakingpaymentforExtra/deviateditemswith

    denovorateanalysisafterapplyingthelabourmarkupandoverheadandprofit

    Asmita 8/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..9.. ARA6/07

    markup,asawardedbytheearlierarbitrationpanelwasunderconsiderationat

    variouslevelsoftheGovernment.ThecontractorinitiatedthesaidClaimon30th

    March1999andthesamewasrecommendedbytheEngineeroftheGovernment.

    TheissuewasunderconsiderationatdifferentlevelsoftheGovernmentasthe

    GovernmentdidnotpayevenattherateadoptedbytheArbitralTribunalinthe

    earlierarbitration,thecontractorinvokedarbitrationvideletterdated27th July

    2000. Itissubmittedthatthelearnedarbitratorhasrenderedafindingoffact.

    ClaimNo.1wasreferredbytheGovernmentitselfforadjudicationofthearbitral

    tribunal. The District Judge also rejected this contention advanced by the

    Government inparagraph45oftheimpugnedorder. TheDistrictJudgeheld

    that the disputes referred in 19971998were distinct than present one and

    therefore,noquestionofresjudicataarises.Thelearnedseniorcounselpointed

    outthattheonlygroundraisedinarbitrationapplicationfiledunderSection34

    onthisissuewasthattheClaimwasbarredbytheprinciplesofresjudicata.Itis

    pointedoutthatsimilargroundisraisedevenintheappealmemoinground(g).

    The learned senior counsel submits that the claim made before the arbitral

    tribunal in thesecondreferencewasadmittedlynot madebefore thearbitral

    tribunalinthefirstreference.Therewasnoadjudicationofanysuchclaiminthe

    earlierproceedings.Thequestionofapplicabilityoftheprinciplesofresjudicata

    therefore,didnotarise.

    Asmita 9/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..10.. ARA6/07

    16. Onperusaloftheimpugnedawardaswellastheorderpassedbythe

    learnedDistrict Judge, it is clear that the finding is renderedby the arbitral

    tribunal as well as the learned District Judge that Claim No.1 pertained to

    variationinproposedpercentages for the labourmarkupandoverheadsand

    profitonthesamelinesforextraitemsanddeviateditemswhichhadcroppedup

    duringtherestofthecontractwork. Ithasbeenheldthatmajorpartofthese

    itemshadbeenexecutedevenpriortoreferringtheclaimtotheearlierArbitral

    Panel.ThelearnedTribunalobservedthatClaimNo.1hadbeenincludedbythe

    Government itself foradjudicationbeforetheArbitralTribunal inthesecond

    reference.Afindingisrecordedthattheitemexcludedandclaimedinthesecond

    referenceweredifferent.TheDistrictJudgealsonegativedthecontentionofthe

    Governmentontheissuewhilerecordingdetailreasons. Inmyview,asClaim

    No.1madeinthepresentproceedingswasnotclaimedadmittedlyintheearlier

    arbitrationproceedings,therewasnoadjudicationonsuchclaimbytheArbitral

    Tribunal,andthus questionofapplicabilityofprinciplesof resjudicata didnot

    arise. The only ground raised by the Government in its application under

    Section34beforetheDistrictJudgeandinthisappealmemofiledunderSection

    37of theAct, it is urgedthat theclaimwasbarredbytheprinciplesof res

    judicata.Inmyview,thereisnomeritinthepleaoftheGovernmentthatClaim

    No.1isbarredby resjudicata andthus,thisplearaisedbytheGovernment is

    Asmita 10/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..11.. ARA6/07

    rejected.

    17. ThenextsubmissionurgedbyMrKumbhakoni,thelearnedcounselfor

    theGovernmentisthattheclaimsarebarredbylawoflimitation.Itissubmitted

    thattheworkofpressureshaftexcavationwasstartedon9thJuly1993andwas

    completedon2ndSeptember1997. Thecontractorreferredthedisputeagainst

    item No.3 to the Executive Engineer on 10th February 1997 and invoked

    arbitrationon20th November2011. AsfarasworkofTransformerHallArch.

    Concrete is concerned, it is submittedthat thesaidworkwasstartedon23rd

    October 1992 andwas completed on19th February 1994. The dispute was

    referred in respect of this item to Executive Engineer on 14th October 1996

    whereasarbitrationwasinvokedon1stJune2001.AsfarasworkofTransformer

    Hallexcavationisconcerned,itissubmittedthatthesaidworkwasstartedon

    16thJuly1992andwascompletedon31stMarch1995,whereasissuewasraised

    beforetheExecutiveEngineeron4thJune2001.ItissubmittedthatasperClause

    66Aof theGeneral Conditions of Contract, in caseof dispute, thecontractor

    ought to have promptly asked the Engineer's Representative in writing, for

    writtendecisionandtheEngineer'sRepresentativewouldgivethedecisionwithin

    60days.Itissubmittedthatonexpiryof60days,thecauseofactionhadarisen

    forinvokingarbitration.ItissubmittedthatuponthefailurebytheExecutive

    Asmita 11/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..12.. ARA6/07

    Engineertodecidethedisputewithin60days, thecontractoroughtto have

    appealedtotheSuperintendingEngineerwithin30days. It issubmittedthat

    afterpreferringthedisputetoExecutiveEngineer,contractorwaitedfor3years

    butdidnotexercisehisrighttofileanappeal.ItissubmittedthatitemNos.3,4

    and5 wereinexistenceintheyear1998whenthefirstarbitrationtookplace.

    The learned counsel placed reliance upon Article18 PartI of schedule to

    LimitationAct1963.ItissubmittedthatasperArticle18ofLimitationAct,asno

    timehasbeenfixedforpayment,theperiodoflimitationis3yearscommencing

    fromthedatewhentheworkwascompleted. Itissubmittedthatinrespectof

    ClaimNos.3,4and5,theworkwascompletedmuchpriorto3yearsbeforethe

    arbitration clause was invoked by the contractor. The learned counsel

    demonstratedfromtablereferredinwrittensubmissions,thedateofcompletion

    ofwork,referencemadetoExecutiveEngineer,rejectionofExecutiveEngineer;

    reference made to Superintending Engineer, rejection by Superintending

    Engineer; reference made to Chief Engineer and rejection of Claim by Chief

    Engineerandalsothedateofinvokingarbitration.Thesaidtableisreproduced

    asunder:

    Asmita 12/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..13.. ARA6/07

    Claim

    Nos.

    Work

    completed

    Ref.to

    EE

    Rej.by

    EE

    Ref.to

    SE

    Rej.by

    SE

    Ref.To

    CE

    Rej.By

    CE

    Arbitrationinvoked

    3 02.09.97 10.02.97 17.07.00 03.08.00 22.09.00 12.10.00 08.11.00 20.11.00

    4 19.02.94 14.10.96 04.11.00 27.02.01 12.04.01 10.05.01 21.05.01 01.06.01

    5 31.03.95 14.10.96 19.09.00 27.02.01 12.04.01 10.05.01 25.05.01 04.06.01

    Article18 and Article55 of PartII, Article113 of PartX and

    Article137ofPartIIoftheLimitationActreadasunder:

    Art. Descriptionofapplication Periodof

    limitation

    Timefromwhichperiodbeginstorun

    18 Forthepriceofworkdonebytheplaintiffforthedefendantathisrequest, wherenotimehasbeenfixedforpayment.

    Threeyears When the work isdone.

    55 For compensation for the breach of anycontract, express of implied not hereinspeciallyprovidedfor.

    Threeyears Whenthecontract isbroken or (wherethere are successivebreaches) when thebreach in respect ofwhich the suit isinstituted occurs or(where the breach iscontinuing when itceases).

    113 AnysuitforwhichnoperiodoflimitationisprovidedelsewhereinthisSchedule.

    Thereyears Whentherighttosueaccrues.

    Asmita 13/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..14.. ARA6/07

    137 Anyotherapplicationforwhichnoperiodoflimitation is provided elsewhere in thisdivision.

    Threeyears When the right toapplyaccrues.

    18. MrKumbhakoni,thelearnedcounselsubmitsthatoncecauseofaction

    had commenced, it did not stop. It is submitted that merely because the

    representationand/orClaimwasmadebythecontractorbeforevariousofficers

    were pending andwere not decided, cause of action would not stop. The

    learnedcounselpressedintoserviceSection9oftheLimitationActinsupportof

    thisplea.ThelearnedcounselplacedrelianceuponthejudgmentofthisCourt

    decidedon9thOctober2012incaseofAdityaBirlaChemicals(India)Ltd.Vs.

    TataMotorsLtd.2inArbitrationPetitionNo.1027of2011deliveredbythisCourt

    (R.D.Dhanuaka,J.)andmoreparticularlyparagraphs18an19whichreadthus:

    18. InmyviewclaimmadebytheRespondentwasaclaimsimplicitorforrecovery of additional lease rent by virtue of disallowance of depreciation byassessingofficer.Inmyview,Article54oftheScheduletoLimitationActdoesnotapplytoamoneyclaim.Inmyview,therelianceplacedbythelearnedArbitratoronArticle54whilerejectingthepleaoflimitationistotallyperverseandwithoutapplicationofmind. ThelearnedArbitratorhasmisdirectedbyapplyingwrongarticleofScheduletolimitation. InmyviewtheLearnedArbitratorhasdecidedcontrarytosubstantiatelawinforceinIndia.AwardiscontrarytoSection28(a)oftheArbitrationandConciliationAct,1996andisthusinconflictwithpublicpolicy.Inmyview,sincetheclaimmadebytheRespondentwasbarredbythelawoflimitationasonthedateofthereceiptofnoticeofinvokingarbitrationclause,itwasdutyoftheLearnedArbitratortorejectsuchtimebarredclaim.

    19. InmyviewrighttosueaccruedwhenclaimfordepreciationmadebyRespondent was rejected on 31st March, 2004 and raising of demand by theRespondentbyissuingdebitnoteon19th June,2006andrefusaltopaythesaiddemandbythePetitioneron17thAugust2006wouldnotcommencefreshperiod

    2 MANU/MH/1642/2012

    Asmita 14/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..15.. ARA6/07

    of limitation, whichhadalreadycommencedon31st March, 2004. InviewofSection9oftheLimitationAct,1963,oncetimeisbeguntorun,nosubsequentdisabilityorinabilitytoinstituteasuitormakeanapplicationstopsit.Oncetimestarts running, it does not stop. Limitation is not extendedunless there is anacknowledgmentofliabilityorpartpayment.ItisnotthecaseoftheRespondentthatthePetitioneracknowledgeditsallegedliabilityortherewasanypartpaymentmadebythePetitionerafter31stMarch,2004.Inmyview,correspondencesdoesnotextendtheperiodoflimitation.

    19. MrKumbhakoni, the learnedcounsel alsoplacedrelianceuponthe

    JudgmentofSupremeCourtincaseofJ.C.Budhrajavs.Chairman,OrissaMinig

    CorporationLtd.AndAnother3andmoreparticularlyparagraphs25and26in

    supportofhispleathatlimitationforasuitiscalculatedasonthedateoffilingof

    suit,whereasincaseofarbitration,limitationoftheClaimistobecalculatedon

    thedateonwhichthearbitrationisdeemedtohavebeencommenced.

    25. The learned Counsel for the Government submitted that thelimitationwouldbeguntorunfromthedateonwhichadifferencearosebetweentheparties,andinthiscasethedifferencearoseonlywhenOMCrefusedtocomplywiththenoticedated4.6.1980seekingreferencetoarbitration.Weareafraid,thecontentioniswithoutmerit.TheGovernmentisobviouslyconfusingthelimitationforapetitionunderSection 8(2)oftheArbitrationAct,1940withthelimitationfortheclaimitself.Thelimitationforasuitiscalculatedasonthedateoffilingofthesuit.Inthecaseofarbitration,limitationfortheclaimistobecalculatedonthedateonwhichthearbitrationisdeemedtohavecommenced.

    26. Section 37(3)oftheActprovidesthatforthepurposeofLimitationAct, anarbitration isdeemedtohavebeencommencedwhenonepartytothearbitration agreement serves on theother party thereto, a notice requiring theappointmentofanarbitrator.Suchanoticehavingbeenservedon4.6.1980,ithastobeseenwhethertheclaimswereintimeasonthatdate.Iftheclaimswerebarredon4.6.1980,itfollowsthattheclaimshadtoberejectedbythearbitratoron the ground that the claims were barred by limitation. The said period hasnothingtodowiththeperiodoflimitationforfilingapetitionunderSection8(2)oftheAct.InsofarasapetitionunderSection8(2),thecauseofactionwouldarise

    3 (2008)2SupremeCourtCases444

    Asmita 15/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..16.. ARA6/07

    when the other party fails to comply with the notice invoking arbitration.Therefore,theperiodoflimitationforfilingapetitionunderSection8(2)seekingappointmentofanarbitratorcannotbeconfusedwiththeperiodoflimitationformaking a claim. The decisions of this Court in Inder Singh Rekhi v. MANU/SC/0271/1988 : Delhi Development Authority [1988]3SCR351 , PanchuGopal Bose v. MANU/SC/0385/1994Board of Trustees for Port of Calcutta[1993]3SCR361 and Utkal Commercial Corporation v. MANU/SC/0028/1999 : CentralCoalFields[1999]1SCR166alsomakethispositionclear.

    20. The learned counsel submits that limitation for seeking an

    appointmentofanarbitratorcannotbeconfusedwithperiodof limitationfor

    makingaclaim.ItissubmittedthatthelearnedarbitratoraswellastheDistrict

    Judgehavemixedthetwoseparatearticlesoflimitationi.e.applicabletoClaims

    andformakingapplicationforappointmentofarbitrator. Thelearnedcounsel

    submitsthatthelearnedDistrictJudgehasplacedrelianceuponArticle137of

    ScheduleI to the Limitation Act and also Article 55 which are not at all

    applicabletotheClaimsmade. ItissubmittedthatArticle137appliestothe

    applicationinCourtandnottotheClaim.Itissubmittedthattherewasnoclaim

    forcompensationbeforethelearnedarbitratorwhichwouldfallunderArticle55.

    The learned counsel then placed reliance upon the Judgment of this Court

    delivered on 16th December 2011 in case of Maharahshtra State Power

    GenerationCo.Ltd.Vs.M/s.GeoMillerCo.Pvt.Ltd.inArbitrationPetition

    No.466of2006andmoreparticularlyparagraphs2to8whichreadthus:

    2.Therelevantfactsare,thePetitionerhadfloatedatenderforthedesign,manufacture, supply, erection, testing and commissioning of the prewater

    Asmita 16/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..17.. ARA6/07

    treatment plant, MSEB Chandrapur Thermal Power Station, Unit 6 andadvertisement in that behalf was published by MSEB in the year 1987. TheRespondent participated in the bid and the contract was awarded to theRespondent.DisputearosebetweenthepartieswithregardtocertainclaimsoftheRespondentforextraworkcarriedoutbytheRespondent.ItisanadmittedpositionthattheArbitrationclausewasinvokedbytheRespondentbyletterdated2712001.BeforetheArbitrator,oneoftheobjectionsraisedonbehalfofthePetitionerwasthatthereferenceisbarredbythelawoflimitation. ItisalsocommongroundbeforemethatsofarasthepaymentforthecivilworkdonebytheRespondentisconcerned,thepaymenthasbeenmade.TheclaimwhichhasbeenawardedbythelearnedArbitratorisinrelationtothepriceoftheextraworkcarriedoutbytheRespondent.BeforethelearnedArbitrator it wasclaimedonbehalfofthePetitionerthattheextraworkinrelationtowhichtheclaimhasbeenmadewascompletedon1561992andtheplantwashandedovertothePetitioneron2481994.Thereafter,theRespondentmadeclaimforthepriceoftheextraworkandthatclaimwasrejectedbyletterdated10101995.TheRespondentinvokedarbitrationclauseandmadetheclaimon2712001,andtherefore,itwasclaimedthatitisbarredbythelawoflimitation. ThelearnedArbitratorhasconsideredthisobjectioninhisaward. Heacceptedthatthoughit isclearthattheworkwascompletedon1561992,thattheplantwashandedoverbytheRespondenttothePetitioneron2481994andthatthoughtheclaimswererejectedon10101995,accordingtothelearnedArbitratorasthefinalbillwasnotsubmittedtilltheyear2000andasthecorrespondencebetweenthepartieswasgoingon,causeofactionforinvokingthearbitrationwouldnotarisetill16thDecember,2000. ItisthecaseofthepresentRespondentthatthefinalbillwaspreparedon16122000.

    3.ThelearnedCounselappearingforthePetitionersubmitsthatthelearned ArbitratorfailedtoseethattheperiodoflimitationforinvokingthearbitrationclausewillbegovernedbyArticle18oftheScheduleoftheLimitationAct. According to the learned Counsel, the cause of action for invoking thearbitrationclausewillarisewhentheworkforthepriceofwhichthearbitrationclausehasbeeninvokedwasdoneandthat was in the year 1992 andtherefore,invocationofthearbitrationclauseinJanuary,2001isbarredbythelawofLimitation.ThelearnedCounselreferringtotheprovisionsofSection9oftheLimitationActsubmittedthatoncetheperiodoflimitationiscommence,itwillruncontinuouslyandtherefore,merelybecausecorrespondencewasgoingonbetweenthepartiesinrelationtotheamounttobepaid,runningoftheperiodoflimitationwillnotstop.ThereferencehastobemadebytheRespondentwithinaperiodofthreeyearsfromthedateonwhichtheworkwascompleted.

    4. The learned Counsel appearing for theRespondent,ontheotherhand,relyingonseveraljudgmentsincludingthejudgmentofthelearnedsingleJudgeofthis court inthecaseofShri NyaneshwaBhiku Dhargalkar v/s.ExecutiveEngineer, 1999(3)RAJ(B0m)submittedthat it is Article 137of theLimitationActwhichappliesinthepresentcaseandthattherighttoapplywill

    Asmita 17/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..18.. ARA6/07

    accruewhenthedisputebetweenthepartiesarose.AccordingtothelearnedCounseltill thenegotiationsbetweenthepartiesweregoingonandastherewasnodenialtomakethepaymentintheyear1992,thecauseofactionwillnotaccrueandthereforethearbitrationclausewasinvokedwithintheperiodoflimitation.ThelearnedCounselalsoreliesonthejudgmentofthelearnedsingleJudgeoftheDelhiHighCourtinthecaseofPremPowerConstruction(Pvt)Ltd.v/s.NationalHydroelectricPowerCorp.Ltd.&Anr.160(2009)DelhiLawTimes610.PerusalofthejudgmentofthelearnedsingleJudgeofthiscourtinthecaseofNyaneshwar(supra)andthejudgmentofthelearnedsingleJudgeoftheDelhiHighCourtinthecaseofPremPowerConstructionLtd.(supra)showsthat both have relied on the judgment of the Supreme Court in the case ofMajor(Retd.)InderSinghRekhiv/s.DelhiDevelopmentAuthority,(1988)2SCC338. ThelearnedCounselfortheRespondentalsosubmittedthatinanycasetheperiodoflimitationwouldbegovernedbyArticle113oftheLimitationAct. Accordingtohim,thecauseofactionwillarisewhentherighttosueaccruesandtherighttosuewillaccruewhenthePetitionerrefusedtomakethepaymentfortheextraworkafterfinalbill.Thus,therighttosueaccruedintheyear1999whentherewasrefusaltomakethepayment.

    5. Now in the light of these rivalsubmissions,iftherecordisperused, it is clear fromtheaward itself that there is no disputebetween thepartiesthattheextraworkforthepaymentofwhichthepresentreferencewasmade was completed on 1561992. There is also no dispute that thePetitioner rejected theclaimmadebytheRespondent for extra workby letterdated10101995.ThelearnedArbitratorhasreferredtothisaspectofthematterinparagraph21oftheawardandhasobservedthus:

    EveniftherewasrejectionoftheClaimantsclaimforextraworkon10101995assubmittedbythemthelimitationcannotbesaidtohavecommencedfromthatdate,ifregardbehadtothefactthatevenaccordingtotheRespondentsthefinalbillwaspreparedaslateason16thDecember,2000.

    Thus,accordingtothelearnedArbitratorthecauseofactiondoesnotaccrueoncompletionofthework.Itdoesnotaccrueevenonrejectionoftheclaim,butitaccrueswhenthefinalbillisprepared.

    6.OnbehalfofthePetitionerrelianceisplacedonArticle18oftheLimitationAct.ThatArticlereadsasunder:

    (18)Forthepriceofworkdonebytheplaintiffforthedefendantat hisrequest, wherenotimehasbeenfixedforpayment.ThePeriodoflimitationisthreeyearsandthetimebeginstorunwhentheworkisdone.

    7.PerusaloftheabovequotedArticleshowsthatwhenasuitistobe instituted for recovery of the price of the work done by the Plaintiff for the

    Asmita 18/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..19.. ARA6/07

    Defendant,andwhenthereisnotimefixedforpaymenttobemade, thecauseofactionforinstitutingthesuitariseswhentheworkiscompletedandthesuithastobeinstitutedwithinaperiodofthreeyearsfromtheaccrual ofcauseofaction.ItisclearfromtherecordthatthepresentdisputewhichwasreferredtoarbitrationisforrecoveryofthepriceoftheextraworkdonebytheRespondentforthePetitionerattherequestofthePetitionerandtherewasnotimefixedformakingthepayment. Therefore,accordingtothisArticle,thecauseofactionwillaccruewhentheworkisdone. Thelearned CounselappearingfortheRespondentreliedonArticle113oftheLimitationAct.

    Article113readsasunder:

    113.Anysuitforwhichnoperiodoflimitationisprovidedelsewherein the Schedule, the period of limitation is three years and the timebeginstorunwhentherighttosueaccrues.

    8.PerusaloftheaboveArticlemakesitclearthatthisArticlecomesintoplayonlyonafindingthatforinstitutionofasuitfortheclaimwhichisinvolvedinthepresentmatter,thereisnoperiodoflimitationprovidedelsewhereintheschedule.Therefore,unlessafindingisrecordedthatArticle18doesnotapply,Article113cannotapply.IdonotseeanyreasonwhyArticle18willnotapplytothepresentdispute,becausethepresentdisputeisinrelationtothepriceoftheworkdonebytheRespondentforthePetitioner.ThelearnedCounselfortheRespondentalsocouldnotgiveanyreasonwhyArticle18willnotapply.Thus,astheworkwascompletedintheyear1992,thecauseofactionintermsofArticle18willaccruein1992andthereforethereferencewillhavetobemadewithin a period of 3 years from 1992 unlessaccordingtoRespondentthetimegetsextendedbecauseof any acknowledgement etc.Admittedlyneitherarbitrationclauseisinvokedwithinthreeyearsfrom1992noranyextensionoftheperiodoflimitation is claimed by the Respondent,and therefore the claimwill be barred by the lawof limitation. What isinterestingisthatthequestionbeforethelearnedArbitratorwaswhethertheclaim was made within the period oflimitation. ThelearnedArbitrator has recorded a finding that the claim is not barred by the law oflimitation, but in the entire award there is no reference to any Article in theScheduleoftheLimitationAct,whichappliestothepresentcase.Inmyopinion,thisisanimpossibility.AnargumentastowhetheraclaimismadewithintheperiodoflimitationhasalwaystobemadewithreferencetosomeArticleintheScheduleoftheLimitationAct,withoutreferringtoanyarticleintheScheduleoftheLimitationAct,afindingeitherthattheclaimisbarredbylimitationoritisnotsobarredisimpossibletoberecorded.

    SofarasapplicationofArticle137isconcerned,that Article is in PartII,relating to applications. For invoking the arbitration clause the limitationprovidedbytheLimitationActformakingapplicationwillnotapply,thelimitationprovidedbythescheduleforinstitutionofasuitwillapply. ThelearnedsingleJudgeofthisCourtinhisjudgmentinNyaneshwarcase(supra)andthelearned

    Asmita 19/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..20.. ARA6/07

    singleJudgeoftheDelhiHighCourtinthecaseofPremPowerConstructionLtd.(supra)havereliedonjudgmentoftheSupremeCourtinthecaseofInderSinghRekhi,referredtoabove.PerusalofthatjudgmentoftheSupremeCourt showsthat theretheSupremeCourtwasdealingwiththeapplicationmadeunderSection20ofArbitrationAct,1940,andasunderSection20 oftheArbitrationAct,1940anapplicationwastobemadetothecourt,obviouslyArticle137oftheLimitationActwillapply.Butintheschemeofthe1996Actnosuchapplicationiscontemplatedtobemadetoanycourtforinvokingthearbitrationclause. PerusaloftheprovisionsofSection 21 of the Arbitration ActshowsthatArbitralproceedingscommence,unlessthereisanagreementcontrarybetweentheparties,onthedateonwhicharequestforreferenceofthedisputetoarbitrationisreceivedbytheRespondent.The1996Act doesnotcontemplateanyapplicationtobemadetothecourtfor invokingthearbitration application and for commencement of arbitration proceedings.Subsection 2 of Section43of theArbitrationAct lays downthat for thepurposeoflimitationActanarbitrationshallbedeemedtohavecommencedonthedatereferredto inSection21. Therefore, it is clear that invocationof thearbitrationclausehastobemadewithintheperiodoflimitationprovidedbytheLimitationActforinstitutionofasuitonthesamecauseofaction.SofarasanapplicationtobemadeunderSection11isconcerned,thatapplicationisnotforinvokingthearbitrationclause.Thatapplicationisforappointment of arbitrator, after invoking the arbitration clause.Invocation of the arbitration clause precedes an application under Section 11.Therefore,whenanapplicationunderSection11ismade,thatapplicationhastobemadewithintheperiodoflimitation,whichisprovidedbytheLimitationActforinstitutionofthesuitonthatcauseofaction.AnapplicationunderSection11cannot be made after expiry of the period oflimitationprovidedforinstitutionofsuitforrecoveryoftheclaim.TheHonbletheChiefJusticeorhisdesignatewillhavetomakeaninquirytofindoutwhethertheappointmentofArbitratoratthisjuncturewouldbenecessaryasaperiodoflimitationisover.TheSupremeCourtinitsjudgmentinthecaseofNationalInsuranceCo.Ltd.v/s.M/s.BogharaPolyfabPvt.Ltd.,AIR2009SC170,hasreferredtotheissueswhichhavetobedecidedbytheChiefJusticeorhisdesignateunder Section11andtheissueswhichcanbeleftfordecisionbytheArbitrator.Oneoftheissues,accordingtotheSupremeCourtthathastobedecidedbytheHonbleChiefJusticeorhisdesignateunderSection11iswhethertheclaimisadead claim or a live claim. It means that if an objection is raised, whenapplicationunderSection11ismade,thatinvocationofthearbitrationclauseinthatcasehasnotbeenmadewithintheperiodoflimitation,thenthatquestionhastobedecidedbytheChiefJusticeorhisdesignate.ThequestiontobeconsideredatthattimeisnotwhetheranapplicationunderSection11ismadewithintheperiodoflimitation,butwhethertheinvocationofthearbitrationclausewasmadewithintheperiodoflimitation.Inmyopinion,therefore,thereisnoquestionofprovisionsofSection137applyinginsofarasinvocationofthearbitrationclauseandcommencement of the period oflimitationisconcerned.Sofarasthepresentcaseisconcerned,tomy

    Asmita 20/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..21.. ARA6/07

    minditisclearthatArticle18oftheLimitationActappliesandthereforeastheinvocationoftheArbitrationclauseisnotwithinperiodofthreeyearsfromthedateofcompletionofthework,whichwasintheyear1992,theclaimwasclearlybarredbythelawoflimitation.

    21. RelyinguponthisJudgmentofthisCourt,thelearnedcounselsubmits

    that Article18 was applicable to the claims made by the contractor andnot

    Article55or Article 137as sought to beappliedby the District Judge. The

    learnedcounselsubmitsthatboththeseissuesareconsideredbythisCourtand

    thefactsofthiscaseareidenticaltothefactsofthecaseincaseofMaharashtra

    StatePowerGenerationCo.Ltd.(supra)andthesaidJudgmentisthusbinding.

    22. ThelearnedcounselalsoplacedrelianceupontheJudgmentofPunjab

    AndHaryanaHighCourtincaseof JullunderImprovementTrust,Jullunder

    Vs.KuldipSingh4andmoreparticularlyparagraphs4and5whichreadthus:

    4. Themaincontroversyinthisappealis:whetherthesuitoftheplaintiffwanwithintimeornot?ItisthecommoncaseofthepartiesthatitisArticle18,Limitation Act, 1963, which would govern the plaintiffs case. It provides alimitationofthreeyearsfromthetimetheworkisdone.Thepresentsuitwasfiledon 921971. According to the plaintiff the cause of action arose to him on14121967,whenthepaymentofthefinalbill,ExhibitD.19,wasreceivedbyhimunderprotestwhereasthecaseofthedefendantisthattheperiodofthreeyearswouldcommence fromthedatetheworkwasdonewhichaccordingto it wascompletedon2891967, asadmittedbytheplaintiff himself vide, Exhibit D.4,dated2891967,writteninthisownhandwhereinhehadstatedthat90feetwideroadunder84acresschemewascompleteand,therefore,hisfinalbill,bepreparedaccordingly.Inanycase,accordingtothedefendant,inthefinalbill,ExhibitD.19,thecertificatetotheeffectthatnecessarydetailedmeasurementshavebeentakenasrecordedintheMeasurement BookNo. 44, wasgivenon7101967, bythe

    4 AIR1984PunjabAndHaryana185

    Asmita 21/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..22.. ARA6/07

    EngineerinchargeMohinderSingh,whoappearedasD.W.7.Thus,itwasarguedonbehalfofthedefendingthatevenafterthatdate.i.e.7101967,thepresentsuitfiledon921971,evenafterallowingthenoticeperiodoftwomonthswasbarredbytime.AccordingtothetrialCourt,thecauseofactionwouldarisetotheplaintiff for the price of the work done only on furnishing of the completioncertificate bytheEngineer incharge. Thecertificate of theEngineer incharge,accordingtothetrialCourtdidnotbearanydate.Since,accordingtothetrialCourt thepayment of the lastbill wasreceivedbytheplaintiff on14121967,under protest, the periodof limitation will start from that date and that afterallowing the notice period of two months, the suit filed by the plaintiff on921971,waswithintime.ThetrialCourtalsofoundthattheplaintiffprosecutedwithduediligenceanothercivilproceedingfoundeduponthesamecauseofactioninaCourtwhichcouldnotgivethereliefand,therefore,hewasentitledtoget,theperiodspentinprosecutingthoseproceedingsexcludedunderS. 14,LimitationAct,(hereinaftercalledtheAct).

    5. After hearing the learned counsel for the parries, I am of theconsideredopinionthattheplaintiffssuitwasbarredbytime.

    23. Mr Chinoy, the learned senior counsel appearing on behalf of the

    contractor on the other handsubmits that Article18 is not applicable to the

    claimsmadebythecontractor. Thelearnedseniorcounselsubmitsthatthe

    claimsmadebeforethearbitraltribunalwereforenhancementofthepricefor

    theworkdoneandthusArticle113ofSchedule1ofLimitaitonActwouldapply.

    The learned senior counsel placed reliance upon the Judgment in case of

    GannonDunkerley AndCo. Ltd. v. Union of India5 and more particularly

    paragraphs2to11whichreadthus:

    2. The Sindri Factory Buildings were tobeconstructedunder theadvice andguidance of M/s. Chemical Construction Corporationof NewYork. That Firmmadedelayinsupplyingthedrawingsandspecificationswhichinvolvedworkofa

    51969(3)SupremeCourtCases607

    Asmita 22/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..23.. ARA6/07

    complicatednaturenotincludedintheoriginalcontract. TimeforcompletionoftheworkwasonthataccountextendedtillFebruary26,1950.

    3. On September 20, 1950 the Government Company made a demand forpaymentofanenhancedrateof421/2%overthebasicratesstipulatedundertheoriginalcontract.Thisclaimwasmadeonfivegrounds:

    1.thattherewasasubstantialdeviationinthenatureofworkofwhichthedetailedworkdrawingsweresuppliedtotheGovernment Companyafterthedateofthecontract.Theworkinvolvedwasofacomplexnaturerequiringhighlyskilledlabour,andthatadditional labourandmaterialsnotcoveredbythecontractrateswererequired;

    2. thattherewasgreatincreaseinthepriceofmaterialsandlabouronaccountofundueprolongationoftheperiodofwork;

    3.thattherewasincreaseinthecostoftransportationonaccountofriseinthepriceofpetrolandincreaseinrailwayfreight;

    4.thattheGovernmentofIndiaenteredintoothercontractsincidentaltotheconstructionoftheSindriFactoryatsubstantiallyhigherrateswhichdirectly affected the cost of labour and materials of the GovernmentCompanywhohadtocompetewiththeothercontractors;

    5. thatadditionalworkorderedtobedoneinvolvedinmanyinstancesquantityofworkseveraltimestheworksetoutinthecontract.

    4. ByhisletterdatedSeptember13,1950,theAdditionalChiefEngineer

    rejectedtheclaim.InSeptember1954thedisputesrelatingtotheclaimforriseincostofmaterialandlabourduetodelayinsupplyingdetailedworkdrawings,theclaimarisingfromriseinpriceofpetrolandforincreaseinthecostofmaterialandlabourduetoothercontractorsworkingonthesite,werereferredtoarbitration,butnottheclaimsforrevisionofratesduetocomplexnatureoftheworkandincrease in the quantity of work. The arbitrator rejected the claims of theCompanyinrespectofthematterswhichwerereferred.

    5. ThereaftertheGovernmentCompanyfiledasuitonAugust9,1956,against theUnionofIndia,for adecreeforRs.3,62,674/9/6beingtheamountclaimedattherateof421/2%abovethecontractrate,inthealternative,adecreefor Rs.2,44,000/ being the amount claimed at the rate of 28.1% above thecontract rate as recommended by the Executive Engineer, and in the furtheralternative,adecreeforRs.1,36,222/attherateof18.17%abovethecontractrateascertifiedbytheSuperintendingEngineer. TheUnionofIndiacontended,interalia,thattheclaimwasbarredbythelawoflimitation.

    6. TheTrial Court held that theclaimwasnot barredby the lawof

    Asmita 23/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..24.. ARA6/07

    limitation and decreed the claim for Rs. 1,36,222/ as certified by theSuperintending Engineer. Against the decree passed by the Trial Court theGovernmentCompanyaswellastheUnionofIndiaappealedtotheHighCourt.

    7. Before the High Court, in support of the appeal only the plea oflimitationwaspressedonbehalfoftheUnionofIndia.IntheviewoftheHighCourttheclaimwasgovernedeitherbyArticle56orbyArticle115oftheFirstScheduletotheLimitationAct,1908,andthesuitnothavingbeenfiledwithinthreeyearsofthedateonwhichtheworkwasdoneandinanyeventofthedateon which the claimwas rejected was barred. The Government Company hasappealedtothisCourtwithcertificate.

    8. TheGovernment Companyhadundertakenunderthetermsofthecontracttodospecificconstructionworkat"basicrates".TheEngineerinchargewasbythetermsofClause12oftheagreementcompetenttogiveinstructionsforwork not covered by the terms of the contract, and it was provided thatremunerationshallbepaidattheratefixedbytheEngineerinchargeforsuchadditional work, and in case of dispute the decision of the SuperintendingEngineer shall be final. It is common ground that the claim made by theGovernmentCompanywasnotcoveredbythearbitrationagreement,andonthataccount it was not referred to the arbitrator. The claim in suit related to therevisionofratesduetothecomplexnatureoftheworkandduetoincreaseinthequantity of work and also grant of contracts to other competing parties atsubstantiallyhigherratesandotherrelatedmatters.

    9. Article56oftheFirstScheduletotheIndianLimitationAct, 1908,prescribesaperiodofthreeyearsforasuitforthepriceof, workdonebytheplaintiff for the defendant at his request, where no time has been fixed forpayment,andtheperiodoflimitationcommencestorunfromthedatewhentheworkisdone.AsuitisgovernedbyArticle56ifitarisesoutofacontracttopaythepriceofworkdoneattherequestofthedefendant.Theclaiminthepresentcaseisforpaymentatanadditionalrateoverthestipulatedrateinviewofchangeincircumstances,andnotforpriceofworkdonebytheGovernmentCompany.ItistruethatadditionalworkwasdoneattherequestoftheEngineerincharge,buttheclaiminsuitwasnotforthepriceofworkdonebutforenhancedratesinviewofalteredcircumstances.

    10. Article115oftheFirstScheduletotheLimitationActisaresiduaryarticledealingwiththeclaimforcompensationfor thebreachofanycontract,expressorimplied,notinwritingregisteredandnotspeciallyprovidedfor,intheFirst Schedule. The period of limitation in such cases is three years and itcommences to runwhen thecontract is broken, or where there aresuccessivebreacheswhenthebreachinrespectofwhichthesuitisinstitutedoccurs,orwherethe breach is continuing when it ceases. The suit filed by the Government

    Asmita 24/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..25.. ARA6/07

    Companyisnotasuitforcompensationforbreachofcontractexpressorimplied:itisasuitforenhancedratebecauseofchangeofcircumstances,andinrespectofworknotcoveredbythecontract.TheadditionalworkdirectedbytheEngineerincharge when carried out may be deemed to be done under the terms of thecontract:buttheclaimforenhancedratesdoesnotariseoutofthecontract:itisinanycasenotaclaimforcompensationforbreachofcontract.

    11. TheclaimisthereforenotcoveredbyanyspecificarticleundertheFirstSchedule,andmustfallwithinthetermsofArticle120.TheSolicitorGeneralappearingonbehalfoftheUnionofIndiacontendedthateveniftheclaimfallswithin the terms of Article 120 of the Limitation Act, it was barred, for, theGovernmentCompanyhadinthesuitmadeaclaimforworkdonemorethansixyearsbeforetheinstitutionofthesuit.CounselsubmittedthatunderArticle120theperiodoflimitationcommencestorunfromthedateonwhichthedefendantobtainsthebenefitoftheworkdonebytheplaintiff.ButunderArticle120oftheLimitationActtheperiodofsixyearsforsuitsforwhichnoperiodoflimitationisprovided elsewhere in the Schedule commences to run when the right to sueaccrues.Inourjudgment,thereisnorighttosueuntilthereisanaccrualoftherightassertedinthesuit,anditsinfringement,oratleastaclearandunequivocalthreattoinfringethatrightbythedefendantagainstwhomthesuitisinstituted;Bolov.KokanandOrs.

    24. ThelearnedcounselsubmitsthattheSupremeCourthadconsidered

    Article120oftheLimitationAct,1908andArticle56whicharecorrespondingto

    Article113andArticle18 to the first schedule to LimitationAct 1963. It is

    submittedthatafterconsideringtheseArticles,theSupremeCourtheldthatthe

    periodof6yearsforsuitsforwhichnoperiodoflimitationisprovidedelsewhere

    intheSchedulecommencestorunwhentherighttosueaccrues.Itisisheldthat

    therewasnorighttosueuntiltherewasaccrualoftherightassertedinthesuit,

    anditsinfringement,oratleastaclearandunequivocalthreattoinfringethat

    rightbythedefendantagainstwhomthesuitisinstituted.Itissubmittedthat

    theSupremeCourthasheldthatinasuitforenhancedratebecauseofchangeof

    Asmita 25/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..26.. ARA6/07

    circumstances, and in respect of worknot coveredby thecontract, claim for

    enhancedratedidnotariseoutofcontractandwouldbethusnotgovernedby

    Article56correspondingtoArticle18underLimitationAct1963butwouldbe

    coveredbyArticle120(correspondingtoArticle113underLimitationAct1963).

    Thelearnedseniorcounselthus,submitsthatthefactsofthiscaseareidenticalto

    the factsbefore theHonourbleSupremeCourt incaseof GannonDunkerley

    (supra)andthusprinciplesoflawlaiddownbytheSupremeCourtaresquarely

    applicabletothefactsofthiscaseandarebindingonthisCourt.

    25. ThelearnedseniorcounselalsoplacedrelianceupontheJudgmentof

    RajashthanHighCourtincaseofStateofRajasthanVs.RamKishan(AIR1977

    Rajasthan165),JudgmentofAllahabadHighCourtincaseofStateofU.P.v.

    ThakurKundanSingh(AIR1984Allahabad161),JudgmentofGujratHigh

    CourtincaseofStateofGujratVs.PirojshaWadiareportedin17GujratLaw

    Reporter638; bywhichvariousHighCourtshavetakenasimilarviewwhich

    hasbeentakenbytheHonourableSupremeCourtincaseofGannonDunkerly

    andOrs(supra).

    26. Perusal of theawardindicatesthatbeforethearbitral tribunal, the

    submissionofthecontractorwasthatdisputecouldstartonlyafterrejectionof

    Asmita 26/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..27.. ARA6/07

    theclaimbytheGovernment.Itwassubmittedthattheclaimswerependingfor

    decisionandthuscauseofactionstartedonlyafterdecisionwasfinallytakenby

    theGovernment.Itwassubmittedthatlimitationcommencedfromthedateon

    whichcauseofactionhadaccrued.

    27. Thearbitraltribunalhasheldthatallthoseclaimseventhoughthere

    was specific recognisable period of start of incurring of the loss, the same

    continuedsincethenduringthecurrencyofthecontract,includingtheextended

    periodatleastforClaimNos.1and2.MajorityofthelossincurredforClaimNos.

    3,4and5wasknownwhentheitemswerenearlycompletebyMarch1998.Itis

    heldthatinrespectofClaimNos.1and2,thelosscontinuedtillthecurrencyof

    thecontract. ThearbitraltribunalthenheldthatforClaimNos.3,4and5,first

    referencetoEngineer'srepresentative(ExecutiveEngineer)wasmadeinFebruary

    1997andOctober1996andongettingnodecisionwithin60days,thecontractor

    couldhavereferredthedisputetohigherlevelandthentothe'Engineer'asper

    provisionsofClause66andinvokedthearbitrationwithin220daysatthemost.

    Itisfurtherheldthatthiscoursewasnottakenbythecontractorforthereasons

    bestknowntohim.Thecontractormighttaketheshelteroftheword'may'inthe

    contractormayappealwithin30daystoEngineer'byclaimingthatitwasnot

    obligatoryforhimtoappealincasenoreplywasgiventheExecutiveEngineer.

    Asmita 27/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..28.. ARA6/07

    Inspiteofsuchfindingrenderedbythearbitraltribunal,itisheldthatthecause

    ofarbitrationwouldbecauseofactionandtimeoflimitationshouldberecorded

    fromthedatefor respectiveclaims. Thetribunal held that all fiveclaimsin

    questionwerenottimebarredonaccountoflimitation. Itwouldbeusefulto

    extracttherelevantparagraphsonthisissuefromthearbitralawardwhichareas

    under:

    Forreferringthedisputetoarbitration,therehadtobeanarbitrationagreement(clause)andtherehadtobeadispute. Intheinstantcase,Cl66Settlementofdispute (RTD1/1034) provided for recourse to arbitration. For existence of'dispute'therehadtobean'assertion'byoneparty&'denial'bytheotherparty.'Causeofarbitration'aroseintheinstantcasewhenevertherewasrejectionofaclaimbythe 'Engineer' (ChiefEngineerKoynaProject)(RTD1/38)Rejectionofinactionbythe'Engineer'srepresentative'i.e.ExecutiveEngineer/SuperintendingEngineerdidnot, however, result into 'causeofarbitration'. Inwhichcasetheclaimanthadtoapproachthe'Engineer,furnishrequiredevidenceandonrejectionbythe'Engineer'couldinvokearbitration.

    Clause 66(b) specifically mentioned that 'Performance under thecontract shall if reasonably be possible, continue during the arbitrationproceedings. Henceclaimantcouldeitherlodgeclaimswiththerespondentandpursuethemfortheirsettlementthroughthe'Employer'bynegotiationsorcouldtaketherecourseto arbitration by following obligations/requirements underCl.66culminating into invoking thearbitration. Inall theclaimstheclaimantpreferredtotaketheearlierrecoursetobeginwithandcontinuedforquitesometime. TheclaimantapproachedsecretaryIDandDy.ChiefMinisterduringthisperiod.RecoursetoArbitrationwastakenquitelate,aftercompletionoftheworkphysically. Evenafterreferringsomeoftheirclaimsunderthiscontract totheearlier Arbitral Panel and getting Award for the same in December 1998, theclaimant continued to followthe course of negotiations & pursuations, for thereasonsbestknowntohim.

    QuestionnowbeforetheArbitralPanelwaswhethertheclaimshadbecometimebarredbecauseofthisapparentdelayonthepartoftheclaimantinnotinvokingthearbitrationearlyandpromptly. Theclaimantwassaidtohavebeensufferinglossbecauseofvariousreasonsinrespectofseveralitemsofthecontract,whichresultedintoinitiatingtheclaimsrightfromthebeginningofthecontract andcontinuedtoincurthelossforcertainperiodsincethenforsomeclaims(No.3,4&5)andtillthecompletionofthecontractforsome(ClaimNo.1).

    Asmita 28/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..29.. ARA6/07

    LossonaccountofclaimNo.2wassaidtohaveoccurredonlyduringtheextensionperiodandcontinuedtill completionof thecontract. Theclaimant couldhavepursuedtheseclaimswiththerespondent forsomereasonable timebutshouldhavegoneinforsettlementofdisputeasperCl.66eitherwhenitemsfor3claims(3,4&5)weremostlycompletei.e.after3/98orwhenthecumulativelosseswereforeseentobebeyondthecapacityoftheclaimanttopullonwithoutimpairingtheprogressofthecontractedwork,whicheverwasearlier. IFtheclaimNo.1hadbeenreferredtothearbitration(oreventotheearlierArbitral panel)claimantcouldhavegotthecompensationintime.ForclaimNo.2,issuecouldhavebeenpursuedvigorouslywiththerespondentsayduringayearorsoaftergettingthefirst extensionand failing toget favourable response (or partial response), theclaimantcouldhaveinvokedthearbitration.

    Theclaimantinall thecorrespondencehadbeenmentioningaboutincurringofheavylosses,financialcrunch,heavystrainorfinancialresourcesetc.becauseoftheseclaims.Butapparentlythefollowup/pursuationsforsettlementofclaimswasveryverypoordespiteprovisionofclauseforarbitration.Arbitratorshadhenceobservedduringthethirdmeetingthat'effortsoffollowup&pursuationoftheclaimswouldbeexpectedtoberelatedtotheamountinvolvedintheclaimsbecause, delayinsettlementofsubstantial amountofclaimwaslikelytoaffectperformanceofthecontract'.

    Itcouldnotbeascertainedfromtherecordorfromthedeliberationsduringthemeetingsastowhythislogicalandeasiercoursecouldnotbetakenbytheclaimant.Claimantscontention/argumentonthispointhadconsistentlybeenthat,withoutrejectionoftheclaimsbythe'Engineer',recoursetoarbitrationwasnotopentothem.Inalltheseclaimseventhoughtherewasspecificrecognisableperiodofstartofincurringoftheloss,thesamecontinuedsincethenduringthecurrencyofthecontract,includingtheextendedperiodatleastforclaimNos.1&2.MajorityofthelossincurredforclaimNos.3,4&5wasknownwhentheitemswerenearlycompleteby3/98.ButforclaimNos.1&2thelosscontinuedtillthecurrencyofthecontract. Questionthenwas,whatshouldbeconsideredasthestartofreckoningofthetimeoflimitation.ForclaimNos.3,4&5,firstreferencetoEngineer'srepresentative(ExecutiveEngineer)wasmadeinFeb97&Oct96.On getting no decision within 60 days, the claimant could have referred thedisputetohigherlevelandthentothe'Engineer'asperprovisionsofCl.66andinvokedthearbitrationwithinabout200to220daysatthemost.Thiscoursewasnottakenbytheclaimantforthereasonsbestknowntohim.Theclaimantmighttaketheshelteroftheword'may'inthecontractormayappealwithin30daystoEngineer'byclaimingthatitwasnotobligatoryforhimtoappealincasenoreplywasgivenbytheExecutiveEngineer.

    Therehavebeencitationsstatingthatthecauseofactionandcauseofarbitrationtobethesameforreckoningthestartoftimeoflimitation.Itwastruethatthe'causeofaction',ifitwasotherthanthe'causeofarbitration'couldnotbepinpointedasaspecificpointoftimeintheactivityoftheexecutionofthecontract

    Asmita 29/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..30.. ARA6/07

    (includingextensions).Losscontinued,negotiations/pursuationscontinued,workcontinued but 'cause of arbitration' or invoking the arbitration' were the onlyspecificeventsinthisactivity.

    HencetheArbitralPanelhadcometotheconclusionthat'causeofarbitration' would be the 'cause of action' and time of limitation should bereckonedfromthatdateforrespectiveclaims.Henceallthe5claimsinquestionwerenottimebarredonaccountoflimitations.

    Onequestionthatrequiredtobeconsideredanddecidedwasthat,shouldtheclaimantprefertodeferanddelaytheactionofinvokingthearbitrationapparentlyfornoreasonorforsomeotherreasonsbestknowntohim,everwhenprovisionofclauseforsettlementofdisputeexistedinthecontractandcontinuedtomaketherespondentsufferbecauseofanyextraliabilityonaccountofsuchavoidabledelay.Arbitralpanelhascometoaconclusionthatclaimantshouldnotbeawardedinterestontheclaimsforpastperiodattherateswhichnormally&reasonablyaclaimantwouldhavebeenentitledto.ItwasdecidedthatforclaimNos.1,3,4&5heshouldbegrantedonlypriceescalationasperTenderformulaeup to 3132000 (date of completion of the contract period) by treating thatpaymentforamountoftheseclaimswasmadeonthatdate.From142000tothedateofreferencetoarbitrationforeachclaim,interestonlyat10%(tenpercent)perannumshallonlybepaidontheescalatedamount.

    28. TheDistrictJudgehasdealtwithissueoflimitationinparagraphs35

    to37ofitsJudgment. Thecontractorarguedthatlimitationoftheperiodof

    threeyearshadtobereckonedfromthedateoffinalrejectionbythecompetent

    authorityi.e.Engineerinthepresentcase.Itwassubmittedthatinrespectof

    alltheclaims,arbitrationwasinvokedwithin30daysafterfinalrejectionbythe

    EngineerasperClause66Aofthecontract. Itwassubmittedthatwhenthe

    contract wasspreadover for a periodanddamagewas sustainedduring the

    wholeperiod, thelimitationfortotaldamageswouldcommencefromthedate

    when the period of contract ends. It was submitted that the claim for

    Asmita 30/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..31.. ARA6/07

    compensationforsuccessivecontinuingbreachesofanycontract,theperiodof

    threeyearslimitationwouldbecomputedwhenthebreachceasedtooccur.It

    wassubmittedthatdisputecouldstartonlyafterthedenialofanassertion.The

    contractorsubmittedthatlimitationwouldnotstartfromthedateofentitlement

    ofpaymentbutonwhichtheclaimwasmadebythecontractorandwasrejected

    by theGovernment andsuchrejectionwouldbetheaccrual of thecauseof

    action. Itwassubmittedthattheclaimswerependingfordecisionforyears

    together, thelimitationwouldstartonlyafterthedecisionwascommunicated.

    DistrictJudgerenderedafindingthatthecontractorcouldeitherlodgeclaims

    with the Government and pursue them for their settlement through the

    Governmentbynegotiationsorbyculminatingintoinvokingthearbitration.It

    isheldthatthecontractorpreferredtotakeearlierrecoursetobeginwithand

    continuetoquitesometime. ThecontractorapproachedSecretary, Irrigation

    DepartmentandDy.ChiefMinisterduringthatperiodandrecoursetoarbitration

    wastakenquitelateaftercompletionoftheworkphysically.TheDistrictJudge

    heldthatArticle137oftheLimitationActwouldbeinvokedinthiscase.Relying

    uponArticle137,itisheldthattheperiodoflimitationstartswhentherightto

    apply accrues under Article137. The District Judge held that the period of

    limitationforcommencinganarbitrationrunsfromthedateonwhichcauseof

    arbitrationaccruesi.etosayfromthedatewhenthecontractoracquiredeither

    Asmita 31/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..32.. ARA6/07

    rightof actionorrighttorequireanarbitrationtakesplaceuponthedispute

    concerned. It is held that cause of arbitration arose when the contractor

    becameentitledtoraisethequestion.TheDistrictJudgeheldthatClaimNos.1,

    2,3and5wereinthenatureofextraitemsandnewrateswerenecessitatedby

    thevariationinparticularworkorderedbytheGovernment.TheDistrictJudge

    held that under Article 55 of the Limitation Act, when the breach was

    continuing,thelimitationofthreeyearscommenceswhenitceases.TheDistrict

    Judgefinallyheldthatthecauseofactionwouldcommencefrom25thMay2001

    when the claim was finally rejected by the Chief Engineer. In my view,

    Article55couldnotbeattractedinrespectoftheclaimsmadebythecontractor

    fortheworkdone.ThelearnedDistrictJudge,however,hasappliedArticle55of

    theScheduletotheLimitationActtoalltheclaimswhichshowspatentillegality

    onthefactoftheJudgmentofthelearnedDistrictJudge.

    29. ThearbitraltribunalhasrenderedafindingthatinrespectofClaim

    Nos.3,4and5,theclaimcouldbesaidtohaveinitiatedwhentheconcerneditems

    wereexecutedanditcontinuedtillcompletionofeachsuchitem. Thearbitral

    tribunalalsorenderedafindingthatacontractorcouldhavepursuedClaimNo.2

    withtheGovernment for somereasonabletimebutshouldhavegone infor

    settlementofdisputeasperClause66eitherwhenitemsfor3ClaimNos.3,4and

    Asmita 32/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..33.. ARA6/07

    5weremostlycompletei.eafterMarch1998orwhenthecumulativelosseswere

    foreseentobebeyondthecapacityofthecontractortopullonwithoutimpairing

    theprogressofthecontractedwork,whicheverwasearlier.Similarlyinrespect

    of ClaimNo.2, the arbitral tribunal held that issue could have beenpursued

    vigorouslywiththeGovernment duringtheyearorsoonaftergettingthefirst

    extension and failing to get favourable response or partial response, the

    contractorcouldhaveinvokedthearbitration.Itisfurtherobservedthatthough

    thecontractorinallthecorrespondencewereallegingincurringofheavylosses,

    financialcrunch,heavystrainetc.,followup/pursuationsforsettlementofclaims

    onthepartofcontractorwasverypoordespiteprovisionofclauseforarbitration.

    Thelearnedarbitraltribunalobservedthatitcouldnotbeascertainedfromthe

    recordorfromthedeliberationsduringthemeetingsastowhythislogicaland

    easiercoursecouldbetakenbythecontractor.

    30. Thearbitraltribunalthoughrenderedafindingagainstthecontractor

    for gross delay in making a claim and pursuing it, rejected the plea of the

    Government forrejectionoftheclaimsonthegroundoflimitation. Onone

    hand,thearbitraltribunalobservedthattheGovernment shallnotsufferany

    extraliabilityonaccountofavoidabledelayonthepartofthecontractorand

    contractorshouldnotbeawardedinterestontheclaimsforpastperiodatthe

    Asmita 33/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..34.. ARA6/07

    rateswhichnormallyandreasonablyacontractorwouldhavebeenentitledto.

    Inmyview,itisclearthattheconclusiondrawnbythearbitraltribunalistotally

    inconsistentwiththefindingrenderedbythearbitral tribunal onthe issueof

    limitation. Theissueof limitationhasbeendealt withwithoutapplicationof

    mind.

    31. TheDistrictJudgehasrenderedafindinginfavourofthecontractor

    onerroneouspremisethatArticle137oftheLimitationActwasapplicabletothe

    claimsmadebythecontractor. In myview,Article55of theLimitationAct

    wouldnotapplyfortheclaimforpriceincreaseinrespectoftheworkcarriedout

    undertheprovisionsofcontract.ApplicationofArticle55totheclaimforwork

    done by the District Judge, is totally an erroneous and is on the face of it

    perverse.Article137oftheLimitationActappliestotheapplicationsandnotto

    theclaims. Inmyview,for invokingthearbitrationclause, the limitation

    providedbytheLimitationActformakingapplicationwill notapply, butthe

    limitationprovidedbythescheduleforinstitutionofasuitwillapply.ThisCourt

    hasheldthatthereisnoquestionofprovisionsofArticle137applyinginsofaras

    invocation of the arbitration clause and commencement of the period of

    limitationisconcerned.ThisCourtheldthatinrespectoftheclaimforpriceof

    extraworkcarriedoutbythecontractor,Article18oftheLimitationActwould

    Asmita 34/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..35.. ARA6/07

    applyandnotArticle137.Itisheldthatwhenasuitisinstitutedforrecoveryof

    thepriceoftheworkdonebytheplaintiffforthedefendant,andwhenthereis

    notimefixedforpaymenttobemade,thecauseofactionforinstitutingthesuit

    ariseswhentheworkiscompletedandthesuithasbeinstitutedwithinaperiod

    ofthreeyearsfromtheaccrualofcauseofaction.Itisheldthatcauseofaction

    wouldaccruewhentheworkisdone.AfterconsideringArticle113onwhichthe

    contractorhasplacedreliance,thisCourtheldthatthesaidArticlecomesinto

    playonlyonfindingthatforinstitutionofasuitfortheclaimwhichwasinvolved

    in that matter, there was no period of limitation provided elsewhere in the

    schedule.ItisheldthatonlyonafindingrecordedthatArticle18didnotapply,

    Article113couldnotapply.ThisCourtheldthatthoughthelearnedarbitrator

    hadrecordedafindingthattheclaimwasnotbarredbylawoflimitation,inthe

    entire award there was no reference to any Articles in the Schedule of the

    LimitationAct,whichappliestothatcase.ThisCourtobservedthatsuchfinding

    recordedbythelearnedarbitratorwasanimpossibility.

    32. Inmyview,refusaltopaytheamountdemandedbythepetitioner,

    wouldnotcommencefreshperiodoflimitationwhichhadalreadycommenced.

    InviewofSection9oftheLimitationAct,1963,oncetimeisbeguntorun,no

    subsequentdisabilityorinabilitytoinstituteasuitormakeanapplicationstops

    Asmita 35/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..36.. ARA6/07

    it.Oncetimestarts,itdoesnotstop.Limitationisextendedonlywhenthereis

    an acknowledgment of liability or part payment. Correspondence does not

    extendtheperiodoflimitation.

    33. Itisnotthecaseofthecontractorthattherewasanypartpayment

    madebytheGovernment inrespectoftheclaimsinquestionortherewasany

    acknowledgmentofliabilitymadebytheGovernmentinfavourofthecontractor

    inrespectofsuchclaims.Merelybecause,therewasinactionand/ordelayonthe

    partoftheofficersoftheGovernmentinconsideringand/orrejectingtheclaims

    madebythecontractor, limitationwouldnotbeextended. Thelimitationhad

    alreadycommencedwhentheworkwasdoneandthepaymentwasnotmade.It

    isnotindisputethattheworkinrespectoftheclaimsinquestionwascompleted

    morethanthreeyearspriortothedateofcontractormakingrepresentationtothe

    concernedofficersoftheGovernment. Inmyview,eveniftheofficersofthe

    Government hadnotdecidedtherepresentationand/orclaimofthecontractor

    withinthetimespecifiedunderClause66,causeofactionhadnotstopped.

    34. In myview, the arbitral tribunal as well as the District Judgehas

    mixeduptheissueoflimitationinmakingaclaimandinmakinganapplication

    totheCourtforappointmentofarbitrator. ThereferencemadebytheDistrict

    Asmita 36/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..37.. ARA6/07

    JudgetoArticle137andArticle55istotallymisplacedandcontrarytolaw.In

    myview,limitationformakingaclaimandlimitationformakinganapplication

    forappointmentofarbitratorcannotbemixedup.

    35. Perusal of theaward indicates that ClaimNo.1was for revisionof

    ratesdemandedbythecontractoronthebasisthatcertainitemsofworkwhich

    were different from those included in BOQ (Bill of Quantities) items were

    requiredtobeexecuted.Itwasthecaseofthecontractorthatthereweresome

    extra itemswhererates of itemcouldnotbederivedfromtheBOQratesby

    makingappropriatevariations. UnderClause51ofthecontract,theEngineer

    hadpowerstomakeanyvariationoftheform,qualityorquantityoftheworksor

    anypartthereof.Procedureofvaluationofvariationhadbeenspecifiedunder

    Clause52 of the contract. Accordingly, the Government had prepared rate

    analysiswith 'labourmarkup'as50%andoverheadandprofitas20%. The

    contractor,howeverdemandedthesameas195%and40%respectively. The

    learnedlearnedarbitraltribunal,intheimpugnedawardallowedthisclaim. It

    wasthepleaoftheGovernmentthatdisputeregardingratesofextra/deviated

    itemsstartedwhenthefirstpaymentwasmadepriorto27thJuly1997;whereas

    thecontractorhad invokedarbitrationclauseon27th July2000. It is not in

    disputethatthesaidworkwascarriedoutasorderedbytheGovernmentunder

    Asmita 37/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..38.. ARA6/07

    Clause51 read with Clause52 of the contract. The said work was thus,

    contractualworkasorderedbytheGovernment.Thelimitationformakingsuch

    claimforratesofsuchextra/deviateditemswillthusarisewhensuchitemofwrk

    wasdonebythecontractor,whichinthiscase,muchpriorto27thJuly1997.In

    myview,Article18ofScheduletoLimitationActwouldapplytothisclaimand

    not Article113 as sought to be applied by the contractor in the present

    proceedings.ThelearnedarbitratordidnotrefertoanyArticlewhilerejecting

    thepleaoflimitationintheimpugnedaward.

    36. InsofarasClaimNo.2isconcerned,perusaloftheawardindicates

    that the said claim was for compensation for the work carried out by the

    contractor beyond the original stipulated date of completion which was 19th

    March1997. TheGovernmentgrantedfiveextensionsfortheperiodbetween

    20thMarch1997makingthesametermsandconditionsapplicableforthework

    carriedoutduringtheextendedperiod. Thecontractorthus,oughttohave

    invoked arbitration clause no sooner such extension was granted by the

    Governmentbymakingthesametermsandconditionsapplicableforthework

    carried out during the extended period. The cause of action for claim for

    compensationwouldarisewhenthebreachiscommittedbytheeitherparty. If

    accordingtothecontractor,theGovernmentwasresponsibleforprolongationof

    Asmita 38/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..39.. ARA6/07

    contractandextensionwasnecessitatedduetosuchreasonsandthecontractor

    wasnotboundtocarryoutthebalanceworkonthesametermsandconditions,

    cause of action would begin as soon as such breach was committed by the

    Government according to the contractor. The learned arbitral tribunal,

    however,didnotdecidethisissueintheimpugnedawardbutrejectedthepleaof

    limitationmerelyonthegroundthattheclaimwasinitiatedon18thMarch1997

    i.e the date on which the Government granted extension under the same

    conditions of contract and its effect will start from 20th March 1997 and it

    continuedtill actualcompletionofthecontract. Thelearnedarbitraltribunal

    consideredthattheEngineerhadrejectedtheclaimon6thSeptember2000and

    thearbitrationwasinvokedon21stSeptember2000,thustheclaimwasintime.

    NoArticleofLimitationActhasbeenreferredbythelearnedarbitraltribunal

    while dealing with plea of limitation even in respect of this claim for

    compensation.

    37. AsfarasClaimNo.3madebythecontractorisconcerned,perusalof

    theawardindicatesthatthesaidclaimwasmadeforrevisionofratesforPressure

    Shaft Excavation. According to contractor, it encounteredvarious difficulties

    duringtheexcavationsofthePressureShaftssuchaschangedsequenceofthe

    work,methodandtiming,physicalobstructionsintheworkduetoworkofother

    Asmita 39/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..40.. ARA6/07

    agency, variation in rock strata/geological conditions etc., which was not

    attributabletothecontractor.Accordingtocontractor,inviewofsuchsituation,

    theychangedthescopeofitemandthecontractorpreparedrateanalysisforeach

    component of the work based on componentwise expenditure. The learned

    arbitraltribunalallowedthisclaim.

    38. Perusaloftheawardindicatesthatthisitemwascarriedoutduring

    theperiodbetweenJuly1993toMarch1998totheextentof94%.Thedemand

    wasmadebeforetheExecutiveEngineeron10thFebruary1997.Itwasrejected

    byExecutiveEngineeron17thJuly2000. Inmyview,thecontractoroughtto

    havemadethisclaimwhenanysuchbreachwascommittedbytheGovernment

    resulting in suffering of compensation due to breaches attributable to the

    Government.Thecontractorwasnotboundtowaitbeyond60daysfordecision

    oftheExecutiveEngineer.Inthiscase,itisclearthatthecontractorwaitedfor

    decision of Executive Engineer for more than three years and four months.

    Limitationoncecommenced,doesnotstop.Thelearnedarbitraltribunalhasnot

    referredtoanyArticleofLimitationActwhiledealingwiththistypeofclaim.In

    my view, the claim in view of the alleged breaches committed by the

    Government,oughttohavemadewithinthreeyearsfromthedateofalleged

    breachandclaimnot havingmadewithin threeyears, was barredby lawof

    Asmita 40/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..41.. ARA6/07

    limitation.

    39. InsofarasClaimNo.4isconcerned,perusalofawardindicatesthat

    thesaidclaimwasmadeforfixationoftherateonaccountofvariationinthe

    itemofTransformerHallArchConcreteduetotheproblemssuchaschangesin

    natureofrock,doingadditionalworknotprovidedinthecontract,changesin

    sequenceandmethodology,delayinissueofdrawings,increaseinquantitiesetc.,

    resultingincontractortoincurextraexpenditurenotcontemplatedintherate

    analysis.Thecontractormadethatclaimbywayofcompensationtowardsextra

    expensesallegedtohavebeenincurredbyit. Thelearnedarbitral tribunal

    allowedthisclaim.Thedataplacedonrecordintheawardindicatesthatthis

    workwascarriedoutduringtheperiodbetweenOctober 1993andFebruary

    1994. ThecontractormadeademandbeforetheExecutiveEngineeron14th

    October1996.TheExecutiveEngineerrejectedthisclaimon4thNovember2000.

    Arbitrationwasinvokedon1stJune2001.Inmyview,thecontractoroughtto

    havemadethisclaimwhensuchworkwasdoneandnopaymentwasmadeto

    thecontractorforthesame.Thecontractorwasnotboundtowaitfordecision

    ofExecutiveEngineerbeyondtheperiodof60dayswhereas, inthis case,he

    waited fordecisionof theExecutiveEngineer foraperiodof morethanfour

    years.Inmyview,thisclaimwasonthefaceofitisbarredbylawoflimitation.

    Asmita 41/48

    ::: Downloaded on - 05/02/2013 13:37:34 :::

  • Bom

    bay

    High

    Cou

    rt..42.. ARA6/07

    Thelearnedarbitraltribunalhasnotconsideredthesefactsinproperdirection.

    40. InsofarasClaimNo.5isconcerned,thesaidclaimwasmadebythe

    contractor for fixation of new rate on account of variation in the item of

    TransformerHallexcavation.Itwasthecaseofthecontractorthatexcavationof

    horizontalnicheshaddelayedtheworkandcausedextraexpensesduetoother

    reasons,suchasstoppageofworkofshotcrete,increaseinquantityofrockbolts,

    frequentrevisionofdrawings,additionalworks,reductionandomissionofsome

    worksetc.necessitatedappropriatedcompensationinfavourofcontractor.The

    learned arbitral tribunal allowed this claim for compensation. The award

    indicatesthatthisworkwasexecutedduringtheperiodbetweenJanuary1993

    and September 1995. The contractor made this claim before the Executive

    Engineeron14thOctober,1996whichwasrejectedbytheExecutiveEngineeron

    19thSeptember,2000.Arbitrationclausewasinvokedon6thJune2001.Inmy

    view, when the work was carried out and payment was not made by the

    Government,causeofactionhadcommenced.Inanyevent,thecontractorwas

    notrequiredtowaitforthedecisionoftheExecutiveEngineerformorethan60

    dayswhereasforthis claim,thecontractorwaitedfordecisionforaboutfour

    years.Inmyview,theclaimonthefaceofit,isbarredbylawoflimitation.

    Asmita 42/48

    ::: Downloaded on - 05/02/2013 13:37:35 :::

  • Bom

    bay

    High

    Cou

    rt..43.. ARA6/07

    41. In so far as judgment of the Supreme Court in case of Gannon

    Dunkerly(supra)relieduponbythecontractorisconcerned,inmyview,itwas

    notthepleaofthecontractorbeforethearbitraltribunalorbeforetheDistrict

    JudgethatArticle113oftheLimitationAct(correspondingtoArticle120ofthe

    LimitationAct1908)wouldapplytothefactofthiscase.Inmyview,asnosuch

    pleawasnotraisedbeforethearbitraltribunalplacingrelianceuponArticle113

    corresponding to Article120 of Limitation Act 1908, and since no finding is

    rendered by the arbitral tribunal applying Article113, contractor cannot be

    permittedtoraisesuchpleaforthefirsttimeinthepresentproceedingsunder

    Section37oftheActof1996.Pleaoflimitationisamixedquestionoffactand

    lawandunlesssuchspecificpleabyplacingrelianceuponArticle113wasfirst

    raisedbeforethearbitraltribunal,itcannotbeallowedtoberaisedforthefirst

    timeinappealunderSection37oftheActof1996.Iam,therefore,oftheview

    thatrelianceplacedbythelearnedseniorcounselappearingforthecontractorin

    caseof GannonDunkerley (supra)isofnoassistancetothecontractorinthe

    factsofthiscase.

    42. Inanyevent,consideringthenatureofclaimsmadebythecontractor

    i.e.ClaimNos.1to5whichwereallowedbythelearnedarbitraltribunal,itis

    clearthattheclaimswereeitherforworkdoneorforcompensationandthus

    Asmita 43/48

    ::: Downloaded on - 05/02/2013 13:37:35 :::

  • Bom

    bay

    High

    Cou

    rt..44.. ARA6/07

    specificArticleforreferringthedisputetoarbitrationwouldbeattractedsuchas

    Article18 or Article55 of Schedule of the Limitation Act and therefore,

    Article113cannotbeattracted.Inmyview,thusthefactsofthecasebeforethe

    HonourableSupremeCourt in caseof GannonDunkerley (supra)areclearly

    distinguishablewiththefactsofthiscaseandthus,saidjudgmentrelieduponby

    thecontractor,withgreatrespect,isofnoassistancetothecontractor.

    43. The next submission of Mr Chinoy, the learned senior counsel

    appearingforthecontractoristhatevenifArticle18isapplicabletotheclaims

    madebythecontractor, periodof limitationwouldcommenceonlywhenthe

    entireworkisdone.Thelearnedseniorcounselsubmitsthattheclaimsmadeby

    thecontractorwerenotfortheentireworkdonebythecontractorbutwasonly

    inrespectofsomeitemsfromthescopeofentireworkawardedtothecontractor.

    Thelearnedseniorcounselsubmitsthatonlywhentheentireworkiscompleted,

    causeofactionwouldariseformakingclaimsevenforitemsfortheworkdone.

    It is submitted that if thecontractor is asked to invokearbitrationclauseon

    completionofeachitemindispute,therewouldbemultiplicityofarbitrations

    underthesamecontract.

    44. MrKumbhakoni, learnedcounsel appearing fortheGovernmenton

    Asmita 44/48

    ::: Downloaded on - 05/02/2013 13:37:35 :::

  • Bom

    bay

    High

    Cou

    rt..45.. ARA6/07

    theotherhandonthisissueinrejoinder submitsthatthecontractorhadmade

    claimsinrespectofeachitemsseparatelyanddidnotmakeclaimfortheentire

    work. It is submitted that even in the earlier arbitration proceedings, the

    contractorhadmadeclaimshavingariseninrespectoftheitemsofthework

    done and did not wait till completion of work. The Government had made

    paymentitemwisetothecontractorandthusitcannotbeconstruedthatcause

    ofactionwouldariseonlyafterentireworkwasdoneandnotwhenitemsof

    workwasdoneinrespectofwhichthedisputehadalreadyarisen.Clause66(A)

    andClause66(b)oftheGeneralConditionsofContractreadasunder:

    66A)SETTLEMENTOFDISPUTESARBITRATION:

    (A) IftheContractorconsidersanyworkdemandedofhimtobeoutsidetherequirementsofthecontractorconsidersanydrawings,recordorrulingoftheEngineer'sRepresentativeonanymatterinconnectionwithorarisingoutoftheContractorthecarryingoutofworktobeunacceptable,heshouldpromptlyaskthe Engineer's representative in writing, for written instructions or decision.Thereupon theEngineer's Representative shall givehis written instructions ofdecisionwithinaperiodof60daysofsuchrequest.

    Uponreceiptofthewritteninstructionsordecisions,thecontractorshallpromptlyproceedwithoutdelaytocomplywithsuchinstructionsordecision.

    IftheEngineer'sRepresentativefailstogivehisinstructionsordecisioninwritingwithinaperiodof60daysofbeingrequestedoriftheContractorisdissatisfiedwiththeinstructionsordecisionoftheEngineer'sRepresentativetheContractormaywithin30daysafterreceivingtheinstructionsordecisionappealupwardstoEngineerwhoshallaffordanopportunitytotheContractortobeheardandtoofferevidenceinsupportofhisappeal.TheEngineershallgiveadecisionwithinaperiodof60daysaftertheContractorhasgiventhesaidevidenceandfurtherdocumentaryprooftheEngineercallsforinsupportofContractor'sappeal.

    IftheContractorisdissatisfiedwiththisdecision,theContractorwithinaperiodof30daysfromreceiptofthedecisionshallindicatehisintentiontoreferthedisputetoArbitration,aspertheproceduresetoutinClause66(b)below,failingwhich

    Asmita 45/48

    ::: Downloaded on - 05/02/2013 13:37:35 :::

  • Bom

    bay

    High

    Cou

    rt..46.. ARA6/07

    thesaiddecisionshallbefinalandconclusive.

    66(b):ARBITRATION:

    Intheeventofanydisputeordifferencearisingoutoforinanywayrelatingtoorconcerning these presents or the construction or effect of these presents (thesettlementwhereofhasnotbeenhereinbeforeexpresslyprovidedfor),thesameinrespectofwhichthedecisionisnotfinalandconclusive,shallontheinitiativeofeitherpartytothecontractbereferredtothreearbitrators,onetobeappointedbytheemployer, thesecondbythecontractor andthirdbytheChairmanCentralWater Commission in the case of Indian Contractors. In the case of ForeignContractor, thethirdarbitratorwillbedecidedbythetwoarbitratorswithin60daysoftheirappointment. ThetermIndianContractorshallincludeanIndianfirm or a group of firms or a joint venture eligible for price preference as adomestictenderer.ThetermForeignContractorshallincludeaforeignfirmoragroup of firms and joint venture consortia not eligible for price preference asdomestic tenderer. TheArbitrationshall be conducted inaccordance with theprovisions of the Indian Arbitration Act 1940 or any statutory modificationsthereof. The arbitration shall be held at such place and time in India as thearbitrators maydetermine. If eitherof thepartiesfail toappoint its arbitratorwithinsixtydaysafterreceiptofnoticefortheappointmentofanarbitratorfromtheotherpartythentheChairman,CentralWaterCommissionshallappointanarbitratoronreceiptoftherequestfromtheaggrievedparty. AcertifiedcopyoftheappointmentsmadebytheChairmanCWCshallbefurnishedtobothparties.

    Thedecisionofthemajorityofthearbitratorsshallbefinalandbindinguponboththeparties.Theexpenseofthearbitratorsshallbepaidasmaybedeterminedbythearbitrators.

    Performanceunderthecontract, shallifreasonablybepossible, continueduringthearbitrationproceedingsandpaymentsduetotheContractorbytheEngineer'srepresentative shall not be withheld, unless theyare the subject matter of thearbitrationproceedings.

    All awardsshall be inwritingand in case of claims equivalent toRupees onehundred thousand or more, such awards shall state reasons for the amountsawarded.

    NeitherpartyisentitledtobringaclaimtoarbitrationifitsArbitratorhasnotbeenappointedbythirtydaysaftertheexpirationofthedefectsliabilityperiod.

    45. Perusalofthearbitrationclauseindicatesthatincaseofanydispute,

    Asmita 46/48

    ::: Downloaded on - 05/02/2013 13:37:35 :::

  • Bom

    bay

    High

    Cou

    rt..47.. ARA6/07

    thecontractorwasrequiredtopromptlyasktherepresentativeoftheGovernment

    inwriting,forwritteninstructionsordecision.Fromtheperusaloftheclauses,it

    is clearthat it contemplatesdispute tobereferredevenduringthecourseof

    executionofworkandthecontractorwasnotrequiredtowaittillcompletionof

    the work. Perusal of the arbitrationclause indicates that thecontractor was

    permittedtoreferthedisputestoarbitrationarisingduringtheexecutionofthe

    workandsimultaneouslytocontinuetoperformunderthecontractifreasonably

    possible. ThisClauseindicatesthatthecontractorwasnotboundtowaitfor

    completionfortheentirework,butcouldhaveinvokedarbitrationpromptlyas

    soonasdisputehadariseneveninrespectofitemsofworkoutofentirescopeof

    workwere executed. It is not in dispute that even in respect of the earlier

    arbitrationarising under the samecontract, the contractor hadalreadymade

    claimsinrespectofsomeoftheitemsofwork.Iamthus,notinclinedtoaccept

    thesubmissionmadebythelearnedseniorcounselappearingforthecontractor

    thatthecauseofactionwouldariseonlywhentheentireworkwascompletedby

    thecontractorandnotwhenthepaymentwasnotmadeinrespectoftheitemsof

    workdoneoncompletionofthatitem. Inmyview,causeofactionhadarisen

    whentheworkwasdoneinrespectoftheitemsofworkdoneandcauseofaction

    wouldnotpostponetillthedateofcompletionofentirescopeofworkawardedto

    thecontractor.Inmyview,thelearnedarbitraltribunaloughttohavereferredto

    Asmita 47/48

    ::: Downloaded on - 05/02/2013 13:37:35 :::

  • Bom

    bay

    High

    Cou

    rt..48.. ARA6/07

    therelevantArticlewhichwouldbeattractedforthepurposesofdecidingthe

    issueoflimitation,whichisabsentintheimpugnedaward.ThelearnedDistrict

    JudgehasmisdirectedbyapplyingwrongArticletothefactsofthiscase.

    46. Theawardisvitiatedandisinconflictwithpublicpolicyontheissue

    oflimitation. ViewtakenbythelearnedDistrictJudgeisalsocontrarytolaw

    anddeservestobesetaside.I,therefore,passthefollowingorder.

    i) Impugnedorderandjudgmentdated29th June2006passedbythe

    learnedDistrictJudge,RatnagiriinArbitrationApplicationNo.44of

    2003andtheimpugnedawarddated26th June2003passedbythe

    learnedarbitraltribunalaresetasideonthegroundoflimitation.

    ii) ArbitrationApplicationNo.44of2003filedbytheGovernment is

    allowed.

    iii)Appealisdisposedofinaforesaidterms.Thereshallbenoorderasto

    costs.

    iv) Respondentisdirectedtorefundtheamountwithdrawnintheabove

    matterwithinterest@12%perannumfromthedateof withdrawaltill

    paymentwithineightweeksofthisorder.

    (R.D.DHANUKA,J.)

    Asmita 48/48

    ::: Downloaded on - 05/02/2013 13:37:35 :::